309.2R-98 Identification and Control of Visible Effects of Consolidation On Formed Concrete Surfaces

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11
At a glance
Powered by AI
This document provides guidelines for identifying and controlling visible effects of consolidation on precast or cast-in-place formed concrete surfaces. It includes factors that can cause surface imperfections as well as examples of typical blemishes seen.

Factors that can cause undesirable surface effects include design of structural members, specifications, forms, properties of fresh concrete, placement, consolidation, and special construction conditions.

Common surface blemishes discussed include honeycomb, air voids, form streaking, aggregate transparency, subsidence cracking, color variation, sand streaking, layer lines, form offsets, and cold joints.

ACI 309.

2R-98
(Reapproved 2005)

Identification and Control of Visible Effects of


Consolidation on Formed Concrete Surfaces
Reported by ACI Committee 309
H. Celik Ozyildirim
Chair
Neil A. Cumming Kenneth C. Hover Larry D. Olson
Timothy P. Dolen Gary R. Mass Steven A. Ragan
Jerome H. Ford Bryant Mather Donald L. Schlegel
Steven H. Gebler Richard E. Miller Brad K. Violetta
Glen A. Heimbruch

Revising Committee:
Jerome H. Ford
Chair
Dan Bonikowsky Gary R. Mass Steven A. Ragan
Neil A. Cumming Bryant Mather Donald L. Schlegel
Timothy P. Dolen Richard E. Miller Brad K. Violetta
Steven H. Gebler H. Celik Ozyildirim

This report provides guidelines for identifying and controlling visible whenever they occur. Some surfaces can tolerate them to some or any
effects of consolidation on precast or cast-in-place formed concrete sur- degree; other surfaces cannot. It is the responsibility of the specifier to
faces. It includes a summary of direct and indirect causes of such imperfec- indicate in the contract documents what constitutes acceptable and unac-
tions. An outline to assist in the reporting on surfaces and photographs to ceptable blemishes for the various surfaces to be produced under the terms
illustrate typical concrete surface blemishes are also included. of a given contract. Terms used in this report are as defined in ACI 116R.
Surface blemishes in concrete may be minimized by proper planning dur-
ing the design and specification stages. Of equal importance is the employ- Keywords: aggregates; bugholes; concretes; consistency; consolidation;
ment of properly trained and motivated supervisory and non-supervisory construction joints; discoloration; formwork (construction); mix propor-
construction personnel to achieve the intended concrete finishes and sur- tioning; placing; preplaced-aggregate concrete; quality control; surface
face textures. defects; temperature; vibration; voids; workability.
The report emphasizes significant consolidation factors that minimize
undesirable surface effects. The reader is cautioned that other potential
causes of such effects may exist beyond those listed in this report. There are
CONTENTS
documents in which a feature designated as a defect is one that must be
Chapter 1General, p. 309.2R-2
prevented, avoided, corrected, remmediated or otherwise dealt with. The
term defect, as formerly used in this report, covers blemishes and depar- Chapter 2Factors causing effects, p. 309.2R-2
tures from perfection that are not features, and must be avoided or repaired 2.1Design of structural members
2.2Specifications
2.3Forms
ACI Committee Reports, Guides, Standard Practices, and
Commentaries are intended for guidance in planning, de- 2.4Properties of fresh concrete
signing, executing, and inspecting construction. This docu- 2.5Placement
ment is intended for the use of individuals who are 2.6Consolidation
competent to evaluate the significance and limitations 2.7Special construction conditions
of its content and recommendations and who will accept
responsibility for the application of the material it con- Chapter 3Surface blemishes, 309.2R-6
tains. The American Concrete Institute disclaims any and 3.1Honeycomb
all responsibility for the stated principles. The Institute shall 3.2 Air voids in formed surfaces
not be liable for any loss or damage arising therefrom.
Reference to this document shall not be made in contract ACI 309.2R-98 became effective August 19, 1998. This document supersedes ACI
documents. If items found in this document are desired by 309.2R-90.
Copyright 1998, American Concrete Institute.
the Architect/Engineer to be a part of the contract docu- All rights reserved including rights of reproduction and use in any form or by any
means, including the making of copies by any photo process, or by electronic or
ments, they shall be restated in mandatory language for in- mechanical device, printed, written, or oral, or recording for sound or visual reproduction
corporation by the Architect/Engineer. or for use in any knowledge or retrieval system or device, unless permission in writing
is obtained from the copyright proprietors.

