PS: HVE:10: EF:01/00
Quantity: System consisting of prime coat, screed coat, and topping coat and total built up thickness of the floor should be 5mm
Serial No. DESCRIPTION OF REQUIREMENT DESIRED ACTION OFFERED BY THE VENDOR DEVIATIONS REMARKS(Only on deviations)
(IF ANY, ELSE PRINT NONE)
End use of the Area: Test equipment like Impulse Volatage Generator,
AC test transformer,Swichgear panael, potential divider and test objects etc.
1.1 Vendor to note
will be installed at different locations. Total load of 25 tons will be
distributed in the 40 X 24 meters area.
Temperature inside the test hall : Maximum expected ambient Vendor to note as input
1.3
temperature is 45 C. parameter
Page 1 of 4
Serial No. DESCRIPTION OF REQUIREMENT DESIRED ACTION OFFERED BY THE VENDOR DEVIATIONS REMARKS(Only on deviations)
(IF ANY, ELSE PRINT NONE)
Matrix coating system: Consists of prime coat, screed coat and topping
2.2 Vendor to conform
coat
Primary coating: The primary coat is a two component full solids coating
with excellent bonding on to concrete surface. The application is by
lambskin short pile roller / screeder at a spreading rate of 0.25 to 0.75 kgs
2.3 Vendor to conform
per sqare meter. Total builtup thickness should be 200 micron. Primary
coat is allowed to get track free before application of heavy duty industrial
screed.
Screed coating: Base lining is done with a three component solvent free
epoxy urethane urea screed to fill the post holes / dents on the base floor
and level the undulation / pot holes of the base floor. The spreading rate for
this is to be determined by the extend of leveling required for the base
2.4 floor and thickness that is proposed to buil up. The buil up thickness of this Vendor to conform
screed floor shall be arround 3000microns. The screed is kept for curing
upto 4 to5 hours to get workable strength for next proceedure. An
intermediate coat (Base coat) is to be applied to avoid any pinholes,
waviness etc.
Top finish coat: Two component epoxy urethane urea coating which is
applied by lambs wool roller / roller notched trowel . Total built up
2.5 thichness shall be arround 2000microns. Dust & dirt has to be removed Vendor to conform
from the surface before starting the top coat.The colour pigment will be
finalised at the time of purchase order .
Page 2 of 4
Serial No. DESCRIPTION OF REQUIREMENT DESIRED ACTION OFFERED BY THE VENDOR DEVIATIONS REMARKS(Only on deviations)
(IF ANY, ELSE PRINT NONE)
3 Surface preparation:
Cleaning of the soaked oil : to get good bonding of the epoxy floor &
durability it is essntial to check the presence of oil (if any) inside the floor.
3.2 Vendor to conform
Burning procedure is to be carried out(if required) to remove the oil till the
floor become bright white.
Filling of the pot holes / cracks: The pot holes and expansion joints (if
any) are to be filled with the suitable material. The pat holes are to be filled
3.3 & leveled with pot filling compound. Similarly the cracks & expansion Vendor to conform
joints have to be filled with crack seal compound which is having the
expansion & compression properties as per the surrounding temperature
Self leveling compound: After final coating ,it should be kept for 24
3.4 hours for functional cure. Self leveling compound can be applied if Vendor to conform
required. to make the surface smooth and level.
BHEL will provide required water ,electricity and storage place for
6.1 Vendor to note
materials, tools brought by supplier and civil work (if any)
Page 3 of 4
Serial No. DESCRIPTION OF REQUIREMENT DESIRED ACTION OFFERED BY THE VENDOR DEVIATIONS REMARKS(Only on deviations)
(IF ANY, ELSE PRINT NONE)
Page 4 of 4