Pp1am - External Street Lighting Work Programme

This document outlines the tasks, duration, dependencies, and timeline for an external street lighting project. The project involves five main tasks over 23 days: 1) footing work from December 21-28, 2) pole installation from December 29-January 11, 3) lamp installation on January 12-13, 4) feeder pillar installation on January 16-17, and 5) testing and commissioning from January 16-20. Each main task has sub-tasks, and tasks have dependencies that must be completed before subsequent tasks can begin.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
243 views2 pages

Pp1am - External Street Lighting Work Programme

This document outlines the tasks, duration, dependencies, and timeline for an external street lighting project. The project involves five main tasks over 23 days: 1) footing work from December 21-28, 2) pole installation from December 29-January 11, 3) lamp installation on January 12-13, 4) feeder pillar installation on January 16-17, and 5) testing and commissioning from January 16-20. Each main task has sub-tasks, and tasks have dependencies that must be completed before subsequent tasks can begin.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ID Task WBS Task Name Duration Start Finish 4 Dec '16Predecessors

Mode S W
0 0 EXTERNAL STREET LIGHTING 23 days Wed 21/12/16 Fri 20/1/17
1 1 FOOTING 6 days Wed 21/12/16 Wed 28/12/16
2 1.1 PACKING THE AREA OF POLE LOCATION 3 days Wed 21/12/16 Fri 23/12/16
3 1.2 FOOTING PLANTING 66 FT ROAD 6 days Wed 21/12/16 Wed 28/12/162SS
4 1.3 FOOTING PLANTING 100FT ROAD 6 days Wed 21/12/16 Wed 28/12/163SS
5 2 POLE 10 days Thu 29/12/16 Wed 11/1/17 1
6 2.1 POLE MOUNTING 66FT ROAD 4 days Thu 29/12/16 Tue 3/1/17
7 2.2 POLE MOUNTING 100FT ROAD 6 days Wed 4/1/17 Wed 11/1/17 6
8 3 LAMP INSTALLATION 2 days Thu 12/1/17 Fri 13/1/17 5
9 3.1 LAMP INSTALLATION FOR 66FT ROAD 2 days Thu 12/1/17 Fri 13/1/17
10 3.2 LAMP INSTALLATION FOR 100FT ROAD 2 days Thu 12/1/17 Fri 13/1/17 9SS
11 4 FEEDER PILLAR 2 days Mon 16/1/17 Tue 17/1/17 8
12 4.1 FEEDER PILLAR INSTALLATION 2 days Mon 16/1/17 Tue 17/1/17
13 4.2 CABLE TERMINATION 2 days Mon 16/1/17 Tue 17/1/17 12SS
14 5 TESTING AND COMMISIONING 5 days Mon 16/1/17 Fri 20/1/17 11SS
15 5.1 DEFECT RECTIFICATION 3 days Mon 16/1/17 Wed 18/1/17
16 5.2 SETTING THE TIMER 2 days Thu 19/1/17 Fri 20/1/17 15

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: EXTERNAL STREET LIGHTI Milestone Inactive Milestone Start-only


Date: Fri 16/12/16 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 1
18 Dec '16 1 Jan '17 15 Jan '17
W S T M F T S W S T M

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: EXTERNAL STREET LIGHTI Milestone Inactive Milestone Start-only


Date: Fri 16/12/16 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 2