2016 Sgca 07 PDF
2016 Sgca 07 PDF
2016 Sgca 07 PDF
[2016] SGCA 7
Introduction
The learned Judge (the Judge) below upheld the summary judgment
entered by the Assistant Registrar (the AR) and this decision is reported in
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
GTMS Construction Pte Ltd v Ser Kim Koi (Chan Sau Yan and Chan Sau Yan
Associates, third parties) [2015] 1 SLR 671 (Judgment). Dissatisfied, the
appellant, Mr Ser Kim Koi (the Appellant) brings this appeal. We heard the
appeal on 26 May 2015 and reserved judgment. We now give our decision.
Background facts
Tenders were called for the Buildings and the respondent, GTMS
Construction Pte Ltd (the Respondent) submitted its tender on 15 November
2010. Three rounds of tender evaluation exercises were carried out and the
Architect made a recommendation on 4 May 2011 to accept the Respondents
tender. The Appellant agreed. The Architect issued the Letter of Acceptance on
behalf of the Appellant on 13 May 2011. 2 The contract sum was $13.13m. 3 The
period of construction was 20 months with a contract completion date of 21
February 2013. 4
1
ROA Vol III (Part A) at pp 137 153.
2
ROA Vol III (Part A) at pp 154 159.
3
ROA Vol III (Part B) at p 14.
4
. ROA Vol III (Part B) at p 62.
2
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
2013. 5 The Appellant takes issue with this extension of time granted by the
Architect.
5
ROA Vol III (Part B) at p 102.
6
ROA Vol III (Part B) at p 131.
7
ROA Vol III (Part C) at pp 201-202.
8
ROA Vol III (Part C) at pp 201-202.
9
ROA Vol III (Part B) at p 131
3
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
A second TOP inspection was carried out by the BCA on 18 June 2013 10
and the Buildings again failed the TOP inspection. TOP was eventually obtained
on 16 September 2013. 11
By then disputes had arisen between the parties over the completion of
the works and the Appellant alleged extensive defects and non-compliant works.
The Appellant employed a chartered building surveyor, Mr Chin Cheong (Chin
Cheong) from Building Appraisal Pte Ltd (BAPL), to document these
alleged defects. 14
10
ROA Vol III (Part C) at pp 206 - 207
11
ROA Vol III (Part C) at p 210.
12
ACB Vol II at p 91.
13
ACB Vol II at p 92
14
BAPL 1st Report (ROA Vol III (Part D) at pp 30 132); BAPL 2nd Report (ROA Vol
III (Part J) at pp 171 196.
4
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
and 6 November 2013 for $418,318.60 and $202,497.72 (both inclusive of GST)
respectively, claiming a total of $620,816.32: see [1] above. 15 When payment
was not forthcoming, the Respondent commenced Suit 50 of 2014 (S
50/2014) on 13 January 2014. The Appellant filed its defence and counterclaim
against the Architect and the Respondent for the alleged numerous defects,
delays and conspiracy. The Appellant also added the Architect and his firm,
Chan Sau Yan Associates, as third parties.
Proceedings Below
(a) the Architect should not have issued the Completion Certificate
because the conditions for its issuance as stated in the parties contract
were not satisfied. Furthermore, the Completion Certificate was issued
even before the TOP was.
15
ROA Vol III (Part H) at p 111.
5
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
Notwithstanding the arguments made, the AR was not satisfied that there
were triable issues as to whether the disputed certificates were tainted by fraud,
improper pressure or interference. He was of the view that the court should not
be concerned with shoddy, poor or unsatisfactory workmanship and that the
evidence borne out at the very highest shows that the Architect was merely
negligent. It therefore cannot be said that he was acting fraudulently and
accordingly granted summary judgment.
The Appellant appealed against the ARs decision but the appeal was
dismissed with costs. The Judge first acknowledged that the Architects
evidence, which we will turn to later, played a significant role in [his]
deliberation in finding that the Disputed Certificates were not tainted by fraud,
improper pressure or interference (Judgment at [43]).
