Drilling Operations Manual Combined - V5Feb2015' PDF
Drilling Operations Manual Combined - V5Feb2015' PDF
Drilling Operations Manual Combined - V5Feb2015' PDF
Approved by:
Approved by:
Objective of this Drilling Operations Manual is to provide checklists, best practices & lessons
learnt, step by step operational programming and background engineering data for the
common drilling and well construction activities.
The key users for whom this document is written are Petrom wellsite staff and in particular the
drilling supervisor and wellsite drilling engineer who will manage and supervise these
operations.
This document is endorsed by the Petrom Drilling Manager to standardise drilling operations.
Tel: +31-528-227710
[email protected]
www.we-p.nl
4 Well control
6 Drill Bits
8 Drilling Fluids
12 Cementing
14 Well Logging
Annular pressure
Fluid pressure in the annulus between tubing and casing or between two strings of casing.
Annular velocity
The speed at which drilling fluid or cement moves in the annulus. It is important to
monitor annular velocity to ensure that the hole is being properly cleaned of cuttings,
cavings and other debris while avoiding erosion of the borehole wall.
Azimuth
The compass direction of a directional survey or of the wellbore as planned or measured
by a directional survey. The azimuth is usually specified in degrees with respect to the
geographic or magnetic north pole.
Bit breaker
A special tool used by the rig crew to prevent the drill bit from turning while the bit sub on
top of it is tightened or loosened. Bits have noncylindrical shapes, so the conventional
wrenches used by the rig crew to tighten cylindrical shapes like pipes do not fit the bits
properly. In addition, some bits, such as PDC bits, have a wide range of unusual and
asymmetric shapes or profiles. The bit breaker must match the bit profile or the bit may
be ruined before ever being used.
Bit record
A historical record of how a bit performed in a particular wellbore. The bit record includes
such data as the depth the bit was put into the well, the distance the bit drilled, the hours
the bit was being used "on bottom" or "rotating," the mud type and weight, the nozzle
sizes, the weight placed on the bit, the rotating speed and hydraulic flow information. The
data are usually updated daily. When the bit is pulled at the end of its use, the condition
of the bit and the reason it was pulled out of the hole are also recorded. Bit records are
often shared among operators and bit companies and are one of many valuable sources of
data from offset wells for well design engineers.
Bleed off
To equalize or relieve pressure from a vessel or system. At the conclusion of high-
pressure tests or treatments, the pressure within the treatment lines and associated
systems must be bled off safely to enable subsequent phases of the operation to
continue.
Break circulation
To establish circulation of drilling fluids after a period of static conditions. Circulation may
resume after a short break, such as taking a survey or making a connection. The
operation is of more concern to drillers and well planners with longer static intervals,
since immobile drilling mud tends to become less fluid and more gelatinous or semisolid
with time.
Break out
To unscrew drillstring components, including tool joints and other threaded connections.
Buoyancy
The upward force acting on an object placed in a fluid. The buoyancy force is equal to the
weight of fluid displaced by the object. Buoyancy can have significant effects in cases in
which the wellbore and tubing string contain liquid and gas. Any change in the relative
volumes or fluid levels will change the buoyancy forces.
Caliper log
A representation of the measured diameter of a borehole along its depth. Caliper logs are
usually measured mechanically, with only a few using sonic devices. The tools measure
diameter at a specific chord across the well. Since wellbores are usually irregular
(rugose), it is important to have a tool that measures diameter at several different
locations simultaneously. Such tools are called multi-arm calipers.
Casing shoe
The bottom of the casing string, including the cement around it, or the equipment run at
the bottom of the casing string.
Centralizer
A mechanical device to position casing concentrically in the wellbore. A centralizer is
usually used during cementing operations to provide a constant annular space around the
casing, rather than having the casing lying eccentrically against the borehole wall.
Centrifuge
An item of solids-removal equipment that removes fine and ultrafine solids. It consists of
a conical drum that rotates at 2000 to 4000 rpm. Drilling fluid is fed into one end and the
separated solids are moved up the bowl by a rotating scroll to exit at the other end.
Choke line
A high-pressure pipe leading from an outlet on the BOP stack to the backpressure choke
and associated manifold. During well-control operations, the fluid under pressure in the
wellbore flows out of the well through the choke line to the choke, reducing the fluid
pressure to atmospheric pressure.
Circulation loss
The loss of drilling fluid to a formation, usually caused when the hydrostatic head
pressure of the column of drilling fluid exceeds the formation pressure.
Close-in
To close a valve to stop or isolate fluid flow. The term is most commonly applied to
"closing-in the well," meaning isolation of the wellbore.
C-plate
Plate with C-shape that can be put around the pipe to support the casing string which is in
the hole preventing it to fall down in the hole. A C-plate can be used for backup in case of
failure of the slips. It cannot be used for flush pipe.
Crossover (X-over)
A short subassembly used to enable two components with different thread types or sizes
to be connected.
Cuttings
Small pieces of rock that break away due to the action of the bit teeth. Cuttings are
screened out of the liquid mud system at the shale shakers and are monitored for
composition, size, shape, color, texture, hydrocarbon content and other properties by the
mud engineer, the mud logger and other on-site personnel. The mud logger usually
captures samples of cuttings for subsequent analysis and archiving.
Dogleg Severity
A particularly crooked place in a wellbore where the trajectory of the wellbore in three-
dimensional space changes rapidly. While a dogleg is sometimes created intentionally by
directional drillers, the term also refers to a section of the hole that changes direction
faster than anticipated or desired, usually with harmful side effects. Higher doglegs may
create problems , such as key seating or damage to the drillstring.
Drilling break
A sudden increase in the rate of penetration during drilling.
Elevator
A hinged mechanism that may be closed around drillpipe or other drillstring components
to facilitate lowering them into the wellbore or lifting them out of the wellbore.
Fines
Very small particles, either in a mud or a mud additive sample.
Float collar
A short length of casing fitted with a check valve. This device may be a flapper-valve
type, a spring-loaded ball valve or another type. The float collar prevents the cement
slurry placed in the annulus to U-tube, or reverse flow back into the casing. The greater
density of cement slurries than the displacement mud inside the casing causes the U-tube
effect.
Fracture gradient
The pressure required to induce fractures in rock at a given depth.
Gauge hole
A wellbore that is essentially the same diameter as the bit that was used to drill it.
Hole cleaning
Synonyms: Cuttings transport, cuttings lifting. Good hole cleaning means the cuttings are
efficiently removed from the wellbore by the drilling fluid.
Junk
Anything in the wellbore that is not supposed to be there. The term is usually reserved for
small pieces of steel such as hand tools, small parts, bit nozzles, pieces of bits or other
downhole tools, and remnants of milling operations.
Junk basket
A tool run into the wellbore to retrieve junk from the bottom of the hole.
Kelly
A long square or hexagonal steel bar with a hole drilled through the middle for a fluid
path. The kelly is used to transmit rotary motion from the rotary table or kelly bushing to
the drillstring, while allowing the drillstring to be lowered or raised during rotation. The
kelly goes through the kelly bushing, which is driven by the rotary table. The kelly
bushing has an inside profile matching the kelly's outside profile (either square or
hexagonal), but with slightly larger dimensions so that the kelly can freely move up and
down inside.
Kelly bushing
An adapter that serves to connect the rotary table to the kelly. The kelly bushing has an
inside diameter profile that matches that of the kelly, usually square or hexagonal. It is
connected to the rotary table by four large steel pins that fit into mating holes in the
rotary table.
Make up
Tighten threaded connections.
Mud
Synonym for drilling fluid.
Neutral point
The point on a string of tubulars at which there are neither tension nor compression
forces present. Below the neutral point, there will be compression forces that build toward
the bottom of the wellbore. Above the neutral point, tensile forces build to a maximum
applied at the hanger or as hook load.
Offset well
An existing wellbore close to a proposed well that provides information for planning the
proposed well.
Pack off
To plug the wellbore around a drillstring. This can happen for a variety of reasons, the
most common being that either the drilling fluid is not properly transporting cuttings and
cavings out of the annulus or portions of the wellbore wall collapse around the drillstring.
When the well packs off, there is a sudden reduction or loss of the ability to circulate, and
high pump pressures follow
Pick up weight
Maximum weight when pulling the string upwards and the complete string is in motion.
Includes string weight and frictional drag.
Pill
Any relatively small quantity of a special blend of drilling fluid to accomplish a specific
task that the regular drilling fluid cannot perform. Examples include high-viscosity pills to
help lift cuttings out of a vertical wellbore, freshwater pills to dissolve encroaching salt
formations, pipe-freeing pills to destroy filter cake and relieve differential sticking forces
and lost circulation material pills to plug a thief zone.
Pipe dope
A specially formulated blend of lubricating grease and fine metallic particles that prevents
thread galling (a particular form of metal-to-metal damage) and seals the roots of
threads. The American Petroleum Institute (API) specifies properties of pipe dope,
including its coefficient of friction. The rig crew applies copious amounts of pipe dope to
the drillpipe tool joints every time a connection is made.
Reverse circulation
The intentional pumping of wellbore fluids down the annulus and back up through the
drillpipe.
Rheology
The science and study of the deformation and flow of matter. The term is also used to
indicate the properties of a given fluid, as in mud rheology. Rheology is an extremely
important property of drilling muds, drill-in fluids, workover and completion fluids,
cements and specialty fluids and pills. Mud rheology is measured on a continual basis
while drilling and adjusted with additives or dilution to meet the needs of the operation.
In water-base fluids, water quality plays an important role in how additives perform.
Temperature affects behavior and interactions of the water, clay, polymers and solids in a
mud. Downhole pressure must be taken into account in evaluating the rheology of oil
muds.
Round trip
The complete operation of removing the drillstring from the wellbore and running it back
in the hole.
Running tool
A generic name for a tool or device that is used in the placement or setting of downhole
equipment such as permanent packers or plugs. The running tool can be retrieved after
the operation or setting process.
Saver sub
A short length of drill collar that has male threads on one end and female on the other. It
is screwed onto the bottom of the kelly or topdrive and onto the rest of the drillstring.
When the hole must be deepened, and pipe added to the drillstring, the threads are
unscrewed between the saver sub and the rest of the drillstring, as opposed to between
the kelly or topdrive and the saver sub. This means that the connection between the kelly
or topdrive and the saver sub rarely is used, and suffers minimal wear and tear, whereas
the lower connection is used in almost all cases and suffers the most wear and tear. The
saver sub is exchangeable and does not represent a major investment.
Space out
To assemble components to ensure that all critical length dimensions are met, as is
required to ensure that the production tubing can be landed in the wellhead and
production packer with the desired weight distribution.
Spud mud
Mud used to drill a well from surface to a shallow depth.
Squeeze job
The careful application of pump pressure to force a treatment fluid or slurry into a
planned treatment zone.
Stab-in
To guide the end of a pipe into a coupling when making up a connection.
Stand
Two or three single joints of drillpipe or drill collars that remain screwed together during
tripping operations.
Swab
To reduce pressure in a wellbore by moving pipe, wireline tools or rubber-cupped seals up
the wellbore. If the pressure is reduced sufficiently, reservoir fluids may flow into the
wellbore and towards the surface. Swabbing is generally considered harmful in drilling
operations, because it can lead to kicks and wellbore stability problems.
Tally
A list that records the total length of pipe, casing, or tubing that is to be run in a well.
Tell tale
Terminology used to describe a screen that, when packed off by gels, will give a pressure
rise at the surface, thereby telling the tool operator that the gel has reached a certain
location.
Trip out
To remove the drillstring from the wellbore. Synonyms: POOH (Pull out of hole).
Twist-off
Parting or breaking of the drillstring downhole due to fatigue or excessive torque.
Underbalance
The amount of pressure (or force per unit area) exerted on a formation exposed in a
wellbore below the internal fluid pressure of that formation. If sufficient porosity and
permeability exist, formation fluids enter the wellbore.
Abbreviations
AH Along Hole
ALARP As Low As Reasonably Possible
API American Petroleum Institute
BHA Bottom Hole Assembly
BHP Bottom Hole Pressure
BOP Blow Out Preventer
BOSIET Basic Offshore Satey Induction and Emergency Training
B/U Bottoms-Up
CR Clearance Ratio
DC Drill Collar
DD Directional Driller
DDR Daily Drilling Report
DLS Dogleg Severity
DP Drill Pipe
DSV Drilling Supervisor
ECD Equivalent Circulating Density
EOWR End Of Well Report
ERD Extended Reach Drilling
FIT Formation Integrity Test
HC Hydro Carbons
HCR High Closing Ratio
HWDP Heavy Weight Drill Pipe
IADC International Association of Drilling Contractors
ID Inner Diameter
MU Make Up
MW Mud Weight
MWD Measure While Drilling
NRV None Return Valve
LCM Lost Circulation Material
LOT Leak Off Test
OD Outer Diameter
OH Open Hole
PDC Poly Diamond Crystalline
PDM Positive Displacement Motor (mud motor)
POOH Pull Out Of Hole
RD Rig Down
RIH Run In Hole
RKB Rotary Kelly Bushing
ROP Rate Of Progress
RPM Rotations Per Minute
RSS Rotary Steerable System
RU Rig Up
RIH Run In Hole
SF Safety Factor
Spec Specifications
SIMOPS Simultaneous Operations
SPM Strokes Per Minute
TD Total Depth
TVD True Vertical Depth
UBHO Universal Bottom Hole Orientation
WOB Weight On Bit
WOC Wait On Cement
WSDE Well Site Drilling Engineer
XO Cross Over
Prepared by WEP
Author:
Verified:
2
HSE programme
For drilling operations, the specific safety related requirements shall be stipulated in the
yearly revised HSE programme. Any deviation from the policy requirements shall be
identified and does require management approval for acceptance.
Process safety
Process safety is important topic for our operations. It is about management of Major
Accidents Hazards (MAH) and prevention of such incidents like well control events leading
to blow-outs, subsequent explosions, fires, collapsing structures, significant
environmental and surrounding impacts. We have to ensure that all our Major Risks are
known, assessed, recorded and controlled to As Low As Reasonably Practicable (ALARP)
Level. Process Safety in wells is also about maintaining Well Control Barriers (for more
see Section 1.4). All drilling MAH risk assessments are reflected and recorded in OMV
Petrom Drilling HSE Case.
Quality
The objective for the Drilling Department is to produce a quality, fit for purpose wellbore,
drilled in accordance with agreed specifications, the standard practices and procedures
and at a competitive cost.
On the rigsite, the Petrom DSV is specifically responsible for the following HSE
matters:
Emergency response:
1. to act, according to the procedures established at the work place, in case of
occurrence of any imminent fire danger or other emergency situation;
2. Provide emergency contingency plans and co-ordination of outside third party
groups such as oil spill response, rig evacuation, etc.
3. DSV has final decision on abandon rig in case of emergency situation. (Acts as
RSES)
1.3 Health
All personnel must strive to prevent all occupational diseases and promote the health of
all employees.
Improvement of occupational health standards shall be implemented in accordance with
the HSE Plan. The required actions which are published in the plan shall be undertaken by
all Petrom, Drilling Contractor and Sub-Contractor personnel.
Specific ways in which improvement of health and hygiene shall be implemented at the
well site are summarised as follows:
Pre-employment and periodic medical checks conducted for all worksite personnel
All rigs must be sound mapped and areas designated for hearing protection.
All Contractors shall provide hearing protection for their personnel.
All rigs shall have a hazardous materials register.
Regular sanitary checks of food and potable water quality
Radioactive sources will be checked regularly, markings verified, and a permit to
work system is mandatory for storing and handling RA sources.
1.4 Safety
To avoid incidents and accidents, and to work safely on the rigsite is the top priority.
Two aspects are to be considered:
1. Occupational safety
2. Process safety
Drilling Process Safety requires any operator undertaking to drill and complete a well, to
take all necessary precautions to keep the well under control at all times., and yet also
includes monitoring, accounting, and communicating the combination of factors which
together indicate probable consequences and thus able to assess the current dynamic
status of risk to make prudent decisions as to operations and also to decide the minimum
qualifications of personnel required to make such operational decisions.
1.5 Environment
All personnel must strive to prevent damage to the environment. Improvements to
environmental protection standards shall be implemented in accordance with Petrom HSE
Plan. The required actions, which are published in the plan, shall be undertaken by the
Drilling Contractor as well as Petrom personnel. Specific ways in which improvement of
environmental protection must be implemented at the well site are summarised as
follows:
Waste Management concept Reduce-Reuse-Recycle applied on site.
Mud/brine/cuttings discharge must be monitored.
All hydrocarbon spills must be reported.
Auditing of domestic, industrial and scheduled waste disposal must be carried
out.
Scrap metal must be segregated.
Paper must be separated from waste.
To preserve smooth function of the system, HSE meetings are divided into different
categories:
Toolbox meeting
Weekly HSE meeting
Workplace safety meeting
Pre-job or Pre-tour meeting
Quarterly HSE-meeting
Annual HSE meeting
Safety Team Meeting
Special meetings (i.e. prior to execution of special operations)
Any time there is a threat to operations or people safety STOP the Work and perform
Time out for Safety (TOFS)
Toolbox meeting
Toolbox meetings are held prior start of operations. The meeting is organised by either
Petrom or the drilling contractor. Service companies involved in the planned operations
are participating. The organising party establishes the minutes of the meeting including
the names of the participants and the subjects discussed. The meetings are documented
by the driller in the DDR.
There shall be clearly labelled storage boxes available for primary explosives
(detonators and igniters) and secondary (charges) explosives.
The Job Supervisor is the only one who is allowed to arm or disarm any tool using
explosives.
If guns are retrieved unfired, they shall be disarmed immediately.
Firefighting equipment is to be operational and placed in appropriate locations on
the rig floor
Radio silence
Radio Silence must be enforced from the time immediately prior to arming
explosives until the tool is 100 meter below ground level. Prior to retrieval of the
tool (whether fired or not) above 100 m below ground, Radio Silence Procedures
shall again be enforced. All radio transmitters within a 500m radius of the well
shall be shut down. This also applies to welding and cathodic protection systems
are shut-down to eliminate possible stray voltages.
1.8.4 Drills
The following drills shall be conducted by the Drilling/Rig Contractor(s)
Emergency Drill Requirements
Drill Frequency Personnel
Kick Drills Weekly All Drill Crews
Stripping Drills After each All Drill Crews
casing
Muster drill Weekly All
Alternative Evacuation Fortnightly All
Fire Fighting Drill Fortnightly Fire Teams
Breathing Apparatus Drill Monthly All Possible Users
Emergency Equipment Drill Monthly All Possible Users
Casualty Handling Drill Monthly Emergency Teams, First Aiders
First Aid Drill Monthly First Aiders
H2S drill Weekly (if All
applicable)
The aim for the kick drills is to measure and improve the well control alertness of the rig
teams. The benchmark for a good kick drill is as follows:
Time to recognize kick (during kick drill) : less than 1 minute
Time to close in well (after recognizing kick) : less than 2 minutes
1.8.5 Audits
At least one technical safety audit shall be carried out by the Company, either just before
or after start-up of the first well to be drilled by the drilling rig.
Rig Acceptance Audits are conducted in accordance with annually approved schedule and
dependent from previous audit scoring:
Less than 80% compliance against rig site check list at the beginning of each
well;
In between 80-90% compliance against rig site check list - once at 3 months;
Over 90% compliance against rig site check list - once at 6 months.
Audit findings with the Auditor and verify the categorization of each finding classified as
the following:
Critical: systems that do not comply with OMV Policy and Standards and the
condition of which presents a risk of major accident. The Subsidiary shall not
accept the unit on contract or commence operations until the Critical non-
conformances are rectified and risk reduced to ALARP levels.
Major or Minor: observations concerning systems that generally comply with
OMV Policy and Standards and present no risk of major accident. This category
may contain items that require to be addressed at the discretion of the OMV
Subsidiary in the interests of operational efficiency.
1.9 Reporting
Good communication is a key factor for optimal performance in a drilling operation. To
facilitate this, the large quantity of data needs to be reported consistently and correctly.
The same applies to raising and tracking actions points.
Reporting and analysis play an important part in a quality management system. Accurate
reporting is a prerequisite for effective analysis which, in turn, lays the foundation for the
feedback loop. The purpose of feedback is two-fold, it must:
It is important that the events are reported as accurately as possible as the information
will be used by the Company for planning and designing future well activities. The main
source of information is from the wellsite with additional analysis being performed in the
office. The information data base is an important company asset which must be complete
and contain good quality and accurate information.
Reports should be kept concise while conveying essential information. Reporting between
the well site and the Petrom office is the responsibility of the DSV.
All routine reports submitted by the rig to the drilling department shall use standard
formats approved by Petrom and be submitted daily.
Reporting should be build up per hole section, the same applies for cost overviews.
To be clear when a hole phase is finished and the next starts to following rule is drawn:
The next hole phase commences from the moment the next diameter drill-bit
deepens the hole from the previous bit-size or cellar floor. From geological TD of
whole well the next phase commences from rig-down of logging"
For example:
Situation as follows: the previous 12 hole final bit depth at 1000 meters, casing shoe
at 998 meters. Float collar at 978 meters, cemented to surface successfully.
The time / costs related to make up 8 assembly, RIH, drill shoe track, pressure test
casing, drill out rat hole and perform FIT go to 12 - 9 5/8 phase-section.
The moment the rotating bit takes weight at 1000+mts all reporting, costs KPI's etc go to
8 1/2" phase.
Possible exception: previous mud displaced must be credited to the previous hole
section/phase and new displacement mud should be credited to the new hole
section/phase.
prior to the commencement of drilling activities and at all times the drilling activities are
in progress. The DSV shall ensure that the following requirements are met prior to
commencement of drilling activities and at all times activities are in progress.
Chairman driller
Participants all crew members and contractor staff
Project :
Date meeting : Start : hr
Rig : Finish : hr
Meeting HSE-meeting
Character of the meeting During this meeting the risks and the defined safety measures
concerning HSE will be discussed and evaluated.
Agenda 1. Opening
2. Go through the minutes/actions of previous HSE-meeting.
3. Risk Inventory & Evaluation
4. Task-risk Analysis
5. Safety measures
6. Other subjects (additional current subjects)
7. Questions before closure of the meeting
8. Closure
Chairman Manager
Minutes Yes, by the QHSE-manager
Present Rig/ Operations Manager QHSE-manager
Drilling Supervisor Participants
Toolpusher
Driller
Mechanic
Electrician
Remarks:
Drillstring: 19
Type Size [in] Length [m] Weight [kg/m] Grade Tooljt. OD [in] Tooljt. ID [in] Connection Hardbanding Coating Last Insp.
Sonic Vision
ARC
AND
Hydraulics: 21
Pump Motor Bit Annular Velocities
Press. [bar] Flowrate [l/s] p mot [bar] his Jet vel [m/sec] HHP [% ] DP [m/min] DC [m/min] DC crit. [m/min]
Offshore data: 24
This instruction is a proactive approach and a proven successful tool to directly prevent
incidents. Multiple approaches have been taken in the past to name, define and set up
JSAs.
PETROM defines the JSA as its procedure to perform effective on-the-job risk
evaluation and protection.
This chapter explains the required Job Safety Analysis (JSA) for drilling and work-over
operations. It is applicable to any non-routine job and any job identified as containing
potential hazard(s). Any job must be performed under PTW system.
It is also recommended, if the planned routine workplan has been changed (management
of change: MOC). The performing authority (PA) for the JSA is the supervisor responsible
for the execution of the work scope. He assembles all personnel appointed to the work for
a joint "step-by-step" work plan discussion and risk analysis before the job will be started.
Subcontractors to PETROM shall be included.
STEP 2. Explain the main job, which is planned Work site supervisor
STEP 3. Describe every single step ("Step-by-step") All involved persons
to execute the work, (begin description
with an active verb, such as disconnect,
check, assemble, etc.), (number each step)
STEP 4. Identify the hazards associated with each All involved persons
single job, (consider accident causes such
as strain, sprain, cut, slip, fall), (consider
environmental hazards)
STEP 5. Decide on actions necessary to eliminate, All involved persons; superseded
reduce or control potential hazards, by work supervisor, if in doubt.
(Recommended safety measures)
Reduction of accidents
Generation of safety initiatives
Supports continuous improvement in productivity and quality
Building of teams at work
Shows that each team member is important
Increase of job satisfaction
Everyone recognizes the job expert
Creates an individual database on site for further use for job planning
A JSA procedure is required to comply with health protection legislation and mining law.
Column 3 of the JSA "Recommended safety measures" list can be used by management
as an HSE Audit Checklist.
Frequency of Job (note: less frequent jobs normally are more critical)
Injury potential of job
Non-routine job preparation
Deviation from common working procedure (MOC)*
The supervisor is doing the completion of the JSA form and he files it in the JSA register
on site for further reference. In the header of the form it is possible to indicate, if the
form is done for a new work or done to revise an existing work plan and its JSA.
Signature:
Prepared by WEP
Author:
Verified:
2
Wellhead integrity shall be assumed to be maintained when the following elements are
achieved:
All valves are capable of being opened and closed.
All valves shall be leak-tight when closed.
All adjustable choke valves shall be operable within their design limits.
All clamps and bolts of BOP stack/wellhead components shall be tightly secured.
system are capable of withstanding the full hydraulic pressure required to shear
pipe.
The BOP closing equipment shall be tested two weekly and its performance
checked for closure time of the preventers and remote controlled valves,
accumululator recharging time and volume pumped.
All function tests must fall within API standards for closing of each element of the
BOPs. For example, closing time for 13 5/8 BOPs and smaller is 30 seconds, for
larger BOPs this is 45 seconds. Recharge time of the accumulator unit needs to be
less than 5 minutes.
In freezing conditions, the BOP control system should be properly prepared with
anti-freeze. Choke and kill lines will be displaced with anti-freeze fluid.
Each and every valve and BOP shall be pressure tested from direction of flow from
the wellbore according to:
Note:
1. A complete inspection (NDT for all critical parts, function and pressure tests) will
be performed by a third party Company in their work-shop. This inspection will be
applied to all components of BOP stack after every 5 year working.
2. As per API RP 53 - the components which can be subjected to pressure have to be
tested on location. The first test is an initial pressure test of high pressure. The
following tests are called Next pressure tests
3. Next pressure tests could be done at the maximum anticipated surface pressure
that may exist in the well (but limited by maximum working pressure of BOP
stack).
All pressure tests must follow API standards for closing of each element of the BOPs.
In freezing conditions, the BOP control system should be properly prepared with anti-
freeze liquid as per API RP 53 recommendations. Choke and kill lines will be displaced
with anti-freeze fluid.
Each and every valve and BOP shall be pressure tested from the direction of flow from the
wellbore in line with details below.
o Ensure pipe has been removed from BOP before operating blind/shear
rams.
Close and open all manual valves.
o Visually check that the correct function has occurred
At the end of the function test the result should be reported and recorded on daily tour
sheets and the Blowout Prevention Equipment Checklist.
The preparations to perform the function test in operating mode without pipe in hole
are:
Perform flow check to check and ensure that the hole is full and static
Conduct function test on all kelly cocks. Including manual lower kelly cock and Upper and
Lower IBOP on top drive system
At the end of the function test the result should be reported and recorded on daily tour
sheets and the Blowout Prevention Equipment Checklist.
To start shut down all chargers, electric as well as the air supply, connected to the
accumulator.
Operate all BOP functions once and record the closing time and remaining accumulator
pressure after every BOP functioning.
Close annular
Close all ram BOPs (except Blind / Shear rams)
o Do not operate shear / blind rams with joint in the BOP stack.
Open one ram BOP
o To simulate the closing of the Blind / Shear rams
Open HCR Valve
Operate all BOP functions a second time and record closing time and pressures
Open annular
Close one ram BOPs
o To simulate the opening of the Blind / Shear rams
Operate all BOP functions third time and record closing time and pressures
Close annular
Close all ram BOPs (except Blind / Shear rams)
o Do not operate shear / blind rams with joint in the BOP stack.
Open one ram BOP
o To simulate the closing of the Blind / Shear rams
Open HCR Valve
Then record the final remaining pressure on the accumulator. This shall be greater than
the minimum pre-charge pressure plus 200 psi. (Acceptable pre-charge pressure range as
per API RP53 recommendations)
Continue by switching on all chargers and record the time required to build up
accumulator pressure back to full working pressure. If longer than 15 minutes is required,
check for the following possible problems:
Low pre-charge on one or more accumulator units
Internal leak in the system
Pump(s) not functioning at full efficiency
Rectify faults and repeat test until unit is functioning at full efficiency.
Cycle the annular preventer and check that the pumps will automatically start when the
closing unit pressure has decreased to less than 90% of the accumulator operating
pressure. This should be checked with only the electric pumps operative.
Should an emergency control system be employed, this should also be tested at the same
time as the accumulator unit.
At the end of the function test the result should be reported and recorded on daily tour
sheets and the Blowout Prevention Equipment Checklist.
The total accumulator volume required can be calculated using Boyles Law:
P1 x V1 = P2 x V2 = P3 x V3 (assuming an isothermal expansion)
and, by definition VR = V2 - V1
Thus, VR = ( P3 x V3 / P2 ) - ( P3 x V3 / P1 ) = V3 ( P3 / P2 ) - ( P3 / P1 )
According to Petrom Drilling Standards (September 2008), number of Koomey bottles has
to be according to API.
API RP53:
1. Close all BOPs (no closed in wellhead pressure) and have 50% remaining pressure
in bottles available for reserve.
2. The pressure of the remaining stored accumulator volume after closing of all BOPs
must exceed the minimum calculated (using BOP closing ratio) operating pressure
required to close any ram (excluding shear ram) at the maximum rated wellbore
pressure of the BOP stack.
Examples of API RP53 calculations for both scenarios are given below.
The BOP control system should have a minimum stored hydraulic fluid volume, with pumps inoperative, to satisfy the greater of the following two requirements:
1) Close from a full open position at zero wellbore pressure, all of the BOP's in the BOP stack, plus 50% reserve.
2) The pressure of the remaining stored accumulator volume after closing all off the BOP's should exceed the minimum calculated (using the BOP closing ratio) operating
pressure required to close any ram BOP (excluding the shear rams) at the maximum rated wellbore pressure of the stack.
Example Stack
13 3/8" 10 K
Close Open
1 Annular 17.90 USG 14.20 USG
1 Upper Ram 5.80 USG 5.50 USG
1 Blind Shear Ram 10.90 USG 10.50 USG
The BOP control system should have a minimum stored hydraulic fluid volume, with pumps inoperative, to satisfy the greater of the following two requirements:
1) Close from a full open position at zero wellbore pressure, all of the BOP's in the BOP stack, plus 50% reserve.
2) The pressure of the remaining stored accumulator volume after closing all off the BOP's should exceed the minimum calculated (using the BOP closing ratio) operating
pressure required to close any ram BOP (excluding the shear rams) at the maximum rated wellbore pressure of the stack.
Example Stack
13 3/8" 10 K
Close Open
1 Annular 17.90 USG 14.20 USG
1 Upper Ram 5.80 USG 5.50 USG
1 Blind Shear Ram 10.90 USG 10.50 USG
Prepared by WEP
Author:
Verified:
2
Conductor shoe ID is usually smaller than conductor joint; ensure bit cannot get stuck in
shoe joint.
3. Sweep hole with 10 m3 of HiVis pill and circulate clean with water or mud.
4. Drop Gyro to UBHO sub.
5. POOH and rack back clean out assembly.
6. Retrieve Gyro from UBHO sub or TOTCO ring.
Note: Based on conductor hammering report, if there is not risk of collapse of the shoe /
conductor, the cleanout of conductor will be performed with the BHA planned to be used
for drilling the section below the conductor shoe.
A key parameter dealing with shallow gas is the small tolerances between formation
pressure overbalance with the fracture gradient. Due to low overbalance margins,
relatively moderate amounts of swabbing or drilled gas can easily reduce the overbalance
and thus initiate gas flows that result in a blowout.
Main principle: a shallow gas kick shall never be shut-in but always diverted. By pumping
mud at a high rate, the well is dynamically killed prior to displacing the well to kill mud.
When suspecting shallow gas, drill a pilot hole (8 1/2 or smaller). The smaller hole size is
easier to keep full and to achieve a dynamic overbalance while circulating gas out.
A surface diverter is used to divert shallow gas before the installation of a BOP. The flow
diverter has to be installed on the conductor when drilling:
1. All exploration and appraisal wells, if they are placed too far away from known
structures and not enough data is available in order to estimate presence / absence
of shallow gas.
2. The first well on a production platform/jacket
3. All consecutive wells on a platform/jacket, if presence of shallow gas is established
Diverter systems should comply with API RP 64 (Diverter Systems Equipment and
Operations).
An emergency procedure shall be put in place in the event of any shallow gas kick
or blowout, detailing positions of key staff, which diverter side to open depending
on wind direction, emergency evacuation.
Windsocks shall be visible from all points.
Consider to hold an emergency evacuation drill to familiarize personnel with their
duties.
Radios shall be placed on the drill floor and shall be fully charged at all times. A
summary of radio channels in use shall be detailed during the safety meeting.
Confirm that all required rig equipment is available and in good working condition
e.g. test all gas detectors and alarms, diverter & Koomey unit, ensure that the
valves are full opening. Before drilling begins, function test and flush diverter
system.
Ensure the diverter bag is large enough to accommodate the running of casing.
Ensure that the diverter has 2 outlets positioned 180 apart that are large enough
diameter, i.e. 10 or larger for land rigs, and is long enough to divert any fluids or
gas away from the rig.
Ascertain that all lines are straight and unrestricted, 90 bends are to be avoided.
Diverter lines are to be securely anchored, especially at bends and at end of lines.
Consider a premix mud for safety; refer to the Drilling Program. Prepare sufficient
tanks of kill mud for 2x hole volume, A minimum 200m per hour water and kill
mud supply shall be available.
Diverter control system should be capable of operating diverter from two locations.
One should be at the drillers console.
A solid, non-ported float valve shall be installed in the drillstring, as close as
possible or above the motor if a dump valve is installed.
3.2.3 Best practices for shallow gas, pilot hole and surface diverter
Automatic sequenced operation is always preferable to manual operation.
Pilot hole shall be drilled with the 8 or smaller bit size. The BHA design shall
include a solid, non-ported float valve and considerations given to deviation and
subsequent hole opening.
The pilot hole shall be logged for hydrocarbons. Only after the absence of
hydrocarbons has been proven may subsequent wells omit drilling a pilot hole.
The ROP shall be controlled to avoid overloading the annulus with cuttings.
Overbalance could be lost by inducing losses or excessive gas from drilled cuttings.
