Cost overrun
From Wikipedia, the free encyclopedia
A cost overrun, also known as a cost increase, underrated or budget overrun, involves unexpected costs
incurred in excess of budgeted amounts due to an underestimation of the actual cost during budgeting. Cost
overrun should be distinguished from cost escalation, which is used to express an anticipated growth in a budgeted
cost due to factors such as inflation.
Cost overrun is common in infrastructure, building, and technology projects. For IT projects, a 2004 industry study
by the Standish Group found an average cost overrun of 43 percent; 71 percent of projects came in over budget,
exceeded time estimates, and had estimated too narrow a scope; and total waste was estimated at $55 billion per
year in the US alone.[1]
Many major construction projects have incurred cost overruns; cost estimates used to decide whether important
transportation infrastructure should be built can mislead grossly and systematically.[2]
Contents
1 Causes
2 Prevention and mitigation
3 Describing
4 List of projects with large cost overruns
4.1 Australia
4.2 United Kingdom
4.3 USA
4.4 Germany
4.5 Finland
5 See also
6 References
7 External links
Causes
Recent works by Ahiaga-Dagbui and Smith suggests a rethink of what is traditionally referred to as overruns in
construction.[3] They attempt to make a distinction between the often conflated causes of construction cost
underestimation and eventual cost overruns. Critical to their argument is the point of reference for measuring cost
overruns. Whereas some measure the size of cost overruns as the difference between cost at the time of decision to
build and final completion costs, others measure the size of overruns as the difference between cost at contract
award and final completion cost.This leads to a wide range in the size of overruns reported in different studies.
Three types of explanation for cost overrun exist: technical, psychological, and political-economic. Technical
explanations account for cost overrun in terms of imperfect forecasting techniques, inadequate data, etc.
Psychological explanations account for overrun in terms of optimism bias with forecasters. Scope creep, where the
requirements or targets rises during the project, is common. Finally, political-economic explanations see overrun as
the result of strategic misrepresentation of scope or budgets. Historically, political explanations for cost overrun
have been seen to be the most dominant.[4] In the USA, the architectural firm Home Architects has attributed this
to a human trait they call "Psychology of Construction Cost Denial", regarding the cost inflation of custom
homes.[5]
https://en.wikipedia.org/wiki/Cost_overrun 1/5
8/7/2017 Cost overrun - Wikipedia
A less explored possible cause of cost overruns on construction project is the escalation of commitment to a course
of action. This theory, grounded in social psychology and organisation behaviour, suggests the tendency of people
and organisations to become locked-in and entrapped in a particular course of action and thereby 'throw good
money after bad' to make the venture succeed. This defies conventional rationality behind subjective expected
utility theory. Ahiaga-Dagbui and Smith explore the effects of escalation of commitment on project delivery in
construction using the case of the Scottish Parliament project.[6] Also, a recent study has suggested that principles
of chaos theory can be employed to understand how cost overruns emerge in megaprojects. This paper seeks to
reclassify megaprojects as chaotic systems that are nonlinear and therefore difficult to predict. Using cases of cost
overruns in oil and gas megaprojects, this study makes strong argument that chaos theory can indeed be a silver
bullet in finding solutions to the recurring problem of cost overruns in megaprojects.
Agile development does not claim to guarantee perfect on-time and on-budget delivery of the original expectations
(which may not be even realistic or suitable to meet user needs). However, in many cases it may be able to:
It has been claimed that agile development did not prevent cost and time overruns in the UK government's
Universal Credit IT project, but there are serious doubts as to whether the Universal Credit software development
project was in fact following a proper agile process in the first place.
In response to problem of cost overruns on major projects, the UK Government set up a Major Projects Authority
to provide project assurance to HM Treasury and other Government departments undertaking major projects.[8]
Independent review of the financial effectiveness of project assurance in reducing cost overruns found the project
assurance process to be effective in reducing cost overruns and recommended an expansion of the process to cover
most of the Government's project portfolio.[9] Project assurance is now also being used by private sector
companies undertaking major projects.
Eriksson and Westerberg (2011);[10] Li, Arditi, and Wang (2012);[11] Chen and Manley (2014),[12] and Cardenas,
Voordijk, and Dewulf (2017)[13] have hypothesized, developed and extensively tested conceptual models in which
relevant project governance instruments and factors were identified and related to the performance and the
reduction in costs overruns of projects.
https://en.wikipedia.org/wiki/Cost_overrun 2/5
8/7/2017 Cost overrun - Wikipedia
Describing
Cost overrun can be described in multiple ways.
For example, consider a bridge with a construction budget of $100 million where the actual cost was $150 million.
