National Policy For Hydro Power Development
National Policy For Hydro Power Development
National Policy For Hydro Power Development
Despite hydroelectric projects being recognised as the most economic and preferred
source of electricity, share of hydro power has been declining steadily since 1963. The
share of hydro power has been continuously declining during the last three decades.
The hydro share has declined from 44 per cent in 1970 to 25 per cent in 1998. The ideal
hydro thermal mix should be in the ratio of 40:60. Because of an imbalance in the hydel
thermal mix especially in the Eastern and Western regions, many thermal power stations
are required to back down during off peak hours. The capacity of the thermal plants
cannot be fully utilised resulting in a loss of about 4 to 5 per cent in the plant load factor.
Even if the share of hydro power is to be maintained at the existing level of 25 per cent,
the capacity addition during the 9th and 10th Plan would work out to 23,000 MW. If the
share were to be enhanced to 30 per cent, it would require a further addition of 10, 000
MW of hydro capacity.
The constraints which have affected hydro development are technical (difficult
investigation, inadequacies in tunnelling methods), financial (deficiencies in providing
long term financing), tariff related issues and managerial weaknesses (poor contract
management). The hydro projects are also affected by geological surprises (especially
in the Himalayan region where underground tunnelling is required), inaccessibility of the
area, problems due to delay in land acquisition, and resettlement of project affected
families, law & order problem in militant infested areas.
Objectives
The programmed capacity addition from hydel projects during the 9th Plan is 9815 MW,
of which Central Sector and State Sector will contribute 3455 MW and 5810 MW
respectively and the balance 550 MW will be contributed by the Private Sector.
Sanctioned and ongoing schemes under implementation will enable a capacity addition
of 6537 MW during the 10th Plan, of which 990 MW, 4498 MW and 1050 MW will be the
contribution of Central, State and Private Sectors respectively. In addition, 12 projects
(5615 MW) have been identified for advance action in the 9th Plan for benefits in the
10th Plan.
The Government of India has set the following objectives for accelerating the pace of
hydro power development:-
(i) Ensuring targeted capacity addition during 9th Plan :
The 9th Plan programme envisages capacity addition of 9815 MW from hydel projects in
the total capacity addition of 40245 MW. The Central Sector hydel projects would
contribute 3455 MW, State Sector would add 5810 MW and Private Sector 550 MW.
Keeping in view that the achievement in 8th Plan had been dismal, the Government is
determined to ensure that no slippage is allowed to occur and the targeted capacity
addition in the 9th Plan is achieved in full.
(ii) Exploitation of vast hydroelectric potential at a faster pace:
The Government would initiate advance action for taking up new hydro projects since the
ongoing projects will contribute a very small percentage of the desired capacity addition
envisioned for 10th Plan and beyond. Towards this end, Government would take up for
execution all the CEA cleared projects, and take steps to update and obtain clearances
for pending DPRs. Measures for vigorously starting survey and investigations for new
green field sites would also be implemented shortly. In addition, Government is keen to
restart and activate the hydro projects which are either languishing for want of funds or
are remaining dormant due to unresolved inter-State issues.
(iii) Promoting small and mini hydel projects
Small and mini hydel potential can provide a solution for the energy problems in remote
and hilly areas where extension of grid system is comparatively uneconomical and also
along the canal systems having sufficient drops. The small hydro potential could be
developed economically by simple design of turbines, generators and the civil works.
Small and mini hydel capacity aggregating to about 340 MW is in operation, and
Government is determined to provide thrust for developing the assessed small hydel
potential at a faster pace henceforth.
(iv) Strengthening the role of PSUs/SEBs for taking up new hydel projects:
In view of the poor response of the private sector so far in hydro development which may
persist for some more years, the involvement of public sector in hydel projects would not
only have to continue but will also have to be enlarged. There are categories of projects
such as multi-purpose, projects involving inter-State issues, projects for peaking power
and those involving rehabilitation and resettlement which may be taken up and
implemented more easily in public sector. Similarly, mega hydro projects in the North
and North Eastern region would also have to be executed by CPSUs in case the State or
the private sector is not in position to implement these projects.
(v) Increasing private investment:
Even though public sector organisations would play a greater role in the development of
new schemes, this alone would not be adequate to develop the vast remaining hydro
potential since it will require huge investments which are difficult to be supported from
the budget/plan assistance in view of competing demands from the various sectors. A
greater private investment through IPPs and joint ventures would be encouraged in the
coming years and required atmosphere, incentives and reliefs would be provided to
stimulate and maintain a trend in this direction.
Policy Instruments
To achieve the above stated objectives for faster development of hydro potential, the
Government proposes to take the following steps and measures: -
3.1 Funding
All the ongoing Central Sector hydroelectric projects namely Nathpa Jhakri (1500 MW),
Tehri Stage I (1000 MW), Ranganadi Stage I (405 MW), Dulhasti (390 MW),
Dhauliganga (280 MW), Doyang (75 MW) and Rangit (60 MW) would be provided with
full budgetary support till completion. Government of India will also provide budgetary
support for the new projects to be taken up by the CPSUs during the 9th Plan. The
actual utilisation of the funds on the ongoing Central Sector hydel projects has been
Rs.1616.87 crores in 1997-98 and the budget provision for 1998-99 has been increased
to Rs.2070 crores. Therefore the remaining three years of the 9th Plan would require
about Rs.5896 crores on the ongoing Central Sector projects (excluding NEC projects).
Having regard to the large capacity addition envisaged in the State Sector (5810 MW) it
is necessary to (a) provide a mechanism for funding hydro projects by earmarking funds
in the plan allocation of the State Governments by the Planning Commission; and (b)
organising supplementary funding of hydel projects where more than 50 per cent of the
expenditure has already been incurred.
The monitoring of all the ongoing projects will be intensified and a task force would be
constituted for this purpose. The progress of important projects in the State and Central
Sector would be reviewed at the level of Minister/Secretary(Power) and all measures will
be taken so that there is no slippage in the schedule for completion of the ongoing
projects.
3.4 Advance Action for Capacity Addition in the 10th Plan and beyond
Government will take immediate steps to tie up funding, execution agencies and convey
investment decision for schemes already accorded techno economic clearance of CEA.
As far as Central Sector is concerned, NHPC would take up Chamera Stage II (300
MW), Parbati Stage-II (800 MW), and Kol Dam (800 MW) in HP; Teesta Stage V (510
MW) in Sikkim, Loktak Downstream (90 MW) in Manipur and NEEPCO will take up
Tuivai (210 MW) in Mizoram, Lower Kopili (150 MW) in Assam, Kameng (600 MW) and
Ranganadi Stage II (160 MW) in Arunachal Pradesh (after the consent of the State Govt.
has been obtained). In addition THDC would take action to start activities on Tehri Stage
II (1000 MW) and Koteshwar (400 MW) in UP. Similarly NJPC would also take up
Rampur Project (535 MW) in HP. These projects would require budgetary support of
about Rs.2000 crores in the 9th Plan.
3.13 Govt. Support for Land Acquisition, Resettlement & Rehabilitation, Catchment Area
Development
The acquisition of requisite Government, forest and private land involves cumbersome
procedure and difficult negotiations with land owners to part with the land. Demands for
employment in lieu of the land cost, land for land at places of land owners choice etc.
has resulted in contractual problems for several projects. There is, therefore, a need
that project authorities are insulated from the problems arising out of land acquisition and
R&R. It will be the responsibility of the State Govt. to acquire the land
(Government/Private/Forest) for the project and also negotiate at its own terms with land
owners as per the policy adopted by respective State Governments. Similarly, all the
issues of resettlement and rehabilitation associated with projects have to be addressed
by the State Govt. The State Governments. may consider to form Authorities to address
the problems of land acquisition and R&R for all infrastructure projects. In case of mega
projects the project specific Authorities may be created not only for land acquisition and
RR but for comprehensive development of the area including catchment area. The
project developer may not be involved in execution and implementation of works by
these Authorities, but will be required to contribute for funding their plans. All such costs
incurred by the developer shall be considered as cost to the project and allowed to be
passed through tariff.