309.2R-1
309.2R-2 ACI COMMITTEE REPORT

3.3 Form streaking CHAPTER 2FACTORS CAUSING EFFECTS


3.4Aggregate transparency Causes of consolidation-related effects on formed con-
3.5Subsidence cracking crete surfaces (Table 1) include:
3.6Color variation A. Design and construction-related causes
3.7Sand streaking Difficult placement due to design of a member
3.8Layer lines Improper selection of horizontal construction joint
3.9Form offsets location
3.10Cold joints Improper design, manufacture, installation, shipping,
preparation and maintenance of forms
Chapter 4Minimizing surface effects, p. 309.2R-8 Improper selection of concrete mixture proportions
Failure to adjust concrete mixture proportions to suit
Chapter 5Consolidation of preplaced-aggregate placement condition
concrete, p. 309.2R-10 Improper placement practices
Improper consolidation practices
Chapter 6Conclusion, p. 309.2R-10 Improper steel detailing
B. Equipment-related causes
Chapter 7Surface condition outline, p. 309.2R-10
Improper equipment
Chapter 8References, p. 309.2R-11 Improper equipment maintenance
8.1Recommended references Equipment failure (crane, pump, concrete plant)
8.2Cited references Interruption of utility service
C. Material-related causes
CHAPTER 1GENERAL Improper selection of release agent
A formed concrete surface, uniformly smooth or deeply Cement characteristics
textured and essentially free of blemishes and color varia- Variation in mixture constituents
tion, is difficult to attain. Since repairs to a defective surface Inappropriate use of admixtures
are costly and seldom fully satisfactory, the need for repairs D. Environmental causes
should be minimized by establishing and maintaining the Extreme weather conditions
quality of the concrete operation and by adhering to accept- Examples of some of the more common blemishes are illus-
able consolidation procedures. Standards for surface finishes trated in Fig. 1 through 10.
are beyond the scope of this report. Guidance for establish-
ing appropriate standards is offered by the International 2.1Design of structural members
Council for Building Research (CIB) (1975), which classi- The common problems requiring consideration during de-
fies formed surface finishes as follows: sign and planning are congested reinforcement (particularly
SpecialHigh standards of appearance required (ACI splices), narrow sections, or complex form configurations.
303R); Conditions that require closed top forming, embedments,
ElaborateDefinite requirements for visual appear- and battered forms also require consideration during design
ance; and planning.
OrdinaryAppearance is of some importance; and To produce properly consolidated concrete with the de-
RoughNo special requirements for finish. sired appearance, the placement and consolidation of the
Concrete construction procedures do not always provide concrete must be understood. The designer must have a
the control necessary to consistently obtain blemish free con- working knowledge of the concrete placement process. The
crete indicated by a special category. designer and the constructor should communicate during the
To achieve any concrete finish, the designer and the con- early phases of the concreting process. Early recognition of
tractor must use materials as well as design and construction problem areas is important to provide time to take remedial
practices that will keep surface effects within acceptable lim- measures, such as staggering splices, grouping reinforcing
its. There is a definite need for understanding the causes of steel, modifying stirrup spacing, increasing the section size,
unacceptable blemishes and effects encountered in concrete and selecting locations of horizontal construction joints.
construction and a need for applying more effective mea- When unfavorable conditions exist that could contribute to
sures to minimize or eliminate them. This report addresses substandard surfaces, one or more of the following actions
those needs and its major emphasis is on consolidation- should be taken:
related effects. 1. Redesign the member;
The most serious effects resulting from ineffective consol- 2. Redesign the reinforcing steel;
idation procedures are: honeycomb, subsidence cracks, cold 3. Provide adequate access for consolidation at horizontal
joints, and excessive surface voids. A detailed description of construction joints;
the blemishes and their causes are provided in Table 1. Some 4. Modify mixture proportions;
imperfections may not conform to contract documents and 5. Use mock-up tests to develop a procedure; and/or
may be considered as defective work. 6. Alert the constructor to critical conditions.
CONSOLIDATION-RELATED SURFACE EFFECTS 309.2R-3

Table 1Summary of primary causes of surface effects


Defects Causes
Design of Construction Properties of
members Forms conditions fresh concrete Placement Consolidation
Name Description Fig. 1 2 3 4 5 6

Vibrator too
Highly Excessive free small,
congested Premature Insufficient fall, excessive frequency and
reinforcement, setting fines, low work- lift of concrete amplitude
Stony zone with narrow section, reinforcement ability, early in forms, drop inappropriate,
air voids; lack- internal interfer- Leaking at too close to stiffening, chute omitted, too short immer-
Honeycomb ing in fines. Due 1 ence, reinforce- joints, severe forms, lack of excessive or insufficient sion time, exces-
to ment splices, grout loss access for vibra- mixing, too length, too small sive spacing
segregation restricted access tion, large aggregate a tremie, segre- between immer-
for vibration, congestion due for placing con- gation due to sions, inade-
high monolithic to splices ditions horizontal quate penetration
lifts movement insufficient num-
ber of vibrators

Low FM of fine
Form face aggregate, lean, Too large an
fine aggregate amplitude,
Small individual impermeable,
poor wetting Excessive with a high FM, Too slow, external
Air surface holes, irregular, Battered or low workability, caused by inade- vibration
ranging up to 1 2 interfering con- characteristics, release agent,
voids formwork too high tempera- excessive cement quate pumping inadequate,
in. (25 mm) in struction or pozzolan, rate, undersized head of
diameter flexible, use of ture of concrete.
improper form particle degrada- bucket vibrator
release agent tion, excessive partially
sand, high air immersed
content

Fine aggregate or
coarse aggregate Leaking at
textured areas joints, tie holes, Usually caused Improper Excessive
Form- lacking cement, caused by loose by horizontal Excess water or timing between amplitude or
streaking 3
usually associ- hardware or concrete high slump placing and frequency for
ated with dark oversized tie movement vibrating form design
color on adjacent holes
surface

Low fine-aggre-
Dark or light gate content,
areas of gap-graded Excessive
similar size and Too flexible, aggregate dry or external
Aggregate shape to that of 4 high-density porous aggre- vibration; over-
transparency the coarse aggre- surface finish gate, excessive vibration of
coarse aggre- lightweight
gate, mottled
appearance gate, excessive concrete
slump with light-
weight concrete

Short cracks Poor thermal Insufficient delay Low fine aggre-


insulation, between top-out gate, high water Insufficient
varying in width, Interference to
Subsidence more often hori- 5 irregular shape of columns and content, too high vibration and
cracking access, lack of Too rapid
zontal than adequate cover restraining settle- placement of slump, Poorly lack of
vertical ment, excessive slab or beam, proportioned revibration
absorbency low humidity mixes

2.2Specifications proportions may need adjustments to produce the desired


Acceptable specifications for concrete and concrete con- concrete characteristics and to minimize consolidation prob-
struction are essential to ensure proper construction practices. lems. However, the mixture should be adjusted with care to
Practical and workable specifications that allow for unusual maintain the design intent and to avoid other problems, such
and complex job conditions are needed.
as excessive cracking. The specifications should require
Specifications should be sufficiently broad in scope to per-
mixing, transporting, handling, and placing that can result in
mit adjustments of mixture proportions and batch adjust-
ments needed to produce uniformly workable concrete that adequate consolidation and minimize chances for surface
will respond readily to vibration. Concrete may still vary due blemishes. Moreover, the specifications should call for
to changes in aggregate grading, ambient and concrete tem- vibrators of proper size and characteristics, as recommended
perature, air content, and batch quantities, even though these in ACI 309R. Small-diameter vibrators should be required to
changes are within specification limits. Accepted mixture supplement larger-diameter vibrators where access is limited.
309.2R-4 ACI COMMITTEE REPORT

Table 1Summary of primary causes of surface effects (cont.)


Defects Causes
Design of Construction Properties of fresh
members Forms conditions concrete Placement Consolidation
Name Description Fig. 1 2 3 4 5 6

Non-uniform color
Variations in Variation in absorp- of materials, incon-
color of the sur- tive capacity of sur- sistent grading, vari-
face, Heavy face, reaction with ation in proportions,
Color
visible within a 6 reinforcement form face, chemical incomplete mixing. Segregation Vibrator too close to
slump too form, vibration next
variation reaction with release Calcium chloride
few hours after close to forms high to forms variable
removing the agents, leakage of can cause darker
formwork forms at joints and color. Too high a
tie holes slump. Over-manip-
ulation

Form leakage.
Variation in Lean over-sanded
Excess water at bot- Low tempera- Excessive vibration.
color or shade tom of form forced mixtures and harsh, Too rapid for Excessive ampli-
Sand streaking due to separa- 7 up along form face ture, wet mix- wet type of tude. Over-
tion of fine parti- tures mixtures mixture
by hydraulic manipulation
cles pressure deficient in fines

Dark colored Slow place-


Insufficient Lack of vibration,
Layer lines zones between Internal Wet mixture with ment, lack of
8 planning, high failure to penetrate
(pore lines) concrete layers interference tendency to bleed equipment or
temperature into previous layer
manpower

Voids, honey-
comb and color Poor planning
or insufficient
variations along Failure to vibrate
boundaries of Insufficient backup equip- Delayed
Cold joints 9 space to insert Too dry, early stiff- into lower lift.
lifts, top layer of ment, ening, slump loss delivery, lifts Insufficient
vibrator substrate too thick
concrete not ade- vibration
quately bonded concrete has
to substrate set

Excessive amplitude,
Abrupt to grad- Construction Poor form
Form offsets ual surface irreg- 10 joint at change Inadequate form-
work design for rate anchorage and Excessive retarda-
tion of time of set-
non-uniform spacing
Rate too high of immersion hori-
in direction of inadequate
ularities of placement ting of concrete zontal movement of
formwork bulkheads concrete

2.3Forms conditions occurs, the concrete surface may peel during form
Some surface blemishes are caused by inadequacies of the removal.
formwork. Examples are leakage at joints, inadequate facing The finish should be observed as the form is stripped so
material, excessive overload on previously placed concrete that appropriate corrective measures, if needed, can be im-
(ACI 303R), inadequate anchorage, poorly braced and ex- plemented promptly. Inward sloping forms have a tendency
cessively flexible forms, improper use of release agents, and to trap or restrict the movement of entrapped air and bleed
oversized and unsealed tie holes. Surface blemishes also re- water to the surface, and increase the occurrence of surface
sult from overuse of forms, poor storage practices, inade- effects. Form strength, design, and other form requirements
quate cleaning, and improper patching and repair of the are covered in ACI 347R.
forms.
The number of visible surface voids (bug holes) may be re- 2.4Properties of fresh concrete
duced by using absorptive forms; however, smooth forms in The composition, consistency, workability, and tempera-
combination with the correct selection of a form release- ture of fresh concrete has a significant bearing on the ease
agent allow air voids at formed surfaces to move upward with which a concrete mixture may be placed and consoli-
more freely. ACI 303R discusses the use of release agents. dated. For critical surface finishes, the effect of each ingre-
Some dry resin-based release agents used on steel forms dient of the mixture may require special consideration.
will greatly increase the number of bug holes. An excessive Placing conditions should also be considered during mixture
amount of release agent collecting in the bottom of the form proportioning.
may result in discoloration of the concrete and may create Mixture adjustments should be made to the proportions to
weak areas. Inadequately cleaned forms, or those which have maintain workability when materials and field conditions
been reused too many times, can contribute significantly to change, provided that critical properties, such as durability
the formation of surface blemishes. When any of these and strength, are maintained.
CONSOLIDATION-RELATED SURFACE EFFECTS 309.2R-5

A review by the designer is essential to ensure that increase in lift thickness from 0.6 to 1.2 m (2 to 4 ft) reduced
strength levels, nominal maximum aggregate size, and bug holes by 50 percent when an air content of 5 percent was
slump requirements for different structural elements are met. specified.
Concrete ingredients should be evaluated and proportions
should be selected well in advance of the concreting opera- 2.6Consolidation
tion to achieve the desired properties for the fresh concrete. Concrete consists of coarse aggregate particles in a matrix
Sticky mixtures may occur if the fine aggregate grading in of mortar, and irregularly distributed pockets of entrapped
the 1.18 mm to 300 m (No. 16 to 50) size range approaches air. If the concrete is air entrained, an additional evenly dis-
the upper limits specified by ASTM C 33, or if high cement tributed system of entrained air bubbles is present. The vol-
contents are used. Some pozzolans also may cause mixtures ume of entrapped air in unconsolidated concrete may vary
to be more cohesive. Thus, the passage of entrapped air may from about 5 to 20 percent depending on the workability of
be restricted and air voids may be trapped at the interface be- the mixture, size and shape of the form, amount of reinforc-
tween the concrete and the form. If fine aggregate contains ing steel, and method of depositing the concrete. The pur-
the proper amount of materials in the 600 to 300 m (No. 30 pose of consolidation is to remove as much of this entrapped
to 50) size range, little bleeding will occur in the resulting air as practical.
concrete. As a result, placement and consolidation of the Vibration is the most common method of consolidation. It
concrete will be facilitated, thereby minimizing surface causes very rapid movement of the concrete mixture parti-
effects. cles and briefly liquefies the mixture, thus reducing the inter-
Soft aggregates may degrade and produce additional fines. nal friction. When vibrated, concrete becomes fluid and
In some instances, the fines may make the mixture more co- through the action of gravity seeks a lower level and denser
hesive and increase the difficulty of removing entrapped air. condition as entrapped air rises to the surface and is expelled.
This is particularly true at high cementitious materials con- It compacts laterally against the form and around the rein-
tents. In other instances, the additional fines can significantly forcing steel. In practice, vibration is normally continued un-
increase the water demand, resulting in lower strength, in- til the entire placement acquires a uniform appearance and
creased shrinkage, and crazing of smooth formed surfaces. its surface just starts to glisten or large bubbles cease to ap-
Experience indicates that a concrete at a given consistency pear. A film of cement paste should be discernible between
will generally flow more easily at lower temperatures than at the concrete and the forms. These visual indicators are not
higher temperatures. necessarily an accurate indication of good consolidation.
When chemical and especially mineral admixtures are ACI 309R provides guidance on judging the adequacy of
used, their effect on placement and consolidation should be vibration.
evaluated when mixture proportions are being established. Undervibration is far more common than overvibration,
All of the factors discussed above need to be considered to and may be caused by the following:
obtain a concrete mixture with the desired composition, 1. Use of an undersized, underpowered, or poorly main-
consistency, and workability to facilitate its placement and tained vibrator;
consolidation. 2. Excessive or haphazard spacing of vibrator insertions;
3. Inadequate vibration during each insertion;
2.5Placement 4. Failure of the vibrator to penetrate into the preceding
Concrete should be placed as quickly as possible with a layer; and/or
minimum amount of segregation and spattering on the 5. Vibrator in the wrong position relative to the form.
forms. Once the coarse aggregate is separated from the mor- Common imperfections resulting from under-vibration are
tar by poor handling and placement practice, it is virtually honeycomb, excessive entrapped air voids, and layer lines.
impossible to work the mortar back into the voids and restore Overvibration can occur if vibration is continued for a pro-
a dense mass by vibration. Segregation and separation cause longed time (several times the recommended time period).
honeycomb. Spattered mortar on the form produces color Overvibration is generally the result of using oversized
variations and poor surface texture. Placing concrete too equipment, improper procedures, high slump, or improperly
slowly may allow workability to be lost and can produce lay- proportioned mixtures. It may result in segregation, exces-
er lines or cold joints due to improper consolidation. The rate sive form deflection, sand streaking, and form damage.
of placement and vibration factors (intensity and spacing) Backstrom et al. (1958) found that air content of concrete is
should be selected to minimize entrapped air in the concrete. decreased by increasing periods of vibration, but little ef-
If concrete is deposited in thick layers of more than 300 mm fect is noted on spacing factor of air-entrained concrete. In
(12 in.), more air may be trapped than if it is placed in a thin- concrete of nominal 6.5 percent air the air content dropped
ner, even layer since the air has to travel farther to escape. from 6.7 to 1.2 after 2, 6, 12, 20, 30, and 60 sec of vibration,
Where mixtures of dry or stiff consistencies are required, the but the spacing factor was unchanged as was the number of
placement rate should be slower to permit adequate consolida- cycles to 25 percent loss in mass.
tion so as to avoid bug holes and honeycombing. However, in The consequences of overvibration will be minimized if a
the case of a sanitary treatment structure with steel forms, an well-proportioned mixture with a proper slump is used. The
309.2R-6 ACI COMMITTEE REPORT

horizontal or less may be erected as temporary forms that are


removed after initial setting for later hand finishing of the
concrete.
Large mass-concrete sections placed in irregularly shaped
forms may have surface blemishes due to non-uniform or
widely spaced locations for tremies, pipes, or chutes. Poorly
planned and executed procedures can cause the concrete to
build up in piles. This will promote segregation, cold joints,
layer lines, honeycomb, and subsidence cracks. To obtain ac-
ceptable results, placing methods must be well planned and
well supervised.

CHAPTER 3SURFACE BLEMISHES


Surface blemishes that can result from ineffective consol-
idation procedures are discussed below.

3.1Honeycomb
Honeycomb (Fig. 1) is a condition of irregular voids due
to failure of the mortar to effectively fill the spaces between
coarse aggregate particles. Where bridging of the coarse ag-
gregate particles or stiffness of the mixture is a cause of hon-
eycomb, vibration may assist in overcoming the bridging by
increasing the flowability of the concrete. Factors that may
contribute to honeycombing are: congested reinforcement,
segregation resulting in insufficient paste content, and im-
proper fine aggregate to total aggregate ratio, improper plac-
ing techniques, rapid stiffening of hot concrete, difficult
Fig. 1Honeycomb. construction conditions, and insufficient consolidation ef-
fort. Changes in construction practices and in mixture pro-
behavior of fresh concrete during vibration is discussed in portions to improve workability and the use of water-
ACI 309.1R. reducing admixtures to increase slump may assist in reduc-
ing or preventing honeycombing.
2.7Special construction conditions
No matter how carefully a concrete finish is specified, the 3.2Air voids in formed surfaces
resultant quality depends on careful construction site organi- Bug holes (Fig. 2) are small regular or irregular cavities,
zation and the use of well-trained and skilled workmen. ranging from nearly invisible to 25 mm (1 in.) but usually not
Competent supervision is essential to assure that the con- exceeding 15 mm (9/16 in.) in diameter, that result from en-
struction forces properly handle and assemble the forms and trapment of air bubbles in the surface of formed concrete
methodically place and consolidate the concrete. Supervisors during placement and consolidation. Bug holes on vertical
must be alert to unfavorable conditions during the installa- faces are more likely to occur in sticky or stiff concrete mix-
tion of forms and reinforcement and immediately bring these tures of low workability that may have an excessive fine ag-
conditions to the attention of the designer. The designer gregate content or entrapped air content, or both. Also, the
should also locate horizontal construction joints at points of use of vibrators with too high of an amplitude or the lack of
maximum access for placement and consolidation exists. complete insertion of the vibrator head may result in an in-
Combining lifts may restrict access for proper consolidation creased quantity of air-voids. Air voids vary in size from mi-
and increase the likelihood of surface effects. croscopic to about 25 mm (1 in.). Excess water normally
Formed concrete surfaces under box outs and battered manifests itself in other textural effects such as bleeding
forms require special considerations for placement. The mix- channels or sand streaks on vertical formed surfaces. Bleed
ture may have to be adjusted to produce a readily flowable water voids can form at the top of a column and on battered
concrete that is capable of completely filling the formed area. formed surfaces. Surface voids can be minimized by the pro-
For large surface areas, it may be necessary to cut holes in a cedures discussed in Section 4.
battered form to provide access for vibrating the concrete.
With thin layers and careful vibration, the air bubbles can be 3.3Form streaking
drawn up the side of the form. Experience shows that sloped Form streaking (Fig. 3) is caused by mortar leaking through
concrete steeper than about 20 deg from horizontal should be form joints and tie holes and may be aggravated by overvibra-
formed and the concrete thoroughly vibrated to minimize tion from vibrators that are too powerful, or by using forms
surface voids. Sloping forms at angles of about 45 deg from that vibrate excessively during consolidation.
CONSOLIDATION-RELATED SURFACE EFFECTS 309.2R-7

Fig. 2Air surface voids. Fig. 3Form streaking.

Placing excessively wet or high-slump concrete mixtures er during the design phase and by using low-slump concrete
will result in more mortar washing out through tie holes and that is well-consolidated.
loose fitting forms. Special care is sometimes required when
high-range water-reducing admixtures are used, as they tend 3.6Color variation
to increase leakage at form joints. Color variation (Fig. 6) may occur within a placement if
the concrete is not uniform or is incompletely mixed.
3.4Aggregate transparency Vibrators inserted too close to the form can cause color
Aggregate transparency (Fig. 4) is a condition character- variation by marring the form surface. External vibration
ized by a mottled appearance on the surface that results from used haphazardly may also cause color variation. Further-
deficiencies in the mortar. It may occur when concrete mix- more, color variations may result from nonuniform absorp-
tures have low fine aggregate content, dry or porous aggre- tion, nonuniform application of the release agent, or both.
gates, or high slump with some lightweight and normal-
weight aggregates. Also, high density or glossy form surfac- 3.7Sand streaking
es may cause aggregate transparency. Sand streaking (Fig. 7) is a streak of exposed fine aggre-
gate in the surface of the formed concrete caused by heavy
3.5Subsidence cracking bleeding along the form.
Subsidence cracking (Fig. 5) results from the development It frequently results from the use of harsh, wet mixtures,
of tension when the concrete settles closed to after time of particularly those deficient in the 300 to 150 m (No. 50 to
initial setting. Cracks are caused because the upper concrete No. 100) and smaller sizes. Streaking tendencies increase
bridges between the forms while the lower concrete settles. when the ratio of fine aggregate to cementitious materials in-
These cracks may occur when there is an insufficient inter- creases, such as in lean mixtures. Although the characteris-
val between placing the concrete in the columns and placing tics of Portland cement and pozzolans, if used, have some
the concrete for the slabs or beams. They may also occur ad- influence on bleeding, the grading of the fine aggregate is of
jacent to block-outs or over reinforcing bars with shallow greater importance. Sand streaking is controlled by the use of
cover. tight forms, proper mixture proportioning, and using well-
To prevent subsidence cracking, the concrete can be revi- graded fine aggregate to minimize bleeding. Streaking can
brated. Revibration is most effective when done at the latest be aggravated by excessive vibration, overmanipulation of
time at which the vibrator head will readily penetrate the the vibrator, the use of a vibrator with excessive amplitude;
concrete under its own weight. Subsidence cracking over re- or excess water at the bottom of the form forced up along the
inforcing bars can be controlled by increasing concrete cov- form face by hydraulic pressure.
309.2R-8 ACI COMMITTEE REPORT

Fig. 4Aggregate transparency. Fig. 6Color variation.


3.10Cold joints
Cold joints (Fig. 10) can often be avoided by contingency
planning, backup equipment, working to keep the concrete
surface alive, the use of retarding admixtures, and working
the vibrator into lower lifts.

CHAPTER 4MINIMIZING SURFACE EFFECTS


A number of studies have been made to determine how to
achieve better consolidation resulting in fewer surface blem-
ishes (Shilstone, 1977; Stamenkovic, 1973; Samuelson,
1970; and Reading, 1972). To minimize the size and number
of bug holes and all other effects, the following practices
should be followed:
Vibration period should be of sufficient duration;
Vibrator insertions should be properly spaced and over-
lapped and the vibrator removed slowly;
Each concrete layer should be consolidated from the
Fig. 5Subsidence cracking. bottom upward;
Vibration periods should be increased on withdrawal
3.8Layer lines when using impermeable forms that permit air trapped
Layer lines (Fig. 8) are dark horizontal lines on formed sur-
at the form surface to escape through joints as between;
faces that indicate the boundary between concrete placements.
Layer lines are caused by premature stiffening or insufficient Inward sloping forms and other complex design details
consolidation of the previous layer of concrete due to lack of should be avoided;
penetration of the vibrator into that layer, or the use of a mor- Depth of placement layers should be limited;
tar bonding layer between placements. Vibrator should penetrate into the previous layer;
Tightening devices and gaskets to prevent leakage at
3.9Form offsets form joints should be provided as necessary; and
Form offsets (Fig. 9) are usually caused by inadequate Placing ports should be designed into the forms as
stiffness or anchorage of the forms and can be aggravated by necessary.
an excessive rate of placement or by using an excessively Where practical, bug holes can be minimized by the use of
powerful vibrator, or both. a 65-mm-(2-1/2 in.-)-diameter vibrator of high frequency
CONSOLIDATION-RELATED SURFACE EFFECTS 309.2R-9

Fig. 8Layer lines.

Fig. 7Sand streaking.

with medium to low amplitude. The vibrator should be im-


mersed in the concrete around the perimeter of the form
without damaging the form. Where reinforcement is placed
near the form wall, the vibrator must be inserted inside the
reinforcement. Care should be taken to ensure that the vibra-
tor has a sufficient radius of action to liquefy the concrete at
the form.
Form vibration may be used to supplement the internal vi-
bration. However, doing so may cause a major increase in
form pressure. An alternate procedure is to use a high-fre- Fig. 9Form offsets.
quency, low-amplitude form vibrator. Vibration procedures
should be evaluated at the beginning of a project to determine
the vibration time for each type of vibrator for a given mix-
ture. Guidance on the selection of appropriate vibration am-
plitudes, frequencies, and equipment is given in ACI 309R.
In areas where surface air voids are most prevalent, revi-
bration may be used to reduce them. Revibration is more ef-
fective if it is done at the latest possible time at which the
vibrator head will readily penetrate the concrete under its
own weight. Greater benefits are obtained with higher slump
concrete mixtures, especially in the upper portion of a place-
ment where excessive entrapped air voids are most preva-
lent. However, this practice may increase laitance that must
be removed from horizontal construction joints. And may
create color non-uniformity.
Other measures, such as altering mixture proportions, us-
ing high-range water-reducing admixtures, and using small-
er nominal maximum size aggregate to improve workability Fig. 10Cold joints.
309.2R-10 ACI COMMITTEE REPORT

should also be considered as methods of minimizing surface proportioning, placement, consolidation, or workmanship.
effects, provided that design requirements are met. These Frequently, the services of a specialist in concrete and con-
measures have often been successful, particularly when try- crete construction can be used to assist in obtaining concrete
ing to consolidate concrete in congested areas. Further guid- surfaces conforming to the higher standards. The execution
ance can be obtained from ACI 309R. of the work by well-trained work crews under competent su-
pervision will ensure a concrete surface meeting the require-
CHAPTER 5CONSOLIDATION OF PREPLACED- ments of the owner or designer.
AGGREGATE CONCRETE
The causes and cures of blemishes in concrete produced CHAPTER 7SURFACE CONDITION OUTLINE
by the preplaced-aggregate (PA) concrete method (ACI The following is an outline of items that should be consid-
304.1R, Chapter 7) are different from conventionally mixed ered by designers and constructors when reporting on the
and placed concrete in certain aspects. condition of a concrete surface and the possible causes of ef-
The rate of grout rise in preplaced aggregate should be fects. By following this checklist and referring to earlier
about 0.3 m/min (1 ft/min) with a maximum of 0.6 m/min chapters in this document, the designer or constructor should
(2 ft/min). If the supply is too rapid, the grout will rise fast- then be in a position to identify the cause and correct most
er through the large voids and cascade into the smaller types of surface effects.
ones, trapping air. The result is spotty honeycombing. To 1Description of structure
avoid the occurrence of layer lines, the lower ends of the 1.1Name, location, type, and size
grout injection ports should always be maintained at least 0.3 1.2Owner, project engineer, contractor
to 0.6 m (1 to 2 ft) below the grout surface. 1.3Design
Grout will not penetrate pockets of fine aggregate; fines 1.3.1Architect and/or engineer
that collect against side or bottom forms will produce honey- 1.4Photographs
combing. Also, care should be taken to ensure that coarse ag- 1.4.1General view
gregate fills the space between the reinforcement and forms, 2Description of wall, beam, or column showing blemishes
and that no large voids are left that will be subsequently filled 2.1Location, size
with grout. Large surface areas of grout not subdivided by 2.2Type of concrete
coarse aggregate may show crazing from drying shrinkage. 2.2.1Architectural
Coarse aggregate should be saturated when placed and at 2.2.2Structural
the time it is grouted. If rewetting in the forms is required, a 3Effect
fog spray may be applied sparingly to dampen the upper 0.3 3.1Name
m (1 ft) or so. If the entire mass of aggregate needs re-wet- 3.1.1Description
ting, the forms should be inundated with water from the bot- 3.1.2Photographs
tom, then drained off slowly. Large quantities of water 4Causes
applied to the top of the aggregate will wash fines to the bot- 4.1Design of member
tom, resulting in a poor surface or honeycomb. 4.1.1Reinforcement (spacing and size)
Light vibration of forms with external vibrators permit the 4.1.2Width, depth
grout to cover the points of coarse aggregate in contact with 4.1.3Configuration
the form. Overvibration of the form should be avoided, how- 4.2Forms
ever, as it will induce bleeding that may result in sand streak- 4.2.1Method
ing. Some trial and error may be required to determine the 4.2.2Shape
optimum amount of form vibration. Form design must be in 4.2.3Anchorage
conformance with increased pressure. Bolted connections in 4.2.4Insulation
formwork require lock washers or double nutting. Formwork 4.2.5Material type, new or used
under external vibration requires positive attachment to foot- 4.2.6Form coatings
ing or previous placement. 4.2.7Texture and finish
Where the appearance of formed surfaces is important, a 4.2.8Tightness
test section of comparable height should be produced, the 4.2.9Structural adequacy
surface examined, and adjustments made to grading, placing, 4.3Construction conditions
and consolidation procedures adjusted to obtain an accept- 4.3.1Temperature
able result. 4.3.2Wind
4.3.3Humidity
CHAPTER 6CONCLUSION 4.3.4Precipitation
Faulty design and construction practices can result in 4.3.5Placing accessibility
blemishes in formed concrete surfaces. To keep these effects 4.3.6Precautions, covered in 4.5
within tolerable limits, an awareness of their causes and their 4.4Properties of fresh concrete
cures is essential. The causes of these effects may lie in 4.4.1Proportions
initial design concepts, specification, materials selection, 4.4.2Workability
CONSOLIDATION-RELATED SURFACE EFFECTS 309.2R-11

4.4.3Grading of aggregate Building Research Studies and Documentation, Rotterdam, 8 pp.


