Department of Transportation: California Test 112 August 2012
Department of Transportation: California Test 112 August 2012
DEPARTMENT OF TRANSPORTATION
DIVISION OF ENGINEERING SERVICES
Transportation Laboratory
5900 Folsom Boulevard
Sacramento, California 95819-4612
A. SCOPE
The installation, maintenance, and data collection procedures for the various embankment
settlement devices used to monitor subsurface settlement are described in this method.
Analysis of the settlement data is included as a separate part of this method.
Settlement devices are used to monitor the rate and magnitude of settlement occurring at a
point within or beneath an embankment during and subsequent to construction. The data
obtained from these devices are used to determine the allowable loading rate during
embankment construction and the appropriate time for removal of surcharge and/or
commencement of permanent structure construction.
The fluid level vented standpipe unit may be used at most locations. A sealed standpipe unit
must be installed at locations where groundwater may interfere with the operation of the unit
or where excess pore water is expected from the use of dredged material or wet soil in
embankment construction. Where it is possible, the tube length between standpipe and
indicator unit should generally be limited to a maximum 300 linear ft. Installations over longer
distances can be made but are not advisable under normal circumstances since it may result
in inconsistent test data. Factors such as larger size tubes, change of platform location, or
changes in elevation of the water line may have to be considered (see NOTE).
NOTE: There may be job conditions with respect to terrain, long tube length between
standpipe and indicator unit, or anticipated large settlements that require special
installations.
The pipe riser settlement device is used for monitoring fill settlement over soft foundation soils
where the fluid level settlement devices are not feasible because of flat terrain, width of
embankment construction, or other features which would make installation of a fluid level
type of settlement platform undesirable. The pipe riser settlement device is a direct-reading
unit which is exposed for the full duration of fill construction and surcharge removal. Because
of the vulnerability of this unit to damage by the contractors operations, the pipe riser
settlement device should be used only on those projects where the fluid level type of settlement
device would be impractical.
B. REFERENCE
None.
California Test 112
August 2012
C. PROCEDURE
A. APPARATUS
B. INSTALLATION
2. Select a point outside of the toe of the proposed embankment for the
indicator unit (see Figure 4). Select this location so that sufficient
vertical distance will be available for lowering the indicator unit as the
standpipe unit settles. A hand level may be used to estimate the desired
elevations for the indicator unit.
5. Upon completion of the excavation, remove all rocks and large clods
from the trench. Prepare a smooth, level area in the pit using fine
embankment material.
-2-
California Test 112
August 2012
7. Install the indicator unit post at the previously selected point for the
indicator unit. This post can be either a metal sign post or 4 in. x 4 in.
timber.
8. Using a hand level, attach the indicator unit to the post so that the 2 ft
graduation on the indicator unit scale is approximately level with the top
of the spill tube on the standpipe unit.
9. Push the in. water line through the metal tube conduit in the center
of the vented standpipe unit until the end is approximately in. above
the top. Push the in. air vent line through the other conduit until
approximately in. extends out the top (see Figure 1).
10. Unroll the water and air vent lines loosely in the trench from the
standpipe to the indicator unit. It might be desirable to encase both
lines in in. flexible metal conduit for additional protection under rocky
material.
11. Cut and attach the water and air lines to the indicator unit as shown in
Figure 2 and Figure 3. Then, fill the system by pouring water in the
sight tube of the indicator unit (see Figure 2) until water comes out of
the top of the spill tube of the standpipe unit with no air bubbles
showing in the line. Generally, one gallon of water is more than
adequate for 300 ft of tubing. When filling, attempt to keep the water
level in the sight tube near the 2.0 ft graduation. Do not allow the water
level to drop below the bottom of the sight tube since this would allow
air to enter the system.
Adjacent to the bottom of the indicator unit, place a reference nail in the
post at the elevation of the 0.0 ft graduation. This provides a reference
point for surveys and relocation of the indicator unit. Complete the
assembly of the standpipe unit by attaching the pipe cap as shown in
Figure 1.
