Renovation of Onups Ward Building
Renovation of Onups Ward Building
Renovation of Onups Ward Building
National Irriga
TARLAC-ZAMBALES IRRIG
Matatalai
SCOPE OF WORKS
I. GENERAL REQUIREMENTS
(a) Project Billboard
(b) Temporary Facilities
Submitted by:
Total of all amount in Words: EIGHTEEN MILLION FOUR HUNDRED NINETY THREE THOUSAND SEVEN HUND
SEVEN PESOS AND EIGHTY TWO CENTAVOS
Submitted by:
NGCUPANG)
TOTAL COST
496,315.00
270,000.00
75,000.00
50,000.00
35,000.00
378,046.00
583,556.00
158,684.00
6,167,976.65
4,618,406.30
717,812.67
821,507.71
966,387.57
507,520.30
733,747.90
942,673.50
850,524.30
134,297.14
776,114.00
845,097.00
964,323.20
157,465.55
467,792.70
17,482.60
198,961.90
40,295.65
145,656.45
376,834.01
90,161.50
175,266.00
551,302.00
853,175.90
1,296,537.15
2,194,533.00
1,955,845.50
54,658.50
320,198.00
77,802.50
337,471.75
1,641,333.10
PHP 32,045,762.99
7, 2017
DETAILED ESTIMATES
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 1.00 800.00
Construction Foreman 1.00 500.00 8.00 4,000.00
Skilled Laborers 4.00 400.00 8.00 12,800.00
Laborers 4.00 300.00 8.00 9,600.00
27,200.00
EQUIPMENT RENTAL:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Elf Truck (9cu.m.) 1.00 14,000.00 3.00 42,000.00
Dump Truck (9cu.m.) 1.00 15,000.00 7.00 105,000.00
Backhoe with Concrete Breaker 1.00 18,000.00 7.00 126,000.00
Wheel Loader (3.0 cu.m.) 1.00 10,000.00 3.00 30,000.00
303,000.00
Direct Cost - 330,200.00
Contractor's Profit - 23,114.00
VAT & Withholding Tax - 24,732.00
Total Item Cost - 378,046.00
Unit Cost - 514.35
III.
EARTHFILL AND COMPACTION FOR SLAB ON
GRADE Qty= 734.61 cu.m.
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
Earthfill 735.00 cu.m. 500.00 367,500.00
367,500.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 9.00 7,200.00
Construction Foreman 1.00 500.00 9.00 4,500.00
Laborers 5.00 300.00 9.00 13,500.00
25,200.00
EQUIPMENT RENTAL:
DESCRIPTION QTY. RATE/day NO.OF DAYS TOTAL COST
Vibratory Plate Compactor/Jampig Jack
Compactor 1.00 13,000.00 9.00 117,000.00
117,000.00
Direct Cost - 509,700.00
Contractor's Profit - 35,679.00
VAT & Withholding Tax - 38,177.00
Total Item Cost - 583,556.00
Unit Cost - 794.38
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Construction Foreman 1.00 500.00 7.00 3,500.00
Laborers 6.00 300.00 7.00 12,600.00
16,100.00
EQUIPMENT RENTAL:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Backhoe Crawler,1.09 cu.m. EL 200B 1.00 17,500.00 7.00 122,500.00
122,500.00
Direct Cost - 138,600.00
Contractor's Profit - 9,702.00
VAT & Withholding Tax - 10,382.00
Total Item Cost - 158,684.00
Unit Cost - 238.31
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
Cement 7,487.00 bags 245.00 1,834,315.00
Sand 412.00 cu.m. 600.00 247,200.00
Gravel (3/4" or 20mm) 823.00 cu.m. 1,150.00 946,450.00
3,027,965.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 40.00 32,000.00
Construction Foreman 1.00 500.00 40.00 20,000.00
Mason/Carpenter 10.00 400.00 40.00 160,000.00
Laborers 20.00 300.00 40.00 240,000.00
452,000.00
EQUIPMENT RENTAL:
DESCRIPTION QTY. RATE/day NO.OF DAYS TOTAL COST
Transit Mixer (5cu.m.) 8.00 15,000.00 15.00 1,800,000.00
Porta Lift 2.00 4,000.00 15.00 120,000.00
Concrete Vibrator 6.00 1,000.00 15.00 90,000.00
2,010,000.00
Direct Cost - 5,489,965.00
OCM - 54,899.65
Contractor's Profit - 219,599.00
VAT & Withholding Tax - 403,513.00
Total Item Cost - 6,167,976.65
Unit Cost - 7,872.51
MATERIALS:
Formworks:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
1/2 " x 4' x 8' plywood 312.00 pcs. 750.00 234,000.00
1099 pcs (2" x 2" x 10' lumber) 3,663.33 bd.ft. 20.00 73,266.60
78 pcs (2" x 2" x 12' lumber) 312.00 bd.ft. 20.00 6,240.00
4,287.33 313,506.60
Scaffoldings/staggings:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
464 pcs (2" x 3" x 12' lumber vertical
support) 2,784.00 bd.ft. 20.00 55,680.00
1242 pcs (2" x 3" x 12' lumber
horizontal support) 7,452.00 bd.ft. 20.00 149,040.00
526 pcs (2" x 2" x 12' lumber diagonal
support) 2,104.00 bd.ft. 20.00 42,080.00
12,340.00 bd.ft. 246,800.00
CHB WALL: MAIN BUILDING (Interior and Exterior Plaster @ both sides) (area = 3835.05 sq.m.)
