The document is a checklist for preventative maintenance and planned downtime (PM/PDM) of weigh bridge scales 1 and 2 at Notore Chemical Industries. The 18-item checklist includes steps to power off and clean equipment, check load cells and terminals, inspect for damage or water ingress, test functionality, and document the condition of the scales before and after maintenance. The performing officer and supervisor must sign off after completing the PM/PDM tasks.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100%(1)100% found this document useful (1 vote)
2K views4 pages
Checklist For Weighbridge
The document is a checklist for preventative maintenance and planned downtime (PM/PDM) of weigh bridge scales 1 and 2 at Notore Chemical Industries. The 18-item checklist includes steps to power off and clean equipment, check load cells and terminals, inspect for damage or water ingress, test functionality, and document the condition of the scales before and after maintenance. The performing officer and supervisor must sign off after completing the PM/PDM tasks.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 4
INST/F/P-01/04
Notore Chemical Industries Rev. No.:1
Instrument Plc Rev. Date:16/08/2016 Title :CHECKLIST OF Page: 1 of 1 PM/PDM FOR WEIGH BRIDGE SCALES 1 & 2
DATE TAG NO..
1. POWER OFF FROM JUNCTION BOX.
2. CLEAN JUNCTION BOX. 3. CLEAN TERMINALS AND EARTH LINKS. 4. CHECK TO ENSURE FIRM TERMINATION ON BLOCKS. 5. CARRY OUT FUNCTIONAL TEST ON THE LOAD CELL CABLES. 6. CHECK FOR POLARITY ON DCV AND MVOLTS IN ALL JUNCTION BOXES. INST/F/P-01/04
Notore Chemical Industries Rev. No.:1
Instrument Plc Rev. Date:16/08/2016 Title :CHECKLIST OF Page: 1 of 1 PM/PDM FOR WEIGH BRIDGE SCALES 1 & 2
7. CARRY OUT RESISTANCE CHECKS ON ALL THE LOAD CELLS.
8. CHECK FOR PHYSICAL DAMAGE ON ALL THE LOAD CELLS. 9. CHECK FOR WATER INGRESS IN ALL THE JUNCTION BOXES. 10. CHECK CONDITION OF SUSPENSION RODS & TENSION RODS. 11. CHECK FIRMNESS OF BOLTS/NUTS ON THE PLATFORM. 12. CHECK PRINTER AND EFFECT FUNCTIONAL TEST. 13. CHECK FUNCTIONALITY OF SECTIONALIZATION CARD/HOUSING. 14. QUARTERLY FLUSHING OF THE BRIDGE EFFECTED? 15. STATE DATE OF LAST FLUSHING EXERCISE. DATE . INST/F/P-01/04
Notore Chemical Industries Rev. No.:1
Instrument Plc Rev. Date:16/08/2016 Title :CHECKLIST OF Page: 1 of 1 PM/PDM FOR WEIGH BRIDGE SCALES 1 & 2
16. WHEN NEXT IS FLUSHING DUE DATE
17. CHECK BRIDGE FOR FUNCTIONAL TEST AFTER PM/PDM 18. STATE CONDITION OF THE BRIDGE: AS FOUND .....