A307 6545 104 Enq Rev0
A307 6545 104 Enq Rev0
A307 6545 104 Enq Rev0
Table of Contents
Document Number Rev. Document Title Page
Number
A307-0IG-VV-MR- 0 ENQUIRY DOCUMENT 3
6545-104-RFQ
A307-0IG-VV-MR- A PRESSURE VESSELS-CS (0-25 THK, 26-50 THK) 59
6545
A307-0IG-16-46-DS- 1 MAKEUP GAS COMP. KO DRUM 2NDSTAGE IG-V-114A/B 64
3014
A307-0IG-16-46-DS- 1 MAKEUP GAS COMP. KO DRUM 2NDSTAGE IG-V-114A/B 65
3014A3 SHEET 3
A307-0IG-16-46-DS- 1 MAKEUP GAS COMP. KO DRUM 2NDSTAGE IG-V-114A/B 66
3014A2 SHEET 2
A307-0IF-16-46-DS- 3 HP FLARE KOD IFP-V-804 67
3954
A307-0IF-16-46-DS- 3 MECHANICAL DATASHEETS 68
395402
A307-0IS-16-46-DS- 1 MECHANICAL DATASHEETS FOR IST-V-504 69
3505
A307-0IS-16-46-DS- 1 MECHANICAL DATASHEETS FOR IST-V-504 70
3505A2
A307-0IS-16-46-DS- 1 MECHANICAL DATASHEETS 71
3505A3
A307-0IS-16-46-DS- 1 MECHANICAL DATASHEETS 72
3502
A307-0IS-16-46-DS- 1 MECHANICAL DATASHEETS 73
3502A2
A307-0IV-16-46-DS- 2 MAKEUP GAS COM. 2NDSTAGE SUCTION KO DRUM IV-V-112 74
3112
A307-0IV-16-46-DS- 2 MAKEUP GAS COM. 2NDSTAGE SUCTION KO DRUM IV-V-112 75
3112A2 SHEET 2
A307-0IG-16-48- 0 IG-V-114A VESSEL PLATF & LADDER DET 76
30707
A307-0IS-16-48- 0 PLTF. FOR VESSEL IST-V-502 77
30772
A307-0IG-16-43-NZ- 0 NOZZLE ORIENTATION 78
4004
A307-000-06-42- 1 PAINTING SPECIFICATION 79
PLS-01
A307-0IG-16-43-NZ- 0 NOZZLE ORIENTATION 127
4005
A307-0IG-16-46- A VDR FOR VDR COMPILATION 128
VDR-6545
A307-0IV-16-46-DS- 2 LEAN AMINE SURGE DRUM IV-V-301 131
3301
A307-0IV-16-46-DS- 2 LEAN AMINE SURGE DRUM IV-V-301 SHEET 2 132
3301A2
A307-0IV-16-48- 0 PLATF. & LADDER FOR VESSEL IV-V-301 133
10773
A307-0IF-16-48- 0 PLTF. & LADDER DET. FOR VESSEL IFP-V-804 134
10769
Input 0 LICENSOR SPECIFICATION 135
7-12-0015 5 Standard bolt hole orientation. 139
6-81-0011 2 ITP for Pressure Vessels / Columns carbon steel. 140
7-12-0010 6 Manhole with davit. 147
7-12-0036 3 Typical details of wire mesh demister and its supports (for vessels 149
and columns).
S10.010-G G LICENSOR STANDARD FOR VORTEX BREAKER 153
6-12-0002 7 Supplementary specification for carbon steel vessels. 154
7-12-0011 5 Ladder rungs for manhole/demister. 161
A307-16-46-SS-6545 A SCOPE OF WORK AND SUPPLY 162
7-12-0032 4 Supports for internal feed pipe. 167
Page 1 of 283
Table of Contents
Document Number Rev. Document Title Page
Number
7-12-0037 3 S.R. nozzle neck. 169
6-12-0001 5 General specification for pressure vessels. 170
7-12-0026 5 Earthing lug. 183
7-12-0029 5 Bracket for name plate. 184
7-12-0005 5 Skirt opening details. 185
6-78-0003 0 Specification for Documentation Requirement from Suppliers 187
S20.030-B B TYP. DETAILS FOR DEMISTER SUPPORT 199
A307-0IG-16-46-SP- 0 JOB SPEC. FOR KNITTED WIRE MESH DEMISTER 200
01
7-12-0018 5 Internal flanges. 204
A307-16-46-TR-6545 A INSTRUCTIONS TO VENDOR/ TECHNICAL REQUIREMENTS 205
7-12-0024 7 Lifting lug top head type (for vertical vessels / columns). 214
7-12-0002 5 Support for horizontal vessel. 215
7-12-0004 6 Skirt base details. 216
7-12-0023 6 Pipe davit. 217
6-12-0011 7 Standard specification for boiler quality carbon steel plates. 220
6-78-0001 0 Specification for Quality Mgt. System Requirements from Bidders 227
7-12-0028 5 Manufacturer name plate. 236
S20.029-B B TYP. DETAILS FOR DEMISTER ATTACHMENT 237
6-12-0014 5 Standard specification for weldable structural quality steel plates 238
for tanks and vessels
A307-16-46-LL-6545 A LIST OF ATTACHMENTS 242
7-12-0013 6 Nozzle reinforcement and projection. 247
7-12-0007 5 Pipe leg support. 249
6-12-0020 7 Standard specification for stainless steel plates. 250
7-12-0027 5 Name plate. 255
S20.028-C C TYP. DETAILS FOR DEMISTER 256
A307-16-46-UR-6545 A UNIT RATES FOR ADDITION DELETION 257
7-12-0009 6 Manhole with hinged cover. 265
6-81-0001 2 Standard specification for Positive Material Identification (PMI) at 267
Supplier's Works
7-12-0025 5 Fire proofing & insulation supports. 275
6-81-0060 2 ITP for wire mesh demisters. 277
7-12-0001 5 Vessel tolerances. 282
Page 2 of 283
th
EI Bhawan 5 Floor, Bhikaiji Cama Place, RK Puram, New Delhi 110 066, INDIA
Phone No : 0091-11-26762121 ; Fax No : 0091-11-26191714, 26167664
REQUEST FOR QUOTATION (RFQ)
RFQ No. : SM/A307-0IG-VV-MR-6545/104 Date: 03-FEB-2015
Gentlemen,
Bids are requested on behalf of our Client M/s Bharat Petroleum Corporation Limited on e-procurement
system for the subject item in total compliance to technical specifications, scope, terms & conditions of enquiry
documents / attachments.
1. Bidder should submit their bids strictly as per the requirements outlined hereunder and as specified in
the material requisition.
2. Bidder can download the RFQ documents from EIL website http://tenders.eil.co.in only.
3. The bidders are required to submit soft copies of their bids electronically on the CPP Portal only (URL:
http://eprocure.gov.in/cppp), on or before the bid submission date and time. Bidders are required to
register themselves at http://eprocure.gov.in/cppp).
Bidders to refer attached E-TENDERING METHODOLOGY (ANNEXURE-I) for detailed instructions
on registration and online bid submission.
4. Special Notes for e-tendering:
a) NIC Portal mandates that the bidders are to be registered on the portal. The enquiry is being issued
through EIL Tender Portal http://tenders.eil.co.in and Bidders can download the complete RFQ
documents from the EIL Tender Portal only. And bidders shall submit their bids through NIC Portal
(https://eprocure.gov.in/eprocure/app ) only.
b) All those vendors who have still not registered on the NIC Portal are required to register on the same
(immediately after issue of enquiry on EIL Tender portal but not later than ten days before the bid due
date) for facilitating uploading of their bids on the NIC Portal failing which it will not be possible for them
to upload their bids. Pursuant to registration, the vendors are required to inform regarding NIC
registration details.
Only NIC registered vendors can upload their bids on the NIC portal. Therefore, all those bidders who
have not complied with the above registration requirements will not be eligible to bid. NIC registered
bidders will be able to upload their bids from about one week before the bid due date up to Bid Due
Date. However, an EIL enlisted vendor for the subject Limited RFQ who completes their NIC
Page 1 of 6
Page 3 of 283
Registration (including Digital Signature Certificate Registration) on NIC Portal atleast 2 (two) working
days prior to the Final Bid Due Date shall be allowed to upload their bids through a Corrigendum issued
by EIL in the NIC Portal, provided such request from the concerned Vendor is received in EIL through E-
mail by concerned Dealing Officer/RFQ Issuing Authority atleast 2 (two) working days prior to Bid Due
Date. Request for extension in due date of submission of bids due to non registration or delayed
registration in NIC portal shall not be entertained.
c) The bid has to be necessarily submitted on the NIC Portal only. Inability of the bidders to upload their
bids on account of not completing the registration with NIC portal as mentioned above will not be a
reason for seeking BDD extension.
d) Enlisted vendors of EIL who have completed the registration on NIC shall only be allowed to submit the
bids through NIC Portal. Therefore, it is in the interest of the bidders that they register on the NIC Portal
at the earliest.
e) The vendor registration on NIC Portal is a very user friendly process. However, in case of any doubt,
the vendor may contact the 24 X 7 CPP Portal helpdesk at Contact No. 1800-3070-2232 or Mobile Nos.
+91-7878007972/ +91-7878007973 and E-mail: [email protected] .
5. Bidders in their own interest are requested to register on CPP Portal and upload/submit their bid well in
time. Bidder will be responsible for any delay due to other issues.
6. Bidders are required to upload the complete bid comprising of Part-I:- Unpriced Bid along with all
supporting documents & Part-II :- Priced Bid on the CPP Portal (http://eprocure.gov.in/cppp) only.- Refer
E-Tendering Methodology (ANNEXURE-I) enclosed with RFQ documents.
7. Upon the successful and timely submission of bids, the portal will give a successful bid submission
message & a bid summary will be displayed with the bid no. and the date & time of submission of the bid
with all other relevant details. The bid summary has to be printed and kept as an acknowledgment of the
submission of bid. This acknowledgment may be used as an entry pass for attending the un-priced bid
opening, if bidders so desire.
8. Technical specification should be strictly as per the Material Requisition attached. It may be noted that
the Bid shal be evaluated as received and technical queries may not be issued.
9. Commercial requirements are specified in the Special Instructions to Bidders, General Purchase
Conditions, Agreed Terms & Conditions (ATC) questionnaire and all other RFQ documents. The pre-
filled Agreed Terms & Conditions Questionnaire should be returned duly signed and stamped along with
copy of your un-priced bid.
10. The order, if placed, will be issued by our above-mentioned client.
11. If not bidding, please inform vide E-mail with attached regret letter within the due date & time, with
reasons(s) of not participating in the RFQ. In case there is no response, names of such bidder may not
be considered for issuance of future enquiries.
12. Direct bids only, without the intermediary of an Indian Agent will be considered from Foreign Bidder.
13. Repeat Order is not applicable to this MR/RFQ.
14. Delivery Period:- Within 6 Months on FOT Despatch Point Basis from the date of Fax of Acceptance.
Date of LR/GR shall be considered the date of delivery.
15. Payment Terms shall be as per following:- The payment shall be made in accordance with S. No. 1.4 &
1.7 Under Section A of Special Instruction to Bidders (SIB).
16. The offer should be valid for 03 (Three) months from final bid due date.
17. Only E-Bids uploaded in the e-tendering portal (http://eprocure.gov.in/cppp) shall be acceptable.
Physical bids and Bids/ Offer through Email or fax/ Telex/Telegraphic or Bids received in open
condition or Bids in any other mode shall not be accepted.
18. The bidder shall bear all costs associated with the preparation and submission of its bid, and the
Purchaser/Consultant shall in no case be responsible or liable for these costs regardless of the
Page 2 of 6
Page 4 of 283
conduct or outcome of the bidding process.
Canvassing in any form by the Bidder or by any other agency on their behalf may lead to
disqualification of their bid.
19. The E-bids received online shall be opened at EIL office on due date and time as specified above.
Bidder can view online the name of the other bidders who have submitted their e-bids after opening is
performed by EIL.
20. All technically and commercially acceptable bidders will be advised of venue, date and time of priced
bid opening. Bids shall be opened online, hence bidders may review opening status at their places.
Interested bidder may sent their representatives (duly authorised by a competent person and having
the Letter of Authority as per proforma enclosed), of such technically and commercially acceptable
bidders. Time and Date of opening of Price Bids shall be notified to the qualified and acceptable
bidders at a later date.
21. As Purchaser intends to contract directly with suppliers of the goods for which bids are invited, the
bids should be prepared by the suppliers and submitted directly. Purchaser reserves the right to reject
offers made by intermediaries.
22. Addendum / corrigendum to the RFQ documents if issued must be signed and submitted along with
the bid.
23. Bidders to note that price changes against Technical / commercial clarifications, in line with terms &
conditions of enquiry documents are not allowed. In case any bidder gives revised prices / price
implications against such clarifications, their bid shall be liable for rejection.
24. EIL reserves the right to use in-house information for assessment of bidders capability for
consideration of bid.
25. In case any bidder is found to be involved in cartel formation, his bid will not be considered for
evaluation / placement of order. Such bidder will also be debarred from bidding in future.
26. The bidder who is providing the technology from the company which is recently acquired / taken over
by them or purchasing the technology by other companies, shall be provide proper documentary
evidence. In the absence of the same their offer shall be liable for rejection.
27. Bidders are requested to quote as per their capability as registered in EIL, as on the date of issue of
RFQ.
28. Owner reserves its right to allow Public Sector Enterprises (Central/State), Micro & Small Enterprises
(MSEs) and MSEs owned by Scheduled Caste (SC)/ Scheduled tribe (ST) entrepreneurs, purchase
preference as admissible/applicable from time to time under the existing Govt. policy. Bidder to submit
documentary evidence for the same duly certified by Statutory Auditor of the bidder or a practicing
Chartered Accountant (not being an employee or a Director or not having any interest in the Bidders
company / firm) where audited accounts are not mandatory as per law.).
29. The Net Worth of the bidder should be positive as per the immediate preceding year's audited financial
results. Bidders are therefore requested to furnish the Audited Financial Statement for the immediate
preceding year including Profit & Loss Account.
Bidders are required to submit the complete audited financial report for the preceding
financial year including balance sheet, profit and loss statements along with all relevant
annexures required to assess the positive net worth of the bidder in that financial year. Failure
to submit the same may render your bid liable for rejection.
30. Purchaser reserve the right to make any changes in the terms and conditions of purchase and to reject
any or all the bids.
Page 3 of 6
Page 5 of 283
31. Category of MR:
i) Please note that this is a Category-I MR whereby no technical offers are invited and no
correspondence shall be entered into or entertained after bid submission.
ii) No technical details of any nature shall be included in the offer and if the offer contains any
technical deviations or clarifications or stipulates any technical specifications, the offer shall be
liable for rejection.
iii) The submission of prices by vendor shall be construed to mean that the vendor has confirmed
compliance with all technical specifications of the correspondence item.
32. Contact Persons for this RFQ are:
Mr Subhendu Mondal, DGM (C&P),
Phone No. +91-(0)11-2676-3883 & email: [email protected]
Ms. Vibha Bharti, Sr. Engineer (C&P),
Phone No. +91-(0)11-2676-3874 & email: [email protected]
(SUBHENDU MONDAL)
DY. GEN. MANAGER(C&P)
ENGINEERS INDIA LIMITED
Enclosure: As per List Attached
Page 4 of 6
Page 6 of 283
LIST OF ENCLOSURES
DOCUMENT
A) Proforma of Letter of Authority for Attending Un-priced / Priced Bid Opening
B) Price Schedule Format
C) Commercial document:
i) Agreed Terms & Conditions (For Indian Bidders)
ii) Special Instruction to Bidders (SIB)
iii) General Purchase Conditions (Indian)
iv) Proforma of Bank Guarantee (Performance)
v) Integrity Pact
vi) E-tendering Methodology (Annexure-I).
D) Technical document MR No. A307-0IG-VV-MR-6545 Rev. A
Page 5 of 6
Page 7 of 283
Proforma of Letter of Authority
for Attending Unpriced / Priced Bid Opening
No. Date:
Dear Sir,
We confirm that we shall be bound by all and whatsoever our representative(s) shall commit.
Yours faithfully,
Signature _________________________
Name & Designation ________________
For & on behalf of __________________
Note:
This Letter of Authority should be on the letterhead of the bidder and should be signed by a
person competent and having the Power of Attorney to bind the bidder.
Page 6 of 6
Page 8 of 283
PREAMBLE TO PRICE SCHEDULE
RFQ NO. SM/A307-0IG-VV-MR-6545/104
BIDDER'S NAME :
1 Scope of supply including testing, inspection, documentation etc., shall be strictly as per Material Requisition and other documents which are part of RFQ.
2 Bidder must quote Transportation Charges inclusive of Service Tax plus ed. Cess thereupon in the space provided in the price schedule as per MR.
3 Bidder shall furnish built-in CIF value if any, against each quoted item, giving details of description of goods, qty. rate of Custom Duty etc. in attached FORM- 2..
4 All the Columns of quoted items in the Price Schedule must be filled with required information, as applicable.
5 Bidder must quote the price in enclosed Price Schedule formats only. The formats shall not be changed and/or retyped.
6 Bidder to clearly indicate 'Quoted' / 'Not Quoted' against each Sr. No. in the price column in the unpriced Price Schedule. Bidders to submit Price Part of above Price Schedule in their Priced Bid
and Unpriced Part with the Unpriced Bid.
7 Quoted prices are firm and fixed till complete execution of the entire order and no variation on any account is allowed.
8 Bidders shall quote Unit Rates for Addition/ Deletion purpose, as per Format provided with Material Requisition.
9 Bidder to note that inspection shall be carried out by EIL and the charges for the same shall be borne by Owner. However, in case of certain Import Contents as required by bidder for subject item
the same shall be procured under TPIA (Lloyds/BV/DNV/TUV/CEIL) inspection in the country of origin and the quoted prices shall be inclusive of the same.
10 Bidder must submit signed and stamped Un-Priced copy of Price Schedule indicated "Quoted" against each item with their Unpriced offer.
11 In case of any discrepancy between Unit Price and Total Price, Unit Price shall prevail.
12 Bidder to confirm that he has noted the contents of the Preamble to the Price Schedule, Price Schedule, RFQ, Material Requisition etc and quoted his prices accordingly without any deviation.
13 Evaluation shall be done on itemwise basis as per relevant provisions of RFQ documents.
NOTES: 1.Bidders must submit this document duly signed and stamped with both unpriced & priced offer.
Page 9 of 283
PRICE SCHEDULE
01.00 Supply of following Tags/ Items as per complete scope mentioned in Material Requisition No. A307-0IG-VV-MR-6545 REV.A
Page 10 of 283
FORM-2
DETAILS OF BUILT-IN-CIF VALUE OF IMPORT CONTENT CONSIDERED AND INCLUDED IN QUOTED FOT DESPATCH POINT PRICES UNDER PRICE SCHEDULE
DESCRIPTION CIF value of Import RATE OF IMPORT DUTY INCLUDED IN QUOTED SUPPLY PRICES
For Item Sl Description Qty. Content included in CUSTOM BASIC CVD + EDU. EDU. CESS SAD (%) TOTAL CUSTOM
. No. as per of Imported (Unit____) quoted supply TARIFF CUSTOMS CESS ON ON DUTY (%)
MR Items *(1) prices for column NO. DUTY (%) CVD (%) CUSTOM
(2) Qty. DUTY (%)
(In Rs)
1 2 3 4 5 6 7 8 9
i)_____
ii)_____
For Item
SL. No.
Note: Bidder to furnish item tag wise CIF value break up in separate sheet.
Page 11 of 283
A307_ATC (I) Page 1 of 8
2. DULY SIGNED & STAMPED COPIES OF THIS QUESTIONNAIRE, WITH ALL THE
CLAUSES DULY CONFIRMED/ PRECISELY REPLIED TO BY THE SUPPLIER, SHALL BE
ENCLOSED.
SL.
DESCRIPTION SUPPLIERS CONFIRMATION
NO.
1. Price Basis:
i) Quoted supply prices are on FOT - Despatch Point basis Confirmed
inclusive of Packing & Forwarding.
ii) Specify Despatch Point
-----------------------
iii) Freight Charges:
a) Confirmed , Quoted in Price
a) Confirm firm transportation charges inclusive of Service Tax Schedule
and Ed Cess, upto project site, has been quoted separately
by you in Price Schedule.
b) Confirmed
b) No Variation on any account (including Statutory Variation) on
Service Tax on Transportation Charges shall be paid by the
owner.
iv) Insurance:
Page 12 of 283
A307_ATC (I) Page 2 of 8
SL.
DESCRIPTION SUPPLIERS CONFIRMATION
NO.
b. Present Rate of Excise Duty & Edu. Cess payable extra on ..%
finished goods (including Spares)
c. Any variations in Excise Duty & Edu. Cess at the time of Confirmed
supplies for any reasons including variation due to Turnover
shall be borne by the Seller. Only Statutory Variations within
the Contractual Delivery / completion period shall be borne by
Purchaser.
d. If Excise Duty & Edu. Cess is not applicable at present due to Confirmed
any reason, the same shall be borne by Seller if it becomes
applicable later.
e. Confirm Excise Duty & Edu. Cess will not be applicable on Confirmed
transportation charges.
Page 13 of 283
A307_ATC (I) Page 3 of 8
SL.
DESCRIPTION SUPPLIERS CONFIRMATION
NO.
7. Site Work:
For Site Work, if in the scope of the Bidder as per MR, please
confirm the following:
Confirm that quoted site work prices are exclusive of Service
a. Tax & Edu. Cess but inclusive of VAT on Works Contract and Confirmed
all other applicable taxes & duties.
b. Percentage of Service Tax & Edu. Cess as applicable extra -------------------%
on Site Work.
c. Supplier shall submit the Assessment/ Liability
Certificate from Sales Tax authorities indicating the VAT
on Works Contract payable for enabling Owner to
deduct the same from Supplier Invoices & make Confirmed
payment to the tax authorities. TDS Certificate towards
VAT on Works Contract shall be provided by Owner.
Statutory variation on VAT on Works Contract shall not
be payable by Owner.
d. Statutory Variation on Service Tax & Edu. Cess on Site work
shall be paid by the Owner against documentary evidence
Confirmed
within Contractual completion period.
Page 14 of 283
A307_ATC (I) Page 4 of 8
SL.
DESCRIPTION SUPPLIERS CONFIRMATION
NO.
a. Charges for Supervision / Training, if in the scope of the Confirmed, Quoted in Price
Bidder as per MR have been indicated by bidder separately in Schedule
the Price Schedule.
e. Bidders shall also provide additional BG of an amount equal Noted & Confirmed
to the per diem charges for the number of days considered for
evaluation, over and above 10% PBG to cover compensation
for delay in mobilizing the erection/ commissioning personnel.
This BG will be released to the bidder upon the erection/
commissioning personnel reporting at site. This BG shall be
furnished along with payment milestone for submission of
final documentation as per MR and shall be initially valid up to
six months which shall be extended based on the request by
Owner.
Page 15 of 283
A307_ATC (I) Page 5 of 8
SL.
DESCRIPTION SUPPLIERS CONFIRMATION
NO.
13.1 PART ORDER:
a. Confirm acceptance of Part Order clause as per GPC Confirmed (If Applicable as per MR)
(Indigenous). And bidder also confirm acceptance to part
quantity orders of any items (having quantities 5 Nos. & more)
to facilitate purchase preference to MSME bidders as per
Govt. guide lines.
13.2 MSME BIDDERS:
YES/ NO
a Confirm whether the bidder is a MSME bidder or not. (Please tick whichever is applicable)
b In case bidder is a MSME bidder, they must submit
documentary evidence for the same duly certified by
Statutory Auditor of the bidder or a practicing Charted
_________________
Account (not being an employee or a Director or not
having any interest in the Bidders company/ firm) where
audited accounts are not mandatory as per law.
c In case bidder does not submit duly authenticated
documentary evidence as required above, bidder shall Confirmed
not be considered eligible for availing MSME benefits.
d Any charges quoted extra as lumpsum (like IBR,
Testing, freight, etc.) shall be applicable prorata on
Confirmed
value basis in the event of part order / part quantities/
split order.
14. Repeat Order:
Confirm Acceptance of Repeat Order clause as per RFQ Confirmed
Covering Letter / SIB / GPC.
Page 16 of 283
A307_ATC (I) Page 6 of 8
SL.
DESCRIPTION SUPPLIERS CONFIRMATION
NO.
Confirmed
iii) Inclusive of all statutory certification charges PESO/CCOE
etc. (if applicable) as required in the Material Requisition
Confirmed
c. Is your shop approved by IBR/CCE authority, if yes, indicate
validity.
i. IBR IBR Approved
ii. CCE
It is the responsibility of supplier to get the entire imported
materials and the built in imported contents inspected by TPIA Confirmed
(i.e. Lloyds/BV/DNV/TUV/CEIL) in the country of origin and
the quoted prices are inclusive of charges towards the same.
19. Import Content:
If your offer is based on certain imported raw materials (Applicable / Not Applicable)
required for equipments/ materials offered, please specify the (Please tick whichever is applicable)
following :
b. Indicate rate of Import Duties considered and included in the Refer Annexure to Price Schedule
quoted prices.
c. Indicate brief description/ specification with itemised CIF Refer Annexure to Price Schedule
value and country of origin of imported material.
d. Indicate classification with tariff no. under which Vendor Refer Annexure to Price Schedule
intends to import.
Page 17 of 283
A307_ATC (I) Page 7 of 8
SL.
DESCRIPTION SUPPLIERS CONFIRMATION
NO.
l. The CIF Value(s) indicated by the vendor shall be deemed to Confirmed
be the maximum value(s) for the purpose of payment of
variation in custom duty and/or other statutory variations, if
any, thereon.
22. Whether any of the Directors of Bidder is a relative of any Confirmed No relation
Director of Owner/EIL or the Bidder is a firm in which any
Director of Owner/EIL or his relative is a Partner or the Bidder
is a private company in which any director of Owner/EIL is a
member or Director.
23. Please confirm you have not been banned or delisted by any Not Banned
Government or Quasi Government agencies or PSUs. If you
have been banned, then this fact must be clearly stated. This
does not necessarily mean cause for disqualification.
However if this declaration is not furnished the bid shall be
rejected as non-responsive.
24. Please confirm your offer contains the following:
Page 18 of 283
A307_ATC (I) Page 8 of 8
SL.
DESCRIPTION SUPPLIERS CONFIRMATION
NO.
contradiction between the confirmations given above and
terms & conditions mentioned elsewhere in the offer, the
confirmation given/confirmed herein above shall prevail.
28. Confirm that Net worth of the Bidders company is Confirmed & Submitted
positive as per the immediate preceding years audited
financial results & Immediate preceding years audited
annual financial results has been submitted along with un-
priced bid.
Page 19 of 283
BPCL-KR
Job: A307
Page 20 of 283
BPCL-KR
Job: A307
INDEX
SECTION A (TERMS OF PAYMENT)
1.0 Payment Terms For Indian Bidders
2.0 Payment Terms For Foreign Bidders
3.0 Ocean Freight
SECTION B: EVALUATION CRITERIA FOR COMPARISION OF BIDS
4.0 Where only Indian Bids are under comparison
5.0 Where only Foreign Bids are under comparison
6.0 Where Indian as well as Foreign Bids are under comparison
7.0 General Notes
8.0 Special Notes on Taxes/Duties and CENVAT benefits
9.0 Price Reduction Schedule Towards Delay In Delivery
10.0 Guarantee / Warranty Period
SECTION-C: (COMMERCIAL LOADING OF OFFERS IN CASE OF DEVIATIONS)
11.0 Basis of Loading
12.0 Payment Terms
13.0 Performance Bank Guarantee (PBG)
14.0 Delayed Deliveries
15.0 Price Variation
16.0 Freight charges
17.0 Indian taxes/ duties
18.0 Utilities
19.0 Delivery/Completion Period
20.0 Foreign Exchange Rate Variation/Custom Duty Variation For Indian Bidders (On
Built-In Import Content)
21.0 VAT on Works Contracts/ Service Tax/ Splitting Of Orders
22.0 Entry Tax
23.0 Rejection Criteria
24.0 Suo-Moto Changes In Prices
25.0 Price Implication Not Permitted
26.0 Integrity Pact
SECTION-D: SPECIAL CONDITIONS.
27.0 Delivery Schedule/ Completion Period
28.0 Despatch Instructions for Indigenous Supplies
29.0 Additional Taxes & Duties (Applicable For Indian Bidder)
30.0 Recovery Of Custom Duty, Excise Duty And Sales Tax
31.0 Governing Law
32.0 Purchasers Rights And Remedies
33.0 Deduction At Source
34.0 Statutory Approval
35.0 Lien
36.0 Limitation Of Liability
SECTION-E: GENERAL INSTRUCTIONS
37.0 General
38.0 Fraudulent Practices
39.0 One Bid Per Bidder
40.0 Language Of Bid
41.0 Earnest Money Deposit:
42.0 Modification And Withdrawal Of Bids
43.0 Examination Of Bids And Determination Of Responsiveness
44.0 Owners Right To Accept Any Bid And To Reject Any Bid
45.0 Notification Of Award
46.0 Waiver Or Transfer Of The Agreement
47.0 T&C For Foreign Suppliers (To Whom RFQ Issued) Operated Through Their Indian
Office / Subsidiaries
48.0 Tax Residency Certificate (TRC) Format For Foreign Bidder
49.0 Requirement of Employment Visa For Foreign Nationals
Page 21 of 283
BPCL-KR
Job: A307
1.1 Where the Material Requisition is only for supply of materials and there is no Supplier Data
Requirement specified in MR e.g. Bulk Piping Items, etc.
1.1.1 100% Payment within 30 days after receipt and acceptance of materials at site and on submission of
Performance Bank Guarantee for 10% of Total Order Value, valid till the full guarantee period plus
Three months claim period.
1.2 Where the Material Requisition calls for Supplier Drawings/Technical Documentation.
1.2.1 90% Payment within 30 days of receipt and acceptance of materials at Site and on submission of
dispatch documents.
1.2.2 10% Payment after receipt of final technical documentation as per PR against EILs certification and
on submission of Performance Bank Guarantee for 10% of Total Order Value, valid till full guarantee
period plus Three months claim period.
1.3 Where Supply of materials and Erection or Site Work are in the scope of Supplier and
Package Items.
1.3.1 Supply
1.3.1.1 5% Payment on approval of all drawings atleast in CODE-2 by EIL against submission of Bank
Guarantee of equivalent amount valid till complete execution of Order plus Three months claim
period.
1.3.1.2 15% Payment after receipt of identified raw materials at Suppliers Works and against certification by
EIL and submission of Bank Guarantee of equivalent amount valid till complete execution of Order
plus Three months claim period.
1.3.1.3 60% Payment after receipt of equipment/materials at BPCLs Site. Billing Schedule to be furnished
by the Supplier in case pro-rata payments are required.
1.3.1.4 10% payment after completion of Site Work and submission of final Technical documents as
specified in the Purchase Requisition against EILs Certification and submission of Performance
Bank Guarantee for 10% of Total Order Value (Supply plus Site Work), valid till full guarantee period
plus three months claim period.
In case of delay in start of the site work beyond 6 months, the above 10% Payment shall be released
against submission of Bank Guarantee of equivalent amount valid initially for 1 year and subject to
extension upto completion of the site work. However, in the event of delay in the site work, the
Supplier is not relieved of his responsibility to carry out the same.
1.3.1.5 10% payment within 30 days of handing over the successfully commissioned equipment. Wherever
commissioning is not in the Suppliers scope, the payment will be released after completion of Site
Work as per PR and handing over of equipment.
Page 22 of 283
BPCL-KR
Job: A307
1.4.2 15% after receipt of identified raw materials at Suppliers Works and against certification by EIL and
submission of Bank Guarantee of equivalent amount valid till complete execution of Order plus
Three months claim period.
1.4.3 60% Payment through NEFT against receipt of materials at BPCLs Site. Billing Schedule to be
furnished by the Supplier in case pro-rata payments are required.
1.4.4 10% Payment after receipt of final documents as required in Purchase Requisition against EILs
certification and on submission of Performance Bank Guarantee for 10% of Total Order Value, valid
till full guarantee period plus Three months claim period.