COLUMNS, BEAMS : MAIN RAMP (area = 427.87 sq.m.)
DESCRIPTION QTY. UNIT PRICE TOTAL COST
Portland Cement 774.00 bags 245.00 189,630.00
Sand 65.00 cu.m. 600.00 39,000.00
228,630.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 7.00 5,600.00
Construction Foreman 1.00 500.00 25.00 12,500.00
Mason 10.00 400.00 25.00 100,000.00
Laborers 14.00 300.00 25.00 105,000.00
223,100.00
Direct Cost - 451,730.00
OCM - 4,517.30
Contractor's Profit - 18,070.00
VAT & Withholding Tax - 33,203.00
Total Item Cost - 507,520.30
Unit Cost - 119.05
IX. CARPENTRY
(a) Gypsum Board Ceiling (first floor only) (area = 711 sq.m.) 711.00
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
3/4" x 2' x 2' Gypsum Ceiling Board 2,074.00 pcs. 175.00 362,950.00
0.50mm x 5m Metal Furrings 598.00 pcs. 230.00 137,540.00
Miscellaneous materials(furring clips,
fasteners, etc.,) 1.00 lot 75,000.00 75,000.00
575,490.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 3.00 2,400.00
Construction Foreman 1.00 500.00 16.00 8,000.00
Carpenter 4.00 450.00 16.00 28,800.00
Laborers 8.00 300.00 16.00 38,400.00
77,600.00
Direct Cost - 653,090.00
OCM - 6,530.90
Contractor's Profit - 26,124.00
VAT & Withholding Tax - 48,003.00
Total Item Cost - 733,747.90
Unit Cost - 1,031.99
(b) Marine Plywood Ceiling (2nd floor only) (area = 743 sq.m.) 743.00
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
1/4" x 4" x 8' Marine Plywood 271.00 pcs. 350.00 94,850.00
0.50mm x 5m Metal Furrings 625.00 pcs. 230.00 143,750.00
Blind Rivet 1,873.00 pcs. 250.00 468,250.00
Miscelaneous materials 1.00 lot 35,000.00 35,000.00
741,850.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 4.00 3,200.00
Construction Foreman 1.00 500.00 20.00 10,000.00
Carpenter 4.00 450.00 20.00 36,000.00
Laborers 8.00 300.00 20.00 48,000.00
97,200.00
Direct Cost - 839,050.00
OCM - 8,390.50
Contractor's Profit - 33,562.00
VAT & Withholding Tax - 61,671.00
Total Item Cost - 942,673.50
Unit Cost - 1,268.74
(c) Spandrel Ceiling(corridor at main bldg and ramp) (area = 286.28 sq.m.) 286.28
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
0.50mm 7" PPGI Spandrel 3,006.00 ln.m. 150.00 450,900.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 4.00 3,200.00
Construction Foreman 1.00 500.00 20.00 10,000.00
Carpenter 4.00 450.00 20.00 36,000.00
Laborers 6.00 300.00 20.00 36,000.00
85,200.00
Direct Cost - 752,200.00
OCM - 7,522.00
Contractor's Profit - 30,088.00
VAT & Withholding Tax - 55,287.00
Total Item Cost - 845,097.00
Unit Cost - 3,402.87
XI. TILE WORK
(area = 1,472
(a) Main Building Floor Tiles (F1) sq.m.) 1,472.000
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
60 x 60cm Unglazed Ceramic Tiles 4294 pcs 125.00 536,750.00
Portland Cement 696 bags 245.00 170,520.00
Sand 39.00 cu.m. 600.00 23,400.00
Tile Adhesive 118.00 bags 135.00 15,930.00
Tile Grout 773.00 kgs 40.00 30,920.00
777,520.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 3.00 2,400.00
