Quotation: 5/31/2017 OKI Mill Plant MEI Installation Work Package #1 & #4 Recovery Boiler & Fiber Line

The document is a quotation from PT. Truba Jaya Engineering for additional work at the OKI Mill Plant, including making filter devices. It details manpower and equipment costs for tasks like dismantling pumps and includes signatures from supervisors approving the work.

Uploaded by

Indra Harapan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
64 views27 pages

Quotation: 5/31/2017 OKI Mill Plant MEI Installation Work Package #1 & #4 Recovery Boiler & Fiber Line

The document is a quotation from PT. Truba Jaya Engineering for additional work at the OKI Mill Plant, including making filter devices. It details manpower and equipment costs for tasks like dismantling pumps and includes signatures from supervisors approving the work.

Uploaded by

Indra Harapan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 27

PT.

TRUBA JAYA ENGINEERING DATE 5/31/201


OKI Mill Plant MEI Installation Work Package #1 & #4
Recovery Boiler & Fiber Line

QUOTATION
TIME SHEET AND ACTIVITIES REPORT ADDITIONAL WORK

Name of Additional Work Filter Sand Device Dynasand WTP#3

Ref. No

WORK'S DESCRIPTION :
Making a Device for Filtering Small stone with a sands at Dynasand WTP#3

Qty Hour Days Total (Manhour)


No Description
(F) (G) (H) (F) x (G) x (H)

A Manpower
1. Engineer 1 2 -
2. Supervisor 1 2 -
3. Fitter Mechanical 3 2 -

Sub Total A
B Tools & Equipment
1. Welding Engine 1 Set
2. Grinding Machine 2 Ea
3. Measuring Tape 1 Ea

Sub Total B
D Consummable Qty Unit
1. Oxygen 1 Ea
2. Aceteylene 1 Ea
3. Cutting Wheel 7" cs 7 Ea
4. Cutting Wheel 4" cs 4 Ea

Sub Total C
E Others Qty Unit
1.

2.
Sub Total D
Total A+B+C+D

Submited By : Approved By :
PT. TRUBA JAYA ENGINEERING PT. OKI PULP & MILL

...................................... ......................................
Eng / Sptd / SM PT. OKI Representati
5/31/2017

OTATION
VITIES REPORT ADDITIONAL WORK

Remarks
PT. OKI PULP & MILL PLANT

......................................
PT. OKI Representative
PT. TRUBA JAYA ENGINEERING DATE 5/31/201
OKI Mill Plant MEI Installation Work Package #1 & #4
Recovery Boiler & Fiber Line

QUOTATION
TIME SHEET AND ACTIVITIES REPORT ADDITIONAL WORK

Name of Additional Work Filter Sewage Device at Sludge Lift Regulating Tank

Ref. No

WORK'S DESCRIPTION :
Making a Device for Filtering Small stone with a sands at Dynasand WTP#3

Qty Hour Days Total (Manhour)


No Description
(F) (G) (H) (F) x (G) x (H)

A Manpower
1. Engineer 1 4 -
2. Supervisor 1 4 -
3. Fitter Mechanical 3 4 -

Sub Total A
B Tools & Equipment
1. Grinding Machine 1 Set
2. Drill Machine 2 Ea

Sub Total B
D Consummable Qty Unit
1. Cutting Wheel 7" cs 10 Ea
2. Cutting Wheel 4" cs 5 Ea
3. Drill bit 12 6 Ea

Sub Total C
E Others Qty Unit
1.