12. Cut the air line at approximately the 2.0 ft graduation of the indicator
unit. Then loop the air line inside of the indicator unit over the lock
hasp (see Figure 2). The end of the air line should be pointing downward
to prevent the entrance of water or debris. This air line must be free of
water at all times since it serves to equalize atmospheric pressure at the
standpipe unit and the indicator unit.
-3-
California Test 112
August 2012
During cold weather when the air line is too stiff to be looped, cut the air
line at the 1 ft graduation mark. Then insert the end of a one foot length
of in. plastic tubing in the end of the air line and loop the smaller
tubing inside the indicator unit.
13. Carefully backfill the trench and pit with material that is free from large
rocks or sharp objects and compact by hand for a depth of at least 12
in. Special care must be taken around the base of the standpipe unit to
prevent separating the base plate from the plywood platform and to
prevent breaking or distorting the plastic tubing.
14. After hand backfilling and compacting for a depth of 12 in. has been
completed, mechanical methods may be used to finish the backfilling
operation until the trench is level with the existing fill height. In those
cases when the standpipe unit extends above the existing fill height,
attach a marker post to the unit and mound fill material around it until
it is completely covered. In no case should compaction equipment be
allowed directly over an installation until a minimum of 1 ft of
compacted material has been placed over the standpipe unit.
A. APPARATUS
B. INSTALLATION
Installation is similar to that for the vented standpipe unit with the following
expectations:
5. Attach the in. water tube to the base plate as shown in Figure 5.
6. Unroll the water, air vent, and drain tubes loosely in the trench from the
standpipe to the indicator unit.
-4-
California Test 112
August 2012
NOTE: It may be desirable in some cases to fill around the sealed units
with sand so that the tubes will be supported at their attachment
points.
9. Cut the drain tube near the base of the indicator unit post. Position the
drain tube so that water flows out freely and intrusion of soil or debris is
prevented.
10. Follow the procedures in Part 1, Section 1 (B)(13) and Section 1(B)(14).
A. COLLECTION OF DATA
2. Settlement readings.
b. Pour sufficient water in the sight tube to raise the water level
approximately 0.2 ft.
c. Take a reading at 1 hr. The water level after adding the water
should drop to the first reading or slightly above it.
-5-
California Test 112
August 2012
B. MAINTENANCE
2. If the water level in the sight tube does not drop after adding water,
check the unit over a period of several days. Do not, however, add an
excessive amount of water; just observe the system to see if the unit is
slow to respond.
-6-
California Test 112
August 2012
water line. If the sealed standpipe unit is used, plug the drain
line during this operation. Occasionally, force air through the
water line to clear the lines if no return is observed when
pressurizing the air line. If successful in clearing obstructions
from the water line in this manner, considerable care is required
while recharging the system with water to not use too much
water and to not introduce large voids in the system. For this
reason, recharging the unit should be performed only by
personnel experienced in this type of activity.
3. If the water level in the sight tube is below the 0.05 ft graduation or if
there is no water in the sight tube, look for leaks around the connection
between the sight tube and the water line. If no leak is seen, measure
the vertical difference between the 0.0 ft graduation on the indicator
unit and the reference point. Remove the unit from the post and lower it
approximately 1.5 ft or until water is observed in the sight tube. If
possible, and without adding water, adjust the height of the indicator
unit on the post so that the water level in the sight tube is
approximately at the 2.0 ft graduation. Add a small quantity of water
and check the water level before attaching the indicator unit to the post.
After adjusting the height of the indicator unit, again measure the
vertical distance between the 0.0 ft graduation on the indicator unit and
the reference point and record the correction on the settlement data
form (Figure 7, Column 3).
4. Be sure to replace the cover on the indicator unit after each reading to
prevent excessive loss by evaporation and contamination by debris.
5. Occasionally, it may be necessary to protect the air and water lines from
rodents or pests. If such a problem exists, protect these lines in flexible
conduit extending from the bottom of the indicator unit to below the
ground surface. Although this should be done during installation, the
conduit can be added later if extreme care is taken not to lose water
continuity as described above.
A. APPARATUS
B. INSTALLATION
-7-
California Test 112
August 2012
4. Measure and record the distance from the top of the pipe coupling to the
top of the wood platform. Then slip the 1 in. x 5 ft protective sleeve,
which may be either rigid polyvinyl chloride (PVC) or iron pipe, over the
control pipe until it is about 2 in. above the floor flange. Place a duct
seal or other seal to hold the protective sleeve in place (see Figure 8). Do
not attach the protective sleeve to the wood platform or the control pipe.
This protective sleeve is used to absorb the friction between the fill
material and the settlement unit and, therefore, must be free to move
independently from the wood platform and control pipe.
5. Firmly seat the settlement device on the prepared area in the bottom of
the pit. Then fill and compact by hand using fine embankment material
free of large rocks and clods around the settlement device to a depth of
one foot.
6. Using a spirit level, check to make sure the control pipe is reasonably
plumb, then carefully fill the pit with embankment material and
compact in place.
NOTE: It has been found that a 6 ft long, 2 in. x 4 in. post painted with
alternate 1 ft wide stripes of red and white is satisfactory for this use. It
is recommended that flagging be attached to the top of this post. The
post should be attached so that it can be easily removed and reattached
as additional pipe is added during embankment construction.
C. COLLECTION OF DATA
-8-
California Test 112
August 2012
4. Enter all data on the form provided (see Figure 11) using the example
shown in Figure 9 as follows:
Column 6 - Record the height of the riser above the original ground
(Column 4 minus Column 5).
-9-
California Test 112
August 2012
Column 9 - Record the height of the fill above original ground in total
feet.
The procedure for plotting and analyzing settlement data obtained from all types of
settlement devices is described in this method. Comprehensive settlement analyses are
complex and require extensive knowledge of soil mechanics and soil structure of the area
under study. Considerable information, however, can be obtained by the simplified method
described in this part.
1. Plot the data on a semi-logarithmic chart as shown in Figure 10. Note that the
scale for days is on the logarithmic abscissa of the chart and both settlement
and fill height are scaled arithmetically on the ordinate.
3. After embankment construction has been completed, the rate of settlement will
decrease with time, especially for soft foundation soils. However, a marked
decrease in the rate of settlement may be noticed until an appreciable amount
of time has elapsed since completion of the embankment.
- 10 -
California Test 112
August 2012
b. When the plotted data indicate that the slope of the rate of settlement
curve is essentially horizontal, the embankment surcharge may be
removed and/or permanent structure construction may be started. For
example, from data shown in Figure 10, a practical minimal rate of
settlement was obtained at about 360 days; at this time the
embankment surcharge was removed as shown.
4. Data should be collected throughout the life of the contract. Longer data
collection periods are necessary if significant rates of settlement are measured.
It is the responsibility of the user of this test method to establish appropriate health and safety
practices and determine the applicability of regulatory limitations prior to use. Prior to
handling, testing or disposing of any materials, testers must be knowledgeable about safe
laboratory practices, hazards and exposure, chemical procurement and storage, and personal
protective apparel and equipment.
http://www.dot.ca.gov/hq/esc/ctms/pdf/lab_safety_manual.pdf
End of Text
(California Test 112 contains 22 pages)
- 11 -
California Test 112
August 2012
- 12 -
California Test 112
August 2012
- 13 -
California Test 112
August 2012
- 14 -
California Test 112
August 2012
- 15 -
California Test 112
August 2012
- 16 -
California Test 112
August 2012
- 17 -
California Test 112
August 2012
- 18 -
California Test 112
August 2012
- 19 -
California Test 112
August 2012
- 20 -
California Test 112
August 2012
- 21 -
California Test 112
August 2012
- 22 -