Guide - Schedule For Testing Materials
Guide - Schedule For Testing Materials
Guide - Schedule For Testing Materials
MAY 2016
Using the Guide Schedule
Research of sampling and testing rates listed for project tests in the following Guide Schedule show that the Departments and the Contractors risk of
either rejecting good material or accepting bad material range from 20% to 40%.
To reduce this risk, we recommend that the sampling rate be increased during initial production. A four-fold increase in testing frequency will generally
reduce risk to approximately 5%. The intent of increasing testing at the start of production is to insure that the Contractors processes are in control and to
establish acceptability requirements early.
There is a need to increase the frequency of testing for high-variability materials and when testing results do not meet specifications. The Engineer may
require the Contractor to reimburse the Department for costs resulting from failing test results, in accordance with the specifications.
Materials incorporated in TxDOT projects are subjected to various quality assurance procedures such as testing (as outlined in this document), certification,
quality monitoring, approved lists, etc. The Engineer and testing staff should familiarize themselves with materials to be used before work begins by
reviewing the specifications and this document. Discuss material testing requirements with the Contractor.
Other testing required by the specifications, but not shown in the Guide Schedule, should be performed at a frequency necessary to provide adequate
confidence that materials meet specifications.
NOTE: For projects subject to FHWA construction oversight activities, use the Letter of Certification of Materials Used" to document reasons for material
acceptance when a test fails. For all other projects, document the justification and explanation for acceptance of materials that fail project tests in the
project file.
Assuring the quality of the product and proper incorporation of materials into the project begins with proper sampling practices. Sampling, testing, and
construction inspection must be performed collaboratively to assure the specific attributes of the finished product reflect quality workmanship. Sampling
guidance for hot-mixed asphalt is contained in Tex-225-F, Random Selection of Bituminous Mixture Samples, and the respective specification for that
material. All remaining materials are covered by method and materials specifications, to which the following applies.
For acceptance testing, especially that which directly determines payment for the Contractor, sampling personnel should provide randomness in sampling
by avoiding patterned sampling routines. Examples of such sampling practices are as follows:
Soils/flexible base: Vary sampling between stockpiling operations, completed stockpile, windrow, and project site. Vary the time of day sampling is
performed.
Aggregates: Sample aggregates nearest the point of incorporation into the work. Vary sampling between stockpiling operations, completed
stockpile, belt sampling, and if deemed necessary, railroad cars/trucks. Vary the time of day sampling is performed.
Concrete (structural and miscellaneous: Always sample as near as practicable to the point of placement. For strength testing, vary the time of day
or the number of truck from which the concrete is sampled. Tests for slump, air, and temperature should be done often to ensure the consistent
control of the concrete production (not applicable to miscellaneous concrete).
This Guide Schedule is applicable to all contracts associated with the 2014 Standard Specifications.
1
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
RETAINING WALL Not required for rock backfill. For walls greater than
(SELECT BACKFILL) 500 ft. in length, perform one test per lift for every
(continued) 500 ft. in length. (F)
In-place Density As designated by the 1 per backfill lift, Correct the moisture contents measured by nuclear
Tex-115-E
(A) Engineer. per wall density gauge in Tex-115-E with the moisture
contents determined in accordance with Tex-103-E
for each different material or notable change in
material and adjust the density accordingly.
During stockpiling
operations, from
Liquid Limit
Tex-104-E completed stockpile, or Each 5,000 CY Sample in accordance with Tex-400-A.
(A) windrow
(B)
During stockpiling
operations, from
Plasticity Index
Tex-106-E completed stockpile, or Each 5,000 CY
(A) windrow
(B)
During stockpiling
operations, from
Gradation
Tex-110-E completed stockpile, or Each 5,000 CY Sample in accordance with Tex-400-A.
(A) windrow
UNTREATED BASE (B)
COURSES
From completed Not required for ordinary compaction.
Moisture/Density Tex-113-E stockpile at the source Each 20,000 CY
Sample in accordance with Tex-400-A.
(E)
From completed
Wet Ball Mill As required by the plans.
Tex-116-E stockpile at the source Each 20,000 CY
(A) Sample in accordance with Tex-400-A.
(E)
As required by the plans. When base material is
from a source where the District has a record of
satisfactory triaxial results, the frequency of testing
From completed may be reduced to one per 30,000 CY. If any one
Strength
Tex-117-E stockpile at the source Each 20,000 CY test falls below the minimum value required, the
(A)
(E) frequency of testing will return to the original
frequency of 20,000 CY.
Sample in accordance with Tex-400-A.
Enter customize text here for your needs or delete if not needed.
3
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
Enter customize text here for your needs or delete if not needed.
4
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
Enter customize text here for your needs or delete if not needed.
5
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
Thickness As designated by the Not required where survey grade control documents
Tex-140-E Each 3,000 CY
(A) Engineer are used for compliance
Required only for contractor furnished recycled
material, including crushed concrete. Not required
Sulfate Content Tex-145-E During stockpiling Each 5,000 CY for RAP.
operations, from Sample in accordance with Tex-400-A.
completed stockpile, or
RECLAIMED ASPHALT PAVEMENT windrow Required only for contractor furnished recycled
(RAP), CRUSHED CONCRETE, and Deleterious Material Tex-413-A Each 5,000 CY material, including crushed concrete.
RECYCLED MATERIALS Sample in accordance with Tex-400-A.
During stockpiling
operations, from Required only for contractor furnished RAP.
Decantation Tex-406-A Each 5,000 CY
completed stockpile, or Sample in accordance with Tex-400-A.
windrow
TABLE I FOOTNOTES
When this project acceptance test fails but the product is accepted, document the reasons for acceptance on the Letter of Certification of Materials Used or in the SiteManager
A
Remarks field.
Engineer will select any of these locations or any combinations thereof with the provision that the initial sample will be obtained from the completed stockpile at the source and at least
B
one out of ten consecutive samples will be taken at the project site (from the windrow for treated and untreated bases and embankments when possible).
C Attach the corresponding QM test report for SiteManager projects to satisfy project sampling and testing requirements.
Enter customize text here for your needs or delete if not needed.
6
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
For acceptance testing, especially that which directly determines payment for the Contractor, sampling personnel should provide randomness in sampling by avoiding patterned
sampling routines. Examples of such sampling practices are as follows:
D Soils/Flexible Base: For gradation, liquid limit, and plastic limit, vary sampling between stockpiling operations, completed stockpile, windrow, and project site. Vary the time of
day sampling is performed.
Aggregates: Sample aggregates nearest the point of incorporation into the work. Vary sampling between stockpiling operations, completed stockpile, belt sampling, and if
deemed necessary, railroad cars/trucks. Vary the time of day sampling is performed.
E The Engineer will sample from the completed stockpile at the source and test prior to placement.
F Each test performed that is based on a quantity of material is considered or fraction thereof for calculating number of tests.
Enter customize text here for your needs or delete if not needed.
7
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
Enter customize text here for your needs or delete if not needed.
8
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
During stockpiling
RECYCLED ASPHALT Tex-217-F, operations, from
Decantation Each 10,000 CY Sample in accordance with Tex-400-A.
SHINGLES (RAS) Part III completed stockpile, or
prior to mixing
As designated by the 1 per project, per This test may be waived, when shown on the plans.
Moisture Susceptibility Tex-530-C
Engineer design Sample in accordance with Tex-222-F.
Roadway cores, as Not required for ordinary compaction or when air void
Each 2,500 CY
In-Place Air Voids designated by the requirements are waived.
ROADWAY Tex-207-F (3,000 tons) or
(A) Engineer
days production Sample in accordance with Tex-222-F.
(C, D)
TABLE IA FOOTNOTES
When this project acceptance test fails but the product is accepted, document the reasons for acceptance on the Letter of Certification of Materials Used or in the SiteManager
A
Remarks field.
Engineer will select any of these locations or any combinations thereof with the provision that at least one out of ten consecutive samples will be taken at the project site (from the
B
windrow for treated and untreated bases and embankments when possible).
For acceptance testing, especially that which directly determines payment for the Contractor, sampling personnel should provide randomness in sampling by avoiding patterned
sampling routines. Examples of such sampling practices are as follows:
C
Soils/flexible base: Vary sampling between stockpiling operations, completed stockpile, windrow, and project site. Vary the time of day sampling is performed.
Aggregates: Sample aggregates nearest the point of incorporation into the work. Vary sampling between stockpiling operations, completed stockpile, belt sampling, and if
deemed necessary, railroad cars/trucks. Vary the time of day sampling is performed.
D Each test performed that is based on a quantity of material is considered or fraction thereof for calculating number of tests.
Enter customize text here for your needs or delete if not needed.