The drill string should be pumped out of the open hole, unless the absence of
hydrocarbons has been proven.
To avoid swabbing the tripping rate should be adjusted to ensure the pumped
volume is a minimum of 120% of the hole capacity of the pulled pipe length.
All losses shall be cured prior to drilling ahead.
Pump pressure shall be closely monitored and all connections shall be flow
checked.
3. Check wind direction, open diverter valves, close valve to shaker and close Annular /
Diverter.
4. Essential personnel shall proceed to assigned duties. Non-essential personnel shall go
to muster points and wait for further instructions.
5. Switch suction on mud pumps to heavy mud in the reserve pit. Zero the stroke
counter.
6. Pump twice hole volume of kill mud at the highest possible rate, then stop pumps and
observe returns.
7. Whilst pumping kill mud, continue appraising the severity of gas influx.
8. If gas is still flowing, continue to pump kill mud at the highest possible rate. Consider
preparing a pit with heavier mud. Do not stop pumping for as long as the well
continues to flow. If running out of mud, pump water at the highest possible rate.
9. If gas content of the mud decreases, open the diverter and take returns to the
mudpits. Continue circulating until bottoms up and observe gas readings. If not
decreasing, increase mud weight slowly and in stages until gas levels are back to
background level. Flowcheck.
10. When well is stable, conduct a wipertrip. From here onwards, pump out of hole.
Start
Location Survey
Drill or drive conductor/
Indicates Risk of Shallow No (No Residual Risk)
stove pipe
Gas.
Flow
No
Diminishes
No
Yes
Yes
Yes
Open diverter circulate returns
to mud tanks
Shut down and abandon
Installation.
Yes
Yes
The hole will have been circulated clean, so it should be possible to trip the motor
BHA in the elevators.
Maximum overpull 15 mT. When exceeding, run down 2 stands, circ hour, check
tight spot, and repeat circulate clean if overpulls indicate cuttings beds.
Monitor P/U hookload against the modelled curve while tripping, and record every
5 stands. Also record S/O hookload rotating string weight every 10 stands (for
friction factor back calculation).
Consider check trip if hole dictates.
1. Drill ahead Tophole section to section TD dependent on casing tally plus 3-5 m
rathole.
2. Circulate the hole clean, following the hole cleaning and tripping best practices.
3. POOH, using tripping best practices.
4. Break out the bit. Download MWD (when applicable). Stand back BHA.
5. M/U wearbushing running tool. Run in and retrieve wearbushing as per wellhead
manual report hang off depth. Jet the wellhead.
6. Prepare for next operations: Running casing and cementing.
General Properties
Density 1.05 1.10 sg
MK 80 100 sec
PV + 20
YP 20 -30
Fluid loss + 30 ml API
pH 9 10
In case water is used as a drilling fluid when drilling top hole, often returns are not
sufficient for proper hole cleaning. In this case slugs of rehydrated bentonite with Marsh
Funnel viscosities between 100 and 120 sec must be circulated occasionally for hole
cleaning.
3.4 Anti-collision
In particular during tophole drilling, anti-collision can become an issue due to the close
proximity of neighbouring wells.
During the well planning process, the Directional Drilling Contractor shall provide a
calculation of clearance ratio to all potential collision risk wells: all wells at 100 m
or less from each other or less at any position of their planned well path.
Inclination Accuracy
Azimuth Accuracy 0-2 degrees Not applicable
2-6 degrees 6 degrees
6-12 degrees 3 degrees
> 12 degrees 2 degrees
Inclination Accuracy 0.4 degrees at any hole inclination
When doubt exists as to the accuracy of magnetic based survey information, these
must be checked with a gyro based tool before drilling ahead.
Proximity calculations and projections shall be performed at regular intervals, the
interval depending on the collision risk. A minimum frequency of twice daily is
mandatory, however when drilling within a clearance ratio of less than 1.5, the
frequency shall be increased to every joint drilled.
The following precautions shall be taken when the clearance ratio falls below 2.0 with a
well with natural flow:
Clearance Actions
Ratio
The clearance ratio, for each collision risk well, projected 60m ahead of
the bit shall be calculated at every survey station or every stand drilled.
< 2 .0
The clearance ratio shall be reviewed by the Drilling Manger prior to
drilling ahead
A constant surveillance of wellhead and casing pressures shall be
<1 .5
maintained.
The existing well shall be closed in and de-pressurized from a depth
<1 .25 greater than the deepest potential collision depth by either wireline
plugs or the sub-surface safety valve.
Drilling shall stop and shall only be recommenced if the well bores are
1.0
diverging otherwise the well shall be plugged back.
The last survey station shall be calculated, plotted and agreed by the Directional
Driller, the DSV and the Drilling Engineer.
The last survey station shall be extrapolated along hole depth corresponding to the
bit position after drilling next single.
A position uncertainty ellipsoid shall be plotted around the extrapolated bit
position.
A check shall be made that this ellipsoid does not overlap the ellipsoid(s) of
uncertainty for the neighbouring well(s)
A clearance ratio shall be calculated.
In the event that a proximity scan reveals a clearance ratio of less than 1.5, the Drilling
Engineer shall order drilling to cease and shall enact the following:
Notify the Senior Drilling Engineer and request suspension of the appropriate
collision risk well(s).
Review corrective actions required in consultation with the Directional Drilling
Engineer, Toolpusher and the Drilling Engineer.
Drilling shall only be resumed when all of the above actions have been performed
and written verification of completion of collision risk well shut in(s) have been
received.
A proximity calculation and projection to all collision risk wells shall be performed
at each survey station before drilling ahead is recommenced. The survey shall be
reported to Drilling Engineer (and directional contractors office) for immediate
back up calculation and confirmation.
In case of discrepancies, the rig shall be contacted by the Drilling Engineer (or
directional driller) to resolve the discrepancy at the earliest opportunity. If the
discrepancy cannot be resolved, the Drilling Manager shall be notified immediately.
Returns shall be monitored regularly for the presence of cement.
The annuli on the collision risk well shall be pressured and monitored regularly for
sudden pressure changes. Where available, the alarm facility shall be set and
monitored accordingly.
The drilling operation shall be conducted at a reduced ROP to minimise the
potential for damage should a collision occur. The Driller and Directional Driller
shall constantly monitor drilling parameters for any sudden changes in ROP,
drilling torque or other irregularities. If detected, drilling shall be immediately
ceased and the irregularity investigated before drilling is recommenced.
In the event the proximity scan reveals an overlap of ellipsoids (a CR of less than 1), the
following shall be enacted:
When the CR to any collision risk well is projected to be less than 1.0, the Rig
Superintendent shall be informed and drilling operations shall cease immediately.
A plan of action shall be formulated after considering the following options:
o Re-survey the current well with a more accurate survey tool to reduce the
radius of uncertainty and increase the projected CR to an acceptable level.
o If unable to increase the CR to an acceptable level, plug the well and side
track at a depth where the well can be safely re drilled.
Operations shall be resumed after the proposed corrective actions have received
documented management approval.
The survey program shall ensure that the following requirements are met:
Avoidance of collision with other wells.
To provide accurate well path information for correlation of geological, geophysical
and electric logging data parameters between wells.
To accurately locate the well path in the event that a relief well is required.
To identify doglegs which may affect casing or completion plans.
To accurately determine wellbore position versus the planned well trajectory.
3Ddist
SF =
3Ddist IBseparation
Where:
3Ddist =3D centre to centre well distance
IB separation =the inter-boundary distance between the envelopes of the borehole
position uncertainty
Collision avoidance
The following criteria are used in the analysis of well-bore proximity and form the basis of
the decision making processes and policies defined by the company to ensure
maintenance of safe operations whilst drilling in proximity to existing wells. The vertical
section view below illustrates graphically the definitions.
Clearance Ratio:
The Clearance ratio uses the minimum distance between the ellipse of uncertainty of the
two wells at the requested depth. The Clearance Ratio is (CR) defined as:
Clearance Distance:
The Clearance Distance is the distance in meters between the ellipse radius of uncertainty
of the planned well (Er) and the existing collision risk well (Eo) along the line of closest
approach.
4 Well control
Prepared by WEP
Author:
Verified:
2
4 Well control
All well control principles rely upon an understanding that good planning and early
recognition and the well closed in, is the best form of Well Control. Not all kicks are
swabbed kicks; many wells are drilled into unknown formations.
1. Primary Well Control: Involves the use of fluids of sufficient quantity and density to
maintain an overbalanced hydrostatic head in the wellbore, thus preventing influx
of formation effluents. The programmed mud gradients shall exceed the expected
pore pressure gradient of the exposed permeable formations by a trip margin as
specified in the PETROM Drilling Standards.
2. Secondary Well Control: Is the proper application of suitable and approved surface
blowout prevention equipment to control the well in the event that primary well
control is lost or cannot be maintained.
Conventional well killing procedures are based on the assumption that all of the well
control equipment operates as designed and the wellbore is able to withstand the imposed
pressures. However problems can arise due to other factors such as mechanical problems
and formation fracturing.
Ensure that all Kick drills are performed in accordance with PETROM Drilling
Standards. These are:
o Weekly kick and trip drills to confirm readiness of rig crew response to
alarms
o Well shall be shut-in prior to drilling out casing and circulated through BOP
to familiarize rig crew on proper circulating techniques
Note: Before this operation is mandatory to clean the drilling fluid from any debris,
cement hard or soft (could block choke manifold line and poor boy) circulate a
volume bottom/up before close BOP.
o The drills shall include the full sequence of shutting in a well.
o Stripping drills are also recommended where appropriate.
o Out-of-hole drills may be conducted at any time when out of hole with no
tools or wireline through the BOP stack.
Ensure that the well control equipment is tested and in fully functional condition.
Before drilling out casing shoe, a Kill Sheet needs to be completed and then
updated every 150m or at least once per shift.
Obtain slow circulation rates (SCR) when drilling ahead. Take new SCRs every
shift, for every new BHA, when mud properties (mud weight) have changed and
after change out of pump liners.
A solid (non-ported) float valve shall be installed in the drill string at all times. This
helps to prevent back flow into the drill string during tripping or making
connection.
A full bore Kelly cock shall be installed at the base of the Kelly or top drive.
It is mandatory to have FOSV and Gray valve on rig floor and ready to be picked
up and installed on the string.
Formation Integrity Tests (FIT) shall be performed, refer to Chapter FIT. The
Maximum Allowable Annular Surface Pressure (MAASP) shall then be calculated
using the fluid density used for drilling below the shoe.
A pre-spud checklist related to well control shall be filled in and signed by the PETROM
Drilling Supervisor.
DSV TP
Item Comments
Initial Initial
BOP function /pressure test successfully completed,
including all rams and body
Wellhead SOVs and connection to BOP successfully
tested
Accumulator test successfully completed according to
including control hoses (date of last full working
pressure test)
Kelly cocks and Gray valves successfully tested from
below
Kelly cocks and Gray valves on rig floor, including all
crossovers for other connections
Top drive, successfully tested from below
Standpipe manifold and kill lines successfully tested
Choke manifold and choke lines successfully tested
Cementing manifold and lines successfully tested
Automatic choke panel function tested
BOP stack up configuration covering all pipe sizes
planned to be run in hole
Ram space out to allow landing off drill pipe and
shearing above tool joint
Kick detection equipment and alarms such as flow
meters, level indicators and associated gauges,
alarms, recorders and controls working correctly
BA sets charged and ready for use in dedicated
locations
All well control equipment used from original
equipment manufacturer
All well control equipment within certification and
inspection frequency
Sufficient chemicals and weighting materials available
on site (offshore rigs) to increase the fluid gradient of
the active system to the maximum expected kill
gradient
Signed and agreed: Signed and agreed:
DSV TP
Item Comments
Initial Initial
Strip drill performed /planned dates (including all
crews)
Trip drill performed /planned dates (including all
crews)
Pit drill performed /planned dates (including all crews)
Confirmed latest valid copy of Drilling Programme
available and used by all on site
Basis of required fluid gradient in programme
reviewed and agreed
Fluid gradient in line with specifications in programme,
including correct overbalance to highest planned
pressures and risk assessed and plans in place for
encountering highest anticipated formation pressures
Kill methods and scenarios discussed and agreed
(including Drillers and Assistant Drillers)
MAASP protection on automatic choke disabled
Close-in and choke manifold set-up (hard shut-in)
agreed and displayed
What-if scenarios in relation to well control discussed
with all parties, agreed and documented
Structure of command and roles and responsibilities
agreed and in line with HSE Cases and Company and
Contractor requirements
Any discrepancies identified in structure of command
and roles and responsibilities? Are these documented
and agreed with Rig Manager and PETROM Drilling
Supervisor?
All critical staff comply with minimum well control
training and competency requirements
HSE Cases reviewed for HSE Critical Activities and
Positions
Communications equipment checked and in good
working order
Emergency Response Procedures available and
understood by all
CPRA Procedures available and understood by all
Any specific conditions or procedures (HPHT, UBD,
Bullheading,) considered and understood. Do they
impact well control response?
Signed and agreed: Signed and agreed:
1. Kick alarm
2. Stop rotary
3. Position drill string
4. Stop pumps
5. Close pipe rams or annular
6. Open HCR
7. Ensure well is closed in
Visually check rams/annular is closed
Ensure flow has stopped
Close ram lock
Circulate over trip tank, above closed preventer
8. Monitor and record data
9. Record time to perform drill
1. Kick alarm
2. Position drill string
3. Install FOSV
4. Close FOSV
5. Close pipe rams or annular
6. Open HCR
7. Ensure well is closed in
Visually check rams/annular is closed
Ensure flow has stopped
Close ram lock
Circulate over trip tank, above closed preventer
8. Connect TDS
9. Open FOSV and iBOP
10. Monitor and record data
11. Record time to perform drill
1. Kick alarm
2. Close blind/shear rams
3. Open HCR
4. Ensure well is closed in
Visually check rams are closed
All require immediate action: flow check to detect if it is kick; any indication of a kick in
progress, shut in well & observe pressures.
# Warning Remarks
Signs
Increase in Pit This is the definitive indicator of a kick. When pit volume alarm
1
Volume goes off: shut well in !
This is often the first positive indicator that a kick is occurring,
Increase in
2 however an influx from a low permeability formation may be
Relative Flow
difficult to identify.
Incorrect Hole
3 If this happens, the formation fluids may be entering the wellbore.
Fill
An increase in mud gas level may signify that formation gas has
flowed into the well which could lead to an undesirable reduction in
4 Gas Cut Mud
mud weight. Gas readings will significantly deviate from
background level.
Reduced Mud Mud weight reduction (or any significant change in other mud
5
Weight properties) may indicate a dilution of the mud by formation fluids.
A drilling break is due to a change in formation drilling
characteristics, and may indicate increases in formation porosity,
6 Drilling Break
permeability and pore pressure. Breaks may be positive or
negative.
A large influx of formation fluids reduces the hydrostatic pressure
in the annulus. The mud in the drill string can then U-tube into the
Decrease in
annulus and the result is a reduction in pump load and pressure.
7 Pump
The pressure reduction can cause the pumps to speed up.
Pressure
Normally if this indicator is seen, a serious kick has occurred and
other indicators should be associated with it.
1. Stop rotary
2. Position drill string to ensure no tool joint is opposite the pipe ram
3. Stop the pump(s)
4. Close the pipe ram
5. Open HCR (the remotely operated choke line valve)
6. Inform Drilling Supervisor, Toolpusher and crew members.
7. Ensure well is closed in
Visually check rams/annular is closed
Ensure flow has stopped
Close ram lock
Circulate over trip tank, above closed preventer
8. Record the casing and drill pipe pressures and the pit gain.
Note: In the case of high pressure wells, where the expected surface pressures during the
well kill exceed the normal circulation system rating, a designated kill assembly should be
used. The kill assembly consists of a high pressure pump, manifold and connection that
are rated to sufficient pressure. To install: close the lower kelly cock or top drive internal
BOP, break the Kelly or topdrive connection to the drillstring, install and test the kill
assembly, pressure up to the closed-in drill pipe pressure and open the kelly cock or top
drive internal BOP.
1. Drillers method. With the Drillers method, the influx is first circulated out with the
original drilling mud while applying backpressure on the well and thereafter
increasing the mud weight to restore the minimum overbalance. The main
advantages of this method are that circulating out the influx can be started
immediately, the influx is removed soonest and only a minimum of information is
required prior to start of circulation. The disadvantages are (i) that higher annular
pressures result and (ii) the well is longer under pressure.
2. Wait-and-weight method. With the Wait-and weight method a kill mud of the
correct density is prepared prior to circulating out the influx under reducing
backpressure at the choke. The main advantages of this method are lower wellbore
pressures and a minimum on-choke circulating time. The disadvantages are (i)
that there is considerable waiting time to observe the well and weight up the mud,
allowing migration of the influx and (ii) lack of uniformity in mud weight if a major
increase is required.
3. Concurrent (circulate and weight) method. With the Concurrent method, the influx
is circulated out, with mud that is being weighed up in stages. It is in fact a
combination of the previous two methods, Drillers and Wait-and-weight. The main
advantages of the Concurrent method are that circulating out the influx can be
started immediately and it will create lower annular pressures than the Drillers
method. The disadvantages are (i) that at any one time the wellbore will have
zones of different weights of mud being circulated, making the calculations for
choke pressures more difficult and (ii) increasing the possibility of mistakes during
an already stressful / difficult situation.
Concurrent (circulate and weight) method when bit is on / near bottom, a lower
wellbore/shoe pressure is required, but mud with kill weight cannot be mixed in
one go and circulation is possible.
Volumetric method when gas is percolating up the well, circulation or stripping in
is not possible.
Stripping in when insufficient pipe in hole after shut-in and circulation is possible.
Volumetric Stripping when insufficient pipe in hole after shut-in, gas percolating
up the well will increase the pressures to above the limit and circulation is possible.
Bullheading when an influx will exert too high casing and surface pressures if
circulated out or in case of poisonous substances e.g. H2S in the influx and
circulation is possible.
Selection of kill pump and pressure rating (setting of pressure relief valves
(PRV)).
5. Installation of a non-return valve (NRV) in high pressure line to prevent an influx
trough the drill string if no sub-surface NRV is installed
Before any circulation can be started the poor boy degasser should be lined up to deal
with the influx once it reaches surface. While circulating, the expansion of the gas will
lead to an increase in surface volume. Until the gas reaches surface, more mud will
coming out of the well than is being pumped in. One must ensure enough storage volume
is available to deal with this. At the same time heavier kill mud will have to be available,
needing a separate tank as well. Confirm that exposed formations and casing can support
the higher pressures.
The pressure required on the drill pipe for start of circulation of the well can be calculated
with the following formula:
= +
= [] []
= [] []
= [] []
The next step is to prepare the kill mud needed to regain overbalance in the wellbore.
For the Drillers method the kill mud is only needed during the second circulation, for the
concurrent method the mud weight will increase throughout the kill operation, reaching
the kill mud density at some point and for the wait-and-weight method the circulation will
only start once the kill mud is ready.
In any case the kill mud density will have to be calculated and the mud engineer will have
to prepare and start to mix kill mud to the required volume and properties. The kill mud
density can be calculated with the following formula.
For SI units:
= +
0.0981
= [/]
= [/]
= []
= []
= +
0.052
:
= []
= []
= []
= []
At the start of the first circulation the pump stroke counter will be set to zero, in order to
keep track of how much mud has been pumped down the drill pipe. The pump will be
started slowly, while at the same time the choke will be opened slowly. While bringing the
pump up to kill speed (SCR), the choke should be adjusted so that choke pressure will
equal SICP. With the pump up to kill speed the pressure read at the drill pipe side should
be equal to ICP. In case of a big difference between calculated and recorded ICP, the
reason for this should be investigated. Once kill rate has been achieved the choke
operator will now adjust the choke to keep the drill pipe pressure equal to ICP. Continue
to circulate at kill speed, until all of the kick fluid has been circulated out, while adjusting
the choke as to keep drill pipe pressure at ICP. The annular pressure will rise as the influx
rises. The highest annular pressure will be once the influx reaches surface. If the amount
of gas coming out of the well is too much for the poor boy degasser to handle, it might be
necessary to lower the kill speed. When doing this, the new SCR pressure will need to be
calculated and the difference between old and new SCR pressure will have to be deducted
from the ICP to determine the new ICP to which the drill pipe pressure will be held by
operating the choke.
The formula for the new SCR pressure is:
2
=
= [] []
= [] []
= [/]
= [/]
After the influx has been circulated out the well will be shut in again by shutting down the
pump slowly and closing the choke simultaneously. Monitor the SIDPP and SICP. SIDPP
after first circulation should be equal to the SIDPP before circulation. SIDPP and SICP
should be equal (with the pumps off) because there is the same hydrostatic head in both
the drill pipe and the annulus. In case SICP is higher than SIDPP there is still an influx in
the well and circulation should be continued. If SIDPP equals SICP, but both are slightly
higher than the SIDPP before circulation, this means that there is some trapped pressure
in the well, most likely caused be closing the choke completely before the pumps were off.
This is not a problem and the well kill can continue with the next step.
The situation at the end of the first circulation is as follows.
The influx is circulated out
Shut in drill pipe pressure (SIDPP) equals Shut in casing pressure (SICP)
SIDPP after 1st circulation equals SIDPP before 1st circulation
The following preparations should be carried out before continuing with the drillers
method:
Enough volume of kill mud with the correct density and properties shall be
prepared before the second circulation can begin. The suction lines should be lined
up to the tank with the kill mud.
A kill graph, representative for the situation should be prepared. A kill graph for a
vertical well is straight forward, a kill graph for a deviated well needs some more
input.
In case of a vertical well the following steps are needed to prepare the kill graph.
Calculate the final circulating pressure (FCP) by using the following formula.
= ( )
:
= [] []
= [] []
= [] []
= [/] []
= [/] []
Obtain number of strokes from surface to bit, which can be found on the pre-
recorded data sheet.
Plot ICP at zero strokes, FCP at strokes from surface to bit. The drill pipe pressure
must decrease from the ICP to the FCP over the number of strokes required to
pump the kill mud from the surface to the bit.
In case of a deviated well the following steps are needed to prepare the kill graph.
Calculate the final circulating pressure (FCP) by using the following formula.
= ( )
:
= [] []
= [] []
= [] []
= [/] []
= [/] []
Calculate dynamic pressure loss at KOP. DPL at KOP = DPL + [ (FCP - DPL) * (MD
kop / MD td) ]
Calculate remaining SIDPP at KOP. SIDPP at KOP = SIDPP - [ (kill mud density -
original mud density) * 0.052 * TVD kop]
Calculate circulating pressure at KOP. CP at KOP = DPL at KOP + SIDPP at KOP
Calculate dynamic pressure loss at EOB. DPL at EOB = DPL + [ (FCP - DPL) * (MD
eob / MD td) ]
Calculate remaining SIDPP at EOB. SIDPP at EOB = SIDPP - [ (kill mud density -
original mud density) * 0.052 * TVD eob]
Calculate circulating pressure at EOB. CP at EOB = DPL at EOB + SIDPP at EOB
Obtain number of strokes from surface to KOP, which can be found on the pre-
recorded data sheet
Obtain number of strokes from surface to EOB, which can be found on the pre-
recorded data sheet
Obtain number of strokes from surface to bit, which can be found on the pre-
recorded data sheet
Plot ICP at zero strokes. The drill pipe pressure must decrease from the ICP to the
FCP over the number of strokes required to pump the kill mud from the surface to
the bit.
Plot CP at KOP at strokes from surface to KOP
Plot CP at EOB at strokes from surface to EOB
Plot FCP at strokes from surface to bit
Set up a graph and step down chart. Make step-down chart in order to always stay
above the ICP-FCP line. Typical steps are 100 strokes.
At the start of the second circulation the pump stroke counter will be set to zero, in order
to keep track of how much mud has been pumped. When the kill mud starts to go the drill
pipe, i.e. the surface line volume has been displaced, the pump stroke counter is reset to
zero again.
The pump will be started slowly, while at the same time the choke will be opened slowly.
While bringing the pump up to kill speed (SCR), the choke should be adjusted so that
choke pressure will equal SICP after the first circulation. With the pump up to kill speed
the pressure read at the drill pipe side should be equal to ICP. In case of a big difference
between calculated and recorded ICP, the reason for this should be investigated. Once kill
rate has been achieved the choke operator will now adjust the choke to let the drill pipe
pressure follow the kill graph. Continue to circulate at kill speed, until the kill mud has
reached the bit. At this point the drill pipe pressure should be the FCP.
Continue circulating to displace the annulus to kill mud while adjusting the choke as to
keep drill pipe pressure at FCP.
Once the kill mud has reached surface the well will be shut in again by shutting down the
pump slowly and closing the choke simultaneously. Monitor the SIDPP and SICP. These
should be zero (0 psi / 0 bar). If drill pipe and casing pressures are not zero, bleed-off the
pressures and check for trapped pressure. Perform a flow check through the choke line to
the trip tank. If the well is not dead, resume circulation to ensure a uniform weight of kill
mud throughout the wellbore.
Figure: Drillers method: end of second circulation; displaced well with kill mud
Once the well is confirmed to be dead, the well can be circulated conventionally. In order
to this the preventer(s) that were closed shall be opened and the HCR valve closed. Set
all back pressure manifold valves to normal operating position and resume normal
circulation, while checking for losses. If required add a suitable overbalance to the mud
weight and circulate the hole clean.
Overbalance:
When drilling from 0-1,500m the mud has an overbalance of 3.5 to 7 bar at the
expected top of any potentially productive formation.
When drilling from 1,500-3,000m, the overbalance to be at least 10 bar.
When drilling at depths greater than 3,000m the overbalance to be at least 14 bar.
How to control this increasing pressure, while maintaining a constant bottom hole
pressure to prevent any further escalation (i.e. a 2nd influx), is described under
volumetric control. Other applications for this method are:
Pipe is near surface and the weight of string is insufficient to perform stripping
operations.
Pipe is completely out of the hole pre-empting a stripping operation.
Annular BOP is damaged and stripping through pipe-rams is not an option (no
double set of pipe-rams or spacing for tool joint is not sufficient)
Circulation through the drill string is not possible due to plugged nozzles, forgot to
open FOSV when stripping had commenced, etc.
The first step in the preparation is to determine the choke pressure by using the following
formulas.
= [/] [/]
= [/] [/]
= [/] [/]
= [/] [/]
= [/ ; 0.22 ] [
/ ; 0.1 ]
Then calculate Ps
= [] []
= [] []
= [/] [/]
= [] []
= [] []
= [] []
= [; 3 ] [ ; 50 ]
The next step in the preparation is to determine the bleed off volume with the formula.
;
=
:
= [] []
= [; 3 ] [ ; 50 ]
= [/] [/]
= [/] [/]
Ensure that the choke line and manifold are properly aligned to discharge bled off
liquid into the trip tank
Ensure the trip tank is approximately 1/3 full
Ensure the BOP control system allows fast response and guarantees a seal when a
tool joint is stripped through the sealing element.
A schematic overview of the regulator system to control the closing pressure of the
annular preventer is given below.
Before stripping can start a stripping schedule (Plan of action) should be prepared. For
this the following should be calculated;
Calculate how much wellbore pressure can be allowed before the pipe is pushed
out
:
= []
= []
= []; 15000
= 2
:
= [2 ]
= []
=
:
= []
= [2 ]
1 =
:
1 = []
= 1 [/],
= []
Regardless of the method used to strip pipe into the hole, to enable effective pressure
control, it is important to measure all the fluid movements on surface and from the
wellbore accurately. Influxes that have entered the well could be gas and migration may
take place. If there is no migration it could mean that a fluid, oil or formation water is
swabbed but it also could mean that conditions are such that gas is still in liquid phase
and can break-out higher up the hole. As long as we face a liquid phase, as pipe is
stripped in, the volume of mud released from the wellbore should equal to the closed-end
displacement.
To minimise wear, the pipe should be lubricated and the closing pressure applied to the
preventer should be kept to a minimum whilst avoiding leakage. Additionally, drill
pipe/casing protectors should be removed and the drill pipe (and tool joints) surface to be
smoothened from tong & slip marks.
At this point it might be useful to circulate for a short time to confirm that the pipe in the
hole is not plugged before beginning to strip in.
The next step is to prepare a stand of drill pipe. Make up a stand of drill pipe to the pipe
in the hole and make sure of the following.
Ensure that casing protectors are removed
Ensure tong and slip marks are smoothened
Ensure tool joints are lubricated
Now the first stand can be stripped in. Slowly lower the drill pipe and move the tool joints
slowly through the preventer, avoiding excessive pressure surges. Monitor the closing
pressure of the annular BOP while tool joints are being stripped through, to ensure that
the regulator is functioning correctly. Then fill the stand with fluid from the active system.
After stripping the entire stand in the hole, measure the mud which leaked past the
annular preventer. Then bleed the closed end displacement volume minus the leaked
volume into the stripping tank.
Let the shut in (casing) pressure rise till it reaches the choke pressure as calculated. This
pressure will be Pchoke1. Then release the calculated bleed off volume at choke, while
maintaining the choke pressure constant (=Pchoke1). Collect the bled off fluid in the trip
tank and close the choke once the required volume is bled off.
Continue stripping in while increasing Pchoke in steps of Pw and keep releasing the bleed
off volume until gas reaches surface or until pipe on bottom.
If gas reaches surface before the bottom is reached continue by lubricating the well. This
process starts by pumping the calculated volume of mud in the well and allowing it time
to fall through the gas bubble. Then bleed off gas pressure equal to Pw by opening the
choke and letting pressure drop to Pchoke new.
After the choke pressure has dropped, close the choke, pump the required volume of mud
and continue this process until all gas is replaced with mud. Then continue stripping in to
bottom.
If bottom is reached, then the initial circulating pressure (ICP) should be obtained. Bring
the pump to kill rate while keeping the casing pressure constant. The drill pipe pressure is
the required ICP. Now refer to either Drillers method or Wait-and-weight method to
circulate the influx out and kill the well.
Form for pressure and volume records during Volumetric Stripping Method (use of Annular
only)
LOSS OF CIRCULATION
4.12.1 BOPs
The requirements for different types of BOPs are listed below according to their working
pressures. The choice of a given BOP depends on the maximum expected surface
pressure that could encounter during drilling and workover operations.
1. 2M BOPs:
One annular preventer.
Two ram type preventer.
One choke line and one kill line outlet.
Ring gaskets will be of metal to metal sealing.
2. 3M and 5M BOPs:
One annular preventer.
Two ram type preventers.
One choke line outlet. One kill line below shear rams, with 2 valves per outlet.
Ring gaskets will be of the metal to metal sealing type.
Regulator valves of 3000 psi (200 bars) shall be fitted with manual overrides and
fail-safe close features.
The unit should be positioned in a safe area away from the wellbore to allow
operation of the unit in an uncontrolled well situation.
The unit should be fitted with 4-way valves that will be kept in the open or closed
position during the operations.
The unit shall have two remote panels and each panel clearly marked with Open
and Close for all functions.
The choke manifold must be sized correctly and in good working order. It is the
responsibility of the Driller to ensure that the choke manifold is lined up correctly at all
times. All open valves of annular line from BOP stack to poor boy will be painted in a
white color to see direction of fluids from annulus to surface. The Driller must check the
line up at the start of his shift.
According to API it is recommended to have two chokes; one manual and the other
remotely-operated.
The choke and standpipe manifolds should have two isolation valves and have an option
to be lined up with the cementing unit.
There are two types of float valves; the flapper type and the spring-loaded ball or dart.
The main advantage of the flapper-type is that it offers a full opening approximately the
same as the ID of the tool joint. The advantage of the spring-loaded type is that it gives
an instantaneous and positive shut-off of backflow through the drill string.
App. 1.2 Surface BOP kill sheet Deviated well (SI units)
Prepared by WEP
Author:
Verified:
2
5.1.1 Preparations
Ensure that drilling objectives and anticipated drilling conditions for the next bit
run are reviewed and understood prior to make up of BHA.
Check that the depth referencing and grid correction is correct.
Check if surface coordinates and bottom hole coordinates are the same as per
directional drilling plan. Confirm surface coordinates with the Final Survey for the
well cellar with conductor
Check that the survey procedures are known and that the correct grid is selected.
Verify available Weight on Bit for drilling operations, ensuring the drill string is not
in compression.
Directional Company to ensure there are sufficient Nonmagnetic drill collars in the
string for surveying purposes for the section to be drilled.
Verify that all drill pipe, drill collars, crossovers, jars, etc, have been recently
inspected and are in useable condition.
Ensure that the mud pump dampeners have the correct pressure.
Check X-O and connection types of the various down hole tools.
Check that the flow ranges of the various down hole tools are compatible with the
anticipated flow rate.
Ensure that all BHA components are callipered for OD & ID and that a schematic is
prepared, including lengths, prior to running in the hole.
Select the correct fishing tools, based on measurements of BHA components.
Ensure that the torque sensor is pumped up and the torque gauge is calibrated
(use iron roughneck and tong load sensor).
API RP 7G shows the recommended make-up torques for commonly used tool-joints in
Premium Class. For OD's between those shown, estimate the make-up torque (torque
proportional to diameter) or use 60% of torsional yield.
New joints
Make up new tool-joints very slowly and torque to minimum specified torque. Then
break out, clean thoroughly, and inspect for minor damage. Re-lubricate and make
up to operational torque.
Pipe recovered in a fishing operation should be replaced or, as a minimum,
inspected before it is run in the hole again.
On side track wells depths shall similarly be recorded below actual RKB but shall also be
referenced to the original derrick floor elevation.
For reservoir engineering purposes the depths shall be reported below a universal datum.
All BHAs cause a side force at the bit that affect hole inclination:
positive side force: Fulcrum effect : build inclination
zero net side force: Lockup BHA: no change in inclination
negative side force: Pendulum effect: a drop in inclination
Additional directional behaviour (bit walk) can result from specific rotary BHAs and
drilling parameters, such as WOB and RPM.
5.3.4 Stabilization
It is important to understand the effect the stabilisers have on directional behavior.
If the near-bit stabilizer is under-gauge this results in a loss of bit side force. For a build-
up BHA the build rate is thus reduced. For a locked-up BHA, a drop in inclination is the
result.
The more under-gauged, the greater the effect. For drop-off BHA's, the use of an under-
gauged near bit stabilizer is recommended in "S" wells at the drop-off.
If the second stabilizer is under-gauge it becomes easier to get a tangency point below it:
it becomes easier to build angle. The more under-gauge this second stabiliser is, the
greater the effect. For holding (locked) BHA's, an under-gauge second stabilizer is usually
deliberately included in the BHA. The objective is to reach a condition of zero net side
force at the bit.
