DPR-July-06, 2017

EPTISA SERVICIOS DE INGENIERIA S.L


Z-MORH TUNNEL PROJECT (J&K)

EPTISA SERVICIOS DE INGENIERIA S.L Z MORH PROJECT (J & K)

DAILY PROGRESS
REPORT
PROGRESS SUMMARY

July 2017

CZARA RESORT, NH-1D, FOREST BLOCK, GAGANGIR, KASHMIR-1912002


DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

THE ENGINEER ATTENDANCE AT THE SITE


Sr. Shift From To
Engineer Position
No. Day HRS HRS
1 M.IMRAN TUNNEL ENGINEER Day 09.00 PM 07.00 PM
ASST. TUNNEL EXCAVATION
2 B.D.BARMAN Day 09.00am 06.30pm
EXPERT
3 S. K SINGH MATERIAL ENGINEER Day 09.00 AM 06.00 PM

4 DR.JAVED ENVIRONMENT EXPERT Day - -

5 B.P.SINGH SURVEY ENGINEER Day 09.30 AM 6.00 PM

6 M.BHAT SURVEY ENGINEER Day 09.30 am 7.30 pm


DRAINAGE ENGINEER
7 HARISH KR. MAHAVAR Day - -
/ HYDROLOGIST
8 JUGENDRA SINGH GEOLOGIST Day 10.00 AM 06.00 AM

9 JAGANNATH MONDAL CAD EXPERT Day - -


10 VIKASH KUMAR SINGH LAB TECHNICIAN DAY 9.00 AM 6.00 PM
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

PROGRESS SUMMARY
Monthly
Previou Current
(July 17) Total Progress Till Date
Jobsite s chain Daily Progress (m) chain
Progress (m)
age (m) age (m)
(m)
West Portal

Main
71.50 02.50 74.00 11.50 74.00 m
Tunnel

Egress 173.50 02.50 176.00 14.50 176.00 m


Ventilation
308.00 03.00 311.00 15.00 311.00 m
Tunnel
Main to
-- -- -- -- --
Ventilation Tunnel

East
Egress to
-- -- -- -- --
East
Main to
-- -- -- -- --
west
Egress to
-- -- -- -- --
West
Main -- -- -- -- --
East
tunnel Egress -- -- -- -- --

EL-2638.70 S.D.R Drilling and grouting in progress, 100 numbers completed & 100 grouted.
Eastern Portal
Micro pile 126 COMPLETED AND 126 GROUTED, work is in progress.
Total SDR-100 Nos. grouting complete, Micro pile 126 Nos. completed & 126 nos Grouted.
Remarks: 1. Micro piles 126 Nos drilled and Grouted till date. (Up to 06-07-2017)
2. In Main Tunnel Support System changed from Ch: 71.50 M from S-II BIS to S-IV with
Cross Section S-IV
25< RMS (Bieniawski) < 35
0.1 < Q (Barton) < 0.4

3. Micro piling Machine breakdown from 09:00 am onwards, Work stopped at Eastern Portal.
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

II . CSIR (RMR) SYSTEM OF ROCKMASS CLASSIFICATION (Bieniawski -1973 )

DAILY PROGRESS REPORTS IN GEOLOGY DEPARTMET


Z-MORH TUNNEL (J&K)
DATE GROUN Formatio Key Paramitrrs Description LOCATION CHAINAG BLASTING ROCK SUPPORT REMA
D TYPE n Rock Type E TIME MASS SYSTEM RKS
RATIN
G

06-07-2017 (GT-4) Zojila 1-(UCS) GT3-Fractured West Portal- 175 9 V to VI Very


Formation 2-(RQD) , Metabasite Egress Poor
3-(SPACING OF and Mass Tunnel
DISCONTINUITY) , Quartzphyllite
4 (CONDITION OF and Calcschist.
DISCONTINUITY0 ,
5-(GROUND
WATER)
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

06-07-2017 (GT-3) Zojila 1-(UCS) GT3-Fractured West Portal- 73 19 V to VI Very


Formation 2-(RQD) , Metabasite Main Tunnel Poor
3-(SPACING OF and Mass
DISCONTINUITY) , Quartzphyllite
4 (CONDITION OF and Calcschist.
DISCONTINUITY0 ,
5-(GROUND
WATER)

