National Policy For Hydro Power Development

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

NATIONAL POLICY FOR HYDRO POWER DEVELOPMENT

Need For a Hydel Policy


Hydro power is a renewable economic, non polluting and environmentally benign source
of energy. Hydro power stations have inherent ability for instantaneous starting,
stopping, load variations etc. and help in improving reliability of power system. Hydro
stations are the best choice for meeting the peak demand. The generation cost is not
only inflation free but reduces with time. Hydroelectric projects have long useful life
extending over 50 years and help in conserving scarce fossil fuels. They also help in
opening of avenues for development of remote and backward areas.
Our country is endowed with enormous economically exploitable and viable hydro
potential assessed to be about 84,000 MW at 60% load factor (1,48,700 MW installed
capacity). In addition, 6781.81 MW in terms of installed capacity from small, mini and
micro hydel schemes have been assessed. Also, 56 sites for pumped storage schemes
with an aggregate installed capacity of 94,000 MW have been identified. However, only
15% of the hydroelectric potential has been harnessed so far and 7% is under various
stages of development. Thus, 78% of the potential remains without any plan for
exploitation.

Despite hydroelectric projects being recognised as the most economic and preferred
source of electricity, share of hydro power has been declining steadily since 1963. The
share of hydro power has been continuously declining during the last three decades.
The hydro share has declined from 44 per cent in 1970 to 25 per cent in 1998. The ideal
hydro thermal mix should be in the ratio of 40:60. Because of an imbalance in the hydel
thermal mix especially in the Eastern and Western regions, many thermal power stations
are required to back down during off peak hours. The capacity of the thermal plants
cannot be fully utilised resulting in a loss of about 4 to 5 per cent in the plant load factor.
Even if the share of hydro power is to be maintained at the existing level of 25 per cent,
the capacity addition during the 9th and 10th Plan would work out to 23,000 MW. If the
share were to be enhanced to 30 per cent, it would require a further addition of 10, 000
MW of hydro capacity.

The constraints which have affected hydro development are technical (difficult
investigation, inadequacies in tunnelling methods), financial (deficiencies in providing
long term financing), tariff related issues and managerial weaknesses (poor contract
management). The hydro projects are also affected by geological surprises (especially
in the Himalayan region where underground tunnelling is required), inaccessibility of the
area, problems due to delay in land acquisition, and resettlement of project affected
families, law & order problem in militant infested areas.