2.
Sub Total D
Total A+B+C+D

Submited By : Approved By :
PT. TRUBA JAYA ENGINEERING PT. OKI PULP & MILL

...................................... ......................................
Eng / Sptd / SM PT. OKI Representati
5/31/2017

OTATION
VITIES REPORT ADDITIONAL WORK

Remarks
PT. OKI PULP & MILL PLANT

......................................
PT. OKI Representative
DAY Thursday
DATE 5/25/2017
SUPERVISOR Darmono

TIME SHEET AND ACTVITIES REPORT


WTP#3
MORNING SHIFT
No Badge No. Name Classification REMARKED
IN SIGN OUT SIGN

1 6855 Nalwan Hadi Fitter 1 09.00 17.00

2 7070 Domi Ferdiyan Fitter 2 09.00 17.00

3 6862 Syukron Ma'mun Scaffolder 09.00 17.00

4 6864 Abdullah Scaffolder 10.00 17.00

5 6854 Hermansyah Scaffolder 10.00 17.00

10

11

12

13

14

15

16

17

18

19

20

NO. JOB DESCRIPTION REMARKED


1 Dissmantle Coupling and Impeller Pump 17133-U2036 at Water Supply Pump Room

NO. TOOL USAGE QTY UNIT HANDLING UNIT PT. TRUBA JAYA ENGINEERING
SUPERVISOR SUPERINTENDEMT CONTRUCTION MANAGER

NAME : NAME : NAME :


DATE : DATE : DATE :

HANDLING UNIT PT. OKI PULP & PAPER

NAME : NAME : NAME :


DATE : DATE : DATE :
AREA
PT. TRUBA JAYA ENGINEERING
01 RECOVERY BOILER
Client : OKI PULP & PAPER
Client : PT. OKI PULP & PAPER 02 FIBER LINE
Job No. : T-5108
Project Name : OKI MILL PLANT MEI INSTALLATION RB & FL
Location : SEI BAUNG - PALEMBANG - SUMSEL
Day and Date :
Supervisor WBS Holder
Sign : Sign :

Badge No : Badge No :
Name : DARMONO Name : M UDIN
DAILY TIME SHEET REPORT

No Badge No. Name Classification In Out Ba

1 6833 Bambang Swidal Fitter 1

2 3343 Angga Fitter 3

3 6855 Nalwan Hadi Fitter 1

4 6856 Suparman Fitter 3

5 6857 Jafar Sidik Fitter 3

6 7070 Domi Ferdiyan Fitter 2

7 7251 Adi Muzaid Fitter 2


PROGRESS REPORT *)

No. Drawing No Description Material No. Received Open Case Mate


Material
1
2
3
4
5
6
Note : Equipment
Remarks Code : No. Name Capacity
L : Annual Leave, S : Sick, P : Permition, A : Absent 1
Loss Time Code : 2
01:Weither, 02:Waiting For Permit, 03:Waiting For 3
Equipment, 04:Waiting For Consumable, 05:Lack Of 4
Material, 06:Lack Of Consumable, 07:Reworks, 08: 5
Tool Box Meeting, 09:Travel To Site, 10:Wait For Other 6
*) Bila tidak muat dalam pengisian progress, gunakan form tambahan 7
8
AREA WBS : T5108 (X) 22AG
RECOVERY BOILER A B C D E F G H I J K

FIBER LINE N O P Q R S T U V W X

General Activities

ME SHEET REPORT

Basic Over Time Lost Time Total Actual Sign. Remarks


RESS REPORT *)
Quantity
Lifting Up on Fit Up Welding/ Inspect/Test Unit
Material On Site Base Install Alignment /NDE/PWHT

Equipment Main Consumable & Tools


Capacity Hours Consum & Tools Name Quantity Unit
PT. TRUBA JAYA ENGINEERING DATE
OKI Mill Plant MEI Installation Work Package #1 & #4
Recovery Boiler & Fiber Line

QUOTATION
TIME SHEET AND ACTIVITIES REPORT ADDITIONAL WORK

Name of Additional Work Assist Man Power Commisioning

Ref. No

WORK'S DESCRIPTION :
Assist Commisioning/Water Run Fiberline#1 As Per OKI requirement For Night Shift

Qty Hour Days Total (Manhour)


No Description Remarks
(F) (G) (H) (F) x (G) x (H)

A Manpower
1. Supervisor 1 1 -
2. Foreman 3 1 -
3. Pipe Fitter 13 1 -
4. Scafolder/Rigger 3 1 -
5. Welder 1 1 -

Sub Total A
B Tools & Equipment
1. Wrench 20,24,30,32,36,41,46,50,55,60,70,75 3 Set
2. Hummer 6 Ea
3. Adjustabel Wrench 18" 2 Ea
4. Welding Machine 1 Unit
5. Grinding Machine 4" 1 Ea

Sub Total B
D Consummable Qty Unit
1.
2.