6
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
The Judges reasons for rejecting each of the grounds to set aside the
Disputed Certificates are as follows:
(a) First, the evidence that the Respondent sought to rely on (set out
in [12] above) were circumstantial and insufficient to prove fraud
(Judgment at [56]). Furthermore, there was a qualitative difference
between fraud and negligence. The Judge noted at [57]:
7
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
16
Notice of Appeal filed on 2 October 2014.
17
Summons for Stay of Execution of Judgment/Order (SUM 5454/2014) filed on 31 Oct
2014.
18
Defendants written submissions for SUM 5454/2012 at [22] (see also AEIC of Ser
Kim Koi dated 31 October 2014 at [13]).
8
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
Arguments on appeal
Appellants arguments
Before us, Mr Mohan Reviendran Pillay (Mr Pillay), counsel for the
Appellant, submitted that leave to defend should be given because there was a
19
Excerpt in AEIC of Ser Kim Koi dated 31 October 2014 at [17] (see Dennis Tans
AEIC dated 7 April 2014 in OS 317/2014 (SUM 1731/2014) at [33]).
20
Dennis Tans AEIC dated 6 Nov 2014 at p 214 (OS 317/2014 (SUM 1731/2014).
21
Minute Sheet dated 12 Nov 2014.
22
Minute Sheet dated 19 Nov 2014.
23
Minute Sheet dated 19 Nov 2014; Order of Court (ORC 7665/2014) 3rd order.
9
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
(a) First, the Architect should not have issued the Completion
Certificate. This is because:
(i) The Buildings were not ready for occupation and use
when the Completion Certificate was issued as the TOP was only
issued months after the Completion Certificate was issued.
Moreover, entering into occupation of and using a building
which has not obtained TOP was an offence under s 12 of the
Building Control Act (Cap 29, 1999 Rev Ed) (the Act).
(ii) The conditions for its issuance under cl 24(4) of the SIA
Conditions read with Item 72 of the Preliminaries (Item 72)
were not satisfied. The Architect therefore cannot say that the
Buildings appear to be completed and to comply with the
[c]ontract in all respects, save for minor outstanding works, as
he did in the Completion Certificate: see [6] and [7] above. The
relevant portions of cl 24(4) and Item 72 read:
72 COMPLETION CERTIFICATE
10
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
24
ROA Vol III (Part D) at p 131.
25
ROA Vol III (Part D) at p 131.
11
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
26
ROA Vol III (Part J) at pp 203217.
27
ROA Vol III (Part J) at pp 203205.
12
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
13
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
1. CHANGE OF FINISHES
We hereby confirm change of internal timber flooring
from 150mm wide x 2mm thk White Oak wood strips
to 90mm wide x 15mm thk Indian Rosewood strips with
plywood sub base.
And staircase finishes from 25mm thk solid White Oak
tread & 15mm thk Teak riser to 90mm wide x 15mm
thk Indian Rosewood with plywood sub-base, where
applicable.
[another persons signature,
signing on behalf of the Architect]
CHAN SAU YAN, SONNY
ARCHITECT
[underlined in original]
28
ROA Vol III (Part K) at p 151.
14
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
The Appellant no longer relies on his point that the Architect granted
unwarranted extensions of time for the Respondent to ensure that there was
permanent electrical supply to the Buildings: see [12(e)] above. We therefore
need say no more on this.
Respondents arguments
(a) First, the Appellant cannot argue that the Disputed Certificates
were tainted by fraud simply by taking issue with the issuance of the
Completion Certificate. This is because the Disputed Certificates and
the Completion Certificate are completely different certificates issued
apart from one another. The Disputed Certificates were issued some
15
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
Our decision
The central issue in this appeal against the entry of summary judgment
is whether the Appellant has made out any of the grounds found in cl 31(13) of
the SIA Conditions so as to deprive IC 25 and 26 of temporary finality.
Applicable principles
16
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
17
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
have considered the matters which are said to have been dealt
with in his certificate.