Objectives
The programmed capacity addition from hydel projects during the 9th Plan is 9815 MW,
of which Central Sector and State Sector will contribute 3455 MW and 5810 MW
respectively and the balance 550 MW will be contributed by the Private Sector.
Sanctioned and ongoing schemes under implementation will enable a capacity addition
of 6537 MW during the 10th Plan, of which 990 MW, 4498 MW and 1050 MW will be the
contribution of Central, State and Private Sectors respectively. In addition, 12 projects
(5615 MW) have been identified for advance action in the 9th Plan for benefits in the
10th Plan.
The Government of India has set the following objectives for accelerating the pace of
hydro power development:-
(i) Ensuring targeted capacity addition during 9th Plan :
The 9th Plan programme envisages capacity addition of 9815 MW from hydel projects in
the total capacity addition of 40245 MW. The Central Sector hydel projects would
contribute 3455 MW, State Sector would add 5810 MW and Private Sector 550 MW.
Keeping in view that the achievement in 8th Plan had been dismal, the Government is
determined to ensure that no slippage is allowed to occur and the targeted capacity
addition in the 9th Plan is achieved in full.
(ii) Exploitation of vast hydroelectric potential at a faster pace:
The Government would initiate advance action for taking up new hydro projects since the
ongoing projects will contribute a very small percentage of the desired capacity addition
envisioned for 10th Plan and beyond. Towards this end, Government would take up for
execution all the CEA cleared projects, and take steps to update and obtain clearances
for pending DPRs. Measures for vigorously starting survey and investigations for new
green field sites would also be implemented shortly. In addition, Government is keen to
restart and activate the hydro projects which are either languishing for want of funds or
are remaining dormant due to unresolved inter-State issues.
(iii) Promoting small and mini hydel projects
Small and mini hydel potential can provide a solution for the energy problems in remote
and hilly areas where extension of grid system is comparatively uneconomical and also
along the canal systems having sufficient drops. The small hydro potential could be
developed economically by simple design of turbines, generators and the civil works.
Small and mini hydel capacity aggregating to about 340 MW is in operation, and
Government is determined to provide thrust for developing the assessed small hydel
potential at a faster pace henceforth.
(iv) Strengthening the role of PSUs/SEBs for taking up new hydel projects:
In view of the poor response of the private sector so far in hydro development which may
persist for some more years, the involvement of public sector in hydel projects would not
only have to continue but will also have to be enlarged. There are categories of projects
such as multi-purpose, projects involving inter-State issues, projects for peaking power
and those involving rehabilitation and resettlement which may be taken up and
implemented more easily in public sector. Similarly, mega hydro projects in the North
and North Eastern region would also have to be executed by CPSUs in case the State or
the private sector is not in position to implement these projects.
(v) Increasing private investment:
Even though public sector organisations would play a greater role in the development of
new schemes, this alone would not be adequate to develop the vast remaining hydro
potential since it will require huge investments which are difficult to be supported from
the budget/plan assistance in view of competing demands from the various sectors. A
greater private investment through IPPs and joint ventures would be encouraged in the
coming years and required atmosphere, incentives and reliefs would be provided to
stimulate and maintain a trend in this direction.

Policy Instruments
To achieve the above stated objectives for faster development of hydro potential, the
Government proposes to take the following steps and measures: -

3.1 Funding
All the ongoing Central Sector hydroelectric projects namely Nathpa Jhakri (1500 MW),
Tehri Stage I (1000 MW), Ranganadi Stage I (405 MW), Dulhasti (390 MW),
Dhauliganga (280 MW), Doyang (75 MW) and Rangit (60 MW) would be provided with
full budgetary support till completion. Government of India will also provide budgetary
support for the new projects to be taken up by the CPSUs during the 9th Plan. The
actual utilisation of the funds on the ongoing Central Sector hydel projects has been
Rs.1616.87 crores in 1997-98 and the budget provision for 1998-99 has been increased
to Rs.2070 crores. Therefore the remaining three years of the 9th Plan would require
about Rs.5896 crores on the ongoing Central Sector projects (excluding NEC projects).
Having regard to the large capacity addition envisaged in the State Sector (5810 MW) it
is necessary to (a) provide a mechanism for funding hydro projects by earmarking funds
in the plan allocation of the State Governments by the Planning Commission; and (b)
organising supplementary funding of hydel projects where more than 50 per cent of the
expenditure has already been incurred.

The monitoring of all the ongoing projects will be intensified and a task force would be
constituted for this purpose. The progress of important projects in the State and Central
Sector would be reviewed at the level of Minister/Secretary(Power) and all measures will
be taken so that there is no slippage in the schedule for completion of the ongoing
projects.