Construction Foreman 1.00 500.00 14.00 7,000.00
Mason/Tile Setter 6.00 450.00 14.00 37,800.00
Laborers 8.00 300.00 14.00 33,600.00
80,800.00
Direct Cost - 858,320.00
OCM - 8,583.20
Contractor's Profit - 34,333.00
VAT & Withholding Tax - 63,087.00
Total Item Cost - 964,323.20
Unit Cost - 655.11
(b) Comfort Room Floor Tiles (F2) (area = 186 sq.m.) 186.000
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
30 x 30cm Unglazed Ceramic Tiles 2,170.00 pcs 45.00 97,650.00
Portland Cement 88.00 bags 245.00 21,560.00
Sand 5.00 cu.m. 600.00 3,000.00
Tile Adhesive 15.00 bags 135.00 2,025.00
Tile Grout 98.00 kgs. 40.00 3,920.00
128,155.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 2.00 1,600.00
Construction Foreman 1.00 500.00 4.00 2,000.00
Mason/Tile setter 2.00 450.00 4.00 3,600.00
Laborers 4.00 300.00 4.00 4,800.00
12,000.00
Direct Cost - 140,155.00
OCM - 1,401.55
Contractor's Profit - 5,607.00
VAT & Withholding Tax - 10,302.00
Total Item Cost - 157,465.55
Unit Cost - 846.59
(d) Stop Sink at Comfort Room (F4) (area =12 sq.m.) 12.00
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
20 x 20cm Glazed Ceramic Tiles 315.00 pcs 35.00 11,025.00
Portland Cement 6.00 bags 245.00 1,470.00
Sand 1.00 cu.m. 600.00 600.00
Tile Adhesive 1.00 bag 135.00 135.00
Tile Grout 7.00 kgs. 40.00 280.00
13,510.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 1.00 800.00
Construction Foreman 1.00 500.00 1.00 500.00
Mason/Tile setter 1.00 450.00 1.00 450.00
Laborers 1.00 300.00 1.00 300.00
2,050.00
Direct Cost - 15,560.00
OCM - 155.60
Contractor's Profit - 623.00
VAT & Withholding Tax - 1,144.00
Total Item Cost - 17,482.60
Unit Cost - 1,456.88
Acrylic Gloss Latex Paint (Two coats) 359 gallons 650.00 233,350.00
Concrete neutralizer 99 gallons 330.00 32,670.00
Roller with pan 2.00 pcs 125.00 250.00
4" paint brush 2.00 pcs 30.00 60.00
2" paint brush 4.00 pcs 20.00 80.00
Sand paper #120, Patching compound,
etc. 1.00 lot 1,500.00 1,500.00
335,410.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 8.00 6,400.00
Construction Foreman 1.00 500.00 30.00 15,000.00
Steelman/Welder 5.00 450.00 30.00 67,500.00
Laborers 4.00 300.00 30.00 36,000.00
124,900.00
EQUIPMENT RENTAL:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Welding Machine (300Amp) 1.00 2450 25.00 61,250.00
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
A. CONDUITS FOR LIGHTING AND CONCVENIENCE OUTLET
1" X 3m PVC pipe 10 pcs. 150.00 1,500.00
3/4" x 3m UPVC pipe 800 pcs. 125.00 100,000.00
2" RSC pipe 2 pcs. 350.00 700.00
2" Long Elbow RSC pipe 2 pcs. 35.00 70.00
2" UPVC pipe 6 pcs. 75.00 450.00
2" UPVC Pipe Long Elbow 8 pcs. 100.00 800.00
Fittings (PVC Elbow, Coupling, Tee,
etc.) 1.00 lot 1,500.00 1,500.00
Circuit Breaker 15Amp 16 pcs. 245.00 3,920.00
Circuit Breaker 20Amp 10 pcs. 250.00 2,500.00
Circuit Breaker 30Amp 12 pcs. 350.00 4,200.00
2" dia. Entrance Cap (heavy duty) 2 pcs. 350.00 700.00
Panel box (1-main, 10 branches) 2P-50
