Production Planning Control
Production Planning Control
co m
.
3. (a) List and explain the different costs of inventory system.
ld
(b) The annual demand for an item is 36,000 units. The carrying cost is Rs.0.50
per unit
o r
per unit per year. Ordering cost is Rs.25 per order, and the shortage cost is RS.15
tu w
per year. Find the optimal values of:
EOQ, Maximum shortage quantity, Cycle time.
. j n
4. (a) Briefly explain the purpose and concept of Line of Balance.
(b) What does the bill of materials structure mean? Explain by an example.
w w
5. (a) Define the functions of Routing. Explain the concept of Route sheet.
(b) Describe the different types of scheduling.
w 6. (a) Distinguish between single machine scheduling and flow shop scheduling.
(b) Use graphical method to minimize the time needed to process the following
jobs on the machines shown (for each machine, find the job which is to be
scheduled first).
Also calculate the total elapsed time to complete the jobs.
Job 1 Sequence A B C D E
Time (Hrs) 2 6 5 4 7
Job 2 Sequence C B D A E
Time (Hrs) 6 5 7 4 8
SET- 1
Code No: 2420305
7 (a) Distinguish between the Rank Positional Weight and COMSOAL algorithm for
Assembly Line Balancing.
(b) Describe the different aggregate planning strategies.
co m
ld .
o r
tu w
. j n
w w
w
SET- 2
Code No: 2420305
IV B. Tech II Semester Regular Examinations, April/May 2009
PRODUCTION PLANNING & CONTROL
( Mechanical Engineering )
Time: 3 Hours Max. Marks 80
Answer any FIVE questions
All questions carry equal marks
********
1. (a) Describe the elements of Production Control.
(b) Explain the various functions of Production Planning and Control.
2. The following table represents the sales data (in hundreds of units) for an item:
1 2 3 4 5 6 7 8 9 10 11 12
Month
Sales 96 106 92 114 108 98 99 115
co
106 m 91 102 99
ld .
initial forecast of 100.00
o r
(a) Use single exponential smoothing to forecast demand with α of 0.20 and an
tu w
(b) Use trend adjusted exponential smoothing to forecast sales through period 13 for
the following data. Use an α of 0.30, a β of 0.50, an initial base of 29.0 and a
trend of 1.0
. j n
3. (a) What is ABC analysis? Explain by an example.
w w
(b) The annual demand of a product is 48,000 units. The average lead time is 3 weeks.
The standard deviation of demand during the average lead time is 100 units/week.
w
The ordering cost is Rs.500 per order. The cost of purchase of the product per unit
is Rs.15. The cost of carrying per unit per year is 20% of the purchase price. The
maximum delay in lead time is 2 weeks and the probability of this delay is 0.30.
Assume a service level of 0.90. If P system is followed, find the reorder level.
4. The master production schedule to manufacture a certain item is shown in Table 1
below. The details of Bill of Materials along with EOQ and stock on hand for the
final product and sub assemblies are shown in Table 2. Complete the Materials
Requirement Plan for the different parts of the item shown in Table 2, and find
what quantities of orders must be released, and when they should be released in
order to satisfy the MPS.
SET- 2
Code No: 2420305
co m 350
Valve Assemblies
Valve
400
350
1
1
1
1
ld . 325
150
Valve Housing
Handle Bars
450
700
1
2
o r 1
1
350
650
tu w
n
5. (a) What are the factors affecting the Routing procedure? Explain.
. j
(b) Differentiate between Loading and Scheduling with suitable examples.
w
w w
6. (a) Discuss the use of Gantt Chart for scheduling purposes.
(b) Eight jobs are to be processed on three machines A,B, and C in the same order
ABCand the processing times (in hours) required for the jobs on the machines are
shown
below. Find the job sequence that minimizes the total processing time for all jobs.
Job A B C D E F G H
A 4 8 5 9 3 4 9 6
B 6 4 7 1 4 2 5 2
C 8 7 9 7 9 8 9 7
SET- 2
Code No: 2420305
7. (a) A line balancing analysis resulted in a precedence grouping as shown in the Table
below. Find the balance efficiency, assuming the longest actual time is the cycle
time.
Work centre Activity Numbers Actual Time (Min)
A 1,2 1.2
B 3,5,6 1.4
C 4,7 0.9
D 8,10,11 1.3
E 9 1.5
co m
ld .
(b) What are the merits and demerits of the Transportation problem of method of
aggregate planning?
o r
tu w
8. (a) What is dispatching and what is the function of the dispatch list?