3.2 Power Development Fund


The survey and investigation of hydro projects have been discontinued since long in the
States due to paucity of funds. As a result, there are not enough projects right now that
could be taken up in the next 2 to 3 years and get completed in the 10th Plan or early
11th Plan. It is necessary to carry out survey and investigations continuously and
prepare a shelf of projects for execution over a decade and more.
In case fully investigated projects with Detailed Project Reports are offered to private
developers, their response could be more favourable. If pre-construction activities and
enabling works could be completed and these sites offered to IPPs the chances of IPPs
opting to invest in these projects would further improve. Further this would reduce the
gestation period which would make investment in hydro projects more attractive.
The above approach is possible and successful only if a dedicated fund is available for
this purpose.
It is proposed to levy a Power Development Cess at 10 paise per kwh of electricity
consumed in the country. The levy of cess was recommended by the Sub Committee of
the NDC Committee on Power which gave its report in January, 1994. The cess would
be levied on the electricity billed by SEBs/Electricity Departments/Bulk
licensees/Distribution licensees. The State/UT Governments would be responsible for
the collection of the cess. The amount would thereafter be credited to a “National Power
Development Fund". It is expected that about Rs.3000 crores per annum can be
realised by levying a cess of 10 paise per kwh.
It would be necessary to establish a legal and organisational frame work for levy of a
cess. Electricity being a Concurrent Subject, the Central Government is empowered to
legislate on all aspects of electricity including the levy of cess, the proceeds of which is
to be utilised for power development. In order to levy a Power Development Cess, it
would be necessary for Parliament to enact a legislation on the subject. The cess will be
imposed on the consumption of electricity throughout the country. The State Electricity
Boards will be the responsible agencies for the collection of cess. The proceeds of the
cess will be shared with the State/UT Governments and the Central Government. Two-
thirds of the amount realised from the State/UT Government will be allocated to the
respective government to be utilised for power development. This amount would be
released from the National Power Development Fund for financing schemes/projects
recommended by the State Government. The remaining one-third will be utilised by the
Central Government for promoting hydel projects in the Central Sector and for
investment in transmission lines for evacuation of power from mega hydel projects which
will benefit more than one State.

3.3 Basin-wise Development of Hydro Potential


The assessment of hydro potential in 845 identified conventional hydro projects and 56
pumped storage projects is on the basis of desk studies using toposheets and discharge
data. Further, detailed studies to firm up the parameters of the projects as identified by
CEA would be taken up on the basis of development of hydro potential in a basin as a
whole for maximising benefits and prioritising execution of projects. These studies will
be done in close co-ordination with CWC and Planning Commission and in harmony with
development for other uses of water like irrigation, drinking water etc. While CEA would
carry out these studies, CPSUs/other Central Government Organisations and State
authorities would do the investigations and prepare the detailed project reports, by
adopting an integrated approach towards planning and development of the various
projects, evacuation arrangement and environmental impact assessment. This would
enable an optimal harnessing of hydro potential in each river basin.

3.4 Advance Action for Capacity Addition in the 10th Plan and beyond
Government will take immediate steps to tie up funding, execution agencies and convey
investment decision for schemes already accorded techno economic clearance of CEA.
As far as Central Sector is concerned, NHPC would take up Chamera Stage II (300
MW), Parbati Stage-II (800 MW), and Kol Dam (800 MW) in HP; Teesta Stage V (510
MW) in Sikkim, Loktak Downstream (90 MW) in Manipur and NEEPCO will take up
Tuivai (210 MW) in Mizoram, Lower Kopili (150 MW) in Assam, Kameng (600 MW) and
Ranganadi Stage II (160 MW) in Arunachal Pradesh (after the consent of the State Govt.
has been obtained). In addition THDC would take action to start activities on Tehri Stage
II (1000 MW) and Koteshwar (400 MW) in UP. Similarly NJPC would also take up
Rampur Project (535 MW) in HP. These projects would require budgetary support of
about Rs.2000 crores in the 9th Plan.