19 The need for an [a]rchitects certificate to cohere with the
conditions laid down in cl 31(13) of the SIA Conditions was also
recognised by this court in Lojan Properties Pte Ltd v Tropicon
Contractors Pte Ltd
18
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
Both the trial judge and this court were unanimous that on these facts,
(which included the architects revocation of his previous extensions of time,
his re-valuation of the interim payment certificates, his issuing of a further
19
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
interim payment certificate which was not issued in compliance with cl 31(1)
and (2) as it was issued long after completion of the works, recording in his
certificate entitlement to liquidated damages more than two and a half years
after practical completion and only after the owner had written to him), the court
was entitled to draw the conclusion that there was undue interference and/or
improper pressure by the owner thereby depriving these certificates of any
temporary finality enforceable by summary process.
20
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
findings of fact, the trial judge below was correct in finding that a prima facie
case of fraud was made out. But more than that, this court went on to state that
in light of these facts, it could not have been disputed that the [d]isputed
[c]ertificates had not been issued in accordance with cl 31(13) of the SIA
Conditions [emphasis in original] and went on to note at [25] that:
This court ruled that even if the irregularities only affected part of an
interim payment certificate, there could be no severance and under the SIA
Conditions that deprived the whole certificate of temporary finality. These
certificates ceased to attract any temporary finality because they were in some
material part not issued strictly in accordance with the contract and/or were
tainted by fraud or improper pressure or interference (Chin Ivan at [26] and
[27]).
These cases illustrate the nature and level of scrutiny of the integrity of
the certification process leading up to the interim payment certificate as well as
21
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
The exposition in Derry v Peek is over 125 years old and the Singapore
courts have endorsed it on many occasions (see eg, Panatron Pte Ltd and
another v Lee Cheow Lee and another [2001] 2 SLR(R) 435 at [13]; Wishing
22
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
Star Ltd v Jurong Town Corp [2008] 2 SLR(R) 909 at [16]; Wee Chiaw Sek
Anna v Ng Li-Ann Genevieve (sole executrix of the estate of Ng Hock Seng,
deceased) and another [2013] 3 SLR 801 at [35]; Raiffeisen Zentralbank
Osterreich AG v Archer Daniels Midland Co and others [2007] 1 SLR(R) 196
at [38]; and Chu Said Thong and another v Vision Law LLC [2014] 4 SLR 375
at [114]).
23
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
Clause 31(13) requires that the Architect shall in all matters certify
strictly in accordance with the terms of the Contract [emphasis added]. It is
therefore apposite to see what this contract called for in relation to the
Completion Certificate and its issuance. Clause 24(4), set out above at
[20(a)(ii)], provides that the Architect shall issue the Completion Certificate
when the Works appear to be complete and to comply with the Contract in all
respects whereupon the Contract shall be deemed to be completed. More
importantly, Item 72 of the Preliminaries, also set out at [20(a)(ii)] above, sets
out when works can be deemed completed in order for the Completion
Certificate to be issued. Item 72 is worth repeating:
29
ROA Vol III (Part I) at p 17-22.
30
ROA Vol III (Part I) at p 29.
24
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
The meaning of the phrase in Item 72 para (a): All parts of the Works
are ready for occupation and for use ... [emphasis added in bold italics] is
clear. It means, in no uncertain terms, that the employer can go into occupation
of and use the premises. It is difficult to understand how the Architect could
have issued the Completion Certificate on 15 May 2013, certifying contract
completion on 17 April 2013, 31 when just two weeks prior to his issue of that
Completion Certificate, the Buildings had failed the first TOP inspection on 30
April 2013. 32
Mr Pillay rightly points out that anyone in the building and construction
industry knows that entering into occupation of and using a building which has
not obtained TOP or its Certificate of Statutory Completion is an offence under
s 12 of the Act, the relevant provisions of which read:
Occupation of buildings
12.(1) Except as otherwise provided in this Act, no person shall
occupy, or permit or cause to be occupied, any building where
any building works have been carried out unless the
Commissioner of Building Control has issued a certificate of
statutory completion in respect of that building.
(2) Nothing in subsection (1) shall prohibit
(b) the occupation by any person of any building in
respect of which a temporary occupation permit has
been granted.
(6) Any person who contravenes subsection (1) shall be guilty
of an offence and shall be liable on conviction
31
ROA Vol III (Part B) at p 131.