4.4.4Slump Mather, B., 1987, The Warmer the Concrete the Faster the Cement
Hardens, Concrete International, V. 9, No. 8, Aug., pp. 29-33.
4.4.5Nominal maximum size aggregate
4.4.6Cohesiveness Reading, T. J., 1972, The Bug Hole Problem, ACI JOURNAL, Proceed-
ings V. 69, No. 3, Mar., pp. 165-177.
4.4.7Air content
Samuelson, P., 1970, Voids in Concrete Surfaces, ACI JOURNAL, Pro-
4.4.8Time of setting ceedings V. 67, No. 22, Nov., pp. 868-874.
4.5Placement Shilstone, J. M., 1977, Surface Blemishes in Formed Concrete, Pro-
4.5.1Rate ceedings, RILEM/ASTM/CIB Symposium on Performance Evaluation of
4.5.2Conditions External Vertical Surfaces of Buildings (Otaniemi, Espoo, Aug.-Sept.),
4.5.3Adequacy of equipment Technical Research Centre of Finland, Espoo, Finland, pp. 3-7.
4.6Consolidation Stamenkovic, H., 1973, Surface Voids Can Be Controlled, Concrete
Construction, V. 18, No. 12, Dec., pp. 597-598, 600.
4.6.1Frequency
4.6.2Amplitude
4.6.3Physical size 8.3Bibliography
4.6.4Schedule of insertions Fiorato, A. E., 1973, Geometric Imperfections in Concrete Structures (A
Literature Survey), National Swedish Institute for Building Research,
4.6.5Number of vibrators Stockholm, Sweden.
4.6.6Depth of penetration Harding, M. A., 1995, Vibrating Concrete in Wall Forms, Concrete
4.6.7Length of vibration Construction, V. 40, No. 2, Feb., pp. 180-184.
Harrell, T. R., and Goswick, G. M., 1987, Tunnel ConcreteConsoli-
CHAPTER 8REFERENCES dation Achieved by a Harmonic Blend of Internal and External Vibration,
8.1Recommended references Consolidation of Concrete, SP-96, American Concrete Institute, Farming-
The documents of the various standards-producing orga- ton Hills, Mich., pp. 102-118.
nizations referred to in this report are listed below with their Holland, T. C.; Husbands, T. B.; Buck, A. D.; and Wong, G. S., 1980,
serial designation. Concrete Deterioration in Spillway Warm-Water Chute, Raystown Dam.
Pennsylvania (Final Report), U. S. Army Engineer Waterways Experiment
American Concrete Institute Station, Vicksburg, Miss., Structures Lab. WES/MP/SL-80-19; CTIAC-42,
55 pp.
ACI 116R Cement and Concrete Terminology
Houston, B. J., 1967, Methods of Reducing the Size and Number of Voids
ACI 303R Guide to Cast-In-Place Architectural Con- on Formed Concrete Surfaces, Report No. TR 6-788, U. S. Army Engineer
crete Practice Waterways Experiment Station, Vicksburg, Miss., 36 pp.
ACI 304.1R Guide for the Use of Prepackaged-Aggre- Hurd, M. K., 1993, Patterned Form Liners for Architectural Concrete,
gate Concrete for Structural and Mass Concrete Construction, V. 38, No. 5, May 5, 5 pp.
Concrete Applications Kennedy, T. B., 1960, Investigation of Methods of Finishing Formed
ACI 309R Guide for Consolidation of Concrete Concrete Surfaces, Report No. TR 6-559, U.S. Army Engineer Waterways
ACI 309.1R Behavior of Fresh Concrete During Vi- Experimental Station, Vicksburg, Miss., 19 pp.
bration Kenney, A. R., 1984, Problems and Surface Blemishes in Architectural
Cast-in-Place Concrete, Concrete International, V. 6, No. 1, Jan., pp. 50-55.
ACI 347R Guide to Formwork for Concrete
Kenney, A. R., and Kenney, B. P., 1986, Problems and Repairs in Tilt-
American Society for Testing and Materials Up Construction, Concrete International, V. 8, No. 6, Jun., pp. 41-50.
ASTM C 33 Specification for Concrete Aggregates King, J. C., 1971, Special Concretes and Mortars, Handbook of Heavy
Construction, 2nd Edition, McGraw-Hill Book Co., New York, pp. 22-1 to
The above publications may be obtained from: 22-17.
Mass, G. R., 1987, Consolidation of Concrete, Lewis H. Tuthill Inter-
American Concrete Institute national Symposium on Concrete and Concrete Construction, SP-104,
P.O. Box 9094 Gant T. Halvorsen, ed., American Concrete Institute, Farmington Hills,
Farmington Hills, MI 48333-9094 Mich., pp. 185-204.
Reading, T. J., 1985, Deleterious Affects of Wood Forms on Concrete
American Society for Testing and Materials Surfaces, Concrete International, V. 7, No. 11, Nov., pp. 57-62.
100 Barr Harbor Drive Sansalone, M., and Carino, N. J., 1988, Impact-Echo Method: Detecting
Honeycombing, Depth of Surface-Opening Cracks, and Ungrouted Ducts
West Conshohocken, PA 19428-2959 (Final Report), Concrete International, V. 10, No. 4, Apr., pp. 38-46.
Shilstone, J. M., 1979, Surface Blemishes in Formed Concrete, Con-
8.2Cited references crete Construction, V. 24, No. 11, Nov., pp. 719 and 765.
Backstrom, J. E.; Burrows, R. W.; Mielenz, R. C.; and Wolkodorff, V.
E., 1958, Origin, Evolution and Effects of the Air Void System in Con- Smith, John R., 1984, Architectural Concrete: Defects Demand Discre-
crete, Part 3Influence of Water-Cement Ratio and Compaction, ACI tion, Concrete International, V. 6 No. 1, Jan., pp. 64-66.
JOURNAL, Proceedings V. 55, Sept., pp. 359-375. Watanaba, T., and Uomoto, T., 1993, Monitoring Concrete Placing by
International Council for Building Research, 1975, Tolerances on Infrared Image Analysis, Doboku Gakkai Rombun-Hokokushu/Proceed-
Blemishes of Concrete, CIB Report No. 24, International Council for ings of the Japan Society of Civil Engineers, No. 478, Part 50-21, pp. 55-59.

You might also like