9
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
TABLE II FOOTNOTES
When this project acceptance test fails but the product is accepted, document the reasons for acceptance on the Letter of Certification of Materials Used or in the SiteManager
A
Remarks field.
B Attach the corresponding QM test report for SiteManager projects to satisfy project sampling and testing requirements.
For acceptance testing, especially that which directly determines payment for the Contractor, sampling personnel should provide randomness in sampling by avoiding patterned
C sampling routines. Examples of such sampling practices are as follows:
Aggregates: Sample aggregates nearest the point of incorporation into the work. Vary sampling between stockpiling operations, completed stockpile, belt sampling, and if
deemed necessary, railroad cars/trucks. Vary the time of day sampling is performed.
D Each test performed that is based on a quantity of material is considered or fraction thereof for calculating number of tests.
Enter customize text here for your needs or delete if not needed.
11
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
TABLE III HYDRAULIC CEMENT CONCRETE STRUCTURAL (Classes: C, F, H, S, CO, K, LMC, or SS)
PROJECT TESTS
LOCATION OR TIME OF FREQUENCY OF
MATERIAL OR PRODUCT TEST FOR TEST NUMBER REMARKS
SAMPLING (D) SAMPLING (E)
Each 20,000 CY of
Decantation
Tex-406-A concrete (each Sample in accordance with Tex-400-A.
(B)
source)
Each 1,000 CY of Sample in accordance with Tex-400-A.
Sieve Analysis
Tex-401-A concrete (each
(A) (B) Test combined aggregate when used.
source)
1 per project or as
Deleterious Materials
Tex-413-A necessary for Sample in accordance with Tex-400-A.
COARSE (B) From stockpile at control
AGGREGATE concrete plant
Verify the value of the source, as listed on the current
Material Producer list for CRSQC, meets the project
Los Angeles Abrasion
Tex-410-A Two, each source specifications. If not, sample and submit to CST/M&P
(A) (B) for testing prior to use in accordance with Tex-499-A.
Sample in accordance with Tex-400-A. (C)
5-cycle Magnesium
Sulfate Soundness Verify the value of the source, as listed on the current
Tex-411-A Two, each source
CRSQC, meets the project specifications. (C)
(A) (B)
1 per project or as Sample in accordance with Tex-400-A.
Sand Equivalent
MINERAL Tex-203-F necessary for
(B) Test combined aggregate when used.
AGGREGATE control
Organic Impurities 1 per project, per
Tex-408-A Sample in accordance with Tex-400-A.
(B) source
Each 1,000 CY of
Sieve Analysis
Tex-401-A concrete (each Sample in accordance with Tex-400-A.
(A) (B)
source)
Sample in accordance with Tex-400-A.
1 per project or as
Fineness Modulus Test combined aggregate when used. Test to confirm
FINE Tex-402-A From stockpile at necessary for
AGGREGATE (B) concrete plant material variability when strength values are in
control
question.
1 per project or as Sample in accordance with Tex-400-A.
Deleterious Material
Tex-413-A necessary for Test to confirm material variability when strength
(B)
control values are in question.
Only for concrete subject to direct traffic. Verify the
value of the source, as listed on the current CRSQC,
Acid Insoluble Residue meets the project specifications. If not, sample and
Tex-612-J Two, each source submit to CST/M&P for testing prior to use in
(A) (B)
accordance with Tex-499-A.
Sample in accordance with Tex-400-A. (C)
Compliance with 1 per project, per
Railroad car, truck, bags class of concrete
SILICA FUME DMS-4630 Sample in accordance with Tex-320-D.
or silos (For each type and
(A) brand)
Enter customize text here for your needs or delete if not needed.
12
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
TABLE III HYDRAULIC CEMENT CONCRETE STRUCTURAL (Classes: C, F, H, S, CO, K, LMC, or SS)
PROJECT TESTS
LOCATION OR TIME OF FREQUENCY OF
MATERIAL OR PRODUCT TEST FOR TEST NUMBER REMARKS
SAMPLING (D) SAMPLING (E)
Compliance with 1 per project, per
Railroad car, truck or class of concrete
METAKAOLIN DMS-4635
silos (For each type and
(A) brand)
Verify if cement, fly ash, slag cement, and chemical
admixture sources are listed on the Material Producer
Lists. If not, sample and submit to CST/M&P for
Compliance with testing. Water testing is contracted by the concrete
At source (if not Min. 1 design per
MIX DESIGN Standard Specification supplier (commercial lab report to be reviewed by
approved) class, per source
Item 421.4.A TxDOT).
Sample in accordance with Tex-300-D for cement and
in accordance with Tex-733-I for fly ash.
Sample in accordance with Tex-500-C.
Compliance with Verify the source is listed on the Material Producer List
JOINT MATERIAL
DMS-6300 for Joint Sealers. If not, sample and test prior to use in
accordance with DMS-6310. (C)
Only products listed on the Material Producer List for
Sampled at jobsite; Concrete Curing Compounds will be allowed. When
Compliance with When requested by sample is requested by CST, sample in accordance
CURING COMPOUND tested by CST/M&P. See
DMS-4650 CST with Tex-718-I. Ensure container has been agitated
remarks.
and mixed prior to sampling. (C)
Compliance with Only products listed on the Material Producer list for
EVAPORATION RETARDANTS Evaporation Retardants will be allowed. (C)
DMS-4650
Compliance with the Only materials from CST/M&P approved sources listed
REINFORCING STEEL Std. Specifications & As Specified on the Material Producer Lists for Reinforcing Steel
Spec. Provisions Mills and Seven Wire Steel Strand will be allowed. (C)
3 couplers per lot
Only materials from CST/M&P approved sources listed
Compliance with Sampled at jobsite; (500 couplers) for
MECHANICAL COUPLERS Tex-743-I on the Material Producer List for Mechanical Couplers
DMS-4510 Tested by CST/M&P each type, model,
will be allowed. (C)
bar size and grade
Compliance with
Min. of 1 test per
LATEX DMS-4640 for concrete Sampled at jobsite. Sample in accordance with Tex-321-E.
project
chemical admixtures
Verify the source is listed on the Material Producer List
Compliance with Sampled at jobsite if not for Epoxies and Adhesives. If not, sample and test prior
1 per batch or
EPOXY DMS-6100, unless pre-approved by to use in accordance with DMS-6100.
shipment
otherwise specified CST/M&P.
Sample in accordance with Tex-734-I. (C)
Enter customize text here for your needs or delete if not needed.
13
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
TABLE III HYDRAULIC CEMENT CONCRETE STRUCTURAL (Classes: C, F, H, S, CO, K, LMC, or SS)
PROJECT TESTS
LOCATION OR TIME OF FREQUENCY OF
MATERIAL OR PRODUCT TEST FOR TEST NUMBER REMARKS
SAMPLING (D) SAMPLING (E)
4 cylinders for each
60 CY per class, Sampling must be in accordance with Tex-407-A.
per day Test two cylinders at 7 days, and if the average value is
(For bridge railing below the design strength as defined in Item 421
Compressive Strength and traffic railing, Table 8, test the remaining 2 cylinders at 28 days. If
CONCRETE Tex-418-A
(A) testing may be the average value of the 2 cylinders tested at 7 days
reduced to 4 meets the minimum design strength listed in Item 421
cylinders per 180 Table 8, the 2 remaining cylinders are not required to
CY per class be tested.
regardless of days)
At point of concrete Sample in accordance with Tex-407-A.
placement
Slump Tex-415-A Perform slump and temperature tests on the same
load from which strength test specimens are made.
Perform entrained air test only when entrained air
1 test per 4 concrete is specified in the plans.
Entrained Air Tex-416-A or strength
specimens Check temperature of every load for bridge slabs and
(A) Tex-414-A mass concrete placements.
CONCRETE
Temperature of Contractors required testing will be in accordance with
Concrete Tex-422-A specification requirements for the appropriate
(A) specification Item #.
During dry run and during
Slab Thickness and Tex-423-A, concrete placement
1 per span Min 6Max 18 locations per span
Depth of Reinforcement Part II (Bridge decks and direct
traffic culverts)
Enter customize text here for your needs or delete if not needed.
14
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
TABLE IV FOOTNOTES
When this project acceptance test fails but the product is accepted, document the reasons for acceptance on the Letter of Certification of Materials Used or in the SiteManager
A
Remarks field.
For acceptance testing, especially that which directly determines payment for the Contractor, sampling personnel should provide randomness in sampling by avoiding patterned
B sampling routines. Examples of such sampling practices are as follows:
Concrete (miscellaneous): Always sample as near as practicable to the point of placement. For strength testing, vary the time of day or the number of truck from which the
concrete is sampled.