32
ROA Vol III (Part C) at pp 201-202.
25
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
Item 72 para (b) is also unambiguous in its requirements, viz, that all
services have been tested, commissioned and operating satisfactorily. Yet in
the Schedule of minor outstanding works attached to the Completion
Certificate, the Architect had noted that some basic works and services had yet
to be tested, commissioned or checked if they were operating satisfactorily: 35
33
ROA Vol III (Part C) at pp 206-207.
34
ROA Vol III (Part C) at p 210.
35
ROA Vol III (Part B) at p 132.
26
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
36
ROA Vol III (Part I) at p 17.
37
ROA Vol III (Part I) at p 17.
27
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
inspection as it was the thinking then that applying for and obtaining TOP was
the architects duty), which are no longer in use, or a mere truism or statement
of fact that all the works must have been properly carried out before it can pass
the TOP inspection. But this was not the true issue, which the Architect side-
steps, and not what this contract stipulated. Moreover, this explanation glosses
over his errors that were pointed out by the BCA as one of the causes for the
Buildings failing the first TOP inspection.
38
ROA Vol III (Part I) at p 18.
39
ROA Vol III (Part B) at p 132.
28
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
If it was the latter, then we cannot understand how the Architect could
label this as minor outstanding works. It is anything but minor. Staircases are
potentially dangerous structures because tripping and falling on staircases can
have very dire consequences including serious physical injury or even death.
The BCAs Approved Document: Acceptable Solutions (Version 4.0, July
2011) (BCA Approved Document), issued by the Commissioner pursuant to
Regulation 27 of the Building Control Regulations 2003 has detailed provisions
governing this aspect, especially at clauses E.3.4.1 and E.3.4.2 as to minimum
sizes of the tread, ie, the horizontal part of a step on which a persons foot will
rest (275 mm) and the maximum height of risers, ie, the vertical height of a
step (175 mm) in staircases.
29
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
It need hardly be said that if these defects (not minor in nature) were
apparent, then he does not say why he nonetheless issued his Completion
Certificate on 15 May 2013, certifying completion on 17 April 2013.
40
ROA Vol III (Part I) at p 18.
30
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
the requirements of paras (a) and (b) of Item 72 had clearly not been fulfilled.
There is no explanation or reasons why he was of the opinion that they had been
fulfilled. The Architect also states here that all parts of the works were, in his
opinion, ready for occupation. It will readily be seen that the Architect
conveniently ignores Item 72 requiring the works to be ready for occupation
and for use. [emphasis added]. Further, the Architect really has no answer to
the fact that on his own attachment to the Completion Certificate, it clearly
shows that not all services had been tested, commissioned and operating
satisfactorily: see [47] above. That was certainly not the case on 17 April 2013.
41
ROA Vol III (Part I) at p 13.
31
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
shows that the Architect cannot defend or explain his issue of the Completion
Certificate.
It will be apposite to note what the BCA stated on the works failing the
1st TOP inspection. On 30 April 2013, some 15 days before the Architect issued
his Completion Certificate, the Commissioner of Building Control, wrote to
both the Respondent and the Architect stating that the Buildings failed the 1st
TOP inspection (30 April 2013 letter). The material portion of that letter
provides: 42
42
ROA Vol III (Part C) at pp 201 to 202.
32
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
33
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
H.3.4.3 In all buildings, except for industrial buildings
(a) the size of any opening or gap in a barrier shall not
be large enough as to permit the passage of a sphere of
a diameter of 100mm; and
Besides the problem with the height of the risers and the uniformity of
the risers and treads on staircases, there were other errors that were made by the
Architect himself which were picked up by the BCA. The first was in an area at
or near the swimming pool of Unit No 12B, where there was a vertical drop of
more than 1 metre; contrary to clause H.2.1 there was no barrier to prevent
people from falling. This was noted by the BCA as CYSA [the Architect]
missed out the barriers at no.12B-swimming pool. The second also related to
barriers where an item is noted as CYSA missed out barriers at no.12A
pavilion. Further, within that item, it appears that where barriers were provided
for, there were also construction errors in relation to the inadequate height of
the barriers (see clause H.3.2.1 of the BCA Approved Document). The Architect
does not explain these lapses, which he should have picked up when he carried
out the pre-TOP inspections.