This scenario could be truthfully represented by the following statement
The final example is the most commonly used as it specifically describes the cost overruns exclusively whereas the
other two describe the overrun as an aspect of the total expense. In any case care should be taken to accurately
describe what is meant by the chosen percentage so as to avoid ambiguity.
United Kingdom
National Programme for IT, described by the British Members of Parliament (in the Public Accounts
Committee) as one of the "worst and most expensive contracting fiascos" in the history of government
contracts[7]
Scottish Parliament Building[6]
Edinburgh Trams
USA
The Boeing Dreamliner programme, announced in 2003, was supposed to cost $6 billion and see the plane
take to the air in 2008. The final bill was closer to $32 billion; and the 787 arrived three years late.
Germany
Finland
See also
https://en.wikipedia.org/wiki/Cost_overrun 3/5
8/7/2017 Cost overrun - Wikipedia
Admissible heuristic
Benefit shortfall
Escalation of commitment
Megaproject
Optimism bias
Planning fallacy
Reference class forecasting
Scope creep
References
1. Standish Group (2004). CHAOS Report (Report). West Yarmouth, Massachusetts: Standish Group.
2. Flyvbjerg, Bent; Holm, Mette K. Skamris; Buhl, Sren L. (2002). "Underestimating Costs in Public Works
Projects: Error or Lie?". Journal of the American Planning Association. 68 (3): 279295. SSRN 2278415 (ht
tps://ssrn.com/abstract=2278415) . arXiv:1303.6604 (https://arxiv.org/abs/1303.6604) .
3. Ahiaga-Dagbui, Dominic D.; Smith, Simon D. (2014). "Dealing with construction cost overruns using data
mining" (https://www.researchgate.net/publication/262932913_Dealing_with_construction_cost_overruns_u
sing_data_mining). Construction Management and Economics. 32 (78): 682.
doi:10.1080/01446193.2014.933854 (https://doi.org/10.1080%2F01446193.2014.933854).
4. Cantarelli, Chantal C.; Flybjerg, Bent; Molin, Eric J. E.; van Wee, Bert (2010). "Cost Overruns in Large-
Scale Transportation Infrastructure Projects: Explanations and Their Theoretical Embeddedness". European
Journal of Transport and Infrastructure Research. 10 (1): 518. SSRN 2237990 (https://ssrn.com/abstract=2
237990) . arXiv:1307.2176 (https://arxiv.org/abs/1307.2176) .
5. "Psychology of Construction Cost Denial - Mountain Home Architects, Timber Frame Architect, Custom
Homes" (http://www.homearchitects.com/psychology-of-construction-cost-denial).
6. Ahiaga-Dagbui, Dominic; Smith, Simon (2014). "Exploring escalation of commitment in construction
project management: Case study of the Scottish parliament project" (http://hdl.handle.net/10059/1303).
Proceedings 30th Annual ARCOM Conference. Association of Researchers in Construction Management:
753762. ISBN 9780955239083.
7. Stecklein, Jonette M.; Dabney, Jim; Dick, Brandon; Haskins, Bill; Lovell, Randy; Moroney, Gregory (2004).
Error Cost Escalation Through the Project Life Cycle (https://ntrs.nasa.gov/search.jsp?R=20100036670)
(Report). JSC-CN-8435.
8. "Major Projects Authority - GOV.UK" (https://www.gov.uk/government/groups/major-projects-authority).
9. "Assurance for major projects - National Audit Office (NAO)" (http://www.nao.org.uk/report/assurance-for-
major-projects/).
10. Eriksson, Erik C.; Westerberg, Mats (2011). "Effects of cooperative procurement procedures on construction
project performance: A conceptual framework". International Journal of Project Management. 29 (2): 197
208. doi:10.1016/j.ijproman.2010.01.003 (https://doi.org/10.1016%2Fj.ijproman.2010.01.003).
11. Li, Huimin C.; Arditi, David; Wang, Zhuofu (2013). "Factors That Affect Transaction Costs in Construction
Projects". Journal of Construction Engineering and Management. 139 (1): 6068.
doi:10.1061/(ASCE)CO.1943-7862.0000573 (https://doi.org/10.1061%2F%28ASCE%29CO.1943-7862.000
0573).
12. Chen, Le; Karen, Manley (2014). "Validation of an instrument to measure governance and performance on
collaborative infrastructure projects". Journal of Construction Engineering and Management. 140 (5).
doi:10.1061/(ASCE)CO.1943-7862.0000834 (https://doi.org/10.1061%2F%28ASCE%29CO.1943-7862.000
0834).
13. Cardenas, IC; Voordijk, H; Dewulf, G (2017). "Beyond theory: Towards a probabilistic causation model to
support project governance in infrastructure projects". International Journal of Project Management.
doi:10.1016/j.ijproman.2017.01.002 (https://doi.org/10.1016%2Fj.ijproman.2017.01.002).