06-07-2017 (GT-2) Panjajal 1-(UCS) GT2 Group Ventilation 308 7.00am 65 III Good
Trap 2-(RQD) , Mass Tunnel
Formation 3-(SPACING OF Metabasite of (Adite)
DISCONTINUITY) , Panjal Trap
4 (CONDITION OF
DISCONTINUITY0 ,
5-(GROUND
WATER)

Prepared By - Jugendra Singh (Geologist)


DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

1- DAILY QUANTITY OF SHOTCRETE (QA/QC)


Remarks
m3
Main

-
West Tunnel

Shotcrete (PFRS) 28.00


Egress

Shotcrete (PFRS) 29.00


Main

--
East Tunnel

Egress

--
V to E

--
Main
V to
W

--
Ventilation Tunnel

V to E

--
Egress
V to W

--
Ventilatio

Shotcrete (PFRS) 12.00 m3


n
(11+180)
Bridge
Major

--

Prepared By Santosh Singh (Quality Expert)


DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

2- QUANTITY OF DAILY CONSUMPTION/BALANCE EXPLOSIVE

Date W. P. Ventilation Tunnel Ventilation E. P. TOTAL Re


Tunnel ma
MAIN EGRES MAIN EGRESS MAIN EGRESS
rks
S
W to V W to V V to V to E V to V to E E to V E to V
W W
Detonating 50 M - - - - - 150 Mts - - -
Cord m.
25 - - - - - - - - - - -
kg

32 - - - - - - - - - - -
Cartridge

40 24.2 kg - - - - 420.320 kg - - -

TOTAL - - - - - - - - - - -

Elect. 01 - - - - - 01 - - -
Detona

No 19 - - - - - 238.00 Nos - - -
tors

Elect.
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

3- CYCLE TIME MONITERING WESTERN PORTAL ( MAIN TUNNEL )

By Blast By Blast
Operations Total
From To From To Total Hrs
in Hrs Remarks
Tunnel
Cycle-01 Cycle-02

01 Face Breaking 11.00 am 11.40 am 0.40 11.30 pm 01.00 am 1.30


02 Charging 11.40 am 12.30 pm 0.50 - - -
03 Blasting 12.30 pm 12.40 pm 0.10 - - -
04 Defuming 12.40 pm 02.00 pm 1.20 - - -
05 Mucking 02.00 pm 03.30 pm 1.30 01.00 am 03.30 am 2.30
Scaling with 03.30 pm 04.00 pm 0.30 03.30 am 04.00 am 0.30
06
bottom cleaning
Surveying and 04.00 pm 04.30 pm 0.30 04.00 am 04.30 am 0.30
07
face mapping
Initial Layer 04.30 pm 05.30 pm 1.0 04.30 am 05.30 am 1.0
08
Shotcrete
09 Rib erection - - - - - -
SN Rock Bolt & 05.30 pm 06.30 pm 1.0 05.30 am 06.30 am 1.0
10
Swellex
Lattice Girder 06.30 pm 07.30 pm 06.30 am 07.30 am 1.0
11
Installation
12 Underpinning - - - - - -
Final layer 07.30 pm 11.30 pm 4.0 07.30 am 10.00 am 2.30
13
shotcreting
Total 11.30 Total 10.30 Hrs
Hrs= Hrs Hrs=

RMR 19

REMARKS:
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

4- CYCLE TIME MONITERING WESTERN PORTAL (ESCAPE TUNNEL)


Operations Face Breaking Face Breaking Face Breaking Remarks
in
From To Total From To Total From to Total
Tunnel
Hrs Hrs Hrs
Cycle-01 Cycle-02 Cycle -03

1 Face Breaking 02.00 03.00 1.0 11.00 12.00 1.0 - - -


pm pm pm am
3 Charging - - - - - - - - -
4 Blasting - - - - - - - - -
5 Defuming - - - - - - - - -
6 Mucking 03.00 04.00 1.0 12.00 01.00 1.0 - - -
pm pm am am
7 Scaling & 04.00 05.00 1.0 01.00 02.00 1.0 - - -
bottom pm pm am am
cleaning
8 Surveying and 05.00 05.30 0.30 02.00 02.30 0.30 - - -
face mapping pm pm am am
9 Initial Layer 05.30 06.30 1.0 02.30 03.30 1.0 - - -
Shotcrete pm pm am am
10 Swellex Rock 06.30 07.30 1.0 03.30 04.30 1.0 - - -
Bolt pm pm am am
11 SN Rock Bolt - - - - - - - - -
12 SDR Rock Bolt - - - - - - - - -
& Wiremesh
13 Lattice Girder 07.30 08.30 1.0 04.30 05.30 1.0 - - -
Installation pm pm am am
14 Under pinning 08.30 09.30 1.0 05.30 06.30 1.0 - - -
& Grouting pm pm am am
15 Final Layer 09.30 11.00 1.30 06.30 09.00 2.30 - - -
Shotcrete. pm pm am am
TOTAL 09.00 10.00 Hrs
Hrs Hrs
16 RMR 09
Remarks: -
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