3.5 Survey & Investigations


As a long term strategy efforts will be made to ensure that DPRs which are under various
stages of processing for accord of TEC by CEA are finalised and cleared so that a start
could be made on these projects in the next one or two years. Survey and investigation
of the potential hydro sites on an advanced scientific basis would be essential
requirement for the future. The progress on this front has been dismal given the funds
constraint and outdated technology. The funding agencies like World Bank and ADB
have shown their interest towards funding the survey and investigation activities for
hydroelectric projects. Concerted efforts would be made towards availing the funds
quickly. This would not only help in preparation of the bankable DPRs for large
hydroelectric projects but would also bring in advanced technology by involving reputed
international consultants. The Central organisations like CWC, Brahmaputra Board,
NEEPCO and NHPC, besides SEBs would be provided with funding support from the
proposed Power Development Fund for the purpose of carrying out survey and
investigations and preparation of bankable DPRs.
Since the private sector has so far been hesitant and cautious to invest in hydro projects,
it is proposed that new projects will initially be taken up by CPSUs/SEBs for
investigations, updatation of DPRs, obtaining the necessary clearances and pre-
construction activities. After these stages, the projects could be offered to the private
sector for execution either on ‘stand alone’ basis or for joint venture participation with the
CPSU/SEB. The expenditure incurred by CPSUs/SEBs on these activities would be
adjusted in the project cost to be recovered from the executing agency to be decided at a
later stage. The Government expects that more private investment would be possible
with this approach. In case for a particular project no such private investment is
forthcoming, it will be executed entirely by the concerned CPSU/SEB which initiated its
development.

3.6 Inter-State Projects


A substantial hydel power potential has remained locked up and many mega hydel
projects could not be taken up for implementation, even though these projects are well
recognised as attractive and viable, because of unresolved Inter-State issues. Govt. of
India recognises the need for evolving an approach to ensure that the available hydro-
electric potential is fully utilised without prejudice to the rights of the riparian States as
determined by the Awards of the Tribunals/Agreements arrived at among the party
States for a given river basin with regard to water sharing. The selection and design of
project would be based on integrated basin wise studies, so as to arrive at an optimal
decision and care will be taken that such projects do not in any way prejudice the claims
of basin states or affect benefits from the existing projects. A consensus would be
evolved amongst the basin states regarding the location of such project, basic
parameters involved and mechanism through which each project would be constructed
and operated. As far as possible, there would be preference to take up simple run-of-
the-river schemes that do not involve any major storage or consumptive uses.

3.7 Renovation, Modernisation & Uprating


Renovation, Modernisation & Uprating of old hydro power plants is being accorded
priority as it is a faster and cheaper way of capacity addition than installing new capacity.
As per recommendations of National Committee set up in 1987 and based on the
subsequent reviews, 55 hydro schemes with an aggregate capacity of 9653 MW were
identified for RM&U. Out of these, 20 hydro schemes have been completed providing a
benefit of 971.5 MW and work on 27 schemes is in progress. In order to provide a
greater thrust for RM&U, Government would set up a Standing Committee, to identify the
new schemes and for tying up technology, funding and executing agencies.

3.8 Promoting Small and Mini Hydel Projects


The Ministry of Non-Conventional Energy Sources (MNES) deals with all matters related
to Small Hydel Projects (up to 3 MW capacity). These projects are being provided with
the following incentives.
(i) Incentives for detailed survey & investigation and preparation of DPR.
(ii) Incentives during the execution of the project in the form of capital/ interest subsidy.
(iii) Special incentives for execution of small hydro projects in the North Eastern Region
by the Government departments/SEBs/State agencies.
(iv) Financial support for renovation, modernisation and uprating of old small hydro
power stations.
The Small Hydel Projects are site specific and depending on the hydrology, typically the
plant load factor varies from 40 to 60%. The Small Hydel Projects upto 25 MW will also
be transferred to MNES in order to provide greater thrust for its development.
Government of India proposes to provide soft loans to these projects (up to 25 MW)
through IREDA/PFC/REC and other financial institutions and Ministry of Non-
conventional Energy Sources would announce a suitable package of financial incentives
for the accelerated development of Small Hydel Projects upto 25 MW station capacity.
The State Government and Central and State Hydro Corporations like NHPC/NEEPCO
etc. would be encouraged to take up a cluster of small/mini hydel schemes on Build,
Operate and Transfer basis, and other suitable arrangements.