1.4.5 Balance 10% Payment within 30 days of receipt of equipment at Site.
1.6 Payment for PGTR / Per Diem Charges for Supervision of Erection, Testing &
Commissioning
1.6.1 100% Payment of Invoice Amount shall be paid on completion of supervision services / PGTR
against submission of Invoice along with Time Sheet duly certified by EIL/BPCL Site-In-Charge.
Payment shall be made after deducting Income Tax at applicable rate. Service Tax, if any, shall be
paid on submission of Service Tax Invoice.
1.6.2 Where erection/commissioning supervision, commissioning assistance is required from the vendor,
penalty for non mobilization/delay in mobilization as per order shall also be specified in the
specifications. The penalty shall generally be 1.5 times the per diem rate for each day of delay of
reporting to site and shall be in addition to price reduction for delayed delivery.
1.6.3 Wherever supervision is in the scope of MR, bidders shall provide additional BG of an amount equal
to the per diem charges for the number of days considered for evaluation over and above 10%
PBG to cover compensation for delay in mobilising the erection/ commissioning personnel. This BG
will be released to the bidder upon the erection/ commissioning personnel reporting at site. This BG
shall be furnished along with payment milestone for submission of final documentation as per PR
and shall be valid up to six months which shall be extended based on the request by BPCL. (In case
where commissioning, Performance Guarantee Test, etc. are required and the 10% is under hold,
this condition shall not be applicable).
1.7 Transportation charges
1.7.1 100% Payment within 4 weeks after receipt of materials at site.
1.8 General
1.8.1 Excise Duty, Service Tax & VAT on Supplies shall be released only on receipt of Cenvatable/
Vatable copy of corresponding Invoice enabling availing of Input Credit by BPCL.
1.8.2 No initial advance payment along with Order shall be made by the Owner against Supplies as well
as Services (i.e. Transportation, Erection, Site Work, etc.). If a Supplier insists on the same, their
Offer shall be rejected.
1.8.3 Bank Guarantee(s) shall be issued through Scheduled Commercial Bank in India/ Indian Branch of
Foreign Bank, directly to BPCL as per the Pro-forma enclosed with RFQ documents and Supplier
shall also enclose copy of the same along with Invoice.
Page 23 of 283
BPCL-KR
Job: A307
1.8.4 All payments shall be released either through Electronic Clearing System (ECS) / Electronic Fund
Transfer (EFT)/ Real Time Gross Settlement (RTGS) or through internet, within 30 days of receipt of
Invoice and all requisite documents, complete in all respects.
1.8.5 Billing schedule shall be submitted to EIL & BPCL by the Supplier for approval within 30 days from
the date of Purchase Order wherever specified therein. No payment against pro-rata dispatch shall
be made without approval of Billing Schedule.
1.8.6 Major Raw Material: Shall be as specified below:
i. Columns and Vessels: Plates and Forgings
ii. Heat Exchangers: Plates, Forgings and Tubes
iii. Pumps/Compressors: Castings and Drivers
iv. Any other item(s) as may be defined in MR/PR.
2.2 Where the Material Requisition calls for Supply of material and Erection or Site Work in the
scope of Supplier and Package Items
For Supply Portion
2.2.1 90% Payment of FOB Supply value through an Irrevocable Letter of Credit against submission of
Shipping Documents. The Letter of Credit shall be established only on receipt of acceptance of Fax
of Acceptance/Purchase Order along with submission of Bank Guarantee of 15% of Order Value
(10% towards Performance Bank Guarantee valid till full Guarantee period plus Three months claim
period & separate 5% Bank Guarantee towards Price Reduction Schedule due to delay in delivery
valid till contractual delivery date (CDD) + Five and half Months).
2.2.2 10% Payment of FOB Supply value through direct wire transfer through banking channels on
completion of Erection or Site Work or Commissioning/Performance Guarantee Test Run (PGTR) at
site, as applicable as per Purchase Order/Purchase Requisition (PR) against submission of final
documents or Certificate of Completion of Work by BPCL Site.
For PGTR cases only
The above amount (10%) shall be released against successful demonstration of Performance
Guarantee Test Run & submission of Invoices duly certified by Site-In-charge or 6 months from
receipt of material at site (against BG of equivalent amount valid for 1 year), whichever is earlier.
However in the event of delay in conducting the PGTR, the bidder is not relieved of his responsibility
to carry out the same. No additional payment shall be made for visit of supplier to site for
demonstrating the PGTR, if the same is included in the scope of supplier.
Page 24 of 283
BPCL-KR
Job: A307
period plus Three months claim period & separate 5% Bank Guarantee towards Price Reduction
Schedule due to delay in delivery valid till contractual delivery date (CDD) + Five and half Months).
2.5.3 Wherever supervision is in the scope of MR, bidders shall provide additional BG of an amount equal
to the per diem charges for the number of days considered for evaluation over and above 10%
PBG to cover compensation for delay in mobilising the erection/ commissioning personnel. This BG
will be released to the bidder upon the erection/ commissioning personnel reporting at site. This BG
shall be furnish along with dispatch documents which shall be initially valid up to six months whixh
shall be extended based on the request by BPCL.
2.6 General
2.6.1 No initial advance payment along with Order shall be made by the Owner against Supplies as well
as Services (i.e. Transportation, Erection, Site Work, etc.). If a Supplier insists on the same, their
Offer shall be rejected.
2.6.2 All Bank Guarantee(s) shall be issued through any Indian Scheduled Bank or branch of an
International Bank situated in India and registered with Reserve Bank of India as scheduled foreign
Bank as per Pro-forma provided in RFQ documents. All Bank Guarantees will be directly to BPCL by
the Bank.
2.6.3 All bank charges and stamp duties payable outside India in connection with payments shall be borne
by the Supplier. All bank charges and stamp duties payable in India shall be borne by BPCL except
L/C Amendment charges for delays in delivery. Confirmation charges for Confirmed L/C shall be
borne by Supplier.
2.6.4 Billing schedule shall be submitted to EIL & BPCL by the Supplier for approval within 30 days from
the date of Purchase Order wherever specified therein. No part shipment shall be made without
approval of billing schedule.
2.6.5 Subject to Technical Acceptability, For supplies sourced within India (if any) by Foreign
Bidder & directly dispatched to Site shall have following provisions: (Refer Annexure-A)
Page 25 of 283
BPCL-KR
Job: A307
Freight Charges/ CFR prices should be valid for additional 4 months from the date of Order. The
bidder is required to furnish the shipping details within 45 days from the date of order. In case the
bidder is not able to prove the shipping details within 45 days then 4 months shall be considered
from the date of receipt of shipping details of consignment for converting FOB to CFR.
3.4 Above clause no. 3.1 to 3.3 is not applicable for Turn-Key jobs where ocean freight along with
Marine cum transit cum erection insurance in bidders scope.
If a Bidder does not quote Ocean freight charges, his offer shall be loaded with maximum freight
charges as quoted by the other bidders.
Comparison shall be done on equivalent Indian Rupees considering RBI Reference rate of Foreign
Exchange published on the day of Opening of Priced Bids.
Normally, deviations in Payment terms, Firm prices & Performance Bank Guarantee are not
acceptable. However, wherever Bidder insists, the loading shall be done as applicable to Indigenous
cases on FOB price.
Page 26 of 283
BPCL-KR
Job: A307
Foreign Bidders:
Bids shall be evaluated on the basis of landed cost at Site including the charges of inspection by
Third Party Inspection Agency, all duties, taxes and ocean freight charges as under less Cenvatable
CVD/SAD, Cenvatable Service Tax, VAT on Supplies, VAT on Works Contract, whichever is
applicable.
Wherever supervision and site works are involved, in that cases service tax plus Ed. Cess shall be
loaded with as applicable rates
7.0 GENERAL NOTES:
i. Cost of Mandatory (Insurance) Spares, if identified in the Material Requisition, Commissioning
spares and Special Tools & Tackles will be included for price evaluation of bids, but costs of Spares
for Two Years Normal Operation & Maintenance shall be excluded.
ii. Cost of loading towards Technical Parameters (Utilities, etc.) wherever applicable shall be carried
out.
iii. BPCL shall claim CENVAT benefits on Excise Duty, CVD/SAD, Service Tax as well as the Cess
applicable and accordingly Excise Duty/ CVD/ SAD/ Cess/ Service Tax shall be considered and
necessary credit shall be given for evaluation and comparison of bids.
Wherever Site Work, AMC, Training, Supervision, etc. are required as per MR/RFQ, the same shall
be considered for evaluation.
iv. Bidders shall indicate the Customs Duty at Merit Rate in their Offer.
v. The Bidder must ascertain and confirm along with supporting documents in the bid, if any Custom
duty exemption / waiver is applicable to the products being supplied by bidder under any multi-lateral
/ bi-lateral trade agreement between India and Bidders country.
The bidder shall liable to provide all documentation to ensure availment of the exemption / waiver. In
case the bidder defaults on this due to any reason whatsoever, they shall be liable to bear the
incremental Custom Duty applicable, if any.
Any Custom Duty applicability on account of any change in the bi-lateral / multi-lateral agreement
shall be in bidders account.
Page 27 of 283
BPCL-KR
Job: A307
Documentation to be furnished for availing any exemption / waiver of Custom Duty shall be
specifically listed in Letter of Credit also as the pre-requisite for release of payment against shipping
documents and this documentation shall necessarily from a part of shipping documents.
vi. BPCL shall issue Concessional Form C for Central SalesTax, for all applicable cases.
vii. Comparison shall be done on equivalent Indian Rupees considering RBI Reference Rate of Foreign
Exchange published on the day of opening of the Price Bids.
viii. Third Party Inspection charges for foreign bidder must be included in quoted prices or anything
specifically mentioned in RFQ documents..
ix. Excise Duty, Central Sales Tax, VAT on Supplies & Service Tax shall not be included in the quoted
prices and shall be payable extra at actual. BPCL shall claim eligible credit on CENVAT/Service
Tax/VAT quoted by the Bidder and therefore eligible portion of CENVAT/Service Tax/VAT shall be
considered for price comparison. Bidder shall be required to furnish proper invoices issued in
accordance with relevant rules for enabling BPCL to avail CENVAT benefits. Further, the amount of
Excise Duty, Service Tax & VAT shall only be payable against submission of CENVATABLE/
VATABLE Invoices, subject to maximum amount quoted in the Offer and in case of non-submission,
will not be paid.
x. Bidders quoted transportation charges shall be inclusive of service tax plus education cess
thereupon applicable on transportation.
xi. Transit Insurance/ Marine Insurance shall be excluded from Suppliers scope for the items where
only supply is involved, and in such cases, the same shall be arranged by the Owner. For purchases
involving Site Work, the Comprehensive Insurance (Transit/Marine cum Storage, Erection, till
handing over of equipment) shall be in the scope of Supplier.
xii. Owner reserves its right to allow Public Sector Enterprises (Central/State), Micro & Small
Enterprises (MSEs) and MSEs owned by Scheduled Caste (SC)/ Scheduled tribe (ST)
entrepreneurs, purchase preference as admissible/applicable from time to time under the existing
Govt. policy. Bidder to submit documentary evidence for the same duly certified by Statutory Auditor
of the bidder or a practicing Charted Account (not being an employee or a Director or not having any
interest in the Bidders company / firm) where audited accounts are not mandatory as per law.). In
this regard, item wise quantity may be splitted and the quoted price shall remain valid.
xiii. If various item rates are present in the RFQ and if there is correction/wrong entry or a difference
between the values entered in figures and in words, the following procedure shall be adopted for
evaluation.
i. When there is a difference between the rate in figures and in words for an item, the rate
which corresponds to the amount worked out by the Bidder for the item based on the
notional quantity specified, shall be taken as correct.
ii. When the rate quoted by the Bidder in figures and words tallies but the amount is incorrect,
the rate quoted by the Bidder shall be taken as correct.
iii. When it is not possible to ascertain the correct rate as detailed above, the rate quoted for
the item in words shall be adopted as the quoted rate.
iv. If the total amount written against an item does not correspond to the rate written in figures
and if the rate in words is missing, then the higher of the rates, i.e. higher of the rate worked
out by dividing the amount by the notional quantity and the rate quoted shall be considered
for evaluation In the event that such a bid is determined as the lowest bid, the lower of the
rates shall be considered for award of works.
Page 28 of 283
BPCL-KR
Job: A307
bids. Credit shall be taken during evaluation for 20% of Kerala VAT rate, 96% of Service Tax
rate and full amount for other Cenvatable taxes and duties.
(iv) Excise Duty, Central Sales Tax, Kerala VAT & Service Tax shall not be included in the
quoted prices and shall be payable extra at actuals. Further, the amount of Excise Duty,
Service Tax, Central Sales Tax, KVAT shall only be payable against submission of
supporting documents/Cenvatable/Vatable invoices subject to maximum amount quoted in
the offer and in case of non-submission, will not be paid.
(v) Non Cenvatable Excise Duty, if any is to be included in quoted prices & no variation on any
account (including statutory variation) shall be paid by Owner.
(vi) All New taxes/duties/cess/levies notified after the last date of submission of bid (final bid due
date) but within contractual delivery/ completion period, shall be to Owners account.
(vii) The bidder shall be required to furnish details of any special dispensation regarding
concessional/ exempted taxes/ duties.
Price Reduction schedule for (Supply + Site work) shall be @ 0.5% of value of total order value
(TOV) of per week of delay or part thereof subject to maximum of 5% total order value (TOV).
Price Reduction Schedule (Supply + Site work) towards delay in delivery for foreign bidder shall be
applicable as per clause no. 17 of GPC Import of RFQ subject to following modification:
Imports, for any delay in delivery of equipments / materials or part thereof beyond the delivery
date stipulated, the vendor shall be liable to pay, compensation at 0. 5% of the total FOB Value of
order per week of delay or part thereof subject to maximum of 5% of the total FOB Value of
order.
iii. Wherever the supply period and site work are indicated as two separate periods and
notice of site readiness is required for site work, intervening period, if any shall be
excluded, while calculating the price schedule for delay.
b) In case item involving supply and site work excluding comprehensive Insurance
policy:-
Performance Guarantee shall be as per clause 30 of GPC (For Indigenous materials &
equipments).
Page 29 of 283
BPCL-KR
Job: A307
b. In case item involving supply and site work Excluding comprehensive Insurance
policy:-
Performance Guarantee shall be as per clause 26 of GPC (For Foreign materials & equipments).
In cases like turnkey jobs, to derive the delivery period of supply items, the total period of turnkey
jobs shall be split into delivery period of supplies & site work period in the ratio of 70:30 for loading of
differential payment terms for the supply periods as defined above.
ii. Foreign suppliers shall not be permitted to offer differential payment terms as against the terms
specified in the RFQ/ GPC and in case they insist, their offer shall be rejected.
iii. Advance along with FOA/ PO will not be allowed. If a supplier insists for advance payment along
with FOA/PO, his offer shall be rejected.
Page 30 of 283
BPCL-KR
Job: A307
In case a Supplier does not accept the delayed delivery clause and/or takes any deviation (indicates
Penalty clause/Liquidated damages in place of Price Reduction Clause) or takes exception to the
percentage rate mentioned in GPC, the offer of such supplier(s) shall be loaded as under:
0.5% UDOV to 5%TOV : No loading
0.5% UDOV to 5% UDOV : 5%
0.5% UDOV to less than 5% TOV : Differential between the offered %age and 5%
Any other deviation/Liquidated : 5%
Damages/ penalty or non acceptance
of price reduction schedule
ii. For Supply + Site Work: [considering 0.5% total order value (TOV) ~ 5% total order value
(TOV)]
0.5% TOV to 5%TOV : No loading
0.5% UDOV to 5%TOV : 5% loading
0.5% TOV to less than 5% TOV : Differential between the Offered % and 5%
Any other deviation/Liquidated : 5%
Damages/ penalty or non acceptance
of price reduction schedule
15.0 PRICE VARIATION:
Suppliers must quote firm & fixed prices unless price variation is specified in the RFQ. Where price
variation is permitted as per RFQ, the loading thereto shall be as follows:
c) No ceiling on the formula specified (This 1.5 times the maximum ceiling specified by
loading other Suppliers. In case all other Suppliers
shall be done only after putting efforts with have quoted firm prices then @ 1.25% for
Supplier to indicate ceiling and obtaining every month of quoted delivery period to be
BPCLs approval) taken as ceiling.
d) No formula and no ceiling specified by Offer may be rejected.
Supplier
(This shall be resorted to only after putting
efforts with Supplier and obtaining BPCLs
approval)
19.0 UTILITIES:
Cost loading in respect of utilities etc. will be considered as mentioned in RFQ documents.
20.0 FOREIGN EXCHANGE RATE VARIATION/CUSTOM DUTY VARIATION FOR INDIAN BIDDERS
(ON BUILT-IN IMPORT CONTENT) :
i. Prices shall remain firm and fixed without any escalation except for statutory variation in customs
duty rate.
The prices shall be firm and fixed on account of FE variation also.
Page 31 of 283
BPCL-KR
Job: A307
ii. Indigenous bidders shall be required to quote their prices including customs duty (Merit rate)
towards their built in import content. CIF content in Indian Rupees shall also be furnished by
Bidders along with the merit rate of customs duty considered.
iii. The statutory variation in customs duty shall be subject to the following
guidelines and the supplier shall confirm the following in their bid:
(a) Maximum CIF value of import content shall be furnished in the bid.
(b) The material to be imported covering the above CIF value to be indicated in the bid.
(c) Any increase in price due to increase in customs duty rate beyond two-third of the quoted
delivery period will be to suppliers account. However, any decrease in price due to
decrease in customs duty rate at the time of actual clearance of imported materials shall
be passed on to BPCL.
(d) Variation in price due to customs duty rate will be dealt with separately after receipt of
materials at site against documentary evidence.
Page 32 of 283
BPCL-KR
Job: A307
(i.) Any Suo-moto reduction in price offered by a supplier within the bid validity by way of discount or
revised prices subsequent to the bid due date and which is not as a result of any change in scope of
supply or terms and conditions, shall not be taken into account for evaluation. However, such
reduction in price shall be taken into account for ordering if such supplier happens to be the
recommended supplier as per the originally quoted prices.
(ii.) However, in the event of any suo-moto price increase sought by a supplier subsequent to the bid
due date and which is not as a result of any change in scope of supply or terms and conditions, the
bid of such a supplier shall be rejected for the items in which such suo-moto increase is made.
(iii.) Any wrong interpretation of taxes & duties or any taxes & duties not specified in the offer shall be
borne by Bidder.
25.0 PRICE IMPLICATION NOT PERMITTED:
Price implications on account of technical clarifications shall not be permitted as long as
BPCL/EIL do not change the specifications/ scope spelt out in the RFQ.
Page 33 of 283
BPCL-KR
Job: A307
29.0 NEW / ADDITIONAL TAXES & DUTIES (Applicable for Indian Bidder):
i. Within the contractual delivery period, if any new taxes and/or duties come into force the same will
be reimbursed to bidder against documentary evidence. However any new or additional taxes/
duties imposed after contractual delivery shall be to borne by seller.
ii. All necessary taxes & duties registration, if required for carrying out the site activities shall be done
by the bidder and cost towards the same shall be included in quoted prices.
iii. The statutory variations on Customs duty (rate) considered on above CIF value of built in import
content, within contractual delivery period shall be to Employers account against submission of the
documentary evidence. However, any increase in the rate of Customs duty beyond the contractual
completion period shall be to bidders account. In case of wrong classification, no variation
including statutory variation of Customs Duty will be payable extra. Any decrease in the rate of
Customs duty shall be passed on to the Employer.
iv. The statutory variations on Excise rate and amount of Excise Duty, CST with concessional form &
VAT without concessional form, which will be payable on the finished goods and Cenvatable
Service Tax, as applicable, within the contractual delivery period shall be to Employers account
against submission of the documentary evidence. Any increase in the rate of these taxes and
duties beyond the contractual completion period shall be to bidders account. However, any
decrease in the rate of taxes & duties shall be passed on to the Employer.
v. Works Contract Tax & service tax on transportation, if applicable, shall be included in the quoted
prices and no variation including statutory variations shall be payable by BPCL.
Approval from any authority (i.e. Inspector of Boiler, Electrical Inspector, and Municipal Corporation
of Greater Kochi (MCGK) etc.) required as per statutory rules and regulations of Central/ State
Government shall be the responsibility of Contractor agency.
The application on behalf of the OWNER for submission to relevant authorities along with copies of
required certificate complete in all respects shall be prepared and submitted by the Contractor
agency well ahead of time so that the actual construction/ commissioning of the work is not delayed
for want of the approval/ inspection by concerned authorities. The Contractor agency shall arrange
the inspection of the works by the authorities and necessary coordination and liaison work in this
respect shall be the responsibility of the Contractor agency. Reimbursement by the OWNER of the
A307_SIB Rev.6 dt. 14.04.2014 Page 15 of 20
Page 34 of 283
BPCL-KR
Job: A307
statutory fees payable by Contractor agency (as per advance approval of OWNER) may be provided
for, subject to submission of receipt.
The Contractor agency shall carry out any change/ addition required to meet the requirements of the
statutory authorities, within the quoted rates. The inspection and acceptance of the work by statutory
authorities shall be the responsibility of the Contractor agency.
List of all documents, drawings, forms, affidavits etc required for the approvals shall be submitted by
the contractor agency.
35.0 LIEN:
Supplier shall ensure that the Scope of Supply supplied under the Agreement shall be free from any
claims of title/liens from any third party. In the event of such claims by any party, Supplier shall at
his own cost defend, indemnify and hold harmless Purchaser or its authorised representative from
such disputes of title/liens, costs, consequences etc.
37.0 GENERAL: Bidders shall submit their Bids in following manner & containing the listed inputs, duly
filled-in, stamped & signed by authorized signatory of Bidder holding Power of Attorney, as a
minimum requirement:
a) PART-I: UNPRICED OFFER
A. All technical specifications as per requirement of MR.
B. Agreed Terms & Conditions duly filled in.
C. Terms & Conditions for Supervision of Erection/Testing/Commissioning, if applicable
D. Terms & Conditions for Site Work, if applicable
E. Copy of Registration with EIL, if applicable
F. Copy of MOU/ MOM, if any, signed with EIL and referred in offer.
G. Integrity Pact, duly filled-in, stamped & signed on each page (if applicable).
H. Complete Audited Financial Report of latest preceding Financial year.
I. Deviation sheet, if any.
J. Price Schedule with prices blanked out but Quoted/ Not quoted to be mentioned & its
relevant enclosures, duly filled-in, stamped & signed on each page.
b) PART-II: PRICED OFFER
A. Price Schedule with prices filled in.
B. Statement that all specifications and terms & conditions are as per un-priced part of offer.
Note:
Bidding currency shall be Indian Rupees for supplies dispatched from India & and USD/EURO for
supplies dispatched from foreign.
Page 35 of 283
BPCL-KR
Job: A307
b) In case, the information/ document furnished by the Bidder/ Contractor forming basis of
evaluation of his bid is found to be false/ forged after the award of the contract, Owner shall
have full right to terminate the contract and get the remaining job executed at the risk & cost of
such Bidder/ Contractor without any prejudice to other rights available to Owner under the
contract such as forfeiture of CPBG/ Security Deposit, withholding of payment etc.
c) In case, this issue of submission of false documents comes to the notice after execution of
work, Owner shall have full right to forfeit any amount due to the Bidder/ Contractor along with
forfeiture of CPBG/ Security Deposit furnished by the bidder/ contractor.
d) Further, such bidder/ contractor shall be put on Blacklist/ Holiday/ Negative List of OWNER/EIL
debarring them from future business with Owner & EIL for a time period, as per the prevailing
policy of OWNER & EIL.
b) In the event of submission of any document/ certificate by the Bidder in a language other than
English, the English translation of the same duly authenticated by Chamber of Commerce of
Bidders country shall be submitted by the Bidder. Metric measurement system shall be
applied.
41.0 EARNEST MONEY DEPOSIT:
Bidder shall furnish, as part of its Bid, EMD for an amount as indicated in the NIT/ IFB. If the
Bidder is unable to submit Bid Document Fee & EMD in original within the due date & time, then
bidder shall submit the original Bid Document Fee & EMD within 7 days from the date of unpriced
bid opening, provided copy of the same have been uploaded on E-Tendering Website. In case
the bidder fails to submit the same in original within 7 days, then their bid shall be rejected,
irrespective of their status/ ranking in tender and notwithstanding the fact that a copy of Bid
Document Fee & EMD was earlier uploaded by the bidder. OWNER shall not pay any interest on
EMD furnished.
The EMD shall be in favour of BPCL and shall be acceptable in the form of Crossed Demand Draft
or Bank Guarantee in the prescribed pro-forma.
The Bank Guarantees/DD for EMD shall be issued by any Scheduled Commercial Bank (other than
co-operative Bank) in India or any Indian Branch of Foreign Bank and same shall be as per the
format given in this bidding document. Swift Message or Cash or Cheque in lieu EMD shall not be
acceptable.
The bank guarantee for submission of EMD shall be valid as period mentioned in EMD / Bid
Security format or elsewhere mentioned in Bid Document / RFQ.
EMD/ Bid securities of unsuccessful bidders will be returned upon award of Contract. However,
EMD of the successful Bidder will be returned upon the Bidder's acceptance of PO/ signing the
Contract and furnishing the PBG.
The EMD may be forfeited:
If a Bidder withdraws its bid during the period of Bid Validity or does any breach of
tendering terms and conditions, or
In case of a successful Bidder, if the Bidder fails, within the specified period:
i. To submit the order acceptance.
ii. To furnish the PBG.
Page 36 of 283
BPCL-KR
Job: A307
Page 37 of 283
BPCL-KR
Job: A307
I. The parent company shall issue an authorization from the authorized signatory like CEO, CFO, CS
to confirm their authorization to the subsidiary to manufacture & supply the equipments.
II. The parent company shall furnish a back-up guarantee duly signed by above signatory for the
performance of the equipment.
III. The order shall be placed on Indian subsidiary and the payment shall be released to Indian
subsidiary.
IV. Indian subsidiary shall be a manufacturing company in the same product & not a liaison /
representative office.
V. Bidder to submit bipartite agreement between parent & subsidiary to ensure experience &
compliance to contract.
VI. All critical components / parts to be supplied by parent company only which is enlisted with EIL.
Page 38 of 283
BPCL-KR
Job: A307
ANNEXURE-A
INTEGRATED REFINERY EXPANSION PROJECT (IREP) OF
M/s BPCL KOCHI REFINERY, KOCHI, KERALA (INDIA)
(Job No. A307)
TERMS & CONDITIONS FOR INDIAN SOURCED COMPONENTS / SERVICES BY FOREIGN
BIDDER
Foreign bidder may source components / sub-supplies and services from India, if allowed as per Material
Requisition. Such sub-supplies / services shall be subject to following Commercial Terms & Conditions:
1. PRICING:
1.1 The Foreign bidder shall quote firm price for items being sourced from India in Indian rupees on FOT
Site basis inclusive of packing, forwarding, transportation, all applicable taxes, duties & levies payable
upto site.
1.2 Materials if ordered against this Bidding Document are required to be dispatched on door delivery basis
through a reliable bank approved Road Transport Company unless the transport company is named by
the Owner.
2. AWARD OF ORDER:
Client will place single order for Main Supplies/ Services including Indian source supplies/ Services
with single point responsibility taken care by foreign (principal) bidder. However obligation of
Performance Bank Guarantee & Price Reduction Schedule for complete package shall always be in
scope of foreign (principal) Bidder.
3. DELIVERY:
The delivery period for items being sourced from India, shall be on FOT site basis within the delivery
period specified for foreign bidder as per Terms of Bidding document.
5. OVERALL RESPONSIBILTY:
Overall responsibility towards the contractual obligations like delivery, bid security, order execution,
performance guarantee etc. including supplies being sourced from India shall be only with the
foreign (principal) bidder.
7. INSPECTION
i. Inspection of Item being sourced from India shall be by EIL/Owner.
ii. Any change in sourcing from indigenous supplies to imported supplies and vice-versa after bid
submission is not permitted.
iii. Considering EIL Inspection charges, during evaluation prices of Indigenous source item shall be
loaded by @1.25% of FOT Despatch Point Price price.
8. PAYMENT TERMS:
8.1 Indian Sourced supplies:
100% payment along with taxes and duties will be paid against receipt & acceptance of Indian sourced
goods/material at project site and on presentation of invoice suitable for availing Cenvat.
8.2 Payment of Indian source supplies/Services shall be released directly to Indian counterpart against
Invoices raised by Indian counterpart duly endorsed by Foreign principal for payment.
8.3 The payments shall be made after Adjustment of Price Reduction Schedule.
9. In case of any deviation to above requirement, loading shall be applicable as mentioned for Indian
Bidder.
Page 39 of 283
Page 40 of 283
Page 41 of 283
Page 42 of 283
Page 43 of 283
Page 44 of 283
Page 45 of 283
Page 46 of 283
Page 47 of 283
PROFORMA OF BANK GUARANTEE
( Performance )
(Ref. clause 26)
To
Bharat Petroleum Corporation Limited
Kochi Refinery, Ambalamugal, Kerala- 682 302
Dear Sir,
In consideration of the Bharat Petroleum Corporation Limited (hereinafter called the
Company which expression shall
include its successors and assigns) having awarded to M/s.
(Name)................................... ..(address)
............ ................................................. ...................
................................................... (hereinafter
referred to as The Supplier which expression wherever the subject or context so
permits include its successors and assigns) a supply contract in terms interalia, of the
Companys Purchase Order Nodated and the
General Purchase Conditions of the company and upon the condition of suppliers
furnishing security for the Performance of the suppliers obligation and/or discharge of
the suppliers liability under and/or in connection with the said supply contract up to a
sum of (in figure)......................... (in words)
..........................................................................................
........................................................................
..............................................) contract value.
We,
(Name)...........................(constitution)....................
......... (hereinafter called the Bank which expression shall include its successors and
assigns) hereby jointly and severally undertake the guarantee to pay to the Company in
(Currency) forthwith on demand in writing and without protest or demur of any and all
moneys anywise payable by the Supplier to the Company under in respect of or in
connection with the said supply contract inclusive of all the Companys losses and
damages and costs, (inclusive between attorney and client), charges and expenses and
other moneys anywise payable in respect to the above as specified in any notice of
demand made by the Company to the Bank with reference to this Guarantee up to
aggregate limit of Rs...... (Rupees .....
...................................................................
..only)
This Guarantee / Undertaking shall be a continuing / undertaking and shall remain valid
and irrevocable for all claims of the Company and liabilities of the Supplier arising up to
and until midnight of..
This date shall be 6 months from the last date of guarantee period
Page 48 of 283
Company in enforcing or requiring enforcement of any other security shall have the
effect of releasing the Bank from its liability hereunder.
The company shall be at liberty without reference to the bank and without affecting the
full liability of the Bank hereunder to take any other security in respect of the Suppliers
obligations and/or liabilities under or in connection with the said supply contract and to
vary the terms vis a vis the supplier of the said supply contract or to grant time and/or
indulgence to the supplier or to reduce or to increase or otherwise vary the prices of the
total contract value or and/or the remedies of the company under any other security (ies)
now or hereafter held by the company and no such dealing(s), variation(s), reduction(s),
increase(s) or the indulgence(s) or arrangement(s) with the supplier or release or
forbearance whatsoever shall have the effect of releasing the Bank from its full liability to
the Company hereunder or of prejudicing rights of the Company, against the Bank.
The Bank hereby waives all rights at any time inconsistent with the terms of its
Guarantee / Undertaking and the obligations of the Bank in terms hereof shall not be
anywise affected or suspended by reason of any dispute or disputes having been raised
by the supplier (whether or not pending before any Arbitrator, office, Tribunal or Court) or
any denial of liability by the supplier or any other of communication whatsoever by the
supplier stopping or preventing or purporting to stop or prevent any payment by the Bank
to the Company in terms hereof.
The amount stated in any notice of demand addressed by the Company to the
Guarantor as liable to be paid to the Company by the supplier or as suffered or incurred
by the Company on account of any losses or damages of costs, charges and or
expenses shall as between the Bank and the company be conclusive of the amount so
liable to be paid to the Company or suffered or incurred by the Company, as the case
may be and payable by the Guarantor to Company in terms hereof.