PROGRESS SUMMARY WESTERN PORTAL (MAIN TUNNEL)


Excavation up to previous month(Up to 62.50 Meters Remarks
june17)
Excavated in current month(July17) 11.50 Meters S IV
(m) Cross Section S-IV
Total excavated Length (m) 74.00 Meters 25< RMS (Bieniawski) < 35
APCO start Chain age -2.47 Meters 0.1 < Q (Barton) < 0.4

Previous Daily Current Monthly Rock No. of Excavated Total


Chain age Progress Chain Progress Class Blast by Progress
age (Month Till Date
of July)
(m) (m) (m) (m) (m) (m)

71.50 Mts 02.50 Mts 74.00 Mts 11.50 Mts Poor One blast Rock 74.00 Mts
Breaker

5- PROGRESS SUMMARY WESTERN PORTAL (ESCAPE TUNNEL)


Excavation up to previous month (Up to 161.50 Meters Remarks
june17) (m)
Excavated in current month(July17) (m) 14.50 Meters Rock class SGE-II BIS
Total excavated Length (m) 176.00 Meters 30< RMR (BIENIAWSKI)<40
APCO start Chain age -2.47 0.08 Q (BARTON) <1

Previous Daily Current Monthly Rock No. Excavated Total


Chain age Progress Chain age Progress Class of by Progress
meter meter meter (July17) Blast Till Date
(m) (m) (m) (m) (m)
173.50 02.50 Mts 176.00 14.50 Mts Very No Rock 176.00
Mts Mts poor Blast Breaker Mts
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

6- 10 STATUS OF THE SUPPORTING MEASURES (INITIAL ROCK SUPPORT) IN THE


TUNNEL

Western portal
(MAIN TUNNEL) LATTICE GIRDER S -IV (G T 4)

Western portal LATICE GIRDER SGE-II ( GT 3)


(ESCAPE TUNNEL)

REMARKS:
A.) CROSS SECTION S IV MAIN TUNNEL
Cross Section S-IV
25< RMS (Bieniawski) < 35
0.1 < Q (Barton) < 0.4

B.)CROSS SECTION SGE-II ESCAPE TUNNEL


30< RMR (BIENIAWSKI) <40
0.08 Q (BARTON) <1
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

7- CYCLE TIME MONITERING VENTILATION TUNNEL

First Blast Second Blast Third Blast


Operations Total Fro Total Fro Total
From To To To Rem
in Hrs m Hrs m Hrs arks
Tunnel
Cycle-01 Cycle-02 Cycle-03
12.00
1 Face Drilling 10.00 am 2.0 - - - - - -
pm
1.30
3 Charging 12.00 pm 1.30 - - - - - -
pm
02.00
4 Blasting 1.30 pm 0.30 - - - - - -
pm
02.30
5 Defuming 02.00 pm 0.30 - - - - - -
pm
08.00
6 Mucking 02.30 pm 5.30 - - - - - -
pm
Scaling with
09.00
7 bottom 08.00 pm 1.0 - - - - - -
pm
cleaning
Surveying and 09.30
8 09.00 pm 0.30 - - - - - -
face mapping pm
Initial Layer 10.30
9 09.30 pm 1.0 - - - - - -
Shotcrete pm

10 Rib erection - - - - - - - - -
Swellex Rock
11 12.00
bolt 10.30 pm 1.30 - - - - - -
am
SN Rock Bolt
Lattice Girder
12 - - - - - - - - -
Installation
Final Layer 02.00
13 12.00 am 2.0 - - - - - -
Shotcrete. am
Total 16.00 Total Hrs
Hrs= Hrs Hrs=
14 RMR 65

Face Tunnel Meter = 311.00 Meters.