(b) Write a note on the applications of computers in production planning and control.
. j n
w w
w
SET- 3
Code No: 2420305
IV B. Tech II Semester Regular Examinations, April/May 2009
PRODUCTION PLANNING & CONTROL
( Mechanical Engineering )
Time: 3 Hours Max. Marks 80
Answer any FIVE questions
All questions carry equal marks
********
1. (a) Would Operations Planning and Control in service industries be different from PPC
in manufacturing industries? Discuss.
(b) Discuss centralization and decentralization in the context of PPC.
2. (a) Discuss the general principles of forecasting.
(b) A company used a 9-month moving average forecasting method to predict the
co m
inventory requirements of an item. The actual demand for the item is shown in the
.
table below. Using the previous moving average data, convert to an exponential
ld
smoothing forecast for month 10.
Month
Demand 78
1 2
65
3
90
4
71
5
80
o
6
r
101
7
84
8
60
9
73
tu w
3. (a) Distinguish between ABC analysis and VED analysis.
. j n
(b) Distinguish between the P and Q systems of inventory.
w
4. (a) Given the forecast requirements for end item Y shown in the table below, complete
the Material Requirements Plan. Note that a scheduled receipt of 60 units is due in
m
1 2 3 4 5 6 7
co
Activity X 5 7 2 1 8 3 16
Activity Y 4 9 7 2 2
ld . 9 5
7. Tasks A through I have the predecessor and time requirements as shown in the table
o r
below. The output ia to be 200 units per day, and the operating time is 450 minutes per
w
day. Using the Most Successors rule to assign the tasks to work centres, and the
tu
longest work-time rule as a tie breaker,
. j n
(a) group the tasks into work centres, and
(b) compute the balance efficiency, idle time, and the balance delay.
Task
w
A w Predecessor
None
Time(Sec)
40
w B
C
D
A
None
C
20
60
40
E D 30
F None 35
G F 45
H G 60
I H 40
Total 370
8. (a) What are the types of follow up? Explain.
(b) What is dispatching and what is the function of the dispatch list?
SET- 4
Code No: 2420305
IV B. Tech II Semester Regular Examinations, April/May 2009
PRODUCTION PLANNING & CONTROL
( Mechanical Engineering )
Time: 3 Hours Max. Marks 80
Answer any FIVE questions
All questions carry equal marks
********
1. (a) What are the main types of production systems? Explain.
(b) Write a note on the organization of the PPC department.
2. (a) In what situations, the following forecasting techniques are well suited?
(i) Market Research Technique (ii) Trend line
(b) A food processing company uses a moving average to forecast the next month’s
demand. Past actual demand (in units) is shown in the table below.
co m
.
(i)Compute a simple 5-month moving average to forecast the demand for the
ld
month 52.
o r
(ii)Compute a weighted 3-month moving average, where the weights are highest
for the latest months, and descend in order of 3, 2, 1.
Month 43 44 45
tu
46 w 47 48 49 50 51 52
Actual 105
. j
106
n 110 110 114 121 130 128 137
w
Demand
w w
3. (a) Discuss the various costs involved in the inventory management.
(b) The annual demand of a product is 48,000 units. The average lead time is 3 weeks.
The standard deviation of demand during the average lead time is 100 units/week.
The ordering cost is Rs.500 per order. The cost of purchase of the product per unit
is Rs.15. The cost of carrying per unit per year is 20% of the purchase price. The
maximum delay in lead time is 2 weeks and the probability of this delay is 0.30.
Assume a service level of 0.90. If Q system is followed, find the reorder level.
4. (a) Briefly explain the steps which are followed in a Kanban system.
(b) What is ERP system? What are its benefits?
5. (a) Define Routing and explain the Routing Procedure.
(b) Discuss Loading and Scheduling as an essential part of Production Control.
SET- 4
Code No: 2420305
6. (a) Distinguish between flow shop scheduling and job shop scheduling.
(b) A machine operator has to perform three operations (turning, threading and
knurling) on different jobs. The times required to perform these operations (in
minutes) for each job is shown below. Determine the order in which the jobs are to
be processed in order to minimize the total time required to turn out all the jobs.
Job Time for Turning Time for Threading Time for Knurling
(Min) (Min) (Min)
m
1 3 8 13
co
2 12 6 14
3
4
5
2
4
6
ld . 9
12
5 9 3
o r 8
6 11
tu
1
w 13
. j n
7. (a) What are the merits and demerits of the Transportation problem of method of
w w
aggregate planning?
(b) Distinguish between the Rank Positional Weight and COMSOAL algorithm for