The figure above provides the general idea of the effect in the drilling tendency for the
various stabilizer sizes (full gauge vs. under gauge) and stabilizer placement.
Stabilized BHA can be designed to build, hold or drop inclination. Critical elements:
Stabilizer gauge & position
Drill collar OD/weight/moment of inertia
Hole inclination
WOB, RPM, flow rates
Hole gauge
Bit Type
Prediction issues (formation effects, bit walk, hole washout)
Conventional steerable design is driven by the dogleg requirements of the trajectory. This
translates to:
In some instances the maximum allowed Surface RPM is well below what is required for
cuttings agitation. To compensate for the lack of rotation,do:
1. Increase the flow rate. (In most cases we wont be able to increase the flow rate to
a sufficient rate that would make up for the lack of rotation).
2. Ensure rotation of sufficient speed is achieved in the tangent section after the
build-up section. This only applies if there is a tangent section after the build.
3. Change the trajectory. This means reducing the build rates so that a lower bend
setting can be used.
4. Putting in dedicated hole cleaning procedures and measures. This could involve
reducing ROP if drag increases due to cuttings build-up or to perform clean-up
trips during the build-up section and having dedicated assemblies for different
parts of the section i.e. one assembly for the build-up and a different assembly for
the tangent section.
Tight annular clearance between the wellbore and the motor sleeve or integral stabilizer
can also easily cause cuttings to build up.
Pre-job checks
Check if the motor speed range is suitable for the type of bit in use.
Compatibility of stator elastomer with drilling fluid system (NADF or WBM).
Compatibility of motor temperature rating with circulation temperature, in
particular internal fit and resulting performance.
Compatibility of flow range of the MWD tools with the anticipated drilling flow rate.
Gauge the bottom stabilizer on the motor and ensure it is in accordance with the
planned under-gauge requirements.
Check bent housing setting to ensure it is able to achieve the dog legs required by
the wellbore trajectory.
Make up the motor, MWD and bit. Test the motor and MWD at two or 3 different
flow rates and record the circulating pressures and rates.
Make up the MWD, aligning the scribe mark on the motor with that of the MWD.
Clearance between downhole drilling equipment and wellbore and number & type
of stabilisers.
Pulling speed.
is important to stress that a rotary steerable system alone will not solve your hole
cleaning problems unless the other key parameters are optimized.
The main advantages with the use of rotary steerable systems are:
1. Continuous rotation maximizing hole cleaning efficiency and ROP.
2. Full inclination and azimuth control for wide range of dogleg capabilities.
3. Not limited by weight stacking and buckling issues, as is the case with motors.
4. Minimises tortuosity in the wellbore. Smooth wellbore aids further torque and drag
reduction.
The additional advantage of a RSS system that includes a motor is its performance
capability. The motor increases usable torque and rotation speed at the bit. Due to the
higher torque available more WOB can be given, this all results in higher ROPs. In
addition of that the casing wear is decreasing due to low string rotation.
Typical applications:
High-performance directional drilling.
High rate of penetration in hard-rock drilling applications
Rigs with low torque capacity.
The use of the extreme heavy 9 1/2 DCs should be avoided since pipe handling and
making up is too risky.
First a distinction needs to be made between vertical wells and deviated wells. For the
vertical wells the approach stays unchanged with the use of DC, to keep the string in
tension and the available weight is supplied by the DC and the neutral point in the Drill
collars.
For deviated wells there are two approaches 1) the use of conventional BHAs having
150 200 m drill collars in the BHA and 2) omitting the Drill collars all together.
Omitting the DC and providing all the weight by the HWDP gives no significant effect on
directional tendencies when drill collars are replaced by HWDP. Furthermore the HWDP
assemblies do exhibit less shocks and stick-slip.
Available weight:
= cos
Where:
is the hole inclination in degrees
w is weight per unit length
L is the length of DCs below the Tangent
BF is the buoyancy factor
(/)
= 1
7.85
Neutral point
Drill pipe must not be run in compression in a non-horizontal well. To ensure that the drill
pipe is always in tension, the neutral point must be either in the HWDP or in the DC's.
Obviously, the lower the WOB, the closer the neutral point is to the bit. Therefore, the
BHA must be designed to account for the worst case (i.e. when maximum WOB is
applied).
A 10% Safety Factor (SF) should be used in the calculation for the required BHA weight.
For tapered drill strings, the WOB calculation is done as follows:
= ( ) (cos )
=
cos
Circulating Subs
A circulating sub shall be run into the drill string under the following circumstances:
1. When tools or restricted flow paths are in the drill string (e.g. MWD, core barrels,
downhole motors, turbines, fishing tools).
2. When drilling in areas of expected lost circulation so that LCM can be pumped
without plugging the MWD or bit. In this case it is preferred to run large or open
jets. However, this may not be desirable for bit hydraulic.
3. When changing mud situations. This could result in high viscosities, high gel
strength or the settling out of barite.
Notes:
Ensure that ID of the circulating sub does not restrict running wireline tools (e.g.,
FPI, String shot, Severing tool).
Opening the circulation sub in open hole is not recommended while drilling.
For the optimum position of the jar and accelerator follow the recommendations of the jar
supplier.
To avoid jarring down when tagging bottom the following procedures need to be
followed:
Wash down the last stand, gently tag bottom, establish the required tool face
before commencing with drilling.
Continue to slowly lower string weight after tagging bottom allowing the jar to
completely close and move through detent without causing an impact. A slight
movement of the weight indicator might be detectable as the jar exits the detent.
Now additional weight can be added.
The time to close the jar without firing will vary depending on the wear of the jar
and the down hole temperature.
The above assumes that the neutral point moves up from below to above the jar when
WOB is applied (from tension while RIH to compression after set down).
In order to avoid jarring-up when making a connection or tripping out of the hole with the
jar in compression, the procedure below should be followed:
Slowly raise string off bottom, allowing the jar to open and move through detent
without causing an impact. Again the slight movement of the weight indicator
needle will be observed as the jar exits the detent. Now the jar is in the open
position and normal practices of pulling out can continue.
The impact created by the jar is the result of a complex pattern of compressive and
tensile stress waves that travel through the BHA. The effectiveness is usually measured
by the amplification factor which is defined as the ratio of maximum impact force over
static preload force. Jarring vendors provide services to calculate and optimize the
amplification factor by using specialized software.
It performs the same function as the free length of drill string, which stores strain energy
during normal drilling. The difference being that the jarring accelerator stores strain
energy over significantly less length than that required for the drill string. This is
accomplished by compressing a series of springs inside the tool or compressing gas or a
compressible fluid, such as silicon, inside the tool. The result is that less energy is lost to
friction resulting in a higher impact when the jar fires.
Accelerators will effectively reflect shock waves. Hence shock loading of surface
equipment when using jars at shallow depth is minimized in case accelerators are used.
This is key to protect top-drives during a shallow jarring operation. Jarring with the top
drive connected directly to the string can cause damage of the top drive, despite the
accelerator. Jarring should be done using the elevators instead of the top drive.
It is recommend to change out the accelerator after 150 hrs and limit the use of
accelerators to 250 hrs. The name accelerator is a proprietary name of Weir-Houston
Engineers (currently owned by Smith Drilling and Completions Inc.) Other designations
are Intensifier (Griffith), Impact Enhancer (IPE, International Petroleum Equipment),
Hypulse Jar Slinger (Dailey/Weatherford).
When drilling horizontal wells (ERD) the jar/Accelerator position in the BHA is critical. For
the best jar/accelerator recommended position, ask the jar supplier.
The effective length of the pendulum and the side force on the low side are both reduced
when the collar makes contact with the low side of the hole. This situation is undesirable
because the bit axis has been tilted upward in relation to the hole axis which will reduce
the dropping tendency. (In itself, this would produce a build tendency).
Careful selection of drilling parameters is required to prevent this. High rotary speed
(120-160+) helps keep the pendulum straight. Initially low weight on bit should also be
used, again to avoid bending the pendulum towards the low side of the hole. Once the
dropping trend has been established, Moderate weight can be used to achieve a
respectable penetration rate.
Recommended Practices:
Concentrate on producing a side force on the low side of the hole. This is best achieved by
running an assembly where the pendulum portion is as stiff and straight as possible. It is
also desirable that the section immediately above the first string stabilizer is also stiff and
straight. Therefore a second string stabilizer within 10m of the first is recommended.
When azimuth control is not a concern or when drilling with a PDC bit omit the
near bit stabilizer. When drilling with roller cone bit, use an under-gauge near-bit
stabilizer if azimuth control is a concern. Typically, the near bit stabilizer needs
only to under-gauge in order to produce a dropping tendency.
The assembly should have 2 string stabilizers with the second stabilizer not more
than 10m above the first.
Initially, use low WOB until the dropping tendency is established, then gradually
increase bit weight until an acceptable penetration rate is achieved.
If possible, do not plan drop sections in hard formation.
Below a graphical presentation is given showing the effect on dropping tendency of the
BHA by changing the configuration of the stabilizer placement.
Excessive doglegs or a drop in build rate have a much greater effect on torque and drag
in top hole than in deeper hole sections. Use of torque and drag analysis while drilling
should be made to assess the impact of directional variations on the overall directional
operations plan. Severe dog legs may render drilling to TD impossible and as such an
accurate analysis of the well trajectories implication of the Torque and Drag profile and
Road map charts for highly deviated wells (Pick-up/Slack-off/Rotate of bottom) at TD is
essential.
5.6.3 Tangent
The tangent section may include a drop-off interval on S - shaped wells, or may
maintain a constant inclination to the target for build-and-hold wells. With Steerable
Mud-Motor assemblies corrections can be performed as required, however the economics
of running the steerable system should be checked. With large targets, the enhanced
directional control afforded by these systems may not be required.
For tangent sections a hold BHA is typically used. Prior to the bit run an estimate must
be made of the drop/walk rates required and stabilization selected accordingly. BHA
behaviour is highly field-dependent. In general, the best guide is the previous BHA but
this should be cross-referenced with offset records whenever possible.
Tripping in the hole with a stiffer assembly (i.e. locked assembly after a build assembly
and particularly any rotary assembly following a steerable mud motor run) requires
particular care to avoid becoming mechanically stuck or generating an unplanned
sidetrack. When approaching the bottom it is good practice to wash and ream the last one
or two stands even if reaming has not been required.
Once on bottom, drilling parameters should ideally be selected for optimum ROP. It is,
however, sometimes necessary to correct an undesirable directional tendency by varying
WOB and RPM. For general guidance:
WOB: increase to get more build with build and hold assemblies. Decrease to
encourage drop or maintain vertical hole with pendulum assemblies.
RPM: increase to reduce right-hand bit walk. Decrease and add WOB to
encourage walk. Individual/local experience may, however, prove otherwise.
The choice of bit should take into account the degree of reactive torque produced. Some
aggressive PDC bits can make motor tool face control difficult resulting in not being able
to follow the planned trajectory. The use of specially designed tri-cone bits or steerable
PDC bits should be considered when a lot of steering is anticipated.
After completing the well, the complete BHA must be returned for further
inspection.
All components must have stress relief grooves (including non magnetic
components and jars).
Use Enhanced hydraulic (up/down) short jars in the BHA assembly.
Final Build and Horizontal Hole Section
Several studies confirmed that washouts occurred near the end of the shape of the
internal upset, closest to the tube body-the most highly stressed area of the drill pipe
during drilling and the most prone to fatigue failure.
Important:
Clean and visually inspect pipe & connections for damage when pipe is on the rack
Redope using PETROM approved thread compound
Re-install thread protector and leave them on when moving and picking-up pipe
Drill pipe inspections on the rig between wells are more detailed than trip inspections.
Thus, they can reveal defects or wear otherwise overlooked. This early detection permits
lower cost repairs before extensive damage occurs. By keeping full records of these
inspections, the contractor also reduces the cost of later third-party inspections.
6 Drill bits
Prepared by WEP
Author:
Verified:
2
6 Drill bits
The third and fourth characters indicate the general features of the bit itself, such as the
type of bearing, whether there is gauge protection or not and whether the bit has any
special features or whether it is intended for any special applications, such as air drilling.
The first character indicates the cutter type and the body material. The second character
indicates the profile of the cutting face of the bit. The third character indicates the design
of the bit with regards to the flow of drilling fluid across its face. The fourth and last
character indicates the size and density of the cutters.
Refer to attachment II for the classification scheme of PDC and diamond bits.
In addition to the selection of the correct bit the main factors which play a role in the bit
performance are the drilling parameters, drilling fluid properties and hydraulic factors.
( + ) +
=
Where:
C = drilling cost / meter [RON / m]
R= rig operating cost [RON / hr]
T= trip time [hrs]
D= drilling time [hrs]
B= bit cost [RON]
F= footage drilled [m]
Additional benefits for using a PDC bit could be to stay in hole when conditions getting
worse. For example:
Avoid dangerous hole sections.
Avoid tripping in bad weather.
Reduce rig wear.
No moving parts.
6.2.2 Bits to use for formations with altering soft and hard layers
Local offset and experience would be the starting place for any recommendations. Where
these are limited or absent, it would be prudent to focus on the hardest formations that
will be accounted to limit bit damage. If the hard/ soft formation boundaries are known
with any certainty, it would be prudent to manage the drilling parameters when
approaching these intervals. Typically lowering both RPM and WOB where possible when
both entering and leaving harder formations - running into a different and significantly
softer formation with very high weights could result in damage to both the bit and BHA as
the bit takes a substantial bite of the softer formation. Typical wear mode in these
applications for PDC bits will be impact damaged resulting in chipped cutters, with the
utilization of managed depth of cut technologies, cutter damaged can be minimized as the
bit matrix affords the cutters a good deal of protection.
6.2.3 Bit style for steerable motors (Rock bits vs. fixed cutter PDC bits)
When drilling with steerable motor, power to the bit is generated by Torque (TQ) and
RPM. When sliding or steering constant flow rate will be applied this will generate a
certain RPM and TQ value.
In the majority of cases, Rollercone (RC) bits will be easier to steer than fixed cutter bits
due to the difference in cutting action. Crushing and scraping for RC bits rather than the
shearing action on a PDC bits, torque from a RC bit will most likely be less than that
generated by a PDC bit and more importantly, it is also likely to be more consistent which
will be a big aid in maintaining toolface when steering.
provide this and other additional information on the relative steerability of different
designs.
Fixed cutter PDC bits managed depth of cut (MDOC); the bit cant overbite in the
formation creating undesired torque fluctuations in soft and/or laminated formation.
Example on dull gage breakage Push the bit RST after drilling chert and chalk
Dull on inner row breakage Point the bit RST after drilling chert and chalk
In most cases for fixed cutter PDC bits, the requirements for Rotary Steerable and Motor
drilling bits are actually quite similar: Directional response and vibration mitigation are
critical, so a stable cutting structure with moderate backrakes and although less critical
than on motor bits the utilisation of a managed depth of cut (MDOC). With MDOC
directional response is improved and adds effective impact protection the cutters on the
bit. Cone angle is medium to shallow and profile is short similar to that of the steerable
motor requirements as detailed above.
In terms of pack off, swab and surge risk when pulling out hole, bit junk slot is something
that should be considered but when looking at the application and formation to be drilled,
bit selection will be dictated by durability, stability and directional performance. We would
generally not recommend dropping blades purely because an ERD well is being drilled
rather than a conventional profile well.
Generally speaking a bit with a bigger junk slot would be preferred purely from the swab
surge risk but picking a bit solely because it has the biggest junk slots is false economy;
good ERD drilling practices will outweigh the singular benefit that such a bit may promise
to provide.
Hydraulic energy as supplied to the bit can be divided in three functions and dependant
on the application, lithology, rig, bit type and downhole conditions, the importance of in
terms of what is most important for bit performance does vary:
Cutting Structure Cleaning/Cooling (CSC)
Bottom Hole Cleaning (BHC)
Cuttings Evacuation (CE)
Generally, with HSI below 2, jet velocities will likely fall into an area where nozzle
plugging is much more common and Rollercone bits suffer from cuttings regrind (cutting
formation that has already been cut but not displaced from the hole bottom) as well as
the potential for more damage to the seal systems as cuttings get drawn towards the
bearing with cone rotation rather than efficiently evacuated up the hole away from the bit.
Good mud systems will decrease the likelihood of bits balling up in the majority of cases,
but paying attention to Hydraulics in all cases should benefit bit performance and further
minimise the tendency of any bit to ball up.
As shown on the above graph, dependant on the application, the hydraulic needs of a bit
drilling the softest formation could be quite different from a bit drilling through the
hardest of rocks and field information along with local knowledge can provide information
on recommended hydraulics for both these extremes and the areas in the middle.
Optimizing bit hydraulics is recommended for all mud system to improve overall drilling
and bit performance.
Two approaches can be used either to optimise the bit hydraulic horsepower, which will
occur when Pb (bit pressure drop) is approximately equal to 2/3 Pt (total pressure
drop) or to optimise the jet impact force, which will occur when Pb is approximately
equal to Pt. Nozzles can then be chosen to achieve the required result.
Note that the relationships quoted above are approximate and are presented to give a
feeling for the order of magnitude of the values required. For a more accurate estimate of
the required Pb the properties of the drilling fluid need to be taken into account, in this
case the parameters C and N in the equation Ps= C*Q^N. The procedure below shows
how to determine these, and how to apply them to calculate the optimum nozzle sizes
corresponding to each approach.
Note also, however, that the optimisation of bit hydraulics is often compromised by other
hydraulic requirements such as hole cleaning and the pressure drop / flowrate restrictions
associated with certain pieces of downhole equipment.
Prior to pulling out of hole to change the bit, determine the following:
2. N & C Values
Find the bit pressure drop (Pb) for different values of Q.
15.7 * df * Q 2
Pb = in bar
An 2
Find the system pressure drop (Ps) for different values of Q.
Ps = Pt Pb [bar]
Ps1
Log
Ps 2 Ps1 Ps1
N= and C = N
= N
Q1 Q Q2
Log 1
Q2
Ps = C * Q N in bar
Pt
To optimise Bit Hydraulic Horsepower: Ps = in bar
N +1
2 Pt
To optimise Jet Impact Force: Ps =
in bar
N +2
Ps 1 / N
Find pump output to give Ps: Qopt = ( ) in m3/hr
C
Find available bit pressure drop: Pb = Pt Ps in bar
df
So nozzle area is: An = 3.962 * Qopt in mm2
Pb
Nozzle size Nozzle Flow area of 1 Flow area of 2 Flow area of 3
number nozzle nozzles nozzles
inch mm inch mm inch mm inch mm
7/32 5.5 7 0.0376 24.3 0.0752 48.5 0.1127 72.7
8/32 6.4 8 0.0491 31.7 0.0982 63.4 0.1473 95.0
9/32 7.1 9 0.0621 40.1 0.1242 80.1 0.1864 120.2
10/32 7.9 10 0.0767 49.5 0.1534 99.0 0.2301 148.4
11/32 8.7 11 0.0928 59.9 0.1856 119.7 0.2784 179.6
12/32 9.5 12 0.1104 71.2 0.2209 142.5 0.3313 213.7
13/32 10.2 13 0.1296 83.6 0.2592 167.2 0.3889 250.9
14/32 11.1 14 0.1503 97.0 0.3007 194.0 0.4510 291.0
15/32 11.9 15 0.1726 111.4 0.3451 222.6 0.5177 334.0
16/32 12.7 16 0.1963 126.6 0.3927 253.4 0.5890 380.0
18/32 14.3 18 0.2485 160.3 0.4970 320.6 0.7455 481.0
20/32 15.9 20 0.3068 197.9 0.6136 395.9 0.9204 593.8
22/32 17.5 22 0.3712 239.5 0.7424 479.0 1.1137 718.5
24/32 19.0 24 0.4418 285.0 0.8836 570.1 1.3254 855.2
28/32 22.3 28 0.6013 287.9 1.2026 575.9 1.8040 863.7
Table: Nozzle sizes and flow areas
4. Jet velocity
It is not recommended to use extended nozzles during junk or cleanout runs, where larger
pieces of debris might be encountered and could damage a nozzle.
Centre jets are common on most Rollercone bits in excess of 9 7/8 typically they provide
flow to the nose area of the bit to limit the likelihood of balling in this area. In non balling
apps, a centre jet is less important and could either be blanked or given a smaller % of
the available flow by running a tighter nozzle.
Bits placed on their pin are top heavy. Keep feet away from bit when attempting to
handle it.
Use a piece of wood or rubber under the bit face.
Bit Inspection
Inspect bit for integrity (cutting elements, pin connection and make-up shoulder).
Ensure there are no foreign objects or obstructions in the internal fluid
passageways.
Do not use a PDC gauge ring on a 3-cone bit or vice-versa. Gage the bit and verify
type of ring gauge used, as tolerances are dependent upon the bit type fixed
cutter or roller cone. See gage specifications in appendix. Ensure gage conforms to
customers casing program.
For roller cone bits, especially sealed bits, ensure that the cones do not rotate
freely (they should be difficult if not virtually impossible to rotate).
Check inserts on tungsten carbide insert bits for integrity.
Record bit size, type and serial number.
Nozzles Installation
Verify TFA on bits with fixed TFA.
Ensure O-rings are seated properly in the nozzle bore, feel them for any defects
Check for proper nozzles, these will typically have part numbers associated with
the bit size ranges. For roller cone bits place the nozzle in the bore to ensure the
right size. For any threaded nozzles inspect the threads on the nozzles, and screw
the nozzle into the bit to ensure no problems.
If different size nozzles are to be used ensure that the correct sized nozzles are in
the correct place, e.g. 12 PDC with 3x13s and 3x12s, put 3x13 in the center.
Check for proper nozzle installation tools, including nails, hammer, snap rings,
snap ring pliers and Loctite for threaded nozzles if recommended (blue coded
Loctite is typically used)
Make certain nozzle gauges are on location and gauge all nozzles.
Make certain that the bit is properly fitted with the correct size of nozzles (TFA).
Use nozzle wrench for final tightening. Excessive force is not necessary and can
damage the carbide nozzle.
If nozzle sizes below 9/32 are to be used, recommend the use of drill pipe screens
and / or a float to prevent reverse circulation plugging. Use grasshoppers if
necessary.
Engage the hanging box connection to the doped threads of the bit pin.
Proper make-up for small diameter bits is to make-up by hand for several turns,
then place in the bit breaker and make-up to the recommended torque.
Uncover the rotary and locate the bit and breaker onto the breaker holder.
Make-up, applying the recommended torque.
Make-up torque specifications are from API spec RP7G.
Tagging bottom
Approach the hole bottom cautiously, monitoring WOB and torque. An increase in
WOB or torque will indicate either contact with the hole bottom or fill. Fixed cutter
bits will typically show an increase in torque first. Bit is on bottom when torque
increases with the WOB. Difference between measured depth and contact point
should be depth of fill.
If fill is present, pick up above the fill and rotate to bottom with full circulation until
bottom hole contact is assured. Regardless if fill is present, the pipe should always
be reciprocated off-bottom.
On rotary assemblies, use a maximum of 500 pounds per inch of bit diameter, 40
to 60 RPM.
On motor assemblies, use a maximum of 500 pounds per inch of bit diameter and
the minimum allowable RPM.
Do not use high WOB when in fill. This could cause the bit to ball.
Circulate and rotate off-bottom (as close as possible preferably less than 6, no
more than 1 foot) enough (5 to 15 minutes, application dependent, recommend 15
min. as minimum) to ensure the hole bottom is clear of fill or junk.
Procedure
Frequently raising and lowering the bit while continuing circulation and rotation will
help keep the bit clear of debris. When ROP decreases, flush after every 1 to 2 in.
drilled while reciprocating 1 to 2 m will ensure debris is removed and new material
is being drilled. Should the penetration rate decrease suddenly, repeat this step
until it resumes.
Do not spud. Spudding (impacting on the hole-bottom) can damage cutting
structure elements on both fixed cutter and roller cone bits. It can also damage
the roller cone bearing / seal system.
Monitor pump pressure to ensure nozzles do not become plugged.
Change RPM if bouncing or erratic torque is encountered.
Rotating Plugs
Should a plug begin to rotate, set down on plug with no RPM
Increase WOB until 1 to 1.5 mT per inch of bit diameter is reached or alternatively
an increase of 300 psi over the normal standpipe occurs.
6.4.4 Reaming
Ream using very light WOB and low RPM.
Use the maximum allowable flow rate.
Use lower RPM when reaming harder or more abrasive formations.
Consider reducing bit size to avoid reaming cored/undergauge sections on the last
bit run, e.g. 8 3/8 below 8 or 5 7/8 below 6.
6.4.5 Establishment of bottom hole pattern when start drilling with PDC
Bottom hole pattern break-in has to be applied when a new bit is run to achieve uniform
cutting structure loading. Proper break-in is critical to durability and ROP.
After drilling out the casing shoe, establish the bottom hole pattern. There may be
some BHA dictated WOB and RPM guidelines until the BHA is below the casing
shoe. Optimization of WOB and RPM may have to wait until the BHA or some
portion of the BHA has cleared the casing shoe.
Use extra care establishing a new bottom hole pattern when following a bit with a
substantially different bottom hole profile, e.g., a PDC bit following a roller cone bit
or vice-versa.
Roller cone bits typically drill a larger size hole than a fixed cutter bit. Be sure to
properly establish the bottom-hole pattern when following a roller cone bit in order
to insure stability.
Establishment of bottom-hole pattern can be dependent upon factors such as bit
design, BHA, etc.
Note: Anytime WOB and RPM are changed, time is needed to allow a steady state
condition to occur in order to know the true effects. The fluctuations and minimal time
used in some drill-off tests may not allow the optimum WOB or RPM to be realized.
There are many variations of drill-off tests. All are presented in the attachment.
Drilling Sand:
More responsive to WOB than RPM.
Porosity in sand is a major factor in ROP. Everything else being equal, a higher
porosity sand will yield a higher ROP. An over-pressured sand can also increase the
ROP.
Depleted sands are difficult to drill due to the high differential pressure across the
face of the rock. Expect the bit to drill slowly in this situation. Also, the bit may
drill off center, which will produce an even slower ROP. Consider changing mud
properties to reduce the chip hole down pressure (mud weight, spurt loss).
Maintain minimum RPM to minimize gage wear. In known extremely abrasive
formations, monitor torque to ensure a gage hole.
Evaluate cuttings and other downhole tools to estimate degree of abrasiveness and
adjust RPM if necessary.
Drilling Carbonates:
More responsive to WOB than RPM.
Monitor for bit bouncing.
Chert nodules, often encountered in limestone and dolomite formations, can move
or roll underneath the cutting structure similar to broken formations. This can
overload cutting structure elements leading to chippage and or breakage. Ensure
excessive WOB or RPM is not used.
Drilling Quartz:
Use minimum RPM to reduce gage damage, but with adequate WOB to effectively
drill high compressive strength rock.
Monitor bit for torque indicating a potential undergauge condition, which dictates
pulling the bit.
Drilling Pyrite:
Pyrite is extremely abrasive and hard. Use minimum RPM to reduce gage damage,
but with adequate WOB to effectively drill high compressive strength rock.
Pyrite can move or roll underneath the cutting structure similar to broken
formations. This can overload cutting structure elements leading to chippage and
or breakage. Ensure excessive WOB or RPM is not used.
Monitor for bit bouncing.
Monitor bit for torque indicating a potential undergauge condition, which dictates
pulling the bit.
Symptoms:
The surface measurable symptoms indicating potential bit related problems are:
Decreased ROP.
Increased, Decreased or Erratic Torque (pump pressure on motor applications).
Reduced Directional Characteristics.
Decreased or Increased Pump Pressure
Please note that there are other application factors that can create the same surface
measurable symptoms.
Any deviation from accepted norms should be investigated. With no changes in current
operating parameters, the potential bit related causes of the above symptoms are:
Bit Balling.
Bit Bouncing (see also axial vibration).
Off-Center Rotation / Whirl (see also lateral vibration).
Tracking.
Cutting Structure Damage and / or Wear.
Bearing / Seal Failure.
Formation Change.
Bit Washout / Lost Nozzle / Plugged Nozzles.
Inadequate Hole Cleaning / Annulus Packing Off.
Junk.
Note that all of the symptom changes will vary in magnitude and may not be measurable
or identifiable on the surface due to many factors.
Roller cone bit symptoms are more subtle than fixed cutter bits due to the lesser amount
of torque generated per WOB.
Ensure that symptoms are indicative of problems and not just an expectation within the
run.
The answer on how to reduce one of the above vibration modes might be as simple as to
have attentive rig personnel who are willing to alter parameters in order to mitigate any
vibrations.
Various guides are available on how to manage vibration, however recent practical
experience and modelling with software programs (for example Smith IDEAS) has often
shown that the reverse of the established methodology to be successful. For example:
minimising stick slip - it is commonly suggested that lowering WOB and increasing RPM
may help, however in many cases if it is the bit that is generating this form of vibration
then increasing the weight may actually be the best course of action as this will help the
bit shear the formation more effectively and consistently.
Some different modes of vibration and the commonly adopted practices for mitigation:
Procedure
Reduce RPM approximately 50%. Maintain a minimum rotary of 60 to 80 RPM.
Drill off 50% of WOB.
Stop rotary and lift off bottom.
Make connection.
Start rotary at 60 to 80 RPM.
Circulate approximately 1minute off-bottom before making connection or after
connection is made.
Slowly set bit back on bottom.
Add weight slowly to attain previous weight on bit.
Increase rotary speed to previous RPM.
=
( + )
When very high on-bottom torque with little WOB and a decrease in ROP occurs
(bit undergauge, abrasive formation)
When erratic torque occurs (bearing wear)
Dramatic decrease in ROP and on-bottom torque.
Note: Refer to bit manufactures recommendations on bit hours or bit revolutions and
compare with actual.
Careful analysis of all drilling parameters is always recommended. Generally a flat lining/
gradual reduction of torque with an accompanying reduction in ROP will indicate a worn
bit, though the effects formation changes and stringers can often mask or confuse this.
Torque spikes and further reductions in ROP, usually also associated with increased
parameters are indications perhaps of bearing failures and cones locking. It is advised to
use spread sheets to track bit life accurately throughout the run to avoid any potential of
failed bearings and the associated dangers.
The annotated example following shows a real life example when 3 cones were lost from a
bit and despite many warning signs, no remedial actions were taken.
A common question asked is how long can I run this bit? Field run data should support bit
reliability; if not available, proceed as follows.
To go beyond a simple hours based answer we can use a combination of hours, WOB and
RPM to produce a more accurate measure of bearing life used. These measures can be
defined:
Total Energy considers WOB and RPM as well as hours showing how much work the bit
has done over the course of the run. This gives a far more accurate idea of bearing life
expended than hours on bottom does because it considers WOB and RPM, however
variations in application, bits formations and drive types do mean that usually some form
of local calibration is necessary to give really accurate numbers using total energy.
( )
=
Work Rate is best utilised as a real time calculation- this is a measure of the amount of
energy being expended by the bit at a particular WOB and RPM (Work rate shows how
hard the bit is run). Increasing WOB or RPM will increase Work Rate, decrease WOB or
RPM will decrease Work Rate. Work rate will affect the Rollercone bit life as it is an
indicator on how hard bit is run, the higher the WR to faster Total Energy consumption
will be. If bits are run above certain WR thresholds, bit life will usually be severely limited.
( )
=
Krevs (total bit revs) is perhaps the most frequently used method of evaluating bit life. It
is often considered less accurate than Total Energy as it does not consider what weight is
on the bit. However in highly deviated wells where surface weight cannot always be fully
transmitted to the bit Krevs is often used as Total Energy figures cannot be trusted.
= ( 0.06)
When calculating TE during an actual bit run one must consider an average WOB during
the life of the run. TE values must be carefully considered when in high angle and
horizontal applications when not all WOB (as recorded at surface) is fully transmitted to
the bit.
6.9.3 Reaming
Reaming long sections of undergauged hole is not recommended, but has been
accomplished successfully with varying degrees of damage to the bit.
If reaming is absolutely necessary, observe the following guidelines:
Without a Mud Motor:
Ream with full flow
Use 40 to 60 RPM and 2,000 to 4,000 lbs. weight on bit
Ream slowly and avoid high torque
Generally recommended mud motor speeds have been 120+RPM. Recent testing in
vertical applications has suggested that in 30fph or slower drilling applications a slower
speed motor will increase ROP and reduce damage to the bit.
Critical: The instantaneous ROP (in ft/hr) must be limited to no more than 2.5 times the
RPM to ensure a gauge hole is drilled. For example, when running at 100 RPM, do not drill
faster than 250 ft/hr. Drilling faster than this will lead to a spiraled hole condition
(screwing the bit in the ground).
Note: A high percentage of the runs this data was extracted from utilized performance
motors, which were in the 30 ft range. The more successful runs placed the stabilizer 40
to 60 ft from the bit, used a 1.75 or grater bent housing motor and a minimum motor
speed of 120 RPM (Source NOV).
The first four of these are objective measurements which can be obtained by reference to
the standard daily reports. The condition however is a very subjective assessment made
by the driller or directional driller. In order to provide a measure of consistency between
bit condition reports made by all drillers (world wide) a grading system has been
introduced. This system applies to roller cone bits, diamond bits and core heads. It uses
code characters for describing six categories of wear, grouped into the three sections
cutters, bearings and gauge, and adds two codes for remarks.
If a standard bit report form is being completed there are eight boxes in which the
individual codes are entered (see table below).
More information about dull grading can be found in the attachments. (Reference: NOV)
All PDC cutters should be graded on the condition of the visible diamond table, regardless
of cutter shape or exposure.
Wear is recorded on a linear scale as a single digit from 0 to 8. Grading numbers increase
with the amount of wear with 0 equal to no wear, 4 is equal to 50% and 8 is no usable
cutting structure remaining.
For surface set bits the percentage of diamond /TSP wear is determined by comparing the
initial visible cutter height with the amount of visible cutter height remaining.
IADC wear can be measured using a IADC PDC wear gauge. These gauges will measure
several different cutter sizes. The example shown can be used on cutters with diameters
from 13 mm to 38mm.
Bi-center - the inner section is considered the entire pilot section. Degrees of cutter wear
on bi-centers are the same as for PDC bits
Impregnated bits - have Grit Hot-Pressed Inserts (GHI), which protrude out of the ribs on
a new bit. At the point
where the GHI wear is flush with the ribs, the bit should be graded a 1. Wear after that
point is measured the same as diamond bits
The code for the most prominent or primary characteristic of the dull bit should be
entered here. Any secondary dull characteristics of the bit can be entered in the chart in
box 7, Other Characteristic.
Use a letter code to indicate the location on the bit face where the major dull
characteristic occurred.
This box is for roller cone bits. Fixed cutter bits will always be designated "X".
It is used to record the condition of the bit gauge. It is based upon nominal ring gauge
(ensure that a PDC and not roller cone ring gauge is used as tolerances between the two
are different).
I is used if the bit is still in gauge.
Otherwise, the amount the bit is undergauge is recorded to the nearest 1/16th of an inch.
Next, measure the height of the longest reamer blade from the outer surface of the
shank. This can be accomplished by using a straight edge and a ruler. This step is
illustrated in next figure.
This space is used to record secondary bit wear. This could relate specifically to cutting
structure wear or may identify wear to the bit as a whole, such as erosion. This field is in
addition to the wear identified and recorded in box three and may highlight the "cause" of
this wear. "Other characteristics" can be used to record whether a bit is rerunable "RR" or
not "NR". The codes for both "major" and "secondary" wear are the same.
The inner and outer rows are graded using a 0-8 scale that measures the tooth height
remaining, as shown below. This includes removal of the tooth or insert for any reason,
including wear, breakage or loss.
1. Inner Rows
The inner rows include all of the cutting structure except those that are in contact with
the hole wall. This generally means everything except the gage row inserts.
2. Outer Row
This includes only the rows that cut gage and maintain a properly sized hole.
4. Location
This code indicates where on the bit the dull characteristic occurred. The location is
indicated as follows
5. Bearings
This code is used to indicate the condition of the bearings on roller-cone bits. For sealed
bearing bits, the options are:
E- Effective
F- Failed
N- Not able to grade
No other characters should be used with sealed bearing bits. However, it is preferable
when possible to indicate the condition of all three bearings separately. For instance,
when only the #2 bearing is failed and the others are effective, indicating EFE in the dull
grade is more descriptive than simply entering F.
6. Gauge.
This is a measure of how the diameter of the bit has changed during the run. Generally,
wear on the gage of the bit will eventually cause the bit to be slightly undersized. It is
also possible for the bit to be undersized due to being pinched (see PB dullgrade
characteristic in the next section). It is quite rare for a bit to be pulled after drilling and be
oversized.
The code shown indicates the amount that the bit is under-gage, in 1/16 increments. For
instance, a bit that is 3/16 under-gage would be listed as 3 in the dull grade.
To measure the gage of a bit, a standard nominal sized ring gage should be used. This
means that for 8-1/2 hole, the gage should be 8.5 in diameter.
For three-cone roller bits, gage should be measured as shown in the following
illustrations. Due to the fact that there are three points of contact, and neither are directly
opposite the other for a true diameter measurement, the actual gage of the bit is not
equal to the gap. The gap measurement should be multiplied by 2/3 to get the correct
measurement.
8. Reason Pulled
This final section of the dull grade is used to indicate the reason why the bit run was
terminated. This reason is not necessarily related to the performance of the bit and can
generally found on the bit record or on daily drilling reports. The possible reasons are
listed below.
Drill-Off Test #2
Pick off bottom and set the RPM and flow rate and evaluate operating parameters
Return to bottom, building to a low starting WOB
From this WOB, increase weight in a predetermined weight increment (typically
between 2000-5000 lbs). Record the time required to a suitable footage
increment. Footage increment typically ROP based (5+ feet for higher ROPs, 1-3
feet for lower ROPs)
Calculate and plot the resulting ROP versus WOB. At some point, the ROP may
drop off or decrease with increasing WOB. The optimum WOB is just below the
weight that caused a flattening of the ROP plot.
Repeat the test using the optimum WOB from step 2 and increase RPM in 5-20
RPM increments. Drill a convenient time or footage interval (1 minute or 1 foot)
Calculate and plot ROP versus RPM. At some point, increasing RPM will result in a
very small or no increase in ROP. The optimum RPM is just below the RPM that
caused a flatting of the ROP plot
Continue testing until the optimum is determined.
If the shortest time increment occurs at several different weights or rotary speeds,
use the lowest weight rotary combination
Drill-Off Test #3
Pick off bottom and set the RPM and flow rate and evaluate operating parameters
Return to bottom, build to the maximum or selected WOB
Lock the brake
Let the bit drill-off and record the WOB every minute or suitable time interval
Calculate and plot the resulting ROP versus WOB
Repeat the test and increase the RPM in 5 20 RPM increments. Continue testing
until the optimum is determined
If the shortest time increment occurs at several different weights or rotary speeds,
use the lowest weight rotary combination
Drill-Off Test #4
This test is mostly used when an approximate operating WOB is known.
This can be either per time interval or per footage interval.
This method is used in areas of high ROP where WOB drills off too fast to record or in
non-homogeneous formations where the ROP fluctuates greatly.
Pick off bottom and set the RPM and flow rate and evaluate operating parameters
Return to bottom, build to the maximum or selected WOB
Drill for a set time interval (typically 5 minutes) or a set footage interval (5 feet,
up to a kelly length) with constant WOB. Calculate the ROP for the interval
Repeat the test at other WOB values until the optimum WOB is found
Repeat the test and increase the RPM in 5 20 RPM increments. Continue testing
until the optimum is determined
If the shortest time increment occurs at several different weights or rotary speeds,
use the lowest weight rotary combination
Drill-Off Test #5
Also known as an active drill-off test
Select a mid-range WOB and RPM
Maintain RPM and record ROP over 5 minutes with varied WOB
Determine optimum WOB
Maintain WOB and record ROP over 5 minutes with varied RPM
Determine optimum ROP
The true WOB may be less than the measured weight by the amount of hydraulic lift
(pump-off force) acting beneath the bit. Hydraulic lift occurs with any type of bit that
develops pressure drop due to fluid flowing between the bit face and the rock. This force
is generally less with PDC bit than with natural diamond bits.
5. Record the indicated weight as the bit drills off. The data is usually recorded with
each 1000 lb decrease of indicated weight or at some regular time interval such as
5 minutes
6. End the test when it is clear that the indicated weight has stopped decreasing. The
weight indicator should give a direct reading of the pump-off force at this point.
Record this value
7. Raise the bit approximately 1 foot off bottom and check that the indicated weight
has returned to the original value. Discrepancies can arise from hole drag
Gage specifications, per API spec 7.7 for diamond and PDC bits
Go and No Go gages should be a ring fabricated from 1 steel with and OD
equal to nominal bit size plus 1-1/2
Go gage ID should equal nominal bit size plus 0.002 (0,051 mm) clearance with
a tolerance of +0.003, -0.0 (+0,076mm, -0mm)
No Go gage ID should equal minimum bit size (nominal less maximum negative
tolerance) minus 0.002 interference with a tolerance of +0.0, -0.003 (+0mm, -
0,076mm)
If acceptable the bit should enter the Go gage (bit not too large)
If acceptable the bit should NOT enter the No Go gage (bit not to small)
Both ring gages and the bit should be within 200F (110 C) of one another
Prepared by WEP
Author:
Verified:
2
10. Mud density should be minimum density at start of interval and should then be
slowly increased to maximum desired density near interval TD before POOH to run
casing
11. Make sure enough space between drilling tools( RSS pads, stabilizers etc.) and
hole to avoid annular restrictions
12. Avoid string/BHA vibrations and/or stick/slip by adjusting RPM and WOB (use
vibration monitoring devices whenever possible)
13. Consider roller reamers instead of stabilizers in hard formations only
14. Use bits with low vibration tendency
15. Install soft torque systems on rigs whenever possible to reduce string vibrations
16. Synchronize mud pumps
17. Avoid to build well trajectory with 40-70 degrees inclination through unstable
formations
18. Minimize check trips by drilling each section from shoe to next shoe depth
19. Ensure mud salinity is close to or the same as formation salinity to avoid hole
instability(osmotic phenomenon (break-out))
20. Use shale shakers only with correct screens to ensure maximum solids removal
(refer to API charts and cut points for optimum screen selection)
21. Use minimum ( slim) BHA when is possible less DCs combined with HWDP, less
stabilizers, (smaller size drilling tools)
22. The use of under reamers to enlarge the standard hole size is recommended to
avoid back reaming hole conditions
23. Back reaming is well known for destabilizing well bore conditions and poses a high
risk for potential stuck pipe. Back reaming is only recommended when other
methods to POOH are not successful
24. Pumping out of the hole is the preferred method using a minimum 50 75% of
drilling flow rate if hole conditions dictate
25. Consider using continuous circulating tool on critical wells as this tool permits
circulation whilst breaking or making up pipe connections
26. Use wellbore strengthening materials in WBM and SBM when drilling weak
formations (multi-fractured) .
27. WBM should always be used to drill down fault planes where formation breakdown
is expected and downhole losses are severe enough to make use of SBM
uneconomical
By applying most of these pointers, we can improve drilling performance when drilling
sensitive formations to avoid hole problems caused by either or a combination of
excessive flow rates, ECD values, high mud rheology, and high LGS. We can also avoid
annular restrictions caused by not having enough space between BHA and the hole, we
also avoid excessive string vibrations, and uneven pumping.
To initiate a kick off, at least 4-5 ton WOB must be applied. If this cannot be achieved the
flow rate must be reduced. After 4-5 inclination has been achieved, the WOB can be
reduced to 2 mT if required.
Keep pump rate moderate, typically 2000 2500 lpm. Only when kicking off just below
the conductor shoe, keep the flow rate to a minimum (max 2000 lpm). As soon as more
WOB can be applied, the flow rate can be increased. Project trajectory ahead to avoid
collision and to drill a smooth wellbore!
Drill ahead
Mud conditioning followed by a FIT
POOH for BHA change.
1. Drill the stand down. In soft formations do not drill off the WOB.
2. Work/Ream a minimum of one single; circulating cuttings above the BHA. More
reaming may be required depending on observed hole condition. The DSV
shall confirm reaming requirement every shift.
Example;
Minimum required reaming circulating time to get the majority of the cuttings above the
BHA;
Hole size: 17.5
Majority of BHA diameter: 9
Flowrate; 65 lps (3900lpm)
Annular velocity [m/min]: 34.2 m/min
Slip velocity: [m/min]: 0.1-1 m/min
Length BHA till HWDP [m]: 250 m/min
Note: The directional driller shall be notified before any reaming is carried out.
4. Begin collecting T&D data by stopping the pipe 5m above connection depth.
5. While pumping & rotating record:
Standpipe pressure.
ECD from the MWD display above the drillers console (when applicable).
Record rotating off bottom torque and string weight. (See below)
Stop rotary and pick up 5 meters at constant speed of 10 m/min, record up
weight. This will also release any trapped torque in the string.
Slack off at 10 m/min and record stabilized down weight. If tight hole (due
to cuttings), repeat same process until resistance is gone, but now with
pumps on and rotate and reciprocate.
6. Make sure the pipe is off-bottom. Weight indicator should display full string weight.
7. Stop the pumps and set the DP in the slips as low as possible. Bleed off residual
pressure from the standpipe manifold.
8. Break out Top drive, apply pipe dope to the saver sub pin, unlatch and clean
elevator, switch pipe handler to make-up mode.
9. Pick up a new stand. Stab in pipe at rotary, spin stand in with top drive, torque top
connection with pipe handler, and make up bottom connection with iron
roughneck.
10. Lift the pipe, remove the slips and break circulation slowly.
11. Start pumps slowly & pick up out of slips. Note: max surge occurs in first 15 sec,
so ramp up pumps slowly.
12. When out of the slips, bring pumps up to full strokes slowly. Start rotating once
returns established.
13. Take directional survey as per Directional Driller. MWD will advise the driller,
immediately the survey is satisfactorily received on surface. In the meantime the
driller can commence to work the pipe.
14. Directional driller will advise on commencement of drilling.
Note: When the pipe is in the open hole, always set the slips on a down stroke long
enough to insure that the pipe is actually moving down the hole when the slips are set to
ensure the pipe is free so to avoid becoming differential stuck.
If the actual results starts to diverge away from the predicted trends, than a hole-cleaning
problem may be developing. The combination of this data, and carefully monitored
cuttings, mud and drilling parameter data can then be used to optimize drilling ROP and
/or what remedial action is necessary.
To perform this operation in an adequate way, the T&D software model must be of a good
quality but also the way the readings are taken must be constant throughout the
operation using properly calibrated gauges. In order to make a proper T&D model the
following points must be considered:
The torque and drag simulation results should match with the measured values. Often the
error is caused by an incorrectly assumed weight of block, hook and top drive.
Example torque and drag simulation & actual data (road map)
3. With the measured hookload data a drag chart can be plotted to compare the
actual and predicted values. A good initial quality check is to ensure that the
measured and predicted curves for rotating-off-bottom weight are lined up. There
is no upward or downward drag when rotating off bottom, so the weight should be
independent of friction factor.
4. If there is a significant difference in predicted and measured rotating weights at
this stage, there are various sources of error that can be checked out:
Is the estimate of hoist equipment weight correct?
Have all of the drillstring components been entered correctly?
Is the mud density as expected, are the weights being recorded accurately?
5. Ensure that correct tool joint outer diameters are entered in the torque and drag
software. For a given side load and friction factor the friction torque is proportional
to the tool joint outer diameter.
6. Be aware that the hook load reduces when the flow rate increases due to the
'pump out' effect.
7. Friction factor values:
For non-complex wells an open hole/cased hole friction factor of 0.2 - 0.3 is a
good starting point.
Generally, SBM will lead to lower friction factors than WBM. Typically SBM
yields 0.2 and WBM 0.3. For this reason, it is essential that the offset and the
planned well have the same mud type when using calibrated friction factors.
In chalk sections with WBM high friction factors can be expected. It is common
to have a friction factor of 0.4-0.5 for the open hole.
If vibrations occur adjust RPM and see if this helps, if not call for help.
For hole cleaning purposes high surface RPMs are required (>120 rpm). In practice it is
found that at high rpms the rotation is much smoother than at lower RPM, this is due the
harmonics or natural frequencies of the drill string and BHA. All efforts should be done to
avoid rotating at these natural frequencies, as this will result in excessive and rotationally
destructive vibrations.
Drillers should be aware of the detection method of shock and vibrations and preferably a
traffic sign system should be used for the down hole measurements. Below a table is
given how to distinguish the different types of shocks and how to cure them.
Stick-slip not only affects the ROP but also has also big influence on the logging quality.
Therefore stick-slip should be kept to a minimum.
Some of the LWD tools are equipped with full gauge straight bladed stabilizers; these
stabilizers can have increased effect on the down hole shock and vibrations.
Notes: During repairs where the top drive is disconnected install an internal BOP and a
circulation head on the DP and establish circulation. If no circulation is possible the hole
must be circulated through the trip tank.
If it is not possible to pull the bit to remove plugged nozzles, circulation can be re-
established by perforating the drill pipe above the BHA.
If the cuttings are reported to be soft, ROP is slow, drilling torque is low or
reduced and there is an increase in the standpipe pressure, the chance that the
bit is balled up is high.
Reduction in ROP
The ROP may slow down gradually due to intermittent balling. Believing that the
formation is harder, increasing the WOB will in turn push the bit deeper into the
soft clay resulting in poor cleaning of the bit face causing the entire bit to ball up.
A balled bit can affect the force distribution, flow of cooling mud, leading to
accelerated wear and premature bit failure. ROP may return to normal after
cleaning but might be followed by another drop in ROP as the bit balls again.
Cleaning methods:
1. Spinning:
Position the bit as close as possible to the bottom of the hole or pick up the
string until the differential pressure diminishes.
Circulate at maximum rate for 15 mins.
Rotate the string at maximum RPM for 1 minute and reduce to drilling RPM for
1 minute varying the RPM maximizes the available centrifugal force to aid in
spin off soft sticky formation from the bit face. A cleaning pill will aid in the
cleaning the balled bit face.
Spinning the bit at high RPM and circulating a cleaning pill at maximum rate is
the most effective technique in cleaning balled bit.
2. Brine Pill
A saturated KCL brine pill (1.15 S.G.) can be spotted around and soak for 10-15
minutes or circulated through the bit. The high concentrations of KCL will have
dehydrating and dispersing effect on the clays sticking to the bit. The best use of
such pills is by initially soaking the bit/BHA in the pill followed by rapid rotation
and circulation to wash off the adhering clays.
3. Detergent Pill
Usually such a pill is made up from active mud with 5 - 10 % detergent added and
circulated straight through the bit, or the entire mud system can be treated with 2
- 3 % as a preventive measure.
Detergent pills can also be made up in brine, where the bit/BHA should be allowed
to soak in the pill. The detergent acts by reducing surface tension thus reducing
the sticking tendency of the clay. These pills can readily be viscosified and weighed
as required. The detergent may have other negative effects on the mud system
(i.e. foaming, polymer performance etc.).
6. Dispersant Pill
A highly concentrated dispersant pill using 35 kg/l of lignosulfonate with seawater
or brine can fully disperse balled up clays. Such a pill should be made with Caustic
Soda (or Lime/Soda Ash) to a high pH of 11. The best use of such pills is by
initially soaking the bit/BHA in the pill followed by rapid rotation and circulation to
wash off the adhering clays. This type of pill would not normally be used in a no
dispersed drilling fluid, as mixing it into the active mud can rapidly alter the mud
properties. The majority of polymer systems are run non-dispersed. Such pills can
create washouts in the wellbore.
Select Tool Face orientation 180 of the original TF when original drilled preferably
on the low side of the hole (TF 110 240)
Run in hole with a cement stinger and place a 100-meter cement plug as described in
cementing chapter of the manual.
If no positive indications of formation in the cuttings are seen, remain at 0.5 m/hr. If
indications of the start of a sidetrack are seen, the ROP can be increased with 0.3 m/h
each hour until the sidetrack is confirmed.
Calculate the slide distance required, drill the rest in rotary without picking up above the
kick off point.
Re-entry with a rotary steerable tool, run in sidetrack dry and set rotary steerable tool 1
meter above bottom.
Select the best place to set and to orient the whipstock so that the window is
opposite good cement and competent formation. Avoid casing connections.
Consider hole angle and radius of curvature (build, drop, left or right turn) in the
vicinity of casing exit.
Select proper whip face orientation methods ( MWD, gyro )
Consider length of sidetracking assembly, anticipated mill wear and sidetrack
section trajectory (dogleg, deviation, inclination) to determine the depth of rat hole
after milling window.
Note: The requirements stated above might implicate that additional logging (CBL) needs
to be performed to assess the quality of the cement bond and to determine the location of
the casing collars.
Hole Angle
Well bore inclination needs to be considered because sidetracking equipment will tend to
lie on the low side of the hole. On holes with more than two degrees of inclination at the
setting depth the whipstock should be oriented. It is best to orient the whipstock face
0 deg to 90 deg to the right or left of high side. It should not be set at an angle
greater than 105 degrees. This will prevent the top of the whip from falling towards the
centre of the well bore.
Hole angle plays an important role in any directional drilling operation. The same goes for
a milling operation. Ideally, one wants the milling assembly to be able to build away from
the whip face. Keeping the mill from extensively cutting the whip will mean that fewer
metal cuttings need to be removed from the hole and the life on the mill will be extended.
Orientation
Proper positioning of the whipstock assembly in highly deviated well bores is necessary
for successful milling of window and retrieval of the whipstock assembly. It is best to
place the window in a section of casing with least amount of dogleg severity. Orientation
of the whipstock face relative to high side depends on the radius of curvature (build, drop
and/or turn) near the casing window.
Subsequent BHAs
All of the well bore characteristics must be considered when designing and then
navigating the subsequent assemblies through the well bore, window and the open hole
after completing the sidetrack.
An acceptable milled window can be quantified as one that allows uninterrupted passage
of drilling and completion assemblies from the casing into the open hole and v/v.
The length of the rat hole should be sufficient to accommodate the drilling assembly to be
used in the lateral. If a full gauge drilling assembly is to be used it is important that the
window is opened up to full gauge. If a more flexible and under gage assembly is to be
used then having a large window is not as important.
Dogleg Severity
It is crucial to check the severity of all doglegs between the surface and the location of
the window. If the whipstock assembly hangs-up or becomes stuck in the hole above the
desired location, this can lead to serious problems. Check that all equipment can freely
pass through the borehole. In general, be very careful if severe doglegs exist in the hole.
A good guideline to follow is: doglegs greater than 7 deg/30m in the well bore require
checking with the equipment manufacturers for specifications and recommendations.
Equipment capabilities will vary based on diameter, length, and flexibility of the
components within the system.
Orientation Method
Proper positioning of the whipstock assembly in highly deviated well bores is necessary
for successful milling of the window and retrieval of the whipstock assembly. It is best to
place the window in a section of casing with least amount of dogleg severity. Orientation
of the whipstock face relative to high side depends on the radius of curvature (build, drop
and/or turn) near the casing window.
The whipstock assembly can be oriented to the proper direction for the sidetrack with
either a surface readout gyro or MWD system. Both systems are used by the industry in
sidetracking operations. The whipstock face is aligned to the orientation sub or MWD
collar as the sidetracking assembly is picked up.The gyro surveying tool is used in vertical
and angles wells and in magnetic interference environments.
The MWD system is used with multi-cycle bypass valve (MCBPV) in angled wells to survey
inclination and high side tool face for orienting the whipstock assembly.
Casing Conditions
The casing must be in good condition from the surface to the sidetrack depth. Casing in
poor condition can cause problems with tripping of milling and drilling assemblies,
orientation of the whipstock assembly and obtaining a secure setting of the
anchor/packer. Whipstock assembly movement during milling could result in a crooked or
lost window, preventing passage of a full gauge assembly into the open hole or being
unable to complete the well.
Formation
Formation logs such as Gamma Ray, Sonic, and drill bit records are useful in determining
the best location for the sidetrack based on drillability.
High compressive strength of certain formations may warrant a change in the location of
the window due to the probability of low penetration rates. Sidetracking in extremely hard
or highly consolidated formations can prove to be disastrous. Mills can wear very rapidly,
dictating multiple mill runs in order to achieve a good window and a limited length of rat
hole. This situation cannot always be avoided. When studying the bit records, it is
important to note what type of bit was used. How well a bit performed is a very good
indication of the drillability of the formation outside the casing.
In general, if the strength of the formation exceeds 30,000 psi, then getting the
sidetracking mill into the formation to produce a rat hole could be difficult.
When the formation is much harder than the cement surrounding the casing, the mill can
sometimes become trapped in this cement seam because it will follow the path of least
resistance. Once the mill is trapped in this position, it is very difficult to initiate a
sidetrack.
A mill designed to constantly push away from the whip along with a bottom hole assembly
that wants to build angle will greatly help this situation.
Setting Method
The whipstock assembly anchors are set either hydraulic or mechanical. The hydraulic
activated anchor may include packer elements to provide a casing to anchor seal. The
hydraulic method employs high pressure transmitted from the surface through the drill
string to the anchor to move the slips to the casing to prevent rotation or vertical
movement of the whipstock. The mechanical set anchor is set down on a bridge plug, fish
or cement plug. Weight releases the trigger and the slips will bite in the casing. Additional
weight is then set down to shear the bolt between the mill and the whipstock causing the
slips to set set firmly in the casing. Milling can then begin.
Mud Properties
Milling mud is not required for a successful sidetrack, but the drilling fluid must be in good
condition, clean and compatible with formation surrounding the milled window. Drill pipe
filters screens and suction pit screens should be used to remove all forms of swarf and
debris. It is essential to circulate the well clean prior to drilling ahead to ensure that the
fluid is the hole is in good condition. Any debris that enters the drill string can cause
problems for the sidetracking systems, especially on MWD systems.
Exiting:
1. Always be aware of Whipstock Bottom, Top, and face orientation.
2. Always exit very slowly, watching weight indicator closely.
3. With directional or Bent BHA, always orient bit towards window opening before
reaching Bottom of Whipstock.
4. If difficulty with exiting your window occurs, contact Whipstock supplier / Milling &
fishing specialist.
DO NOT:
1. Rotate stabilizers or bit across the Whipstock face.
2. Set weight down on the Whipstock and attempt to rotate.
3. Torque up on the Whipstock
Perform a full bore and scraper run. It is recommended that this be done with the
following assembly: The mills and stabilisers would be sized to suit the casing drift.
Note: It is strongly recommended that if possible the scraper be run past setting depth,
by 50 ft, then pulled back and circulation commenced. This is to ensure any debris is
pushed below the setting depth and not circulated back up past the scraper.
The TrackmasterPlus can be set at any depth. It is set hydraulically therefore there is no
requirement to interact with a cement or bridge plug to initiate the setting of the
Whipstock. As with any Whipstock sidetrack the TrackmasterPlus system should be set
between 2 casing collars.
This is to ensure integrity between the anchoring packer and the milling and the drilling
assemblies. Casing coupling positions may be pre-verified using a CCL or from the casing
tally (if this is sufficiently accurate). Should a CCL be used, correlation between drill pipe
and wire line depth will be necessary.
Preparation
Check with the rig that ditch magnets have been installed. This will protect the
pumps from re-circulated cuttings.
Measure all component parts of the bottom hole assembly
Prepare whipstock assembly as per Smith procedure.
Test the MWD and Multi cycle By-Pass valve as per Smith procedure.
Note: If there is a problem with the signal or the pulse is interfering with the MCBPV it
may be necessary to run in the hole a further 5 to 10 stands to achieve a dampening
effect from the hydrostatic that will allow the tools to function. Normally the same flow
used for the MWD reading is sufficient for indexing the valve. As an example a cycling
rate expected with seawater would be 1100 lpm with 1 1/8" nozzle. One mud pump is
easiest and quickest for cycling valve. Switch pump off and when pressure is at zero,
bring pumps back on steadily to the previously recorded flow rate. Repeat until the fifth
cycle, remembering the valve starts in cycle 2. Ensure the driller notes the trend of pump
volume versus pressure.
Safety note: Ensure the driller is aware that when the by-pass valve closes he
will be pumping against a closed system with a small volume and the pressure
will rise very rapidly.
1. Pick up the Trackmaster Mill and Running Tool horizontally to the drill floor using
the crane.
2. Install a lifting cap in the 6 5/8 Reg Box of the running tool.
3. Connect the tugger to the lifting cap and pick up while lowering on the crane. Once
in vertical position supported by the tugger remove the transit cover from the mill.
4. Check that there is a blank plug in the hydraulic connect. This will stop any ingress
of mud when lowered through rotary.
5. Run assembly through the rotary and secure with slips and dog collar.
6. Pick up the previously stood back assembly and make up the Kelly valve chain
tong tight. Pick up and torque up fully, the connection between the running tool
and the mill. Hold the assembly back, clear of the rotary.
Note: Do not sit the assembly down on the deck as the knock off plugs are exposed and
may be damaged.
Note: For ease of fitting, the hydraulic hose may be fitted to the mill head while
suspended in the blocks, just prior to mating with the Whipstock face.
15. Remove the false rotary table and scribe a line from the Whipstock face to the top
of the running tool.
16. Run the assembly down and set the running tool in the rotary and secure with slips
and a dog collar.
17. Back out the Kelly valve, with it still closed, and stand the assembly to the side.
The valve can be opened at this point to allow any residual fluid to drain from the
string.
18. Fill up the whip, mill and running tool with clean base oil or water, depending on
well fluid.
19. Check the MWD for the offset correction and record this information. Run in the
hole with the rest of assembly.
20. Make up the remainder of the BHA and run in the hole under controlled conditions,
2-3 minutes per stand. Watch the weight indicator carefully and record up-weights
regularly. Monitor the trip-tank for the correct fill up. Extra caution should be
observed when at the BOPs and casing cross-overs etc.
Note: Ensure that when the string is being set in, or picked up out of, the slips that
there are no sudden shocks to the system. Continual shocking can weaken the
shear bolt in the system.
To mitigate the risk of the pipe slipping through the slips, the following is recommended:
a safety clamp should be used until ~ 25 T of assembly & pipe have been run
Slips Dies should be checked on a regular basis and cleaned as necessary
The backside of the slips and the I.D. of the Rotary Bowls should also be doped on
a regular basis.
Note: If no scraper run was performed and there is any doubt about the condition of the
mud or the cleanliness of the hole e.g. if it is thought that scale, settled barite or drilled
solids may be present, then consideration should be given to including a Float Valve in the
above assembly. This will ensure that there is no ingress of debris from the hole to the
string which could potentially pack-off the MCBPV and prevent the setting of the anchor.
The valve should be positioned between the MWD Valve and the MCBPV. If the valve is
installed then the string will have to top filled on the trip in the hole. This should be done
using a casing fill up line or similar the top drive should not be connected and circulation
should not be broken whilst RIH
1. At the required setting depth record the up and down weights and mark pipe for
the required setting depth.
2. Run the string 3-5 m down past the mark and then come back up to the mark.
3. Break circulation slowly, less than 10 spm, and once returns have been recorded
increase the flow rate steadily to activate the MWD. Keep the pumps running
during the orientation process to obtain continuous tool face readings and to avoid
unnecessarily cycling of the valve. This is not essential but it will save the cycles of
the valve should they be required in case of an unforeseen event.
4. Obtain a reading and record the direction of whip face. To achieve the desired
orientation turn the string as required and then work the torque through the
string, by first slacking off then picking up. Work the string up and down as
required to ensure the torque is transmitted to the Whipstock and then re-survey.
Patience is required at this time.
5. When whip is at required orientation, slack the string down past the setting depth
mark and then pick back up to it.
6. Cycle the pumps off and on and re-check the orientation. If it is okay continue to
index MCBPV to the closed position.
Note: High pressures may be experienced during the setting sequence. All
personnel must be made aware and all necessary precautions taken.
7. When the valve has closed switch off the pumps and allow pressure to settle, then
slowly pressure up to 240 bar. Hold and maintain this pressure while going
through the setting and shearing procedures.
8. Slack off to 10 12 T below previous down weight, then pick up to 10 12 T over
up weight.
9. Continue to pick up and shear off of the whip. If the bolt has not sheared off after
its rated value of 35 T plus 50%, then work the string by slacking off and picking
up several times to fatigue and weaken the bolt.
10. As soon as mill has sheared from whip, monitor for the pressure drop as the
hydraulic hose ruptures, and once observed bring the pumps back on and maintain
a circulating flow rate giving a pressure of around 140 bar +/-. This will stop
MCBPV opening and having to re-index through its six cycles to close it for milling.
This will be achieved with a minimal flow rate as the only means of circulating at
this point is through the ruptured hose
11. Pick up 3 m and then come down with 80-100 Rpm and observe the knock off
plugs breaking as the whip top is contacted. The pumps can now be increased to
the milling flow rate. Record the contact depth as the top of Whipstock.
12. Pick back up 3 m and record all the string parameters at the milling flow rates.
Start Milling
Mill through the window and then drill a rathole, usually 15 to 20 ft beyond the end of
whipface although this can be varied depending on individual requirements
Note: When the mill reaches the end of the whip face the quality of the cement/formation
must be assessed. If the ROP in the formation is unusually high i.e. greater than 7 m/hr,
then milling and washing should be kept to a minimum in case the formation in the
window area is washed out or made unstable.
Milling Completed
Check the passage of the mills through the window with different parameters, recording
any drag and torque observed.
Rotating with pumps on.
No rotation with pumps on.
No rotation and no pumps on.
Circulate bottoms up with the mill above the window then pull out of the hole. A
Formation Integrity Test, if required, can be performed prior to pulling out of the hole.
Factors affecting the mill wear such as formation type and the length of rat hole drilled
should be taken into consideration
Drilling Assembly
Make up drilling assembly and run in the hole. Take care at all times when passing
through window with any bottom hole assembly.
Bent housing motors may require to be orientated in order to allow them to pass
the window without hindrance.
If it can be avoided, drill bits and stabilisers should not be rotated down whip face.
PDC Drill bits should not be rotated down the whip face if it can be avoided
For information
Various steerable drilling systems have been used, without problems, in conjunction with
our Whipstock systems. It has been observed that very occasionally a drilling assembly
requires to be orientated to allow the drilling assembly to pass the whip face.
8 Drilling fluids
Prepared by WEP
Author:
Verified:
8 Drilling fluids
The correct selection and maintenance of drilling fluids is a critical element in the Petrom
drilling operations. The drilling fluid main purposes are to maintain overbalance and to
give maximum hole cleaning and ROP performance.
The table below summarizes the different functions of drilling fluid and how these
functions can be optimized.
# Function Effective Control
a) Determine pump rates by hole cleaning requirements whilst
preventing discharge of mud across shale shakers.
Removal of b) Raise by adding viscosifiers e.g. bentonite or CMC HV.
1
cuttings c) Lower by dilution or adding dispersants, eg. CFL
d) Reduce PV by removing solids.
e) Viscous slugs (cleaning pills) may be circulated in top hole.
a) Raise mud weight by adding weighting materials never by
using drilled solids
b) Lower by dilution and effective use of solids removal
2 Pressure control
equipment.
c) Centrifuge to remove low gravity solids or barites.
d) Constant monitoring of all mud tank levels.
a) Lower by adding bentonite, stabilise etc.
b) For surface hole utilise the plastering effect of bentonite, or
soltex (air blown asphalt).
c) Maintain density by adding weighting materials or removal
of solids.
3 Wellbore stability
d) Solids removal or dilution.
e) Establish optimal mud weight. Increase mud weight
depending on geological conditions.
f) Observe returns and tank levels, and monitor drill speed
logs, torque etc.
a) Facilitate cementing operation by assuring proper
Cementing and displacement of drilling fluids and by using low rheology
mud, prior cementing.
4 wireline
b) Assure retrieval of correct reservoir and geological data.
operations
c) Facilitate wireline operations by having optimum (low)
rheology.
Suspend cuttings
Use viscosifier/ disperser to maintain properties, to avoid
5 and weighting
barite/solids sag and to reduce swab and surge pressures.
material
Hydraulic energy
Establish appropriate rheological parameters to ensure proper
6 transmission to
flow rate for directional tools and bit.
BHA
Cool and
a) Use flow rate as per bit company recommendations.
7 lubricate the bit
b) Mud cake should be thin and tough.
and drillpipe
a) Control by good use of solids control equipment/ addition of
Prevent dilution.
8 formation b) Use of non-damaging products (e.g. calcium carbonate).
damage c) Lower by adding additive or sized bridging agents.
d) Proper mud selection with respect to formation damage.
9 Environmental Use of environmental friendly products
Impact
Person
Tasks Person to Check
Responsible
Prepare and maintain the drilling
Mud Engineer Drilling Supervisor
fluid properties as per job program
Conduct routine mud testing,
Mud Engineer Drilling Supervisor
monitoring and reporting
Ensure that rig personnel adhere
to the safe handling procedures for Driller, Asst Driller Drilling Supervisor
chemicals and equipment
Perform quality control checks of
drilling fluid, base oil & bulk Mud Engineer Drilling Supervisor
chemicals
Maintain inventory of all drilling
Mud Engineer Drilling Supervisor
fluid chemicals and additives
Ensure that HSE requirements are
Mud Engineer Drilling Supervisor
complied with on site
Prepare daily mud reports Mud engineer Drilling Supervisor
Ensure that solids control
Solids control
equipment are run efficiently and Drilling Supervisor
engineer
when needed
8.2 HSE
It is important that drilling fluids are mixed correctly and safely. A pre-job toolbox
meeting shall be performed before any fluid mixing operation. The following points shall
be covered in the meeting:
The job procedure and responsibilities for the personnel involved in the operation.
Personnel have the correct Personal Protective Equipment (PPE) for the operation
as per MSDS of the chemicals used.
How discharges shall be handled in an environmentally friendly manner.
Health risks associated with chemical usage shall be discussed.
Availability of Eye wash stations and First Aid kits.
Appropriate signs shall be used for hazardous substances, stating risks and First
Aid treatment.
All chemicals shall have a Material Safety Data Sheet (MSDS).
MSDS shall be displayed in rig yard, close to the mixers/chemicals area.
The Drilling Supervisor shall as a matter of daily routine, discuss all mud
requirements/ treatments with the mud engineer.
Ensure that there are sufficient amounts of mud-treating chemicals and weighting
materials at the wellsite.
Ensure that there is adequate lost circulation material and cement at the wellsite.
Review mud testing requirements with the Mud engineer. Also verify that the mud
lab is adequate and equipment in good working condition.
Review mud sampling and weighting with rig personnel.
Review systems monitoring equipment and emergency shutdown systems with rig
crew, mudloggers and mud engineer.
Review piping and valves, pumps, all mud related equipment and tanks with all
relevant personnel.
Verify that data is available for system capacities and volumes.
Ensure that there is sufficient handling equipment for the anticipated mixing.
Where:
= density of mud [kg/l]
P = pressure drop in annulus between depth D and surface [bar]
D = true vertical depth [m]
ECD is used as a tool to ensure that formation fracture gradients are not exceeded
thereby reducing lost circulation and expensive non-productive rig time.
2. Add the material in stages. Stop after the desired concentration has been reached,
or when it is observed that the material cannot be held in suspension, or if it is
floating.
3. If a higher LCM content is desired, leave the pill to soak for a period of time and
then try adding more material.
4. All rigs shall have an LCM pill pit available and connected to the mud pumps for
wells where losses are expected.
Formulations and procedures that can be taken for the different types of losses are given
in appendix 2.
Solids control equipment is used to minimise the volume of mud required to drill an
interval by concentrating drilled solids in their discard.
The most important points of focus when we talk about solids control performance are:
What is the maximum flow rate going to be?
Do we have enough shaker units to handle that volume once screens have been
inserted into the shakers?
Good shaker management is based on having sufficient contingency in the event
that a shaker suddenly breaks down
Rule of thumb if you can drill with 2 shakers on a land rig and handle maximum
flow rates then make sure to install 3 shakers so you have that contingency. No
contingency means the rig operation will slow down as fewer shakers means the
ability to handle maximum flow rates is then reduced by 50% and it's unlikely the
hole can be cleaned properly if flow rates have to be reduced to allow fewer
shakers to cope with the flow rate until the damaged shaker is repaired and put
back online.
When you have the comfort factor that you have contingency you have the ability
also to not only cope with optimum flow rates but you can also run much finer
mesh screens and remove more solids by having an extra shaker for contingency.
You can also handle higher flow rates if needed.
The API D100 cut point tells you how much drill solids are removed in microns so
remaining drill solids below that micron cut size are allowed to pass through the
screen openings and back into the mud system, and consequently back into the
hole. This is why it's important to run the finest screen size as possible. This
ensures good optimum shaker screen performance however you still need to deal
with the smaller solids that bypass the shaker screens because they are too small.
(Always use API square mesh screens -DO NOT USE OBLONG MESH SCREENS
BECAUSE THEY ALLOW TOO MUCH SOLIDS TO PASS THROUGH THE LARGER
SCREEN OPENINGS. (2 SQUARES = 1 OBLONG)
Even the small particle drill solids that bypass shaker screens lead to serious hole
issues/problems if not dealt with properly. These particles must be arrested and
removed as early as possible and the only equipment on the rig to do this
effectively is the centrifuges. Make sure there are two centrifuges on the rig for
optimum efficiency and contingency. These small particles if not removed lead to
rapid build up of low gravity solids (LGS) and this can lead to high plastic viscosity
readings thus affecting not only the rheology but also the ECD.
The most efficient shakers on the market today are balanced elliptical motion
shakers such as the NOV Brandt VSM 300 which incorporates use of two screen
decks (Scalping plus Primary fine screen deck) and when drilling with SBM they
have an attachment secondary drying screen that can be connected at the front of
the primary deck to allow cuttings to have an extra surface area with retention
strip of silicone to slow down the movement of the cuttings just long enough for
them to shake of some of the mud. Mud recovered is put back into the mud
system so cost savings to be seen when these attachment screens are fitted.
There are other so called equivalent balanced elliptical motion shakers on the
market however be aware they do not have a scalping deck to deal specifically
with the larger sized cuttings. This means the single screen deck has to cope with
the full load of cuttings so screen wear will be an issue leading to frequent
repairing/changing of shaker screens.
Centrifuge Performance depends on the knowledge and skill of the operator so
ensure there is always a fully trained and experienced Solids Control Engineer on
all Petrom operated rigs. Solids Control Engineers know how much feed rate to use
to feed the centrifuge. They know what bowl and scroll speeds to use for any given
mud weight, and they know this is important to know to be able to process as mud
and solids efficiently and avoid having torque issues and plugged centrifuge bowls
as a result of not having sufficient knowledge and skills to deal with that issue.
Centrifuges must be run to control the level of LGS in the mud to ensure the level
of LGS meets Operators mud specifications. Centrifuge operating hours must be
highlighted in the daily mud report and the LGS values must also be highlighted in
the daily mud report as well. The mud report must always show the hours each
shaker has been running as well as show what size screens are being used. It is
the responsibility of the Drilling Supervisor and/or Wellsite Drilling Engineer to
make sure these values are reported before accepting the daily mud report. If not
reported give it back to the mud engineer and make sure he corrects the report
before sending.
Spud Mud
Can incorporate use of water, caustic and native clays from the formation or it can
incorporate use of water, caustic and bentonite, CMC or a chemical thinner.
Gel/CMC System
Uses a bentonite base for fluid loss control and viscosity and Carboxy-Methyl Cellulose
(CMC) is a technical grade polymer to aid in tighter control of fluid loss as well as boost
viscosity. CMC is a cheap alternative to using more expensive premium grade polymers.
Xanthan gum is also used to provide gels and yield point values. To reduce progressive
gels a chemical thinner can be used. This type of mud system comes under the category
of Dispersed Polymer mud system.
Application: For drilling shallow wells or surface intervals such as 26 and/or 17 hole
size however both bentonite and CMC polymer have temperature limitations and if
temperature limits are exceeded the mud system will quickly degrade. This system cannot
be inhibited properly with salt but it can be inhibited with gypsum. The type of clay in the
formation to be drilled is very important because if you drill a dispersive type of clay then
you must avoid using a dispersed mud system otherwise you can over disperse the clay
particles and convert the mud to toothpaste consistency!
Application: For drilling moderate to highly reactive clay formations successfully, through
use of chemical inhibitors to prevent clay swelling that can lead easily to stuck pipe
scenario.
Application: It has the same application as KCl Polymer system depending on the reactive
level of the formation being drilled. If we have evidence we can drill without having to use
PHPA then we can elect to use KCL Polymer Mud System. KCL actually provides sufficient
levels of inhibition and its cheap. It is also corrosive to drill pipe and pump parts as well
as downhole tools even when using filming agents and corrosion inhibitors especially if
steel is exposed to the mud for extended periods of time.
shale stabilizers so you have to be sure you can justify using this system over cheaper
options because this system is very expensive due to the high costs for glycol and shale
stabilizer products.
Application: KCL Glycol can be used when experiencing excessive over-pull when
attempting to pull pipe out of the hole. By adding glycol this will aid in additional inhibition
and also provide a good level of lubricity that will help make it easier to pull pipe out of
the hole. KCL Glycol was never designed to replace KCL/PHPA it was designed as an
alternative to using SBM for environmentally sensitive areas. Once it became clear that
glycol additions are limited to 3% by volume then this cannot compete with the 75% base
oil for example used in 75/25 oil water ratio SBM mud systems. Glycol is handy to add if
you have niggling issues with tight hole.
Application: Sodium Chloride is used to saturate the mud so you have a stable drilling
fluid for drilling large sequences of salt or drilling through salt domes for example. This
system is based on the Non-Dispersed, Low Solids Polymer Mud System which uses
premium grade polyanionic cellulose (PAC), thats designed to handle high levels of salt or
calcium ions to enable you to have good rheological mud properties. Xanthan gum is also
used. All the products are generic in the industry however mud companies choose
different brand names for their products so its important to know if the products being
offered are of technical or premium grade. This is important to help decide whether or not
you can get away with using the most economic option.
Technically graded products have a shorter life than premium graded products so you
have to consider the length of time the mud will be left in the open hole particularly if
there is a strong presence of highly reactive, water sensitive shales present in the
formation. The more reactive the formation, the higher the level of inhibition you need.
The more salt you add you will see less efficiency from mud properties if using technically
graded products. The purer the products are, then the longer mud properties remain
stable before requiring additions of product for maintenance. If we know we will drill
highly reactive shale intervals where we intend using high levels of salt for inhibition
purposes then we should specify that mud should be built using pure grade PAC polymers
as well as XCD polymer which is specifically designed to yield quickly in a high salt
content drilling fluid. If we are drilling only moderate levels of water sensitive clay where
a small amount of salt inhibition is required then we should specify that we require a
technical grade PAC. PAC is the generic industry name for Polyanionic Polymer. The mud
companies will provide either technical or premium grade products if you indicate clearly
what you want. Technical grade products are cheaper than premium grade products. Its
important to know the application first before deciding which product to use.
Application: The technical limit of this system is that it cant be used to drill highly
reactive shale formations. Moderate reactive clay formations yes but highly reactive
formations-NO. If you know you will drill highly reactive formations then go with one of
the KCL polymer options instead. Moderately reactive means equivalent clay content or
MBI value up to 40 kg/m3, so if you know the formation will yield much greater than 40
kg/m3 equivalent clay content then you should select to drill with one of the KCL Polymer
options since potassium ions provide much higher levels of inhibition when drilling large
sections of highly reactive shales. This Gypsum Polymer system can be used on all hole
intervals, providing there are no large sections of highly reactive shales present, so its
not limited to hole diameter. It is a very suitable and economical alternative to Sodium
Chloride or Potassium Chloride mud systems so no need to use corrosion inhibitors and
filming agents. This means no risk either to washing out the drill string due to erosion
from the effects of lengthy exposure to salt inhibited drilling fluids. Ideal for use on
shallow wells similar to our Oprisenesti and/or Independenta wells.
NADF
Non diesel based, ultra clean paraffin based mud. This system has gone through
enormous evolution since diesel based mud came into use extensively in the North Sea
UK and Norwegian sectors during the 1970s. The evolutionary changes have been HSE
driven in order to come up with an acceptable low toxic/low aromatic base oil fluid that
has minimum impact on our environment and our health.
Application: The main application for using NADF is on our deeper wells beyond 2500m
where there is a long history of stuck pipe scenario due to well-bore stability issues.
By avoiding stuck pipe scenario you avoid the additional time and associated costs trying
to free stuck pipe where you can end up having to cement and side-track if unsuccessful
in freeing the stuck pipe. Drilling these high risk wells with water base mud (WBM) is not
recommended and should therefore be avoided.
This is where NADF is justified because this most certainly reduces the risk of getting
stuck in the hole. Its not just rig time and associated costs that get incurred whenever
we have a stuck pipe scenario. We also risk losing the entire bottom hole assembly which
can be enormously expensive to replace.
Other applications and advantages are that the mud filtrate going into the formation is
100% oil content so no risk of water sensitive clays imbibing free water from the mud
which is always the case when drilling with water base mud systems. This means no
water loss from the NADF filtrate to inter-act with formation clays so the risks of getting
stuck due to clay hydration is eliminated effectively just using NADF.
NADF also reduces the risk for water blocking of sensitive pore throats in the reservoir so
it can be an excellent drilling fluid for the reservoir interval as it can lead to higher levels
of production due to its non/damaging effect on the reservoir. Of course barite is always a
threat to reservoirs as it can plug up pore throats also however you can always use
graded calcium carbonate in place of barite if preferred but again this needs to be
indicated to the mud companies before the tender is issued or via a
statement/instruction/guideline in the mud tender documents.
Contaminants tend to become apparent more quickly with lightly treated muds such as
CMS / CMF muds rather than with more highly inhibited varieties.
Advance treatment to prevent contaminants affecting the mud can be made if, for
example, a complete geological prognosis is available or when drilling out cement.
Whenever the mud has been contaminated and a cure is required, careful pilot testing
should be carried out before treating the complete mud system.
Sources of Carbonates
CO2 from drilled formations or air ingress.
Thermal degradation of organic additives.
Over treatment with Soda Ash or Sodium Bicarbonate.
Carbonate formations.
Treatment
1. Increase pH to 9.5 - 10.0 with Caustic.
2. Add Lime at concentration shown in table.
3. If the required quantity of Lime exceeds 1.4 kg/m3, treat with Gypsum at
concentration shown in table.
4. Whilst treating with Gypsum, continue to add Caustic to maintain pH in 9.5 - 10
range.
5. When adding Lime or Gypsum, the mud will become very viscous if large
treatments are made.
6. Treatments should be made through a chemical barrel and must not exceed 1.4
kg/m3 over a 6 hour treatment period.
7. In areas where Carbonate contamination is known to be a problem, the pH should
be maintained with Caustic and Lime in the ratio 2 cans Caustic to 1 sack Lime.
Sources of Contamination
The main source of this contamination is the drilling of green cement or poor placement
procedures.
Diagnosis
Treatment
1. Prior to drilling cement, pre-treat the mud with 0.7 kg/m3 of Sodium Bicarbonate
and 0.7 KG/M3 of Citric Acid. If this is insufficient, treat cement contamination at
the rate of 0.43 kg/m3 Sodium Bicarbonate per 100 ppm Calcium (determine
Calcium using procedure below).
2. If Sodium Bicarbonate treatment levels are based on filtrate Calcium only, an
incorrect treatment level will be obtained. This is because the majority of the
cement will stay in suspension rather than go into solution due to the high pH. To
obtain the total Calcium level, the following procedure should be adopted:
Add 10 cm3 mud to 90 cm3 distilled water.
Titrate with 0.1N H2SO4 to a pH of 7.5 - 8.0.
Continue mixing for 2 mins to ensure no pH rise.
Filter the slurry on the standard filter press.
Titrate 10 cm3 of filtrate with standard Versenate (0.01 molar).
Calcium = ml Versenate x 4000.
3. The calcium level should be maintained below 400 mg/l. The high ph should be
reduced to below 10 by calculated addition of sodium bicarbonate and citric acid.
4. When large quantities of cement are drilled, it may not be practical to treat out the
contamination due to the large concentrations of Bicarbonate required. In this
case, the best course of action may be to change out the contaminated mud for
new mud.
App. 2.3 Hardness
Cause & Effects
1. Hardness in water is due to dissolved Calcium and Magnesium ions.
2. High levels of hardness will result in flocculation of Bentonite with associated
severe increase in viscosity. Subsequently, as the cation exchange process
continues, the clay particles will aggregate and the result will be a low viscosity
fluid.
3. The main effect of hardness on polymer fluids is precipitation of polymers at high
pH, in which viscosity may decrease and fluid loss increase.
Diagnosis
Calcium and Total Hardness tests should be used.
Treatment
1. Increase the pH to 10.5 with Caustic to precipitate out Magnesium as Magnesium
Hydroxide.
2. Treat Calcium with Soda Ash at 0.26 kg/m3 per 100 ppm Calcium.
3. Cement mix water must be checked and treated for hardness before use.
H2S will cause no adverse effects to the mud. However the gas is highly poisonous and
corrosive.
Increase Duratone HT
Concentration in the
system
The amount of LCM that can be added to a mud depends very much on the mud
properties. High gels and YP will help keep the material in suspension. Since LCM is
generally of low gradient, excess material tends to float on top if too much is added.
The following procedure may prove useful for mixing LCM pills and avoiding the problem
of flotation.
Ensure the pill has enough viscosity to keep the low gradient material in
suspension before addition of LCM. Add appropriate viscosifier if required.
Add the material in stages e.g. 14-28-42-56-70-84-98-112 kg/m3.
Stop after desired concentration has been reached, or when it is observed that the
material cannot be held in suspension.
If a higher LCM content is desired, leave the pill to soak for a period of time and
then try adding more material.
Loss Rate < 2 m3/hr Loss Rate 2 - 3.5 m3/hr Loss Rate 3.5 - 7 m3/hr
Size Concentration Size Concentration Size Concentration
50 micron Add to circ. 50 micron 43 kg/m3 50 micron 43 kg/m3
system at 4-5 150 micron 43 kg/m3 150 micron 43 kg/m3
x 25 kg 600 micron 43 kg/m3
sacks/hr
Bentonite/Cement/Synthetic Gel/Drillwater # 1
10bbl batch 13.7 kPa/m 10 bbl batch 19.3 kPa
7.2bbl Synthetic Oil 5.9 bbl Drillwater
1,600 lbs Bentonite 10 lbs Caustic Soda
1316 lbs cement 5 lbs Q-Broxin II
LCM if required 16.5 lbs Caustic Soda
Barite for density 1625 lbs Geltone II
3000 lbs Barite
App. 3.4 Formulation & Procedure for Barite Plugs, Synthetic Mud
(1m3)
1. Start with 450 l of Ester base oil
2. Add 3 l of water
3. Add 1.5 l of surfactant eg. Drillfoam S-55
4. Add 3 l of Drilltreat oil wetting agent
5. Add 2300 kg of barite to reach a weight of about 26 kPa/m
6. Another 1 l/m of Drilltreat should be added to the pill just before pumping.
1. Purpose
To ensure that correct handling procedures of NADF are in place in accordance with the
following procedures:
Reporting procedures for NADF spills and/or discharges to the environment for
both onshore/offshore rigs
All rig personnel are wearing proper PPE
Operation of dump-valves and integrity test of mud pits.
Maintenance and monitoring of mud transfer hoses.
Procedures for loading, back loading and pit transferring of NADF and Base Oil
Procedures for displacing NADF in or out of the hole
Pre-circulation checks/procedures prior to using NADF
SBM shale shaker losses
Loading cutting skips.
2. Responsibilities
OIM/Rig Manager:
Integrity of mud circulating and storage tank system to be maintained to a
reliable, acceptable standard
Pre-circulation check/spot on charge pumps and mud circulating system is
correctly lined up for drilling commencement to begin
Dump valves -Ensure that all mud pit dump valves are closed, chained and
padlocked to retain all the NADF in the mud pits. All padlock keys must be retained
by rig manager and issued only once a cold work permit has been approved by him
NADF displacements in or out of hole - Hold pre-job meeting with all involved key
personnel prior to displacing NADF on the rig floor, and be present on the drill floor
during the displacement until NADF M has been safely displaced
Have a full knowledge of the NADF handling procedures and ensure that all rig
personnel are familiar with them.
Drillers:
Use all equipment and personnel necessary to avoid any loss of NADF
NADF/Seawater/Drill-water displacement: Notify mud engineer and derrickman at
least 1000 pump strokes ahead before spacer returns at surface
Ensure proper use of the mud-bucket and drill pipe wipers if available during every
pipe trip
Adjust flow-rates as necessary for the shale shakers to cope with the feed rate and
avoid pumping excessively to reduce the risk of losing mud over the shakers
Monitor floor crew behaviour and their awareness level of NADF handling
procedures. Ensure that they wear proper PPE
Assistant drillers:
Pre-circulation check- inspect line-up of mud system, to ensure that NADF flow is
correctly routed from suction pit to rig pump, as well as routed correctly from
shakers to active pit via solids control system
NADF losses over shakers Call driller to reduce flow rates to stem losses then
assist shaker hand to replace and/or clean screens as necessary
Mud vacuum units and/or liquid recovery pumps-Check at the beginning of the
tour the condition and instruct all floorman on their use accordingly
NADF displacement-Pump-man and Mud engineers to be in the shaker/mud pit
area (offshore/onshore rigs) Mud Cop to supervise accordingly until NADF fluid is
successfully displaced in or out of the hole
Maintain constant vigilance over all floorhand operations to reduce any possible
NADF losses
Monitor condition and operation of drainage system and also trip tank/mousehole
recovery tank etc
To be fully aware of the NADF handling procedures and adhere to wearing proper
PPE
Derrickman:
Integrity test of pits- conduct tests as written down in procedures
Pre-circulation - Check that pumps are lined up correctly and always inform Driller
and mud logging company accordingly on any mud pit activity so they are aware of
what is going on
Transfer of NADF from mud delivery truck to pit to mud engineer at the end of the
transfer. Agree on volume received together and report same respectively to your
supervisor
NADF displacement Obtain cold work permit for fluid transfer permit. Check that
all valves and gates are correctly aligned. Remain in pit room to assist Mud Cop
and mud engineer with pit allocation and be onhand to transfer NADF returns when
necessary to additional storage tanks.
To be fully aware of NADF handling procedures and wear proper PPE
Shaker man:
Pre-circulation check -Inform the driller that the shakers are ready to be used as
soon as they have been inspected by mud engineers that the correct size screens
have been installed
Shakers -Monitor the shakers continuously during circulation. And wash screens
with base oil gun to prevent blinding. Inform driller ASAP whenever mud flows too
much over the shakers so he can reduce flow rates if necessary
Centrifuges - Check centrifuges are running properly and look-out for any leaks
every 15/20 minutes. Initiate centrifuge shut down immediately if required to stop
leak, by communicating with mud engineer on duty as well as solids control
engineer on duty and inform the driller accordingly
Ensure the shakers work correctly and that the screens are in good condition. Any
mechanical problem with the shakers must be brought to the attention of the mud
engineer and rig mechanic for proper action to be carried out
Clean the shaker screens during every connection if needed using Greco spray gun
To be fully aware of NADF handling procedures and adhere to wearing proper PPE
Incident Report to be done by the Rig Manager (with input from mud cop/mud engineers
on duty) for land rig and OIM for offshore rig. Incident Report must be submitted to
Petrom rig supervisors who will then verify and approve the report before it is sent to
Petrom office. This report should be simple and highlight only the facts and what
measures have been taken to deal with the spill as well as identify and highlight the cause
for the incident to occur
Personal involved:
Derrickman to carry out the operation.
Tool pushers/and or Barge Engineer.
Mud Cop
Procedure:
Ensure all pits have been fully cleaned and test each pit for leaks as well as inspect
all transfer, mixing equalizing lines and valves to make sure they do not leak. If
they do leak, alert the mud engineer and also alert the rig manager so he can
implement corrective action right away in order to repair any leaks in the system
Inspect all dump valves and replace leaking valves with new seals accordingly
Close the dump valves and fill the pits to 30% of total operating volume with water
to test the valves even when new seals have been fitted to be 100% sure against
leaks
Allow 15 minutes for integrity testing of valves for any leaks
Measure tank levels accurately and monitor same for 15 minutes and if no leaks
the valve seals are definitely working
Note:
The Rig Superintendent should monitor steps 5 and 6, as he should retain the keys for
the padlocks and issue same only on a cold work permit basis. The Rig
Superintendent/OIM shall only issue the keys once a cold work permit request has been
submitted and approved once he is confident of the following:
He is convinced that there is no risk of any surface mud loss or pollution to the
environment
Offshore Rigs
o Monthly: Visual inspection of all hoses (Results of the inspection to be
recorded)
o Six Monthly: Pressure test hoses with water to 8 bar.
When a hose is in use, it will be monitored permanently to detect damage for
potential leaks or poor connections.
Any damage to transfer hoses should be rectified immediately. Should a hose
require attention, it should not be used until it has been repaired or replaced,
tested and approved first
Signs of wear and tear, such as kinks, crushed or flat areas or tears or holes
should be investigated immediately so a decision can be made to repair or replace
any damaged hose used for transferring NADF
Personnel required:
Mud Cop
o Co-ordinates personnel and communications.
o Ensures the correct line up of pumps and valves.
o Designates a responsible person to stand by at the fill manifold and visually
observes hoses during transfer (Radio contact mandatory)
Deck foreman/Mud Cop
o Inspect hoses and connections prior to start transfer.
Derrickman
o Check mud pit levels prior to start transfer and during transfer up to
completion of transfer and note all volumes transferred
o Monitor and record transfer flowrate
Mud engineer
o Monitor all transfer operations closely and assist mud cop and/or
Derrickman as required
If NADF/BASE OIL Transfer hoses or valves leak during transfer-Take immediate action to
stop leak as follows:
Stop pumps and close all valves
Notify mud cop/rig manager of cessation of pumping
Take corrective action to repair or replace hose or faulty valves
Personnel required:
Toolpusher:
o Remains on drill floor during the displacement.
o Ensures driller is fully briefed
Mud Cop/ Mud Engineer:
o Supervision in mud pit area near to the shakers
Assistant Driller/Derrickman:
o Under supervision of mud cop/mud engineer to ensure that the lines and
the valves are lined up correctly prior to starting up any pumps
Prior to displacement:
1. All personal involved to read and understand displacement procedures
2. Meeting to be held by Companyman and OIM/Rig Superintendent with all
personnel involved to discuss the following points and any others that may raised
at the meeting
Which tank is allocated for spacers to be mixed and pumped first (Provide
volume to be pumped in m3 and in pump strokes)
Which fluids will be pumped next and from which tanks in what order? Highlight
volume to be pumped in m3 and in pump strokes and make sure mud loggers
have a copy of the procedures, volumes etc
Any high-lights during displacement e.g. flow-check and who will be at the
shakers to monitor returns
Transfer procedures if NADF is transferred from rig pits to external storage pits
during displacement
3. Derrickman to obtain work permit and notify driller and mud cop of any changes in
pit volumes
4. An accurate volume calculation of the hole/casing and riser is mandatory prior to
start the displacement operations
5. All volume and stroke counters on rig floor and in the logging unit, if available to
be zeroed before starting the displacement
6. Mud pit preparation for brine, mud or seawater:
7. Pit to be emptied and cleaned in accordance with NADF handling procedures
making sure people wear proper PPE
8. Double check all valves and gates for leaks and proper alignment before starting
displacement operations and confirm to driller at the pre-displacement meeting
that everything has been checked and double checked with the mud cop. The mud
cop can then verify also that everything has been double checked at the meeting
before displacement commences so everyone receives proper assurance which is
important. This is a standard risk assessment task for NADF displacements /
transfers / mixing of NADF
Driller to monitor the stroke counter to follow the spacer carefully and notify the Mud
Engineer/Shaker-man and Derrickman 1000 strokes before returns are due to arrive at
the shakers
Pumping should be slowed down prior to and stop completely when the interface fluid
reaches the surface.
The used spacers and /or contaminated mud to be diverted to a separate pit or tank for
treatment or back-loading
After displacement:
The Rig Superintendent will together with the Mud Engineer determine when normal
operations can resume.
Return all valves and gates to their normal positions.
Inform all personnel that the operation is completed.
Derrick man to sign off work permit and returns same to OIM.
Prior to break circulation, the Assistant Driller should check that the following is lined up
correctly:
Drill floor standpipe manifold.
Mud pump discharge valves.
Mud pump suction valves.
Choke and kill manifold.
Shale shakers functioning and flow correctly diverted.
Cutting dump gutter and direct overboard from shakers blinded-off and isolated
All dump valves are locked closed
The Driller shall not start pumping until he has received confirmation from the Assistant
driller/Mud Cop that all above checks have been properly carried out
Shaker man:
Function test the wash down unit near the shakers.
Inform the driller as soon as mud returns arrive on surface.
Note 1: Mud engineer to advise shaker man what size screens to use for the displacement
and once the mud warms up and gets fully sheared in it will be possible to change to finer
screen sizes when optimum flow rates are achieved.
Note 2: Mud Engineer to be present near the shakers to monitor the break of circulation
Note 3: It must be made clear to the shaker man that if any losses occur over the
shakers, he has to inform the driller immediately. Driller must then slow down pump rate
and maintain lower pump rates to avoid further shaker losses, until it is established that it
is possible to increase flow rates again
Note 4: Check and record the mud weights and viscosity every 15 min and record results
on a tour report. This report should be kept in a safe area away from water splashes or
shaker spray guns
No mud conditioning equipment should be started up until good circulation has been
established and the mud engineer confirms that it is clear to do such thing
If, for any reason, the volumes of the mud measured are doubtful, the pumps should be
shut down immediately and the reason investigated
No transfer of mud from either one of the pits or the trip tank should take place until good
circulation has been established and the driller confirms that it is clear to do such thing.
The Assistant driller will assist by communicating with driller and derrickman.
Note: It should be made clear to all personnel on the rig location that if they see or feel
something is not right and are unsure about anything, they should contact the MUD COP
immediately NO MATTER how small the problem may appear to be. The Mud Cop is
present on the rig for a reason which is to ensure we do everything correctly to avoid
spills or discharges of NADF into the environment
At the start of the circulation with NADF losses across the shakers can easily occur
(cold mud).To limit these start-up losses, the Driller should work closely with the
Shaker hand and the Mud Engineer to control pump rates which will allow the
shakers to handle the flow
Mud Engineers and Shaker hands should also be ready to change screens or limit
the flow from the well to ensure that no fluid losses occur
In the event of mud losses across the shakers or through the solids control
equipment, the shaker hand shall:
o Inform the Driller and the Mud Cop/Mud Engineer immediately.
o Inform the Toolpusher.
o Adjust flow gates on shakers and/or clean the shaker screens with base oil
spray gun if this helps to correct the situation
o If still losing mud over the shakers reduce pump rates till the mud is fully
sheared-in where it is then possible to increase flow rates again
Back loading of cutting skips shall be organized by deck crew under supervision of
Barge Engineer
Any liquid on top of the cuttings in the skip shall be removed and special attention
shall be paid to the closing lids to avoid leaking skips during the transport over
the sea by crane and during the trip on deck of the supply vessel to the port
The weight of the cutting skips loaded with OBM cuttings will be carefully
measured with the hook-load indicator of the crane and shall not exceed 10 Ton
It is not allowed to fill the skips over 70% of their capacity to avoid spillage on
PUBLIC ROADS during transportation to waste site unless skips can be sealed tight
using bolt-down lids or fasteners
The skips shall not contain other disposable materials other than NADF cuttings to
avoid damage to disposal equipment
Only the new type of skip with the fixed lid is permitted to be used
Following information should be mentioned on inbound boat manifests:
o Serial no of the skip.
o Weight of the skip.
o Depth interval cuttings.
11. Deviation.
Deviation from these procedures is only possible after consulting with the Drilling
Contractors Office (Rig Manager) and PETROM Drilling Office concurrence.
Prepared by WEP
Author:
Verified:
Good hole cleaning means removal of sufficient solids from the wellbore to allow
reasonably unhindered passage of the drill string and casing.
5. Use the highest possible annular velocity thus flow rate to maintain good hole
cleaning. If soft & unconsolidated formations are to be penetrated, the flow rate
must be tuned to avoid excessive erosion or washouts.
6. If the optimum flow rate for drilling cannot be maintained due to pump problems,
reduce ROP while monitoring for any indications of cuttings loading while repairing
the pump. If cuttings build up, stop drilling, clean well while rotating /
reciprocating.
7. Use the highest possible surface RPM to enhance good hole cleaning.
8. Monitor hole cleaning indicators:
While drilling, monitor cutting returns at the shakers to assess hole
cleaning efficiency. Be aware of correct hole volume and lag time for
cuttings to travel to surface.
Monitor Torque and Drag trends (road mapping).
i. In extreme case, excessive overpull on connections indicates
cuttings build up, leading to becoming stuck or hole pack off.
ii. Erratic and increasing torque while drilling: often this is caused by
bit whirl / stick-slip, but may originate from poor holecleaning.
iii. Reduced overpull when pumping (pump-off force): when this
happens, you are an instant away from getting a complete pack-off
and stuck pipe. Stop drilling & clean the hole.
9. When encountering hole cleaning problems, pump sweep pills. On high angle
holes, if viscous pills do not appear to improve hole cleaning, use low vis pills
(combo tandem pill).
10. Verify any torque and drag change after sweeping the hole. If improved, consider
maintaining sweeps.
11. Keep sand and silt content of the mud as low as possible, typically sand < 1%.
Directional wells
1. Pay extra attention to hole cleaning for 35 to 60 hole sections (risk of
avalanching). Hole sections > 60 practices must be designed to move cuttings
over long stationary beds.
2. Pump at optimum flow rates, usually the highest.
3. Rotate pipe at recommended RPMs for the given hole size to prevent bed
formation and to help remove pre-existing beds.
4. Maintain the 6 rpm fann reading between 1.0 and 1.2 times the hole diameter in
inches.
5. Increase mud weight to correct wellbore stresses problems causing hole cleaning
problems.
6. Expect little help from viscous sweeps, unless they are accompanied by high flow
rates and pipe rotation and/or reciprocation.
7. Consider for drilling horizontal small-diameter holes in competent formation to use
low-viscosity mud to induce turbulent flow. Low-viscosity fluids enter a state of
turbulence at lower flow rates than viscous ones. Any cutting beds which form can
be eroded by turbulent flow.
7. Barite Sag. Evidence of Barite sag will be seen as uneven mud gradient measured
at the shakers. It is of the utmost importance to ensure that Yield Point and Gel
Strength are sufficiently high to suspend barite. Barite sag can be a particular
problem in deviated wells since the barite particles only have a very short distance
to fall before they form a bed on the low side of the hole. This bed tends to slump
down the hole thus promoting further barite sag.
The ROP determines directly the amount of cuttings to be removed from the annulus.
Consequently, ROP may have to be controlled for reasons of hole cleaning efficiency.
High instantaneous ROP should be avoided as this may load up the annulus with
cuttings.
The amount of clearance between the BHA and wellbore is extremely important
because in most cases cuttings beds are left in the hole. The trick is to have enough
annular clearance around the BHA to allow the upcoming BHA to pass over the
remaining cuttings bed without increasing the height of the bed. If the bed height
increases, cuttings build up around the BHA and the risk of pack-off increases and
stuck pipe incidents will occur.
Good tripping practices are required to stop cuttings building up to a height that can
cause the BHA to pack-off. A major factor is the speed at which the BHA is pulled out
of hole and the ability to recognize a build-up before it is too late.
The following input data are required to carry out complete analysis of hydraulics:
ROP
Total depth of hole section
Formation fracture gradient
Hole geometry
Hole angle
Drill string geometry
Mud gradient
Mud rheology
Lithology
Cuttings gradient
Cuttings size
Annular Mud Flow Rate is the PRIMARY HOLE CLEANING PARAMETER and every effort
should be made to maintain the programmed flow rate. The 17 1/2 and 12.1/4 hole
sizes are generally known as the most difficult with regards to hole cleaning since flow
rates (and consequently mud annular velocities) are relatively lower in these sections and
their deviation often increases towards horizontal. This is particularly the case on rigs with
reduced pump capacity. The annular Mud Flow Rate is dictated by three factors:
Table below gives rule of thumb optimum flow rates for different hole sizes:
Hole size Flow range Minimum flow rate
57 75 lps 50 lps (3000 lpm) with ROP at 20m/hr
17
(3400 4500 lpm)
16 53 70 lps 50 lps (3000 lpm) with ROP at 20m/hr
Note: The proposed flowrates are based on in gauge holes, if the hole is not in gauge be
alert!
The chart below shows the detailed decision-based hydraulics optimisation process.
If it is not possible to drill with the optimum parameters, implement procedures to cope
with the reduction in the hole cleaning efficiency. If this is not possible, stop drilling until
optimum parameters can be returned e.g. if one pump is down.
The instantaneous ROP shall be controlled to a level at which cuttings can be removed.
Pipe rotation
Pipe rotation is critical in cleaning the hole and therefore pipe rotation must be planned in
advanced. Factors affecting pipe rotation:
In general, to maximize hole cleaning rotate the pipe as fast as possible within the limits
of the downhole tools and surface equipment.
There are some differences in opinion on the mechanism that causes the improvement in
hole cleaning, but there is no doubt that it has a huge impact. The different theories are:
Mechanical agitation: at low rpms the drill pipe rolls up the walls and slides back
down. At a certain threshold rpm, the pipe breaks out of the cutting bed and will
rattle around the wellbore and mechanically agitates the cuttings.
Hydraulic action: The pipe rotation creates fluid movement in the bed and the whirl
moves pipe around the wall creating additional velocity at the sides. This velocity
causes frictional drag and lifts the cuttings to where the mud is moving (viscous
coupling concept).
The table below shows the recommended rule of thumb drill string rpm for different hole
sizes.
The minimum rpms are a realistic target and if the string is rotated faster e.g. to the high
end of the desirable RPMs, then other problems may be created like more equipment
failures.
The 6 RPM FANN viscometer reading should be at least 1.2 times the hole
diameter.
The Plastic viscosity (PV) and Yield Point (YP) relation should be as PV : YP = 1 : 2
Mud weight should be that ECDs are not exceeding the formation strength at the
shoe.
Recommended total volumes (low viscosity + high weighted pills) for pumping sweep pills
in deviated wells.
The principal behind these pills is that the Low Vis pill, which is in turbulent flow, agitates
and lifts cuttings from the low side of the hole. These cuttings drop through the Low Vis
pill into the High Vis pill, which is in laminar flow. Once into the High Vis pill the additional
viscosity in the pill helps to slow down the gravitation of the cuttings towards the low side
of the hole.
Notes:
1. The best results are achieved if the High Vis pill is WEIGHTED since the additional
weight provides additional buoyancy to the cuttings, which in itself slows the
gravitation of the cuttings to the low side of the hole.
2. These COMBO pills should be used with caution, however, since their over-use will
very quickly affect the rheology of the main mud system.
3. It is recommended to pump no more than 2 COMBO pills per day whilst drilling and
one prior to tripping.
4. Check reduction in the loss of hydrostatic head vs. overbalance for the lo-vis pill.
5. After the pills enter the annulus, then the pumps are not stopped until they come
back at the shakers i.e. no connection allowed when circulating bottoms up !
6. Prior to the return of the pills, the shale shaker header boxes should be cleaned
out since a false impression of the hole condition can be the result of the pills
picking up large quantities of cuttings as they pass through Dirty header boxes.
7. The COMBO pill should consist of a Low Viscosity mud pill followed by a High
Viscosity, High Weight pill in 50:50 ratio.
8. The weight of the heavy pill should be at least 0.25 S.G. heavier than the mud
weight in use, and together, the low and high weight pills should equal the mud
weight in use.
9. The use of low viscosity, turbulent flow pills are not recommended in weakly
consolidated formations as washout or hole collapse may occur.
10. Pumping pills can have a serious impact on the mud rheology and are sometimes
counter productive.
Use pills with common sense. Monitor shakers carefully for increased returns. If no
increase is seen do not continue to pump pills. This will result in unnecessary building of
mud volume and make mud properties variable around the system. Use standard high
viscosity pills for vertical wells, and wells deviated up to an angle of 45.
Types of pills
Commonly used types of pills and the function is described below:
High Viscosity Pill. Viscosifiers (e.g. polyvis, HEC, starch) are added and pumped
around the well, the usual volume being 3 to 6 m. A highly viscous pill will be
Low Viscosity Pill. The unweighted base fluid of the mud is often used for this pill.
The base fluid usually has a low viscosity and will therefore become turbulent at
lower flow rates. A low viscosity the pill will help to lift and remove a cuttings bed.
Use of a low viscosity pill alone may not be successful. It will not be able to carry
the cuttings up a vertical section of the hole or suspend the cuttings when the
pumps are stopped.
Weighted Pill. A weighted pill comprises of base fluid with additional weighting
material to create a pill weight 0.25 to 0.40 S.G. heavier than the mud. This type
of pill will aid hole cleaning by increasing the buoyancy of cuttings slightly. Heavier
mud also tends to be more viscous. This type of pill is usually used as part of a
tandem pill.
Tandem Pill (also called Combination pill). This consists of two pills, a low viscosity
pill followed by a weighted pill. The concept is that the low viscosity pill stirs up the
cuttings from the low side of the hole and the weighted pill sweeps them out of the
hole. The weighted pill is sometimes substituted for a viscous pill. Tandem pills can
be very effective at stirring up cuttings and should be used as a preventative
measure for hole cleaning problems. If the hole is full of cuttings and a tandem pill
is pumped, there is a chance the amount of cuttings stirred up can cause a pack-
off. If holecleaning problems are being encountered, initially use high circulation
rate, drill pipe rotation and reciprocation to clean the hole. After the hole has
apparently been cleaned up, then use a tandem pill for further cleaning.
For the 17 1/2 section where the hole angle is built-up, this can often involve substantial
sections of oriented drilling with a steerable system during which the drill string is not
rotated assuming a Rotary Steerable System is not used. As discussed previously pipe
rotation is an important factor in hole cleaning and the lack of pipe rotation combined with
barely adequate flow rates can result in sub-optimal hole cleaning during this hole
section.
In addition it has been well established that the most difficult holes to clean are in the
range 40 to 60 of inclination since cuttings beds are almost certain to form in this
range. These cuttings bed are particularly unstable and once formed they can slide down /
avalanche the hole and even cause stuck pipe or packing-off.
In the 12 1/4 hole the high inclination extended tangent section is drilled, predominantly
in rotary mode. Despite this pipe rotation however, hole cleaning problems still occur as a
result of the built-up of extensive cutting beds on the low side of the hole any time the
pumps / rotary are stopped and this combined with barely adequate flowrates can result
in sub-optimal hole cleaning during this hole section.
In the 8 1/2 and smaller hole sections the tangent section may be extended to TD or the
hole built up to become horizontal, which will be drilled predominantly in rotary mode. In
general, hole cleaning in these hole sections should not cause the same degree of
problems as the larger hole sizes since flow rate limitations generally do not apply in
these sections. However well specific criteria such as weak formations (need to modify the
mud rheology / flowrates) or substantial azimuth / inclination changes (oriented drilling
mode with no pipe rotation) may result in sub-optimal hole cleaning during this hole-
section. It should be realized that any mistake in these hole sections will more often than
not result in struck pipe!
The most common sticking mechanisms in these wells are hole packing off, becoming
mechanically stuck when tripping, or a combination of both.
Extended Reach Drilling hole cleaning is an issue which cannot be over emphasized since
it is often the deciding factor between the success or failure of the well. It is a historical
fact that most, if not all, struck pipe incidents on extended reach wells can be attributed
to POOR HOLE CLEANING. Hole cleaning in extended reach wells is complicated by such
factors as:
Extended length of the larger hole sections.
Mud pump limitations
High hole angles for extended lengths of hole.
Time the hole is left open.
All of these factors impose considerable demands on the rig equipment and personnel and
it requires careful management to ensure that shortcuts are not taken which could
jeopardize the well.
9.2 Tripping
It cannot be emphasized enough that prior to tripping out of the hole, circulation must be
continued until the return of cuttings has genuinely reduced to a stable, minimal level.
The table below gives rules of thumb for the minimum bottoms up circulations required
for different hole sizes and angles. It assume that the circulation is taking place at the
minimum string RPM and pumprate for achieving hole cleaning.
1. If a tight spot is encountered do not initially pull more than 15mt. Assume in
deviated wells all overpull exceeding 15 mt as hole cleaning related due to
cuttings bed build up. Always RIH until the BHA is clear of the obstruction -
typically 2 stands - and circulate either bottoms up or minimum of 30 minutes.
2. Always bring the pumps up slowly and watch for pack-offs. The best way to raise
the flow rate is in pre-determined steps once the circulating pressure has stabilised
for that step.
3. Pull up wet through the tight spot without rotation. If the tight spot has
disappeared, then it was caused by a cuttings pile that has now been moved up
the hole. Return to step 1 and circulate the cuttings out of the hole.
4. If the tight spot remains in the same place, then it is likely another mechanical
process (i.e key seating, ledge). If this is the case, ream through section and try to
eliminate the tight spot.
5. Pull up dry through the tight spot again without rotation to see if it has been
eliminated after reaming. If obstruction has been removed, continue with tripping
out.
6. If the resistance is still there after circulation, reaming can be considered. Back
reaming should be used as a last resort if a cuttings bed cannot be circulated out.
If back reaming due to cuttings bed is started, it very likely has to be continued
until hole inclination is < 30.
Back reaming is extremely hard on equipment, especially motors e.g. shocks and
vibrations. Back Reaming whilst POOH should only be undertaken if all else has failed
(i.e.: circulating clean under the tight spot has already been attempted).
7. Large volumes of settled cuttings or new cavings can be introduced to the hole
when back reaming. It is critical that this material is circulated out of the hole.
Reaming speed and circulation time should be adjusted if the returning cuttings'
volume rate is excessive.
8. If the rig is equipped with Soft Torque, do not use this while reaming as it may
disguise torque trends since the torque feedback system is used to reduce
torsional vibrations.
9. When washing in, with a motor in the BHA, rotate the whole drill string at low rpm.
3. Study offset well data to identify any unstable formations which have caused
problems in the past. These formations shall be highlighted in the Well
Programme.
4. Ensure that the mud formulation is designed to cope with gumbos and swelling
shales where they are indicated.
5. Offset well data shall be reviewed for incidents of key seating and any occurrences
shall be noted in the Drilling Programme.
6. Do not plan a stiff assembly to follow a flexible BHA without flagging in the Well
Programme that care must be taken when tripping in. This is particularly important
when, and after, running core barrels.
1. At the first signs of the drill string torque-ing up and trying to pack-off, the pump
rate must be reduced. This will reduce the risk of fraccing the formation should the
hole pack-off. Excessive pressure applied to a pack-off will seriously worsen the
situation as it compacts the cuttings and will form a solid, impermeable lump. If
the hole cleans up, return flow to the normal rate.
2. If the string packs off, immediately stop the pumps and bleed down the standpipe
pressure [not possible with a non-ported float valve]. When bleeding pressure
down from under a pack-off, control the rate so as not to "U" tube solids into the
drill string in case they plug off the string.
3. Leave low pressure (< 25 bar) trapped below the pack-off. This will act as an
indicator that the situation is improving should the pressure bleed off.
4. Holding a maximum of 25 bar on the standpipe and with the string hanging at its
free rotating weight, start cycling the drill string up to maximum make-up torque.
At this stage do not work the string up or down.
5. Continue cycling the torque, watching for pressure bleed off and returns at the
shakers. If bleed off or partial circulation occurs, slowly increase pump strokes to
maintain a maximum of 25 bar standpipe pressure. If circulation improves
continue to increase the pump strokes.
6. If circulation cannot be regained, work the pipe between free up and free down
weight. DO NOT APPLY EXCESSIVE PULLS AND SET DOWN WEIGHTS AS THIS
WILL AGGRAVATE THE SITUATION (25 MT max). Whilst working the string
continue to cycle the torque to stall out and maintain a maximum of 25 bar
standpipe pressure.
7. DO NOT ATTEMPT TO FIRE THE JARS IN EITHER DIRECTION.
8. If circulation cannot be established increase the standpipe pressure in stages and
continue to work the pipe and apply torque.
9. If the pipe is not free once full circulation is established, commence jarring
operations in the opposite direction to the last pipe movement. Once the pipe is
free rotate and clean the hole prior to continuing the trip.
There are several main reasons for solids not being cleaned out of the well bore, these
are:
Low annular flow rate.
Inappropriate mud properties.
Inadequate mechanical agitation.
If any of the above are missing good hole cleaning will be very unlikely.
In 35-65 degree wells the cuttings bed will slide down the low side of the hole. This can
happen while pumping, not just when the pumps are off. In highly deviated wells of 65
degrees or more cuttings settle very quickly in spite of high flow rates. This is known as
avalanching. A cuttings bed of 10% of the hole diameter (4.5 cm in 17 1/2 hole) looks
harmless enough. Add a drill string and the situation looks very different.
Cuttings beds can also increase drag in the well and cause problems with applying WOB in
horizontal holes.
Preventative Action
Maximize the annular velocity.
Consider using larger drill pipe.
Ensure circulation times are adequate.
Monitor the cuttings returns at the shakers.
Maximize mechanical agitation of cuttings beds, Rotation and Reciprocation.
Optimize mud properties.
Increase YP in near vertical wells.
Freeing
See First actions - Solids induced packing off
Preventative action
1. Any action taken to reduce or eliminate one or more of the above causes will
reduce the risk of differential sticking.
2. Where possible design casing setting depths to minimise overbalance across
potential sticking zones, i.e. design for minimum overbalance.
3. Limit mud weight to the minimum required for hole stability and well control.
4. Use OBM where possible. Keep fluid loss to a minimum.
5. KEEP THE STRING MOVING. Pre-plan to minimize the down time for operations
that require the string to remain static (surveys, minor repairs, etc .).
6. Minimise BHA length when possible. Maximise BHA stand-off. Use spiral drill
collars.
7. The rig team can be made aware of the depth of permeable formations and the
estimated overbalance in those zones.
8. Aim to keep differential pressures across permeable formations to a minimum by
keeping the mud weight at the lowest safe level. A 10 bar static overbalance is a
general rule of thumb.
9. All mud parameters must be maintained within the specifications of the Well
Programme. In particular the following points apply:
10. Maintain HTHP and low pressure fluid loss within specification. These values should
be measured 3 times per day at the minimum.
11. While maintaining consistency with suspension and hole cleaning requirements,
maintain the gel strengths at the minimum value possible. Pipe release agents are
adversely affected by high gel strengths. The 30 minute gel strength should be
measured as well as the 10 second and 10 minute value and should not be
significantly higher than the 10 minute value.
12. Drilled solids content should be minimised.
13. Maintain the lubricant concentration specified in the Well Programme.
14. Stabilisation and spiral drill collars should be used to centralise and minimise wall
contact.
15. In depleted formation, differential sticking is a greater concern. In addition to the
measures mentioned above, the following should also be considered:
Ensure that a pup joint or a single is readily available
Increase the stand-off across depleted zones by adding stabs or torque
reducing subs
While tripping out through the depleted zones try to have the stabs across the
depleted zones at all times, or pull slick section of BHA past the zones in one
move.
Have a lithology sketch available on the drillfloor to assist driller when tripping.
Rig site indications
Overpulls on connections and after surveys
No string movement
Full unrestricted circulation
Losses
High overbalance
Permeable formation exposed in open hole
Freeing
1. Establish that Differential Sticking is the mechanism, i.e, stuck after a connection
or survey with full unrestricted circulation across a permeable formations
2. Initially circulate at the maximum allowable rate. This is to attempt to erode the
filter cake.
3. Slump the string while holding 50% of make-up torque of surface pipe.
4. Pick up to just above the up weight and perform step 2 again.
5. Repeat 2. & 3. Increasing to 100% make-up torque until string is freed or until
preparations have been made to either; Spot a releasing pill or conduct U" tube
operations to reduce the over pressure (only possible if there is no float sub in the
string)
Preventative Action
These formations need an adequate filter cake to help stabilize the formation.
Seepage loss can be minimized with fine lost circulation material.
If possible, avoid excessive circulating time with the BHA opposite unconsolidated
formations to reduce hydraulic erosion.
Spot a gel pill before POOH.
Slow down tripping speed when the BHA is opposite unconsolidated formations to
avoid mechanical damage.
Start and stop the pumps slowly to avoid pressure surges being applied to
unconsolidated formations.
Control-drill the suspected zone to allow time for the filter cake to build up,
minimize annulus loading and resultant ECDs.
Use sweeps to help keep the hole clean.
Be prepared for shaker, desilter and desander overloading.
A method successfully used in the North Sea is to drill 10m, pull back to the top of
the section and wait 10 minutes. Note any fill on bottom when returning to drill
ahead. If the fill is significant then ensure the process is repeated every 10m. It
may be impossible to prevent the hole collapsing. If so let the hole stabilize itself
with the BHA up out of harms way.
This mechanism normally occurs while drilling salt, in particular when encountering KCl or
KMgCL or MgCl salts (Bischofite and Carnalite) or sometimes in unconsolidated clays.
Preventative action
Maintain sufficient mud weight.
Select an appropriate mud system that will not aggravate the mobile formation.
Plan frequent reaming/wiper trips particularly for this section of the hole. Consider
bi-centre PDC bits.
Slow tripping speed before BHA enters the suspected area.
Minimize the open hole exposure time of these formations.
With mobile salts consider using a slightly under-saturated mud system to allow a
controlled washout.
Preventative action
Ensure planned mud weight is adequate. Plan to minimize hole exposure time. Rigorous
use of gas levels to detect pore pressure trends. Use of other information to predict pore
pressure trends. Once the shale has been exposed do not reduce the mud weight. It may
also be the case that the mud weight will need to be raised with an increase in inclination
Preventative action
Use an inhibited mud system or use SBM.
Maintain the mud properties as planned. The addition of various salts (potassium,
sodium, calcium, etc.) will reduce the chemical attraction of the water to the shale.
Various encapsulating (coating) polymers can be added to WBM mud to reduce
water contact with the shale.
Monitoring mud properties is the key to detection of this problem.
Open hole time in shale should be minimized.
Regular wiper trips or reaming trips may help if shales begin to swell.
The frequency should be based on exposure time or warning signs of reactive
shales.
Ensure hole cleaning is adequate to clean excess formation i.e. clay balls, low
gravity solids .
Preventative action
Plan to case off these formations as quickly as possible.
Maintain mud weight within planned mud weight window.
Well bore instability shows itself as a hole cleaning problem.
If possible drill these formations in smaller hole sizes. This will minimize the impact
of a hole cleaning problem.
Ensure that the circulation system is capable of handling the additional volume of
cavings often associated with this mechanism.
Use offset data to establish optimum inclination and azimuth as these are key
factors in reducing the extent of the problem.
9.5 Mechanical & well bore geometry stuck pipe types - first action
Guidelines for freeing stuck pipe other than Pack-offs and Differential sticking.
1. Ensure circulation is maintained.
2. If the string became stuck while moving up, jar down.
3. If the string became stuck while moving down, do not apply torque and Jar up.
4. Jarring operations should start with light loading (25 T) and then systematically
increased to maximum load over a one hour period.
5. Stop or reduce circulation when; a) cocking the jars to fire up and b) jarring down.
6. Pump pressure will increase jar blow when jarring up, so full circulation is
beneficial. Beware of maximum load at the jar.
7. If jarring is unsuccessful consider acid pills, if conditions permit.
Preventative action
Use suitably gauge-protected bits and stabilisers. Consider the use of roller
reamers. Always gauge all BHA components both when running in and
pulling out of the hole. Ream suspected undergauge sections. Slow the trip
speed down before the BHA enters an undergauge zone.
Bit stuck near the bottom of the hole or at the top of a cored section.
Freeing
Jar up with maximum trip load. Do not jar down. Consider the use of an acid pill. Consider
applying torque as a lastresort.
Doglegs: While drilling a well bore, the characteristics of the rock cause the bit to be
deflected and can result in a change in direction. Likewise when drilling with a directional
BHA, sudden changes in angle can cause a kink in the well bore direction. Sharp
deviations in wellbore direction are called doglegs.
9.5.4 Junk
Debris that has fallen into the hole from surface or from downhole equipment, which falls
down the well bore and jams the drill string. This mechanism usually occurs:
Due to poor housekeeping on the rig floor.
The hole cover not being installed.
Downhole equipment failure.
Preventative action
Encourage good housekeeping on the rig floor and regular inspection of handling
equipment.
Keep the hole covered at all times.
Inspect downhole equipment before it is run in the hole and again as it is being run
through the rotary table.
Inspect slip and tong dies regularly.
Install drill string wiper rubber as quickly as possible.
Freeing
Ensure circulation is maintained.
If the string became stuck while moving up, (apply torque) jar down.
If the string became stuck while moving down, do not apply torque and Jar up.
Jarring operations should start with light loading (50k lbs) and then systematically
increased to maximum load over a one hour period.
Preventative Action
Allow sufficient curing time for cement before attempting to kick off or drillout.
Ream casing shoe and open hole plugs thoroughly before drilling ahead.
Limit casing rathole length to minimise a source of cement blocks. Slow the trip
speed down before the BHA enters the casing shoe or the plug depth.
Use of fibre additives to the cement can increase its integrity. Maintain sufficient
distance between the paths of platform wells to reduce the
possibility of cement blocks from adjacent well bores.
Rig site indications
Circulation unrestricted.
Cement fragments.
Rotation and downward movement may be possible.
Erratic torque.
Freeing
Ensure circulation is maintained.
If the string became stuck while moving up, (apply torque) jar down.
If the string became stuck while moving down, do not apply torque and Jar up.
Jarring operations should start with light loading (25 T) and then systematically
increased to maximum load over a one hour period.
Preventative action
Do not rely solely on surface samples.
Know the cement setting time, but do not assume it will be set when you trip in to
the hole. Know the calculated top of cement (Theoretical TOC) before tripping in
hole but always expect it to be higher.
Do not rely on the weight indicator to find the top of the cement. If the cement is
not set you may not see any indication on the weight indicator when you run into
it.
When approaching TTOC begin washing down two stands above the theoretical top
of the cement.
Consider to wash through 3-4 stands above the theoretical cement top in small
hole sizes (< 8.5).
If set down weight is observed when tripping in hole after a cement operation, pull
back 2 stands before attempting circulation.
Control ROP when drilling / washing / cleaning out soft cement.
Rig site indications
Increase in pump pressure leading to inability to circulate.
Loss of string weight.
Sudden decrease in torque.
Green cement in mud returns, discoloration of mud.
Freeing
Bleed off any trapped pump pressure.
Jar up with maximum trip load.
Attempt to establish circulation.
Prepared by WEP
Author:
Verified:
10.1 HSE
All personnel must be informed of and observe the following safety and environmental
requirements for handling casing:
Never walk under loads suspended in the crane or high line.
Always wear gloves and eye protection when cleaning joints.
Never get between loads and another object.
Adhere to proper lifting practices when handling tubulars: always have taglines on
pipe bundles or when lifting individual joints through the V-door to the rigfloor.
Have pinch-points identified.
Ensure bundles with casing or tubing are properly slung and secured with clamps.
Be careful rolling casing across racks to ensure feet do not get trapped.
Never use diesel oil for cleaning connections.
Maintain good communication between rig floor, deck crew and crane operator.
Well control equipment shall be tested and ready.
26. The final copy of the running list will be signed off by the WSDE, the WSS, the DSV
and the TP. Copies will be distributed to DSV, Toolpusher, senior roughneck/crane
operator and driller.
27. Every time a joint is rejected the WSDE shall be informed and the tally updated
accordingly.
28. When a tally error is found, the job shall be stopped and all signatories shall be
informed. Supervisors shall investigate what the impact is of the error.
29. Any time the tally requires updating, it is the responsibility of the WSDE that all
relevant parties are given an updated tally, and that the old tallies are destroyed.
30. Every tally shall have a version number, and in the footer of the tally there shall be
a statement of date and time of print.
Casing/liner accessories
Float shoe and collar
Casing / liner
Pony casing / liner to ensure proper space out to cover the base of the perforations
and to be able to rig up and anchor the cement head at an appropriate height
above the rig floor
Stage cementing collar (if required)
Centralisers type (e.g. spiralizers, bowspring)
Stop rings
Casing thread lock compound (for shoetrack)
Landing joint
Spare Couplings
Casing hanger
Radioactive pip tags, if required
Running Equipment
Elevators; single joint/side door/slip type
Bails, ensure they fit in the elevator ears
Slings, ensure rating of slings is sufficient for the job
Slips, check condition of dies
Spider elevator
Spare dies for slips and spider elevator
Casing tongs
Power tongs, ensure that powerpack is properly functioning and not leaking
hydraulic oil from powerpack or lines.
Torque gauges
Clamp-on thread protectors
Wellhead Equipment
Casing head housing (clamp-on or threaded)
Casing head spool
Slip and seal assembly or integral type casing hanger; when using integral type
hanger have a slip & seal assembly available on site for back-up.
Wear bushing, seal bushing, plastic sticks and injection tool.
Ring joint gaskets
Studs and nuts/clamp assembly
Steel gate valves/companion flanges
Plug type tester/wear bushing running tool
Cup type tester
Special clearance drift required for narrow tolerance (e.g. 6 bit through 7 32# casing or
8.1/2 through 9.5/8 47#)
10.4 Procedures
1. Conduct Toolbox meeting for all relevant rig personnel to review and discuss the
liner program and safety issues.
2. In case of a rotating liner:
Check the torque rating of the running tool.
Do not use centralizers unless of rotating type, such as spiralizers.
3. In case of a sliding liner centralizers are allowed. In principle no rotation is
allowed, check torque rating of running tool in case of emergency rotation
required.
4. Assure liner and drillpipe displacements are monitored and compared to trip chart.
5. Verify landing criteria.
6. Verify circulating and conditioning criteria before cementing. Refer to the liner
(cementing) program.
7. Verify the proper slips for the weight of the liner string.
8. Ensure that all joints in the casing-liner overlap are centralized. When there are
close clearances, minimum-clearance centralizers should be used. Casing
centralizers shall be installed in accordance with the cementing contractors
centralization software program.
9. If liner is slotted, ensure that the crew understands how to drop the liner in the
hole in the event of well control procedures.
10. Make up the liner hanger and visually inspect it to ensure that the slips will operate
and that there is no damage to the slips, the J-slot, or other components. A prior
check of the OD's on the hanger should indicate the need for special-size tong
heads or rotary slips to handle the liner hanger.
11. Check casing float valve operation on initial insertion into the hole.
12. Ensure that any singles which must be picked up to allow tagging bottom on an
even stand should be picked up, and stood back if possible, before the liner is run
into open hole.
13. Verify that after all of the liner assembly has been picked up, it is possible to
circulate through the entire assembly before proceeding to go in the hole.
14. Verify the correct amount of casing run by counting liner left on the deck /
location.
15. Check of the actual liner weight after picking up the first stand of drillpipe. Be sure
that the liner is completely full of mud and take into account the weight of the
blocks and the stand of drill pipe.
16. Pipe must be filled at a minimum every 5 10 joints.
17. An accurate pick up and slack off weight shall be recorded whilst filling the pipe.
18. Ensure that the bottom is tagged with the cement head high enough above the
rotary to allow for the activation of the liner slips.
19. Before the liner is run into the open hole, a cementing standpipe and the cement
lines should be rigged up with long enough bails to allow maximum pipe
movement or washing down.
20. Ensure drill string is spaced out to put the surface cementing equipment as close
as possible to the rotary table when shoe is on bottom (keep in mind additional
slack off weight required).
21. Ensure that reciprocation of the liner begins immediately. While reciprocating to
break the mud gel strength, break circulation as slowly as possible (40 to 80 lpm).
The speed of reciprocation should not exceed that of the recommended lowering
speed.
22. Ensure that the place where bottom is to be tagged is marked on the drill pipe.
23. Record the exact liner and DP string weights including drag (hook load down and
up) to calculate the exact neutral point for the setting tool release (10-15t max).
24. Ensure that prior to setting hanger that all drill pipe on surface is counted and
matches with correct number from original count.
25. Ensure that before running tool is released, the hanger has had set down weight
applied that is equal to or greater than weights applied during the cementing,
rotating or packer setting process.
26. Ensure that the Drilling Supervisor or Toolpusher supervise the running of the liner
into the open hole.
27. Gradually increase the circulating rate to the maximum rate to be used, as per the
liner procedure.
28. The job is not finished until all reporting has been completed!
Also check to see that the blocks are aligned directly over the well. If not, be aware that
this may cause some problems in running the pipe. For example: a misalignment of 0.40
m for 10 3/4" VAM SL and 0.50 m for 10 3/4" VAM HW ST are sufficient to get the threads
crossed with a length of 11 m.
Stabbing
1. Install the stabbing guide.
2. Stab the pipe either with the help of a skilled stabber or with a penny yoke.
Note: the stabber must ensure that the connection is properly stabbed, and once this is
done, he must also maintain the joint in a vertical position.
Note: avoid obscuring the driller operator's view during pipe running and ensure he is able
to see the stabbing. Ensure that the pipe does not move too much during initial thread
engagement.
Caution: the stabbing operation is particularly critical, with pipe of 9%Cr, 13%Cr and
above.
Make up
1. Start to make-up by hand or with a strap wrench for at least two turns.
2. It's up to the discretion of the field engineer and customer to decide starting by
hand or not for large diameter tubulars.
If it is difficult to make-up by hand at the beginning, make sure that the stabber is
keeping the pipe in vertical position so that it may turn freely.
When making up, the main elevator shall remain off the pipe and sufficiently far enough
away to avoid hindering the stabbing work.
Important: as steels with 9%Cr, 13%Cr and above have more tendency to gall than
carbon steels, the initial make-up is critical. For high alloy material the make-up must be
made by hand until it becomes difficult to turn.
3. Put the power tong in place (back up tong should be placed below the coupling).
4. Remove the single joint elevator
5. Only after this, use the power tong.
6. Make-up to required torque.
Once torque increase is noted, change the make-up speed to a low speed in
order to obtain the final torque.
Any torque increase before 1.5 turns from shouldering is indicative of a
problem in make-up (such as a cross threading or galling), and rotation should
be stopped and the connection broken-out.
Torque build-up does not normally start until six or seven complete turns are
obtained.
When the connection is made-up, check the torque graph on the monitoring
system.
During all the make-up the stabber should take an active part in the operations
to keep the pipe in the best position.
7. When the make-up is finished and the torque/turn graph is accepted, disengage
the power tong.
8. Set the elevator.
Important: it is essential to close the main elevator only when the makeup is
completed and accepted.
Rigid Centralisers
Rigid centralisers are used inside casing only. They are installed over stop collars or
between stop collars or collared couplings and stop collars. The method of installation
depends entirely upon the centraliser design.
When specifying rigid centralisers for surface casing, care must be taken to ensure that
they will pass through the riser/landing ring.
Centraliser placement
The number of centralisers needed per joint depends on hole conditions, well trajectory,
well dimensions, etc. The cementing service company will usually perform the calculations
and provide advice. The following can be used as an initial guideline:
1 centraliser per 1-3 joints in a vertical well
1 centraliser per 1-2 joints till 45 degrees inclination
1 centraliser per joint over 45 degrees inclination
Centraliser installation
Whenever possible, centralisers should be installed over stop collars. It is however
necessary to fit centralisers above and below stop collars in the following cases:
When using close tolerance centralisers in case of a spring type.
When the design of the centraliser does not allow the installation over a stop
collar, e.g. in the case of solid sleeve centralisers.
Where possible, centralisers shall be pre-installed on the rack to save time. Stop collars
are available in sizes from 4 1/2" to 20". The type may be advised by the supplier.
10.5 Examples
Offline work:
Install Centralisers as per tally
Install hose on 20 casing head side outlet to take returns back to pit during
cement job
Dowell to pressure test cement unit and surface lines up to the last LTV to
cementing head. Complete the Pre-job check list and discuss with DSV.
WSDE to calliper 10% of casing and use the calliper ID for displacement.
Fluff the tank prior to cementing operation and stick to agreed surge tank setting
level.
Check the vent line a day prior to cementing job.
Clean the threads on joint to be baker locked. Wrap pin connection with rags.
Cameron to check the O ring in 13 5/8 compact head & confirm condition ok.
Check and confirm housing orientation.
Check, confirm compatible cement head. Count and note number of turns for
release pin.
Note:
Establish a clear signalling strategy between stabber and driller.
Ensure X-over from 13 3/8 BTC to 5 7/8 XT-57 DP & to 2 Weco on the rig floor.
No casing rams, shut in procedure to close annular preventer and strip with X-over
and drill pipe.
Float collar is rated to 34,500kpa.
Model for casing hook load whilst RIH must be used for an early indication of hole
problems.
Slightest deviations from trend to be highlighted and discussed for remedial action.
Rate Pressure
40 SPM
50 SPM
60 SPM
Pressure test compact housing to casing head seals to 20,700 kPa through test
port.
Prepare well control X/O to Kelly Cock c/w 7 HYDRIL 513 Pin XT-57 Box Water
Bushing (for circulation).
The Setting Sleeve/PBR has a screen type debris barrier (Pal mix polymer already
added) in PBR ID annulus for further debris isolation.
Ensure all TDS inspections are done & slip /cut minimize exposure of swell
packers in mud.
Make up HWDP in stands in derrick use all 45 joints (22 in drilling BHA). Ensure
HWDPs are cleaned and drifted.
Drift all drillpipe to 2 on way in.