AT/AF/10 KAIC CB 2 units 3,500.00 7,000.00
Panel box (1-main, 6 branches) 2P-70
AT/70 AF/10 KAIC CB 2 units 4,500.00 9,000.00
Panel box (1-main, 4 branches) 2P-70
AT/70 AF/10 KAIC 2 units 4,300.00 8,600.00
NEMA 1-3P 150A CB CASING 2.00 units 1,000.00 2,000.00
70 AT/70AF/10 KAIC 4 units 1,500.00 6,000.00
150AT/150AF/35 KAIC 2 units 2,500.00 5,000.00
153,940.00
B. WIRINGS
2.0mm THHN 24 box 3,800.00 91,200.00
3.5mm THHN 16 box 3,300.00 52,800.00
3.5mm THHN (color white for
grounding) 5 box 3,500.00 17,500.00
5.5mm THHN 1.00 box 2,800.00 2,800.00
14mm TW 25 lm 4,500.00 112,500.00
22mm THHN 25 lm 5,000.00 125,000.00
30mm THHN 25 lm 5,500.00 137,500.00
100mm THHN 26 lm 7,500.00 195,000.00
734,300.00
C. LIGHTING OUTLET FIXTURES/CEILING FAN
Pin light (11W LED BULB) 266 units
Utility box with screw 118.00 pcs. 25.00 2,950.00
Junction box with cover and screw 18 pcs. 25.00 450.00
1 gang plate cover 85 pcs. 150.00 12,750.00
2 gang plate cover 90 pcs. 165.00 14,850.00
3-gang plate cover 2 pcs. 175.00 350.00
Switch 3-way 30 pcs. 350.00 10,500.00
Switch elemet 71 pcs. 75.00 5,325.00
Exhaust fan (10'') 17 pcs. 350.00 5,950.00
Orbital Ceiling Fan 60.00 pcs. 1,800.00 108,000.00
Miscellaneous materials 1 lot 5,000.00 5,000.00
166,125.00
D. AIR CONDITIONING UNITS
Split Type Wall Mounted Air
Conditioning Unit (with inverter) 2.0 HP
completed 2 units 40,000.00 80,000.00
80,000.00
E. CONVENIENCE OUTLET FIXTURES
Junction box with screw 40 pcs. 25.00 1,000.00
C.O. Universal Element with ground 160.00 pcs. 150.00 24,000.00
ACU Outlet with plate and screws 6 pcs. 4,500.00 27,000.00
RSC locknut,adaptor, etc. 1 lot 5,000.00 5,000.00
57,000.00
F. CONSUMABLES
Electrical Tape (big) 50 pcs 75.00 3,750.00
Rubber tape 15 box 500.00 7,500.00
Solvent Cement 10 can 350.00 3,500.00
14,750.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Electrical Engineer 1.00 800.00 8.00 6,400.00
Construction Foreman 1.00 500.00 10.00 5,000.00
Electrician 1.00 450.00 10.00 4,500.00
Laborers 4.00 300.00 10.00 12,000.00
27,900.00
Direct Cost - 1,154,015.00
OCM - 11,540.15
Contractor's Profit - 46,161.00
VAT & Withholding Tax - 84,821.00
Total Item Cost - 1,296,537.15
Unit Cost - 1,296,537.15
XVI. STEEL DECK (main bldg. second floor and roof) QTY = 1005.612 ln.m. 1005.612
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
1.00mm D-1022 Steel Deck 1056 ln.m. 1,500.00 1,584,000.00
Miscellaneous materials (shear studs,
etc.) 1 lot 250,000.00 250,000.00
1,834,000.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 1.00 800.00
Construction Foreman 1.00 500.00 30.00 15,000.00
Carpenter 5.00 450.00 30.00 67,500.00
Laborers 4.00 300.00 30.00 36,000.00
119,300.00
Direct Cost - 1,953,300.00
OCM - 19,533.00
Contractor's Profit - 78,132.00
VAT & Withholding Tax - 143,568.00
Total Item Cost - 2,194,533.00
Unit Cost - 2,182.29
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
A.FIXTURES AND ACCESSORIES
Water Closet, Lavatory with faucet,
soap holder, tissue holder 25 set/s 5,000.00 125,000.00
Lavatory with fitings 31 units 4,500.00 139,500.00
Shower 27 pcs. 3,000.00 81,000.00
Floor strainer (4" x 4") 42 pcs. 200.00 8,400.00
Urinal 4 units 4,500.00 18,000.00
Miscellaneous materials (gate valve,
faucet, teflon tape, etc.) 1 lot 6,000.00 6,000.00
377,900.00
B. SEWERAGE SYSTEM
2" X 10' PVC pipes series 1000 60 pcs. 350.00 21,000.00
3" x 10' PVC Down Spout series 600 70 pcs. 450.00 31,500.00
4" x 10' PVC pipes series 1000 100 pcs. 550.00 55,000.00
Assorted PVC fittings 1.00 lot 5,000.00 5,000.00
PVC Solvent Cement 20 250cc 450.00 9,000.00
Catch Basin (see drawing) 25 units 3,000.00 75,000.00
30" x 1m Reinforced Concrete Culvert
Pipe (RCCP) 175 lm 6,000.00 1,050,000.00
Miscellaneous Materials 1 lot 7,500.00 7,500.00
1,254,000.00
C. WATER SUPPLY SYSTEM
1/2" X 10' PPR pipes 50 pcs. 450.00 22,500.00
1/2" Assorted PPR Fittings 1.00 lot 4,500.00 4,500.00
Teflon tape 50 pcs. 75.00 3,750.00
Miscellaneous Materials 1 lot 5,000.00 5,000.00
35,750.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Sanitary Engineer 1.00 800.00 4.00 3,200.00
Construction Foreman 1.00 500.00 20.00 10,000.00
Plumber 4.00 450.00 20.00 36,000.00
Laborers 4.00 300.00 20.00 24,000.00
73,200.00
Direct Cost - 1,740,850.00
OCM - 17,408.50
Contractor's Profit - 69,634.00
VAT & Withholding Tax - 127,953.00
Total Item Cost - 1,955,845.50
Unit Cost - 1,955,845.50
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
CONCRETE: (VOLUME = 2.40 CU.M.)
Portland Cement 23 bags 245.00 5,635.00
Sand 2 cu.m. 600.00 1,200.00
Gravel 3 cu.m. 835.00 2,505.00
RSB:
10mm x 6m dia RSB 36 pcs.
# 16 G.I. Tie wire 2 kgs. 60.00 120.00
CHB WALL: (AREA = 32.00 SQ.M.)
Portland Cement 18 bags 245.00 4,410.00
Sand 2.00 cu.m. 600.00 1,200.00
4" Thick CHB 420 pcs. 12.00 5,040.00
12mm x 6m dia RSB 12 pcs. 225.00 2,700.00
10mm x 6m dia RSB 13 pcs. 125.00 1,625.00
#16 G.I. Tie wire 5 kgs. 60.00 300.00
PLASTERING(Interior only): (AREA = 32.00 SQ.M.)
Portland Cement 7 bags 245.00 1,715.00
Sand 1.00 cu.m. 600.00 600.00
False Works (Form Lumbers and
Scaffoldings) 1 lot 5,000.00 5,000.00
32,050.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Sanitary Engineer 1.00 800.00 1.00 800.00
Construction Foreman 1.00 500.00 4.00 2,000.00
Steelman 5.00 450.00 4.00 9,000.00
Laborers 4.00 300.00 4.00 4,800.00
16,600.00
Direct Cost - 48,650.00
OCM - 486.50
Contractor's Profit - 1,946.00
VAT & Withholding Tax - 3,576.00
Total Item Cost - 54,658.50
Unit Cost - 54,658.50
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
2" dia Stainless Steel Pipe Hand
Railings 149 pcs. 1,500.00 223,500.00
Miscellaneous materials (Expansion
bolt, TIG Weld, etc.) 1 lot 15,000.00 15,000.00
238,500.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 5.00 4,000.00
Construction Foreman 1.00 500.00 5.00 2,500.00
Welder 4.00 450.00 5.00 9,000.00
Laborers 4.00 300.00 5.00 6,000.00
21,500.00
