Primavera Project Planner: Predecessor (Successor)
Primavera Project Planner: Predecessor (Successor)
/ :
(Predecessor)
. (Successor)
( - )
:
( - ) + .
.Formwork for P.C Foundation
. Finish to Start (FS) Rel .
. Lag .
. .
.
. Predecessors
.
Activity Description (Successors) Rel Lag
ID
S.00.100 Excavation works Formworks for PC Foundations FS 0
S.00.200 Filling Up works Formwork for RC Slabs - Ground floor FS -1
P.01.100 Formworks for PC Foundations Pouring for PC Foundations FS 0
Removing Formwork for PC FS 0
P.01.120 Pouring for PC Foundations
Foundations
Formwork for RC Foundations FS 0
Removing Formwork for PC Formwork for RC Foundations SS 0
P.01.130
Foundations
R.01.100 Formwork for RC Foundations Steel Fixing for RC Foundations FS -2
R.01.110 Steel Fixing for RC Foundations Pouring for RC Foundations FS 0
Removing Formwork for RC FS 0
R.01.120 Pouring for RC Foundations
Foundations
Formwork for RC Columns - Ground FS 0
floor
Removing Formwork for RC Formwork for RC Columns - Ground SS 0
R.01.130
Foundations floor
Formwork for RC Columns - Steel Fixing for RC Columns - Ground FF 1
R.02.100
Ground floor floor
Pouring for RC Columns - Ground floor FS 0
R.02.110 Steel Fixing for RC Columns - Pouring for RC Columns - Ground floor FS 0
Ground floor
Pouring for RC Columns - Removing Formwork for RC Columns - FS 1
R.02.120
Ground floor Ground floor
Removing Formwork for RC Formwork for RC Slabs - Ground floor SS 0
R.02.130
Columns - Ground floor
Filling Up works FS 0
Formwork for RC Columns - Steel Fixing for RC Columns - First FF 1
R.02.200
First floor floor
Pouring for RC Columns - First floor FS 0
Steel Fixing for RC Columns - Pouring for RC Columns - First floor FS 0
R.02.210
First floor
Pouring for RC Columns - First Removing Formwork for RC Columns - FS 0
R.02.220
floor First floor
Removing Formwork for RC SS 0
R.02.230 Formwork for RC Slabs - First floor
Columns - First floor
Formwork for RC Slabs - FS -2
R.03.100 Steel Fixing for RC Slabs - Ground floor
Ground floor
Steel Fixing for RC Slabs - FS 0
R.03.110 Pouring for RC Slabs - Ground floor
Ground floor
Pouring for RC Slabs - Ground Removing Formwork for RC Slabs - FS 10
R.03.120
floor Ground floor
Formwork for RC Columns - First floor FS 1
Removing Formwork for RC Formwork for RC Columns - First floor SS 0
R. 03.130
Slabs - Ground floor
Formwork for RC Slabs - First Steel Fixing for RC Slabs - First floor FS -2
R. 03.200
floor
Steel Fixing for RC Slabs - First FS 0
R. 03.210 Pouring for RC Slabs - First floor
floor
Pouring for RC Slabs - First Removing Formwork for RC Slabs - FS 10
R. 03.220
floor First floor
Removing Formwork for RC
R. 03.230
Slabs - First floor
Tools Schedule .
.( - )
( - )
( - )
( - )
. OK
- ) .
.(
( - )
View Activity Form Double Click
( - )
( - )
OD : Ordinary Duration
RD : Remaining Duration
( )
:
:
Data Calendars -
( - )
( - ) -
( - )
Global Calendar
01
Add
. ( - )
( - )
- ) ( - ) Standard
. (
( - )
. Nonwork
( - )
( - ) Holidays
( - )
Repeating End Start
.
Exceptions
. Repeating
ES : Early Start
LS : Late Start
EF : Early Finish
LF : Late Finish
TF : Total Float
FF : Free Float
/ : Primavera Project Planner
WBS :
:
Educational Project (1
P
(2
:
A Soil Works
B PC
C RC
(3
.
(4
.
:
WBS Code
Level
1 P *Edu.
Project
* Soil
2 P.A Works
S.00.100 Excavation works
S.00.200 Filling Up works
* PC
2 P.B Works
P.01.100 Formworks for PC
Foundations
P.01.120 Pouring for PC
Foundations
P.01.130 Removing
Formwork for PC
Foundations
* RC
2 P.C Works
3 P.C.01 RC Foundation
R.01.100 Formwork for RC
Foundations
R.01.110 Steel Fixing for RC
Foundations
R.01.120 Pouring for RC
Foundations
R.01.130 Removing Formwork
for RC Foundations
3 P.C.02 RC Columns
4 P.C.02.00 Ground Floor
R.02.100 Formwork for RC
Columns - Ground
floor
R.02.110 Steel Fixing for RC
Columns - Ground
floor
R.02.120 Pouring for RC
Columns - Ground
floor
R.02.130 Removing Formwork
for RC Columns -
Ground floor
4 P.C.02.01 First Floor
R.02.200 Formwork for RC
Columns - First floor
R.02.210 Steel Fixing for RC
Columns - First floor
R.02.220 Pouring for RC
Columns - First floor
R.02.230 Removing Formwork
for RC Columns - First
floor
3 P.C.03 RC Slabs
RC Slabs Ground
4 P.C.03.00 Floor
R.03.100 Formwork for RC
Slabs - Ground floor
R.03.110 Steel Fixing for RC
Slabs - Ground floor
R.03.120 Pouring for RC Slabs -
Ground floor
R. 03.130 Removing Formwork
for RC Slabs - Ground
floor
RC Slabs First
4 P.C.03.01 Floor
R. 03.200 Formwork for RC
Slabs - First floor
R. 03.210 Steel Fixing for RC
Slabs - First floor
R. 03.220 Pouring for RC Slabs -
First floor
R. 03.230 Removing Formwork
for RC Slabs - First
floor
:
-1
Structure (1-5) Data WBS
(1-5)
.(2-5) Structure 2
(2-5)
48 WBS 3
Width
. Separator
. 2
. 2
(3-5) (.)
