PDOC-476-CTRU-06 Rotating Equipment Installation Procedure
PDOC-476-CTRU-06 Rotating Equipment Installation Procedure
PDOC-476-CTRU-06 Rotating Equipment Installation Procedure
PETRODAR OPERATING
COMPANY LIMITED
Contractor
CHINA PETROLEUM
ENGINEERING & CONSTRUCTION DOCUMENT No.:
PDOC/476-CTRU-06
CORPORATION
REVISION RECORD
Submission
Rev. NO. Da Revision Details Prepared By Approved By OWNER
te
A 2007-9-23 Submitted for reviewed Li Yonggang
MELUT BASIN OIL DEVELOPMENT
QA/QC DEPARTMENT PROCEDURE PROJECTGUMRY FIELD
PRODUCTION FACILITIES PROJECT
SUBJECT Rotating Equipment PROCEDURE NO.:
Installation Procedure PDOC/476-CTRU-06
CONTENTS
1.0 Scope
2.0 Reference Documents
3.0 General
4.0 Rotating equipment installation
5.0 Pumps
6.0 Packaged Compressors
7.0 Installation of Crane
8.0 Quality record and review reports
9.0 Revision note
Rev. A 2
MELUT BASIN OIL DEVELOPMENT
QA/QC DEPARTMENT PROCEDURE PROJECTGUMRY FIELD
PRODUCTION FACILITIES PROJECT
SUBJECT Rotating Equipment PROCEDURE NO.:
Installation Procedure PDOC/476-CTRU-06
1.0 Scope
To define and establish procedures for on site handling, movement and installation of
mechanically rotating equipment.
Rev. A 3
MELUT BASIN OIL DEVELOPMENT
QA/QC DEPARTMENT PROCEDURE PROJECTGUMRY FIELD
PRODUCTION FACILITIES PROJECT
SUBJECT Rotating Equipment PROCEDURE NO.:
Installation Procedure PDOC/476-CTRU-06
3.0 General
3.1 Foundations shall be completed and checked for correctness and levelness as per drawings
and specifications. Prior to installation, foundation shall be clean with correct anchor
boltholes location, centerlines marked, elevations and levels established for correctness.
Shimming and wedging shall be carried out as per drawings and specifications.
3.2 As required, perform on-site installation of the various equipments as per approved
construction drawings and specifications, and instruction by a manufacturer/vendor
representative.
3.3 Final insulation jacketing shall be completed so that there will not be an excessive amount
of scaffolding erected in the plant areas where operators will work during start-up. The
number of insulation crews still working in the area shall not be excessive.
3.4 At the time of Mechanical Completion all fire proofing and rough insulation shall be
completed, i.e. all equipment, piping, instruments, instrument leads, etc. requiring
insulation for heat conservation shall be covered so that start-up operations will not be
delayed due to excessive heat loss. Insulation required for personnel protection shall also
be completed. Only areas that would be required to be open for tightness testing (flanges,
valve stems, etc.) will not be covered prior to Mechanical Completion. Exposed
insulation is to be properly protected and sealed.
5.0 Pumps
Rev. A 4
MELUT BASIN OIL DEVELOPMENT
QA/QC DEPARTMENT PROCEDURE PROJECTGUMRY FIELD
PRODUCTION FACILITIES PROJECT
SUBJECT Rotating Equipment PROCEDURE NO.:
Installation Procedure PDOC/476-CTRU-06
Rev. A 5
MELUT BASIN OIL DEVELOPMENT
QA/QC DEPARTMENT PROCEDURE PROJECTGUMRY FIELD
PRODUCTION FACILITIES PROJECT
SUBJECT Rotating Equipment PROCEDURE NO.:
Installation Procedure PDOC/476-CTRU-06
6.10 Check rotation of driver and compressor is correct and rotating freely after the final
tightening of holding down bolts and pipe flange bolts.
6.11 Chemically clean any completed lube and seal oil system, when specified. Dispose of
wastes and cleaning media in accordance with OWNER instructions.
6.12 When specified, the lube oil, control oil and oil cooling systems with flushing oil and
circulate for cleaning purposes. Dispose of any flushing oil in accordance with OWNER
instructions.
6.13 Arrange for pipe work to be finalized to the compressor sets. Support the suction and
discharge pipes independently by the use of proper pipe supports.
6.14 Charge the lube oil, control oil and oil-cooling systems with the operating oil
recommended by manufacturer in accordance with OWNER specifications.
6.15 Operate the auto-changeover of the oil coolers and oil filters to ensure that it is operating
correctly.
6.16 Install the compressor casing drains and vents as per approved drawings and
specifications.
6.17 Check that machinery guards are available and fitted as per drawings and vendors
recommendations.
6.18 Check that all safety devices and controls are functioning properly as per drawings and
vendors recommendations.
6.19 Install other auxiliary equipment as per drawings and vendors recommendations.
6.20 Rotate compressor and driver periodically after installation as per vendor
recommendations and recorded on the appropriate form.
6.21 Perform all the tests as specified in the relevant data sheets and specifications.
Rev. A 6
MELUT BASIN OIL DEVELOPMENT
QA/QC DEPARTMENT PROCEDURE PROJECTGUMRY FIELD
PRODUCTION FACILITIES PROJECT
SUBJECT Rotating Equipment PROCEDURE NO.:
Installation Procedure PDOC/476-CTRU-06
Rev. A 7