Sub Total C
E Others Qty Unit
1.

2.

Sub Total D
Total A+B+C+D

Submited By : Approved By :
PT. TRUBA JAYA ENGINEERING PT. OKI PULP & MILL PLANT

...................................... ......................................
Eng / Sptd / SM PT. OKI Representative
DAY
DATE
SUPERVISOR SUDAYONO

TIME SHEET AND ACTVITIES REPORT


PRE COMMISIONING FL#1 & FL#2
NIGHT SHIFT
No Badge No. Name Classification REMARKED
IN SIGN OUT SIGN

1 6833 Bambang Swidal Fitter 1 19:00 7:00

2 3343 Angga Fitter 3 19:00 7:00

3 6855 Nalwan Hadi Fitter 1 19:00 7:00

4 6856 Suparman Fitter 3 19:00 7:00

5 6857 Jafar Sidik Fitter 3 19:00 7:00

6 7070 Domi Ferdiyan Fitter 2 19:00 7:00

7 7251 Adi Muzaid Fitter 2 19:00 7:00

8 4273 Slamet W Welder 19:00 7:00

9 3343 Darius Welder 19:00 7:00

10 2398 Ihsan Welder 19:00 7:00

11 1221 Mauludin Fitter 1 19:00 7:00

12 2546 Indra Gunadi Fitter 2 19:00 7:00

13 5120 Aidil Fitri Fitter 3 19:00 7:00

14 7382 Rusliyadi Sapura Fitter 19:00 7:00

15 7329 Moh Thoifin Fitter 19:00 7:00

16 5929 Johan Saputra Fitter 19:00 7:00

NO. JOB DESCRIPTION REMARKED

NO. TOOL USAGE QTY UNIT HANDLING UNIT PT. TRUBA JAYA ENGINEERING
SUPERVISOR SUPERINTENDEMT CONTRUCTION MANAGER

NAME : NAME : NAME :


DATE : DATE : DATE :

HANDLING UNIT PT. OKI PULP & PAPER

NAME : NAME : NAME :


DATE : DATE : DATE :
AREA
PT. TRUBA JAYA ENGINEERING
01 RECOVERY BOILER
Client : OKI PULP & PAPER
Client : PT. OKI PULP & PAPER 02 FIBER LINE
Job No. : T-5108
Project Name : OKI MILL PLANT MEI INSTALLATION RB & FL
Location : SEI BAUNG - PALEMBANG - SUMSEL
Day and Date :
Supervisor WBS Holder
Sign : Sign :

Badge No : Badge No :
Name : SUDAYONO Name : SUPROBO
DAILY TIME SHEET REPORT

No Badge No. Name Classification In Out Ba

1 5144 WAHYU ARYADI P SKILL FITTER 2

2 5145 ARSEDI IRAWAN SKILL FITTER 2

3 5147 UJANG FOREMAN

4 5149 ANDIKA SKILL FITTER 1

5 5165 KODIRIN UMAR BIN D SKILL FITTER 2

6 5456 ALI YUSNI FOREMAN

7 5465 MIKTISEN SKILL FITTER 3

8 6191 FAUZAN SKILL FITTER 1

9 7455 RIO SELI CHECKER 3

10 7458 EDI SIDIK SKILL FITTER 3

11 7382 RUSLIYADI SAPUTRA SEMI SKILL FITTER

12 7384 WISNU NARO SIMA SKILL FITTER

13 7385 NURHADI SKILL FITTER 1

14 7386 SLAMET SETYO UTOMO FOREMAN

15 2589 RELI PURWADI PIPE FITTER 3


16 3279 HAMAM AZRUL PIPE FITTER 3

17 6128 TAUFIK L/H SCAFFOLDER

18 4813 DWI TEGUH PANUNTUN SCAFOLDER 1

19 7434 RANO SEMI SKILL SCAFOLDER

20 5472 AHMAD NUR HIDAYAT WELDER

PROGRESS REPORT *)