Minimise stationary pipe in open hole > long blank pipe sections, high risk of
becoming stuck!
Detailed instructions
1. Hold PJSM running liner.
2. Rig-up to run 7 26# HYDRIL 513 pre-drilled liner.
3. Make-up Reamer Shoe joint -without float valve / drilled holes- and RIH the 7
pre-drilled liner as per signed off tally to first swell packer.
Before running in, WSDE to count liner joints on deck & check against tally. All
spare joints must be marked & isolated. Counter check no.of joints left on deck
after RIH.
4. Make up Swell packer assembly.
Remove protection without touching the rubber with a knife, inspect packer for
damage prior to running through Rotary DSV to witness.
Drift the OD of the packers with OD drift, confirm as 8.2.
Avoid prolonged contact with base oil, diesel or other oil-based fluids.
Do NOT run centralizer on the upper packer pup joint. Centralizer must be run
just below the box of the joint below.
5. Continue to run 7 pre-drilled liner as per signed off tally.
6. Repeat installing Swell packer assemblies acc. tally.
Important:
Be aware the liner running tool will release mechanically by LH turn with 5000 ft-lbs.
The HRD running tool will be released hydraulically at 17,236 kpa (2500 psi).
Hanger setting pressure 10,350 kPa (1500 psi).
With updated drag data, update the drag model and provide updated road map
to driller as soon as possible.
Important: Do not exceed 50 kftlbs at any stage when rotating at 20-30 rpm. Be aware
the liner running tool will be release mechanically by LH turn with 5000 ft-lbs. The HRD
running tool will be released hydraulically at 17,236 kpa (2,500 psi). Hanger setting
pressure 10350 kPa (1500 psi).
Adhere to following procedure for making a connection when rotating down is required:
Rotate liner at 20-30rpm. Take static rotating weight.
Rotate 7 liner down at 20-30 rpm, limit surface torque to max 50 kft-lbs.
Release torque from top drive in a controlled manner, NO LH torque !
Set on slip (Rotary locked) and Break connection from topdrive.
Make up another stand of 5 7/8 D/P and Make up to the topdrive.
Apply break on topdrive, Remove slip, unlock topdrive break and pick up to rotary
weight, rotate string first then continue rotating liner down.
Do not keep string stationary for long. If required, keep string in slow rotation
15. Rotate down liner to 7950 m (one stand before liner setting depth @ 7990m BDF).
Confirm pipe tally and depth of packer is correct, report last rotating weight.
Record Free Rotating hook load on each stand prior to start reaming down
Take up weight when safe as per Engineer / Tool pusher
16. Drop 1.5 ball. Make up new stand. Start rotary and record free rotating weight.
Slowly rotate down liner and pump down ball as per engineer, limited pump
pressure to 6,200kpa (~900psi). Meantime, slowly rotate down liner (20-30 rpm)
to setting depth while pumping. Once on depth, stop rotation & any movement in
the string. Release residual torque in string. Slow down pump to 400 lpm at 500
strokes prior to seating the ball to prevent premature shear of the ball seat.
17. Once the ball is on its seat, pressure-up to 12,400 kPa (1,800 psi) to set the liner
hanger. Hold pressure for 5 minutes. Set down with 27 kdaN, to ensure slips are
set on the casing & confirm hanger set (NOTE: Hanger setting pressure 10350 kPa
(1500 psi).
18. Continue pressure-up to 20,000 kPa (2,900 psi) to release running tool. Bleed off
pressure. Pick up 1-2 m more than Up Weight before setting to confirm tool is
released. Record Pick Up weight & loss of liner weight.
Contingency: In case the running tool does not release, apply 5000 ftlbs left
hand torque and work down the string. Repeat with 8000ftlbs, 9000 ftlbs and
etc until tool is released.
19. Once released, set down ~ 14 kdaN. Pressure up to 25,000 kPa (3,600 psi) to
shear ball seat in ported ST landing sub. Expect shear at 23,800 kPa (3450 psi).
20. Pick up Running tool to above liner hanger and circulate well gas free, at least 1.5
bottoms up.
21. Flow check well. Might see back flow due to mud imbalance. Preferably no slug.
22. POOH to surface and lay out running tool, report status.
If plug has to be pumped, POOH very slow initial 20-30 meter. Contd POOH to
surface.
Do not rotate string when POOH.
Ball is still inside > careful handling.
Service break running tool & lay out same.
23. Prepare for drift run.
Interval lengths At TD Running in
5 7/8 DP 622 0 622 7368 7990
5 7/8 DP + NRDPP 1700 622 2322 5668 7368
HWDP 423 2322 2745 5245 5668
5 7/8 DP 1400 2745 4145 3845 5245
7 Liner 3845 4145 7990 0 3845
Prepared by WEP
Author:
Verified:
1. Mechanical: Is performed while RIH with scraper and brushes sized as per the well
configuration. These tools are used to remove solid debris, cement, scale or rust
which might be on the casing. Casing cleaning operations are improved by the
mechanical action of scraper and brushes.
2. Chemical: Once the cleaning BHA is on bottom, a sequence of fluids is pumped to
remove any build-up on the casing which could not be removed by the mechanical
action of the scraper and brushes and to remove any debris loosened from the
casing face by the scraper and brushes run in hole.
The objective of the casing cleaning program is to minimise the potential formation
damage from drilling mud or other solids such as formation fines, particles or rust present
in the wellbore prior to installing well completion equipment. An efficient wellbore cleanup
should:
Eliminate risk of completion tools, packers and slickline tools from obstruction or
becoming inoperable.
Eliminate particle invasion to the formation.
Enhance productive capability of the well.
11.2 HSE
A toolbox meeting shall be held and the following topics discussed:
Job operational procedures including contingency plans.
Job co-ordination and responsibilities.
Emergency procedures.
An agreed Muster point in case of emergencies and designated smoking areas.
Location of First aid facilities.
Secondary well control equipment like stab-in valves and BOPs shall be tested and
ready in case there is a well control issue.
Returns from the well shall be monitored and managed to avoid environmental
pollution.
Handling and lifting of equipment for instance Razorback scraper or barrels
containing hazardous chemicals and identification of pinch-points.
Chemical hazards i.e. actions required if hazardous contact occurs. Show & discuss
Material Safety Data Sheets (MSDS) of unusual or hazardous chemicals.
Required personal protective equipment (PPE) for chemical handling on location as
per MSDS.
For acids and caustic fluids, ensure correct PPE is in good condition and is worn!
Please note that HF Hydrofluoric (extremely hazardous chemical) should NOT be
used in our operations. IF, by exception, this chemical is to be used, then the
drilling company and supervisors on location must mandatory have the following in
place:
o A special approval sent by Drilling Team and HSE Team of Well Engineering
Department.
o A particular Company with special HSE procedure and emergency response
plan will be involved in transportation/manipulation/cleanout operational
program.
o Drilling company will be involved on easier working while cleaning operation
will be unrolled.
o Safety measures made on location- recommendations:
o Understand the specific danger of HF and always treat it with the greatest
respect, knowing how to protect and how to apply first aid.
o Ensure MSDS (material safety data sheet) is available and known in detail
and always respected.
o Rigorously control the knowledge and competency of everybody including
contractors personnel - who deal with it.
o Treat all HF containers the same whether they are full, partly full or empty.
o Speed in First Aid is essential; Have sufficient amounts of water and
Calcium Gluconate Gel available.
o Ensure that nearby medical facilities are capable of treating persons injured
by HF contamination, before commencing work with this chemical.
o Test and verify that those measures are being followed.
7. Chase HEC spacer with water/detergent from the clean mud tanks to displace mud
out of hole.
8. Ensure mud tanker truck is hooked up and ready to receive mud returns from hole
then once tanker truck is full, leave remaining mud in the mud tank so it can be
collected later by tanker truck.
9. Clean up mud pit when empty.
10. While using water/detergent to clean casing continue reciprocating string with
clean-up tool assembly taking water returns back to the same tank pumping water
downhole. Use opportunity to clean flow ditch from flow-line to mud pits.
11. Fill tanks with clean water then mix the brine in the empty water/detergent tank.
Alternatively brine already mixed can be transported to the site and be transferred
into the tanks.
12. Check that the solids content of the clean brine is below 0.002% and if not, filter
the brine using 2 micron filters.
13. Ensure corrosion/scale inhibitor and oxygen scavenger is added to the brine.
14. Continue well clean-up using more HEC pills from the pill tank if necessary to
remove debris from the hole.
15. Once ready to displace hole to clean filtered brine, pump 3m3 of HEC pill followed
by clean filtered brine and take care to route the pill when it comes back at surface
to the pill tank.
16. Commence completion program.
17. Use the flocculation and filtration units to clean up the dirty cleaning water prior to
recycling this water for spud mud or for abandonment fluid.
Note: Pure Hydroxethylcellulose (HEC) is used to viscosify water or brine and/or brine pills
and this product should be mixed in neutral pH 7.0 to avoid forming "Fish Eyes"
(unsheared polymer). Corrosion/Scale inhibitors and oxygen scavenger should also be
added to brine prior to pumping and leaving brine in the hole. Be sure mud company
always has a pallet of this product available for all well clean-up programs.
12 Cementing
Prepared by WEP
Author:
Verified:
12 Cementing .................................................................................................... 3
12.1 HSE........................................................................................................... 3
12.2 To do list prior to cementing......................................................................... 3
12.3 Mud circulation and conditioning prior to cementing ........................................ 6
12.4 Cementing best practices ............................................................................. 6
12.5 Operational sequence for cementing operations .............................................. 8
12.5.1 Stab-in / stinger cementing for surface casing only ................................ 8
12.5.2 Plug-type casing cementing.................................................................... 9
12.5.3 Liner cementing .................................................................................. 11
12.5.4 Balanced cement plug ......................................................................... 14
12.5.5 Squeeze cementing ............................................................................. 15
12.6 Additives.................................................................................................. 16
12.7 Cementing graphics................................................................................... 19
Appendix 1 Cement design information sheet ....................................................... 21
Appendix 2 Petrom cementing checklist............................................................... 23
Appendix 3 Cementing recipe form example ...................................................... 27
Appendix 4 Summary........................................................................................ 28
12 Cementing
12.1 HSE
Perform Toolbox talk before starting operation. Designate responsibilities.
Permit to work and JSA must be made.
Surround the working area with warning tape.
Required personal protective equipment (PPE) shall be worn for chemical handling on
location. Wear dusk masks when mixing cement.
Chemical hazards i.e. actions required if hazardous contact occurs
If losses have occurred while drilling, use fibres in the first 8 m3 cement.
Cement thickening time (BC-40 time) has to be as short as possible while still
allowing to circulate out 50% of the total cement quantity. In practice this means
1-2 hours safety margin for the pumptime.
The shoetrack shall consist of 2 full joints, where practicable. Note that for some
applications short shoe tracks will be considered.
All casing shall be reciprocated or rotated (where possible) while displacing the
cement until a significant increase in drag is seen; then hang off while ensuring
that no collar is opposite the slip-seal hanger area.
Casing centralization
Ensure sufficient centralizers are installed for proper casing centralization. Refer to
chapter on casing and liner running.
Ordering Cement
Type and quality as specified in programme
Specify additives required.
o Accelerator or retarder (if required) water loss control agent
o Friction reducer
o Lost circulation material
o Slurry density reducer
o Slurry density enhancer
o Antifoam and de-foam agents
o Gas control agents
o Anti-settling agents
o Spacers
o Pre-flush
Cementation Accessories
Cementation head/plug housing
High pressure lines and valves.
Top and bottom plugs > DSV to witness proper installation in cement head!
With the casing installed and mud conditioned the hole should be circulated for at least
one hole volume. Circulating rate should be equal or higher than the planned
displacement rate during cementing so that the risk of losses during cementing can be
assessed.
The mud company can provide recommendations on the optimal flow rate for mud
conditioning and hole cleaning.
33. Upon conclusion verify that cement & mix water volumes match with material
balance to confirm that the cement was pumped as designed.
34. Follow design procedure for waiting on cement. Complete all company & regulatory
reporting, immediately. The report should include at least:
Calculated top of lead and tail cement
Cement volume returned to surface
Losses
Plug bump pressures
Note: When cementing intermediate and production casings in wells drilled with WBM with
a mud weight less than 1.3 SG, a scavenger slurry of 1.45 SG will be used as spacer.
Note: Mix water and spacers will be prepared 2 hours before reaching the casing/liner
setting depth, especially in wells where the open hole is in good condition.
This rule is applicable also in casing drilling jobs.
Note: For production casing, the displacement of slurries will be made with brine (or
formation water) when the mud density used for drilling is lower than 1.3SG.
Note: Stab-in tools must be used with caution. In case the hole bridges off, pressure
could exceed casing collapse pressure.
Note: When the pressure starts to exceed expected pressures and a flash cement job is
suspected, stop mixing, un-stab stinger and circulate cement out. The rig mud pump shall
be ready to pump at all times throughout the cement job.
13. When cement returns are seen at surface, drop the plug and displace the stinger
contents. Do not overdisplace more than half the shoetrack.
14. After landing the plug, check for backflow.
15. POOH DP stinger & WOC.
16. In case of (expected) losses, be prepared to take returns to the cellar and to pump
such returns from the cellar to the shale shakers, using either a deep well or fly
pump, or venture pump system
17. If no cement returns are seen, a topfill shall be conducted.
1. Ensure that the pumping simulation schedules are used to determine optimum flow
rates and identify downhole reactions, besides freefall and U-tubing, also calculate
the extra ECD caused by restriction between liner hanger and the casing.
2. Ensure the use of pump down plug cementing head for liners. Check head for
proper operation.
3. Have rotating liners!
4. Ensure that the surface lines are manifolded in advance to facilitate plug release
without having to break connections to drop plugs.
5. Hold pre-job safety meeting.
6. Pump spacer.
7. P/T lines if not pressure tested prior to linerhanger setting procedure.
8. Pump lead and tail cement as specified in the programme.
9. Drop DP wiper plug.
Slow the pump down to 300 l/min prior to the DP wiper plug landing into the
Liner wiper plug. If the shear is observed, use the calculated liner volume from
the time the shear was seen.
Displace until both plugs land on the landing collar or upon reaching the
calculated displacement volume.
Bump the plug with 300 l/min. If the liner wiper plug shear out was not seen,
use calculated displacement volume only. Only pump half the shoetrack
capacity if plug fails to bump.
Record pre-bump static differential at calculated theoretical displacement
volume. Compare with pre-calculated theoretical pressure.
10. Bump the plugs with +/- 35 bar over differential pressure.
11. Check for backflow.
12. Pressure test the liner to the programmed test pressure.
13. Pull back to pull setting dogs above liner top.
14. Set liner packer with weight as per manufactures recommendation and observe
shears.
15. Pull running tool above liner top 1 to 2 joints.
16. Circulate out excess cement. Reversing: The decision to reverse must be clearly
decided and communicated in advance of the job and can only be done when the
plugs have bumped and the liner packer has set.
17. POOH with liner running tool.
Note: For abandonment plugs and for plugging the perforations, use cement slurries of
1.8 1.9 SG density and a minimum 2.0 SG density for sidetrack plugs.
Use of a retrievable packer provides more flexibility as it can be set and released many
times. A drillable cement retainer is used to prevent backflow if no cement dehydration is
expected or when a high negative differential pressure may disturb the cement.
1. Injection rates and pressures should be determined prior to start of squeeze job.
2. Verify any staging requirements.
3. Become familiar with isolation tools prior to running, i.e. permanent or retrievable
tools.
4. Beware of casing collapse when using isolation tools on large casing.
5. Reversing out must be decided in advance since thickening time may need to be
increased if circulating out conventionally.
12.6 Additives
The following information concerning additives is intended only to illustrate the function of
the various classes of cement additives and also to highlight which chemicals are used for
which purpose. The recipe supplied shall be followed. Refer to the cement
contractor/supplier for more detailed information.
Accelerators
Accelerators are added to reduce the thickening and setting times of the slurry, to
avoiding unnecessary time spent waiting on cement.
Salt is the most common type of accelerator, typically added in the form of
seawater or Sodium Chloride. Calcium Chloride is most commonly used, and
Potassium Chloride less commonly.
In general accelerators increase the viscosity of the cement slurry and decrease
the effectiveness of most other additives.
Retarders
Increased depths and formation temperatures may require the use of retarders in order to
extend the pumpable time of the cement.
Thixiotropic slurries may require retarders at shallow depths and low
temperatures.
Most retarders affect the viscosity of the cement as follows:
Lignin Derivative Increase
Organic Acids Reduce
Cellulose Derivatives Increase
Gasblocking additives
During the hardening process, the cement slurry passes through a semi / solid phase in
which the liquid has gelled up. As a result, the overburden pressure will be lost thus
permitting gas influx into, and in some cases migration through, the cement matrix.
Surfactants added to the slurry will form a stable foam with the gas bubbles preventing
their transport through the cement slurry.
When gas is anticipated to be a problem during cementation, surfactants should be
added to slurries
Additives may be incorporated into the slurry which act to block the gelled cement
pore structure preventing gas migration.
__________________ ________________
Pre-job checks
Float collar and float shoe have been checked for proper function. As minimum two (2)
joints of casing have to be installed between float shoe and float collar.
Sufficient tank space for the expected volume of returns of the cement job is
available.
Monitor tank volumes of all mud tanks before pumping anything and to continue to
monitor tank levels closely throughout the job to check for losses or gains.
Report losses or gains during the cement job and time of occurrence. This information
is useful when analysing the job. In case of losses during the job, consider lowering
the pump rate based on the predicted ECD, the remaining volume and thickening time
of cement slurry.
Mud engineer at the shakers to empty the cuttings waste pit before the cement job to
accommodate any cement returns at surface. Discuss and have available chemicals
which will be used to neutralize the cement slurry returns into the cuttings box.
Mud engineer at the shakers during cement displacement to identify cement returns
and to route these directly to a waste pit.
Calibrated Halliburton mud balance ready for measuring the cement during the job.
Take sample of dry cement and mix fluids to check quality with lab analysis. A sample
of the mix water must be taken and Chloride content reviewed on site before the job,
this result must be compared against the Lab report and any deviation should be
noted Minimum quantity of 12 kg dry cement, 4 liter of fresh water and 4 liter mix
water.
Detailed cement program is available approved by drilling manager or drilling engineer
in charge.
Lab test conducted and report available. Check that the lot numbers for chemicals
used in the Lab report and on site are the same.
Thickening time (BC-40 time) of lead and tail slurry should exceed the total pumping
time and allow for circulating cement out but should be as short as possible.
Recommended is minimum 1 hour or the required time to pump/displace out the
cement with the estimated circulation rate for displacement.
Preflush and spacer volumes and composition are agreed and compatibility with the
drilling fluid tested.
Perform physical check of pumps and lines prior to the cement job.
Check BHCT of mud, as well as flowline and active mud tank temperatures then
compare with simulated temperatures.
Circulation test performed prior to the cement job. To reduce risk of losses, it is
important the mud is thinned and the hole is reasonably clean of cuttings. Check
values with Cementing Program and Mud Engineer.
Calibrate stroke counters and pit level indicators whilst conducting the circulation test.
Perform volumetric efficiency test with rig pumps and determine pump efficiency in
case rig pumps need to be used in any stage of the cementing operation
Pump 1 Pump 2
Pump efficiency % %
Stroke volume l/stk l/stk
Drilling fluid circulated and conditioned prior to the cement job (use prejob circulating
time and flowrate for bottom hole circulating temperature estimation).
Check number of casing centralizers available on location, which must be the same as
the number programmed. The cement job must not proceed unless the programmed
number of centralizers is onsite.
Cement engineer and Drilling Engineer have agreed on the casing centralization and
all centralizer and stop collar are available. Consider pre-installing centralizers.
Hot water bath must be available for every production casing and liner cement job.
Calliper log has been run prior to cement job and is used for volume calculations. Use
the excess percentage of the table below for calculations.
On-job checks
Detailed pre-job meeting conducted prior to the job.
All cement lines are pressure tested prior to use (1.5 times maximum working
pressure) and have been secured with safety wire.
High pressure warning signs placed over the cementers lines and at high pressure
area throughout the duration of the job.
Mud transfer pump with sufficient volume is connected to the cementing unit to avoid
stopping to pump while displacing the plug. The mud pump is not to be used to
transfer mud.
DSV to witness loading the bottom plug in the cement head and to function test the
telltale in the cement head.
DSV to witness loading the top plug in the cement head and to function test the
telltale in the cement head.
Decide upfront to chase the top plug with the rig pump or cement unit. If it is decided
to use the rig pump ensure that a quick change over is achievable. To ensure effective
displacement, the recommended displacement rates are:
The spacer or scavenger slurry must reach turbulent flow (if possible)!
DSV, Senior Drilling Engineer and cementing company shall calculated all cement
volumes prior to the job, compare the results from their calculations, discuss and
agree prior to starting the cement job.
DSV, Senior Drilling Engineer and cementing company shall calculated all excess
volumes prior to the job, compare the results from their calculations, discuss and
agree prior to starting the cement job.
DSV, Senior Drilling Engineer and cementing company shall calculated the
displacement volume prior to the job, compare the results from their calculations,
discuss and agree prior to starting the cement job (the displacement volume shall
include the surface line volume).
Calculated top level of lead and tail cement are reported in the DDR. Top of Cement
(TOC) for intermediate and production casing shall be a minimum 150 m above
shallowest hydrocarbons. If shallowest HC are not known TOC shall be a minimum of
100 m into last casing.
Surface samples (minimum 3 samples of each slurry) are placed:
o in an open cup and then into sealed plastic bags or
o in sealable cups
And then in a hot water bath with the temperature regulated to the BHST to simulate
downhole temperature. Based on the lab test results (and this surface sample as a
reference) the waiting time on cement is defined. The surface samples are not very
accurate on deep wells because pressure and downhole temperatures above 85 C can
not be simulated with the water bath.
In case of expected gas migration the cement slurries have been designed to prevent
migration. Consider self healing cement or cement insurance packers for critical jobs.
In case of expected losses during the cement job effective loss prevention chemicals
like fibres are added to the slurry or lightweight slurries have to be designed.
Count the number of tank volumes pumped while displacing, in addition to using flow
meters and/or stroke counters (applicable when using displacement tanks on cement
unit while displacing).
Monitor and estimate cement volume returned to surface by using rig stroke counters
and/or displacement tanks and report on DDR.
Reciprocate production casing while displacing the cement to ensure a better cement
bond. If an increase in hole drag is noticed, the pipe has to be moved immediately
down to prevent the casing be landed off depth. Reciprocating casing depends on
historical results and may vary by area.
Rotate production liner while displacing the cement to ensure a better cement bond.
Plug bump pressures monitored closely and noted in the DDR. The pressure shall not
exceed 80% of casing or float shoe burst pressure. Do not exceed the plug pressure
rating as per table below or as per manufacturers specification.
Plug Size
20 to 16 14 to 10-3/4 9-5/8 to 7 5-1/2 to 5 4-1/2 to 4 3-1/2
[inch]
Plug pressure
207 414 552 469 414 345
rating [bar]
After bumping the plug casing and liner shall be pressure tested. Increase the bump
pressure to the calculated casing test pressure and test for minimum 5 minutes. As far
as possible no test pressure shall be applied to cemented casing.
If on liner jobs the plug is not bumped after theoretic displacement volume is pumped,
pump maximum half of the shoetrack volume as additional displacement. For surface,
intermediate and production casing we pump until we bump.
If the floats in the casing string do not hold, the string shall be pressured up to the
differential pressure between the cement and the displacement fluid and held until
surface cement samples have hardened.
If returns are lost while displacing, the pump rate shall be staged to attempt to regain
circulation but no more than 30 minutes shall be taken. Be aware of U-tube effect
when cement is displaced inside casing or stinger. (In case of losses, consider
lowering displacement rate based on remaining volume of displacement and
thickening time of cement slurry).
Cementing parameter (slurry density, pump pressure, pumping time) have been
recorded during the job and print outs are available.
Comments:
____________________
Appendix 4 Summary
Casing Type of
Application Density Additives
size slurry
(inch) (sgu) (ppg)
Bentonite and Antifoam,
20, Lead 1.5 1.55 12.5 12.9 Calcium Chloride, if
Surface
13 3/8, necessary
casing
9 5/8 Antifoam, Calcium
Tail 1.8 1.9 15.0 15.9
Chloride, if necessary
Bentonite and Antifoam,
Lead 1.5 1.6 12.5 13.3
Retarder, if necessary
Intermediate 13 3/8, Antifoam, UniFLAC at 2
casing 9 5/8 kg/t (providing moderate
Tail 1.8 1.9 15.0 15.9
FL control < 200 ml API),
Retarder, if necessary
Antifoam, Bentonite,
UniFLAC at 3.5 kg/t
Lead 1.5 1.7 12.5 14.2 (providing moderate FL
control < 200 ml API),
7,
Production Retarder, if necessary
6 5/8,
casing Antifoam, Bentonite,
5
UniFLAC at 5 kg/t
Tail 1.75 1.9 14.6 15.9 (providing excellent FL
control < 50 ml API),
Retarder, if necessary
Antifoam, Bentonite,
7, UniFLAC at 5 kg/t
Liner 5, Tail 1.75 1.9 14.6 15.9 (providing excellent FL
4 control < 50 ml API),
Retarder, if necessary
Futur, Antifoam, GASBLOK
7 Lead 1.7 1.8 14.2 15.0 MT (120 l/t), Dispersant (2
l/t), Retarder
9 5/8, Antifoam, GASBLOK LT (80
Gas
7, l/t) < 72 degC or
migration
6 5/8, GASBLOK MT (180 l/t) 72
Tail 1.8 1.9 15.0 15.9
5 , 150 degC, Dispersant (3-
5, 5 l/t), Retarder, if
4 necessary
Antifoam, FLAC 8%,
Bentonite 1.5%, Perlite
9 5/8, Lead 1.25 10.4
6.8%, Calcium Chloride
7,
3%
Lost 6 5/8,
Antifoam, Bentonite,
circulation 5 ,
UniFLAC at 5 kg/t
5,
Tail 1.7 1.9 14.2 15.9 (providing excellent FL
4
control < 50 ml API),
Retarder, LCM added
LiteCRETE, Antifoam,
GASBLOK MT (150 l/t),
7 Lead 1.4 1.45 11.7 12.1
Dispersant (2 l/t),
Lost Retarder, LCM added
circulation 9 5/8,
and gas 7, Antifoam, GASBLOK LT (80
migration 6 5/8, l/t), GASBLOK MT (180
Tail 1.8 1.9 15 15.9
5 , l/t), Dispersant (3-5 l/t),
5, Retarder, LCM added
4
Prepared by WEP
Author:
Verified:
In case the expected formation strength is low and tolerance for error is very small, a
Limit test can be carried out. The limit test is a FIT to a fixed pre-set number and has to
be high enough to demonstrate that the next section can be safely drilled ahead.
Formation strength tests are justified for a majority of cases below all casing shoes, they
may however be unnecessary if no hydrocarbon-bearing or over-pressured formations are
to be penetrated in the following hole section, and when drilling in an area with good
knowledge of the formation strength.
The information obtained will provide data for calculating the maximum allowable annular
surface pressure (MAASP, for casing setting depth) and the maximum mud weight
equivalent (for kick tolerance). The FIT shall be carried out below each pressure
containing casing shoe on exploration and production wells.
Generally two methods for taking an FIT are commonly used: static and dynamic.
Sometimes the static method is called the Hesitant method. The dynamic or continuous
pumping method is has an increased risk to fracture the shoe.
Petrom standard is to carry out a static FIT i.e. where small increments are pumped and
each accompanying pressure increase and remaining static pressure is plotted on a scaled
paper to detect a deviation from the straight line.
The point at which the pressure/ volume plot deviates from a linear relationship (leak-off
point) should be taken as the last measure point on the straight line. No extrapolation
should be performed that would yield an increased formation strength.
All formation strength tests should be carried out with the lowest drilling fluid density
necessary for primary well control of the formations exposed during the test i.e to achieve
an overbalance at the anticipated reservoir pressures below the shoe by approx. 15 bars.
In one case a failed FIT led to hydrocarbons migrating along the created fracture to
surface. The reason the failure occurred was because the mud weight was not verified and
the job was not properly supervised.
On another occasion the FIT was continued until the formation broke because it was
thought to be correct procedure. Better training, awareness, basic understanding and
proper supervision would have prevented this.
When insufficient new hole is drilled, the FIT will be taken from a cemented hole. For
shallow set casing shoes, this results in an unrealistically high FIT, up to lithostatic
gradient (~2.2 bar/10m). Thus always keep a good check on the drillpipe tally, casing
tally vs. amount of rathole, signs of when the shoe was drilled (punch through) and
ROPs.
When drilling out 3-5 m of rathole, the BHA or near-bit stabilizer may become stuck due
to loose cement fragments falling from just underneath the shoe or because of unmilled
sections from the float shoe itself. Hence, reduce drilling parameters (WOB, RPM,
pumprate) when drilling out last few meters of the shoetrack and rathole.
In situations where good zonal isolation behind the casing is critical to the wells success
in both short and long term, it is recommended to carry out the formation strength test
using a retrievable packer to avoid the creation of micro-annuli.
When testing below the intermediate casing strings, the annulus outside the casing being
tested should be left open and observed for returns. Do not forget to close the side outlet
valves following the test.
Ensure that the hole is circulated clean and that the mud in use is properly
conditioned to have uniform density: mud weight in = out.
Ensure that the cement pump is operational and in good working condition. It
should also have a calibrated gauge tank and the capability to pump small volumes
(25-50 litres/minute) in small steps.
Ensure that table and graph are prepared prior to job to record and plot pumping
pressure vs. volume of mud pumped.
Cement pump gauge to be confirmed in good working order and ensure data is
recorded electronically or on a chart recorder.
Ensure that a shut-off valve is installed between pump and pressure gauge.
Ensure that a bleed valve is installed between shut-in valve and pump. This valve
will be opened during shut-in period to bleed off pressure.
Ensure that a well calibrated pressure gauge is available for the job.
Ensure that on surface and intermediate casing, pressure test is performed with
the casing-casing annulus filled up and the valve open to observe for possible
channelling or communication.
16. Stop pumping. Do not increase the leak-off pressure to formation fracture!
17. Check pressure to stabilize for a maximum of 15 minutes. Record the volume
pumped.
18. Bleed off pressure until 5 bars and take returns back into cementing displacement
tanks. Stop and record volume in the tank, determine volume lost into the
formation. If there is a float valve in the drillstring, the pressure has to be bled
down from the annulus via the choke manifold.
19. Note the cumulative mud volume pumped, volume lost to the formation, the final
pumping and final static pressures.
20. Keep well closed in to verify that a constant pressure has indeed been obtained.
21. Bleed-off remaining pressure, check annulus pressure is zero.
22. Open BOPs when all pressure is bled off.
23. Rig down lines and line up for drilling ahead.
Graph below explains fracturing and other definitions. Unless otherwise indicated, do NOT
exceed leak-off! An extended leak-off test is only carried out if specific data is required for
certain types of borehole stability or fracture mechanics analysis.
13.6 Calculations
Effective Mud Gradient (EMG):
EMG = { LOP + (CSD x MG)} / CSD [bar/m]
Where:
LOP = Leak Off Pressure [bar]
CSD = Casing Shoe Depth [TVD m with reference to Rig Floor)]
MG = Mud gradient [bar/m]
RIG NAME
PRESSURE
VOLUME PUMPED
8
1
14 Well logging
Prepared by WEP
Author:
Verified:
14 Well logging
Logging is the systematic way of recording the information required to evaluate formation
characteristics of a well being drilled. Logging tools measure certain properties of the
formation, the interpretation of which can yield information on properties such as density,
porosity, permeability, lithology, formation pressure etc.
It is the plan of PETROM to obtain the formation evaluation information in the most
economical and efficient manner with due regard to safety of personnel and the
environment. Target is to log the hole in one run by using multiple logging tools in one
toolstring. It is important to place radioactive tools at the front of the toolstring to avoid
activation of the formation before non-radioactive tools have logged the formation.
The data obtained from well logs shall be used:
To obtain the information for drilling engineering purposes including presence of
shallow gas or hydrocarbons and pore pressure analysis
To obtain reservoir and production engineering data
* In case a Wellsite Geologist is not present at the rig site, a logging witness shall take all
responsibilities to ensure date accuracy.
the PETROM Drilling Supervisor to ensure the hole and mud condition remain
stable.
The Drilling Supervisor shall verify that the hole is dead and in good condition prior
to logging operations.
The hole shall be circulated over the trip tank during logging operations. The Driller
must ensure that the hole is maintained full throughout and record the trip tank
volume every 15 mins and monitor the trends whilst running in and pulling out of
hole. The mudloggers should also monitor fluid levels during this period.
The required logging interval shall be discussed and confirmed with the Logging
Contractor. Any special requirements shall also be noted.
Review with the logging engineer the previous log suites or correlation logs to
determine expected Spontaneous Potential values in clean sands, Gamma Ray
values in shale and expected resistivities and porosities in zones of interest.
The scope of responsibilities for the different parties involved in the logging
operation shall be known and clearly communicated.
It is important to list all the reference depths before commencement of logging.
The drilled depth at which wireline logging is to be performed will be advised by
Petrom following evaluation on all available data.
Ensure the run order is optimized in order to reduce NPT (Petrom DSV
responsibility).
Ensure that the log header information is correct. This should include information
on well name, field name, latitude & longitude, RKB elevations, well depth, casing
sizes and weights, mud type etc.
If fluid samples are to be taken, ensure that an adequate supply of containers are
available.
Also ensure that a liquid measuring vessel, a gas meter and resistivity meter are
available.
A copy of the printouts for both the master calibrations and the wellsite
calibrations performed on the logging tools should be available.
Only the Logging Contractor shall handle radioactive material and explosives.
The logging cable strength, calculated tool weight and maximum pull limits shall be
given to the Drilling Supervisor prior to start of logging operation.
The logging contractor shall ensure that fishing equipment is available on the rig
for all logging tools.
Mud samples shall be taken from both the pits and flow line just before the end of
circulation prior to a logging job for analysis and resistivity measurement.
A logging report shall be delivered at the end of logging program by Wellsite
Geologist/logging witness.
14.3 Guidelines
14.3.1 General
The following guidelines should be adhered to during all logging operations:
Calibration records must be made before and after each logging run.
The wireline logging depths shall be set to zero at surface and checked when
pulling out to surface. Additional check shall be made at casing depths and at TD.
Always switch on the logging tools (except density and neutron pad tools) while
RIH and make a log down. This is to ensure that the logging tools are functioning.
If tools hangs up while running in and the section has not been logged before, log
out of the well. When anticipating poor hole conditions, always log in and out of
the well to secure data.
It is recommended to run the repeat section prior to the main log, so any tool
problems can be immediately apparent. This should be run at or near the casing
shoe or over any reservoir interval.
If running cable in drillpipe, the drillstring should be monitored for compression or
buckling especially if tight holes are encountered.
A tension curve should be presented on every log run.
If the well is very hot, the likelihood of tool failure is increased. In such cases, it is
important that a downlog is performed as the tool is run into the hole and the main
log started as soon as the tool reaches the bottom of the well.
The cable head weak point shall not be broken when radioactive sources are in
hole.
10. Lower SES below drill floor. Run in hole wireline to 150m above downhole latching
assembly.
11. Circulate slowly through downhole latching assembly with approx. 10 bars and
spot 150m of fresh water pill through the drill pipe above the lower latching
assembly.
12. Latch onto toolstring, check resistance of conductor pairs to confirm proper latch,
then power up and check that the tool is functioning correctly.
13. Pull SES above drill floor and install SES line clamp. Install cable clamp above SES
at bottom of first joint of drill pipe. Toolstring is now ready to be lowered into
open-hole. Constant clear communications should be maintained between the
driller and the winch operator. The cable must not slack off.
14. Run in hole with drill pipe in casing at 2 min/stand and 3 min/stand in open hole.
Pipe rotation must be avoided to prevent damaging the wireline.
15. The winch operator will follow the pipe in hole and maintain a tension of 450 kg
above line weight at all times. Start logging at rate of 1 stand every 3 minutes.
16. Fill up drill pipe every stand and break circulation every 15 stands. Stop drill pipe if
any indication of being stuck.
17. Stop the drillpipe when the bottom of the toolstring is approx. 5m above TD. Do
not tag to avoid accidentally crushing the toolstring.
18. Log up (repeat section). Pull out of hole and continue to connect the top drive and
circulate every 15 stands for 5 minutes. Unlatch and retrieve wet connect.
Disconnect SES and laydown cable.
19. Pull out of hole with drill pipe and logging tools.
20. Rig down wireline sheaves.
Wet connects
The primary depth control is the logging contractors depth measurement system,
with a secondary check being the casing shoe depth and the cased hole overlap
from a previous logging run.
Depths measured with drillpipe may be significantly different from Wireline depth.
Depths measured using casing information are much closer to Wireline depths. The
driller, mud logger and wireline engineer should agree within about 1m to the
correct depth.
On the first logging run into the well, the tool should be zeroed at the Rotary Kelly
Bushing (RKB) or the Derrick floor. Subsequent logging runs over the same
interval should be tied into the first run.
In the event of a significant difference between the drillers and loggers casing shoe
depths, always look at the encoder wheels. Nothing should be allowed to be deposited on
the wheels. Additionally, the following checks should be undertaken:
Were the logging contractors depth control procedures applied correctly?
Was an excessive shift applied to tie-in to the previous run?
Is the casing tally correct?
The difference between loggers depth and Drillers depth shall be established immediately
after logging operations. When discrepancies exist between these depths (such as during
washing perforations or tagging bridge plugs or packers), logging depths shall be reported
as Wireline (W/L) in the Petrom daily drilling report.
A reference depth run (GR-CCL) shall be performed before perforations.
2. If a tension meter is installed in the top of the tool and does not register overpull,
then the cable or top part of the logging tool above the tension meter is stuck. If
this happens, continue the following:
Make a stuck point estimation by stretch measurement.
Pull up to cable tension limit slowly, checking for any response on the cable
head tension meter.
3. If the tool does not come free after the actions described above, additional
attempts to work the tool shall be considered in consultation with the Logging
Contractor.
10. A little strain is pulled on the cable and the C-plate is removed.
11. Lower the drillpipe through the rotary and set it in slips.
12. The C-plate is then placed on top of the drillpipe tool joint sticking up in the rotary
table.
13. Release the spearhead overshot pulling it to the monkey board and feed it into the
next stand of drillpipe.
14. Repeat the above procedure until the overshot is within a short distance of the
fish.
15. A special circulating head or stuffing box is installed on the last stand.
16. Break circulation to clean the end of the pipe, the overshot and the top of the fish.
17. Record pump strokes per minute versus pressure to get indication of when the fish
is caught in the overshot.
18. Once it is confirmed that the fish is caught, clamp the cable hanger on the cable
below the rope sockets.
19. Remove the rope sockets and set the hanger in the elevators.
20. The weak point is broken by pulling on the cable with the elevators.
21. The cable is pulled out of the drillpipe and the string pulled out of hole with the fish
attached.
NOTE: It is unsafe to break the weak point in a wireline by pulling the winch. This is
because the greatest tension in a wireline is at surface. If the line breaks at surface in
comparison to underground the recoil will be violent.
1. Indications of Permeability
Several logs give indication of permeability. Though permeability cannot be directly
calculated from logs, these indications will give a basis for further analysis.
SP deflection away from the shale baseline (the direction depends on the Rmf /
Rw ratio).
Invasion profile on resistivity logs (Rxo / Rt on the Rmf / Rw ratio).
Low Gamma Ray counts.
Mudcake indications of the Caliper log.
Separation of the Micro-Normal and Micro-Inverse curves.
2. Porosity Estimation
The quickest way to calculate porosity is by using the Density and/or Neutron logs
depending on the lithology. Density is generally scaled in g/cc while the Neutron is in
porosity units. In sandstones, porosity is calculated from the density log using a matrix
density of 2.65 g/cc. In carbonates, the FDC/CNL crossplot (provided in chart books) is
used to estimate the matrix density. The fluid density is estimated based on the salinity of
the mud filtrate.
3. Lithology Indicators
A potential reservoir rock can be differentiated from a non-reservoir rock using the GR,
SP, calliper and porosity logs. The best way to determine lithology, formation tops and
exact formation depths is through a combination of wireline, MWD and mud logs. It is
always the best to use as many logs as possible.
Location of transfer of sources to tool is determined by crew (either catwalk or rig floor).
This area is to be cleared during the transfer process.
The wireline crew shall ensure that the area in which explosive systems is connected to
the wireline, armed, disarmed or shot and disconnected from the wireline is cleared of all
personnel not necessary for the operation. The line of fire shall be kept clear of all
personnel while performing these functions.
Preventive method: wireline cable area to be barricaded and only service company
personnel to deal with cable.
Devices used to increase chances of RIH and reducing risks of stuck tools
To prevent sticking, the engineer carefully plans the job, determining the conditions of the
well and adapting the speed and technique to run in and pull out safely.
If, while evaluating the logging environment, the engineer thinks that there might be
some risks, the client shall be advised of the dangers of such jobs, and the engineer and
the client shall agree on the right actions to be taken.
It is the responsibility of the service company field engineer or field specialist to ensure
that:
1. Data acquisition shall be performed following standard operating procedures.
2. Data processing shall be performed following standard operating procedures. Data
resulting from processing shall be clearly marked and traceable.
3. Data interpretation shall not intentionally produce results inconsistent or biased
with the measurements or processed data. Due to the inherent element of
judgment involved in data interpretation, employees performing such services are
permitted to make choices of parameters or interpretation methodology, provided
it is not done to alter or bias the final product intentionally. Results of
interpretation activities shall be clearly marked and traceable.
4. Data storage and delivery shall conform to pre-defined standards. Data storage
shall ensure no degradation of the intrinsic quality of the data.
Make up toolstring
1. Move tools from wireline unit to catwalk using wireline cable. Flag man on the
catwalk giving hand signals to winch operator.
2. Move CSES, Stabilizer, DWCH and sheave wheels to catwalk. Flagman present on
the catwalk giving signals to crane operator.
3. Pick up tools from the catwalk using a tagger line. Install on sling in elevators with
shackle to lower the WL tools into the well.
4. Make up toolstring using elevators
5. After making up the DWCH hold in rotary table using 4 slips and dog collar.
Remove top hat and makeup plate.
6. Connect PWCH (pump down head) for tool checks at surface
7. Remove head (PWCH)
8. Connect 3 IF lifting sub (pup-joint) to lift toolstring.
9. Clear rig floor for personnel. Lift toolstring and load RA sources.
10. Lower the toolstring up to the DWCH.
11. Disconnect lifting sub and connect first stand of pipe.
12. RIH as per instructions below.
Running in hole
1. Do not rotate drill pipe - Lock Rotary
2. 3 min/stand RIH speed.
3. Minimum dope to be used only on the pins.
4. Rabbit all pipe / cross overs etc. min 2.4.
5. Stop every 10 stand stands and circulate and fill pipe
6. Service company crew to prepare CSES readily available on catwalk.
7. If any hang-ups observed STOP and contact service company engineer.
8. Ensure pipe remains topped up
9. Avoid landing string heavily in the slips and sudden starts / stops
10. Take care going past crossovers and BOPs.
11. Max allowable compression on service company tools 3000lbs
12. Stop 2 stands above casing shoe.
13. Circulate 1,5 Bottoms/Up or as necessary to eliminate gas. FLOW RATE 1000l/min.
Check the flow rates to detect packing of ports.
14. While circulating service company crew rigs up the sheave wheels, Stabilizer, CSES
and snatch pulley.
Logging
1. Log down from 2 stands above casing shoe to 5 m above TD (DO NOT TAG TD with
the TOOLSTRING)
2. Log up back to 1 stand above casing shoe.
3. Geologist to take decision on the repeat section.
4. RIH below the repeat section bottom depth
5. If required, dependant on gas shows, start circulation as per company man
decision. Flow rate not to exceed 200 l/min as cable damage may result.
6. POOH until the CSES reaches drill floor. Snatch block to be removed one stand
before.
7. Service company will unlatch and POOH the cable and PWCH.
8. Unlatch procedure as per instructions below
Unlatch - POOH
1. Disconnect CSES and stabilizer (use only chain tongs).
2. POOH drill pipe. 2 min/stand excluding connections
3. When DWCH reaches surface service company crew to be announced and present
on drill floor.
4. Clearing of all personnel from drill floor for unloading of RA sources.
5. Tools at surface.
6. Rig down tools using reverse procedure of rigging up.
Prepared by WEP
Author:
Verified:
In the appendix a Pre-job information sheet can be found that needs to be filled in before
any fishing job.
A successful fishing job considers the economics of fishing. Confirm with the office
the number of days that can be spent fishing before it is cheaper to re-drill the
section.
+ +
=
+
= ( )
The above formula does not consider the reduced probability of each attempt.
Or:
= +
1.43
=
( )
= 0.4003 0.7847
Time is of the essence in fishing operations. Keep a tank of premixed spotting fluid
on location if working in areas where differential sticking often occurs. Spotting
products are all different and have various methods of working from lightening the
annulus fluid, loosening or removing filter cake and increasing viscosity. Once the
fluid is placed there should be no jarring or working pipe.
Backing off
For backing off, check that all required crossovers, subs and handling equipment
are available to apply left-hand torque and overpull while having the back off shot
run in with E-line.
Consider maintaining string shot equipment on the rig in remote locations.
In cased hole, dont mill too long in one place.
Never rotate the fish out of the hole since it may unwind and drop out of usually
right-hand release overshots.
Twist off
If a twist-off occurs and conditions allow, the hole shall be circulated clean and
mud conditioned prior to pulling out of the hole.
Where a twist-off has occurred, the fish shall be tagged prior to pulling out of the
hole and the pipe shall be strapped on the trip out.
15.2 Checklist
Make detailed diagrams of Top Fish prior to running in the hole: determine size,
shape and condition of the fish.
The maximum allowable pull for all fishing tools and associated equipment shall be
determined.
Internal diameters of fishing tools to be run shall be checked to verify that back-off
tools can pass through.
Discuss with fishing company the fishing BHA: grapple size, jar & accelerator
placement and weakpoint. Fishing jars should be placed as close to the overshot as
possible, accelerators in collars to allow needed hammer mass below. Consider
including a bumper sub. When running spears or overshots, bumper subs must be
run, and in open hole lubricated bumper subs are recommended.
Soft blade or non-rotating stabilizers are required inside casing, only when milling.
Stabilizers can interfere with jarring and cause additional problems.
The pull shall be limited to 85% of the minimum yield strength of the weakest tool
joint in the string.
Be aware of all drilling string and components and fishing tools fatigue life (mean
hours between failures).
Remember to rotate drillpipe connections on trips.
Always be aware of the capacities of the entire string and BHA. Ensure that
displacements are always known. In particular when fishing large OD components
or balled up assemblies, be aware that hole fill may be problematic.
Prior to connecting to the fish, the following information shall be obtained:
o Establish circulating pressures and rates
o String weight up/down and rotating string weight (with and without
circulation)
o Free rotating torque of string.
o Pipe stretch and stroke of bumper sub, jars, etc.
After freeing the fish, circulate bottoms up before POOH, if circulation is possible
through the fish.
15.3 Tools
Below is a list of fishing tools that are commonly kept on the rig site for various hole sizes
or which can be loaded out on very short notice.
Type of Fishing
Type of Fish Names of Tools
Tool
Recovery of non- Junk basket
tubular fish Circulating junk basket
Reverse circulating basket
Magnet
Wireline spear
Junk sub
Fish destruction Milling shoe
Packer retriever
Section mill
Jet bottom-hole cutter
15.3.6 Mills
Mills are extremely varied and have multiple uses and designs, this is where the
knowledge and skill of the fishing company (operator) should be used to pick specific mills
to meet the needs of the fish, well and other issue at the time.
Prior to jarring always mark the string at the level of the rotary table.
Tie off drill pipe in the derrick that will not be needed, clear the V-door and cat
walk of un-needed pipe and get all pipe on location accounted for and stowed. You
must know your exact count for all pipe, heavy weight, and collars on location.
Before jarring, clear rig floor of unnecessary personnel.
Every 6 hours of jarring, inspect derrick equipment and check for loose and
unscrewed nuts and bolts.
If utilizing spotting fluids, caution should be taken to prevent reducing hydrostatic
pressure and allowing an influx of wellbore fluid or gas.
Always run a pack off in the overshot.
Circulate over fish with the pump at idle, watch for pressure increase as an
indication of latching on.
Attempt to circulate through fish prior to jarring.
Jar with kelly or top drive on string. When this is not possible, elevator latch
should be secured with rope or chain.
First attempt at back-off should be done one full joint above stuck point. If
unsuccessful, attempt back-off one stand above stuck point.
Ensure to plan the fishing operation with the relevant rig personnel and hold a
toolbox meeting to discuss procedure and safety
Taper taps are made of very brittle material and break easily. They should only be
run as a last resort, together with a safety joint, since they do not have an
emergency release.
Spiral grapple type overshots and spears will handle heavier loads than the basket
types. However, the spiral grapples are easier to damage and break while getting
onto the fish, due to the brittleness of the spiral grapples. A mill guide should be
run below the grapples if possible in order to dress off the top of the fish before
engagement.
If string shot equipment is not available, consider manual back-off only as last
resort. Drill collars are seldom if ever backed-off this way.
If the circulating sub is run into the fishing string, strip down sub and install new
shear pin prior to use (especially during round trip after jarring).
Ensure that elevators are latched around the pipe and slackened off under a tool
joint with the hook locked when torque is being applied to the string.
Care should be taken when applying torque or releasing it from the string. Ensure
that no torque remains in the string when it is picked out of the slips, unless the
pipe is properly held with a back-up tong.
Backing off is a non-routine operation and as such, all procedures must be performed
under the direct supervision of the Fishing Tool Supervisor and Toolpusher.
where:
Lf = length of free pipe (m)
l = differential stretch between two marks from overpull (T2 T1 in (mm))
Pdp = weight per meter of pipe (kg/m)
T2 = Overpull two (Ton)
T1 = Overpull one (Ton)
Lf, will give you the length of free pipe thus allowing you to determine the location
of the stuck point.
When possible the fishing tool operator should be on location during the electronic free
point indicator run.
The most accurate and commonly used technique for determining the free point is
through the use of an electronic free point indicator. The electronic free point indicator
measures the axial and torsional strain in the pipe body through application of tension
and torque to the drill string. Provided the pipe is completely free, a fixed and measurable
degree of strain will be recorded by the system's electronics. Once the degree of strain
diminishes, or reduces to zero, the pipe is stuck. To achieve a successful back-off, the
pipe must be 100% free!
The following procedures and guidelines are to be followed to determine the free point
using electronic instruments. The free point indicator can be run in combination with the
back off shot to reduce the number of wireline runs required.
Calculating the required surface tension and how this tension is applied, prior to firing the
string shot, is critical to successfully backing off the pipe at the intended depth. If too
much tension is applied, or if the pipe is in compression, it may not back off. If it does
back off, it will most likely be further up the string and not at the planned depth.
To determine the necessary surface tension to optimise the tension at the back-off point,
the following information is required:
Pickup, slack-off and off bottom rotating weights of the drill string prior to
becoming stuck.
o These measurements should have been taken with the pumps off. If the
pipe became stuck while tripping, the required figures may have to be
estimated based on previously recorded pickup, slack-off and rotating
weights recorded while drilling at the depth of the stuck point.
The weight per foot and length of individual components of the drilling assembly.
The density of the drilling fluid in the well
Once the hook load required to put the back-off point in zero tension has been
determined, an additional 2 Ton of overpull should be applied to ensure that the pipe is in
tension rather than compression.
A generalised equation for determining the correct weight indicator reading when the
string shot is fired is as follows:
= +
100000
where:
T = Weight indicator tension (103 daN)
P = Weight in mud of free length of drill pipe plus traveling block, hook, etc. (103 daN)
HP = Hydrostatic pressure at back-off point (kPa)
S = Area of mating surface of tool joint (cm2)
(From Drilling Data Handbook, K24 and K25)
The correct amount of right hand torque to work down the drill string will depend on
several factors including well depth, wellbore profile, and degree of hole drag in both
tension and torsion. The correct string tension to be applied at the surface in order to
effectively work torque down to the back-off point should have been determined while
locating the free point. In this regard, it does not necessarily follow that the pipe should
be worked between the calculated pickup and slack-off weights at the back-off point. For
this reason the torque measurements taken while determining the free point should be
used as an indicator of the correct surface tension to use for applying both left hand and
right hand torque.
When working right hand torque down the hole, the following practices are to be followed:
The amount of right hand torque that must be worked into the pipe should be
sufficient to generate a full scale torque reading on the free point tool at the
planned back-off depth plus 30%. This will ensure that maximum left hand torque
can be applied to the pipe when the string shot is fired. In general there should be
one round per 1000 ft, the pipe should be worked until all of the rounds placed
into the string return, if 9 rounds are placed in the pipe, nine rounds should come
out when released.
The torque is to be worked down the pipe from surface to the free point. Since tool
joints can only be torqued correctly with minimum axial tension, the pipe is to be
raised and lowered between the calculated free pipe pickup weight at the planned
back-off point and zero surface tension while progressively increasing the applied
right hand torque.
The torque is to be applied in 3 - 4 steps until the maximum make up torque has
been worked into the string. Be certain to record the number of total turns
necessary to achieve maximum make up torque, as well as the number of turns
that can be anticipated when the required left hand torque is applied.
Complete make up of all connections will be indicated when no loss of trapped
torque occurs as the pipe is cycled between the range of pick-up and slack-off
weights being used.
Release the right hand torque gradually to avoid unscrewing connections higher up.
In certain cases where the pipe has backed off high, it may be desirable to pull out of the
hole and run an alternative fishing assembly. This will be decided on a case-by-case basis
following consultation with the Drilling Superintendent.
Calculated weight indicator reading (T) when string shot is fired (103 daN):
28000 43.34
= + = (52 + 8) + = 72 103
100000 100000
Therefore, prior to firing the string shot, the pipe will be slacked off to below the initial
slack-off weight and then picked up and tensioned to a weight indicator reading of 72 + 2
= 74 x 103 daN.
It should be noted that in order to apply the correct pick-up weight, the weight of all tools
and equipment that were suspended below the hook are accounted for in this pickup
weight calculation. For instance, if the Kelly has been removed, this weight must be
subtracted from the required pickup weight.
Prepared by WEP
Author:
Verified:
2
1. Pick up the 9 meter (30 foot) outer core barrel bottom section from the catwalk
using the drill floor winch.
2. Hoist the core barrel into the V-door and latch the drill pipe elevators around the
elevator lift sub.
3. Slack off on the upper lifting sling and remove the sling from the core barrel.
4. Ensure that the top stabilizer and lift sub connections are chain tong tight and that
each joint is chalk marked for safety.
5. Hoist the core barrel into the vertical position using the blocks or top drive.
6. Control the motion of the core barrels lower end while coming off of the V-door
onto the rig floor.
7. Break out and remove the outer barrel protector using chain tongs.
8. Screw the Core Bit onto the bottom section of core barrel and install the bit
breaker.
9. Set the core barrel down in the rotary table and make up the connection between
the Core Bit and bottom stabilizer, and the connection between the bottom
stabilizer and outer barrel to the recommended torque. (See specifications for
recommended torque specs).
Note: Ensure the rig tongs are positioned correctly above and below the connection of the
outer barrels (at least 6 below the box) during all make-up procedures
10. Remove the bit breaker and lower the core barrel into the hole. Set the slips 23
feet below the connection between the outer barrel and the top stabilizer. Leave
enough room to install the drill collar clamp.
11. Make up the connection, between the outer barrel and the top stabilizer, to the
recommended make up torque using the rig tongs. Lower the core barrel to
position the drill collar clamp 2 above the slips. Make up the drill collar clamp
below the stabilizer blade.
12. Break out the elevator lift sub and hoist the blocks or top drive to expose the inner
barrels approximately 1 foot. Install the inner barrel clamp one foot from the top
of the inner barrel. Break and screw out the elevator lift sub.
13. If a core barrel longer than 9 meters (30 feet) is required, repeatedly pick up the
required amount of 9 meter (30 foot) middle sections from the catwalk using the
drill floor winch to make up the required amount of core barrels.
14. After picking up the bottom section and required amount of middle core barrel
sections, install the elevator lift sub into the top section of the core barrel on the
catwalk. Follow the above procedures to pick up the top section of core barrel onto
the rig floor.
15. Using chain tongs, remove the outer barrel protector exposing the inner barrel.
Remove the inner barrel protector. Lower the blocks to mate the upper and lower
sections of inner barrel. Use chain tongs to screw the inner barrels together and
pipe wrench them tight using a 6 snipe. Do not use rig tongs to tighten the
inners as this may crush the inner barrels.
16. Lift the inner barrel assembly and remove inner barrel clamp. Lower the blocks or
top drive to mate the outer barrels. Use chain tongs to screw the outer barrels
together. Use the rig tongs to torque the outer barrels to the recommended torque
specs.
17. Lower the blocks and proceed to torque all remaining connections on the core
barrels up to and including the safety joint using the above procedures. (If running
a barrel that is longer than the rigs hoisting limit, a 12 lead sub must be installed
between the safety joint and inner barrels in order to check lead).
18. If capable, hoist the core barrel out of the hole, install the hole cover and inspect
the lead. With steel inner barrels, the lead should be 1/8- 1/4. When using
aluminum inner barrels bottom hole circulating temperature must be determined
to allow for thermal expansion. Correct thermal expansion rates for aluminum
inners can be obtained from the Thermal Expansion Compensation Chart. Adjust
the LAS for a normal lead plus the correct amount of thermal expansion. If there
is any doubt as to the amount of thermal expansion, a slightly greater lead would
be preferable to a smaller lead. Ensure that the inner barrels turn inside the outer.
Note: It is essential that the coring drop ball is NOT dropped until bottom has been
tagged and it is determined that the hole is in good condition.
8. Hold A Safety Procedure Meeting When Circulating Bottoms Up. Cover The
Following Points:
What action to take if coring has to stop due to rig equipment failure.
The procedure to follow for making a connection.
The potential use of breathing apparatus, in case of H2S
What parameters to observe while coring.
The importance of keeping all parameters as constant as possible (except for
changes requested by the 3rd party Coring Technician).
Note: Reduce the flow rate so that the standpipe pressure is no more than 6000 kPa until
the ball seats. This procedure will eliminate any shock on the formation and the aluminum
inner barrels (if used) when the ball reaches the ball seat. It is possible to collapse the
inner barrels if the flow ports of the core head are plugged when reaming to bottom and
the flow rate is too high.
1. Rotate the drill string at approximately 40-60 RPM and adjust the flow rate to the
rate desired for coring.
2. Ensure the weight indicator has been zeroed.
3. Slowly lower the core barrel to bottom.
4. Tag bottom and start coring. Mark the Kelly or drilling stand with a meter stick
while coring. This will be beneficial in the event that the Pason malfunctions.
5. Apply a starting WOB of 2000daN (4400 lbs) to allow the Core Bit to cut a pattern.
6. Maintain these parameters until approximately 0.6 of a meter of core has been cut.
Note: Do not allow WOB to drill off as this may damage the core or cause jamming.
Record the differential of the off and on bottom pump pressure
7. Increase the WOB in increments of 1000daN (2200 lbs) while observing the rotary
torque response.
8. Adjust the RPM to the desired level.
Note: 3rd Party Coring Services representatives are on site to determine optimum coring
parameters.
Note: If drilling fluid becomes gas cut and reaches an unacceptable level, coring will cease
until the gas levels have dropped to an acceptable operating limit. This will require the
core barrel to be lifted off bottom to circulate the gas cut drilling fluid out of the well bore.
9. Making a Connection
It is required to break the core off bottom to make a connection on drilling rigs
without a top-drive.
10. To make a connection the following steps should be taken
Stop rotating the drill string, minimizing any backspin.
Slow the mud pumps.
Slowly pick the weight off of the core bit until an over pull is observed.
Pull to approximately 10,000daN (22,000 lbs) over the total of string weight
and hole drag. If the core does not break, hold the string at this level and wait
a few minutes for the core to break. If the core still does not break, kick the
mud pumps out and back in. This should in most cases break the core. If no
over pull is observed, pick the drill string up slowly. If core seems to be slipping
in the catcher, lower the string back to bottom and try again to get a core
break.
If excessive over pull is applied it may not be possible to release the core
catcher off the core to resume coring.
Once the core has broken pull the drilling stand up out of the bushings. Stop
the mud pumps and make the connection as per drilling contractor's
procedures.
Note: It will be necessary to make the connection as quickly as possible to reduce any
differential sticking and gas entering the well bore.
11. Once the connection has been made, start the mud pumps and re-establish the
same coring parameters as before the connection.
12. Compare the pump pressure and torque to before the connection and record the
differences and any observations.
13. Continue coring, keeping all the parameters constant, until the barrel is nearly full.
Note: It is poor practice to completely fill a core barrel. If the core is compacted into the
inner barrel it could be damaged by compression.
Note: Ensure the core barrel has been pulled out of the cored hole before circulating
bottoms up. The coring technician and the operators well site supervisor will determine
circulation rate.
2. Circulation should continue until gas levels are at an acceptable level and sufficient
geological samples have been collected.
3. CAODC and Company Specific Flow check and trip procedures apply.
Note: The tool joints must be broken with tongs and NOT the rotary table. Tool joints
should be rotated out slowly. If core is expected to be unconsolidated, or if there is no
break off bottom, chaining out is recommended. Under no circumstances should string be
dropped suddenly or set into slips with a bang. This could cause core to become
dislodged from core catcher.
4. Hold a safety procedures meeting with the bit in the casing and review well
control, and the core recovery procedures.
Note: If the well starts to flow, notify the drill site supervisor immediately and prepare to
implement well control procedures. This may include tripping back to bottom.
5. Once the core barrel is at surface, set the slips and install the drill collar clamp.
6. Retrieve the drop ball. If necessary, check for H2S and be aware of the possibility
of H2S trapped below the ball.
Note: If there are obstructions on top of the drop ball caution must be taken when digging
it out to remove it. Be aware of gas trapped below the ball.
7. Screw the elevator lift sub into the top of the core barrel and torque to
recommended specs.
8. Break the safety joint connection and back out until the connection is completely
disengaged.
9. Hoist the inner barrels out of the outer barrels and lower them to the rig floor.
10. Break off the shoe with pipe wrenches and install the core tong shoe and handle.
11. Recover the core keeping in mind the safety topics discussed in the pre job safety
meeting.
1. Screw the elevator lift sub into the top of the core barrel chain tong tight. Break
the connection of the safety joint and back out until the connection is completely
disengaged. Hoist the safety joint to expose the top aluminum inner. Install the
inner barrel clamp with sling at least 15 cm below the inner barrel box. Break the
swivel assembly out of the inner barrel and lay it down. Attach the winch line to
the lifting chain on the inner barrel clamp and hoist the inners to the next
connection.
2. Install the inner barrel double clamp on the bottom inner approximately 4 below
the connection. Take the pipe cutter and cut the aluminum, this prevents the tube
turning and fracturing the core.
3. Install the guillotine boot which is hydraulic for smooth breaking of the core. Install
the core into the core lay down cradle and carefully lay the inner barrel down on
the catwalk with the winch line.
4. Repeat the process for the remaining inner barrels.
5. Mark the Inner Barrels Clearly with Permanent Marker for Identification.
1. If steel inner barrels were used, unfasten the winch line and lower inner barrels
back inside outer barrels.
2. Make up the safety joint pin to the safety joint box using chain tongs only.
3. Break the connection between the safety joint and the elevator lift sub using the
rig tongs.
4. Remove the drill collar clamp.
Note: Ensure that all the connections in the following procedures are loosened so they can
be unscrewed with chain tongs in the workshop.
5. Pick up the core barrel and service break the connections between the safety joint
box and the stabilizer, and between the stabilizer and the outer barrel.
6. Pick up the core barrel and set the slips below the blades of the top stabilizer on
the bottom section of the core barrel leaving enough room to install the drill collar
clamp. Install the drill collar clamp.
7. Break the connection between the outer barrel of the top section and the stabilizer
of the bottom section.
8. Unscrew the outer barrel using chain tongs only.
9. If steel inner barrels were used, install the inner barrel clamp one foot below the
top of the bottom inner barrel. Break the connection between the inner barrels,
and lower the top section of the core barrel till the inner barrel clamp is just above
the stump. Screw the inner barrels apart.
10. Fit the inner barrel protector to the pin end hand tight. Fit the outer core barrel
protector to the pin end and tighten with the chain tongs.
11. Turn the elevator handles opposite the V-door.
12. Lay the top section down onto the catwalk using the drill floor winch.
13. Remove the elevator lift sub. Screw an API box protector into the outer barrel box.
Note: Drill floor personnel under the direction of the driller perform the lay down
procedures for lowering the core barrels to the catwalk.
14. Screw the elevator lift sub chain tong tight into the next inner barrel section in the
rotary table. Attach the elevators. Lift the core barrel and remove the inner barrel
clamp. Screw the lift sub into the outer barrel and make it up chain tong tight.
15. Remove the drill collar clamp.
16. Pick up the core barrel and break the connection between the stabilizer and the
outer barrel.
17. Pull the core barrel all the way up out of the bushings.
18. Ensure the hole cover is fitted prior to fitting the bit breaker on the core head.
19. Fit the bit breaker on the core head, holding the handles for safety, and install the
bit breaker plate in the rotary table.
20. Break the connections between the bottom stabilizer and the core head.
21. Hoist the barrel out of the rotary table, install the hole cover and remove the core
head. Screw the core barrel protector on to the stabilizer pin.
22. Tighten the protector with chain tongs.
23. Lay down the bottom section to the catwalk using the drill floor winch.
Note: The 3rd party Coring Technician will ensure that all coring equipment and handling
tools will be cleaned and packed away in the Coring Services Container.
Before any assumption that the core barrel is jammed, check that all surface equipment is
functioning correctly and that no additives into the mud system are causing pressure
fluctuation.
The following LCM products & particle sizes are recommended as most suitable.
Prepared by WEP
Author:
Verified:
Specific cases may require specific ways of assuring safety. Specific cases are for instance
damaged casings, pressure and / or accumulation of hydrocarbons in the annular space
between casings, long intervals crossing salt, etc.
The occurrence of specific cases must be verified prior to the preparation of the
abandonment plan.
All activities concerning abandoning wells must comply with the existing HESQ
instructions, best practices and methods of operation.
The plug and abandonment program for a well contains complex technical documentation,
economic, social and environment reasons for closure of the well and contains the
necessary actions to secure funding and to ensure effective fulfilment of this program in
compliance with HSEQ.
Ensure that the abandonment procedure is executed so that it achieves a hermetic seal
over the liquid and/or gas under any circumstances, and that any undesirable changes to
groundwater and/or soil are avoided.
The program for plug and abandonment must specify the following:
Well name and number, field name, all hydrocarbon bearing layers behind casing
The history of the well; production data, flow rates, initial and final pressure, total
volume produced
A schematic drawing of the well, showing construction of the well, including
casings, cement tops and geological sections
Reason for abandonment
Depth of the well and depth of the cement plugs
The program to restore the land for normal use
17.3.1 Reservoirs
The cement shall cover a section from 50 m below the reservoir to 50 m above the
reservoir. See figure 1.
Figure 1
Perforations must be sealed with a squeeze cementing job. If for this job a cement
retainer is used, it is enough to place a 50 m cement plug on top. See figure 2 and 3.
Figure 2
Figure 3
If a squeeze job as above is not possible or only possible under difficult conditions, a
mechanical isolation (packer/bridge plug) must be inserted, if possible directly above of
the screen (of the perforation zone), with a 50m long cement plug on top. See figure 4.
Figure 4
Figure 5
17.3.2 Cased hole with open-hole from the bottom of the shoe,
liners, casing section and annulus.
Figure 6
Figure 7
Liner hangers
The liner hanger must be isolated with a cement plug from at least 50 m below to 50 m
above it (Fig. 8); if the larger diameter casing is mechanical sealed directly above the
section respectively liner hanger, a cementing job of 50m above the packer/bridge plug is
enough (Fig. 9).
Figure 8
Figure 9
Figure 10
Figure 11
Figure 12
Figure 13
At surface all the casing will be removed to the depth of 2.5m, in order to prepare for
future use of the area.
On top of the remaining casing, a lid will be welded which will be covered with topsoil
(Fig. 14).
Figure 14
The strength of the cement slurry shall be verified through observation of representative
surface samples from the slurry under a representative temperature and pressure.
The cement plug can only be considered a barrier once one the following tests, or a
combination thereof, is successful:
Weight test of at least 100 kN (~10.2 tonne)
Pressure test of at least 50 bar / 15 min.
Inflow test
Furthermore a job performance report shall be made for each cement pug set to provide a
record of volumes pumped, volumes returned, cement recipe, etc.