QA
QA
QA
Note : The following comments are guidelines only and are not
instructions from TECHNIP. Descons Method statement for
Underground (Carbon Steel) Piping Construction and
Installation is their full responsibility.
Material Handling
Will the large diameter pipe be fabricated in situ? Suggest:-
For the general large diameter of spools and fittings no shop
prefabrication will be attempted to minimize handling. All spools
will be delivered to place of erection and prepared. Any of pipe
elements or branch connections will be done either next to the
trench in moveable temporary shelters or inside the trench in
situ conditions. Care will be taken to avoid fitting branches to
spiral weld seams and spools will be turned to offer maximum
interference. Where compensation pads fit over spiral seams
same will be ground flush and inspected for any cracks or other
defects prior to fitting pad. T weld connections will be subject to
X-ray inspection to prove compliance.
Note: Clarification is required on where the medium and small
bore pipe will be fabricated / stored.
a) RECEIPT & STORAGE OF PIPE RAW MATERIAL
The piping raw material received from Technip shall
be offloaded in designated lay down yard or Near the
Site where piping will be installed. Specify the
transport.
During offloading, pipes shall not be dropped off the
transport. A crane & nylon slings shall be used to
handle CS pipes & fittings. More details required for
the handling. How to remove the slings, will pipe be
on sandbags for easy removal?
The pipes shall be placed with suitable material in
place to ensure that no damage to pipe or paint
occurs. They shall be adequately supported to
minimize sagging.
The piping end covers shall be kept in place to
prevent foreign particle entry into the pipes.
All material shall come with color-coding as per size,
material & schedule.
The piping material shall be segregated accordingly to
facilitate location of items.
Small-bore pipe fittings, less than 2, shall be stacked
on racks in warehouses. They will be segregated
accordingly to material, size, and rating & by tag
number.
Suggest: A maximum of one week spool requirement
will be stockpiled on site to avoid congestion.
IDENTIFICATION OF SPOOLS
Heat No of Pipe shall be transferred on each cut
length of Pipe spools by Permanent Paint Marker.
Spool identification shall be done by marking spool
no, Isometric No/Line No of Pipe spools with
Permanent Paint marker.
FIT UP
BUT WELDS
The fit up of pipe ends, fittings & weld neck flanges
shall be done to obtain uniform root opening. The
criterion given in related WPS shall be followed.
The primer paint coat on pipes & fitting ends required
to be welded shall be removed. What distances from
the end of the pipe will the paint is removed?
The pipes shall be tack welded by qualified welder with
approved wire /Electrode. Where bridge tacks are
deemed to be required it will be in the form of tack
welded wedge clamps (strong backs) in area requiring
adjusting. After fit up strong backs will be removed, area
ground smooth and MPI carried out to verify integrity of
pipe. It will require conformation from TECHNIP QA/QC
to apply bridge tack method.
If the pipes are of different thickness, the larger
thickness will be tapered in compliance with the
standard to match the smaller thickness.
The adjacent section of longitudinally welded pipes
that are to be joined by butt-welds shall have
longitudinal welds seam positioned such that they are
at least 30 apart from horizontal center line Ref Fig
NoX. The fabricator will also not locate longitudinal
weld seams on top or bottom of the pipes so that
branch connection is not located on the seam.
Tack weld for fit up joint shall be done by using a
bridge Clit of same material in such a way that it will
not disturb the root face of the weld joint Ref Fig
No2X:
SOCKET WELDS
The pipe for welded sockets joints shall be ground to remove
burrs due to cutting. A gap of approximately 1.6 mm
between ends of the pipe & bottom of socket will be provided
Ref Fig N o:3X How will this be achieved and what
inspection will be undertaken to verify?
WELDING
All welding work will be according to approved
WPS, B31.3 and Technip piping welding
specification. Only qualified welders shall be
employed.
All welders will carry an approved weld
identification badge when welding.
Before welding of joint following information
shall be provided at adjacent of pipe joint.
a) Piping Class
b) WPS NO.
c) Pipe material (CS)
d) Welding Process (GTAW/SMAW)
e) Tig wire for Root (ER70S-6)
f) Welder Stamp NO
g) Electrode (E7018-1)
The welding work piece will be shielded against
high winds and rain. The wind speed exceeding
10m/sec and 3 m/sec for SMAW & GTAW
respectively.
The weld surface shall be cleaned with the wire
brush or grinding prior to welding operations to
give a surface free from rust, scale or mill
cutting.
Between each layer of welding any cracks,
pores or welding spatters shall be removed by
grinding the surface before application of next
layer.
The appearance of finished welds shall
conform to ASME B 31.3 codes & WPS and
shall be free from any under cuts, spatters &
cracks.
All branch connections shall be joined to
header with full penetration welding. The bore
side shall be ground smooth, free from rust.
For flange to pipe connections if welding
shrinkage can lead to misalignment, two similar
flanges shall be joined by inserting a temporary
gasket and then welded.
Above Sequence shall be followed for heavy
wall thickness for avoiding after or during weld
distortion.
THREADED JOINTS
In case of threaded pipes (for Potable Water Line) screw
threads shall be concentric with axis of pipes with no
burrs or stripping. The Threading dies shall be sharp &
properly designated for piping material.
GALVENIZED PIPES
The pipe work up to 2 shall be threaded & galvanized by
c) INSPECTION
The fabricated pipe spools shall be checked against
TECHNIP drawings to verify its compliance.
The dimensions angle and direction of bent portions and
allowances for field welding shall be according to ASME
B 31.3 (Chapter V).
NDE shall be performed as per ASME section V after
PWHT if specified on isometric drawings.
The acceptance criteria for visual inspection shall be
done according to ASME B 31.3(Chapter V).
Visible small transverse cracks & star cracks of limited
thickness shall be removed by grinding & repaired by
welding. However circumferential cracks shall result in
weld rejection. The defective material will be cut out & re
welding shall be performed.
NDE (RT/ UT/MPT) will be requested as per piping
specification of welding provided by Technip.
NDE results shall be interpreted by qualified inspectors
(level II) & if resulted in defect, repair of the same joint
shall be done & Re inspection shall be offered.
After NDE clearance in all respect Pipe spool shall be
released for Painting/Storage/Erection.
Branch connection shall be examined by dye penetrate or
magnetic particle or ultrasonic methods. Where the
header thickness exceeds 16 mm, this type of
examination shall be made for every 9 mm thickness of
weld built up.
All welding records for each joint shall be maintained
throughout the fabrication work.
Low temperature carbon steel material traceability shall
be maintained through out the fabrication work such that
location & heat numbers of all welded pressure retaining
pipe component is maintained. Permanent marker will
transfer the heat number to all pieces cut from pipe.
d) IDENTIFICATION
Each fabricated spool shall be clearly marked with a
number. This number shall include line number &
spool number as shown on the piping isometric. For
piping up to 6 it will be hard marked on to a steel
plate 2 x 3 x 1/16 which shall be securely wired to
the pipe. However for piping greater than 6, the
number will mark on inside of the pipe using a
permanent marker.
e) STORAGE