There was one more construction error that was noted: Opening at
pavilion which contravened cl H.3.4.3 of the BCA Approved Document, viz,
an opening or gap in a barrier which allowed passage of a sphere of a diameter
of 100 mm. The Respondent was asked by the BCA to extend the parapet wall
to maintain the gap at 100mm.
34
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
Having had errors in relation to the risers and treads pointed out by the
BCA in the first TOP Inspection, 43 one would have expected the Architect to
have carried out another careful pre-TOP inspection to ensure that all such
errors were rectified. This was especially so as the BCA had stated that their list
of non-compliant items was not exhaustive. The Architect clearly did not do so
because, in the second BCA TOP inspection on 18 June 2013, 44 further failures
to comply with the same requirements as to risers and treads were noted by the
BCA in another area the steps at the reinforced concrete flat roof for all units
and the last step at the landscaped area of Unit No 12A.
43
ROA Vol III (Part C) at pp 201-202.
44
ROA Vol III (Part C) at p 206-207
35
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
36
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
whether it was true or false. The Architects affidavit and his contradictory and
shifting statements only serve to underscore the serious irregularity in his
certification and certification process.
The Architect failed to certify the release of one moiety of the retention
sum upon issuing his Completion Certificate, as he should have under cl 31(9)
of the SIA Conditions. Clause 31(9) provides:
37
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
sum to cover the cost of outstanding work (if any) not yet
completed pursuant to Clause 24.(5) of these Conditions at the
date of the said Certificate.
[emphasis added in italics and bold italics]
Whilst cl 31(9) allows the Architect to withhold a reasonable sum to cover the
cost of outstanding work not yet completed, if any, there is no evidence from
the Architect that this was the case or that it was withheld for that reason.
Instead, IC 25 was issued some 4 months after the works were, in the opinion
of the Architect, complete and complied in all respects with the contract and
some 3 months and 19 days after he issued his Completion Certificate. The
evidence shows the full moiety of the retention sum was released. In Interim
Certificate 24 dated 1 July 2013 (IC 24), the retention sum was $644,195.65.
In IC 25 (dated 3 September 2013) the retention sum was reduced to
$315,945.65. The retention sum released to the Respondent was thus $328,250
or approximately 51% of the retention sum certified in IC 24. There is no
explanation from the Architect whatsoever, despite his acknowledging in para
36 of his affidavit that 50% of the retention sum had to be released upon
the issuance of the Completion Certificate (emphasis added). IC 25 clearly did
not comply with cl 31(13)s stricture that the Architect shall in all matters
certify strictly in accordance with the terms of the Contract. The Interim
Certificate is invalidly issued and therefore cannot have any temporary finality
under the SIA Conditions.
We also find it strange that the Respondent did not appear to have made
any complaint about the late release of the retention sum, especially since it
appears that the Respondent was, on its own admission, in a weak financial
38
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
position: see [17] above. Dennis Tan had this to say in an affidavit filed in
related proceedings, ie, OS 317/2014: 45
45
Excerpt in AEIC of Ser Kim Koi dated 31 October 2014 at [17] (see Dennis Tans
AEIC dated 7 April 2014 in OS 317/2014 (SUM 1731/2014) at [33]).
39
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
46
Ser Kim Kois 1st AEIC at [33] (ROA Vol III (Part A) at p 98).
47
ROA Vol III (Part I) at p 22.
40
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
We note a second strange feature of this case. Whilst the Architect has
given fairly detailed explanations for his time extensions and the alleged
defects, in stark contrast, he says very little substantively about the completion
and even less about what items were comprised in IC 25 and IC 26: see [74]
41
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
above. We note that instead, it is the Respondents Dennis Tan who attempts to
explain what was being certified for payment under IC 25 and IC 26. It is
important for us to point out that where certificates are being impugned, it is not
for the Respondent, who is a party to the dispute with the Appellant, to speak
for the Architect. In enforcement proceedings, where the temporary finality of
his certificates are in question, it is important for the courts to hear from the
Architect himself about his certification process and on the certificates he
issued; this is especially so where he has been made a party to the action and
therefore has the opportunity to explain his position and certification.
Accordingly, what the Respondent, (or Appellant for that matter) has to
say in these circumstances is of very little weight. Thus if there are serious and
legitimate doubts about the Architects certification, and if the Architect has
chosen not to explain his certification, it will often be insufficient for an
interested party to do so on his behalf. Nonetheless, without derogating from
the foregoing, we shall put that to one side and examine Dennis Tans
explanations contained in his 3rd affidavit dated 30 April 2014. He attributed the
amount certified under IC 25 to prime cost (PC) adjustments. At para 17, he
states:
42
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
out that the Interim Certificates do not show the PC items. We have to look at
the accompanying Interim Valuation for the Prime Cost & Provisional Sums
(the PC Items). A perusal of the Interim Valuation by M/S Faithful & Gould,
the quantity surveyors, shows there was indeed an increase in the PC Items, but
that occurred between the Interim Valuation for IC 23 and IC 24. The PC Items
increased from $596,015.15 to $788,126.90. However the PC Items in the
Interim Valuations for IC 24 and IC 25 remain unchanged and in IC 26 there
was only a very small increase of $19.19 compared to IC 25: 48
Interim Certificate/
PC Items Valuation Change
Interim Valuation
IC 22 (19 April 2013)
$583,229.26 -
IV 22 (14 March 2013)
IC 23 (5 June 2013)
$596,015.15 +$12,785.89
IV 23 (30 April 2013)
IC 24 (1 July 2013)
$788,126.90 +$192,111.75
IV 24 (30 May 2013)
IC 25 (3 Sept 2013)
$788,126.90 -
IV 25 (31 July 2013)
IC 26 (6 Nov 2013)
$788,146.09 +$19.19
IV 26 (31 Oct 2013)
Dennis Tans attempt to then suggest the PC rate adjustments were under
the Main Building Works is also misleading. First, there is already an item for
PC Items in the Interim Valuation and, as noted above, except for an increase
between IC 23 and IC 24, the PC Items remains, in effect, constant from IC 24
48
ROA Vol III (Part J) at p 154 and ROA Vol III (Part K) at p104.
43
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
to IC 26. Secondly, the Main Building Works were 95.73%, 95.5% and 95.51%
(for Unit No 12, 12A and 12B respectively) complete by value in Interim
Valuation 22, on which IC 22 was based, and this figure remained constant from
IC 22 to IC 25. It was only in IC 26 that the Main Building works increased to
100% by value:
(b) Interim Valuation No. 23, 24 50 and 25 (on which IC 23, 24 and
25 respectively were based) all contain identical figures on
completion by value as those in (a)(i), (ii) and (iii) above for the
three units. 51
49
ROA Vol III (Part K) at p 70.
50
ROA Vol III (Part C) at p 106.
51
ACB Vol II at p 111.
44
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
The significance of the above figures is first that the three units were
only 95.73%, 95.5% and 95.51% complete respectively by value when IC 22
was issued on 19 April 2013 (with valuation as at 14 March 2013), which was
2 days after the works were completed on 17 April 2013, and remained at the
same level of completion by value through to IC 25 which was issued on 3
September 2013, some 4 months after the Architect certified the works were
complete. Secondly, this fact, ex facie, shows that there were no further works
done between the issue of IC 23 dated 30 April 2013 and IC 25 dated 3
September 2013 as valued by the quantity surveyor because the level of
completion of these units by value did not change. On the evidence before us,
IC 25s $62,701.96 (the remainder after deducting $328,250 of retention monies
released) could not have been for any PC rate adjustments.
52
ACB Vol II at p 117.
45
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
For the above reasons, it is very clear that IC 25 was not issued strictly
in accordance with the terms of the contract, and accordingly cannot be
accorded temporary finality.