C Each test performed that is based on a quantity of material is considered or fraction thereof for calculating number of tests.
Enter customize text here for your needs or delete if not needed.
15
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
Enter customize text here for your needs or delete if not needed.
16
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
EVAPORATION Compliance with Only products listed on the Material Producer List for
RETARDANTS DMS-4650 Evaporation Retardants will be allowed. (C)
Compliance with
Only materials from CST/M&P approved sources listed on
the Std.
REINFORCING STEEL As Specified the Material Producer List for Reinforcing Steel Mills and
Specifications &
Seven Wire Steel Strand will be accepted. (C)
Spec. Provisions
Sampled at jobsite if Only materials from CST/M&P approved sources listed on
not sampled at source the Material Producer List for Multiple Piece Tie-bars for
Compliance with Refer to Tex-711-I for
MULTIPLE PIECE TIE BARS Tex-712-I by CST/M&P; tested by Concrete Pavements will be allowed. Sample in
DMS-4515 sampling rates
CST/M&P. See accordance with Tex-734-I.
remarks.
Sampled at jobsite if Verify the source is listed on the Material Producer List for
Compliance with not pre-approved by Epoxies and Adhesives. If not, sample and test prior to use
EPOXY 1 batch per shipment in accordance with DMS-6100. Sample in accordance with
DMS-6100 CST/M&P. See
remarks. Tex-734-I. (C)
Enter customize text here for your needs or delete if not needed.
17
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
Enter customize text here for your needs or delete if not needed.
18
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
TABLE V FOOTNOTES
When this project acceptance test fails but the product is accepted, document the reasons for acceptance on the Letter of Certification of Materials Used or in the SiteManager
A
Remarks field.
B When a project test does not meet the specified strength requirements and a reduced pay factor is assigned, document the analysis on the Letter of Certification of Materials Used.
C Attach the corresponding QM test report for SiteManager projects to satisfy project sampling and testing requirements.
D Each test performed that is based on a quantity of material is considered or fraction thereof for calculating number of tests.
Enter customize text here for your needs or delete if not needed.
19
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
TABLE VI ASPHALT CONCRETE PAVEMENT (Items 341, 342, 344, 346, 347 and 348)
(All testing as noted in Table VI may be waived for exempt production as defined by specification.)
PROJECT TESTS
LOCATION FREQUENCY OF
MATERIAL OR PRODUCT TEST FOR TEST NUMBER REMARKS
(Per Design) SAMPLING (E)
L. A. Abrasion
Tex-410-A
(A)
1 per project, per Verify the published value of the source, as listed on the current
Magnesium Sulfate source Material Producer list for BRSQC, meets the project
Soundness Tex-411-A specifications. If not, sample in accordance with Tex-221-F and
(A) Stockpile submit to CST/M&P for testing prior to use in accordance with
COARSE AGGREGATE Surface Aggregate Tex-499-A. (C)
(B) 1 per project, per
Classification Tex-499-A
source
(A)
Not required when the Rated Source Soundness Magnesium
1 per project, per loss is 15 or less as listed on the current published BRSQC. If
Micro Deval Tex-461-A
aggregate source testing is required, sample in accordance with Tex-221-F.
Stockpiles, hot Does not apply to Item 342.
1 per project, per
COMBINED AGGREGATE Sand Equivalent Tex-203-F bins or feeder Sample in accordance with Tex-221-F. The timing of when the
source, per design
belts test is performed is at the discretion of the Engineer.
Sampled, tested
Compliance with Item and pre-approved Test a minimum of one sample taken from the project. Sample
1 each for binder
300 by CST/M&P. tack coat at the distributor on the roadway in accordance with
and tack coat per
ASPHALT BINDER Project test Tex-500C, Part III. Sample binder at hot mix plant in accordance
Binder & Tack Coat project, per grade,
sampled at the with Tex-500-C, Part II. Binder should arrive on the project pre-
(A) per source
Plant for Binder & approved. If not pre-approved, sample binder before use.
Road for Tack Coat
Verify that aggregates, recycled asphalt pavement, recycled
asphalt shingles, mineral filler, asphalt binder, anti-stripping
Compliance with Min 1 design per
At source (if not additives, and warm mix systems are on the Material Producer
MIX DESIGN applicable Tex-204-F Mix Type and
approved) List where applicable and that they meet project specification
specification Asphalt Grade
requirements. Project sampling and testing may be conducted
on individual materials as necessary for control.
Enter customize text here for your needs or delete if not needed.
20
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
TABLE VI ASPHALT CONCRETE PAVEMENT (Items 341, 342, 344, 346, 347 and 348)
(All testing as noted in Table VI may be waived for exempt production as defined by specification.)
PROJECT INDEPENDENT
PROJECT TESTS
ASSURANCE TESTS
MATERIAL OR TEST FREQUENCY
TEST FOR LOCATION LOCATION FREQUENCY REMARKS
PRODUCT NUMBER (Per Design)
Sample in accordance with Tex-222-F.
Engineer Truck
Asphalt Content (%) Determine correlation factors for ignition oven
Tex-236-F Sample Minimum 1 per Lot
(A) using Tex-236-F at a minimum of one per
(D)
project.
Enter customize text here for your needs or delete if not needed.
21
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
TABLE VI ASPHALT CONCRETE PAVEMENT (Items 341, 342, 344, 346, 347, and 348)
(All testing as noted in Table VI may be waived for exempt production as defined by specification.)
PROJECT TESTS
FREQUENCY
MATERIAL OR PRODUCT TEST FOR TEST NUMBER LOCATION REMARKS
(Per Design)
Two cores taken per Sublot and averaged. Sample in accordance
In-Place Air Voids Roadway with Tex-222-F.
ROADWAY Tex-207-F 2 cores per Sublot
(A) (D)
Does not apply to Items 342, 347, and 348.
Segregation
Tex-207-F,
Profile Roadway 1 per project
Part V Not required when Contractor uses thermal imaging system. Does
(A)
not apply to Items 342, 347, and 348.
Joint Density Tex-207-F,
Roadway 1 per project
(A) Part VII
Immediately behind
Thermal Profile Tex-244-F 1 per project Not required when Contractor uses thermal imaging system.
ROADWAY paver
Engineer may verify Contractors results for surface test Type B. For
Ride Quality Test traditional design-bid-build TxDOT projects, CST has contracted with
Final riding surface of
Type B Tex-1001-S 1 per project TTI to perform random ride verification at 10% frequency.
travel lanes
(A)
Results for surface test Type A are not required to be reported.
Permeability Tex-246-F Roadway 1 per project Only applies to Items 342, 347, and 348.
TABLE VI FOOTNOTES
When this project acceptance test fails but the product is accepted, document the reasons for acceptance on the Letter of Certification of Materials Used or in the SiteManager
A
Remarks field. This letter is required only for Asphalt Content and/or Gradation when production of complete mixture is suspended as required by QC/QA specifications.
Sampling may be performed at the plant, quarry, or both. Aggregate properties may be re-tested at any time during the project. These project tests may be used for one or more
B
projects furnishing hot mix with the same aggregate source.
C Attach the corresponding QM test report for SiteManager projects to satisfy project sampling and testing requirements.
D Perform random sampling as specified in Tex-225-F, Random Selection of Bituminous Mixture Samples.
E Each test performed that is based on a quantity of material is considered or fraction thereof for calculating number of tests.
Enter customize text here for your needs or delete if not needed.
22
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
Enter customize text here for your needs or delete if not needed.
23
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
Enter customize text here for your needs or delete if not needed.
24
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
COARSE AGGREGATE Stockpile 1 per project, per Sample in accordance with Tex-221-F. Testing frequency may
Micro Deval Tex-461-A be reduced or eliminated based on a satisfactory test history.
(B) source
Enter customize text here for your needs or delete if not needed.
26
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
Enter customize text here for your needs or delete if not needed.
27
This is a guide for minimum sampling and testing.
Testing frequency may need to be increased for high material variability or when test results approach specification limits.
TABLE IX FOOTNOTES
When this project acceptance test fails but the product is accepted, document the reasons for acceptance on the Letter of Certification of Materials Used or in the SiteManager
A
Remarks field. This letter is required only for Asphalt Content and/or Gradation when production of complete mixture is suspended as required by QC/QA specifications.
Sampling may be performed at the plant, quarry, or both. Aggregate properties may be re-tested at any time during the project. These project tests may be used for one or more
B
projects furnishing hot mix with the same aggregate source.
C Attach the corresponding QM test report for SiteManager projects to satisfy project sampling and testing requirements.
D Each test performed that is based on a quantity of material is considered or fraction thereof for calculating number of tests.
Enter customize text here for your needs or delete if not needed.
28