Federal Builders, Inc. v. Power Factors
Federal Builders, Inc. v. Power Factors
Federal Builders, Inc. v. Power Factors
,-,tt"~ t;,t>...
,,.._...,
$)upreme QI:ourt
;fflllmt iln
THIRD DIVISION
Promulgated:
POWER FACTORS, INC.,
Respondent. March 8, 2017
x---------------------------------------------------~~-~:!___ ~-~----x
DECISION
BERSAMIN, J.:
The Case
Designated as additional Member of the Third Division per Special Order No. 2417 dated January 4,
2017.
I
Rollo, pp. 32-45; penned by Associate Justice Leoncia R. Dimagiba and concurred in by Associate
Justice Rosmari D. Carandang and Associate Justice Ricardo R. Rosario.
2
ld.at98-128.
~
Decision 2 G.R. No. 211504
' .
Antecedents
Id. at 33.
Id.
Id. at 44.
Id. at 34-35.
Id. at 35.
?)
Decision 3 G.R. No. 211504
On February 8, 2010, the CIAC issued an order setting the case for
hearing, and directing that Federal's motion to dismiss be resolved after the
reception of evidence of the parties. 8
The foregoing amount shall earn legal interest at the rate of 6% per
annum from the date of this Final Award until this award becomes final
and executory, Claimant shall then be entitled to 12% per annum until the
entire amount is fully satisfied by Respondent.
Federal appealed the award to the CA insisting that the CIAC had no
jurisdiction to hear and decide the case; and that the amounts thereby
awarded to Power lacked legal and factual bases.
Id.
9
Supra note 2.
10
Supra note I.
~
t'. ...-.
SO ORDERED. 11
Issue
11
Id. at 44-45.
12
Id. at 38.
13
Id. at 42-43.
14
Rollo, p. 47.
~
Decision 5 G.R. No. 211504
1.
The parties had an effective agreement
to submit to voluntary arbitration;
hence, the CIAC had jurisdiction
15
Rule 4, CIAC Revised Rules; l!COMCEN. Inc. v. Foundation Specialists. Inc., G.R. Nos. 167022 &
169678, April 4, 2011, 647 SCRA 83, 97.
q
'' ....... Ill
in writing, but it need not be signed hy the parties, as long as the intent
is clear that the parties agree to submit a present or future
controversy arising from a construction contract to arbitration. It
may be in the form of exchange of letters sent by post or by telefax,
telexes, telegrams, electronic mail or any other mode of
communication.
Under Article 1318 of the Civil Code, a valid contract should have the
following essential elements, namely: (a) consent of the contracting parties;
(b) object certain that is the subject matter of the contract; and (c) cause or
consideration. Moreover, a contract does not need to be in writing in order
to be obligatory and effective unless the law specifically requires so.
1
" Sc:e perambulatory clauses of E.0. No. I 008.
17
Na1ional Irrigation Administr.:irion v Court of Appeals, GR. No. 129169, November 17, 1999, 318
SCRA 255, 269.
q
Decision 7 G.R. No. 211504
Pursuant to Article 1356 18 and Article 1357 19 of the Civil Code, contracts
shall be obligatory in whatever form they may have been entered into,
provided that all the essential requisites for their validity are present. Indeed,
there was a contract between Federal and Power even if the Contract of
Service was unsigned. Such contract was obligatory and binding between
them by virtue of all the essential elements for a valid contract being present.
The CIAC and the CA both found that the parties had disagreed on the
amount of the downpayment. On its part, Power indicated after receiving
and reviewing the draft of the Contract of Service that it wanted 30% as the
downpayment. Even so, Power did not modify anything else in the draft, and
returned the draft to Federal after signing it. It was Federal that did not sign
the draft because it was not amenable to the amount as modified by Power.
It is notable that the arbitration clause written in the draft of Federal was
unchallenged by the parties until their dispute arose.
18
Article 1356. Contracts shall be obligatory, in whatever form they may have been entered into,
provided all the essential requisites for their validity are present. However, when the law requires that a
contract be in some form in order that it may be valid or enforceable, or that a contract be proved in a
certain way, that requirement is absolute and indispensable. In such cases, the right of the parties stated in
the following article cannot be exercised.
19
Article 1357. If the law requires a document or other special foim, as in the acts and contracts
enumerated in the following article, the contracting parties may compel each other to observe that fonn,
once the contract has been perfected. This right may be exercised simultaneously with the action upon the
contract.
20
Rollo, p. 34.
~
>
Decision 8 G.R. No. 211504
21 Id.
22
Section 4. Form of arbitration agreement. - A contract to arbitrate a controversy therearter arising
between the parties, as well as a submission to arbitrate an existing controversy, shall be in writing and
subscribed by the party sought to be charged, or by his lawful agent.
The making of a contract or submission for arbitration described in section two hereof, providing for
arbitration of any controversy, shall be deemed a consent of the parties of the province or city where any of
the parties resides, to enforce such contract of submission.
n An Act to Authorize the Making of Arbitration and Submission Agreements, to Provide for the
Appointment of Arbitrators and the Procedure j(Jr Arbitration in Civil Controversies, and fiJr Other
Purposes; June 19, 1953.
24
Subsection 4.1.2, Rule 4 of the CIAC Revised Rules.
25
LM Power Engineering Corporation v. Capitol Industrial Construction Groups, Inc., G.R. No. 141833,
March 26, 2003, 399 SCRA 562, 569.
2
'' Id. at 570.
'J
Decision 9 G.R. No. 211504
2.
Amounts as modified by the CA are correct
SO ORDERED.
WE CONCUR:
J. VELASCO, JR.
Aociate Justice
Chairperson
/
.i~~
/BIENVENIDO L. REYXS /~ANCISUl. JARD"ELEZA
i Associate Justice/f\ 1 . I _ J Associate Justice
S. CAGUIOA
I attest that the conclusions in the above Deci~iop had been reached
in consultation before the case was assigned to the w.Jfter of the opinion of
the Court's Division.
J. VELASCO, JR.
A'ociate Justice
Chairperson
~
CERTIFICATION