Again, it is the Respondent, not the Architect, who tries to furnish the
explanation. The Respondent maintains no new work was done but instead
offers two reasons for the sum certified for payment in IC 26:
(a) First, the sum on IC 26 was due to completed works and [t]he
PC rate adjustments were made between the QS Consultants and the
46
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
(b) Secondly, the certified sum for the M&E works contained an
omission of $205,605.41 and was due to the submission of operation
manual and drawings and the regularization of the contract sum arising
from variation works. 54
With respect to (a), for the same reasons set out at [77] to [80] above,
except for $19.19, the sum certified in IC 26 cannot be due to PC rate
adjustments. As noted above, whilst there was a large increase in PC Items
between IC 23 and IC 24, and, in effect no increase in PC Items from IC 24 to
IC 26, there was no increase in the percentage completion of the buildings from
IC 22 to IC 25.
53
Dennis Tans 3rd AEIC dated 30 April 2014 at [17(iii)] (ROA Vol III (Part K) at p 14).
54
Dennis Tans 3rd AEIC dated 30 April 2014 at [18] (ROA Vol III (Part K) at p 15).
55
ROA Vol III (Part B) at p 70.
47
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
On the face of these Interim Valuations, works were still being valued
well after the purported completion under cl 24(4) and Item 72. If so, then the
works could not have been complete under cl 24(4) and Item 72 as of 17 April
2013, or, if they were indeed complete and complied in all respects with the
contract, then the Architect has not explained why these sums for work done
came to be certified so many months after contract completion. The
Respondents explanation for these figures is inconsistent with the evidence
presented. It should also be noted that of the documents exhibited by the
Respondent, there are many missing documents, and some important documents
that are exhibited are not complete.
56
ROA Vol III (Part K) at pp 7778.
57
ROA Vol III (Part J) at p 148.
48
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
58
ROA Vol III (Part J) at p 154.
59
ROA Vol III (Part J) at p 160.
60
ROA Vol III (Part J) at p 166
49
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
value, all services, including M&E services, could have been tested,
commissioned and found to be operating satisfactorily. If at all so, then there is
no explanation as to the sudden increase of M&E work by 10.32% in IC 26.
Needless to say there is no explanation from the Architect or the M&E
Consultant.
(a) The first point to note is the admission by the Respondent that
IC 26s payment for M&E items was for the submission of operation
manuals. This means Item 72(b) was not fully complied with until after
IV 25 which valued works as at 31 July 2013.
61
Dennis Tans 3rd AEIC dated 30 April 2014 at [18] (ROA Vol III (Part K) at p 15).
50
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
then states that the net certification for M&E works in IC 26 was only
$31,150 which was for the submission of operation manuals, drawings
and the regularization of the contract sum arising from variation
works. It is difficult to make much sense of these statements.
(c) On their face, the interim certificates (as is usual in the industry)
do not have a sufficient level of breakdown to validate the first point
made in Dennis Tans statement above at (b), eg, it does not contain a
separate M&E component, let alone the figure $205,605.41, as M&E
works are within the item: Work carried out by Contractor:
$11,334,625.80 (for IC 25).
51
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
(f) We now move down a further level, since these are M&E Works,
to examine the M&E consultants valuation and payment
recommendations (M&E Valuation); again some, but not all or
complete copies, are exhibited in Dennis Tans affidavit.
62
ROA Vol III (Part K) at p 105.
63
ROA Vol III (Part K) at p 103.
52
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
64
ROA Vol III (Part C) at p 186.
65
ROA Vol III (Part H) at p 131.
53
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
54
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
items that were in fact ordered and installed. It also does not tell
us whether the works comprised in these items were carried out
or not and if so when. If these were variations ordered by January
2013, then at least IC 22 (19 April 2013) and the interim
certificates after that, and probably a few interim certificates
prior to that, were wrong and under-certified. This would include
IC 23 and IC 24. Importantly, we do not know if this is a
complete document and equally importantly, there were other
items in this document which do not appear in the EIs set out in
M&E Valuation No 25 as one would expect, eg, S/No 28, AI No
25 with the description: Supply and delivery of light fittings and
accessories, 21,453.421 and with the remarks: As advised
by M&E Engineer.
