Procurement Procedures
Procurement Procedures
Procurement Procedures
2 Purpose
The aim of this procedure is to ensure that all purchases made by SQA staff
conform to the regulations stated above, and embrace our management
principles. An integral part of this procedure is the provision of a process which
facilitates and supports those charged in carrying out any procurement task.
3 Scope
Procurement covers the process of acquisition of goods and services (including
consultancy) from third parties. It ranges from initial concept and definition of
business need through to the end of the useful life of a purchased asset or
service contract.
4 Policy
As a public sector organisation, it is vital that SQA observes the highest
standards of integrity when dealing with all matters concerning the procurement
of goods and services. In particular SQA must:
Not only must SQA be seen to be open and accountable in all its transactions,
but we must also ensure that we operate fairly and efficiently and make best use
of taxpayers money. This should be achieved through competition unless there
are compelling reasons to allow for a direct award to a supplier; approval must
sought by the Director of Finance prior to the order being placed.
Best Value, otherwise known as Value for Money, means taking into account the
optimum combination of whole life cost and quality necessary to meet SQAs
requirements and not simply on initial costs. See examples below:
total cost
warranty or maintenance costs
disposal cost of goods
travel costs
maximum product and service development cost
mutually beneficial commercial relationships
effective management of contractual relationships
environmental impact
The Contract Sponsor is the responsible and accountable officer for a given
contract, and owns responsibility for the terms secured and the quality of the
contract in terms of Most Economically Advantageous Tender (Best Value and
Fitness for Purpose).
Purchase Agent
The Purchase Agent is responsible for obtaining quotes for all spend below
25,000 for the relevant business area. The Purchase Agent assists the Contract
Sponsor, in the preparation of the specification, including the evaluation criteria.
The Purchase Agent will also support the Contract Sponsor following contract
award, in all contract review meetings with the supplier. The Purchase Agent will
be supported by the Procurement team as required.
Each business area should have at least one POA to enable purchase orders to
be raised. They will be responsible for ensuring the information on the purchase
order accurately reflects the exact requirements, cost centre and cost. The
following is a summary of POA responsibilities:
Procurement Team
The Procurement Manager, who leads the Procurement team, reports to the
Director of Corporate Services and oversees all contracts.
The Purchasing Manager and Officer are involved in contracts over 25,000
whilst also providing support and guidance on lower value spend. They will work
with the Contract Sponsor and Purchase Agents to ensure their requirements are
understood and incorporated into the tender documentation and be involved
throughout the tender process.
The Director of Finance is required to authorise all non-compliant spend that has
not followed the required competitive process.
SQA staff, at all levels, are required to comply with the procurement rules and
regulations.
Services 173,934
Supplies 173,934
Types of Contract
Contract (General)
These contracts are usually for good or services with an anticipated total contract
value in excess of 10,000. Contracts might also be awarded to suppliers where
the value is less than 10,000 due to the complexity of requirements. A purchase
order is required for all contracts.
Concession Contract
This is solely for contracts where SQA receives income for goods or services
provided (e.g. publishing of past examination papers).
Others
SQA has in place standard terms and conditions which must be used for all
contracts. SQAs terms and conditions form a specific schedule in the Invitation to
Tender (ITT) document and should not be amended without prior approval from
Procurement. Any agreed amendments will be documented in the contract.
The optimum contract period will depend upon the nature of the goods or
services being provided, and the market for them.
give SQA and suppliers greater time and incentive to understand the
requirements of the contract and to co-operate, providing service
improvements and/or cost reductions
give SQA longer to recover the cost of any investment (e.g. in training
or new technology) required for the contract, and hence the ability to
reduce annual charges and total cost of ownership
reduce the cost to both SQA and suppliers of frequent re-tendering
exercises
enhance partnership arrangements
Contracts duration
The recommended duration of a contract is four years and this should not be
exceeded without prior approval from Procurement. Duration of contracts can be
split into an initial period plus the option of an extension to make up the full term
of four years.