3.9 Simplified Procedures for Transfer of Clearances


As stated in the foregoing, the CPSUs and the private sector would need to play a
greater role in hydro development. The immediate requirement would be to transfer the
clearances already accorded to non-starting hydro projects in the State Sector in favour
of CPSU/IPP/Joint Venture of IPP and CPSU. Government would evolve a simple
procedure so that the transfer of CEA’s techno economic clearance would be facile as
only updation of project estimate would be examined by CEA. In the case of
Environment and Forest clearances these could be transferred to CPSU/IPP etc. within a
prescribed time limit on acceptance of conditionalities stipulated in the MOEF clearances
accorded for execution in the State Sector by the above executing agencies. Another
inhibiting factor discouraging IPPs is the need for notification of the scheme as per
Section 29 of ES Act in newspaper and Gazette afresh even if this was done earlier for
execution by SEBs. Government intends to do away with this requirement. The
simplified procedure as proposed would be an encouraging factor for IPP to evince
greater interest in hydro development. Government would initiate action right away
towards this end.

3.10 Rationalisation of Hydro Tariff


The tariff formulation and norms for hydro projects as per existing Government
notification are viewed by CPSUs and IPPs as unfavourable compared to those for
thermal projects and the IPPs tend to prefer thermal projects for investment. There is a
need to reformulate the principles on the basis of which tariff is determined for hydel
generation. The objective is to fix a rate which will be reasonable to the consumer, to
ensure adequate internal resources to repay the loan and also to provide a reasonable
rate of return on investment. Recognising the difficulties in execution of hydro projects,
the Government has decided to rationalise the existing hydro tariff norms, improve the
incentives for better operation and evolve a solution to the contentious issue of
computing the completion cost in the face of geological uncertainties and surprises and
natural incidents of rock slide etc.
In January 1995, the Government issued a notification providing for a two part tariff for
hydel generation stations. The first part of the tariff, denominated as capacity charges
covers (a) interest on loan capital; and (b) depreciation reckoned at an annual amount
not exceeding 1/12 of the loan amount and limited to the actual loan liability of the year
as per approved financial package. The second part of the tariff denominated as energy
charges covers (a) return on equity calculated at 16% (b) O&M charges; (c) tax on
income; and (d) any other variable charge.
Hydro projects provide valuable peak power and have inherent capability for
instantaneous starting and stoppage based on variation of load. The peaking power
stations generally operate at a very low load level. Recognising the value of peak power
to the system and resultant improvement in operation of thermal stations, it is proposed
to allow a premium on the sale rate for hydro generation during peak period. The
formulation of peak tariff and the premium to be allowed would be decided by the Central
Electricity Regulatory Commission and the State Electricity Regulatory Commissions.
Under the present notification, the rate for incentive for secondary energy has to be fixed
at a rate mutually agreed between the State Electricity Board and the generating
company. However, the maximum payment on this account is restricted to an amount
not exceeding 10% return on equity. In order to provide an additional incentive for
attracting investment in hydel projects, it is proposed to allow the sale rate for secondary
energy at the same rate which is applicable for a primary energy.
Recognising the problems in operation of hydro power stations in the initial years
especially in project with silt laden water, the normative availability factor is proposed to
be reduced from 90% to 85%.

3.11 Estimates on Completion Cost (Geological Risks)


During the implementation of hydro power projects specially underground power
stations, there is a likelihood of coming across geological surprises which are not
anticipated at the time of preparation of Detailed Project Report. This results in increase
in capital cost. The developer would need to be compensated for this kind of
eventualities.
In the existing tariff notification for hydro projects, there is no provision for increase in
project cost arising due to geological risks. A realistic estimate of completion cost has to
take into account the geological and hydrological risks, cost escalation and natural
occurrences of land slides, rock falls etc. In such cases, the developer will be allowed to
submit his proposal for the enhanced cost to the Government. Expert Committee would
be constituted at the State and Central level who would evaluate and recommend the
cost increases for acceptance by the Government. The expert committee at the State
Government level would recommend the cost increase proposal upto certain percentage
and beyond that the cost increase would be recommended by the expert committee at
the Central Government level.