55
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
56
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
Besides these serious irregularities, and the fact that the maintenance
period as set out in the Completion Certificate was clearly wrong, there is
another glaring omission. The Architect ignores delays and, as a consequence
of delay, liquidated damages. Whilst the Architect has dealt in some detail with
the extension of time in paras 17 to 34 of his affidavit, 66 he dismisses the
concomitant issue of delay with great brevity in para 41 of his affidavit:
66
ROA Vol III (Part I) at pp 9 - 17.
67
ROA Vol III (Part I) at pp 9 - 17.
57
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
September 2013 68 when the buildings achieved the TOP. The period of delay
would then be significant. If, (i) as is undeniable, TOP was finally obtained only
on 16 September 2013, (ii) if, testing and commissioning for M&E installation
is required before completion, as the Architect admits in para 28 of his affidavit,
(iii) if there were M&E and other services that had yet to be tested,
commissioned and found to be operating satisfactorily as at 17 April 2013, as
noted in the Completion Certificate, and (iv) there were no outstanding
applications for extension of time, then it must follow that liquidated damages
must have started to run from 18 April 2013.
It should be noted that the supply of gas to the Buildings was not tested,
commissioned and found to be satisfactory when the Completion Certificate
was issued. Dennis Tan himself admitted that the gas supply was only tested on
6 August 2013, close to three months after the Completion Certificate was
issued. 69 We have also referred to the evidence of delayed production of the
operating manuals, a requirement for completion under Item 72(b). It goes
without saying that duly certified liquidated damages would be available as a
set-off against any sums certified due to a contractor.
Lastly, it is also clear that the Architect was partly responsible for the
Buildings failing the TOP inspections: see [61] and [62] above. Both the
Respondent and the Architect are silent as to what was done to remedy this. In
a normal case, there would have been an instruction from the Architect to the
Respondent to carry out these additional works. There would then have been an
attendant extension of time and payment for variation work. These additional
68
ROA Vol III (Part C) at p 211.
69
Dennis Tan Chong Keats 2nd affidavit dated 7 April 2014 (ROA Vol III (Part I) at p
226.
58
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
works must have been carried out otherwise TOP would not have been
eventually obtained. No doubt all these issues will be explored at the substantive
hearing stage.
59
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
70
See eg, Plaintiffs Supplementary Submissions before the AR.
60
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
Conclusion
Every case must depend on its own special facts. Whilst we will not lay
down a hard and fast rule to say there can never be a case where the evidence,
as distinct from the process of certification and proper certification strictly in
accordance with the terms of the contract, is so clear as to support a prima facie
finding of fraud or recklessness or irregularity in relation to the merits or
contents of an architects certificate under the SIA Conditions, such a case must
be rare and quite exceptional.
61
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
This case is exceptional in our view and findings. It must be seen against
what must be numerous construction projects contracted on the SIA Conditions
which are completed without such serious irregularities and errors in
certification. What this case does unfortunately illustrate is that some architects,
like those in Lojan Properties and Chin Ivan, project their profession in a very
poor light when they administer their contracts with such disregard for its terms
and conditions and which are, after all, those of a standard form put forward by
their own professional organisation. In the vast majority of cases of this nature,
it is the architect, (albeit with assistance from the quantity surveyors), who
compiles and puts forward the construction contract, to the owner and
contractor, for execution. To then disregard, in a sense their own contract terms
and conditions or to display ignorance of some of its terms or content seems to
be very unfortunate and tarnishes the good name of their profession.
For the reasons set out above, we allow the appeal. The judgment and
orders for costs entered into below by the AR and the Judge are set aside and
the Appellant is to have his costs here and below (including the costs of and
incidental to the application in SUM 5454/2014 which were reserved to this
Court: see [17] above), such costs to be agreed or taxed. There will be the usual
consequential orders for the release of monies furnished by the Appellant as
62
Ser Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7
security for costs for this appeal and the sum of $640,816.32 ordered by the
Judge to be paid into court by the Appellant are to be paid out to the Appellant.
Mohan Reviendran Pillay, Yeo Boon Tat and Danna Er (MPillay) for
the appellant;
Thulasidas s/o Rengasamy Suppramaniam (Ling Das & Partners) for
the respondent.
63