Yours faithfully,
Page 49 of 283
Page 50 of 283
Page 51 of 283
Page 52 of 283
Page 53 of 283
Page 54 of 283
Page 55 of 283
Annexure 1
E-TENDERING METHODOLOGY
http://eprocure.gov.in/eprocure/app .
REGISTRATION
1) Bidders are required to enroll on the e-Procurement module of the Central Public
Procurement Portal (URL: http://eprocure.gov.in/eprocure/app) by clicking on the link Click
here to Enroll on the CPP Portal is free of charge.
2) As part of the enrolment process, the bidders will be required to choose a unique username
and assign a password for their accounts.
3) Bidders are advised to register their valid email address and mobile numbers as part of the
registration process and submit in EIL tender portal for updation of records
(http://tenders.eil.co.in) . These details would be used for any communication from the CPP
Portal.
4) Upon enrolment, the bidders will be required to register their valid Digital Signature
Certificate (DSC) (Class II or Class III Certificates with signing key usage) issued by any
Certifying Authority recognized by CCA India (e.g. Sify / TCS / nCode / eMudhra etc.), with
their profile.
5) Foreign Bidders have to refer DSC details for foreign Bidders for Digital signature
Certificates requirements which comes under Download Tab at
http://eprocure.gov.in/eprocure/app and the remaining part is same as above and below.
6) Only one valid DSC should be registered by a bidder. Please note that the bidders are
responsible to ensure that they do not lend their DSCs to others which may lead to misuse.
7) Bidder then logs in to the site through the secured log-in by entering their user ID / password
and the password of the DSC / e-Token.
Page 56 of 283
3) The bidder should make a note of the unique Tender ID assigned to each tender, in case
they want to obtain any clarification / help from the Helpdesk.
PREPARATION OF BIDS
1) Bidder should take into account any corrigendum published on the tender document before
submitting their bids.
2) Please go through the tender advertisement and the tender document carefully to
understand the documents required to be submitted as part of the bid. Please note the
number of covers in which the bid documents have to be submitted, the number of
documents - including the names and content of each of the document that need to be
submitted. Any deviations from these may lead to rejection of the bid.
4) Bidder, in advance, should get ready the bid documents to be submitted as indicated in the
tender document and generally, they can be in PDF / XLS / RAR / DWF formats. Bid
documents may be scanned with 75 dpi with black and white option. However, Price
Schedule / SOR shall be strictly in RAR format without altering any contents of the
formats uploaded by EIL in their Bidding Document.
5) To avoid the time and effort required in uploading the same set of standard documents which
are required to be submitted as a part of every bid, a provision of uploading such standard
documents (e.g. PAN card copy, annual reports, auditor certificates etc.) has been provided
to the bidders. Bidders can use My Documents area available to them to upload such
documents. These documents may be directly submitted from the My Documents area
while submitting a bid, and need not be uploaded again and again. This will lead to a
reduction in the time required for bid submission process.
SUBMISSION OF BIDS
1) Bidder should log into the site well in advance for bid submission so that he/she upload the
bid in time i.e. on or before the bid submission time. Bidder will be responsible for any delay
due to other issues.
2) The bidder has to digitally sign and upload the required bid documents one by one as
indicated in the tender document.
3) Bidder has to select the payment option as offline to pay the tender fee / EMD as
applicable and enter details of the instrument.
4) Bidder should prepare the EMD as per the instructions specified in the tender document. The
original should be posted/couriered/given in person to the Tender Processing Section, with
in 7 calendar days of the date of Unpriced bid opening. The details of the DD/any other
accepted instrument, physically sent, should tally with the details available in the scanned
copy and the data entered during bid submission time. Otherwise the uploaded bid will be
rejected.
5) A Price Bid format has been provided with the tender document to be filled by all the bidders.
Bidders are requested to note that they should necessarily submit their financial bids in the
format provided and no other format is acceptable. Bidders are required to download the
Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL All rights reserved
Dated -02-July-2014
Page 57 of 283
Price Bid file, open it and complete the cells with their respective financial quotes and other
details (such as name of the bidder). No other cells should be changed. Once the details
have been completed, the bidder should save it and submit it online, without changing the
filename. If the Price Bid file is found to be modified by the bidder, the bid will be rejected.
6) The server time (which is displayed on the bidders dashboard) will be considered as the
standard time for referencing the deadlines for submission of the bids by the bidders,
opening of bids etc. The bidders should follow this time during bid submission.
7) All the documents being submitted by the bidders would be encrypted using PKI encryption
techniques to ensure the secrecy of the data. The data entered cannot be viewed by
unauthorized persons until the time of bid opening. The confidentiality of the bids is
maintained using the secured Socket Layer 128 bit encryption technology. Data storage
encryption of sensitive fields is done.
8) The uploaded tender documents become readable only after the tender opening by the
authorized bid openers.
9) Upon the successful and timely submission of bids, the portal will give a successful bid
submission message & a bid summary will be displayed with the bid no. and the date & time
of submission of the bid with all other relevant details.
10) The bid summary has to be printed and kept as an acknowledgement of the submission of
the bid. This acknowledgement may be used as an entry pass for any bid opening meetings.
RETENDER
Please note that if Tender has been retendered, than it is mandatory for the bidder to
submit their offer again on CPP Portal.
WITHDRAWAL OF BID
It may please be noted that bidders now have an additional feature of withdrawing their
bids before due date and time. After submitting the bid on the CPP Portal, if the bidder
wishes to withdraw his bid, he can do so. However, if the bidder withdraws his bid, he
will be exempted from further participation in the tender and wont be able to submit
his bid again for that particular tender.
ASSISTANCE TO BIDDERS
1) Any queries relating to the tender document and the terms and conditions contained therein
should be addressed to the Tender Inviting Authority for a tender or the relevant contact
person indicated in the tender.
2) Any queries relating to the process of online bid submission or queries relating to CPP Portal
in general may be directed to the 24 x 7 CPP Portal Helpdesk. The contact number for the
helpdesk is 1800-3070-2232 and Mobile Nos +91-7878007972, +91-7878007973.
Page 58 of 283
This drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited
MATERIAL REQUISITION (TOP SHEET)
ITEM DESCRIPTION: PRESSURE VESSEL -CS (26-50 MM), PRESSURE VESSEL -CS (UP TO 25 MM)
GROUP ITEM CODE: 01AB,01AA DESTINATION: As per Commercial Documents
MR CATEGORY: I DELIVERY PERIOD: As per Commercial Documents
DOCUMENT NUMBER
( Always quote the Document Number given below as reference )
NOTES :
1 This page is a record of all the Revisions of this Requisition.
2 The nature of the Revision is briefly stated in the "Details" column below, the
Requisition in its entirety shall be considered for contractual purposes.
3 Vendor shall note the MR category and shall submit his offer in line with the
requirements included in attached 'Instructions to Bidders'.
Page 59 of 283
Sheet 1 of 4
File Name: C:\Users\A869\Desktop\6545 final.pdf
This drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited
TAG NO/
SR. NO. ITEM CODE/ [ ID. NO. ] DESCRIPTION QUANTITY
Vendors shall quote prices in EIL Price Schedule except for Sr.No.9.00. Price for
documentation is implied to be included in the prices quoted against Sr.No.1.00 to
Sr.No.8.00
Page 60 of 283
Sheet 2 of 4
File Name: C:\Users\A869\Desktop\6545 final.pdf
This drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited
TAG NO/
SR. NO. ITEM CODE/ [ ID. NO. ] DESCRIPTION QUANTITY
Vendor to note that the numbers given in square '[]' and curly '{}' brackets are
not for their use and meant for store purpose only. Items shall be tagged as per
main equipment Tag No. only.
or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use. EIL-1641-515 Rev.1 A4-210x297.
Page 61 of 283
Sheet 3 of 4
File Name: C:\Users\A869\Desktop\6545 final.pdf
This drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited
LIST OF ATTACHMENTS
REVISION
SL. REV. REV. REV. REV.
DOCUMENT TITLE DOCUMENT NO.
No.
DATE DATE DATE DATE
1 Instructions to Vendor A307-16-46-TR-6545 A
16/01/2015
2 List of applicable A307-16-46-LL-6545 A
specifications & standards 16/01/2015
3 Scope of supply A307-16-46-SS-6545 A
16/01/2015
4 Vendor data requirements for A307-0IG-16-46-
Vessels VDR-6545
5 Unit rate for addition or A307-16-46-UR-6545 A
deletion 16/01/2015
DATASHEET
or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use. EIL-1641-515 Rev.1 A4-210x297.
GENERAL NOTES:
Page 62 of 283
Sheet 4 of 4
File Name: C:\Users\A869\Desktop\6545 final.pdf
Format No.: EIL-1641-1923 Rev.1
PO No.:
Date of PO: City:
Page 63 of 283
EIL Originating Department: PRESSURE VESSELS Contact Person(EIL): Contact Person: Fax:
Phone: Email:
NOZZLES AND CONNECTIONS uksty o duSD'ku GENERAL NOTES (tujy uksV~l SPECIFICATIONS LisflfQds'kUl DESIGN DATA fMtkbu MkVk
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTI
ON NOTE-
PAD W
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SEC. VIII DIV.1 2010 & ADDENDA 2011
ukfeuy Mka;k
'kMwy o CLASS TYPE FACING 4
xT 1 ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE STATED. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm2g) 37.7
ekdZ DokfUVVh fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. X SUPP. SPEC. FOR CS VESSELS 6-12-0002 DESIGN PRESSURE (kg/cm2g) INT. 51 EXT. F.V.
AO 1
400 10
AS PER EIL STD. 200 x8
ACCESS OPENING 12 2
VESSEL IS SUBJECTED TO STEAM OUT CONDITION OF 0.5 Kg/Cm (g) AT X MANHOLE WITH DAVIT 7-12-0010 PRESSURE (NEW & COLD) 66.3
I.D. THK. 1900C. X LADDER RUNGS FOR MANHOLE/DEMISTER 7-12-0011 INSPECTION BY EIL CIB LLOYDS
13 DEMISTER PAD : YORK MESH TYPE 709 OR EQUIVALENT, DESIGN OF RETAINING PLATE 7-12-0012 MATERIAL OF CONSTRUCTION eSfVfj;y vkQ dUlVD'ku)
DEMISTER SUPPORT TO ENSURE THAT THE FLOW RESTRICTION IS
NEGLIGIBLE. EFFICIENCY FOR A DEMISTER SHOULD BE CONSIDERED AS
X NOZZLE REINFORCEMENT AND PROJECTION 7-12-0013 (AS PER ASME / IS OR EQUIVALENT)
PAD NOZZLES FOR VESSELS 7-12-0014
99.9% WITH AN ALLOWABLE PRESSURE DROP OF 0.05 Kg/Cm2.
X STANDARD BOLT HOLE ORIENTATION 7-12-0015 SHELL / BOOT SA 516 Gr.60
14 COMPLETE VESSEL INCLUDING SUPPORTS SHALL BE STRESS RELIEVED. ALLOY LINER DETAILS 7-12-0016 REINFORCEMENT PAD / INSERT PLATE SA 516 Gr.60
HARDNESS OF BASE METALS, WELDS AND HAZ AFTER PWHT SHALL NOT SIGHT GLASSES FOR PRESSURE VESSELS 7-12-0017 HEADS SA 516 Gr.60
EXCEED 200 BHN. SHELL FLANGES
INTERNAL FLANGES 7-12-0018 -
15 PIPE TO PIPE, PIPE TO FLANGE, PIPE TO FITTING & FITTING TO FLANGE JOINT VORTEX BREAKERS 7-12-0019 NOZZLE FLANGES/SRN/LWN SA 105
SHALL BE WELDED WITH THE SAME TECHNIQUE USED FOR MAIN EQUIPMENT INLET DEFLECTOR BAFFLE 7-12-0020 NOZZLE NECK UPTO 250 NB SA 106 GR.B
WELDING.
SRN - SELF REINFORCED NOZZLE WITH SUPPORT RING AND BOLTING BAR 7-12-0021 NOZZLE NECK ABOVE 250 NB SA 516 Gr.60
INTEGRAL FLANGE 16 ALL SELF REINFORCED INTEGRALLY FORGED NOZZLES SHALL BE PROVIDED SUPPORT RING SIZES FOR PACKED TOWERS 7-12-0022 PIPE FITTINGS SA 234 GR. WPB (SEAMLESS)
WITH LIP.
X PIPE DAVIT 7-12-0023 GASKET EXTERNAL SPIRAL WOUND WITH SS 316 WINDING & GRAFOIL
FILLER WITH CS OUTER & SS INNER RING AS PER ASME
X LIFTING LUG TOP HEAD TYPE 7-12-0024 B16.20
REFER SHT.3 OF 3 FOR DETAILS OF X FIRE PROOFING AND INSULATION SUPPORTS 7-12-0025
SR NOZZLES. X EARTHING LUG 7-12-0026
X NAME PLATE 7-12-0027 GASKET INTERNAL -
X MANUFACTURER NAME PLATE 7-12-0028 EXTERNAL STUDS/BOLTS/NUTS SA 193 GR.B7M / SA 194 GR.2HM
NAME PLATE FOR SMALL EQUIPMENT 7-12-0030 SKIRT/ SUPPORT SA 516 GR.60/IS2062 GR.B
SUPPORTS FOR INTERNAL FEED PIPE 7-12-0032 INTERNAL PARTS (WELDED) SA 516 GR.60
HYDROGEN SERVICE HOT INSULATION SUPPORT FOR HORIZONTAL VESSEL 7-12-0033 INTERNAL PARTS (BOLTED) -
PIPE DAVIT SUPPORT FOR COLD INS. VESSELS 7-12-0034 CLIPS & ATTACHMENTS (EXTERNAL) SA 516 GR.60/ IS 2062 GR.B WELDED OVER BQCS PAD
JOB NO: UNIT NO: DESIGN DATA fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A307
;fuV l[;k IG REVISED AS MARKED BBC MkbZx uEcj REV
1 27.08.2014 1 JS NJB/PSV
MAKE-UP GAS COMPRESSOR K.O. esd&vi xSl dEislj ds- s- Me
NEW DELHI CLIENT : 0 17.10.2013 ISSUED FOR PURCHASE JS TT/DS BBC
DykbZV M/S B.P.C.L., KOCHI
B 16.05.2013 REVISED & REISSUED FOR BIDS/ENGG. B JS SUU/PSV TG DRUM (2nd STAGE) frh; LVst A307-0IG-16-46-DS-3014 1
bathfu;lZ bafM;k fyfeVsM PLANT : A 15.04.2013 ISSUED FOR COMMENTS GCP SUU/DS TG
DIESEL HYDROTREATER UNIT-(IREP) ITEM NO. IG - V - 114 A/B vAbVe uEcj th &oh& 114,@ch SHEET 1 OF 3
Hkkjr ljdkj dk midze IykaV REV DATE REVISION BY CHECKED APPROVED
FORMAT NO.3-1646-0111 REV.2 (06.12.2011) A3-420 X 297
Page 64 of 283
Page 65 of 283
Page 66 of 283
The drawing, design and details given below on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited, or used, except in the limited way permitted by written consent given by the lender to the
NOZZLES AND CONNECTIONS uksty o duSD'ku GENERAL NOTES (tujy uksV~l SPECIFICATIONS LisflfQds'lUl DESIGN DATA fMtkbu MkVk
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTI
ON NOTE-
PAD W
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SEC. VIII DIV.-1 2010 + ADDENDA 2011
ukfeuy 'kMwy o CLASS TYPE FACING 4
xT 1 ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE STATED. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm2g) 0.1-5.5
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. X SUPP. SPEC. FOR CS VESSELS 6-12-0002 DESIGN PRESSURE (kg/cm2g) INT. 7.5 EXT. -
SIGHT GLASSES FOR PRESSURE VESSELS 7-12-0017 REINFORCEMENT PAD/INSERT PLATE SA 516 Gr.70
SUPPORT RING AND BOLTING BAR 7-12-0021 NOZZLE NECK UPTO 250 NB SA 106 GR. B
SUPPORT RING SIZES FOR PACKED TOWERS 7-12-0022 NOZZLE NECK ABOVE 250 NB SA 516 Gr.70
LIFTING LUG TOP HEAD TYPE 7-12-0024 GASKET EXTERNAL SPIRAL WOUND GASKET WITH SS-316 METAL
`T' DENOTES CORRESPONDING NOMINAL THICKNESS OF FIRE PROOFING AND INSULATION SUPPORTS 7-12-0025 WINDING AND GRAFOIL FILLER MATERIAL WITH
X BRACKET FOR NAME PLATE 7-12-0029 EXTERNAL STUDS/BOLTS/NUTS SA 193 GR.B7 / SA 194 GR.2H
SUPPORTS FOR INTERNAL FEED PIPE 7-12-0032 SKIRT/ SUPPORT BASE IS 2062 GR.B
HOT INSULATION SUPPORT FOR HORIZONTAL VESSEL 7-12-0033 INTERNAL PARTS (WELDED) -
PIPE DAVIT SUPPORT FOR COLD INS. VESSELS 7-12-0034 INTERNAL PARTS (BOLTED) -
TYP. DETAILS OF WIRE MESH DEMISTER SUPPORTS 7-12-0036 CLIPS & ATTACHMENTS (EXTERNAL) SA 516 GR.70
JOB NO: UNIT NO: 3 15.01.2015 ISSUED FOR BIDS/ENGG. JSN RV/VIVEK TK DESIGN DATA fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A307
;fuV l[;k FCC-IFP 2 10.01.2014 REVISED AS MARKED JSN RRS/VIVEK TK MkbZx uEcj REV
NEW DELHI CLIENT :
BPCL-KR
1 02.12.2013 REVISED AS MARKED JSN RRS/VIVEK TK HP FLARE KNOCK OUT DRUM ,p ih Qys;j ukWd vkmV Me A307-IF-16-46-DS-3954 3
DykbZV 0 17.09.2013 ISSUED FOR PURCHASE JSN RRS/VIVEK TK
bathfu;lZ bafM;k fyfeVsM PLANT : A 29.04.2013 ISSUED FOR BIDS/ENGG. ANIL RKK/VIVEK TK SHEET 1 OF 2
IREP, KOCHI ITEM NO. IFP-V-804 vAbVe uEcj vkbZ ,Q ih&oh&804
Hkkjr ljdkj dk midze IykaV REV DATE REVISION BY CHECKED APPROVED
FORMAT NO.3-1646-0115 REV.2 (06.12.2011) A3-420 X 297
Page 67 of 283
X
X
Page 68 of 283
The drawing, design and details given below on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited, or used, except in the limited way permitted by written consent given by the lender to the
NOZZLES AND CONNECTIONS uksty o duSD'ku GENERAL NOTES (tujy uksV~l SPECIFICATIONS LisflfQds'lUl DESIGN DATA fMtkbu MkVk
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTI
ON NOTE-
PAD W
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SEC.VIII DIV.-1(2010)+ADDENDA.2011
ukfeuy 'kMwy o CLASS TYPE FACING 4
xT 1 ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE STATED. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm2g) INT. 0.05
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. X SUPP. SPEC. FOR CS VESSELS 6-12-0002 DESIGN PRESSURE (NOTE-18) (kg/cm2g) INT. 3.5 EXT. FV
E 1 50 160 300 WN RF
SEE
- VAPOR OUTLET (NOTE-20)
7 DIMENSIONS OF FLANGES FOR NOZZLES UPTO 600NB SHALL BE AS PER ASME X VESSEL TOLERANCES 7-12-0001 HEAT TREATMENT HEAD AS PER SPEC.
DRG B16.5 AND FOR NOZZLE ABOVE 600NB SHALL BE AS PER ASME B16.47 SUPPORT FOR HORIZONTAL VESSEL 7-12-0002 OPERATING MEDIUM -
SERIES B UNLESS SPECIFIED OTHERWISE.
SEE WOODEN PILLOWS FOR SADDLE SUPPORT 7-12-0003 SP. GRAVITY 1.04
F 1 50 160 300 WN RF - STEAM OUT (NOTE-21)
DRG 8 ID OF WELD NECK FLANGES SHALL MATCH WITH CORRESPONDING ID OF SKIRT BASE DETAILS 7-12-0004 WIND SPECIFICATION IS: 875
SEE NOZZLE PIPE. SKIRT OPENING DETAILS 7-12-0005 SEISMIC SITE SPECTRA + IS 1893
H 1 50 160 300 WN RF - FRESH MDEA INLET
DRG 9 NOZZLES SHALL BE STIFFENED WITH 4 NOS. 100 x 10 THK FLATS AT 90 DEG. ANGLE LEG SUPPORT 7-12-0006 CAPACITY (M ) 3 9.1
SEE 110 APART. MANHOLE,S1,S2 & PUMP NOZZLES SHALL BE STIFFENED WITH 8 NOS PIPE LEG SUPPORT 7-12-0007 PAINTING/CLEANING (NOTE-12) AS PER PAINTING SPEC.
G 1 200 100 150 WN RF GAUGE HATCH 10THKx R.F PAD WIDE FLATS EQUISPACED.
DRG xT BRACKET SUPPORT FOR VERTICAL VESSEL 7-12-0008 INSULATION THICKNESS (mm) NIL HOT COLD
1 PUMP VENDOR. INLET DEFLECTOR BAFFLE 7-12-0020 NOZZLE FLANGES / LWN SA 105 $
15 (b) PUMP NOZZLE COVER BLIND FLANGE WITH PUMP ASSEMBLY, NOZZLE-B, SUPPORT RING AND BOLTING BAR 7-12-0021 NOZZLE NECK UPTO 250 NB SA 106 GR. B $(SEAMLESS)
BOLTING & GASKET SHALL BE SUPPLIED BY PUMP SUPPLIER. SUPPORT RING SIZES FOR PACKED TOWERS 7-12-0022 NOZZLE NECK ABOVE 250 NB SA 516 Gr.60* +SA 20 S(1)
16 CATHODIC PROTECTION IS BY OTHERS. HOWEVER,CLIP FOR THE SAME TO BE PIPE DAVIT 7-12-0023 PIPE FITTINGS SA 234 GR. WPB $(SEAMLESS)
PROVIDED BY VENDOR. LIFTING LUG TOP HEAD TYPE 7-12-0024 GASKET EXTERNAL SPIRAL WOUND WITH SS 316 METAL WINDING &
GRAFOIL FILLER WITH CS OUTER RING AS PER
17 ALL CARBON STEEL MATERIAL SHALL BE PROCURED IN NORMALISED FIRE PROOFING AND INSULATION SUPPORTS 7-12-0025 ASME B16.20
& VACUUM DEGASSED CONDITION. X EARTHING LUG 7-12-0026
18 VESSEL IS SUBJECTED TO STEAM OUT CONDITION OF 0.5 Kg/Cm2(g) AT X NAME PLATE 7-12-0027 GASKET INTERNAL -
1850C X MANUFACTURER NAME PLATE 7-12-0028 EXTERNAL STUDS/BOLTS/NUTS SA 193 GR.B7M / SA 194 GR.2HM
19 ALL INTERNALS SHALL BE SIZED TO PASS THROUGH MANHOLE. X BRACKET FOR NAME PLATE 7-12-0029 INTERNAL STUDS/BOLTS/NUTS SS 304
20 LOCATE NOZZLES 'C' & 'E' NEAR OPPOSITE SEAMS. NAME PLATE FOR SMALL EQUIPMENT 7-12-0030 SKIRT/ SUPPORT SA 516 GR.60
21 STEAM OUT CONNECTION 'F' & VENT 'D' TO BE LOCATED AT EITHER ENDS. DETAILS OF FORGED NOZZLES 7-12-0031 SKIRT/ SUPPORT BASE -
X SUPPORTS FOR INTERNAL FEED PIPE 7-12-0032 INTERNAL PARTS (WELDED) SA 516 GR.60*+SA 20 S(1)/ SA 106 GR.B $(SEAMLESS)
HOT INSULATION SUPPORT FOR HORIZONTAL VESSEL 7-12-0033 INTERNAL PARTS (BOLTED) SA 516 GR.60*+SA 20 S(1)/ SA 106 GR.B $(SEAMLESS)
PIPE DAVIT SUPPORT FOR COLD INS. VESSELS 7-12-0034 CLIPS & ATTACHMENTS (EXTERNAL) SA 516 GR.60
TYP. DETAILS OF WIRE MESH DEMISTER SUPPORTS 7-12-0036 WRAPPER PLATE SA 516 GR.60
`T' DENOTES CORRESPONDING SHELL /HEAD THICKNESS * HIC RESISTANT + NACE MR 0103 COMPLIANT (REFER NOTE-17).
JOB NO: UNIT NO: DESIGN DATA fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A307
;fuV l[;k IST
1 15.01.2015 FINAL ISSUE NS CK AT MkbZx uEcj REV
NEW DELHI CLIENT :
M/S BPCL,KOCHI REFINERY
0 18.11.2013 ISSUED FOR PURCHASE NS CK AT MDEA SUMP DRUM ,eMhb, lEi Me A307-0IS-16-46-DS-3505 1
DykbZV B 24.10.2013 REVISED AS MARKED NS CK AT
bathfu;lZ bafM;k fyfeVsM PLANT : A 14.06.2013 ISSUED FOR BIDS/ENGG. JSN CK/BD AT
IREP,KOCHI ITEM NO. IST-V-504 vAbVe uEcj vkbZ,lVh&oh&504 SHEET 1 OF 3
Hkkjr ljdkj dk midze IykaV REV DATE REVISION BY CHECKED APPROVED
FORMAT NO.3-1646-0113 REV.2 (20.09.2011) A3-420 X 297
Page 69 of 283
Page 70 of 283
Page 71 of 283
The drawing, design and details given below on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited, or used, except in the limited way permitted by written consent given by the lender to the
NOZZLES AND CONNECTIONS uksty o duSD'ku GENERAL NOTES (tujy uksV~l SPECIFICATIONS LisflfQds'lUl DESIGN DATA fMtkbu MkVk
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTI
ON NOTE-
PAD W
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SEC.VIII DIV.-1 2010, ADDENDA 2011
ukfeuy 'kMwy o CLASS TYPE FACING 4
xT 1 ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE STATED. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm2g) INT. 1.07
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. X SUPP. SPEC. FOR CS VESSELS 6-12-0002 DESIGN PRESSURE (kg/cm2g) (NOTE-14) INT. 5.3 EXT. F.V.
JOB NO: UNIT NO: DESIGN DATA fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A307
;fuV l[;k IST MkbZx uEcj REV
NEW DELHI CLIENT :
M/s BPCL-KOCHI REFINERY
1 15.01.2015 FINAL ISSUE JSN CK/BD AT REGENERATOR OVERHEAD DRUM fjtujsVj vksojgSM Me A307-0IS-16-46-DS-3502 1
DykbZV 0 18.11.2013 ISSUED FOR PURCHASE JSN CK/BD AT
bathfu;lZ bafM;k fyfeVsM PLANT : A 17.06.2013 ISSUED FOR BIDS/ENGG. JSN CSM/CK AT
Hkkjr ljdkj dk midze IykaV IREP,KOCHI
REV DATE REVISION BY CHECKED APPROVED
ITEM NO. IST-V-502 vAbVe uEcj vAb,lVh&oh&502 SHEET 1 OF 2
FORMAT NO.3-1646-0119 REV.2 (06.12.2011) A3-420 X 297
Page 72 of 283
Page 73 of 283
fjtujsVj
vksojgSsM Me
The drawing, design and details given below on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited, or used, except in the limited way permitted by written consent given by the lender to the
NOZZLES AND CONNECTIONS uksty o duSD'ku GENERAL NOTES (tujy uksV~l SPECIFICATIONS LisflfQds'kUl DESIGN DATA fMtkbu MkVk
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTI
ON NOTE-
PAD W
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SEC. VIII DIV.1 2010, ADDENDA 2011
ukfeuy 'kMwy o CLASS TYPE FACING 4
xT 1 ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE STATED. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm 2g) 36.4
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. X SUPP. SPEC. FOR CS VESSELS 6-12-0002 DESIGN PRESSURE (kg/cm 2g) INT. 44.3 EXT. -
HYDROGEN SERVICE
FILE NAME : A307-0IV-16-46-DS-3112-2-1.DWG
JOB NO: UNIT NO: 2 29.05.2014 REVISED AS MARKED 2 JS RSU/PSV BBC DESIGN DATA fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A307
;fuV l[;k IV
REVISED AS MARKED BBC MkbZx uEcj REV
1 15.01.2014 1 JS RSU/PSV
MAKE-UP COMPRESSOR esd&vi dEiszlj lsdUM LVst
NEW DELHI CLIENT : 0 24.10.2013 ISSUED FOR PURCHASE JS RSU/DS BBC
DykbZV M/S B.P.C.L., KOCHI
B 16.05.2013 REVISED & REISSUED FOR BIDS/ENGG. B JS SUU/PSV TG 2nd STAGE SUCTION KO DRUM lD'ku dss Me A307-0IV-16-46-DS-3112 2
bathfu;lZ bafM;k fyfeVsM PLANT : VGO HYDROTREATER UNIT, INTEGRATED A 04.04.2013 ISSUED FOR COMMENTS GCP SUU/PSV TG
ITEM NO. IV - V - 112 A/B vAbVe uEcj oh & oh & 112 ,@ch SHEET 1 OF 2
Hkkjr ljdkj dk midze IykaV REFINERY EXPANSION PROJECT (IREP) REV DATE REVISION BY CHECKED APPROVED
FORMAT NO.3-1646-0111 REV.2 (20.09.2011) A3-420 X 297
Page 74 of 283
Page 75 of 283
Page 76 of 283
CLIENT : BPCL KR
PROJECT : IREP
Rev.
Date Purpose Prepared by Reviewed by Approved by
No
Page 79 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 2 OF 48
Abbreviations:
AS : Alloy Steel
CS : Carbon Steel
DFT : Dry Film Thickness
DM : De-mineralized
GI : Galvanized Iron
ID : Internal Diameter
IRN : Inspection Release Note
LTCS : Low Temperature Carbon Steel
MS : Mild Steel
NB : Nominal Bore
OD : Outside Diameter
RCC : Reinforced Cement Concrete
SS : Stainless Steel
WFT : Wet Film Thickness
Page 80 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 3 OF 48
CONTENTS
1.0 General. 4
2.0 Scope 4
3.0 Reference Codes & Standards.... 6
4.0 Equipment 7
5.0 Surface Preparation, Shop Primer,Coating Application & Repair and Documentation.. 7
6.0 Paint Materials.. 16
7.0 Coating Systems... 21
8.0 Coating System for Gratings, Rolling & Stationery Ladders, Spiral Stairways and
Hand Rails in All Location... 23
9.0 Coating System for Offsite Area (Inland Plants). 24
10.0 Coating System For Unit Areas as well as DM, CPP, Cooling Tower of Inland Plants
and for All Areas (Unit, Offsite, DM, CPP, etc.) of Coastal Plants. 25
11.0 Coating System for Effluent Treatment Plant (ETP)... 27
12.0 External Coating Systems for Uninsulated Carbon Steel and Low Alloy Steel Storage
Tanks (For All Plant Locations, Coastal or Inland) - All Process Units & Off-Sites . 28
13.0 Internal Coating Systems for Carbon Steel and Low Alloy Storage Tanks - All
Process Units & Off-Sites 30
14.0 Coating Systems for External Side of Underground Carbon Steel Plant Piping and
Underground Vessels... 32
15.0 Coating Under Insulation (Coastal Or Inland Plants). All Units Areas & Off-Sites 33
16.0 Coating System for Carbon Steel Components of Coolers / Condensers (Internal
Protection) for Fresh Water Service. 34
17.0 Coating System (Internal Protection) for Galvanized or Non Ferrous or Stainless
Steel/ Duplex Stainless Steel Components of Coolers/ Condensers for Fresh Water
Service.......................................................................................................................... 35
18.0 Storage.. 35
19.0 Paint colour code for piping and equipment ... 35
20.0 Identification of Vessels, Piping etc. 41
21.0 Painting for Civil Defence Requirements 41
22.0 Quality Control, Inspection and Testing.. 42
23.0 Guarantee. 45
24.0 Qualification Criteria of Painting Contractor/Sub-Contractor. 45
25.0 Qualification/Acceptance Criteria for Paint Coating System... 45
26.0 Method of Sampling & Dispatch for Laboratory Testing 48
Page 81 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 4 OF 48
1.0 GENERAL
1.1 This technical specifications shall be applicable for the work covered by the contract, and
without prejudice to the provisions of various international codes of practice, standard
specifications etc. It is understood that contractor shall carry out the work in all respects with
the best quality of materials and workmanship and in accordance with the best engineering
practice and instructions of Engineer-In-Charge.
1.2 Wherever it is stated in the specification that a specific material is to be supplied or a specific
work is to be done, it shall be deemed that the same shall be supplied or carried out by the
contractor.
Any deviation from this standard without written deviation permit from appropriate
authority will result in rejection of job.
1.3 This specification covers the requirement for protective coating for new construction.
2.0 SCOPE
2.1 Scope of work covered in the specification shall include, without being limited to the
following.
2.1.1 This specification defines the requirements for surface preparation, selection and application
of primers and paints on external surfaces of equipment, vessels, machinery, piping, ducts,
steel structures, external & internal protection of storage tanks for all services and chimneys
if any. The items listed in the heading of tables of paint systems is indicative only, however,
the contractor is fully responsible for carrying out all the necessary painting, coating and
lining on external and internal surfaces as per the tender requirement.
2.2.1 The following surfaces and materials shall require shop, pre-erection and field painting:
All uninsulated Carbon Steel & Alloy Steel equipments like vessels, Columns, storage
Tanks, Exchangers if any, parts of boilers etc.
All uninsulated carbon steel and low alloy plant and related piping, fittings and valves
(including painting of identification marks), furnace ducts and stacks.
All insulated parts of vessels, boilers, chimneys, stacks, piping and steam piping and if
any other insulated items present.
All structural steel work, pipe, structural steel supports, walkways, handrails, ladders,
platforms etc.
Flare lines, external surfaces of MS chimney with or without refractory lining and
internal surfaces of MS chimney without refractory lining. (If present)
Page 82 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 5 OF 48
Supply of all primers, paints and all other materials required for painting (other than
Owner supplied materials)
Painting under insulation for carbon steel, alloy steel and stainless steel as specified.
Repair work of damaged pre-erection/ fabrication and shop primer and weld joints in the
field/site before and after erection as required.
All CS Piping, equipments, storage tanks and internal surfaces of RCC tanks in ETP
plant.
Quality control, testing and inspection during all stages of work (surface preparation,
application of coating and testing of furnished coating).
2.2.2 The following surfaces and materials shall not require painting in general. However, if there
is any specific requirement by the owner, the same shall be painted as per the relevant
specifications:
2.3 Documents
2.3.1 The contractor shall perform the work in accordance with the following documents issued to
him for execution of work.
Page 83 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 6 OF 48
2.4 Unless otherwise instructed, final paint coating (i.e., application of field primer,
wherever required, intermediate and top coats) on pre-erection/ shop primed
equipments shall be applied at site, only after all welding, testing on systems are
completed as well as after completion of steam purging wherever required .
2.5 Changes and deviations required for any specific job due to clients requirement or otherwise
shall be referred to EIL for deviation permit.
3.1 Without prejudice to the provision of Clause 1.1 above and the detailed specifications of the
contract, latest editions of the following codes and standards are applicable for the work
covered by this contract.
The latest editions of any of the following standards shall be followed for surface
preparation:
3.2.1 ISO 8501-1 / SIS-05 59 00: ISO standard for Preparation of steel substrates before
application of paints and related products. This standard contains photographs of the various
standards on four different degrees of rusted steel and as such is preferable for inspection
purpose by the Engineer-In-Charge.
3.2.2 Steel Structures Painting Council, U.S.A. (Surface Preparation Specifications (SSPC-SP).
3.2.4 Various International Standards equivalent to Swedish Standard for surface preparations are
given in Table-I.
3.3 The contractor shall arrange, at his own cost, to keep a set of latest edition of above standards
and codes at site.
3.4 The paint manufacturer's instructions shall be followed as far as practicable at all times for
best results. Particular attention shall be paid to the following:
Page 84 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 7 OF 48
b. Surface preparation prior to painting shall be followed as per Table 8.0 to 16.0 of
this standard shall be followed.
4.0 EQUIPMENT
4.1 All tools, brushes, rollers, spray guns, blast material, hand power tools for cleaning and all
equipments, scaffolding materials, shot & grit blasting equipments & air compressors etc.
required to be used shall be suitable for the work and all in good order and shall be arranged
by the contractor at site and in sufficient quantity. The manufacturers test certificates / data
sheets for all the above items shall be reviewed by Engineer-in-charge at site before start of
work.
4.2 Mechanical mixer shall be used for paint mixing operations in case of two pack systems
except that the Engineer-In-Charge may allow the hand mixing of small quantities at his
discretion in case of specific requirement for touch up work only.
5.1 General
5.1.1 In order to achieve the maximum durability, one or more of following methods of surface
preparation shall be followed, depending on condition of surface to be painted and as
instructed by Engineer-In-Charge. Adhesion of the paint film to surface depends largely on
the degree of cleanliness of the metal surface. Proper surface preparation contributes more to
the success of the paint protective system.
5.1.2 Mill scale, rust, rust scale and foreign matter shall be removed fully to ensure that a clean and
dry surface is obtained. Unless otherwise specified, surface preparation shall be done as per
provisions of relevant tables given elsewhere in this specification. The minimum acceptable
standard, in case of thermally sprayed metal coatings, in case of mechanical or power tool
cleaning it shall be St. 3 or equivalent. In case of blast cleaning it shall be Sa 2-1/2 as per
Swedish Standard SIS-055900 (latest edition) or SSPC-SP or ISO 8501-01.Blast cleaning
shall be Sa 3 as per Swedish Standard in case thermally sprayed metal coatings.
Before surface preparation by blast cleaning, the surface shall be degreased by aromatic
solvent to remove all grease, oil etc.
5.1.3 Irrespective of whether external or internal surface to be coated, blast cleaning shall not be
performed where dust can contaminate surfaces undergoing such cleaning or during humid
weather conditions having humidity exceed 85%. In case of internal coating of storage tanks,
dehumidifier shall be used, to control humidity level below 60%. Dehumidifier should
depress the dew point of air in the enclosed space, sufficient enough so as to maintain it 3C
Page 85 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 8 OF 48
below the metal substrate temperature during centre period of blasting and coating
application. During the interval time between application of primer coat and subsequent
intermediate and top coats or between blast cleaning completion and start of application of
primer coat, dehumidifier unit should be in continuous operation to ensure that no
condensation occurs on substrate.
Dehumidifier should be able to maintain grain drop (moisture removal) at the rate of 25
grains per pound of air per hour. Dehumidifier should have capacity of at least 2 air changes
per hour of the enclosed space. All necessary psychometric data should be collected by
contractor for the given site conditions before starting operation of dehumidifier to ensure
that desired values of dew point, moisture content in enclosed scope is achieved.
Dehumidification to be maintained round the clock for surface preparation and painting till
the total coating application is over.
Dehumidifier shall not be stopped under any condition till the entire blasted surface is primed
to the satisfaction of the technical representative of the paint manufacturer interested with
quality assurance for the work. In case the dehumidifier breaks down in middle of the job, the
same shall be replaced at the risk and the cost of the contractor and the entire unfinished
work shall be repeated.
5.1.4 The Engineer in-charge shall have the right to disallow usage of dehumidifier if the
performance is not meeting the specified requirements. Under such circumstances the
contractor shall remove the equipment and replace the same with another equipment to
provide satisfactory results without any additional cost to the owner.
5.1.5 Irrespective of the method of surface preparation, the first coat of primer must be applied by
airless spray/ air assisted conventional spray if recommended by the paint manufacturer on
dry surface. This should be done immediately and in any case within 4 hours of cleaning of
surface. However, at times of unfavorable weather conditions, the Engineer-In-Charge shall
have the liberty to control the time period, at his sole discretion and/or to insist on re-
cleaning, as may be required, before primer application is taken up. In general, during
unfavorable weather conditions, blasting and painting shall be avoided as far as practicable.
5.1.6 The external surface of R.C.C. chimney to be painted shall be dry and clean. Any loose
particle of sand, cement, aggregate etc. shall be removed by scrubbing with soft wire brush.
Acid etching with 10-15% HCL solution for about 15 minutes shall be carried and surface
must be thoroughly washed with water to remove acid & loose particles and then dried
completely before application of paint.
The surfaces shall be blast cleaned using one of the abrasives like angular chilled cast iron or
steel grit, copper slag or Nickel slag, A12O3 particles at pressure of 7kg/cm2 at an appropriate
distance and angle depending of nozzle size maintaining constant velocity and pressure.
Chilled cast iron or steel shall be in the form of shot or grit of size in the range of G16 G42
conforming to SSPC AB1 and S250 grade size of steel shots (maximum) to obtain a desired
surface profile of 35-50 microns trough to peak. For all other abrasives, size shall be in the
range of G16 G24. The combination of steel grits and shots shall be normally in the ratio of
3:1. The quality of abrasives shall be free from contaminants and impurities and shall meet
Page 86 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 9 OF 48
the requirements of SSPC AB1. Compressed air shall be free from moisture and oil. The
blasting nozzles should be venturi style with tungsten carbide or boron carbide as the
materials for liners. Nozzles orifice may vary from 3/16 to . On completion of blasting
operation, the blasted surface shall be clean and free from any scale or rust and must show a
grey white metallic luster. Primer/first coat of paint shall be applied within 4 hours of surface
preparation. Blast cleaning shall not be done outdoors in bad weather without adequate
protection or when there is dew on the metal, which is to be cleaned. Surface profile shall be
uniform to provide good key to the paint adhesion (i.e. 35 to 50 microns). If possible
vacuum collector shall be installed for collecting the abrasives and recycling.
Power tool cleaning shall be done by mechanical striking tools, chipping hammers, grinding
wheels or rotating steel wire- brushes. Excessive burnish of surface shall be avoided as it can
reduce paint adhesion. On completion of cleaning, the detached rust mill scale etc. shall be
removed by clean rags and /or washed by water or steam and thoroughly dried with
compressed air jet before application of paint.
For equipments on which application of total protective coating (Primer + Intermediate + top
coat) is carried out at shop, compatibility of finish coat with primer should be checked with
paint manufacturer. If the shop coat is in satisfactory condition showing no major defect upon
arrival at site, the shop coat shall not be removed.
5.4 Shop coated equipments (coated with Primer & finishing coat) should not be repainted unless
paint is damaged. Repair shall be carried out as per Table 7.2 of paint systems depending
upon compatibility of paint.
5.5 Shop primed equipment and surfaces will only be 'spot cleaned' in damaged areas by means
of power tool brush cleaning or hand tool cleaning and then spot primed before applying one
coat of field primer unless otherwise specified. If shop primer is not compatible with field
primer then shop coated primer should be completely removed before application of selected
paint system for particular environment.
5.6 For Package units/equipment, shop primer should be as per the paint system given in this
specification. However, manufacturers standard can be followed after review.
As mentioned in section 2.4, all coating application at field (field primer, intermediate and
top coat) on equipments, structures, piping, etc, shall be carried out only after its erection and
all welding, testing, steam purging (wherever carried out) have been completed.
All paint coatings shall be applied by airless spray excepting at the following special
cases where application can be carried out by brush subject to suitability of the
application of the paint product by brush.
- Spot repair
- Stripe coating on edges
- Small bore parts not suitable for spray application.
Page 87 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 10 OF 48
Irregular surfaces such as sharp edges, welds, small brackets, and interstices may stripe
coated to ensure specified DFT is achieved. Paint manufacturer recommendation
should be followed before deciding for brush application.
5.7.1 Surface shall not be coated in rain, wind or in environment where injurious airborne elements
exists, when the steel surface temperature is less than 5oF above dew point when the relative
humidity is greater than 85% or when the temperature is below 40oF and when the
ambient/substrate temp is below the paint manufacturers recommended temperature of
application and curing. De-humidifier equipment shall be used to control RH and Dew point.
The paint application shall not be done when the wind speed exceeds 20km per hour.
5.7.2 Blast cleaned surface shall be coated with one complete application of primer as soon as
practicable but in no case later than 4 hrs the same day.
5.7.3 To the maximum extent practicable, each coat of material shall be applied as a continuous
film uniform thickness free of probes. Any spots or areas missed in application shall be
recoated and permitted to dry before the next coat is applied. Applied paint should have the
desired wet film thickness.
5.7.4 Each coat shall be in proper state of cure or dryness before the application of succeeding
coat. Material shall be considered dry for recoating when an additional coat can be applied
without the development of any detrimental film irregularities, such as lifting or loss of
adhesion of the under coat. Manufacturer instruction shall be followed for inter coat interval.
5.7.5 When the successive coat of the same colour have been specified, alternate coat shall be
tinted, when practical, sufficiently to produce enough contrast to indicate complete coverage
of the surface. The tinting material shall be compatible with the material and not detrimental
to its service life and shall be recommended by the original paint manufacturer.
5.7.6 Airless spray application shall be in accordance with the following procedure: as per steel
structure paint Manual Vol.1 & Vol.2 by SSPC, USA, Air less spray relies on hydraulic
pressure rather than air atomization to produce the desired spray. An air compressor or
electric motor is sued to operate a pump to produce pressures of 1000 to 6000 psi. paint is
delivered to the spray gun at this pressure through a single hose within the gun, a single paint
stream is divided into separate streams, which are forced through a small orifice resulting in
automization of paint without the use of air. This results in more rapid coverage with less
over spray. Airless spray usually is faster, cleaner, more economical and easier to use than
conventional air spray.
Airless spray equipment is mounted on wheels, and paint is aspirated in a hose that sucks
paint from any container, including drums. The unit shall have in built agitator that keep the
paint uniformly mixed during the spraying. The unit shall consist of in built strainer. Usually
very small quantity of thinning is required before spray. In case of high build epoxy coating
(two pack). 30:1 pump ratio and 0.020-0.023 tip size will provide a good spray pattern.
Ideally fluid hoses should not be less than 3/8 ID and not longer than 50 ft to obtain
optimum results.
Page 88 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 11 OF 48
a. Brushes shall be of a style and quality that will enable proper application of paint.
b. Round or oval brushes are most suitable for rivets, bolts, irregular surface, and
rough or pitted steel. Wide flat brushes are suitable for large flat areas, but they
shall not have width over five inches.
5.7.8 For each coat the painter should know the WFT corresponding to the specified DFT and
standardize the paint application technique to achieve the desired WFT. This has to be
ensured in the qualification trial.
5.8.1 No coat shall be applied until the preceding coat has dried. The material shall be considered
dry for re-coating when another coat can be applied without the development of any film
irregularities such as lifting or loss of adhesion of undercoats. Drying time of the applied coat
should not exceed maximum specified for it as a first coat; if it exceeds the paint material has
possibly deteriorated or maxing is faulty.
5.8.2 No paint shall be force dried under conditions which will cause chalking, wrinkling,
blistering formation of pores, or detrimentally affect the conditions of the paint.
5.8.3 No drier shall be added to paint on the job unless specifically called for in the manufacturers
specification for the paint.
5.8.4 Paint shall be protected from rain, condensation, contamination, snow and freezing until dry
to the fullest extent practicable.
5.9.1 Where pre erection shop primer has been damaged at isolated localized spots during handling
and transportation, or after erection / welding, the repair of damaged coating of pre-erection /
pre-fabrication or shop primer shall be done as given below and as per the Table 7.2 of this
specification.
5.9.2 Repair of damaged inorganic zinc silicate pre-erection / pre-fabrication or shop primer
(F9) after erection / welding in the design temperature of -90oC to 400oC and damaged
silicone aluminium (F-12) pre-erection / pre-fabrication or shop primer after erection /
welding for design temperature range of 401 550 C.
Surface Preparation: Quickly remove the primer from damaged area by mechanical scraping
and emery paper conforming to SSPC-SP-3 to expose the white metal. Blast clean the
surface, if possible. Feather the primed surface over the intact adjacent surface surrounding
the damaged area by emery paper.
Page 89 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 12 OF 48
Primer coating: One coat of F-9 shall be applied wherever damage was observed on pre-
erection / pre fabrication or shop primer of inorganic zinc silicate coating (F-9). Similarly
one coat of F-12 shall be applied wherever damage observed on pre-erection / pre-
fabrication shop primer of silicone aluminium (F-12).
5.9.3 Wherever if damaged areas are found extensive and spread over large areas, then entire pre-
erection / pre-fabrication or shop primer shall be removed by blasting to achieve SSPC-SP-
10 then entire blasted surface shall be primed again with F-9 or F-12 as applicable for the
intended design temp. (See note under table 7.2).
5.10.1 Shop priming/pre-erection priming with F9 or F12 shall be done only on blasted surface
(SSPC-SP-10)
5.10.2 Shop priming / pre-erection priming with F9 or F12 shall be done only with airless spray.
The paint system to be applied for a specific job shall be arrived at sequentially as given
below:
- Identify the environment from area classification details and chose the appropriate table.
- Identify the specific field paint system and surface preparation requirement from the above
identified table and temperature range.
- Identify the shop priming requirement from Table 7.1 based on compatibility of the above
paint system.
- Identify the need of repair of shop primer and execute as per Table 7.2.
5.11.1 A written quality plan with procedure for qualification trials and for the actual work
including test and inspection plan & procedure for approval before start of work.
5.11.2 Daily progress report with details of weather conditions, particular of applications, no of
coats and type of materials applied, anomalies, progress of work versus program.
5.11.3 Results of measurement of temperatures relative humidity, surface profile, film thickness,
holiday detection, adhesion tests with signature of appropriate authority.
5.11.4 Particulars of surface preparation and paint application during trials and during the work.
Page 90 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 13 OF 48
The coating applicator must maintain a job record consisting of all the information as per
5.11.2 -5.11.7 above as well as the approved procedure of work (5.11.1 above). The job
record consisting of information as required in accordance to 5.11.2 5.11.7 shall be entered
on daily basis and should be daily signed by Engineer-in-charge.
Page 91 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 14 OF 48
VARIOUS INTERNATIONAL
Sl. STANDARDS (EQUIVALENT)
DESCRIPTION REMARKS
No. ISO 8501-1/ SSPC-SP, NACE,
SIS-05 59 00 USA USA
Manual or hand tool
cleaning
Page 92 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 15 OF 48
VARIOUS INTERNATIONAL
Sl. STANDARDS (EQUIVALENT)
DESCRIPTION REMARKS
No. ISO 8501-1/ SSPC-SP, NACE,
SIS-05 59 00 USA USA
Commercial Blast For steel required to
be painted with
Blast cleaning until at least conventional paints
two-third of each element of for exposure to
3.3 SA 2 SSPC-SP-6 NO.3
surface area is free of all mildly corrosive
visible residues with desired atmosphere for longer
surface profile. life of the paint
systems.
Brush-off Blast
Page 93 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 16 OF 48
Paint manufacturers shall furnish the characteristics of all paints materials on original printed
literature, along with the test certificate for all specified characteristics given in this
specification. All the paint materials shall be of first quality and conform to the following
general characteristics as per the tables 6.1, 6.2, 6.3 and 6.4.
PAINT MATERIALS
Page 94 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 17 OF 48
PAINT MATERIALS
Sl.
DESCRIPTION F-2 F-3 F-6A/B F-6C F-7
No
Acrylic Chlorinated High build coal
Epoxy-High Build Solvent less
1 Technical name Polyurethane rubber based tar epoxy
coating epoxy coating
finish paint finish paint coating.
Single pack F-6A Two-pack
Two pack, Two pack
plasticised Aromatic amine
cured with polyamide
Two-pack chlorinated cured epoxy resin
Amine cured epoxy
aliphatic rubber based medium suitably
Type and Adduct; resin blended
2 isocynate medium with pigmented.
composition catalyzed with coaltar
cured acrylic chemical and F-6B: polyamide
epoxy resin medium,
finish paint. weather cured epoxy resin
suitably suitably
resistant medium suitably
pigmented pigmented
pigments. pigmented
3 Volume Solids % 40 3 382 603 991 653
DFT (Dry Film
4 thickness) per coat in 30-40 30-40 100-125 200-500 100-125
microns
Theoritical covering
5 capacity in 11-15 11-15 5-6 2-3 5.2-6.5
M2/coat/litre
Weight per liter in
6 1.150.03 1.150.03 1.420.03 1.400.03 1.400.03
kgs/litre
7 Touch dry at 30oC 30 minutes 30 minutes. 3 hrs. 3 hrs. 4 hrs.
Hard dry at 30oC
16 hrs
(max) 48 hrs
8 hrs
8 Full cure at 30oC (for 8 hrs 16 hrs
5 days
immersion/ high 5 days
temperature service)
Over-coating interval Min.12 hrs. Min.: Min.: Overnight Min.: 8 hrs. Min.: 24 hrs
9
at 30 oC Overnight Max.: 5 days Max.: 48 hrs. Max.: 5 days.
Pot life (approx.) at
6-8 hrs. Not
10 30oC for two 4-6 hrs 30 minutes 4-6 hrs.
applicable
component paints
Temperature 120oC(Dry
o o
Resistance 80 C 60 C service), 125oC
80oC
11 (minimum) Dry service Immersion 50oC Immersion
Dry service
min service (Immersion service
service)
Page 95 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 18 OF 48
PAINT MATERIALS
Sl.
DESCRIPTION F-8 F-9 F-11 F-12
No
Self priming type Heat resistant
Heat resistant
surface tolerant synthetic medium
silicone
high build epoxy Inorganic zinc based two pack
1 Technical name Aluminium paint
coating (complete silicate coating Aluminium paint
suitable upto
rust control suitable upto
500oC dry temp.
coating). 250oC dry temp.
A two pack air
Two pack epoxy drying self curing
resin based solvent based
Heat resistant
suitable inorganic zinc Single pack
synthetic medium
pigmented and silicate coating with silicone resin
based two pack
2 Type & composition capable of minimum 80% zinc based medium
Aluminium paint
adhering to content on dry film. with Aluminium
suitable upto
manually The final cure of flakes.
250oC.
prepared surface the dry film shall
and old coating. pass the MEK rub
test.
3 Volume Solids % 783 603 380.03 202
DFT (Dry Film
4 thickness) per coat in 100-125 65-75 15-20 15-20
microns
Theoritical covering
5 capacity in M2/coat/ 6.0-7.2 8-9 10-12 8-10
litre
Weight per liter in
6 1.410.03 2.30.03 0.950.03 1.000.03
kgs/litre
Touch dry at 30oC
7 3 hrs. 30 minutes. 3 hrs. 30 minutes.
(maximum)
Hard dry at 30oC
(maximum) 24 hrs 12 12 hrs 24 hrs
8 Full cure 30oC (for
immersion /high 5days NA NA NA
temperature service)
Min.: 12 hrs.at 20oC
9 Over-coating interval Min.: 10 hrs Min. 24 hrs Min.: 24 hrs
& 50 % RH
o
Pot life at 30 C for two
10 90 minutes. 4-6 hrs. Not applicable Not applicable
component paints
o o o
Temperature 80 C 400 C 250 C 500oC
11
Resistance (minimum) Dry service Dry service Dry service Dry service
Page 96 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 19 OF 48
PAINT MATERIALS
Sl.
DESCRIPTION F-14 F-15 F-16 F-17
No
Ambient temperature
curing Poly Siloxane
Two-component Two component
coating/High build
Epoxy phenolic solvent free type
cold applied inorganic
coating cured with high build epoxy
copolymer based
Polyamine cured Polyamine adduct phenolic/novalac
1 Technical name aluminium coating
coal tar epoxy hardner system epoxy phenolic
suitable for under
(primer + coating cured with
insulation coating of
intermediate coat Polyamine adduct
CS and SS piping for
+ finish paint) hardner system
high temperature
service.
Two pack ambient Two component
Specially
temperature curing Amercoat 738 from solvent free type
formulated
epoxy phenolic PPG Protective & high build epoxy
polyamine cured
coating system Marine Coatings or phenolic/novalac
2 Type & composition coal tar epoxy
suitable for Intertherm 751 CSA of epoxy phenolic
suitable for
application under International (Akzo coating cured with
application under
insulation of Nobel). Note: 6 Polyamine adduct
insulation
CS/SS piping hardner system
3 Volume Solids % 703 703 602 98-100
DFT (Dry Film
4 thickness) per coat in 100-125 75-100 75-100 125- 150
microns
Theoritical covering
5 capacity in M2/coat/ 5-8 4-5 7.0- 9.0 6.5 - 8
litre
Weight per liter in
6 1.450.03 1.650.03 1.3 1.7
kgs/litre (mix paint)
Touch dry at 30oC
7 4 hrs 3 hrs 1 hr 2 hrs
(maximum)
Hard dry at 30oC
(maximum) 24 hrs 24 hrs 16 hrs 24 hrs
8 Full cure 30oC (for
immersion /high 168 hrs (7 days) 168 hrs (7 days) - 168 hrs (7 days)
temp. service)
Over-coating interval Min. 6 hrs Min. 36 hrs Min.16 hrs Min. 16 hrs
9
Max.5 days Max.21 days Max. Not applicable Max.21 days
Pot life at 30oC for
10 two component 4 hrs 4-6 hrs 1 hr 1 hr
paints
Temperature a) upto 400 C for C.
Resistance o o Steel & S. Steel for
-45 C to 150 C
-45oC to 125oC Intertherm 751 CSA
under insulation & -45oC to 150oC for
11 under insulation b) upto 480 C for C.
immersion immersion service
And immersion Steel & upto 600 C
(Note: 5)
for S. Steel for
Amercoat 738
Page 97 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 20 OF 48
2. All primers and finish coats should be cold cured and air drying unless otherwise
specified.
3. All paints shall be applied in accordance with manufacturer's instructions for surface
preparation, intervals, curing and application. The surface preparation, quality and
workmanship should be ensured. In case of conflict between this specification and
manufacturers recommendation, the same shall be clarified through EIL SMMS
department.
4. Technical data sheets for all paints shall be supplied at the time of submission of
quotations.
5. F-15: Two-component Epoxy phenolic coating cured with Polyamine adduct hardner
system (primer + intermediate coat + finish paint) suitable upto 225C (Intertherm 228
from M/s Akzo Nobel Coatings India Pvt Ltd. Bangalore). For all other companies, the
temperature resistance shall be a maximum of 150C.
6. F-16: Ambient temperature curing epoxy poly siloxane Coating or high build cold
applied inorganic co-polymer based aluminium coating.
Amercoat 738 from PPG Protective & Marine coatings. Mumbai, is suitable up to
480oC for CS surfaces and 600oC for SS surfaces.
Intertherm 751 from Akzo Nobel Coatings India Pvt Ltd. Bangalore, Inorganic co-
polymer cold applied Aluminium spray coating is suitable upto 400oC of CS & SS
surfaces.
Page 98 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 21 OF 48
The coating system should be selected based on the Plant location as given below:
- For all unit areas including DM, CPP and Cooling Tower: Table 10.0 to be
followed
- For offsite area, as well as all unit area including DM, CPP, Cooling Tower:
Table 10.0 to be followed
c) For external surface of above ground tanks, table 12.0 to be followed for all
locations (Inland or coastal)
Notes:
2. Primers & Finish paints covered in Tables 8.0 to 17.0 are listed in Table 7.1.
Page 99 of 283
JOB SPECIFICATION JOB SPECIFICATION No.
FOR SURFACE PREPARATION A307-000-06-42-PLS-01
Rev.1
AND PROTECTIVE COATING PAGE 22 OF 48
TABLE 7.1: LIST OF PRIMERS & FINISH COATS COVERED IN TABLE NOS. 8 to 18.0
PRIMERS
P-2 Chlorinated rubber zinc Phosphate Primer
P-4 Etch Primer/Wash Primer
P-6 Two component Epoxy Zinc Phosphate Primer cured with polyamine hardener
Single pack, cold galvanizing compounds containing minimum 92% electrolytic zinc in dry film.
P-7
make ZINGA, LOCKTITE (of HENKEL) or ZRC
Total DFT
Sl. Surface
Design Temp. in oC Coating System in Microns Remarks
No. Preparation
(min.)
NOTES:
1 The application and repair of pre-erection/pre-fabrication or Shop Primer given in above tables
shall be done for all the items to be painted. In case the damages of primer are severe and spread
over large area, entire primer shall be removed by blasting to achieve SSPC-SP-10 and surfaces
to be primed again with F-9 or F-12 as applicable.
Design
Sl. Total DFT
Temp. in Coating System
No. o in Microns (min.)
C
Hot Dip Galvanizing to 80-85 microns (600-610
80 microns of finish coat
gm/m2)as per IS 4759, 2629, 4736, 2633 +
8.1 Up to 60 (excluding the thickness of
1 coat of P-6 @ 40 DFT/coat + 1 coat of F-2 @ 40
galvanizing )
microns DFT/coat
NOTES:
2 Repair of the damaged area of galvanized coatings due to welding during erection shall be
carried out as per recommended practice IS 11759 using cold galvanizing spray process.
Organic Paint systems are not acceptable for repair.
3 After repair of damaged galvanized coating by Cold Galvanized, the repaired area shall be top
coated with paint system as given in Table 8.0 above (i.e., 1 coat of P-6 @ 40 DFT/coat + 1
coat of F-2 @ 40 DFT/coat).
* Flare line within unit or offsite areas shall be coated as per Clause 10.3 of Table 10.0, but
having finish coat of 2 coats of F-12.
NOTES:
1 The list of items given in the heading of the above table is not exhaustive. There may be more
items for a particular contract where these specifications are used. The Contractor is fully
responsible for completing painting including prefabrication primer for all the items supplied
and fabricated through his scope of work as per tender document.
2 If the Pre-erection/Pre-fabrication & Shop Primer has already been completed, the same shall not
be repeated again in the field. In case the damages of primer are severe and spread over large
areas, the engineer-in-charge may decide & advise re-blasting and priming again. Repair of pre-
fabrication/pre-erection primer, if required, shall be done as per Table 7.2.
3 In case of Paint systems as per Sl. Nos. 9.5 and 9.6, the color bands shall be applied over the
Aluminum paint as per the Color coding requirement for specific service of piping given in
Clause 19.0.
4 All coating system including surface preparation, primer, and finish coat for piping shall be done
at field only.
TABLE 10.0 COATING SYSTEM FOR UNIT AREAS AS WELL AS DM, CPP,
COOLING TOWER OF INLAND PLANTS AND FOR ALL AREAS (UNIT,
OFFSITE, DM, CPP, etc.) OF COASTAL PLANTS
SSPC-SP-10; a) No over-
10.1 -90 to -15 1coat of F-9 @ None None 65-75 coating to be
65-75 DFT/coat done on
F-9 as it will
2 coats of F-6A lead to mud
@ 100 cracking.
DFT/coat + 1
SSPC-SP-10; 1 coat of P-6
coat of F-2 @ b) F-12 shall
10.2 -14 to 80 1coat of F-9 @ @ 40 345-355
40 DFT/coat; be ambient
65-75 DFT/coat DFT/coat
(2x100 + 40= temperature
240) curing type
c) Finish coat
including
2 coats of F-12 primer
SSPC-SP-10; @ 20 compatible
10.3 81 to 400 1coat of F-9 @ None DFT/coat 105-115 with finish
65-75 DFT/coat 2x20=40 coat (i.e. field
primer) shall
be applied at
site only.
Finish
2 coats of F-12 coating is not
SSPC-SP-10; permitted at
@ 20
10.4 401 to 550 1coat of F-12 @ None 60 equipment
DFT/coat;
20 DFT/coat manufacture
(2x20=40)
shop.
NOTES:
1. The list of items given in the heading of the above table is not exhaustive. There may be more
items for a particular contract where these specifications are used. The Contractor is fully
responsible for completing painting including prefabrication primer for all the items supplied
and fabricated through his scope of work as per tender document.
2. If the Pre-erection/Pre-fabrication & Shop Primer has already been completed, the same shall not
be repeated again in the field. In case the damages of primer are severe and spread over large
areas, the engineer-in-charge may decide & advise re-blasting and priming again. Repair of pre-
fabrication/pre-erection primer, if required, shall be done as per Table 7.2.
3. For external surface of MS chimney with or without refractory lining and for internal surface
without refractory lining, paint system as per 10.3 above shall be followed.
4. For external surface of RCC Chimney, 2 coats of F-6 @ 100 DFT/coat to obtain total DFT of
200 shall be applied after proper surface preparation as per guidelines in 5.1.6.
5. In case of paint systems as per Sl. Nos. 10.3 and 10.4, the colour bands shall be applied over the
Aluminum paint as per the Color coding requirement for specific service of piping given in
Clause 19.0.
6. All coating system including surface preparation, primer, finish coat for piping shall be done at
site/field only.
NOTES
1. The paint /coating manufacturers shall provide their Quality control test certificate of coating
materials (F-6A) for immersion service of the exposed effluent given in 11.2.
Total
Surface Coating system (Field)
DFT
Sl. Design Temp. Preparation (see note 1 below) in Remarks
No. in oC (Field)
Microns
Primer Finish Coat (min.)
All external surfaces of shell, wind girders, appurtenances, roof tops of all above ground tank including top
12.1
side of external and internal floating roof and associated external structural works.
F-6 should
2 coats of F-6A @
1coat of F-9 @ 65-75 be suitable
100 DFT /coat + 1
SSPC-SP-10 DFT/coat + 1coat of P-6 for
12.1.1 -14 to 80 coat of F-2 @ 40 345-355
@ 40 DFT/ coat ; occasional
DFT/ coat;
water
immersion
12.2 External surfaces of bottom plate (soil side) for all storage tanks.
F-7 should
be suitable
for
SSPC-SP-10 1 coat of F-9 @ 3 coats of F-7@ 100 immersion
12.2.1 -14 to 80 365-375
65-75 DFT/ coat DFT/coat (3x100=300) service of
the
products
given
1 coat of F-15 primer @
80 DFT/ coat + 1 coat
SSPC-SP-10 1 coat of F-15 finish
12.2.2 81 to 150 of F-15 intermediate 240 -
coat @ 80 DFT/ coat
coat @ 80 DFT/coat ;
(80+80=160)
1 coat of F-16 @ 125 1 coat of F-16 @ 125
12.2.3 151 to 550 SSPC-SP-10 250 -
DFT /coat DFT /coat
12.3 For underside of the bottom plate (in case tank is not lifted during PWHT) (see Note 2c)
For CS Products
SSPC SP-6 from
Commercial JOTUN or
HI-TEMP
Blast 2 coats of inert
-180 to 650 1 coat of inert polymeric coatings or
12.3.1 polymeric matrix 350-400
For SS matrix coating @ 125 SK
coating @ 125
SSPC SP-1 FORMULA
with non- TIONS are
chloride recommend
solvent ed.
NOTES
1. All paint coating application including primer for tankage shall be carried out at field after
erection and completion of all welding.
TABLE 13.0 INTERNAL COATING SYSTEMS FOR CARBON STEEL AND LOW ALLOY
STORAGE TANKS
NOTES
1. All paint coating application including primer shall be carried out after erection and completion
of all welding work at site.
2. F-6A should be suitable and resistant for immersion service for the respective Hydrocarbons.
3. This system can be used where maximum operating temperature is below 150oC and design
temperature is upto 200oC. Cases of operating temperature > 150oC are not covered in this spec,
such cases shall be covered in the job specifications.
4 F-6 A shall be suitable for drinking water service and should have competent authority
certification.
For CS
SSPC SP-6 Products from
Commercial Blast JOTUN or HI-
1 coat of inert 2 coats of inert
-180 to Zero TEMP coatings or
15.3.1 polymeric matrix polymeric matrix 350-400
For SS SK
coating @ 125 coating @ 125
SSPC SP-1 with FORMULATIONS
non-chloride are recommended.
solvent
If the piping &
equipments are
already erected
then surface shall
SSPC-SP-10
be prepared by
(15-25 surface 1 coat of F-15 1 coat of F-15
cleaning with
15.3.2 0 to 125 profile) intermediate coat finish coat@ 80 240
emery paper and
1 coat of F-15@ @80 DFT/coat DFT/coat; wash/flush with
80 DFT/coat
chloride free DM
water followed by
wiping with
organic solvent
SSPC-SP-10 Not recommended
1 coat of F-16 @
15.3.3 126 to 400 1 coat of F-16 @ None 250 for operating
125 DFT/coat
125 DFT/coat temperature
NOTES
18.0 STORAGE
18.1 All paints and painting materials shall be stored only in rooms to be arranged by contractor
and approved by Engineer-in-charge for the purpose. All necessary precautions shall be
taken to prevent fire. The storage building shall preferably be separate from adjacent
building. A signboard bearing the word PAINT STORAGE NO NAKED LIGHT
HIGHLY INFLAMABLE shall be clearly displayed outside. Manufacturers
recommendation shall be followed for storage of paint materials.
1 This specification covers the requirement of colour scheme for the identification of the
contents of the pipelines carrying fluids, storage tanks and equipment in refineries. The
following colour coding system has been made based on BPCL-KR input document.
19.1 Identification
The system of colour coding consists of a ground colour and secondary colour bands
superimposed over the ground colour. The ground colour identifies the basic nature of the
service and secondary colour band over the ground colour distinguishes the particular service.
The ground colour shall be applied over the entire length of the un-insulated pipes. For
insulated lines ground colour shall be provided as per specified length and interval to identify
the basic nature of service and secondary colour bands to be painted on these specified length
to identify the particular service. Above colour code is applicable for both unit and offsite
pipelines.
The following ground colour designation for identification of basis classification of various
important services shall be followed.
Secondary colours: The narrow bands presenting the secondary colour which identifies the
specific service may be applied by painting or preferably by use of adhesive plastic tapes of
the specific colour.
The following specifications of colour bands shall be followed for identifying the piping
contents, size and location of bands & letters. The bandwidth and size of letters in legends will
depend to some extent upon the pipe diameter. Either white or black letters are selected to
provide maximum contrast to the band colour. Bands usually are 100 mm wide and regardless
of band width, are spaced 50 mm apart when two bands are employed.
Contrast shall be provided between color field and legend for readability. Use of letters
standard style, in sizes, 1/2inch (13mm) and larger, is recommended. See above table for
specific size recommendations. For identification of materials in pipes of less than inch
(19mm) in diameter, and for valve and fitting identification, the use of permanently legible tag
is recommended.
In addition, ground colour as per specified length should be provided on insulated piping for
easy identification of nature of fluid, on which the colour bands should be painted for
identification of each service. The length of the ground colour should be 3 times the width of
normal bands or 2 meters, whichever is suitable depending on the length of the pipe.
Arrows shall be used to indicate direction of flow. Where flow can be in both directions,
arrows in both directions shall be displayed.
Positive identification of the contents of a piping system shall be by lettered legend, giving the
name of the contents in full or abbreviated form. Contents shall be identified by a legend with
sufficient additional details such as temperature, pressure, etc as are necessary to identify the
hazard. Legends shall be brief, informative, pointed and simple of greatest effectiveness.
Legends shall be applied close to valves or flanges and adjacent to changes in direction,
branches and where pipes pass through walls or floors, where it enters and emerges from road,
culvert and walkway overpasses, unit battery limits and at every 50m intervals on straight pipe
runs sufficient for identification. Identification may be accomplished by stencilling, the use of
tape, or markers. In any situation, the number and location of identification markers shall be
based on the particular piping system.
The letters will be in black on pipes painted with light shade colours and white on pipes
painted with dark shade colours to give good contrast.
Only writing of service name shall be done on stainless steel lines. Precautions should be taken
while painting by using low chloride content painting to avoid any damage to the stainless
steel pipes. It is preferable to use adhesive plastic tapes to protect stainless steel pipes.
Visibility:
Attention shall be given to visibility with reference to pipe markings. Where pipelines are
located above or below the normal line of vision, the lettering shall be placed below or above
the horizontal centreline of the pipe.
Size of letters stencilled / written for equipment shall be as given below:
In addition, the contents of the pipe and/or direction of flow may be further indicated by
arrows and legend. If a hazard is involved it must be identified clearly by legend.
Colour bands: The location and size of bands, as recommended, when used, shall be
applied to the pipe.
For alloy steel / stainless steel pipes and fittings in stores / fabrication yard, colour band
(Minimum wide) should be applied along the complete length of pipe, bends / tees, side-
covered surface (on thickness) of flanges as well as valves as per the metallurgy.
When the piping layout creates or occurs in a limited area of inaccessibility or of extreme
complexity, such segments of layouts may require substitute techniques shall be limited to
such segments and shall not deviate from the concept of identification as defined above.
The specification for application of the complete Piping identification colour code, including
base and bands colours, are presented in the below table.
11 Crude Sweet 1 Light brown ground colour with 1 yellow band in centre
12 Crude Sour 1 Light brown ground colour with 1 orange band in centre
13 VGO / HCU Feed 1 Oxide red ground colour with 1 steel grey band in centre
14 OHCU Bottom / FCCU Feed 1 Oxide red ground colour with 2 steel grey band in centre
6. GRATING GALVANSIED
8. HAND RAILINGS
- HANDRAIL, MIDDLE RAIL, TOE PLATE SIGNAL RED
- VERTICAL POST BLACK
20.1 Equipment number shall be stencilled in black or white on each vessel, column, equipment &
machinery (insulated or uninsulated) after painting. Line number in black or white shall be
stencilled on all the pipe lines of more than one location as directed by Engineer-In-Charge;
Size of letter printed shall be as below:
21.1 Following items shall be painted for camouflaging if required by the client.
a. All Columns
b. All tanks in Offsites
c. Large Vessels
d. Spheres
21.2 Two coats of selected finishing paint as per defense requirement shall be applied in a
particular pattern as per 20.3 and as per the instructions of Engineer-In-Charge.
21.3.1 Disruptive painting for camouflaging shall be done in three colours in the ratio of 5:3:2 (all
matte finish).
21.3.4 The patches should be continuous where two surfaces meet at an angle.
22.1 All painting materials including primers and thinners brought to site by contractor for
application shall be procured directly from manufactures as per specifications and shall be
accompanied by manufacturer's test certificates. Paint formulations without certificates are
not acceptable (see section 24.0).
22.2 The contractor must produce Test Certificate from Pre Qualified Paint Manufacturer for
various tests as detailed out in section 25.1 of this document, for each batch & for each
category of product. The Engineer-in-Charge shall have the right to test wet samples of paint
from each batch at random for verifying quality of paint supplied. Contractor shall arrange to
have such tests, when called for by Engineer-in-Charge, performed at his cost any one of the
independent laboratories listed in the 25.1 of this document.
Samples for the test will be drawn at random in presence Engineer-in-Charge or his
representations. Following tests to be carried out if called for by Engineer-in-Charge:
- Specific Gravity
- % solids by weight (% zinc content in case of inorganic or organic zinc primer)
- Drying time (touch dry & full curing)
- Adhesion
- Flexibility
- Hardness
- Storage stability (pot life)
Test methods for above tests shall be as per relevant ASTM or ISO Standard.
22.3 The painting work shall be subject to inspection by Engineer-In-Charge at all times. In
particular, following stage-wise inspection will be performed and contractor shall offer the
work for inspection and approval of every stage before proceeding with the next stage. The
record of inspection shall be maintained in the registers. Stages of inspection are as follows:
- Test for absence oil & grease after degreasing before blasting as per procedure given in
sec 6.7 of Annexure-I of this specification (specification for thermally sprayed
Aluminium Coating).
- Tests for surface finish of blasted surface shall be done by visual inspection using SSPC-
VIS1. Clear cellophane tape test as per ISO 8502-3 shall be used to confirm absence of
dust on blasted surface. Checks shall be done on each component atleast once per 200 m2
of blasted surface and minimum of 3 checks per shift.
- Test for presence of soluble salt as per method ISO 8502-9. Maximum allowable salt
content shall be considered 20 mg/m2 (2 mg/cm2). Checks shall be done on each
component atleast once per 200 m2 of blasted surface and minimum of 3 checks per shift.
In case salt exceeds specified limit, the contaminated surface shall be cleaned by method
as per Annexure-C of IS 12944-4 (water cleaning). After cleaning surface shall be
retested for salt after drying.
- Blast profile measurement This shall be done as described in sec 6.2 of Annexure-I of
this specification (Specification for thermally sprayed Aluminium).
- Test for blasting Media and Blasting air- this shall be done as described in sec 6.6 of
Annexure-I of this specification (Specification for thermally sprayed Aluminium).
In addition to above, record should include type of shop primer already applied on equipment
e.g. zinc silicate, or zinc rich epoxy, or zinc phosphate.
Any defect noticed during the various stages of inspection shall be rectified by the contractor
to the entire satisfaction of Engineer-In-Charge before proceeding further. Irrespective of the
inspection, repair and approval at intermediate stages of work, contractor shall be responsible
for making good any defects found during final inspection/guarantee period/defect liability
period as defined in general condition of contract. Dry film thickness (DFT) shall be checked
and recorded after application of each coat and extra coat of paint should be applied to make-
up the DFT specified without any extra cost to owner, the extra coat should have prior
approval of Engineer-in-charge.
After surface preparation, the primer should be applied to cover the crevices, corners, sharp
edges etc. in the presence of inspector nominated by Engineer-In-Charge.
22.5 The shades of successive coats should be slightly different in colour in order to ensure
application of individual coats, the thickness of each coat and complete coverage should be
checked as per provision of this specification. This should be approved by Engineer-In-
Charge before application of successive coats.
22.6 The contractor shall provide standard thickness measurement instrument with appropriate
range(s) for measuring.
Dry film thickness of each coat, surface profile gauge for checking of surface profile in case
of sand blasting. Holiday detectors and pinhole detector and protector whenever required for
checking in case of immersion conditions.
22.7 Prior to application of paints on surfaces of chimneys, the thickness of the individual coat
shall be checked by application of each coat of same paint on M.S.test panel. The thickness of
paint on test panels shall be determined by using gauge such as 'Elkometer'. The thickness of
each coat shall be checked as per provision of this specification. This shall be approved by
Engineer-In-Charge before application of paints on surface of chimney.
22.8 At the discretion of Engineer-In-Charge, the paint manufacturer must provide the expert
technical service at site as and when required. This service should be free of cost and without
any obligation to the owner, as it would be in the interest of the manufacturer to ensure that
both surface preparation and application are carried out as per their recommendations. The
contractor is responsible to arrange the same.
1) Coating DFT measurement shall be as per ISO 2808. Type II electromagnetic gauges
should be used for ferrous substrates. DFT gauge calibration, number of measurement
shall be as per SSPC-DA 2. Measured DFT shall be within + 10% of the dry film
thickness, specified in the specifications.
2) Adhesion of the primer to the steel substrate and intercoat adhesion of the subsequent
coat(s) after curing for at least a week after application of the topcoat shall be examined by
a knife test in accordance with ASTM D 6677. For the knife test, if the rating is better than
8, the adhesion is considered acceptable. The adhesion is destructive and tested areas shall
be repaired afterward using the spot repair procedure. Alternatively, the applicator may
perform the adhesion test on a steel coupon coated using the same surface preparation and
coating application procedure as the work piece. Adhesion testing shall be carried out for
each component at least once per 200 m2 (2000 ft2) of coated surface.
3) Holiday testing shall be conducted in accordance with NACE SP 0188. For immersion
services, 100% of coated area shall be inspected for holidays. For atmospheric exposure,
10% of coated area which must include weld seams, corners and edges to be holiday
tested. Voltage at which test is to be carried out will depend upon DFT of coating being
tested and shall be as per NACE SP 0188. Any holiday is unacceptable and should be
marked and repaired immediately.
22.10 The contractor shall arrange for spot checking of paint materials for Specific gravity, glow
time (ford cup) and spreading rate.
A final inspection shall be conducted prior to the acceptance of the work. The coating
contractor and the facility owner shall both be present and they shall sign an agreed inspection
report. Such reports shall include:
General
- Names of the coating contractor and the responsible personnel
- Dates when work was performed
Coating Materials
- Information on coating materials being applied
- Condition of coating materials received
Environmental Conditions
- Weather and ambient conditions
- Coating periods
Surface Preparation
- Condition of surface before preparation
- Tools and methods used to prepare surface
- Condition of surface after preparation
Coating Application
- Equipment used
- Mixing procedure prior to application
- Coating application techniques used
Testing
- Type and calibration of inspection instruments used
- Type of quality control tests performed, and results
23.0 GUARANTEE
23.1 The contractor shall guarantee that the chemical and physical properties of paint materials used
are in accordance with the specifications contained herein/to be provided during execution of
work.
Painting contractor who is awarded any job for EIL, Projects under this standard must have
necessary equipments, machinery, tools and tackles for surface preparation, paint application
and inspection. The contractor mush have qualified, trained and experienced surface
preparator, paint applicator, inspector and supervisors. The contractor supervisor, inspector,
surface preparator and paint applicator must be conversant with the standards referred in this
specification.
Paint Coating manufacture meeting the following requirements shall be considered for supply
of their products. Contractor is advised to select coating manufacturer. Only after obtaining
prequalification from EIL for the manufacturer based on following requirements. Even those
manufacturers, whose names are appearing elsewhere in the tender document, under the list of
EILs Recommended or Approved Vendors, will also be required to meet the following
prequalification requirements.
- Manufacturer should have been in continuous business of paint coating formulation and
manufacturer for at least past 5 years.
- Coating manufacturer should have supplied at least 10000 litre of an individual product
to hydrocarbon processing industry or offshore platform.
- The manufacturers manufacturing procedure & QA/QC system shall meet ISO 9001
requirements and preferably should posses ISO 14000 certificate.
- The Quality control set up should be manned by qualified paint technologists whose bio
data should be sent along with quality control organization chart.
- Pre-Qualification Testing:
Manufacturer should have got his products tested at least one time in last 3 years at a
reputed independent laboratory for the following test items. Test certificates which are
more than 3 years old will not be considered.
1) An infrared scan (fingerprint), for Part A and B, each component as per ASTM
D 2621
2) Specific gravity of Base and curing agent (Ref. ISO 2811)
3) Ash content (ASTM D1650), volatile and non-volatile matters (ISO 3251) of each
component
The identification shall be carried out on the batch, which is used for the Pre-
qualification testing. Pre-qualification of the products shall be carried out at an
independent laboratory.
Test shall be carried out at any one of the following laboratories and tests to be witnessed &
certified by third party inspection agency (TUV, BV, DNV).
IICT, Hyderabad
HBTI, Kanpur
DMSRDE, Kanpur
BIS Laboratories
UICT, Matunga, Mumbai
RITES, Kolkata
PDIL, Sindri
NTH, Kolkata
Contractor along with delivery of paint material has to furnish following information from
paint manufacturer to EIL for acceptance/approval of products.
Along with delivery to site of the paint products from pre-qualified coating manufacturer.
Contractor has to produce test certificate from paint manufacturer for each batch and for
each category of product for the following test items. Test to be witnessed & certified
by third party inspection agency. All test results must mention clearly the batch no. and
category of product tested. Tests to be conducted for following properties:
b) Product information sheet/ technical data sheet for each category of product.
26.1 Samples of coating materials should be submitted to the Govt. laboratory in sealed containers
with batch no. and test certificate on regular format of manufacturers testing laboratory. The
sampling shall be certified and sealed by a certifying agency.
26.2 All test panels should be prepared by Govt. testing agency coloured photographs of test
panels should be taken before and after the test and should be enclosed along with test report.
Sample batch no. and manufacturers test certificate should be enclosed along with the
report. Test report must contain details of observation and rusting if any, as per the testing
code.
26.3 Manufacturers should intimate the company, details of sample submitted for testing, name of
Govt. testing agency, date, contact personnel of the govt. testing agency. At the end of the
test the manufacturer should submit the test reports to the company for approval.
26.4 Coating systems for panel test shall be decided after discussion with EIL.
The following drawings/documents marked " " shall be furnished by the bidder.
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
1. GENERAL ARRANGEMENT DRAWING
INDICATING DESIGN DATA FABRICATED Documents shall be
EQUIPMENT WEIGHT, GENERAL NOTES, submitted within 3 to 5
NOZZLE SCHEDULE, DETAIL OF SHELL, weeks of issue of PR.
HEADS, SUPPORTING ARRANGEMENT, Cutting layout is not
required.
MAIN WELD SEAMS, NOZZLE ORIENTATION
PLAN, CUTTING LAYOUT ETC.
2. DETAIL OF NOZZLES, MANHOLES, Documents shall be
submitted within 3 to 5
ACCESSORIES ETC weeks of issue of PR.
3. DETAILS OF DEMISTER. Documents shall be
submitted within 3 to 5
weeks of issue of PR.
4. DETAILS OF PACKING SUPPORT, Documents shall be
DEMISTER SUPPORTS, GRATINGS, AND submitted within 3 to 5
GRATING SUPPORTS. weeks of issue of PR.
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
12. WELDING PROCEDURES AND Documents shall be
submitted within 5 to 8
QUALIFICATION TEST REPORTS @ weeks of issue of PR.
13. DESTRUCTIVE AND NON-DESTRUCTIVE Documents shall be
submitted within 5 to 8
TEST REPORTS @ weeks of issue of PR.
14. MATERIAL TEST CERTIFICATES @ Documents shall be
submitted within 1
week after final
inspection.
15. RADIOGRAPHIC EXAMINATION REPORTS Vendor to store these
WITH FILMS @ for 5 years.
Notes :
1. "TICK" denotes applicability.
2. Post order, drawing / document review shall commence only after approval of Document Control Index (DCI).
3. All post order documents shall be submitted / approved through EIL eDMS portal.
4. Final documentation shall be submitted in hard copy (Six prints) and soft ( two CDs/DVDs ) in addition to
submission through EIL eDMS.
5. Refer - 6-78-0001: Specification for quality management system from Bidders.
6. Refer - 6-78-0003: Specification for documentation requirement from Suppliers.
7. All drawings & documents shall be submitted in A4 or A3 paper sizes. Documents in higher paper size shall
be submitted in exceptional circumstances or as indicated in the MR/Tender.
8. Post order- The schedule of drawing / data submission shall be mutually agreed between EIL & the bidder /
contractor / supplier during finalization of Document Control Index (DCI).
9. "@" indicates submission of documents to Inspection Agency.
10. Bill of Material shall form part of the respective drawing.
NOZZLES AND CONNECTIONS uksty o duSD'ku GENERAL NOTES (tujy uksV~l SPECIFICATIONS LisflfQds'kUl DESIGN DATA fMtkbu MkVk
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTI
ON NOTE-
PAD W
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SEC. VIII DIV.1 2010, ADDENDA 2011
ukfeuy 'kMwy o CLASS TYPE FACING 4
xT 1 ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE STATED. x GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm2g) 3
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. x SUPP. SPEC. FOR CS VESSELS 6-12-0002 DESIGN PRESSURE (kg/cm2g) INT. 15.3 EXT. -
N2 1
76.2
- 150 LWN RF
SEE 45
VAPOR OUTLET/PSV INLET
LINE TO FLANGE CONTACT FACE.
x STD. SPEC. FOR SS PLATE 6-12-0020 MDMT (0C) 15
I.D. DRG X 24 4 (B) FOR NOZZLES ON HEAD PROJECTIONS ARE REFERRED FROM HEAD T.L TO JOB SPEC. FOR SURFACE PREPARATION AND CORROSION ALLLOWANCE (MM) 3
SEE 175 X FLANGE CONTACT FACE. X PROTECTIVE COATING (NEW CONSTRUCTION) A307-000-06-42-PLS-01
TYPE OF HEAD 2 : 1 ELLIPSOIDAL
N3 1 350 24 THK. 150 WN RF LIQUID OUTLET
DRG 24 5 THE INDICATED THICKNESS IS THE MINIMUM ACCEPTABLE AFTER JOINT EFFICIENCY SHELL 1 HEAD 1
SEE 45 X CONSTRUCTION. RADIOGRAPHY (NOTE-11) SHELL FULL HEAD FULL
N4 1 80 160 150 WN RF DRAIN STANDARDS LVS.MMZl
DRG 24 6 FLANGE GASKET FACE SHALL HAVE 125 AARH FINISH. POST WELD HEAT TREATMENT YES COMPLETE VESSEL (NOTE-12)
N5 1 50 160 300 WN RF
SEE
- VENT
7 DIMENSIONS OF FLANGES FOR NOZZLES UPTO 600NB SHALL BE AS PER ANSI X VESSEL TOLERANCES 7-12-0001 HEAT TREATMENT HEAD AS PER SPEC.
DRG B16.5 AND FOR NOZZLE ABOVE 600NB SHALL BE AS PER ASME B16.47 SUPPORT FOR HORIZONTAL VESSEL 7-12-0002 OPERATING MEDIUM LEAN AMINE
SERIES `B' UNLESS SPECIFIED OTHERWISE. SP. GRAVITY 1.034
WOODEN PILLOWS FOR SADDLE SUPPORT 7-12-0003
N6 1 50 160 300 WN RF 1575 - UTILITY CONNECTION
8 ID OF WELD NECK FLANGES SHALL MATCH WITH CORRESPONDING ID OF X SKIRT BASE DETAILS 7-12-0004 WIND SPECIFICATION AS PER IS : 875
K1
2 50 160 300 WN RF 1575 - STAND PIPE
NOZZLE PIPE/SHELL. X SKIRT OPENING DETAILS 7-12-0005 SEISMIC AS PER IS : 1893 & SITE SPECTRA
A/B 9 NOZZLES 50NB AND BELOW SHALL BE STIFFENED WITH 2 NOS. 40 x 6 THK ANGLE LEG SUPPORT 7-12-0006 CAPACITY (M ) 3 61.4
K2 FLATS 900 APART. PIPE LEG SUPPORT 7-12-0007 PAINTING/CLEANING AS PER PAINTING JOB SPEC.
2 50 160 300 WN RF 1575 - LEVEL TRANSMITTER (DP)
A/B 10 2
VESSEL IS SUBJECTED TO STEAM OUT CONDITIONS OF 0.5 Kg/Cm (g) AT BRACKET SUPPORT FOR VERTICAL VESSEL 7-12-0008 INSULATION THICKNESS (mm) NIL HOT COLD
K3 1900C. MANHOLE WITH HINGED COVER 7-12-0009 FIRE PROOFING (BY OTHERS) X YES NO
2 50 160 300 WN RF 1575 - LEVEL TRANSMITTER (DP)
A/B 11 ALL BUTT WELDS IN PRESSURE PART SHALL BE 100% RADIOGRAPHED. X MANHOLE WITH DAVIT 7-12-0010 HYDROSTATIC TEST (kg/cm2g) HORIZONTAL VERTICAL (AT TOP)
K4
2 50 160 300 WN RF 1575 - LEVEL TRANSMITTER (DP)
12 HARDNESS OF BASE METAL, WELDS & HAZ AFTER PWHT SHALL NOT EXCEED X LADDER RUNGS FOR MANHOLE/DEMISTER 7-12-0011 PRESSURE (NEW & COLD) 19.89
A/B 200 BHN. RETAINING PLATE 7-12-0012 INSPECTION BY X EIL CIB LLOYDS
LT
2 50 160 300 WN RF 1575 - LEVEL TRANSMITTER (DP)
13 PIPE TO PIPE, PIPE TO FLANGE, PIPE TO FITTING & FITTING TO FLANGE JOINT X NOZZLE REINFORCEMENT AND PROJECTION 7-12-0013 MATERIAL OF CONSTRUCTION eSfVfj;y vkQ dUlVD'ku)
1-2 SHALL BE WELDED WITH THE SAME TECHNIQUE USED FOR MAIN EQUIPMENT PAD NOZZLES FOR VESSELS 7-12-0014 (AS PER ASME / IS OR EQUIVALENT)
WELDING.
A1 1 600 24 THK. 150 WN RF 1675
300
MANHOLE + B.F. + DAVIT
X STANDARD BOLT HOLE ORIENTATION 7-12-0015
x24 14 ALL SS SURFACES SHALL BE PICKLED AND PASSIVATED AS PER ASTM A 380. ALLOY LINER DETAILS 7-12-0016 SHELL SA 516 Gr.60 *
SKV 1- SIGHT GLASSES FOR PRESSURE VESSELS 7-12-0017 REINFORCEMENT PAD SA 516 Gr.60
4 100 40 AS PER EIL STD SKIRT VENT
4 X INTERNAL FLANGES 7-12-0018 HEADS SA 516 Gr.60 *
500 250 VORTEX BREAKERS 7-12-0019 SHELL FLANGES -
AO 1 10 THK. AS PER EIL STD ACCESS OPENING
I.D. x18 INLET DEFLECTOR BAFFLE 7-12-0020 NOZZLE FLANGES / LWN SA 105 *
SUPPORT RING AND BOLTING BAR 7-12-0021 NOZZLE NECK UPTO 250 NB SA 106 GR. B *
SUPPORT RING SIZES FOR PACKED TOWERS 7-12-0022 NOZZLE NECK ABOVE 250 NB SA 516 Gr.60 *
X PIPE DAVIT 7-12-0023 PIPE FITTINGS SA 234 GR. WPB * (SEAMLESS)
X LIFTING LUG TOP HEAD TYPE 7-12-0024 GASKET EXTERNAL SPIRAL WOUND WITH SS 316 WINDING & GRAFOIL
FILLER WITH CS OUTER RING AS PER ASME B16.20
X FIRE PROOFING AND INSULATION SUPPORTS 7-12-0025
X EARTHING LUG 7-12-0026
X NAME PLATE 7-12-0027
X MANUFACTURER NAME PLATE 7-12-0028 GASKET INTERNAL COMPRESSED FIBRE ASBESTOS FREE
X BRACKET FOR NAME PLATE 7-12-0029 EXTERNAL STUDS/BOLTS/NUTS SA 193 GR.B7M / SA 194 GR.2HM
NAME PLATE FOR SMALL EQUIPMENT 7-12-0030 INTERNAL STUDS/BOLTS/NUTS SS 316
DETAILS OF FORGED NOZZLES 7-12-0031 SKIRT/ SUPPORT SA 516 GR.60/IS 2062 GR.B
X SUPPORTS FOR INTERNAL FEED PIPE 7-12-0032 SKIRT/ SUPPORT BASE IS 2062 GR.B
HOT INSULATION SUPPORT FOR HORIZONTAL VESSEL 7-12-0033 INTERNAL PARTS (WELDED) SA 516 GR.60 */ SA 106 GR.B *
PIPE DAVIT SUPPORT FOR COLD INS. VESSELS 7-12-0034 INTERNAL PARTS (BOLTED) SS 316L
TYP. DETAILS OF WIRE MESH DEMISTER SUPPORTS 7-12-0036 CLIPS & ATTACHMENTS (EXTERNAL) SA516 GR.60/IS2062 GR. B WELDED OVER PAD
S.R NOZZLE NECK 7-12-0037 VORTEX BREAKER SS 316L
ALLOWABLE NOZZLE LOADS - DEMISTER/GRID -
PAD FOR EXTERNAL ATTACHMENT SA 516 GR.60
DEMISTER SUPPORT -
JOB NO: UNIT NO: 2 20.01.2014 SHT. 2 REVISED ANIL PKB/KRK BBC DESIGN DATA fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A307
;fuV l[;k IV 1 19.06.2014 REVISED AS MARKED JS RSU/PSV BBC MkbZx uEcj REV
1
NEW DELHI CLIENT :
M/S B.P.C.L., KOCHI
0 24.10.2013 ISSUED FOR PURCHASE JS RSU/DS BBC LEAN AMINE SURGE DRUM yhu vekbZu ltZ Me A307-0IV-16-46-DS-3301 2
DykbZV B 13.06.2013 REVISED & REISSUED FOR BIDS/ENGG. B JS SUU/PSV TG
bathfu;lZ bafM;k fyfeVsM PLANT : VGO HYDROTREATER UNIT, INTEGRATED A 15.04.2013 ISSUED FOR BIDS/ENGG GCP PKB/PSV TG
ITEM NO. IV-V-301 vAbVe uEcj oh & oh & 301 SHEET 1 OF 2
Hkkjr ljdkj dk midze IykaV REFINERY EXPANSION PROJECT (IREP) REV DATE REVISION BY CHECKED APPROVED
FORMAT NO.3-1646-0119 REV.2 (06.12.2011) A3-420 X 297
REV.
SCALE
1:50
DATE
NOTES :-
REF. DWG. NO.
A307
JOB NO.
dksph fjQkbujh
IF
UNIT
REVISIONS
16
DIVN.
48
DEPT.
BY
3-1641-0501 REV.2
10769
DWG. NO.
Hkkjr iSVksfy;e dkWiksZjs'ku fyfeVsM
KOCHI REFINERY
0
REV.
A1-841x594
CHKD APPD PEM/PC
NOTES
1. REFER P&ID NO -183506-TGTU-IST-1131.
2. DEMISTER PAD THICKNESS SHALL BE 6" AND DENSITY SHALL BE 9 LB/FT3 (144 KG/M3).
3. DEMISTER DIAMETER SHALL BE 20". MECHANICAL DETAIL SHALL BE AS PER CB&I STANDARD FOR
DEMISTER PAD SUPPORT TYPE 3.
1/4"[6] + (2 x C.A.)
ON
WELD LINE
TECHNOLOGY OW NED
72" [1830]MAX.
. REPRODUCTI
1 1/2"
ON
SSI
[38]
PERM I
BY CB& I
TTEN
DEMISTER PAD
3
9 lb/ft
EXCEPT BY EXPRESS W RI
NG
3]
BI
[144 kg/m
DESCRI
PERFORM ED
DENSITY (U.N.O.)
ELEVATION
TH
RD
I
WI
ANY THI
N
T M AY CONTAI
DDEN
ON
CONNECTI
S FORBI
[25]
1"
SCLOSURE TO
[25]
1"
BY CB& I I
). I
N
ONLY I
COM PANY ("CB& I
NADVERTENT DI
BE USED
PERFORM ED
[150]
6"
[150]
6"
SA 320, B8
[25]
1"
[25]
1"
S TO
BERATE OR I
RON
W ORK
T I
I
VE. I
DGE &
[25]
1"
PART FOR ANY PURPOSE OTHER THAN
[25]
1"
TI
BRI
ALLY SENSI
NST DELI
[25]
1"
RING IN SECTIONS TO
CAGO
PASS THRU MANWAY 2" [50] x 2" [50] x 1/4" [6] ANGLE
S THE PROPERTY OF CHI
AGAI
2" [50] x 2" [50] x 1/4" [6] ANGLE CLIPS X 2" [50] LG. (4 REQD.
BE COM M ERCI
S TO
S DOCUM ENT I
DETAIL "A"
N
W HOLE OR I
NOTES:
T I
BY CB& I AND
THROUGH MANWAY.
2. DEMISTER PAD AND GRID 304 S.S. UNLESS
THI
- - - - - -
- - - - - -
DEMISTER PAD SUPPORT
- - - - - -
TYPE 3
- - - - - -
DRAWN: MLV CKD: RGS APPD: DLB DATE: 6-08 SCALE: NTS PROJECT NO: DWG NO:
CMS-830-04-SD-12044 REV: 0
Page 1 of 1
HORIZONTAL VESSEL
(ELEVATION)
q_
VERTICAL VESSEL
(PLAN)
NOTES
ANY DEVIATION FROM THIS ARRANGEMENT WILL BE INDICATED IN ENGINEERING DRAWING.
BOLT HOLES TO STRADDLE CENTRE LINES INDICATED ( BY q. ) ABOVE.
O
D
03 I V
0
N
7:J
c.)
)1:1
0 c.)
Vl
tt
o
CC
z
z 0
co O
cn
5
a. y 0-3
Eit 0 M
o. 0 lMJ
0 co
O
3 9,
3 `7`
at cn
5 -o 0
tMi
(n
r, o
0. 0 V 1,,
g O
co so
WTI
0 1016
rn
57.Z
444
70 v) VD =.1
rn
r-,
v) c 0
5
,,. =
cm, iz -,<
,.,_,, (i C4D 0.1 t,, ,< rily CI
W il ar r) r) C") g..,
= a -
l
ci -on, ot. Po a q -t = .i.s.
= r4 '0 , ,- 5..- a = r 0"
V) t-, , ,-< -o -, -r i 0 -, rzii -,,
CI. C) 2. g g cn r+.0.8 q
.7,.] n o cl.. CD . P....
(0 n E
n
f a
i-,0 5 co no o = - -I = - 7..,. 5 = rii g k" on
. "
.0 E)t 5 . -' -
= = = A,- = too = F)A . ,. -' '4 < ..co = . =
, F- n a' (D - `,1)( p ,...',='. -6 q cp wpzi'=6 " H F... w0
$4 t-'i ..,. - 5q o
-e 0) CD v) g 0 a. o CD = co 0 0 < g ril
W rt
K (-)" a. 4 oX CM ct, ,-4 VI P7. 11' = Co
-t - 1
4 4 4 . -1 0 011 CD 1,Eo.,,. = -, CD 0 CIO
. 0
H 2 ri'V) 0 0. 0
V) 8 K a g. (.9 (1) . ,-41 0 ,....)
0 V) ODP .4 0 Crq rn)
C.) > X ; ....
4 ..J
. rw. e+ o, 4 2 rri
CA 0 ... V) . 5 ..0 o, p CD
" CrC/
C 0 0 0 5 = ''' :::i
r'' t(1) o
too 5- ZA "0
'-1 '1=1 < cm Fo- -.. = o w 5 ' 5F
o < ,t .. '-' 4 5 CM ,-* CA
c/o c-) - = a r. cD CD z
0 c 0 0 CPO 0r-- P ,?.,
a. CPO = CY" R co
co'.). , e '
P4CD rs R = -
-, II) co 8
0
x '?'-
2 r
ri) -
4 4ri = a
0..
4 C)
.ci
0
-c)
po
. 0
;, < H H EA pc) 't7 'V 'V "c, '17 Z z
-, ,.,,, -i -0 n ci) H 4 x c r-r1 o -0
4 4x ..0
'7:-; p,
8 . AD0" e0 (4 X 0 )) X CA r H
"
0H
CD 0
23
X '..:j
PO
0
-,...,
H g Z
-o 5- ,1:i .c, ,.-3 Q. cA
CM L,
4 f C) = *I
Oo
0
v) AD
- -.4 0 '
,.. ,,,
ro AD -1- .--r-
0 " .'" - a /1:1 4...)
Q.
c ~'0 4 -1 til
'6' 0 *0
=
Fli cr 'To rn ,-, 'g "Q- ,:,''
CL CD CD -. = '- CD .
v) co = sv flt. (")
.-/
cr *0 ' w '-s Crt:/ -/ =
`-< o .n 'V '0 :4/ .-: 1
et) a
.
u, 0 4 C.3
C 5% Crg .-s- 0 l't .-r- I4
'0 0 ..r.', ""
o a c4 5
S. a. cr,,, =
r.. ---- cp K
'7:, =
..1 ..... CD /0 .
..... t-ts C4 p:1
=
CD r)
0) 0
0 oCL r20K,'-')c4vC/3 z-.g n
0 Z
-- w n '4 lz; '-.. = = 5, .
el) O' '4 5 is-,' cm F. a
pp = 0 .,: El. R . =
, CD
CI) e-r-
.-
Ae-I-o--- '01.1:1
,.., $1)
a C)
p ci) < 5 .
a. d 5)
ct CA CD = . a.
Ts (--) H CM 0 CD '0 tzi
..t
cl' n n Pr; 5' '-+ a. P 0
AD p, -1-)PO (PP n FD < 0
cr = ,-1, , yl .... CA . CD v)
nj- CL f,. g = V' < c'-;,. CL
. 0 Z
., 1-4
c CD p P AD go CD r)
p
.1 e) fa. 0
v) LA
x .-- = .0 g
oc
,-ii
c> c, r) ,_,
>
cc, c, Z
x 4
0
CD
--3 a . ,-,:,
0 -,
:1-zi zi .... 0 0
..., , ,__. c 0
gr)
CD A.,'''' a,
"cs 0 0
, 7 (. rD
- C/
3 C1) = o-,
a ,,,, ,-,
v) ,,, n g
a.
cn
od cl)
I PO
Z
t. td
0.0
V)
rit
XI 0
.0
v) rit
0
,11 *11
Z It
til .0
7J
r)
-0
0.4 CO
tit 0 CD
0.1
'17 t..4 0
,"; 'V
CD
Z tH '0 ,
c-)
0 0 4 AT
0 0-.1 t-- - = Clt1 . .1- pa I1 V)
eti- ,
P 0:2 P',,,-,,, CD .--t- =
=
CA CD '- 0 .'. y) co
.t
"0 "0 .-t tg!-D ,, .. ,-. v
'0 pp
0 CD =
po CA
V' 4(-A'
v, .. OD
1., , - - ,-- C
= 0 'CS cn o.1n
"
,,c4 0 ,--, z, F:-,..: cc, . co ti1
5 CD '0 g cp CA Ci. GA
,o-i.t o,.,_ ^-4-.
,-, CD CA
w '' -o 8 E. = .....
co .... 0
',_, ii A) c") crg ,.... 14
0= = n
0
0. n -0 - CI) Z :Lt. cn H
ta .4, 0 En cn 0 'V H
ta. o a ,-.
.. CD il,) $.?..,) = Ao co
"CS .1 ./- M <
/I
91 g CD A) = CD 5. Mt
(-D ,-,. -o = o H
0 o o, A) 1.-4.) = /'
o a. :..., -. cp
- 0-,t
,,CA .., 0
CI) -%
=
Crg
0 1-' ,...
0.. <
H CD LA
5.V)+ 00 '-.-3
H ... 'cil, = ,--i 7z) co a g
-- xCD n
CD co ,-. <
CA co ,
0 s-.., < q .... Z
,-4- H 0 --. ca. -CD to
C.) CA ,..,-, .1 .1, CD 0 .
c
-t 0 " ,-, a o .0 ....
= cw H ..7.f-t ..... 0 0
Pa ..w 0 0. 2, --. 5 2-, a
10 0 0.. 2 Ej C4. Er. ..-t- Ca 'H. '-'' n
0= 1 0". 0 0 (/) 0 A).-1 0 CD /1)
(I)= . A). co..-r-
co (1) 0 Pr C/1 = .- (i) P --. C/D H
A) P...e a.
(1) (1)-. - ta. tt
V) A) ,.-+. crq 0 C4 A) '" 4 =. '-'
cr " 0 0
Qn = tro'5
SI) 0
CD 0 Cro 2 '.-''- o n P ,,, e)
0
'CS Fr CD VI = 0 ca.. ,_ C
'CS < = - CA .
. f,l... '4 r_..41- e-+ - - ci)
cl o = :1, ::1) z o -1 0 .-ti. H
Fi. 0 = 0 A) CA n *4
-.. (1) = .-0 A) = 't3
F) E. ca. "0 r-r- ' e-t- v) CD , n
Po
CA
co co) C") co CA
Fr N E:7. Fi v d'' CD r-r- C/)
0
= -t g _ tw 0
Cr. 0 =
CD
CD
0 C,
1-11
c> c) c) c) 0 0 0 ,_,-
0 0 0 0 0 0 0 Z
0 0 0 0 0 0 tml /-
n
#4
0 4 0 c-)
x 4. C/1 cD Po ^.1 '-.
.1 VI n n)
n *0 CD "cS =a 8- 0 W
a
k
y
e-1-
P-,oP1)
...,. n
'CS CD *0 CD ,L7' -CS
. ti P. ,., .-1 ,+
n 1. 0 :ID
0 0 0 0 = 0 0
,-, .., ,-, = `w = co -1
..., P -t.
=
ty
o _ Q. Cam. 0.,.
- r-t w A) O.
Q. 0
0
= = 0 F9t+ co co
*-3 ,t-
CA
'Si CI)
= Z x . Id
C-4
..., to cA
ti1 n
0
It
ci) til
0
It It
7zi x x .0 1-1
C-4
tTI No
7:J tt
n
H 12)0
ri-) 0 to
to
-c=
x x X x
It
-
,, v)
.- ,s1
..0 ,',
u 4-,
= -,--k
.2 .4
.., -
0 ,,_
CL) 0
,...
= 4-.
o
C.) ,..
0 0
rn
=
o
-+C.):
(1.) C:L
0
=
o
...-. -t
0
1.)
0
CI.
=
o
- t
.
u 0
0 C.
t
o
s:t
cll
3-
U 0
0. c- .4-. ."" 0. o) 0. ci) CI. 0 0. 0 0. 0 i--
cn od 't ri) ,.= (,) ..z
= o = -
tn s. CA
=
L-, 0CA
co 8 =0
c, I
= 0 H
u c:. ..=0 0=
0
E--, w o 0 0 0
c>
o
4 = 0:, 0 c, c0 c) cd fa, 0-.)
et U 0
,-. o
,-,
o (0 <0 C)
,_. W 5 o
- -, -'
Pli 0
0
0' 0
z Cl) cA a)
,-, a)
- =.' 0 rn s- o
-t 0 0 a) a) 0 as
0 -;:. " = `+- LI.
v) .47-1
u a)
sa, u (1) .4. cll 0- =
"
CA " r)
E ,"-,... a) u) 2a)
et
= 03 -..
cu = v)
U Sa. 4. C/)
el
..-, Ci) ' '- at T:i. `/'-
** .- a. ,,,
= o 0
z tao mt r ,- 5 > .41 ...Y
E'1 ol 74 To tE.s, = -cs
c '
0
$:1. .
= 0
cA =>
0 0 = .0 7,d'czi :_. eu .2.,,) c. 4-c..;.
o -o 9
C.) 'T
.) y.., a.) a) ...
C.)
-
En ., .2 = = = -t:J ,`Q ct
- ..,;_-;
0 0
64 0 4.-' ozi
to
0 -1-- ct, - 4c.) bEc 'c2 ''' a'
401 -^ -
Fl a) Li:--_, 0
0 ,-,
13 -4 0 ,.1% 3
'1.) 0 o 0 C "4E5
cil al
0
U
u 0 0 0.
,-, ,.., cn tu a 2
r ) 0
-,-. t to
-q P . - -
LO =
-C3
0 4! i .--4
Ct
"CJ ira., =
(1)
0' "5
0 8 z
. a) I...
= -5 u N a)
a) >-, g -o ,-
g 0? cA'' .-
cn
.0.
.-_-, COD 0
"0 "0
0
H 4. " 4a.'
- E ,.sz
=
U
-"t -c-t <1.) a') , --el 0E0 0
Z == 7,
-_, ':'3 " C a
- .., .,... 76,
H - 7d ,
0 0 -, 4 o =
0z:
74
U CA ..L4 r2 <4-,
O
'- C..) 0 cd - rn ct
> ''A .g
+., a) .,
(A 0. 5 . 4. Z
,..0 > 5 0
U ct .
,-
a)
cn c+- v, 7i
_ ri
- 03 :_c_ $. ,..SZ
.--,
0 cn
023 v, = 0;
z
(I)
.2 = 0 o cu
E-1
1-4 =t sz 0 .4 = cn
O 0 01 4- 0 7 0 0 -0
> - sa. 0 :hr. = E = ::).
' to
0., 0
E a)
H
C) tit's.. ,...,0 ta, cn
4.0
.)
a5 0 cu - u)
0
E0 o..
cr3 o cn -....,1::3 4.
=
0 Sa. cn = -0
-. .--. Ow - = = 0
on -0 ......, 0 0
C..) 0 = +-.
d
i..4 i.-
ct. s-
CA
0 0
4- I.)
.o. "0 = .,.., = H
(-) V]
c",) CA
0
to cz -, =o
a) c'-' -
7:1 en tt .4:: C 3
C.. -.
"0 Col) '-'' 0 = --4C.) -4al.,
"0 ... co3 0 mt < ":
LA ca. E a)
< CD 0 Cl. E 44 =
E-1 3 -a 0 -- = " () 0
z 0 'E > .- L
(I-I
a''C,,
...,
C1)
,, a.,
1-4 c5 in ,c> r 0 ,__, CI M
4 c+1 t",) c; 4 4 4 4
Page 144 of 283
t-il (.11 -1=. -I, - 4=6 -1=, CA
CA &, I
.---) Zm :4=, 0.
0 0 OC
H
5 ,
v, 0 ^" '
:-11:1 P -0 o o'
o
ti CD v)
o a =P
A 0-3
ck CD CT '
0 OP' (1, '-.(-s-':). 0 2
2 0 SW C.)
P "11% N WO z
ro It El/'
0 ,.., po o 1:3 CD 0. tt
AD
= -r, 1Z
AD 0 0'"' cn (7 V, ,...
, 0 - CA ---.
e-t.
^0 - -4- "' CD AD 0 o -cl ,'.'-
' o
!F4- tw .-4- P CA .41
-t-
-o $1) C4
r)
2. z 0 Cr 0 '0
__. 0 cr cc, - H
0
= '0 1-1
.- VI Fr o 'F'," Fr 0 . r-t,t-
AD 0 rD
Fr
0 $1.) ;ID
= UP ti) "0 0- cD g n -
,-+
ci CI. o - ca. pPo *3
0-4 0 (1) l'
tz%)
CD
0_, P 7
n CD
.._.
,,, v) A)
(Y. 0
(/) ta.
1:$__...
"
CD ''''
,-, .o cl
8 P
... a H CJI
-g.
,
r)
Fl.
2 4r-t-.3
,_,.
=
o 43 '-d
cc Ow Z
AD- = ,-r-
__. .- ;.-
= o r, o 04.
= ''- PV X cr
= li
CDP CD H H ,. y)
0 ',I, 5 ,..., ,e4 4) C; P A) AD 0 r)
= .M66 i C4
a "
Ca. 0 *3
0 c .-11 0 c) 0 H AD o..
0 = - = 0- CD AD '0
"0
til
; 2 , CD 0 CI) "0 0
0 po = %
()
*CS Po Z--). CM?
-- Fr,
.0 =) 0 -0 t. 0 0 v)
AD CD 0 *0 0-3
t' ' ,4- VD
.... .5. '"-
CD 8' Fo"' co 0
Po = ,,
4 cr c4
C) (fa S. 0
*11 ,.+, pi, O'ci
Fo- -
H 0 CD
"
cn 0 r0
(4 ,-cs ot
Ts > 0- o - ,..-
c:, c) 0
0 CA c:, c, c> r)
0 0 ----- i:j 0 0 0 ',T.',
.c,,,o, 0. ci, ,:<:3 0
c:2' o c::' tt *i
ti.t.1 .-1 0
.:'
r)
4
H 5 5 0
5 0 (,) , co
co, .____. X -, c.
a n) Co H
a -64
,-, -cs n -0
1:s (1) ,, 0 A -.
=t'
o c., ' -3 71) r)
o0 0 oo 0 0 0 0 0 0
'0:-+ -0 5 W P:1
DI) 0
---
0 0
= = = HH =
cn
i I . , . I cl to
t*
1-1 to v)
r)
0
,Iv
cA ril
o
io .21
id 11
Z = Z =
ci.)
tIl ocl
rii
r)
H
I4
til 0
51
pzJ z z _..i 7:J 4
p:1 .0
.
PD a 0 Pr) <
o- C 5 . cl c- CD
.-I
,,, co
cn
co( ) i CD cA .--1 0 -.
'CS 0 n
11) E-1 = ig H k.)
w CD-t 0 cn Cr 0 0
C' .0 . CD 0 2-3 1:4 0'C..
0
:>
C 'z' ;CD r:!. ,..+ rs) aCt
'CC 0 ..0 ,--
v) z 0
Sr 2 F-2. = CI) p
" z o 5 R. ii , r.)
o .. CD
-+ 0 0 00
* . H
cn < i1
o c,9 til
o CD
0 1
5 cy-,
2t) in> o " =
=
v, et, CD 0. CD
, C . Cl.
'Cj " cn
0 w 0 11) a Hz
or Ir ' g r,' 0 .--,
BCD ,--]
re fr. or . ,-) p .
- rl CD a. .-. = r)
a CD Cd
tc) .--s-.
'-1 -1- = ci) CA
c15- (9, CD tl)
,-s 0
,Hr6g CD
-r M.
> F1
= rs
t=1,.70- =C4 0-
> OD Fr 0
CD Ili
CC, CL, cn n. -- CC
0 0 !0 CD
r) >
CA 1-0, H 000 c> c,
c,
CD cy c:, =
DC ,.:' 0 r=1 '-i
C CD C
co
5- 0 cr4D ,T 4
o CD 0
GA
,
=-'
CD 0
co crto p; = P
CI- la ,,,, cr
5* -< 0 /0 -o71, 'D r)
CD 0 0 6cr. CA
- CD w ;..., 0 0 :-4.1..0
0 FD . ' ' - ' AD
0 CD Cf9 C/) 0 = '
-1 X "
EZ O t CD 0 CD rn C ca, CD C
74. cn 0 -e
cn CD 0.
CD
_
0" A.
4C
CA
C Fa CD 0
4
C )
*IC) 0 Pa 0 co
> 0 *0
:0 O
- cA
Lt2 r)
a P:i o
C- e) it
< til
C. CD cr
,_.- O. C".
-< cn
C
O It *11
P,
0 od ii
co = x
cD
0I cA
0.0
7:J m
CD r)
H -0
co
.
tt
Il
0
0
co = Z
ed
cD ..I
CT) `''
20 0 x 25 LG. SNAP
HEAD RIVET
1
1
6R 15
1NO. 60
DRAIN HOLE
DETAIL 'X'
TELL TALE HOLE
BUND
FLANGE
IM16
jk4j6;.11?l''-
6 30.06.2011 REAFFIRMED AND REISSUED AS STANDARD POREL KM/SC DM
5 11.09.2006 REAFFIRMED AND REISSUED AS STANDARD POREL DNN AKM VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. Page 147 of 283 by by
Approved by
Format No. 8-00-0001-F4 Rev.0 Copyright EIL - All rights reserved
Olar
STANDARD No.
ENGINEERS MANHOLE WITH DAVIT
geINIDIA LIAM 7-12-0010 Rev. 6
/A Govt. of India Undertaking)
Page 2 of 2
8
260 350
(320)
40R NP4,
10V
ti DETAIL OF HAND GRIP
HAND GRIP
141"
0
I
1N
N 20 0 x 25 LG. SNAP
250 HEAD RIVET
// PIPE 'A'
il \\
// \\
\\\
1/ \\ \ I I
/ \\ I I 0
II 1111 I I
30 VENT
\ 11 II
I I // ) 0
\\ // FR
\ \ s.\\
\\
\\
....--
1
1
//
ii
//
//
Y
------_ --------------
1 15
3N0.M16 SS JACK SCREWS
ON BOLT CIRCLE DIAMETER 1NO. 60 )
(SEE NOTE-3) DRAIN HOLE
DETAIL 'Y'
1 N0.-3mm NPT
TELL TALE HOLE
TOP OF DEMISTER
!6!;!.9.!VAtt;!..!..!!:!.!!..!:!..!!....!!:!:!..!:!
UM
DETAIL-X
HORIZONTAL VESSEL
V)
Z
7
CC TOP LADDER RUNGS EQUISPACED AT BOTH LEVELS O
o 2-NOS. FOR DIA. < 1000. 1=1
a"'
0
4-NOS. FOR 1000 < DIA. < 2000 I
cJ p) 1-
< 6-NOS. FOR 2000 < DIA. < 3000 0 W
I I
8-NOS. FOR DIA. > 3000
%.D
V) _j
HANDGRIP 175 175
350+1/2 MANHOL DIA. CU
MANHOLE
II
`1,
e) DETAIL-X
200
r DETAIL-X
F
175 175
HANDGRIP
NOTES
1. ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
A 2. VARIATION IN SPACING BETWEEN LADDER RUNGS IS PERMITTED
IN CASE OF INTERFERENCE WITH SOME NOZZLE OR INTERNALS.
HOWEVER THE SPACING OF RUNGS SHALL BE EQUAL.
SQUARE RODS MAY BE USED FOR HANDGRIP / LADDER RUNGS.
IF FABRICATED FROM PLATE THE EDGES ARE TO BE ROUNDED OFF.
MATERIAL SHALL BE AS PER ENGINEERING DRAWING.
ALL FILLET WELDS SHALL BE 6 mm MINIMUM.
ORIENTATION OF LADDER RUNGS SHALL BE SAME AS OF MANHOLE.
7. DIMENSIONS SHOWN IN BRACKETS ARE FOR STAINLESS STEEL MATERIAL. r
du
5 30.06.2011 REAFFIRMED AND REISSUED AS STANDARD POREL T AKM/SC DM
4 11.09.2006 REAFFIRMED AND REISSUED AS STANDARD POREL DNN AKM VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose by
Convenor Chairman
No. by Approved by
Format No. 8-00-0001-F4
Page 161 Rev.0
of 283 Copyright EIL - All rights reserved
DOCUMENT No.
SCOPE OF SUPPLY A307-16-46-SS-6545
Rev. A
Page 1 of 5
SCOPE OF SUPPLY
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 162 of 283
DOCUMENT No.
SCOPE OF SUPPLY A307-16-46-SS-6545
Rev. A
Page 2 of 5
SCOPE OF SUPPLY
[X] Indicates applicability
1. Owner
[ ] Shell
[ ] Skirt
[ ] Manhole neck, nozzle neck 300 NB and above in carbon steel and 125 NB and
above in stainless steel
[ ] Reinforcement pad
[ ] Wrapper plate
[ ] Internal piping
[ ] Insulation support
[ ] Lifting lugs
[ ] Baffle
[ ] Demister support
[ ] Pipe fitting
[ ] Gasket
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 163 of 283
DOCUMENT No.
SCOPE OF SUPPLY A307-16-46-SS-6545
Rev. A
Page 3 of 5
[ ] Brick lining
[ ] Refractory lining
[ ] Tower packing & associated internals including distributor, feed pipes, support grid /
plates, retaining grid / bed limiters
[ ] Thermowells
2. VENDOR
2.1 Boiler quality/low alloy/stainless/ clad steel / Monel plate conforming to specification
as per respective Mechanical data sheet for
[X] Shell
[X] Manhole neck, nozzle neck 300 NB and above in carbon steel and 125 NB and
above in stainless steel & 200 NB and above in clad steel shall be fabricated from
clad plate.
[] Wear plate
[X] Vacuum stiffening rings, structural & Piping cleats directly welded to shell
[X] All welded support for packing, distributors, chimney trays, other internals
2.2 Structural steel section and plate conforming to IS:226/IS:2062 Gr.B/ SA-283 Gr.C for
[ ] Shell
[ ] Internals
[ ] Flat cover
[ ] Manway flange/cover
2.3 [X] Forged flanges / matching blind flange/ companion flange wherever shown
[X] Studs/bolts and nuts for manway/handholes/internal flanges /nozzles with matching
flange/shell flange/ companion flange, including jack bolts for manway
[X] Gasket for manway/companion flange/shell flange/ nozzles shown with blind flanges
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 165 of 283
DOCUMENT No.
SCOPE OF SUPPLY A307-16-46-SS-6545
Rev. A
Page 5 of 5
[X] Demister with grid and bolting. Material of construction of Grid and bolt shall be
same as demister material.
[X] Seamless nozzle neck 250 NB and below in carbon steel and 100 NB and below in
stainless steel & 150 NB and below for weld overlayed nozzles.
[] Spray nozzle
[ ] Internal packing
[ ] Light and sight glass assembly with 4 sets of spare glasses for each size
[X] All other metallic and non-metallic parts, consumables and gases not covered under
1 and 2 but required to complete fabricated equipments including inspection, testing
and supply of equipments as per this requisition
[X] Spares - 10% of fasteners (minimum two numbers) and two sets of gaskets for each
nozzle shown with blind flange/for each shell flange.
[X] Spares - 10% (min. 4 nos. of each size/type) extra fasteners (bolts,nuts, clamps,
spacers etc.) as required for holding the demister / Steam Coil.
[] Arranging all machinery including crane, tools etc., required for assembly, loading /
unloading, heat treatment, testing, transportation etc. and all equipments for site
activities.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 166 of 283
SUPPORTS STANDARD No.
laftetitErsiGINEaS
dgar faMegvir INDIA UMIT1ED FOR 7-12-0032 Rev. 4
INET! meow =mom) to Govt. of India Undertaking)
INTERNAL FEED PIPE Page 1 of 2
SEE
VESSEL DRG. 00
TYPEIA
100
VENT HOLE
(6+2xC.A.)
50 TO 75 THK. MIN. FLAT
AS PER
PIPE SIZE
I I ' 25 R
TYPE-1
INTERNAL FEED PIPE FOR HORIZONTAL VESSEL
SPARGER/FEED PIPE SUPPORT
NOTE TYPEIA IS APPLICABLE FOR LARGE THERMAL EXPANSION (AIR / GAS SERVICE)
(6+2xC.A.)
THK. MIN. FLAT
TYPE-2
INTERNAL SPLASH FEED PIPE FOR HORIZONTAL VESSEL
65
15 0 HOLE IN PIPE CLEAT (6+2xC.A.)
& 30 LONGx15 WIDE SLOTTED THK. MIN. FLAT
HOLE IN SHELL CLEAT
SUPPORT CLEAT
FOR VERTICAL VESSEL
TYPICAL DETAIL OF BOLTING CLEATS
3MM
CLEARANCE
REINFORCEMENT PAD
(NOTE-6)
TYPEA
(FOR PIPES UPTO 250NB)
TS
20 MIN. D (NB) 50
SHELL
11
II
REINFORCEMENT PAD L
(NOTE-6)
10 NF
0.5G
If)
TYPEB
(FOR PIPES ABOVE 250NB)
T
PIPE N.B. BOLT SIZE E F G
D CA=O CA=1.5 CA=3 CA=5 CA=7
50 80 M 12 6 10 12 16 20 60 40 60
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
IN CASE OF CONFLICT VESSEL ENGG. DRAWING SHALL GOVERN.
MATERIAL OF CLEATS SHALL BE AS PER VESSEL ENGG. DRAWING.
ALL FILLET WELDS TO BE ALL AROUND & SIZE OF WELDS ARE (6+1xC.A.) MINIMUM UNLESS OTHERWISE STATED.
ALL INTERNAL BOLTS SHALL BE MIN. M 12 SIZE AND OF STAINLESS STEEL WITH DOUBLE NUTS.
REINFORCING PAD SHALL BE LARGER BY 50mm ALL AROUND THAN BRACKET CLEATS. NO PAD IS REQUIRED FOR
VESSELS WITH WALL THICKNESS GREATER THAN 25mm.
)?./
4 31.08.2011 REAFFIRMED AND REISSUED AS STANDARD POREL K 4/KM / SC DM
OgMO NO MRS
INDIA WITH)
(A Govt. of India Undertaking)
S. R. NOZZLE NECK 7-12-0037 Rev. 3
Page 1 of 1
* 30*(MIN.)
1.5 t(MIN.) (TYP)
c
NOTES : SELF REINFORCED WELD ENDS
DESIGN CALCULATION FOR ALL THE DIMENSIONS OF S.R. NOZZLES / WELD
DESIGN
ENDS SHALL BE APPROVED BY EIL.
ANY DEVIATION IN THE OVERALL PROJECTION FROM THE SPECIFIED DESIGN
DATA SHALL BE MADE ONLY AFTER OBTAINING PRIOR APPROVAL FROM EIL.
FLANGES MAY BE FORGED INTEGRALLY WITH S.R. NOZZLE NECK.
I.D. OF FORGING SHALL BE AS SPECIFIED ON ENGG. DATA SHEET.
* 5. APPLICABLE FOR ASME SEC. VIII DIV.1 EQUIPMENT ONLY.
6. ALL SHARP CORNERS SHALL BE ROUNDEDOFF SMOOTH.
44,;,,tj
3 23.05.2011 REAFFIRMED AND REISSUED AS STANDARD POREL RKT
10 THK. PLATE
VESSEL PART
tr.)
N
14 DIA. HOLE
(FOR M12 BOLT)
75 25
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
ALL EQUIPMENTS SHALL BE PROVIDED WITH TWO(2) EARTHING
LUGS, UNLESS OTHERWISE STATED.
3.(a) EARTHING LUGS SHALL BE LOCATED DIAMETRICALLY OPPOSITE ON
NORTHSOUTH CENTER LINE ON SKIRT SUPPORTED EQUIPMENTS,
ON ANY TWO(2) LEGS OF THREE(3) LEG SUPPORTED VERTICAL VESSEL,
ON DIAMETRICALLY OPPOSITE LEGS OF FOUR(4) LEG SUPPORTED
VERTICAL VESSEL AND ON EACH SADDLE OF HORIZOTAL VESSEL.
TWO(2) EATHING LUGS ARE TO BE LOCATED ON EACH SADDLE OF
HORIZONTAL VESSEL OF LENGTH GREATER THAN 20 METERS.
FOR SPHERE, TOTAL 4 NOS. OF EARTHING LUGS SHALL BE PROVIDED
PREFERABLY ON DIAMETRICALLY OPPOSITE AND EQUALLY SPACED LEGS.
(SPHERES ARE USUALLY PROVIDED WITH LEGS IN NUMBERS WHICH ARE
MULTIPLE OF 4 FOR THE SYMMETRY)
DO NOT WELD EARTHING LUG ON PRESSURE PART.
IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
6. MATERIAL OF CONSTRUCTION SHALL BE CARBON STEEL.
0
J
V)
10 R
BRACKET
NAME PLATE
0
r-
4-
N
EIL NAME PLATE
o 0:
+
N
0
N
0
MANUFACTURER NAME PLATE
<TYP
2V
200
230
NOTES
I. ALL DIMENSIONS ARE IN inn UNLESS OTHERWISE STATED.
2, BRACKET MATERIAL SHALL BE SAME AS SHELL MATERIAL.
N
PAD ALL AROUND
SEE NOTE-7
SKIRT
INSIDE 100NB SCH. 40
40 PIPE VENI
SKIRT
EQUISPACED INSIDE
BASE PLATE
SKIRT
80x6THK. PLATE
INSIDE
cv II 2mm(TENTATIVE)
CHECK FOR PIPE
THERMAL EXPANSION.
MALLER OF tx+2
OR 14mm (FOR PIPE
SSEE NOTE-6)
OR INSULATED PIPE+10
SEE NOTE-10
2-120 HANDLE
3-50 PINS-15 LG
EQUISPACED
VIEWQ
VIEWP
NOTES (HOT TYPE VESSEL) (COLD TYPE VESSEL)
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
ACCESS OPENING SHALL BE LOCATED BETWEEN ANCHOR BOLTS WHEREVER POSSIBLE.
ACCESS OPENING IS NOT TO BE BLOCKED BY BOTTOM HEAD.
SKIRT DIAMETER ACCESS OPENING DIA.(D) NO. OF ACCESS OPENING
UP TO 1000 400 1
OVER 1000 UPTO 1500 450 1
OVER 1500 UPTO 3000 500 1
OVER 3000 500 2
SKIRT DIAMETER NO. OF VENT HOLES
UP TO 1000 2
OVER 1000 UPTO 2000 3
OVER 2000 4
MINIMUM SIZE OF PIPE SLEEVE IS 150NB SCH 40. USE SCH 40 UPTO 250NB PIPE SLEEVE. FOR 300NB AND
ABOVE, PIPE SLEEVE SHALL BE FABRICATED FROM PLATE.
ALL OPENINGS 300 DIA. AND ABOVE SHALL BE PROVIDE WITH REINFORCEMENT PADS ON INNER SURFACE OF SKIRT.
IN CASE OF CONFUCT ENGINEERING DRAWING SHALL GOVERN.
IN FLARED SKIRT, OPENING DETAIL IS SAME AS THAT FOR CYLINDRICAL SKIRT.
WOODEN BLOCK SHALL BE FIXED TO SLEEVE WITH TWO NO. OF WOOD SCREWS.
ACCESS OPENING/PIPE OPENING/VENT SHALL BE OF SAME MATERIAL AS THAT OF SKIRT.
ALL FILLET WELDS SHALL BE 6 mm MINIMUM.
* 13. PROJECTION OF SLEEVE/NECK SHALL BE GREATEST OF (30+INSULATION THK.), (30+FIRE PROOFING) & 50mm.
14. CENTER LINE OF ACCESS OPENING SHALL BE 850 MM (MINIMUM) ABOVE BOTTOM BASE RING FOR ANCHOR
BOLTS OF SIZE M45 & BELOW AND 1100 MM (MINIMUM) FOR ANCHOR BOLTS OF SIZE ABOVE M45. IF ANCHOR
CHAIR HEIGHT IS MORE THAN THAT OF GIVEN IN STANDARD. LOCATION OF ACCESS OPENING SHALL BE ESTABLISHED
SUITABLY.
1
5 23.05.2011 REAFFIRMED AND REISSUED AS STANDARD POREL RKT
JOB SPECIFICATION
FOR
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
1.0 SCOPE
1.2 Demister assembly shall include wire mesh pads, holding grids, major
support beams (if provided), clamps, bolting, spacers, tie wires/rods etc.
required to hold the grids and pads in position when assembled/
installed on supports welded inside the vessel.
2.0 REFERENCES
3.1 All the raw materials including wire mesh, sheet/plate, sections, bolting,
tie wires etc. required for the manufacture, packing and supply of the
demister assemblies covered in this package shall be in Fabricator's
scope of supply. Owners scope of supply is NIL.
3.2 All materials used for manufacture of the demister components shall be
new and of first quality.
4.1 Demister size to be such to ensure tight fit between each section of the
demister and the vessel walls.
4.2 Demisters with diameters greater than 1800 mm shall be supplied with
support beams. Material of support beams, welded supports etc. shall
be compatible with vessel material as per datasheets.
4.3 Demister pads shall be designed for a net upward thrust of 100.0
KG./M2 (minimum)due to vapour loadings. It shall also be able to
withstand a concentrated live load of 60 Kg. at any point on individual
components.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
4.5 All internal bolts shall be of minimum M10 size and of stainless steel
with double nuts.
4.6 Vendor shall furnish six copies of the detailed drawings for the demister
assemblies to the Purchaser for review. The drawings to incorporate,
minimum following details.
5.1 Vendor shall ensure that the demister pad will be accommodated in the
shell fabricated as per ASME Pressure Vessels Code Section VIII
Division I (out of roundness 1% of the nominal diameter across shell
diameter) and EIL Standard 7-12-0001 ( Vessel Tolerances ) and
Licensor Standards wherever available.
5.2 The individual demister assembly along with grids, beam etc. shall be
trial assembled on shop floor and measurement of diameter shall be
done.
5.3 Materials used for fabrication shall be supported with test certificates.
5.4 The demister shall be inspected stage wise as well as at the time of
dispatch by the Inspecting Authority.
6.0 GUARANTEE
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
7.1 All demisters should be handled with great care as damage can
seriously affect performance. Due to the high free volume and the fine
mesh structure the demister sections can be easily distorted.
7.2 The individual components shall be marked with proper item numbers
and shall correspond to the number given on the drawings. These
identification marks shall be as per enclosed Packing and Marking
Specification No. 6-14-0009.
8.0 SPARES
8.1 Vendor shall supply 10% (min. 4 nos. of each size/type) extra fasteners
(bolts, nuts, clamps, spacers etc.) required for holding the demister as
constructional spares.
8.2 Vendor shall include operational spares, if any, required for two years
normal operation and give the details of the same in their offer
separately.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
O.D.
B.C.D.
18 DIA. HOLES
FOR M16 BOLTS
THICKNESS OF
NOMINAL NUMBER FLANGE t
PIPE SIZE I.D. B.C.D. O.D.
OF BOLTS CARBON S. STEEL
(mm)
STEEL OR MONEL
40 51 110 160 4 16 10
50 63 120 170 4 16 10
80 92 150 200 4 16 10
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
* 3. FILLET SIZE IN BRACKET ARE FOR STAINLESS STEEL / MONEL.
FULL FACED GASKETS SHALL BE USED.
DIMENSIONS EXCEPT THICKNESS FOR INTERNAL FLANGES OF SIZE 25NB OR LESS SHALL BE AS PER
ASME 816.5 CLASS 150. FLANGE THICKNESS AND FACING SHALL BE EQUIVALENT TO 4 NB LANGE
COVERED IN THIS STANDARD. 2 14-4
5 30.07.2011 REAFFIRMED AND REISSUED AS STANDARD POREL AK / SC '' DM
4 11.09.2006 REAFFIRMED AND REISSUED AS STANDARD POREL DNN AKM VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by Approved by
Page 204 of 283 Copyright EIL - All rights reserved
Format No. 8-00-0001-F4 Rev.0
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A307-16-46-TR-6545
Rev. A
Page 1 of 9
INSTRUCTIONS TO BIDDERS
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 205 of 283
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A307-16-46-TR-6545
Rev. A
Page 2 of 9
INSTRUCTIONS TO BIDDERS
(A) CATEGORY I MR
1. Bidders to note that no correspondence shall be entered into or entertained after the bid
submission.
2. Bidder shall furnish quotations only for those items, for which he is approved by EIL and
which he can supply strictly as per MR specifications.
3. No technical details of any nature shall be included in the offer. If the offer contains any
technical deviations or clarifications or stipulates any technical specifications (even if in line
with the MR requirements), the offer is liable for rejection.
4. The submission of prices by the bidder shall be construed to mean that he has confirmed
compliance with all technical specifications of the corresponding item(s).
1. The quoted price includes for the HOLDS details of which are indicated on the drawing.
2. The weights indicated on EIL Engineering Drgs. do not form the basis for offer, since these
are approximations only.
3. Spares included in of doc. A307-16-46-SS-6545 shall be included in the quoted price.
4. Bidder quoted price includes the following finished weight of Structural and piping clips.
Any decrease/ increase in weights shall be recovered/ paid as per Doc.No. A307-16-46-UR-
6545.
1. The equipment having length more than 20 m and / or forming Gross vehicle weight
(Weight of equipment and the weight of vehicle clubbed together) more than 49 MT
shall be transported by Hydraulic axles only with compliance to all statutory norms of
authorities concerned.
2. Prime mover of the vehicle to have GPS tracking system to monitor the movement of
consignment.
Technical Instructions
1. The shape of dished end/toricone, profile of conical reducer, cone angle , knuckle radius and
overall height shall be as per engineering drawing. Minimum thickness of shell, cone and
dished end shall be achieved taking into account thinning and scaling etc.
2. Dished ends and hot formed pressure parts shall have 10% or 2mm (whichever is higher)
allowance for scaling and thinning, in order to achieve minimum thickness specified on the
drawing.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 206 of 283
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A307-16-46-TR-6545
Rev. A
Page 3 of 9
3. a) Wherever hot forming and subsequent heat treatment is involved, adopted procedure shall
not impair the mechanical properties of the material beyond the limits specified in respective
material specification.
b) For low temperature equipment and hot formed parts, number of production coupons and
the tests thereon shall be as per requisition.
4. Post weld heat treatment and all non destructive testing like radiography, ultrasonic testing,
magnetic particle/dye penetrant examination etc. shall be conducted as per requisition.
8. For IBR vessels, approval of drawings, documents, stagewise inspection and final
certification of the equipment by Inspectorate of Boilers shall be included in bidders scope.
Complete design of equipment as per IBR shall be carried out by vendor.
10. The main equipment shall not be subcontracted, however the bought out items/ components
can be sub-ordered or sub-contracted to EIL approved vendors/sub-contractors only.
11. Demister/ Agitator shall be procured from EIL approved vendors only.
12. Fabricator to supply Box type template for checking the orientation of anchor bolts on
foundation and to ensure matching of base plate that is drilled in advance. The schedule of
supply of template at site shall be 8 weeks from FOA.
13. Gaskets used for hydrotesting of vessels shall be of the same specification as service
gaskets and the fabricator shall supply new gaskets for manholes and nozzles with blind
flanges apart from spares. Gaskets used for hydrotest shall not be used for actual hook up.
14. While transporting completed vessels, fabricator shall provide suitable type and no. of
supports so that no deformation of any part of the equipment takes place.
15. Fabricator shall exercise utmost care during loading/unloading of equipment so that no
damage to any part of the equipment occurs. Suitable type and no. of supports shall be
provided for supporting the equipment.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 207 of 283
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A307-16-46-TR-6545
Rev. A
Page 4 of 9
16. Fabricator shall also design and provide suitable stiffening arrangement at the base anchor
chair locations so that deformation/buckling of base and bottom zone does not occur at the
time of lifting while the vessels are being erected.
17. Fabricator shall design and provide lugs/trunnions for handling and assembly of vessel
sections.
18. Number of temporary attachments/cleats, lifting lug/trunnion used for site assembly should be
kept minimum. Temporary attachments / cleats shall be removed by fabricator after complete
execution of work if desired by engineer-in-Charge leaving 12mm from the shell & grinding of
all cut edge burrs.
19. If the equipment is to be transported via sea routes (marine transportation), the following shall
be provided by bidder and included in the quoted price:
After completion of all testing and inspection, the inside of complete equipment shall be
thoroughly drained and dried out. Equipment shall be completely dried by passing hot air for
sufficient time until no further increase in relative humidity of outgoing air is observed. After
drying, the equipment shall be purged and filled with dry N2 at 0.25 kg/cm 2. The equipment
shall be provided with pressure gauge to monitor N2 pressure and non-return valve. All
threaded holes other than tell tale holes for testing shall be suitably protected with steel bar
plugs. All nozzles not provided with blind flange shall be provided with steel covers,
temporary gaskets and bolts. All external surfaces shall be properly protected / covered
against sea environments.
20. Erection weight given in equipment data sheet is approximate. Vendor shall calculate the
actual equipment weight and furnish calculation. Erection weight furnished in vendor drawing
shall be based on fabricators calculation. Calculation of Centre of Gravity (C.G.) of the
equipment shall also be done by vendor and marked on the equipment & in the fabrication
GA drawing.
21. For internal distributor pipes, internal flanges shown are minimum required. It is vendors
responsibility to provide required number of flanges to ensure removability through nearest
manway.
All production welding shall be examined by RT. In case vendor want to perform UT by TOFD
technique in lieu of RT, the same is acceptable subject to the following:
b) With Code Case 2235, Automated UT incorporating TOFD and pulse echo probes or
TOFD and Phased Array mounted on the same chassis that automatically traverses
along the joints to be inspected and displaying both results simultaneously on a single
screen may be considered in lieu of RT.
c) Calibration block of similar material/thickness shall be used. Calibration block shall have
suitable notches to simulate longitudinal as well as transverse cracks on outside and
inside surface. Setup should be capable of detecting defects on outside as well as
inside while scanning from one surface only.
successfully the capability of AUT machine and the defects evaluation in the same
screen during the site visit of EIL inspector/EIL representative. Based on which, the
approval of the parties and their AUT system shall be given.
23. When spot radiography is specified, the extent of radiography defined in Clause 5.4.2 of EIL
specification 6-12-0001 Rev. 5 shall be replaced as follows:
Each category A or B pressure containing weld shall be spot radiographed in accordance with
ASME Section-VIII Division-I, paragraph UW-52 as a minimum requirement. Each Spot
radiograph shall be a minimum of six inches (150mm) in length and minimum one spot shall
be selected in each circumferential & longitudinal seam. Additionally at least one T-joint in
each circumferential seam shall also be selected. Welds from each welding procedure,
welded/welding operator shall be examined.
It is proposed to have Video conferencing of management review and helmet camera for
shop floor view, to bring active involvement and transparency between the customer
(BPCL/EIL) and the major equipment manufacturers. For this purpose, the following
procedure is formulated:
The vendor shall have video conferencing facility at their manufacturing unit.
Management review of the job status shall be done through video conferencing on a
monthly basis or on a mutually agreed interval. Also the work in progress at the
vendors workshop shall be shown live to BPCL/EIL through helmet camera.
The vendor could share the same information of manufacturing like plan vs. actual
progress of the equipment/ system at the OEMs site with the BPCL / EIL.
General Instructions
1. All materials including those used for internals shall be procured with stage-wise inspection.
Stagewise and final inspection of equipments and its components shall be carried out as
follows:
a) For Foreign Vendors: Stagewise & final inspection of the equipment including all
components and internals shall be carried out by third party inspection agency. Quoted
price shall include for the same.
b) For indigenous Vendors: EIL shall be inspection agency for equipments and its
indigenous components. Incase internals/forging/plates etc. are procured from abroad,
the inspection shall be carried out by third party inspection agency. Quoted price shall
include for the same.
Fabrication shall not commence before their approval except as noted at Sl. No. 2 & 3.
2. Raw material procurement may proceed prior to approval of vendor drawings on the basis of
Material Requisition and all testing and agency for testing shall be arranged by Vendor.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 209 of 283
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A307-16-46-TR-6545
Rev. A
Page 6 of 9
3. Shell rolling/welding and dished - head fabrication shall commence without awaiting
fabrication drawing approval. Inspection shall be carried out in accordance with Purchase
Requisition documents till approved fabrication drawings are available.
4. Material for shell, dished ends and skirt shall be considered as major raw material wherever
identification of major raw material is one of the payment milestones.
5. Purchase requisition shall be issued within two weeks of Fax of intent (FOI). Final nozzle
sizes (without any holds) shall be issued along with purchase requisition or latest within one
month of Fax of intent (FOI).
6. Nozzle orientation of the equipment shall be issued latest by mid of contractual delivery
period reckoned from date of issue of Fax of intent (FOI).
7. Pipe support/structural clip details shall be issued latest by three months before contractual
delivery date.
8. Minimum course width shall be 1 metre. Maximum no. of longitudinal seams shall be as
follows:
( a) vessels upto 2 metre diameter : 1 seam
( b) vessels from 2 metre upto 4 metre dia. : 2 seam
( c) vessels from 4 metre upto 6 metre dia. : 3 seam
( d) vessels from 6 metre upto 10 metre dia. : 9 seam
In any case, distance between two longitudinal seams shall not be less than 3 metre.
9. If any discrepancy is found during design and fabrication stages, the fabricator shall inform
EIL immediately and shall obtain necessary clarification/approval before proceeding with that
portion of the job any further. EIL's review of fabricator's drawings and documents must not
be considered as a check and shall not relieve the fabricator of his responsibilities to supply
equipment as per requisition. Fabricator shall remain responsible for conflicts between his
drawings/documents and EIL drawings/documents.
10. English language and metric units shall be used in all documents. Drawings shall be prepared
in prescribed sizes as standardised by bureau of indian standards (BIS) and shall be
preferably in the sizes such as 210 x 297, 297 x 420, 420 x 597, 597 x 841, 841 x 1189 mm.
11. All fabricator's drawings submitted to EIL shall be based on purchase requisition and shall
bear reference number and revision of the corresponding EIL drawings. In addition, it shall
indicate item number, client's name, project name, fabricator's name, purchase order number,
purchase requisition number,,drawing number, revision number etc. all in the lower right hand
corner. All revisions shall be clearly marked by encircling with revision marks.
a). Vendor shall prepare Document Control Index (list of those drawings, which are to be
submitted to EIL along with the submission dates for each drawing) within 15 days of
placement of FOI. Successful bidder to submit DCI (document control index) and all
the vendor data through vendor portal (http://edocx.eil.co.in:7001/vportal) only. The
detail guidelines for uploading the documents on vendor portal are available on the
site itself.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 210 of 283
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A307-16-46-TR-6545
Rev. A
Page 7 of 9
b). Vendor to note that unscheduled documents (documents which are not listed in DCI)
shall not be accepted by EIL. All vendor drawings/documents shall be submitted as
scheduled document only.
14. All drawings shall be thoroughly checked and duly signed by fabricator. Unchecked drawings
and drawings without revisions clearly marked shall be returned without review. Successive
review of the same fabricator's drawing shall apply only to EIL's latest data sheet/comments
on the previous revision. Drawings and documents returned to fabricator for revision shall be
resubmitted preferably within ten days of receipt.
15. Dimensions of all flanges shall be as per ANSI B16.5 for nozzle sizes 24"NB and below and
as per ANSI B16.47 Series B for sizes greater than 24"NB ,unless otherwise stated.
Stage-I
- General arrangement drawing indicating design data, fabricated equipment's weight,
general notes, nozzle schedule, detail of shell, heads, skirt/supporting arrangement, main
weld seams, nozzle orientation plan, cutting layout (in case of free issue material) etc.
- Bill of material for each item showing part size, quantity, material specification, scope of
supply and weight etc.
Stage-II
- Detail of internals such as tray support ring and bolting bar.
- Detail of external clips for ladder, platform, pipe support, insulation, fire proofing, pipe davit,
lifting lugs etc.
- Bill of material for each item showing part size, quantity, material specification, scope of
supply and weight etc.
- In case of owner's free issue plate material, fabricator shall submit plate cutting diagram for
EIL's approval.
17. After receipt of order, fabricator shall submit to EIL, the planning of fabrication which shall
indicate the details and scheduled date of:
- Sub orders.
- Purchase of materials such as plates, pipes, forged flanges, bolting, gaskets, etc.
- Start of fabrication of dished ends and shell, welding of shell and heads.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 211 of 283
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A307-16-46-TR-6545
Rev. A
Page 8 of 9
This planning shall be established to extend from purchasing of equipment components to the
end of fabrication and delivery of equipment.
18. All drawings shall be drawn in AUTOCAD R-14.No hand drawn drawings shall be accepted.
All residual calculations shall be computerised.
19. Documents and letters shall be furnished in electronic format. The software used shall be as
follows.
a) MS OFFICE 97 or above
b) ADOBE ACROBAT 4.0 & ABOVE
20. In case of owner's free issue plate material, fabricator shall tabulate each plate detail as per
following table:
21. Words fabricator, vendor, contractor appearing any where in the MR/Specifications/
Standards etc. shall be read as bidder.
22. Further to pt. No. 8 of General Instructions; Bidder to note that interference of nozzles
with circumferential seams is not acceptable. However, vendor to take suitable care to
avoid fouling of external/internal attachments with C-seams. Vendor to submit shell
development for checking above in the Ist submission.
23. Vendor shall note that the vendor drawing for the following standard components shall not be
reviewed by EIL. It shall be solely vendor's responsibility to ensure the correctness of these
drawings as per EIL Standards and Drawings. If any discrepancy / mistake is found at a later
date the vendor shall rectify the same at his time and cost.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 212 of 283
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A307-16-46-TR-6545
Rev. A
Page 9 of 9
- Earthing lug
- Pipe support cleats and ladder and platform cleats (Fouling of external support cleats (if
any), shall be highlighted to EIL along with shell development drawing and suggestion for
resolution)
However, all these above listed drawing shall be submitted in a separate drawing for
information to EIL ensuring adherence to all the respective EIL Standards and Drawings.
Clarifications (if any) shall be obtained by Vendor from EIL before fabrication.
24. Standard Inspection and test plans are attached with requisition for guidance. Vendor shall
submit inspection test plans for the approval of visiting inspection engineer. Inspection shall
take care of all the requirements of specifications. Inspection engineer has the authority to
modify the plan depending on the criticality of the item.
25. In the event of conflict, most stringent requirement in following order of precedence shall
govern:
However in event of conflict it shall be the duty of the Vendor to bring it to EILs attention for
resolution and resolve it before proceeding with the manufacture. EILs comments shall be
final and binding on vendor without any cost and delivery implications.
26. Finish Paint for buried equipment (IST-V-504) is included in vendors scope.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 213 of 283
LIFTING LUG STANDARD No.
laRtze ENGINEERS
TOP HEAD TYPE 7-12-0024 Rev. 7
fafRegNIFINDIA LIMITED
iiiw ecReelVaX3,10543) (A Govt. of Indio Undertaking)
(FOR VERTICAL VESSELS / COLUMNS) Page 1 of 1
SECTION XX
BOTTOM OF BRACE TO TOP OF LUG F 200 230 300 400 500 600
BOTTOM OF BRACE TO T.L OF HEAD E SEE NOTE 2
T.L. OF VESSEL TO BOTTOM OF LUG B 200 230 280 350 400 480
C 30 40 50 70 90 100
TOP OF LUG TO Q OF HOLE J 90 90 115 150 180 230
K 30 40 50 70 80 100
NO. OF LUGS 2 2 2 2 2 2
NOTES
1. ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
*2. DIMENSION 'E' IS TO BE DETERMINED BY THE SHAPE OF HEAD IN CONJUNCTION WITH DIMENSION 'K'.
DETAIL, DIMENSIONS AND NOTES GIVEN IN ENGINEERING DRAWING TAKE PRECEDENCE OVER THOSE SHOWN HERE.
FOR THIN WALLED EQUIPMENTS, DESIGNER SHALL ANALYSE THE STIFFENESS OF SHELL AT THE LIFTING LUG LOCATION.
IF PADS ARE USED ON STAINLESS STEEL EQUIPMENTS THE SIZE OF FILLET WELD BETWEEN SHELL AND STAINLESS
STEEL PAD SHALL BE ANALYSED.
MATERIAL SHALL BE COMPATIBLE WITH HEAD MATERIAL.
FOR INTERMEDIATE ERECTION WEIGHT, NEXT HIGHER SIZE OF LIFTING LUG SHALL BE USED.
LIFTING LUG SHALL BE MACHINED TO COVER OFFSET BETWEEN OUTER DIAMETERS OF SHELL AND HEAD.
TYPE - A
IUD 1000
1200
950
1100
700
800
330
375
820
960
B
B
12.3
19.4
85
130
HOLE FOR 1400 1250 900 465 1150 B 19.7 140
SLIDING SUPPORT
1600 1450 1000 370 1300 C 23.3 165
1800 1600 1100 410 1450 C 39.1 260
D/18 2000 1750 1200 445 1600 C 43.5 290
O 9R
2200 1950 1300 495 1800 D 49.1 295
i 110 111 2400 2150 1450 545 2000 D 53.5 390
ki iii
__.
..1 2600 2300 1550 585 2150 D 52.9 440
11 1
Li Li
N- II It
1 0
2800
3000
2500
2670
1650
1750
620
670
2300
2500
E
E
52.7
64.9
475
600
I- EARTHING 3200 2800 1850 710 2600 E 63.8 620
I 250
L
26 0 HOLES FOR 3400 3000 1950 760 2800 E 64.9 630
30 M 20 BOLTS
111111 3600 3200 2050 830 3000 E 60.5 725
TYPE - B
DUD ,
3800
4000
3350
3550
2150
2250
845
895
3150
3300
E
E
61.0
60.6
745
820
HOLE FOR
SLIDING SUPPORT
TYPE t1 t2 L3 t3
D/18 A 10 10 170 12
B 10 12 250 12
110 C 12 16 300 16
D 16 20 350 20
2-60 VENT
HOLE (TYP.) E 20 20 400 20
(REF. NOTE-5)
I L 1 I L1 I Li 140
EARTHING
I 250
L2
I 30 0 HOLES FOR
30 M 24 BOLTS
PARALLEL TO VESSEL
TYPE - C. D. E AXIS (TYP)
HOLE FOR
SLIDING SUPPORT
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
VESSEL DIAMETER 'D' REFERS TO THE OUTER DIAMETER OF THE SHELL.
FOR INTERMEDIATE DIAMETERS TAKE THE IMMEDIATE NEAREST DIAMETER SUPPORT.
WELDING SHALL BE DONE ALL AROUND AND SHALL BE CONTINUOUS FILLET WELD. WELD SIZE SHALL
BE 6 mm FOR VESSELS UPTO 1400 mm DIA. AND 8 mm FOR VESSELS ABOVE 1400 mm DIA.
PROVIDE 2 NO. 60 VENT HOLES IN SADDLE WRAPPER PLATE. THESE HOLES SHALL BE PROVIDED DIAGONALLY
OPPOSITE AND BE LEFT UNPLUGED AND SHALL BE FILLED WITH HARD GREASE ONLY.
WHERE EARTHING LUG CANNOT BE PUT AT AN ELEVATION OF 400 mm ABOVE THE SADDLE BASE PLATE
IT SHALL BE LOCATED AS HIGH AS POSSIBLE.
EARTHING LUGS ARE NOT TO BE PAINTED OR GALVANIZED.
DETAIL, DIMENSIONS AND NOTES IN ENGINEERING DRAWING TAKE PRECEDENCE OVER THOSE SHOWN HERE.
MATERIALS SHALL BE AS PER ENGINEERING DRAWING.
EARTHING LUG SHALL BE AS PER STANDARD 7-12-0026
CHAIR CAP
NOTCH GUSSET TO WASHER WELD AT SITE
CLEAR WELD CONTINUOUS RING
NOTCH GUSSET TO
CLEAR WELD
EARTHING LUG
ir
// BOLT 0
+ 3mm
H 20
//
W
n A K
AK +V BOLT 0
-17
I-
II BOLT 0
+ 12mm
L + 12mm
(ALL DIMENSIONS AND DETAILS ARE
BCD BCD SAME AS SHOWN FOR TYPE-2
BCD EXCEPT CONTINUOUS RING)
BOLT 0 + 12mm
[WIDE SLOT RADIUS
+ 6mm
TYPE-1 TYPE-2 SLOT DETAIL TYPE-3
(SEE NOTE-6) (FOR CONTINUOUS RING ONLY)
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
BOLT CIRCLE DIAMETER ( BCD ), NUMBER AND SIZE OF THE BOLTS SHALL BE AS PER ENGINEERING DRAWING.
* 3. DIMENSIONS t1, t2, t3 AND 'I: ARE TO BE CHECKED IN EVERY CASE.
IN CASE OF ANY CONFLICT THE ENGINEERING DRAWING SHALL GOVERN.
NUMBER OF BOLTS USED IS TO BE A MULTIPLE OF 4 AND BOLTS SHALL STRADDLE VESSEL NORTHSOUTH
CENTRE LINE IN PLAN.
USE CONTINUOUS RING ( CHAIR CAP ) IF DISTANCE BETWEEN CONSECUTIVE BOLTS IS LESS THAN 400 mm.
CIRCULAR WASHER SHALL BE SHIPPED LOOSE AND WELDED AT SITE AFTER ANCHOR BOLTS ARE IN POSITION.
8. PREFERRED DIMENSION 'A'
EARTHING LUG SHALL BE LOCATED BETWEEN THE ANCHOR BOLTS AND SHALL BE AS PER STANDARD 7-12-0026.
WHEN THE ANCHOR CHAIR CAP IS NOT CONTINUOUS, THE BASE PLATE SHALL BE SUITABLY STIFFENED USING
REMOVABLE STRUCTURAL SECTIONS (BEAM/SPIDER) AT SITE DURING ERECTION.
t*/
6 30.06.2011 REAFFIRMED AND REISSUED AS STANDARD POREL RKT M/SC DM
5 08.09.2006 REAFFIRMED AND REISSUED AS STANDARD POREL DNN AKM VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by
Approved by
Page 216 of
Format No. 8-00-0001-F4 283
Rev.0 Copyright EIL - All rights reserved
STANDARD No.
lagE1eMENGINEERS
eg fiffleellir (AINDIA LIMITED PIPE DAVIT 7-12-0023 Rev. 6
(WM Govt. of India Undertaking)
Page 1 of 3
W
L_
r= ANGLE SIZE 'SI X IX TAPPED HOLE
o a- Z WITH M16 BOLT
In co
L. 0
N mw
ANGLE SIZE 'S'
DETAIL IN TOP BRACKET
SHT. 2 aq
TOP OF PLATFORM
I
HAND
RAILING
z
TAPPED HOLE 1
WITH M16 DOLT 8
PIPE cu
SIZE 'D' 1 DETAIL-70 0
DETAIL W
, TOP OF
I PLATFORM
1.--1)DAVIT SUPPORT
HAND RAILING
4Q N
(TYPE-1) (TYPE-2)
65
DEVIT FOR TOP DEVIT FOR SIDE TO SUIT
MOUNTED PLATFORM MOUNTED PLATFORM PIPE O/D.
8-180 HOLES
A (MAX) B CAPACITY PIPE SIZE ANGLE SIZE R1 R2 r t EQUISPACED
Cm) (rim) Ckgs.) D S
500 100NBxSCH.160 75x75x6 75 60 10 20
1000 1000 150NBxSCH.80 100x100x8 110 60 12 25 160 LOCKING
I'2
PIN
(Ci
500 150NBxSCH.80 100x100x8 110 60 10 20
2000 1000 200NBxSCH.80 150x150x10 140 60 12 25
0
0 LOCKING PLATE
:: 500 200NBxSCH.80 150x150x10 140 60 10 20
/.
3000 1000 200NBxSCH.160 150x150x12 140 60 12 25 DETAILX DETAILY
R1
D (NB) D1
100 120
150 175
POSITIONING 200 225
PLATE
DETAILZ (DAVIT EYE)
DETAILK
DETAILP
4---
6 31.08.2011 REAFFIRMED AND REISSUED AS STANDARD POREL KM / SC DM
5 12.10.2006 REAFFIRMED AND REISSUED AS STANDARD POREL RKG AKM VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by
Approved by
Page 217 of
Format No. 8-00-0001-F4 283
Rev.0 Copyright EIL - All rights reserved
STANDARD No.
laNzieMENGINEF_RS
*Iges Of5legNW (AINDIA LIMITED PIPE DAVIT 7-12-0023 Rev. 6
Men Govt. of India Undertaking)
Page 2 of 3
EXTENSION ANGLE
DETAIL- -
CHAIN
(MIN. 350 LG.)
REF, LEVEL
ISMC 100
ELEVATION
50 (TYP)
PLATFORM (NOTE-8
N\
DETAIL Q
80
25NB SCH.80 INS. THK.
PIPE SLEEVE +300
030x10 THK.
PLAN (TOP BRACKET)
020 TURNING
12 THK.
REF. AXIS
in
170
17 60 15 25 10 20 17
to
2 CAPACITY KGS
NAME PLATE
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
NAME PLATE
MATERIAL STAINLESS STEEL 2mm THICK.
NAME PLATE IS TO BE TACK WELDED TO THE DAVIT PIPE.
THE LETTERS AND NUMBERS SHALL HAVE RAISED POLISHED FACE.
BACKGROUND SHALL BE BLACK.
DIMENSION 'A' SHALL BE SUCH THAT THE DAVIT EYE EXTENDS PREFERABLY BY 900 mm OUTSIDE PLATFORM.
REFER ENGINEERING DRAWING FOR DIMENSIONS A, B, C, E, CAPACITY OF DAVIT AND INSULATION THICKNESS.
THE DAVIT USED SHALL CLEAR HANDRAIL OF THE EQUIPMENT.
MATERIAL OF PIPE SHALL BE A-53 / IS:1978 OR EQUIVALENT AND STRUCTURAL PARTS SHALL BE IS:2062 GR.B
OR EQUIVALENT.
IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
FOR THIN WALLED EQUIPMENT, DESIGNER SHALL ANALYSE THE STIFFNESS OF SHELL AT THE BRACKET LOCATIONS.
DETAIL DIMENSIONS AND NOTES IN ENGINEERING DRAWING TAKE PRECEDENCE OVER THOSE SHOWN HERE.
LOCKING PLATE (DETAIL Y), LOCKING PIN (DETAIL X) WITH CHAIN, POSITIONING PLATE (DETAIL K), DEFLECTOR
CONE (DETAILP) AND LOCKING SUPPORT CHANNEL (DETAIL Q) SHALL BE SUPPLIED LOOSE BY FABRICATOR AND
WELDED AT SITE BY MECHANICAL CONTRACTOR.
ALL FILLET WELDS SHALL BE 6 mm MINIMUM.
FOR LOW TEMPERATURE SERVICE, BRACKET DETAILS SHALL BE AS PER EIL STD. 7-12-0034
13. IN CASE DIMENSIONS 'B' IS BEYOND THIS STANDARD, IT IS RECOMMENDED TO INSTALL PIPE DAVIT
ON STRUCTURAL PLATFORM.
t-/
-1(j491Ak.
6 31.08.2011 REAFFIRMED AND REISSUED AS STANDARD POREL KT KM / SC
DM
STANDARD No.
15iffazle ENGINEERS
e...111E1f5teg INDIA LIMI TED MANUFACTURER NAME PLATE 7-12-0028 Rev. 5
(llETI FIUME 115r3911771) (A Govt. of Indio Undertaking)
Page 1 of 1
I-
fY
CO
)-
W
_1
m
1.5
L...; V)
C.) o
Q 0_
Li_
I-
o o Li
w Z I
=
La 5
Zi cc o_
0 Li)
a. = La
0
co
i a
M
7"
Z I-
La La
I- VI 1..J La.
I- IX 0
fi)IX C E
t,_ ix
-J N
taJ
in 0 0 a u.
i
W La 0
W 0
CZ CD I J
La I
i La
X - Lai La
1
I- -I
x
< I- 6 (n
'-
0
V)
0 0
w
< 0
ct)mw
Lai IX 0
-I ILI _i J
Z 0
= ix le
I-Li
ce
0 z
LL 4'1
0 I 1-
E m -1 le a) V)
E 0 m .()
4 " L.
Z
z ,, 1.-
< m
0
1 o
N W
V) __I co
,_ m
La le .. I
IX 0
Q 0 i I
< -J N _1
_1
_1 vi 4I 0 ..t
V1 m I cc Z
Z 0 in ..t v)
= ..:
v, Z o
Li) ce = Lai Z 1-61
Z Lai 0 I-
5 < I-
w
m
i ce
1- 0 0_
1
0 0_
5 L i
ICW
X
La La
2
Cl)-J
-J J () 4 < 2 Lu
ll- 41
I- < < CO Z IX Z
0
Z Csi Iii 4 ui (IS
,/0/49-4-1"/ 5/44-k
5 31.08.2011 REAFFIRMED AND REISSUED AS STANDARD POREL RKT AKM / SC DM
4 12.10.2006 REAFFIRMED AND REISSUED AS STANDARD POREL RKG AKM VC
LIST OF APPLICABLE
SPECIFICATIONS & STANDARDS
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 242 of 283
LIST OF APPLICABLE DOCUMENT No.
SPECIFICATIONS & A307-16-46-LL-6545
STANDARDS Rev. A
Page 2 of 5
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 243 of 283
LIST OF APPLICABLE DOCUMENT No.
SPECIFICATIONS & A307-16-46-LL-6545
STANDARDS Rev. A
Page 3 of 5
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 244 of 283
LIST OF APPLICABLE DOCUMENT No.
SPECIFICATIONS & A307-16-46-LL-6545
STANDARDS Rev. A
Page 4 of 5
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 245 of 283
LIST OF APPLICABLE DOCUMENT No.
SPECIFICATIONS & A307-16-46-LL-6545
STANDARDS Rev. A
Page 5 of 5
VS402B 1 -
[X] Inlet Baffle [CB&I]
CMS-830-04-SD-12044
[X] Mist Pad [CB&I]
S20.029-B
[X] Typ. Details of demister
Attachments
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 246 of 283
STANDARD No.
NOZZLE REINFORCEMENT
ENGN33IS
INDIA LIMITED 7-12-0013 Rev. 6
111111171,1111,11MIND (A Govt. of loft Undertaking) AND PROJECTION
Page 1 of 2
0
1
5-
1-30 NPT TELLTALE HOLE
(REFER NOTE-7)
O
NOTES
1. ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
2. IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
C) 3. WIDTH IS MINIMUM AND SHALL BE CHECKED AGAINST CODE REQUIREMENT. CHECK REINFORCEMENT REQUIREMENT FOR
ALL EXTERNAL PIPING LOADING ALSO.
4. NOZZLE PROJECTIONS ARE BASED ON INSULATION THICKNESS EQUAL TO 75mm. FOR INSULATION THICKNESS
GREATER THAN 75mm, THE NOZZLE PROJECTION IS 'A' + [INSULATION THICKNESS(mm)-75].
5. PROJECTION 'A' FOR SELFREINFORCED NOZZLE SHALL BE BASED ON DESIGN OF REINFORCEMENT SUBJECT TO
MINIMUM REQUIREMENTS AS PER THIS STD.
6. EXTEND PAD LOCALLY FOR MANHOLE DAVIT SUPPORT, IF REQUIRED.
7. EXTERNAL REINFORCING PADS SHALL HAVE A MINIMUM OF 1 NO. TELLTALE HOLE EXCEPT THAT PADS FOR
NOZZLES GREATER THAN 10"NB(250NB) SHALL HAVE MINIMUM TWO NOS. TELLTALE HOLES AND NOZZLES IN
EXCESS OF 36"NB (900NB) SHALL HAVE 4 NOS. TELLTALE HOLES. PAD INSTALLED IN SECTIONS SHALL HAVE
ATLEAST ONE TELLTALE HOLE PER SECTION. TELLTALE HOLES ON REINFORCEMENT PADS SHALL BE
EQUALLY SPACED IN CIRCUMFERENTIAL DIRECTION OF PAD.
8. TELLTALE HOLE SHALL NOT BE PLUGGED AND SHALL BE FILLED WITH HARD GREASE ONLY, AFTER
HYDROTEST/PNEUMATIC TEST OF EQUIPMENT.
9. o) FOR COLUMNS & VERTICAL VESSELS, PROJECTION OF NOZZLE ON TOP HEAD SHALL BE 400mm MINIMUM FROM
OUTSIDE.
b) FOR HORIZONTAL VESSELS, PROJECTION OF NOZZLES ON TOP SIDE OF SHELL SHALL BE 300mm MINIMUM FROM
OUTSIDE.
10. PROJECTIONS ARE BASED ON ASME 816.5 FLANGES FOR UPTO AND INCLUDING 24"NB NOZZLES AND ASME 816.47
SERIES 'B' FLANGES FOR NOZZLE SIZES ABOVE 24"NB.
.1 1
Y
NOTCH TO WELD UNE
CLEAR WELD
TANGENT UNE
S./
O
0
0_
to
NOTES
w ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
FOR DESIGN OF SUPPORT, FOLLOWINGS PARAMETERS HAVE BEEN CONSIDERED.
WIND PRESSURE 200 Kg/m2
SHAPE FACTOR 0.7
BASIC SEISMIC COEFFICENT (a0) 0.08
SOIL FOUNDATION SYSTEM FACTOR ( /3 ) 1.5
IMPORTANCE FACTOR (I) 2.0
EMPTY WEIGHT WITH WIND LOADING OR HYDROSTATIC WEIGHT
WITH SEISMIC LOADING.
HEIGHT AND NUMBER OF LEG SUPPORTS AND SIZE OF ANCHOR BOLTS
HOLE DIA = BOLT DIA +
SHALL BE AS PER ENGINEERING DRAWING.
MINIMUM BOLT SIZE SHALL BE M 20.
6rnn\ 91-11-E MAXIMUM INSULATION THICKNESS CONSIDERED IS 150 mm.
IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
ALL FILLET WELDS SHALL BE 6 mm MINIMUM.
MATERIALS SHALL BE AS PER ENGINEERING DRAWING.
EARTHING LUG SHALL BE AS PER STANDARD 7-12-0026.
SUITABLE PAD FOR SS VESSEL SHALL BE PROVIDED.
0--64
5 30.06.2011 REAFFIRMED AND REISSUED AS STANDARD POREL KT KM/SC DM
4 08.09.2006 REAFFIRMED AND REISSUED AS STANDARD POREL DNN AKM VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by
Page 249 of 283 Approved by
Format No. 8-00-0001-F4 Rev.O Copyright EIL - All rights reserved
Page 250 of 283
Page 251 of 283
Page 252 of 283
Page 253 of 283
Page 254 of 283
STANDARD No.
18iatER7 ENGINEERS
,Ig ej. &Aft INDIA LIMITED
INIURFIEVWC1X3,111.1.1) (A Govt. of Indio Undertaking)
NAME PLATE 7-12-0027 Rev. 5
Page 1 of 1
"CE
co
1
6 .. z 1-
Li,
I- u_
<
1- Y 0 E
0
<
E
.1 csj
ce Zt
w
N m 1 L,_
o
w o
cc I _1
w 1 1
w Ww
I- 0 Y i
o T I- 0 v)
a
w 0 IX V)
tr) L.LI CO U)
La 0 w
_1 __I Ix _I
D o C.)
1
Li -4Z
1
cr)
E CD 6 C1
)
E < o LL.
Lo 1-- 1 o
Z a co w N Li,
_1 CD CO
w _J 1
w < _1 N _1
< 2 J _1
V) < 0 <
(/) I CC I
Z 0 V-) < (1)
0 Z 0
U) o Lu WW..
1-- Z
<
0 ,- n
W
w ix
0 CL
V 0_
m
E cr
Y L.L1 L.Li LO
(/) _1
_I C<C) <
2 1- 1 . 1L "i
MI < CO Z O Z
0
Z . CI ri 4 6 tO
/ 11. , ^
4.0 0
2/Vvt'4
KT
5 31.08.2011 REAFFIRMED AND REISSUED AS STANDARD POREL 44.4) AKM / SC DM
4 12.10.2006 REAFFIRMED AND REISSUED AS STANDARD POREL RKG AKM VC
UNIT RATES
FOR
ADDITION/DELETION
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 257 of 283
UNIT RATES DOCUMENT No.
FOR A307-16-46-UR-6545
ADDITION/DELETION Rev. A
Page 2 of 8
1. Offer shall contain the sheets given below & the subsequent sheets for addition / deletion of
nozzles duly filled in, else offer will be rejected. Please note that the same EIL sheets as
given below shall be filled in and enclosed in the offer. Bidder shall not enclose his own
sheets.
2. It is understood that
a) The quoted price includes for the HOLDS details of which are indicated on
respective equipment Engineering Drawing.
b) The weights indicated on EIL Engineering Drawings do not form the basis for offer,
since these are approximations only.
c) Spares as included in Cl. 2.3 of Scope of Supply are considered for in the quoted
price.
- IS:2062 Gr. B
- SA-516 Gr. 60
- SA-516 Gr. 70
- IS-2062 Gr. B with SS Pad
- IS-2062 Gr. B with BQCS
Mat. Pad
- SA-516 Gr. 60
- SA-516 Gr. 60 (HIC resistant
+ NACE compliant)
- SA-516 Gr. 70
- SA-240 Gr. 304
- SA-240 Gr. 304L
- SA-240 Gr. 316
- SA-240 Gr. 316L
- 100 NB Sch.160
- 150 NB Sch.80
- 200 NB Sch.80
- 200 NB Sch.160
- 200 NB Sch. XXS
- 300 NB Sch.160
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 258 of 283
UNIT RATES DOCUMENT No.
FOR A307-16-46-UR-6545
ADDITION/DELETION Rev. A
Page 3 of 8
- IS:2062 Gr. B
- SA-516 Gr. 60
- SA-516 Gr. 70
- SA-240 Gr. 304
- SA-240 Gr. 304L
- SA-240 Gr. 316
- SA-240 Gr. 316L
- SA-106 Gr.B
- SA-53
- IS-2062 Gr.B
- SA-283 Gr.C
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 259 of 283
UNIT RATES DOCUMENT No.
FOR A307-16-46-UR-6545
ADDITION/DELETION Rev. A
Page 4 of 8
- SA-234 Gr.WPB
- SA-234 Gr.WPB (seamless)
- SA-234 Gr.WPB (NACE
compliant)(seamless)
- (SA-234 Gr.WPB + SS 347
Clad) (NACE)
- (SA-234 Gr.WPB + SS 347
Weld Overlay) (NACE)
- SA-234 Gr.WPB + SB 127
Weld Overlay.
- SA-516 Gr. 60
- SA-516 Gr. 70
- SA-516 Gr. 60 (NACE
compliant +HIC resistant)
- SA 516 Gr 60 (HIC)
- SA 516 Gr. 60 ( NACE)
- SA-516 Gr. 60
- SA-516 Gr. 70
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 260 of 283
UNIT RATES DOCUMENT No.
FOR A307-16-46-UR-6545
ADDITION/DELETION Rev. A
Page 5 of 8
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 261 of 283
UNIT RATES DOCUMENT No.
FOR A307-16-46-UR-6545
ADDITION/DELETION Rev. A
Page 6 of 8
SL.NO. NOMINAL SIZE WITHOUT BLIND WITH BLIND WITHOUT BLIND WITH BLIND WITHOUT WITH BLIND REMARKS
NB FLANGE FLANGE FLANGE FLANGE BLIND FLANGE FLANGE
1 25
2 40
3 50
4 80
5 100
6 150
7 200
8 250
9 300
10 350
11 400
12 450
13 500
14 600
15 650
16 700
17 750
18 800
19 850
20 900
21 1050
22 1200
23 1350
24 1400
25 1450
26 1500
NOTES :-
1. MATERIAL SPECIFICATION FOR NOZZLE COMPONENTS SUCH AS NOZZLE NECK, FLANGE, REINFORCEMENT PAD, NOZZLE STIFFENER,
STUDS, NUTS AND GASKETS SHALL BE AS PER ENGINEERING DRAWING. NOZZLE REINFORCEMENT AND PROJECTION DETAIL SHALL
BE AS PER EIL JOB STANDARD NO.7-12-0013.
2. SCOPE OF SUPPLY OF NOZZLE COMPONENTS SHALL BE AS PER MATERIAL REQUISITION.
3. THE RATES QUOTED SHALL INCLUDE SUPPLY OF NOZZLE NECK, FLANGE, STIFFENER, STUDS, NUTS AND GASKETS (WHEN SUPPLIED
WITH BLIND FLANGE) AND ASSOCIATED FABRICATION AND TESTING.
4. PRICES INDICATED ABOVE SHALL BE IRRESPECTIVE OF NOZZLE THICKNESS.NO EXTRA CLAIM ON THIS ACCOUNT WILL BE
ENTERTAINED AT A LATER DATE.
5. THE SCHEDULE OF RATES EXCLUDES COST OF REINFORCEMENT PAD.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 262 of 283
UNIT RATES DOCUMENT No.
FOR A307-16-46-UR-6545
ADDITION/DELETION Rev. A
Page 7 of 8
SL.NO. NOMINAL SIZE WITHOUT BLIND WITH BLIND WITHOUT BLIND WITH BLIND WITHOUT WITH BLIND REMARKS
NB FLANGE FLANGE FLANGE FLANGE BLIND FLANGE FLANGE
1 25
2 40
3 50
4 80
5 100
6 150
7 200
8 250
9 300
10 350
11 400
12 450
13 500
14 600
15 650
16 700
17 750
18 800
19 850
20 900
21 1050
22 1200
23 1350
24 1400
25 1450
26 1500
NOTES :-
1. MATERIAL SPECIFICATION FOR NOZZLE COMPONENTS SUCH AS NOZZLE NECK, FLANGE, REINFORCEMENT PAD, NOZZLE STIFFENER,
STUDS, NUTS AND GASKETS SHALL BE AS PER ENGINEERING DRAWING. NOZZLE REINFORCEMENT AND PROJECTION DETAIL SHALL
BE AS PER EIL JOB STANDARD NO.7-12-0013.
2. SCOPE OF SUPPLY OF NOZZLE COMPONENTS SHALL BE AS PER MATERIAL REQUISITION.
3. THE RATES QUOTED SHALL INCLUDE SUPPLY OF NOZZLE NECK, FLANGE, STIFFENER, STUDS, NUTS AND GASKETS (WHEN SUPPLIED
WITH BLIND FLANGE) AND ASSOCIATED FABRICATION AND TESTING.
4. PRICES INDICATED ABOVE SHALL BE IRRESPECTIVE OF NOZZLE THICKNESS.NO EXTRA CLAIM ON THIS ACCOUNT WILL BE
ENTERTAINED AT A LATER DATE.
5. THE SCHEDULE OF RATES EXCLUDES COST OF REINFORCEMENT PAD.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 263 of 283
UNIT RATES DOCUMENT No.
FOR A307-16-46-UR-6545
ADDITION/DELETION Rev. A
Page 8 of 8
SL.NO. NOMINAL SIZE WITHOUT BLIND WITH BLIND WITHOUT BLIND WITH BLIND WITHOUT WITH BLIND REMARKS
NB FLANGE FLANGE FLANGE FLANGE BLIND FLANGE FLANGE
1 25
2 40
3 50
4 80
5 100
6 150
7 200
8 250
9 300
10 350
11 400
12 450
13 500
14 600
15 650
16 700
17 750
18 800
19 850
20 900
21 1050
22 1200
23 1350
24 1400
25 1450
26 1500
NOTES :-
1. MATERIAL SPECIFICATION FOR NOZZLE COMPONENTS SUCH AS NOZZLE NECK, FLANGE, REINFORCEMENT PAD, NOZZLE STIFFENER,
STUDS, NUTS AND GASKETS SHALL BE AS PER ENGINEERING DRAWING. NOZZLE REINFORCEMENT AND PROJECTION DETAIL SHALL
BE AS PER EIL JOB STANDARD NO.7-12-0013.
2. SCOPE OF SUPPLY OF NOZZLE COMPONENTS SHALL BE AS PER MATERIAL REQUISITION.
3. THE RATES QUOTED SHALL INCLUDE SUPPLY OF NOZZLE NECK, FLANGE, STIFFENER, STUDS, NUTS AND GASKETS (WHEN SUPPLIED
WITH BLIND FLANGE) AND ASSOCIATED FABRICATION AND TESTING.
4. PRICES INDICATED ABOVE SHALL BE IRRESPECTIVE OF NOZZLE THICKNESS.NO EXTRA CLAIM ON THIS ACCOUNT WILL BE
ENTERTAINED AT A LATER DATE.
5. THE SCHEDULE OF RATES EXCLUDES COST OF REINFORCEMENT PAD.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL All rights reserved
Page 264 of 283
geINIDIA
Oliar LIMITED
MINERS
Govt. of India Undertaking)
MANHOLE WITH
HINGED COVER
STANDARD No.
7-12-0009 Rev. 6
Page 1 of 2
SS HINGE
BAR
MIN 3 THK. WASHER
80 C' 4 GAP
BLIND
M16 FLANGE
80 SS COTTER PIN
WITH 3THK. WASHER
1-3mm NPT
-J 120 0
TELLTALE HOLE U-
N
I-
0
1 110 0
M16
0
20 0 ROD
SEE NOTE-2
slue
HANDGRIP DETAIL OF JACK SCREW
di 0
BLIND FLANGE
SLOPE TO FIT
PERIPHERY OF
W.N. OR S.O. MANHOLE FLG.
FLANGE R
W.N. OR S.O.
II d10
R
FLANGE
MIA9111
BLIND FLANGE
NOMINAL G t d R d1 L
FLANGE RATING
BORE
400 298 28 35 55 36 42
450 318 28 35 55 36 42
CLASS 150
500 348 28 35 55 36 42
600 406 28 35 55 36 42
400 324 28 35 55 36 42
450 355 28 35 55 36 42
CLASS 300
500 386 30 35 55 36 42
600 458 30 35 55 36 42
400 342 32 40 55 41 47
450 372 32 40 60 41 47
CLASS 600
500 406 36 40 60 41 47
600 470 36 40 75 41 47
400 352 32 40 60 41 47
450 394 32 40 65 41 47
CLASS 900
500 428 40 40 70 41 47
600 520 40 40 90 41 47
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
WELD HINGE TABS AFTER TIGHTENING THE COVER WITH GASKET IN PLACE
AND MAINTAIN A LOOSE FIT OF HINGE BAR IN HINGE TABS.
BCD OF JACK SCREWS IS TO BE SUITABLY CHANGED IF MANHOLE
STUDS INTERFERE WITH JACK SCREWS.
IF SQUARE RODS ARE USED FOR HANDLES, THEIR EDGES SHALL BE ROUNDED OFF.
IN CASE OF CONFLICT, ENGINEERING DRAWING SHALL GOVERN.
ALL FILLET WELDS SHALL BE 6mm MINIMUM.
TELLTALE HOLE SHALL NOT BE PLUGED AND SHALL BE FILLED WITH
HARD GREASE ONLY.
THE MATERIAL OF COMPONENTS SHALL GENERALLY BE IS : 2062 UNLESS
OTHERWISE SPECIFIED ON ENGINEERING DRAWING. FOR LOW TEMPERATURE
SERVICES AND SERVICES ABOVE 425*C THE HINGE TABS AND HANDLE SHALL
BE OF SAME MATERIAL AS THAT OF SHELL.
I
151fRiseA ENGINEERS FOR POSITIVE MATERIAL
si at efaleg INI NA LIMITED
/A nul na. Lnden.,), IDENTIFICATION (PMI) AT
6 - 81 - 0001 Rev. 2
SUPPLIER'S WORKS Page I of 8
covingii 4
c 1T
STANDARD SPECIFICATION
FOR
POSITIVE MATERIAL
IDENTIFICATION
(PMI)
AT SUPPLIER'S WORKS
40D ., 15,
2 20.10.11 REVISED AND RE-ISSUED AKC DM
Abbreviations:
CONTENTS
1.0 SCOPE 4
2.0 REFERENCE DOCUMENTS 4
3.0 DEFINITIONS 4
4.0 PMI EXAMINATION 5
5.0 ACCEPTABLE METHODS FOR PMI 5
6.0 EXTENT OF PMI EXAMINATION 6
7.0 RECORDING AND DOCUMENTATION 7
8.0 MARKING 7
1.0 SCOPE
1.1 This specification applies to the requirements for Positive Material Identification (PMI) to be
performed at the Supplier's works on Metallic Materials procured either directly by the
Owner/EIL/ LSTK contractor or indirectly through the sub-Suppliers.
1.2 Any post order deviation from this specification must be approved by Owner/EIL in the
Deviation/ Waiver Permit format (No. 5-0000-0180-F1) enclosed with Material Requisition.
1.3 This specification covers the procedures and methodology to be adopted to assure that the
chemical composition of the material is consistent with the material specifications as specified
in purchase documents using 'Alloy Analyzer' at the time of final inspection before dispatch.
1.4 The scope of this specification shall include but shall not be limited to Positive Material
Identification (PMI) to be performed on Materials listed below:
1.5 All grades of material supplies including Stainless Steels shall be liable for PMI test at site. In
case of any defective materials being found at site, the Supplier shall be responsible to effect
replacement of such defective materials at project site without any delays to the satisfaction of
EIL site RCM (Resident Construction Manager).
2.1 API Recommended Practice 578 (First Edition, May 1999) - Material Verification Program for
New and Existing Alloy Piping Systems.
3.0 DEFINITIONS
3.1 Supplier: Any Supplier or Manufacturer on whom an order is placed for the supply of referred
items. This definition shall also include any sub-Supplier or manufacturer on whom a sub-order
is placed by the Supplier.
3.2 Inspection Lot: A group of items offered for inspection covered under same size, Heat and
Heat treatment lot.
3.3 Alloy Material: Any metallic material (including welding filler materials) that contains
alloying elements such as chromium, nickel, molybdenum or vanadium, which are intentionally
added to enhance mechanical or physical properties and/or corrosion resistance.
4.1 The Supplier shall submit a procedure of PMI to comply with the requirements of this
Specification Approval of PMI Procedure shall be obtained from Owner/EIL/TPIA prior to
commencing manufacture/ inspection of product.
4.2 PMI examination of materials is independent of any certification, markings or colour coding
that may exist and is aimed at verifying that the alloy used are as per specified grades.
4.3 The Supplier shall identify all incoming alloy materials and maintain full traceability of all alloy
materials, including all off-cuts. Transfer of identification marks shall be undertaken prior to
cutting to ensure maintenance of identification on off-cuts.
4.4 The Supplier shall ensure that all alloy materials are segregated and stored in separately
identified locations to prevent the mix up of materials of different alloy specifications or alloy
material with carbon steel. Non ferro-magnetic materials shall be segregated at all times from
ferro-magnetic materials.
5.1 The method used for PMI examination shall provide a quantitative determination of the alloying
elements like chromium, nickel, molybdenum or vanadium in Alloy Steel items.
5.2 Instruments or methods used for PMI examination shall be able to provide quantitative,
recordable, elemental composition results for positive identification of alloying elements
present.
5.3 The acceptable instruments for alloy analyzer shall be either "Portable X-Ray fluorescence" or
"Optical Emission" type each capable of verifying the percentage of alloy elements within
specified range.
5.4 Chemical spot testing, magnets, alloy sorters and other methods using eddy current or
triboelectric testing methods are not acceptable for PMI examination.
5.5 The PMI instrument used shall have the sensitivity to detect the alloying elements in the
specified range.
5.6 All PMI instruments shall have been serviced within a 6 month period of the time of use to
verify the suitability of batteries, sources etc., and the data of the last service shall be stated on
the PMI Report Form (Sample enclosed).
5.7 Each analyzer must be calibrated according to the manufacturer's specification at the beginning
and end of each shift. Instrument must be checked against known standard for each alloy type
to be inspected during the shift.
5.8 Certified samples, with full traceability, of a known alloy materials shall be available for use as
a random spot check on the instrument calibration.
5.9 The surfaces to be examined shall be prepared by light grinding or abrasive paper and solvent
cleaner. Evidence of Arc burn resulting from examination shall be removed by light grinding or
abrasive paper. No permanent marks, which are injurious to the usage of product in service, are
acceptable.
5.10 Alloy Steel ring type joint Gaskets shall be inspected by using portable X-Ray fluorescence
instrument.
5.11 Testing shall be done as per the procedures outlined by the manufactures of alloy analyzer
being used. Modification of these procedures if any must be approved by Owner/EIL.
5.12 The persons performing PMI shall demonstrate their capabilities to the satisfaction of
Owner/EIL/TPIA visiting engineer. If the Supplier has qualified operator on their rolls, he may
perform the examination. Otherwise PMI examination shall be sub-contracted to an independent
testing agency approved by EIL.
5.13 Whenever material is identified as not meeting requirements by the visiting engineer a rejection
note shall be issued.
Following sampling plans shall be applicable for PMI examination of various items.
Note:
For Welded Pipes and Fittings, PMI shall be performed on Base Metal as well as
weldments.
Whenever any sample drawn to PMI test on the basis of percentage selection in B & C
above, fails to meet specification requirements, 100% of items of lot shall be tested for
PMI.
The results of PMI examination shall be recorded in a Report Format as enclosed with this
specification.
8.0 MARKING
8.1 All alloy materials tested by PMI shall be identified using either of the following methods by
indicating "PMI OK"
Material Specification/Grade
Element Cr Mo Ni V
Specified Range
Actual observations
Instrument Type / ID
N W.L o b
T.L
5 X COLD INSULATION
THICKNESS ( MIN 600MM)
a_
7
1=-J b
M12 SQUARE NUTS TACK WELD
ON INSIDE AND OUTSIDE OF PIPE G
SKIRT 111SUPPORT
SKIRT ON 450 TRIANGULAR PITCH
FOR FIRE PROOFING (SEE DETAIL-Y) ANGLE LEG
(REFER NOTE-8) SUPPORT
DETAILY
SECTION 'CC'
M6 X 25 LG G.I. BOLTS w 0
BETWEEN TWO CLEATS (TYP) w
AND NUTS. to z
AIR POCKET
6 THK. FLAT (FOR VESSEL TEMP.
10
ABOVE 400T)
3 THK.
ASBESTOS SHEET
L-
O
U-
r
REF. PLANE
ir4
SPECIAL NOTES
CUMULATIVE TOLERANCES ON CONSECUTIVE DIMENSIONS SHALL BE LIMITED BY OVERALL DIMENSIONAL TOLERANCES.
ALL TOLERANCES ARE FROM REFERENCE PLANE UNLESS OTHERWISE INDICATED.
INTERFERENCE BETWEEN INTERNAL AND EXTERNAL PARTS OR ANY RESTRICTION TO THE INTENDED FUNCTION OF ANY
PART SHALL BE KEPT IN VIEW WHERE TOLERANCES ARE CUMULATIVE.
SPECIFIC TOLERANCES FOR ANY PART SHOWN ON EIL DRAWING SHALL BE GIVEN PREFERENCE TO THOSE GIVEN
IN THIS STANDARD.
UNUSUALLY LARGE OR COMPLEX VESSELS MAY BE EXECUTED AS PER FABRICATOR'S STANDARD WHEN THE TOLERANCES
AS SHOWN ARE UNREASONABLE. IN SUCH INSTANCES FABRICATOR'S TOLERANCES & UMITS MUST BE SUBMITTED
FOR APPROVAL.
E. VESSEL UPTO AND INCLUDING 750 mm NOMINAL DIAMETER SHALL HAVE CARTRIDGE TYPE TRAY. FOLLOWING
TOLERANCES ON DIAMETER SHALL APPLY THROUGHOUT ITS LENGTH.
VESSEL NOMINAL DIAMETER TOLERANCE
500 mm AND UNDER VESSEL I.D. + 1 mm
501 mm TO 750 mm VESSEL I.D. 3 mm A