Frameworks duration
delivery timescales
quality of goods or service provided
correct details on all invoices
management information provided
environmental changes/impacts
In addition, it would be useful to consider what is going well and to record the
reasons. There may be important lessons to put into practice, which may prevent
problems in other parts of the contract. This will also help to develop a positive
relationship with a supplier and assist in the contract review process.
Contracts should state formal review dates. The Contract Sponsor should have
them agreed with the supplier at intervals that give them confidence in their
monitoring processes. New suppliers, depending on the nature of the contract,
might be reviewed as often as monthly, although SQA would recommend as a
guide every three to six months. These reviews should be led by the Contract
Sponsor supported by the Purchase Agent and Purchasing Manager or Officer if
required.
A report should be prepared by the Purchase Agent following the review meeting
and agreed with the Contract Sponsor and supplier. If the review meeting
necessitates a change to the existing contract, the Purchase Agent should
contact Procurement to assist with a contract addendum.
Where a supplier fails to meet its contractual obligations, or have not addressed
any action highlighted at the contract management review meetings, SQA may
decide to terminate the contract.
Procurement will store original signed contracts with the successful tendering or
quotation documents. Contract Sponsors may retain a photocopy of final contract
documents, for contract review purposes, for the life of the contract only.
8 Timescales
Timescales should be taken into account when planning any procurement
exercise. From obtaining approval through to contract award, the timescales
vary on the value of the contract.
The Contract Sponsor should ensure that sufficient time is factored into the
procurement process to also allow for SQA Board of Management and Scottish
Government approval. The Contract Sponsor and nominated Procurement
contact should discuss and set out the timescales for the stages in the tendering
process to avoid slippage and ensure that crucial deadlines are met.
9 Market research
Contract Sponsors are encouraged to undertake some market research within
the supply market in order to determine an approximate cost and to obtain
general advice and/or information about their requirement. However, the
following advice should be noted:
10 Risk assessment
A formal risk assessment should be carried out for all high value (over EU
thresholds) or strategic contracts prior to the preparation of the tender, to ensure
risks can be adequately addressed. However, risks (and contingency) should
always be considered when drafting any tender specification.
12 Procurement Processes
Direct award to a supplier for one off purchases up to 300
Invitation to Quote (ITQ) goods and services between 10,000 and 25,000
Planning
The closing date and time for the ITQ return must be advised within the
ITQ as late quotes will not be considered.
The quotes received after the deadline should be evaluated using the
evaluation template (PR11).
Justification comments should be recorded to enable feedback to be
provided to the unsuccessful suppliers.
Award
Planning
Where total expenditure is over 25,000 (incl. VAT) the Purchase Agent
must complete a CRF form (PR 15) and send it to Procurement to
obtain a contract number for use on all future documentation.
This process is led by a member of the Procurement team with input
from the Purchase Agent who will draft the specification with all their
business requirements.
The Procurement team member will assess which procedure to follow
depending upon the requirements. Depending on the process, a Pre-
Qualification Questionnaire (PQQ) can be used.
The issue of a PQQ can be an effective way of ensuring that suppliers
taken forward to the ITT stage have the capacity and ability to meet
SQA requirements.
At this stage the Purchase Agent must consider the evaluation criteria,
including the price and quality split which should be used to evaluate
the ITT. The criteria must be relevant to the particular contract.
The advert will be placed on www.publiccontractsscotland.gov.uk by
Procurement and OJEU if over the EU threshold. The advert will include
the evaluation criteria, type of procedure and total value of the contract.
Evaluation
Award
13 Scottish Government
Non Competitive Action report
An exception report will be created using the information provided in the Non
Competitive Action (NCA) forms completed by the business areas. This report will
list all instances where the procurement process has not been followed, and will
be issued to the Scottish Government each financial year.
Approval from the SQA Board and the Scottish Government is mandatory for new
contracts in the following circumstances: