0% found this document useful (0 votes)
299 views14 pages

E2000-ODF BOX Quick Installation Guide 03 (NA)

E2000-ODF BOX Quick Installation Guide 03(NA)
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
299 views14 pages

E2000-ODF BOX Quick Installation Guide 03 (NA)

E2000-ODF BOX Quick Installation Guide 03(NA)
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 14

E2000-ODF BOX

Quick Installation Guide

Issue: 03
Date: 2013-11-18

HUAWEI TECHNOLOGIES CO., LTD.


Copyright Huawei Technologies Co., Ltd. 2013. All rights reserved.
No part of this document may be reproduced or transmitted in any form or by any means without prior
written consent of Huawei Technologies Co., Ltd.

Trademarks and Permissions

and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.

Notice
The purchased products, services and features are stipulated by the contract made between Huawei and
the customer. All or part of the products, services and features described in this document may not be
within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements,
information, and recommendations in this document are provided "AS IS" without warranties, guarantees
or representations of any kind, either express or implied.

The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.

Huawei Technologies Co., Ltd.


Address: Huawei Industrial Base
Bantian, Longgang
Shenzhen 518129
People's Republic of China
Website: http://www.huawei.com
Email: [email protected]
Description
The E2000-ODF BOX is designed by Huawei for WDM products. It can house a maximum of
six pairs of LSH/APC-LSH/APC (E2000-E2000) fiber adapters, enabling fiber splicing and
facilitating fiber distribution between high-power optical amplifier boards and an ODF. This helps
ensure the cleanness of fiber endfaces and reduce the number of common optical fiber
connectors, minimizing link loss, facilitating fiber connections, fiber management, and
maintenance.
The E2000-ODF BOX can be installed in an ODF rack or a standard rack for Huawei WDM
products. It can also be installed in a 19-inch open rack or 21-inch open rack by adjusting the
positions of the mounting ears.

Specifications
Item Specifications
Splicing capacity 6 cores
Distribution capacity 6 cores
Dimension (H x W x D) / Weight 43.6 mm (1U) x 482.6 mm x 265 mm / 5 kg (full config)
Installation mode 19-inch open rack or 21-inch open rack
Material High quality steel
Work temperature -25C to + 50C
Storage temperature -40C to + 70C
Relative humidity 93% (at 40C)
Individual package 130 mm x 555 mm x 355 mm
Standards compliance YD/T788-2006: ODF

Application Scenarios
Principle drawing
CRPC E2000-ODF Box
The CRPC subrack is used as an example
Subrack in the principle drawing and application
scenarios.
MON SYS LINE

Scenarios 1 Scenarios 2
CAUTION
HAZARDLEVEL1MINVISIBLE
LASERRADIATION

CRPC DONOTVIEWDIRECTLYWITH
NON-ATTENUATINGOPTICAL
INSTRUMENTS ALM RUN

! WARNING: FIBERS MUST


BE CONNECTED BEFORE
POWER UP RS232-1 RS232-2 LAN

CPRC subrack

E2000-ODF Box

E2000 optical fibers to


customer's fiber cable

E2000 optical fibers to


equipment subrack

Outdoor cable

Splicing point

WDM Equipment Customers ODF rack WDM Equipment Customers ODF rack

1
Installation procedure

Procedure 1 Procedure 2

Adopt one installation procedure based on the site


requirements. If the installation space is limited, adopt
procedure 2. Procedure 1 is used as an example in this
installation guide. For details about the differences
between the two procedures, see the appendix.

Installation mode
a On a ODF rack b On a WDM cabinet
Mode 1 A Mode 1
B B A

Mode 2 B Mode 2 A
B A

B Mode 3 A
1. Position A means leading in E2000 optical fibers to
equipment subrack; Position B means leading in E2000
optical fibers to customer's fiber cable.
2. The scenario in which the box is installed on an ODF
rack is used as an example in this installation guide.

2
Installation Tools

Measuring tape Philips screwdriver Protective gloves Kevlar Shears

Cable stripping tool Optical fiber


Diagonal pliers OTDR
splicing tool

Optical fiber Ethanol pump and non-dust


Optical microscopy
fabric or absorbing jig
connector cleaner

1 Install the Box on a rack


Install the floating nuts .

1. This guide takes the box installed on a 19-inch open rack as an example. It can also L
be installed on an 21-inch open rack. The following describes how to adjust the
installation positions for mounting ears when it needs to be installed in an 21-inch open
rack. L L 100 mm
2. It is recommended that 100 mm vertical space be reserved between a box and a
subrack in WDM Equipment.

3
1 Install the Box on a rack
a On a 19-inch open rack
Thread the panel screws through the mounting ears and fasten the screws to fix the box on the rack.

Philips screwdriver

b On an 21-inch open rack


Move the mounting ears to positions for 21-inch open racks.

There are three installation positions for mounting ears.


Position 1 Position 2 Position 3
Choose a proper installation position based on the reserved
installation depth of the rack.

2 Install E2000 optical fibers to equipment subrack


Import E2000 optical fibers to Strip E2000 optical fibers to equipment subrack
equipment subrack from the top of the according to the requirements for stripping lengths.
rack at the back side.
L=2000 mm

Stripped point Strength member 2.0 mm pigtail

L1=600 mm L2=1400 mm

Roll protection tube

E2000 optical fibers to equipment subrack

4
2 Install E2000 optical fibers to equipment subrack
Use a cable stripping tool to cut the outer jacket of a cable about 40 mm from the end of the cable.
Remove the wrap tape, pull the ripcord to rip the outer jacket about 1960 mm, and cut off the stripped
jacket.

Remove
the wrap
tape
Ripcord

Cut off the strength member from the stripped point, install the roll protection tube about 600 mm, and
wrap the end of E2000 optical fibers to equipment subrack with insulating tape.

Roll protection tube Insulating tape

Strength member

Use the strength member to move E2000 optical fibers to equipment subrack from the rear part of
the Box to the front part: Thread the strength member through the cable incoming hole from the front
part of the Box. Fasten the strength member and E2000 optical fibers to equipment subrack using
insulating tape. Pull the strength member to move E2000 optical fibers to equipment subrack to the
front part of the Box.

Insulating tape

E2000 optical fibers to


equipment subrack WDM board
Install E2000 optical fibers
to equipment subrack to the
Box from the incoming cable
hole.

Stripped point

Hose clamp

5
2 Install E2000 optical fibers to equipment subrack
Pull out the Box and coil E2000 optical fibers to equipment subrack.

Fix E2000 optical fibers to equipment subrack with cable tie, open the splicing tray to arrange splicing.

Open the tray

Cable tie

3 Install E2000 optical fibers to customer's fiber cable

Import E2000 optical fibers to


customer's fiber cable at the front
1. Install the roll protection tube from point .
side. 2. Colligation point with the cable tie should be at least 50 mm from the box in
horizontal direction and 200 mm -260 mm in vertical direction so that the
bending radius of the optical fiber is not less than 30 mm.
3. The length of E2000 optical fibers to customers fiber cable is about 1200
mm, and the length of the roll protection tube is L+100mm (L: E2000 optical
fiber length when the box tray is completely pulled out of the rack; 100 mm:
length of the roll protection tube in the box).

E2000 optical fibers to E2000 optical fibers to


customers fiber cable equipment subrack

L1 50 mm
Cable tie
L2: 200mm~260mm
L
L2

E2000 optical fibers to


customers fiber cable

L1
6
3 Install E2000 optical fibers to customer's fiber cable
Install E2000 optical fibers to customer's fiber cable: remove the black cap, insert the connector into the
adapter, and coil E2000 optical fibers to customer's fiber cable in the box.
The number of the pigtail on E2000 optical fibers
to customer's fiber cable must correspond with
Pay attention to the installation
the number of adapter bracket.
direction of adapter.

1. If the fiber connectors are not clean, the optical


loss on the line increases and the test result is
affected. Therefore, all the fiber connectors must be
cleaned during the optical fiber connection and test.
For more information about cleaning the connector
port of E2000, see the Inspecting and Cleaning the
Optical Fiber Connectors chapter in the applicable
product documentations for OptiX WDM Equipment.
2. Ensure that the bending radius of fibers is not less
than 30 mm.