No. Drawing No Description Material No. Received Open Case Mate


Material
1
2
3
4
5
6
Note : Equipment
Remarks Code : No. Name Capacity
L : Annual Leave, S : Sick, P : Permition, A : Absent 1
Loss Time Code : 2
01:Weither, 02:Waiting For Permit, 03:Waiting For 3
Equipment, 04:Waiting For Consumable, 05:Lack Of 4
Material, 06:Lack Of Consumable, 07:Reworks, 08: 5
Tool Box Meeting, 09:Travel To Site, 10:Wait For Other 6
*) Bila tidak muat dalam pengisian progress, gunakan form tambahan 7
8
AREA WBS : T5108 (X) 22AG
RECOVERY BOILER A B C D E F G H I J K

FIBER LINE N O P Q R S T U V W X

General Activities

ME SHEET REPORT

Basic Over Time Lost Time Total Actual Sign. Remarks


RESS REPORT *)
Quantity
Lifting Up on Fit Up Welding/ Inspect/Test Unit
Material On Site Base Install Alignment /NDE/PWHT

Equipment Main Consumable & Tools


Capacity Hours Consum & Tools Name Quantity Unit
DAY Saturday
DATE 5/9/2017
SUPERVISOR Darmono

TIME SHEET AND ACTVITIES REPORT


WTP#3
MORNING SHIFT
No Badge No. Name Classification REMARKED
IN SIGN OUT SIGN

1 6833 Bambang Swidal Fitter 1 19.00 00.00


5

2 3343 Angga Fitter 3 19.00 21.00


2

3 6855 Nalwan Hadi Fitter 1 19.00 21.00


2

4 6856 Suparman Fitter 3 19.00 00.00


5

5 6857 Jafar Sidik Fitter 3 19.00 00.00


5

6 7070 Domi Ferdiyan Fitter 2 19.00 00.00


5

7 7251 Adi Muzaid Fitter 2 19.00 21.00


2

8 4273 Slamet W Welder 19.00 22.00


2

9 3343 Darius Welder 19.00 22.00


2

10 2398 Ihsan Welder 19.00 22.00


2

NO. JOB DESCRIPTION REMARKED


1 Cutting Pipe DN 900 17133-1002-WM-900-10H1A
2 Fabricated Pipe DN 900 Dynasand Bypass WTP#3

NO. TOOL USAGE QTY UNIT HANDLING UNIT PT. TRUBA JAYA ENGINEERING
SUPERVISOR SUPERINTENDEMT CONTRUCTION MANAGER

NAME : NAME : NAME :


DATE : DATE : DATE :

HANDLING UNIT PT. OKI PULP & PAPER

NAME : NAME : NAME :


DATE : DATE : DATE :
DAY Saturday
DATE 5/10/2017
SUPERVISOR Darmono

TIME SHEET AND ACTVITIES REPORT


WTP#3
MORNING SHIFT
No Badge No. Name Classification REMARKED
IN SIGN OUT SIGN

1 3343 Angga Fitter 3 07.00 21.00


12

2 6855 Nalwan Hadi Fitter 1 07.00 21.00


12

3 6856 Suparman Fitter 3 07.00 21.00


12

4 6857 Jafar Sidik Fitter 3 07.00 21.00


12

5 7070 Domi Ferdiyan Fitter 2 07.00 21.00


12

6 7251 Adi Muzaid Fitter 2 07.00 21.00


12

7 4273 Slamet W Welder 07.00 21.00


12

8 3343 Darius Welder 07.00 21.00


12

9 2398 Ihsan Welder 07.00 21.00


12

NO. JOB DESCRIPTION REMARKED


1 Install Collar DN 600 and weldneck DN 900
2 Fabricated Primer & Secondary Support Pipe DN 900 Dynasand Bypass WTP#3
3 Continue Fabricated Line Pipe for tie in to 17133-1003-wm-800-10H1A