3.12 Promoting Hydel Projects with Joint Ventures


With a view to bring in additional private investment in the hydel sector there would be a
greater emphasis to take up schemes through the joint ventures between the
PSUs/SEBs and the domestic and foreign private enterprises. The joint venture company
will be an independent legal entity to be registered under the Companies Act and would
act as an independent developer. The joint venture agreement between the two partners
will bring clearly the extent of participation by each partner and sharing of risks relating to
implementation and operation of the project. It will also provide for arrangement in such
cases where the joint venture partner would not be associated with the operation and
maintenance of the project. While the selection of a joint venture partner would be in
accordance with the policy of the Government, there would be an option for the PSU to
either select the joint venture partner together with their financial and equipment package
or to select a joint venture partner wherein the EPC contract is decided by both the
partners after they have formed the joint venture company. The associated transmission
line connected with the scheme will be constructed by the Powergrid Corporation of
India. The power from joint venture hydel projects will be purchased by the Power
Trading Corporation (PTC) proposed to be formed with equity participation from
Government/CPSUs/Financial Institutions. The security for payment of power
purchased from the joint venture projects would be through a LC to be provided by the
SEBS and recourse to the State’s share of Central Plan Allocation and other devolution.
This security package would enable to raise finances for these projects. As far as the
new schemes to be developed under the joint venture route are concerned, the power
sharing formula as applicable to the Central Sector Projects shall not apply and joint
venture company would be totally guided by the commercial interest. The State
Government (home State/States) will be compensated by way of 12% free power as per
the present policy applicable for Central Sector hydel projects.

3.13 Selection of Developer and Techno Economic Clearance of CEA


As per Government notification of September, 1996, all the schemes estimated to
involve a capital expenditure above Rs.100 crores are to be submitted to CEA for techno
economic clearance and in respect of schemes prepared by a generating company and
selected through a process of competitive bidding by the competent Government or
Governments, the exemption from CEA’s techno-economic clearance is applicable if the
capital cost is Rs.1000 crores or less.
Considering the capital intensive nature of hydel projects especially those of medium
size being executed in the State Sector, it is proposed to increase the limit for exemption
of CEA clearance from the present Rs.100 crores to Rs.250 crores if the projects are
taken in the MOU route. In case of projects through competitive bidding the existing
limit of Rs.1000 crores for CEA techno economic clearance will continue. However,
irrespective of the capital cost or capacity, all hydel projects having inter-State aspect will
require a mandatory clearance from the CEA. Keeping in view the need for transparency
and cost assessment by an accepted mechanism as well as the uncertainties that are
inevitable in the development and execution of hydel projects, t he Government
proposes to allow the selection of developer through MOU route for the hydel projects
upto 100 MW instead of the existing limit of Rs.100 crores. However, these projects
would require CEA techno economic clearance if their capital cost exceeds Rs.250
crores. This would enable more developers to evince interest in medium size hydro
projects due to ease of execution and resource raising and due to exemption in obtaining
clearances.

3.13 Govt. Support for Land Acquisition, Resettlement & Rehabilitation, Catchment Area
Development
The acquisition of requisite Government, forest and private land involves cumbersome
procedure and difficult negotiations with land owners to part with the land. Demands for
employment in lieu of the land cost, land for land at places of land owners choice etc.
has resulted in contractual problems for several projects. There is, therefore, a need
that project authorities are insulated from the problems arising out of land acquisition and
R&R. It will be the responsibility of the State Govt. to acquire the land
(Government/Private/Forest) for the project and also negotiate at its own terms with land
owners as per the policy adopted by respective State Governments. Similarly, all the
issues of resettlement and rehabilitation associated with projects have to be addressed
by the State Govt. The State Governments. may consider to form Authorities to address
the problems of land acquisition and R&R for all infrastructure projects. In case of mega
projects the project specific Authorities may be created not only for land acquisition and
RR but for comprehensive development of the area including catchment area. The
project developer may not be involved in execution and implementation of works by
these Authorities, but will be required to contribute for funding their plans. All such costs
incurred by the developer shall be considered as cost to the project and allowed to be
passed through tariff.

You might also like