PSM I Open Assesment
PSM I Open Assesment
PSM I Open Assesment
Points: 17 out of 30
Percentage: 56.7%
Duration: 00:13:46
Feedback
Thank you for taking the Open assessment of Scrum. Please review The Scrum Guide on Scrum.org and take this
assessment again to improve your score.
Ken Schwaber
Statistics by Category
Question 1 of 30
C) Support the Product Owner with insights and information into high value product and system
capabilities. Support the Scrum Master to cause organizational change that fosters
empiricism, self-organization, bottom-up intelligence, and intelligent release of software.
Points: 1 out of 1
Feedback
Management has no active role in the actual product development through Scrum. However, management
external to the Scrum team is incredibly important in setting the vision and strategy to guide the overall direction
of the organization.
Question 2 of 30
Correct answer: A)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The Development Team uses the Daily Scrum to inspect progress toward the Sprint Goal and to inspect how
progress is trending toward completing the work in the Sprint Backlog.
Question 3 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
B) It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out
what to do next.
C) It is a demo at the end of the Sprint for everyone in the organization to check on the work
done.
Points: 1 out of 1
Feedback
Every event in Scrum, besides the Sprint which is a container for the other events, is an opportunity to Inspect
AND Adapt.
Question 4 of 30
Points: 0 out of 1
Feedback
The duration of a Sprint is fixed and cannot be shortened or lengthened.
Question 5 of 30
Which two (2) things does the Development Team do during the first Sprint?
Correct answer: A) C)
You chose: C) D)
Note: This question displayed answer options in random order when taking this Test.
Feedback
The heart of Scrum is a Sprint, a time-box of one month or less during which a "Done", useable, and potentially
releasable product Increment is created. This applies to every Sprint
Question 6 of 30
Correct answer: C)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
Points: 0 out of 1
Feedback
Scrum is founded on empirical process control theory, or empiricism. Empiricism asserts that knowledge comes
from experience and making decisions based on what is known.
Three pillars uphold every implementation of empirical process control: transparency, inspection, and adaptation.
Question 7 of 30
Which statement best describes Scrum?
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
D) A defined and predictive process that conforms to the principles of Scientific Management.
Points: 1 out of 1
Feedback
Scrum is not a process or a technique for building products; rather, it is a framework within which you can
employ various processes and techniques.
Question 8 of 30
The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress.
What should the Development Team do?
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
B) Add the item to the current Sprint and drop an item of equal size.
D) Inform the Product Owner so he/she can work with the CEO.
Points: 1 out of 1
Feedback
The items selected for a Sprint have been selected as most valuable with the Product Owner. The items serve
the Sprint's goal. No changes should be made that endanger the Sprint Goal. No one external to the Scrum
Team can force changes on the Development Team (Sprint Backlog) and the Product Owner (Product Backlog).
Question 9 of 30
Correct answer: D)
You chose: D)
Note: This question displayed answer options in random order when taking this Test.
C) 4 hours.
D) 15 minutes.
Points: 1 out of 1
Feedback
The length of a daily Scrum is fixed at 15 minutes, it does not change with the length of a Sprint.
Question 10 of 30
Which of the below are roles on a Scrum Team?
Correct answer: A) D) E)
You chose: A) D) E)
Note: This question displayed answer options in random order when taking this Test.
A) Development Team
B) Users
C) Customers
D) Product Owner
E) Scrum Master
Points: 1 out of 1
Feedback
The Scrum Team consists of a Product Owner, the Development Team, and a Scrum Master.
Question 11 of 30
Correct answer: D)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Next Monday.
Feedback
A new Sprint starts immediately after the conclusion of the previous Sprint.
Question 12 of 30
During a Sprint, a Development Team determines that it will not be able to finish the complete
forecast. Who should be present to review and adjust the Sprint work selected?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) The Scrum Master, the project manager and the Development Team.
Points: 1 out of 1
Feedback
During the Sprint, scope may be clarified and re-negotiated between the Product Owner and Development Team
as more is learned.
Question 13 of 30
What are the two primary ways a Scrum Master keeps a Development Team working at its highest
level of productivity?
Correct answer: A) B)
You chose: A) B)
Note: This question displayed answer options in random order when taking this Test.
Points: 1 out of 1
Feedback
A Scrum Master is a servant-leader for the Development Team. Facilitation and removing impediments serves a
team in achieving the best productivity possible.
Question 14 of 30
An organization has decided to adopt Scrum, but management wants to change the terminology to
fit with terminology already used. What will likely happen if this is done?
Correct answer: D)
You chose: B)
A) Without a new vocabulary as a reminder of the change, very little change may actually
happen.
B) The organization may not understand what has changed with Scrum and the benefits of
Scrum may be lost.
Question 15 of 30
The Development Team should have all the skills needed to:
Correct answer: C)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) Complete the project as estimated when the date and cost are committed to the Product
Owner.
B) Do all of the development work, except for specialized testing that requires additional tools
and environments.
C) Turn the Product Backlog items it selects into an increment of potentially releasable product
functionality.
Points: 1 out of 1
Feedback
The Development Team consists of professionals who do the work of delivering a potentially releasable
Increment of "Done" product at the end of each Sprint. Development Teams are cross-functional, with all of the
skills as a team necessary to create a product Increment.
Question 16 of 30
Correct answer: A) B) C)
You chose: A) B) C)
A) The Scrum Master
B) The Product Owner
C) The Development Team
D) Project Manager
E) None of the above
Points: 1 out of 1
Feedback
The Scrum Team consists of the Scrum Master (manages the process), the Product Owner (decides what to do)
and the Development Team (does the work).
Question 17 of 30
Correct answer: C)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
Points: 0 out of 1
Feedback
Teams typically go through some steps before achieving a state of increased performance. Changing
membership typically reduces cohesion, affecting performance and productivity in the short term.
Question 18 of 30
What is the recommended size for a Development Team (within the Scrum Team)?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) Minimal 7
B) 3 to 9
C) 7 plus or minus 2
D) 9
Points: 1 out of 1
Feedback
Optimal Development Team size is small enough to remain nimble and large enough to complete significant
work. Fewer than three Development Team members decreases interaction and results in smaller productivity
gains. More than nine members simply requires too much coordination.
Question 19 of 30
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) 2 hours.
C) As long as needed.
D) 1 day.
Points: 1 out of 1
Feedback
Sprint Review is a four-hour time-boxed meeting for one-month Sprints. For shorter Sprints, the event is usually
shorter.
Question 20 of 30
Correct answer: E)
You chose: A)
Note: This question displayed answer options in random order when taking this Test.
A) Size, where small items are at the top and large items are at the bottom.
B) Risk, where safer items are at the top, and riskier items are at the bottom
Points: 0 out of 1
Feedback
The Product Owner decides what makes the most sense to optimize the value of the work being done by the
Development Team.
Question 21 of 30
Who has the final say on the order of the Product Backlog?
Correct answer: D)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
A) The Stakeholders
E) The CEO
Points: 0 out of 1
Feedback
The Product Owner is the sole person responsible for managing the Product Backlog.
Question 22 of 30
Why is the Daily Scrum held at the same time and same place?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
Points: 1 out of 1
Feedback
The Daily Scrum is held at the same time and place each day to reduce complexity.
Question 23 of 30
What is the main reason for the Scrum Master to be at the Daily Scrum?
Correct answer: B)
You chose: B)
Note: This question displayed answer options in random order when taking this Test.
B) He or she does not have to be there; he or she only has to ensure the Development Team
has a Daily Scrum.
C) To write down any changes to the Sprint Backlog, including adding new items, and tracking
progress on the burn-down.
Points: 1 out of 1
Feedback
The Scrum Master enforces the rule that only Development Team members participate in the Daily Scrum.
Question 24 of 30
Correct answer: A)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
C) Managing the project and ensuring that the work meets the commitments to the
stakeholders.
Points: 0 out of 1
Feedback
The Product Owner is responsible for maximizing the value of the product and the work of the Development
Team.
Question 25 of 30
It is mandatory that the product increment be released to production at the end of each Sprint.
Correct answer: B)
You chose: A)
A) True
B) False
Points: 0 out of 1
Feedback
The product increment should be usable and releasable at the end of every Sprint, but it does not have to be
released.
Question 26 of 30
Correct answer: A)
You chose: A)
A) True
B) False
Points: 1 out of 1
Feedback
The heart of Scrum is a Sprint, a time-box of one month or less during which a "Done", usable, and potentially
releasable product Increment is created.
Question 27 of 30
The Development Team should not be interrupted during the Sprint. The Sprint Goal should remain
intact. These are conditions that foster creativity, quality and productivity. Based on this, which of the
following is FALSE?
Correct answer: B)
You chose: C)
Note: This question displayed answer options in random order when taking this Test.
A) The Product Owner can help clarify or optimize the Sprint when asked by the Development
Team.
B) The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change
during the Sprint.
C) As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes and
may grow as the work emerges.
D) The Development Team may work with the Product Owner to remove or add work if it finds it
has more or less capacity than it expected.
Points: 0 out of 1
Feedback
The Sprint Backlog makes visible all of the work that the Development Team identifies as necessary to meet the
Sprint Goal. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog
emerges during the Sprint.
Question 28 of 30
Correct answer: A)
You chose: A)
A) True
B) False
Points: 1 out of 1
Feedback
A Scrum Team has a Scrum Master, a Product Owner and a Development Team. As a whole they have all
controls needed.
Question 29 of 30
Correct answer: D)
You chose: D)
A) Short enough to keep the business risk acceptable to the Product Owner.
B) Short enough to be able to synchronize the development work with other business events.
Points: 1 out of 1
Feedback
All of these choices are appropriate considerations in determining the length of a Sprint.
Question 30 of 30
A) When it becomes clear that not everything will be finished by the end of the Sprint.
B) When the Development Team feels that the work is too hard.
Points: 0 out of 1
Feedback
A Sprint can be cancelled before the Sprint time-box is over. A Sprint would be cancelled if the Sprint Goal
becomes obsolete. This might occur if the company changes direction or if market or technology conditions
change.