NO. TOOL USAGE QTY UNIT HANDLING UNIT PT. TRUBA JAYA ENGINEERING
SUPERVISOR SUPERINTENDEMT CONTRUCTION MANAGER

NAME : NAME : NAME :


DATE : DATE : DATE :

HANDLING UNIT PT. OKI PULP & PAPER

NAME : NAME : NAME :


DATE : DATE : DATE :
DAY Saturday
DATE 5/11/2017
SUPERVISOR Darmono

TIME SHEET AND ACTVITIES REPORT


WTP#3
MORNING SHIFT
No Badge No. Name Classification REMARKED
IN SIGN OUT SIGN

1 3343 Angga Fitter 3 07.00 18.00


10

2 6855 Nalwan Hadi Fitter 1 07.00 18.00


10

3 6856 Suparman Fitter 3 07.00 21.00


10

4 6857 Jafar Sidik Fitter 3 07.00 21.00


10

5 7070 Domi Ferdiyan Fitter 2 07.00 18.00


10

6 7251 Adi Muzaid Fitter 2 07.00 18.00


10

7 4273 Slamet W Welder 07.00 18.00


10

8 3343 Darius Welder 07.00 18.00


10

9 2398 Ihsan Welder 07.00 21.00


10

NO. JOB DESCRIPTION REMARKED


1 Welding Reinforce Plate DN 1000/900
2 Install Dynabolt & Welding Secondary primer Support for Pipe DN 900

NO. TOOL USAGE QTY UNIT HANDLING UNIT PT. TRUBA JAYA ENGINEERING
SUPERVISOR SUPERINTENDEMT CONTRUCTION MANAGER

NAME : NAME : NAME :


DATE : DATE : DATE :

HANDLING UNIT PT. OKI PULP & PAPER

NAME : NAME : NAME :


DATE : DATE : DATE :
DAY Saturday
DATE 5/12/2017
SUPERVISOR Darmono

TIME SHEET AND ACTVITIES REPORT


WTP#3
MORNING SHIFT
No Badge No. Name Classification REMARKED
IN SIGN OUT SIGN

1 3343 Angga Fitter 3 07.00 18.00


10

2 6856 Suparman Fitter 3 07.00 21.00


12

3 6857 Jafar Sidik Fitter 3 07.00 21.00


12

4 3343 Darius Welder 07.00 18.00


10

5 2398 Ihsan Welder 07.00 21.00


12

NO. JOB DESCRIPTION REMARKED


1 Continue Welding Reinforce Plate DN 1000/900
2 Continue Install Dynabolt & Welding Secondary primer Support for Pipe DN 900

NO. TOOL USAGE QTY UNIT HANDLING UNIT PT. TRUBA JAYA ENGINEERING
SUPERVISOR SUPERINTENDEMT CONTRUCTION MANAGER

NAME : NAME : NAME :


DATE : DATE : DATE :

HANDLING UNIT PT. OKI PULP & PAPER

NAME : NAME : NAME :


DATE : DATE : DATE :
DAY Saturday
DATE 5/12/2017
SUPERVISOR Darmono

TIME SHEET AND ACTVITIES REPORT


WTP#3
MORNING SHIFT
No Badge No. Name Classification REMARKED
IN SIGN OUT SIGN

1 6833 Bambang Swidal Fitter 1 09.00 18.00

2 6855 Nalwan Hadi Fitter 1 09.00 18.00

3 7070 Domi Ferdiyan Fitter 2 09.00 18.00

4 7251 Adi Muzaid Fitter 2 09.00 18.00

5 5572 Aidil Fitter 2 09.00 18.00

NO. JOB DESCRIPTION REMARKED


1 Cutting DN 300 Pipe 17133-1032-WM-300-10H2A (5 Pcs) to disconect with the wall
2 Assist oki team to Moving Pipe Header DN 800 17133-1004-WM-800-10H1A

NO. TOOL USAGE QTY UNIT HANDLING UNIT PT. TRUBA JAYA ENGINEERING
SUPERVISOR SUPERINTENDEMT CONTRUCTION MANAGER

NAME : NAME : NAME :


DATE : DATE : DATE :

HANDLING UNIT PT. OKI PULP & PAPER

NAME : NAME : NAME :


DATE : DATE : DATE :
DAY Saturday
DATE 5/4/2017
SUPERVISOR Darmono

TIME SHEET AND ACTVITIES REPORT


WTP#3
MORNING SHIFT
No Badge No. Name Classification REMARKED
IN SIGN OUT SIGN

1 6833 Bambang Swidal Fitter 1 07.00 18.00

2 6855 Nalwan Hadi Fitter 1 07.00 18.00

3 7070 Domi Ferdiyan Fitter 2 07.00 18.00

4 7251 Adi Muzaid Fitter 2 07.00 18.00

5 6857 Jafar Sidik Fitter 3 07.00 18.00

NO. JOB DESCRIPTION REMARKED


1 Cutting DN 1000 Pipe 17133-1003-WM-800-10H2A
2 Remove Existing Pipe & Elbow DN1000

NO. TOOL USAGE QTY UNIT HANDLING UNIT PT. TRUBA JAYA ENGINEERING
SUPERVISOR SUPERINTENDEMT CONTRUCTION MANAGER

NAME : NAME : NAME :


DATE : DATE : DATE :

HANDLING UNIT PT. OKI PULP & PAPER

NAME : NAME : NAME :


DATE : DATE : DATE :
DAY Saturday
DATE 5/8/2017
SUPERVISOR Darmono

TIME SHEET AND ACTVITIES REPORT


WTP#3
MORNING SHIFT
No Badge No. Name Classification REMARKED
IN SIGN OUT SIGN

1 6833 Bambang Swidal Fitter 1 07.00 18.00

2 6855 Nalwan Hadi Fitter 1 07.00 18.00

3 7070 Domi Ferdiyan Fitter 2 07.00 18.00

4 7251 Adi Muzaid Fitter 2 07.00 18.00

5 6857 Jafar Sidik Fitter 3 07.00 18.00

NO. JOB DESCRIPTION REMARKED


1 Beveling Pipe DN 1000 17133-1003-WM-800-10H2A
2 Continue Remove Existing Pipe & Elbow DN1000

NO. TOOL USAGE QTY UNIT HANDLING UNIT PT. TRUBA JAYA ENGINEERING
SUPERVISOR SUPERINTENDEMT CONTRUCTION MANAGER

NAME : NAME : NAME :


DATE : DATE : DATE :

HANDLING UNIT PT. OKI PULP & PAPER

NAME : NAME : NAME :


DATE : DATE : DATE :
DAY Saturday
DATE 5/8/2017
SUPERVISOR Darmono

TIME SHEET AND ACTVITIES REPORT


WTP#3
MORNING SHIFT
No Badge No. Name Classification REMARKED
IN SIGN OUT SIGN

1 7261 Rionald A.P Fitter 2 07.00 21.00

2 6854 Hermansyah Fitter 1 07.00 21.00

3 6862 Syukron Ma'mun Semi Skill 07.00 21.00

4 6864 Abdullah Fitter 3 07.00 21.00

5 3343 Jonele Welder 07.00 21.00

NO. JOB DESCRIPTION REMARKED


1 Fabricated Reinforce Bracing H-Beam 100 (10 Pcs) to Support the manganese wall
2 Welding Reinforce Bracing H-Beam

NO. TOOL USAGE QTY UNIT HANDLING UNIT PT. TRUBA JAYA ENGINEERING
SUPERVISOR SUPERINTENDEMT CONTRUCTION MANAGER

NAME : NAME : NAME :


DATE : DATE : DATE :

HANDLING UNIT PT. OKI PULP & PAPER

NAME : NAME : NAME :


DATE : DATE : DATE :