REMARKS:
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

8. PROGRESS SUMMARY VENTILATION TUNNEL

Excavation up to previous month (Up 296.00 Meters Remarks


to june17)
Excavated in current month (July17)(m) 15.00 Meters
Total excavated Length Till Date (m) 311.00 Meters
APCO start Chain age -2.47 Meters

Previous Daily Current Monthly Rock No. Excavated Total


Chain Progress Chain Progress(July17) Class of by Progress
age age Blast Till Date

(m) (m) (m) (m) (m) (m)


308.00 03.00 311.00 15.00 Mts Very 01 By Blast 311.00
Mts Mts Mts good Mts

9. STATUS OF THE SUPPORTING MEASURES (INITIAL ROCK SUPPORT) IN THE


TUNNEL

VENTILATION
SVT 1 (G T- 2)
TUNNEL
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

10.CYCLE TIME MONITERING EASTERN PORTAL (MAIN TUNNEL)


Operations First Blast Second Blast
in Total
Tunnel From To From To
Total Hrs Hrs Remarks

Cycle -01 Cycle-02


1 Face Drilling - - NO
2 Pipe roofing - - - - - - -
3 Charging - - - - - - -
4 Blasting - - - - - - -
5 Defuming - - - - - - -
6 Mucking - - - - - - -
Scaling with - - - - - - -
7
bottom cleaning
Surveying and - NO WORK STARTED FOR TUNNELING -
8
face mapping
Initial Layer - - - - - - -
9
Shotcrete
10 Rib erection - - - - - - -
11 SN Rock Bolt - - - - - - -
12 SDR Rock Bolt - - - - - - -
Lattice Girder - - - - - - -
13
Installation
Final Layer - - - - - - -
14
Shotcrete.
Total Hrs= -- Total --
Hrs=
-- -- --
15 RMR-
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

11.CYCLE TIME MONITERING EASTERN PORTAL (ESCAPE TUNNEL)

Operations First Blast Second Blast


in Remarks
Tunnel From To Total Hrs From To Total Hrs

1 Face Drilling - - - - - - -

2 Charging - - - - - - -

3 Blasting - - - - - - -

4 Defuming - - - - - - -
5 Mucking - - - - - - -
Scaling with - - - - - - -
6
bottom cleaning
7 Surveying - NO WORK STARTED FOR TUNNELING -

8 Face Mapping - - - - - - -

Initial Layer - - - - - - -
9
Shorcrete
Swellex Bolt - - - - - - -
10
drilling
11 SN Rock Bolt - - - - - - -

12 SDR Rock Bolt - - - - - - -


Lattice Girder - - - - - - -
13
Installation
Final Layer - - - - - - -
14
Shotcrete
- - Total - - Total Hrs= -
Hrs=

15 RMR -- -- --
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

12.EASTERN PORTAL (MAIN TUNNEL)

Remarks
Excavation up to previous month -- NO WORKS STARTED
Excavated in current month (m) -- --
Total excavated Length (m) -- --
APCO start Chain age -- --

Previous Current
Daily Monthly No. Excavated Total Progress
Chain Chain Rock
Progress Progress of by Till Date
age age Class
Blast
(m) (m) (m) (m) (m) (m)
-- -- -- -- -- -- -- --

13.EASTERN PORTAL (ESCAPE TUNNEL)

Remarks
Excavation up to previous month -- --
Excavated in current month (m) -- --
Total excavated Length (m) -- --
APCO start Chain age -- --

Previous Current
Daily Monthly Rock No. of Excavated Total Progress
Chain Chain
Progress Progress Class Blast by Till Date
age age
(m) (m) (m) (m) (m) (m)
-- -- -- -- -- -- -- --
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

14.STATUS OF THE SUPPORTING MEASURES ( INITIAL ROCK SUPPORT ) IN THE


TUNNEL

EASTERN PORTAL
(MICROPILING
SDRB WITH 20 MTS 2*2 STAGGERED PATTERN WITH DIA 76 MM BIT AND
32 MM INSTALLED 100 NOS AT AN ELEVATION 2436 MTS AT THE FRONTAL
WORKS)BENCH
SLOPE. Micro pile, total-126 Nos drilled and grouted at Top Bench R.L
2638.332.
1 and 2

EASTERN SDRB WORKS COMPLETED OF 32MM DIA, (100 Nos.)


PORTAL SDRB (DIA 51 MM) 4700 RM TO BE DRILLED & GROUTED AFTER MICROPILE.

15.NUMBER OF MANPOWER AND EQUIPMENT FOR THREE SITES

1ST Shift NO.S 2nd Shift NO.S Total nos

24*3 Sites=72 nos 24*3 Sites=72 nos 144 NUMBERS

SITE OBSERVATIONS:

1. THE VENTILATION DUCT TO BE EXTENDED IN THE EGRESS TUNNEL.

2. NO IMPROVEMENT OF THE SEDIMENTATION TANK AT THE WESTERN PORTAL.

3. BEFORE BLASTING IN MAIN OR EGRESS INFORMATION TO THE INDEPENDENT ENGINEER TO BE GIVEN.

4. THE GEOBURGG TEAM FOR CABLING AND TORQUING HAS TO BE DEPLOYED AT THE WESTERN PORTAL.

5. THE DITCH DRAIN ABOVE THE MAIN TUNNEL HAS TO BE CLEARED IMMEDIATELY.

6. THE INVERT AT THE VENTILATION TUNNEL NEEDS TO BE CLEANED AND HOUSE KEEPING JOB TO BE DONE.

7. THE SEDIMENTATION TANK TO BE PROPERLY FUNCTIONABLE AT THE VENTILATION TUNNEL.


DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

8. THE MICROPILING WORKS EXECUTED AT THE EASTERN PORTAL NEEDS MORE EFFICIENCY AND MORE MAN
POWER TO BE DEPLOYED SO THAT THE 2ND SHIFT WORK CAN BE STARTED.

Prepared By Majid Imran(Tunnel Engineer) & Bapan Deb Barman (Asst. Tunnel
Excavation Expert)

16. ENVIRONMENTAL:
1. Gas Monitoring inside the Tunnel:

Location Parameter Readings Permissible Remarks


Recorded limits
Oxygen 20.9% >19%
Carbon Dioxide (CO2) 450 ppm <5000 ppm 10:40 PM
VENTILATION
(0.5000%)
PORTAL Carbon Monoxide (CO) 8ppm <50 ppm (0.0050%)
Ammonia (NH3) 0 ppm 100 ppm
Methane 0 ppm <1000 ppm
(0.1000%)
Oxygen 20.9% >19%
Carbon Dioxide (CO2) 900ppm <5000 ppm
(0.5000%) 11:35 PM
WESTERN Carbon Monoxide (CO) 11 ppm <50 ppm (0.0050%)
PORTAL (ET) Ammonia (NH3) 1 ppm 100 ppm
Methane 0 ppm <1000 ppm
(0.1000%)

1. Dust Pollution at site locations:


Gigantic amount of dust is being generated by moving of vehicles from all site locations. This act is violation of
Air (prevention & control of pollution) 1987 Chapter-iv section 21&22. It must be noted that this dust can be
root cause of various effect on environment constituents (Vegetation and humans); i.e Blocked stomata,
inhibition of pollen germination, reduce photosynthesis, reduce transpiration, reduce growth and block stomata
(vegetation); Tuberculosis, silicosis, lung diseases and eye irritation.
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

Image.1. Dust Pollution

Prepared By: Dr. Javid Sheikh (Environment Expert)

17 SURVEY DAILY ACTIVITIES:


Sr. WESTERN PORTAL VENTILATION EASTERN PORTAL APPROACH REMARKS
No MAIN ESCAPE TUNNEL MAIN ESCAPE ROAD
TUNNEL TUNNEL TUNNEL TUNNEL
1. Face Face Face Marking Micro piling
Marking at marking at for drilling at grouting --- ---- Taken
CH: 74.00 CH: 176.00 CH: 0+311.00 total - Geometry
126.00 Nos. profile of
Main Tunnel.

2. Extenso Extenso Extenso Abutment


Meter Meter Meter A1, Checking --- --- ---
reading at reading at reading at excavation
CH: 0+010 CH: 0+015 CH: 0+034. of Raft at
and CH: And CH: CH: 11+100
--- 0+076. 0+135 of major
bridge.

Prepared by: MR. BRIJESH PRATAP & MR. MANZOOR BHAT( SURVEY EXPERT)
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

SITE PHOTOGRAPHS (06-July-2017) :-

ROCK SUPPORT SN SWELLEW IN PROGRESS IN E.T. & LATTICE GIRDER ERECTION IN


PROGRESS
DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

AFTER FINAL LAYER SHOTCRETE COMPLETED


DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

IN VENTILATION FACE DRILLING ALONG WITH FACE CHARGING IN PROGRESS

IN EASTERN PORTAL MICROPILING & GROUT IN PROGRESS


DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)

IN EASTERN PORTAL DITCH DRAIN LINING WORK IN PROGRESS.


DPR-July-06, 2017
EPTISA SERVICIOS DE INGENIERIA S.L
Z-MORH TUNNEL PROJECT (J&K)