False True

4 Splice and coil fibers


Note the requirements on fiber stripping lengths. L3=600 mm

E2000 optical fibers to equipment subrack 2.0 mm pigtail 0.9 mm fiber core
Stripped point

Strip the 2.0 mm pigtail of E2000 optical fibers to equipment subrack.

7
4 Splice and coil fibers
a) Put the optical fiber into a splicing protection tube. b) Strip the pigtail in E2000 optical fibers to
customer's fiber cable to expose a 30 mm fiber core. c) Strip the fiber in E2000 optical fibers to
equipment subrack to expose a 30 mm fiber core. d) Clean the fiber cores.

Splice the optical fiber.

1 Cut the bare fiber. 2 Power on the fusion 3 Lay the fiber on the 4 Splice the optical
splicer. fusion splicer. fiber.

5 Take out the 6 Move the splicing protection 7 Heat the splicing 8 Take out the fiber after
optical fiber. tube on the optical fiber to the protection tube using a heating.
middle and lay the fiber on the heater.
heater.

Coil the fibers NOTE


in the splicing
1. Only a pair of fibers with the same outer
tray, and close jacket color can be spliced.
the tray cover. 2. There are numbers on the surface of
pigtails in E2000 optical fibers to
Numbers on the surface of pigtails in E2000
equipment subrack.
optical fibers to equipment subrack

0.9mm pigtail outer jacket (installed in Outer jacket of 0.9 mm pigtails (of E2000
Pigtail NO.
advance in the box) optical fibers to equipment subrack)
1 Blue Blue
2 Orange Orange
3 Green Green
4 Brown Brown
5 Grey Grey
6 White White

8
4 Splice and coil fibers
Fill in the route records and attach a label onto each pigtail of E2000 optical
fibers to customer's fiber cable.

NOTE

Ensure that the bending


radius of fibers is not
less than 30 mm.

Route records

Cable tie

Attach a label onto each pigtail of E2000 optical fibers to


customer's fiber cable.

Close the front panel, and the installation is complete.

9
5 Other installations (optional)

Mode-1 B Mode-2 A
B A

L
L1 L2
L3

E2000 optical fibers to equipment subrack 2.0 mm pigtail 0.9 mm fiber core

The Stripped length of E2000 optical fibers to


equipment subrack
1. The same length of E2000 optical fibers to customer's
fiber cable is about 1200 mmin in either of the preceding
Mode
modes. L L1 L2 L3
2. The table on the right lists the length of E2000 optical NO.
fibers to equipment subrack that needs to be stripped in
1 1900 mm 300 mm 1600 mm 600 mm
each of the preceding modes.
2 1850 mm 450 mm 1400 mm 600 mm

Mode-1

Mode-2

Cable tie

10
Install E2000 optical fibers to Install E2000 optical fibers to
equipment subrack customer's fiber cable

Appendix 1 Usage
Install E2000 offibers
optical E-2000
to Service Adapter
Put the Box on a workbench
customer's fiber cable

When checking the endfaces of the optical fiber


Splice and coil fibers E-2000 service
Spliceconnectors
and coil on
fibers
E2000, do not open the metal cap with
Metal cap bare hand. Instead, use an E-2000 service adapter.
adapter

End Install the Box on a rack

End
Appendix 2 Instruction of Procedure 2

Procedure 2 a Put the Box on a workbench


If the installation space is
Start
limited, put the box on a
workbench, remove the
upper cover and proceed
Install E2000 optical fibers to equipment
subrack (the same as procedure 1) with the subsequent steps.

Install E2000 optical fibers to customer's


fiber cable (the same as procedure 1)

Put the Box on a workbench

b Splice and coil fibers


Splice and coil fibers

Install the Box on a rack


(the same as procedure 1)

End

Appendix 3 Checking after the installation


After the installation, pull out and push in the box three times and check the following items:
Outside the box: The optical cable is properly connected and the bending radius of the optical cable is
not less than 30 mm.
In the box: No optical fiber is under strain and the bending radius of optical fibers is not less than 30