(3-5)
OK WBS 4
WBS (1-5)
P + P Educational Project -
.Title
(4-5) -
(4-5)
WBS 5
:
. View Activity form
(5-5)
WBS Steel fixing for R.C. Slab ground floor
P.C.03.00 RC Slabs Ground Floor
:
: WBS 6
(6-5) Format Organize
(6-5)
(7-5) Work Breakdown
(7-5)
*
.
. -
:
Activity ID
.
. Activity Description
Activity Original Duration
.
:
.
Enter C.07.100 Activity ID
Formwork fro RC Foundation Activity Description
. Orig Dur
.
( )
(.)
:
C.01.100
( 100 ) ( 01. ) ( C. )
01. C.
.
:
. Tools Options Activity Inserting
:
( )
Automatically number activities
. A.10.130 A.10.120
Activity Form
View Activity
F7 Form
:
( )
:
. : ID *
. : Formwork for R.C. Foundation *
. Original Duration : OD *
. Remaining Duration : RD *
Percent Complete : Pct *
. : Cal *
. : Type *
. : ES *
. : EF *
. : LS *
. : LF *
Total Float : TF *
Free Float : FF *
. : *
. : *
:
. Task Activity
.
.
.
. Independent Activity
. Meeting Activity
:
:
Monday Tuesday Wednesday Thursday Friday
Activity Cal
Res. 1 Cal
Res. 2 Cal
Res. 3 Cal
. Monday
. Meeting Independent Task
Lag = 0 SS
.
.
. Meeting Independent
.
.
( )
SS
:
Task
.
Independent
.
Wednesday Meeting
.
. Start Milestone
Start Milestone
: =
. =
.
.
( )
. Finish Milestone
Finish
: = Milestone
. =
.
.
( )
. Start Flag
Start
: = Flag
. =
.
.
. Finish Flag
Finish
: = Flag
. =
.
.
.Hammock Activity
.
:
:
= RC Works
. SS , Lag = 0 RC Works Formwork for R.C. Foundation
. FF , Lag = 0 Dismantling Shuttering of R.C. Slab RC Works
:
( )
:
( )
.WBS Activity
. WBS Code
: WBS
= RC Works
. WBS
. WBS
: Primavera Project
/:
Planner
*
.
, - 1
.
. 11
xx.yy.zzz
xx.
yy
. zzz
Soil Works *
A. Soil Works
01.
02
PC works *
B. PC Works
01.
RC works *
C. RC works
01.
02.
03.
.
Activity ID Description Duration ( Days)
* Soil Works
A.01.100 Excavation 8
A.02.100 Filling Up 5
* PC Works
B.01.100 Formworks for PC Foundations 3
B.01.120 Pouring for PC Foundations 5
B.01.130 Removing Formwork for PC Foundations 2
* RC Works
RC Foundation
C.01.100 Formwork for RC Foundations 3
C.01.110 Steel Fixing for RC Foundations 7
C.01.120 Pouring for RC Foundations 4
C.01.130 Removing Formwork for RC Foundations 2
RC Columns Ground Floor
C.02.100 Formwork for RC Columns - Ground 6
C.02.110 Steel Fixing for RC Columns - Ground 3
C.02.120 Pouring for RC Columns - Ground 2
C.02.130 Removing Formwork for RC Columns - Ground 2
RC Columns First Floor
C.02.200 Formwork for RC Columns - First 6
C.02.210 Steel Fixing for RC Columns - First 3
C.02.220 Pouring for RC Columns - First 2
C.02.230 Removing Formwork for RC Columns - First 2
RC Slabs Ground Floor
C.03.100 Formwork for RC Slabs - Ground 8
C.03.110 Steel Fixing for RC Slabs - Ground 5
C.03.120 Pouring for RC Slabs - Ground 3
C. 03.130 Removing Formwork for RC Slabs - Ground 3
RC Slabs First Floor
C. 03.200 Formwork for RC Slabs - First 8
C. 03.210 Steel Fixing for RC Slabs - First 5
C. 03.220 Pouring for RC Slabs - First 3
C. 03.230 Removing Formwork for RC Slabs - First 3
(13) File New -2
( 1 - 3)
:
Current Directory
. Project Name
. 16 Number/Version
Project Title
. Company Name
Planning Unit
.
. Workdays/week
. Week starts on
. Project start
.(23)
(23)
OK -3
Enter
Orig Dur Description
.( 3 3 )
(33)
3) Layout File Save -4
.( 4
(43)
.( 5 3 ) Layout OK
(53)
(33)