EQUIPMENT RENTAL:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Welding Machine 2.00 2500 5.00 25,000.00
25,000.00
Direct Cost - 285,000.00
OCM - 2,850.00
Contractor's Profit - 11,400.00
VAT & Withholding Tax - 20,948.00
Total Item Cost - 320,198.00
Unit Cost - 320,198.00
MATERIALS:
DESCRIPTION QTY. UNIT PRICE TOTAL COST
B.I. Pipe 1" (S-40) 200 pcs. 600.00 120,000.00
B.I. Pipe 2.5" (S-40) 30 pcs. 1,150.00 34,500.00
B.I. Pipe 4" (S-40) 20 pcs. 2,400.00 48,000.00
B.I. Pipe 1" coupling 400 pcs. 150.00 60,000.00
B.I. Pipe 1" elbow 800 pcs. 145.00 116,000.00
B.I. Pipe 1" nipple 400 pcs. 155.00 62,000.00
B.I. Pipe 1" x 1" tee 400 pcs. 150.00 60,000.00
B.I. Pipe 1" x 2" tee 80 pcs. 150.00 12,000.00
B.I. Pipe 2" x 4" tee 14 pcs. 165.00 2,310.00
B.I. Pipe 4" elbow 16 pcs. 180.00 2,880.00
B.I. Pipe 4" coupling 8 pcs. 180.00 1,440.00
B.I. Pipe 4" nipple 8 pcs. 160.00 1,280.00
B.I. Pipe 1 x 2" reducer 80 pcs. 175.00 14,000.00
B.I. Pipe 2 x 4" reducer 4 pcs. 175.00 700.00
OS & Y gate valve 4" dia. 4 pcs. 260.00 1,040.00
supervisory switch 4 pcs. 450.00 1,800.00
waterflow switch 4 pcs. 350.00 1,400.00
sight glass 1" dia. 4 pcs. 230.00 920.00
ball valve 1" dia. 4 pcs. 220.00 880.00
ball valve 2" dia. 4 pcs. 260.00 1,040.00
ball valve 2" dia. 4 pcs. 260.00 1,040.00
Fire sprinkler control panel 4 2 pcs. 4,500.00 9,000.00
sprinkler head 200 pcs. 350.00 70,000.00
622,230.00
FIRE ALARM SYSTEM
Smoke Detector 80 sets 8,000.00 640,000.00
Fire Alarm Buzzer 16 sets 2,300.00 36,800.00
Fire Alarm Buzzer break glass switch 16 sets 2,800.00 44,800.00
Fire exit signs 16 sets 180.00 2,880.00
F.A.C.P. Fire Alarm Control Panel 4 sets 6,700.00 26,800.00
TF Wire Std. 20 box 350.00 7,000.00
2.0mm THHN stranded 20 box 2,800.00 56,000.00
2" dia. PVC Red orange pipe 80 box 45.00 3,600.00
1/2" dia. PVC Red orange pipe 80 box 75.00 6,000.00
823,880.00
LABOR:
DESIGNATION QTY. RATE/day NO.OF DAYS TOTAL COST
Civil Engineer 1.00 800.00 1.00 800.00
Construction Foreman 1.00 500.00 4.00 2,000.00
Plumber 4.00 450.00 4.00 7,200.00
Laborers 4.00 300.00 4.00 4,800.00
14,800.00
Direct Cost - 1,460,910.00
OCM - 14,609.10
Contractor's Profit - 58,437.00
VAT & Withholding Tax - 107,377.00
Total Item Cost - 1,641,333.10
Unit Cost - 1,641,333.10
SUMMARY OF COSTS
DIRECT COST: 26,701,497.40
A. Materials - 21,518,847.40
B. Labor - 2,870,700.00
C. Equipmental Rental - 2,638,750.00
27,028,297.40
INDIRECT COST:
D. OCM - 1,233,503.96
E. Contractor's Profit - 1,891,980.82
F. VAT & Withholding Tax - 1,891,980.82
5,017,465.60
PARTICULAR % Wt. 1st MONTH 2nd MONTH 3rd MONTH 4th MONTH 5th MONTH
Submitted by:
ANG)
NT SCHEDULE
Particular % Wt. 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
No. of Days 90 CD 180 CD 270 CD 360 CD
Accomplishment 25% 25% 25% 25%
Cash Flow 8,011,440.75 8,011,440.75 8,011,440.75 8,011,440.75
Cumulative Accomplishment 25% 50% 75% 100%
Cumulative Cash Flow 8,011,440.75 16,022,881.50 24,034,322.25 32,045,762.99
Submitted by: