4 (6) Laning of Tuni - Anakapalli NH - 5 District - Visakhpatnam Vol - Vi PDF
4 (6) Laning of Tuni - Anakapalli NH - 5 District - Visakhpatnam Vol - Vi PDF
4 (6) Laning of Tuni - Anakapalli NH - 5 District - Visakhpatnam Vol - Vi PDF
Pmi.mt End
November 2000
. 0
CONSULTING ENGINEERING SERVlCES ( INDIA ) LIMITED
57, NEHRU PLACE, ( 5TH FLOOR ), NEW DELHI - 110019 ~?,
Aarucc
CONSULTING ENGINEERING SERVICES (INDIA) LIMITED
E N G I N E E R S A R C H I T E C T S P L A N N E R S
REGD OFFICE 57 NEHRU PLACE (STH FLOOR) NEW DELHl - 11C019 PHONES 6485284.6465484.6465485.6436925 6427159
E-mall ces~nter@vsnlcorn Webs~te www ces~ntercorn Fax 9 1- 11-6460409 Grams CONSENGERS
10
-Phc Gcncral Managcr (East)
National H~gh\\a)Autlior~t)of lnd~a
f3-i29. Nc\\ Fr~cndsColony
Ncn Dclh~- I I 0 065
Sub Preparation of Detailed Project Report for Rehabilitation and Strengthening of the Existing
2-lane Road and widening t o 416 lane dual carraigeway from Tuni (km 30010) to Ankapalii
(km 35912) in Vijaywada - Visakapatnam Section of NH-5 in State of Andhra Pradesh -
Package IV-A.
Dcar Sir.
We are pleased to submit 6 copies of the Detailed Cost Estimates as per B . 0 . Q and the Analysis of Raws
as a part of Detailed Project Report.
The draft cost estimates submitted under our letter no. 99088\RH\1033 dated 30'"eptember. 2000 \\'ere
discussed by the undersigned \\.it11 Mr. S. C. Saluja CGM(Tech.) and his obserl-ations ha\-e bcen
~ncorporated.
Yours faithfull).
for Consulting Engineeri~lgSen-ices
(India) Limited /, )
F:IX No.:
w
Project: 416 Laning of NH-5 from Tuni to Anakapalii Sheet lof 1
I Document: D:\99088\RH\Vol. VI Date: November, 2000
Detailed Rate Analysis Revision: RO
CONTENTS
VOLUME - VI
1. PREAMBLE
2. LEAD STATEMENT
x CHAPTER - 1
Preamble
1.1 General
The National Highway No. 5 (NH-5) connects two metropolis Calcutta and Chennai traversing
through important cities and many industrial centres spread over the states of West Bengal, Orissa,
Andhra Pradesh and Tamilnadu. The traffic on this highway is increasing at a rapid rate due to
accelerated industrial and agricultural activities in the region. The Ministry of Surface Transport
(MOST) through National Highways Authority of India (NHAI) wishes to take up the Project of
strengthening and widening of existing two-lane Tuni - Anakapalli section of NH-5 to four lane with
a provision for upgrading to six lane road in the future.
The Project road for the purpose of rate analysis has been divided in two road sections:
In this Volume, the rate analysis is carried out for the Section-I and this section of road falls farther
to the nearest market i.e. Vishakhapatnam. The analysis of rates has been carried out based on
Standard Schedule of Rates (Andhra Pradesh PWD, 1999-2000) and Most Standard Data Book, for
Analysis of Rates (IRC, 1994). Analysis of rates for items not given in the Most Standard Data Book
has been carried out based on Consultant's experience of similar nature of projects.
1
1.2 Materials
1.2.1 The basic rates of materials have been adopted from the Standard Schedule of Rates (SSR), 1999-
2000. The rate of materials not available in the SSR have been collected from the prevailing market
rates.
2 1.2.2 The stacking charges, loading and unloading charges, wastage etc. have been taken as per SSR 1999-
2000. The rates given in SSR are inclusive of charges for quarrying, breaking and screening of
aggregates and octroi and royalty charges, forest tax etc.
1.3 Labour:
The labour rates have been adopted based on SSR 1999-2000. The rates not available in SSR 1999-
2000 have been taken based on consultant's experience of similar nature of projects. The labour rates
adopted for Rate Analysis are given in Chapter-3.
Since the machinery charges as given in Standard Schedule of Rates (SSR) 1999-2000 are Iess than
the market rates, the machinery rates have been adopted based on Consultant's survey and previous
experience of similar nature of projects. The machinery charges adopted for this project are given in
Chapter-3.
Six numbers of stone quarries for producing crushed aggregates for use in sub-baselbaselsurfacing of
pavement and in cement concrete have been identified in the vicinity of the project road. The average
lead and yield for all quarries are referred from Table 11.2.09 of Feasibility Study Report Vol. 11.
Sand for the use in pavement and concrete works can be extracted from bed of rivers and streams.
The summary of test results with average lead and yield can be referred in Table 11.2.11 of
Feasibility Study Report Vol. 11. The lead calculation for different materials are given in Chapter-2.
The lead charges have been adopted as per SSR 1999-2000.
The rate analysis for various items of work has been worked out based on the above aspects. For
items involving use of stone aggregates and sand, unit rate have been worked out for both, materials
used through Hot Mix Plant / Ready Mix Concrete Plant and materials used for direct purposes.
The items are adopted as per MOST specifications. The analysis of rates for bridges are culverts have
been carried out separately as per item references under Bridges and Culverts as mentioned in MOST
STANDARD DATA BOOK FOR ANALYSIS OF RATES.
Lead Statement
Project: 416 Laning of Tuni - Anakapalli Section of NN-5 Sheet: 1 of 7
Document: 99088/RHIVol. VI/ChapZ Date: November, 2000
Lead Statement Revision: RO
Chapter 2
Lead statement
Average lead distance from crusher plants to the HMP =Km. (26.6+14.0+19.8)13
=Km. 20.13
Section f
Lead distance from Vishakhapatnarn to the MP =Km. 130 + (358.95316.60))
=Km. 72.35
Section I
Lead distance from Vishakhapatnarn to the HMP =Km. [30 + (358.95-316.6 )]
Lead charges as per SSR 1999-2000 =Rs. 270.00 /tonne
Section 2
Lead distance from Vishakhapatnam to the HMP =Km. [ 30 + (358.95-346.211
=Km. 42.75
Lead charges as per SSR 1999-2000 =Rs. (115+22.75'2.5)'1 15
=Rs. 198.00 Ronne
2.1.4 SAND
Section I
Mix plant location =Km. 316.60
Average lead distance from sand quarries (SI,S2.S3) to
HM I RMC plant location =Km. (37.2+2.4+19.9) I 3
=Km. 19.83
Lead charges as per SSR 1999-2000 =Rs. 100'1.15
=Rs. 115.00 1cu.m.
Section 2
Mix Plant 10~atiOn
Average lead distance of quarries (S4.S5,S6) from
HM IRMC Plant location =Km. (1.60+12.60+3.00) 1 3
=Km.5.73
Lead charges for 8 krn. as per SSR 1999-2000 =Rs. 70.00
Average lead of A2
Average lead of A3
Section 2
Average lead of A4
Average lead of A5
Average lead of A6
2.2.2 SAND
Section 1
Average lead of S1
Average lead of S2
Average lead of 53
Section 2
Average lead of S4
Average lead of S5
Average lead of S6
2.2.3 CEMENT
Section I
Lead distance from Vishakhapatnam to Ch. 300.00
Section 2
Lead distance from Vishakhapatnam to Ch. 333.00
=Km. 42.98
Lead charges as per SSR 1999-2000 =Rs.[l15.00+22.98*2.5]
=Rs. 172.45
=Rs. 172.50 (say)
Section 1
Lead charges
Total cost
Section 2
Average lead distance =Km.[30+(358.95333)+30] 1 2
=Km. 42.98
Lead charges as per SSR 1999-2000 =Rs.[2200+5*125+10'115+17.98'105]
=Rs. 5862.90 ( 2 pipes , 5.5177 length )
=Rs. 533.00 perm pipe
(a) Total cost for 900mm pipe incl. Collar =Rs. 2155.50 per m pipe
(b) Total cost for IOOOmm plpe incl. Collar (2.5m length) =Rs. 2348.00 perm pipe
(c ) Total cost for 1200rnrn pipe incl. Collar (2.5rn length) =Rs.2513.00 per m pipe
Average cost for 1000 rnrn pipe for the project =(2613.00+2348.00)/2
=Rs.2480.50
=Rs. 2481.00 (say)
Average cost for 1200 rnm pipe for the project =(2778.00+2513.00)/2
=Rs. 2645.50
=Rs. 2646.00 (say)
2.2.5 STEEL
Section I
Average lead from Vishakhapatnam
2.2.6 GRAVEL
Section I
Base Rate I Lead charges 1 Stagging & Handling charges ( Final Rate
3068.00 1 239.00 1 10.00 1 3317.00
2.3.2.6 GRAVEL
CHAPTER 3
SUMMARY OF BASIC RATES
C. MATERIAL RATE
I
Chapter 4
Chapter-4
Item Rate Analysis
4.1 Site Clearance
By mechanical means
Unit = Hectare
Machinery
Hour 6.00 1985.00 11910.00
Ownership operational a running charges of Dozer
1191.00
Add 10% contractots profit on Machinery
13101.OO
Labour
Each 0.30 68.00 20.40 'A'
Matelsupervisor
Each 6.00 68.00 408.00
Mazdwr for removing the waste material etc.
428.40
Add for contradots profit and overhead charges @ 64.26
15% on items marked 'A'
Rate per hectare 13593.66
say RS. 13594.00 per
Hectare
202 Dismantling sbucture and pavement up40 1.5 mebe in
foundation andlor 1.5 m above ground level including Tap
and scafolding whereever necessary. sorting the
dismantled material, disposal of un-serviceable material and
1.02 staking the serviceable material within a lead of 100 meters.
1.02.1 I. (a) Cement concrete 1:4:8 or 1:5:10
1.02.1.1
Unit= cu.m
Labour
Each 0.10 68.00 6.80
MatelSupewisor
Each 2.00 68.00 136.00 'A'
Mazdoor
142.80
21.42
Contractots profit & overhead charges @ 15% on 'A'.
164.22
164.22
Rate per cu.m
Say Rs 164.00 percum
1.02.1.2 (b) Cementconcrete 1:3:6
Unit = cu.m
Labour
Each 0.15 68.00 10.20
MatelSupervisor
Each 3.00 68.00 204.00 'A'
Mazdoor
214.20
32.13
Contractor's profit & overhead charges @ 15% on 'A'
246.33
246.33
Rate per cu.m
Say Rs 246.00 per cum
-
Project: 416 Lnning of'Tlmi AnnkngnUi Sectial of NH-5
Sheet 2 of75
Dacu~rmt:990XXIRHIChay4 Date: Noven~ba,2000
Revision: RO
ltenl Rate k~nlysis
Labour
Each 0.25 68.00 17.00
MatelSupe~isor
Mazdoor Each 5.00 68.00 340.00 'A'
357.00
Sundries L.S 5.00
Contractots profit 8 overhead charges @ 15% on 'A'
53.55
415.55
Rate per cu.m 415.55
Say Rs 416.00 per cum
(d)ernent concrete with cleaning.
strengthening and cutting of b a n and separating out
1.02.14 from R.C.C
Unit = cu.m
Labour
Matelsupervisor Each 0.50 68.00 34.00
Mazdoor Each 10.00 68.00 680.00
Blacksmith Each 1.00 95.00 95.00 'A'
809.00
121.35
Conlractor's profit 8 overhead charges Q 15% on 'A'
930.35
Rate per cu.m 930.35
Say Rs 930.00 per cum
1.02.2 II. Dismantling Brickllile work in cement mortar
Unit = c u m
Labour
Matelsupe~isor Each 0.17 68.M) 11.56
Each 3.50 68.00 238.00 'A'
Mazdoor
249.56
37.43
Contractor's prolit 8 overhead charges @ 15% on 'A'
286.99
Rate per cu.m 286.99
Say Rs 287.00 per cum
202-04 111. Dismantling Flexible Pavement with Biiminious
1.02.3 courses, without disturbing the base
Unit = 6.25c u m
Labour
Each 0.30 68.00 20.40
MatelSupe~isor
Each 6.00 68.00 408.00 'A'
Mazdoor
I
428.40
Machifwy
Hour 0.50 2150.00 1075.00
Motorised Scraper
64.26
Contractor's profit & overhead charges @ 15% on 'A'
1567.66
Rate per cu.m 250.83
Say Rs 251 .OO per cum
-
Project: 416 Lnning of Tuni Anaknplli Section of NH-5
Sheet 3 of 75
D R ~ choven~her,
: 2000
Document: 990tiHlRHIChay4
Revidon: RO
Item Rate .hnl?ris
4.2 Earthwork
-
i/
SI'No.
Ref. To MOST
Specification
Description Unit Quantity Rate (Rs.) Cost (Rs.)
Ownership. operational and running charges Hour 0.42 275.W 115.501 'B'
of TipperlDumper5 to 6 Tonne
11.55
Add contractor's prom 10% on item 'B'above
Ownership, operational and running charges Hour 0.5 275.00 137.501 'B'
of TipperlDumper 5 to 6 Tonne
Ownership, operational and running charges Hour 0.57 275.00 156.75) 'B'
of TipperlDumper 5 to 6 Tonne
15.68
Add contractots profit lookon item 'B'above
204.40
Rate for 4.00 cu.m Y +Z
51.10
Rate per c u m = (Y+Z)I*.M) 51 per cum ,
Say Rs
I
.... .... ..
Shra 4 of 75
Date: Novmher, ZOO0
Revision: RO
4.2 Earthwork
Ownership. operational and running charges Hour 0.625 275.00 171.88( '8'
of TipperlDumper 5 to 6 Tonne
Ownership. operational and running charges Hour 0.6666667 275.00 183.33) '8'
of TipperlDumper 5 to 6 Tonne
4
Rate per cum 108.90
Say Rs 109.00 per cum
2.02.2 301 a) Earthwork for excavation by manual means 8
carriage by mechanical means with combined
Excavation for lead of 15m in ordinary soil
Roadway
Drains Unit: cum I
Labour
MatelSupe~isor Each 0.02 68.00 1.36 'A'
Mazdoor Each 0.33 68.00 22.44
23.8
Ownership, operational and running Hour 6 275.00 1650.001'A'
charges of tipperldumper
Add contractor's profit 10% on item 'A' above 165.00 ( '5'
0.5%
10.37 'Y
2.59 'N
0.12
1
~ d contractor's
d profit and overhead charges
@15% on item 'A' above i.e., 3.57
30.08
Earthwork in excavation by
30.08
Mechanicalmeans including carriage
Say Rs 30.00 per cum
4.2 Earthwork
unit=6.67ym I
Rate per cum cum 1 57.50
Area in 1 cum= 6.67 sqm 57.50
4.2 Earthwork
4.2 Earthwork
2.08
I
Ref. To MOST
Specification
501
I
Description
I I I
without disturbing the base
Unit = 1Wsqm
I
By manual means
Labour
Mate Each 68.00 61.20
Mazdoor for scarifying Each 68.00 612.00 'A'
Mazdoor for screening and stacking Each 68.00 612.00
1285.20
Sundries
Contractor's profit and overhead charges @
1
305-05 Blade grading on existing road surface a k r removal 0
existing bituminious surface, watering, scarifying as
necessary and compaction to a depth of 0.2 m
Labour
MateISupervisor
Mazdoor I Each
Each
Machinery
I
Motor Grader . Hour
Vibratory Roller Hour
Water Tanker Hour
By mechnical means
Unit cu.m
(Taking output = I00 cu.m.)
a) Labour
a+b+c+d 767.94
Rate per cu.m
100
767.94
Overall rate =
Say 768.00 per cum
Sheet LO of 71
of TLIIU- .hakapaUi Section of NH-5
Project: 416 L m b ~ g
Date: Novanha, LOO0
Doru~ae~lt: 990XXIRHIChap-4
Revision: RO
Item Hutr Annlpsis
Unitcu.m
Taking output = 100 cum.
a) Labour
i) MateISupervisor Each 0.50 68.00 34.00
Dresser or surveyor for alignment Each 8.63 95.00 819.85 'A'
ii)
iii) Mazdoor ( Skilled ) Each 2.00 68.00 136.00
989.85
Add contractor's prom and overhead charges at
15% on items marked 'A'. 148.48
1.138.33
b) Machinery
c) Miscellaneous
Ref. To MOST
SI.Nr Description Unit Quantity Rate (Rs.) Cost (Rs.)
Specification
4A.01 502 Providing and applying primer coat
over prepared surface of granular
Prime coat base with bitumen heated in bitumen
base boiler ftted with spray set (excluding
cleaning of road surface)
Primer from 7.0-9.8kg and 9.8 to 12.2 kg110 Sqm
for surfaces of low and medium porosity
Unit = Sqm
(Taking unit = 3200sqm)
i) Labour
MatelSupe~isor Each 0.40 68.00 27.?0
Sprayer Each 1.00 95.00 95.00 'A'
Hot MazdoorlMazdwr Each 7.00 95.00 665.00
787.20
Add contractofs profit and overhead
charges at 15% on items marked 'A' 118.08
905.28
ii) Machinery
Ownership, operational and
running charges:-
Bitumen boiler oil fed, capacity Hour 6.00 81-00 486.00
1500 litres faed with spay set
output 0.25 Thour "B'
Farm Tractor Hour 6.00 252.03 1512.00
1998.00
Sundries such as maintenance of
diversion traffic conbol sign
boards 8 for quality control 0.5% 9.99
Miscellaneous items such as soap,
joint paper, coconut oil. Bumol etc. L.S. 100.00
Add contractor's profit @ 10% on items
marked 'B' i.e., 199.80
2307.79
iii) Material
Supply of cut back M.C-70 at Tonne 2.24 8476.00 18986.24
site or any other Bitumen
mixed with Diesel @ 7.0 kg per 10 Sqm
Cost for 3200 sqm i+ii+iii= 22199.31
Rate per sqm i+ii+iii 6.94
3200
Add for cleaning (as per sub analysis ) 2.40
9.34
Rate per sqm 9.34
Say Rs 10.00 per sqm
4A.02 502.4.2 Cleaning the existing WBM road
4A.02.1 8 sulface including removing of
503.3.1 binding material and other foreign
matter with wire brushes and
Prime coat small picks, sweeping with brooms
over granular or soft brushes and finally dusting
base with old gunny bags andlor compressed
air to receive bituminous treatment
Tack coat
Unit=Sqm
(Taking output= 500 sqm )
Labour
MatelSupe~isor Each 1.OO 68.00 68.00 'A'
Mazdoor for cleaning road surface Each 20.00 68.00 1360.00
1428.00
Sundries such as small picks 8 axes,
wire brushes, old gunny bagslbrwm etc. L.S. 50.00
Unit= sqm
(Taking unit=500 sqm)
Labour
. MatdSupe~isor
Mazdoor
Each
Each
0.25
5.00
68.00
68.00
17.00
340.00
357.00
Sundries such as son brushes.broom and d d
gunny bags etc. L.S. 20.00
Unit =Sqm
(Taking output= 1800 Sqm)
Hot MazdoorlMazdoor
Sprayer
Tarring matelSupeMsol
b) Machinery
h e r s h i p , operational and ~ n n i n g
charges of
C) Material
Ref. To MOST
Description Unit Quantity Rate (Rs.) Cost (Rs.)
Specification
4A 04 504 Providing and laying bituminous macadam on
prepared surface with specified graded crushed
Bituminous aggregates for basebinding course including
macadam loading of aggregates with F.E. loader and hot
mixing of stone aggregate and bitumen in hot mix
plant transporting the mixed material in tipper to
paver and laying mixed material with paver finisher
to the required level and grade, rolling by power
roller to achieve the desired density but excluding
cost of primerltack coat
A) 50175 mm compactedthickness
with 3.25% bitumen with lead of mix
material one km
Unit =Cum
flaking output= 110 cum or
242 tonne)
a) Labour
Mate Each 0.50 68.00 34.00
Skilled Mazdoor for alignment etc. Each 4.00 105.00 420.00 'A'
Hot Mazdoor with paver finisher Each 4.00 95.00 380.00
Hot Mazdoor with power roller Each 2.00 95.00 190.00
1024.00
1 I
4A.04 c) Material
- 11.2 mm
I I l~rushed
course aggregates 26.4
-
Crushed stone chipping 11.2 2.8 mm size Cum 23.142 489.00 11316.44
15%of106.4 = 15.96cumx1.45
= 23.142
Cum 37.24 191.00 7112.84
Fine aggregate 2.8 mm below
a+b+c =
I 136931.10
172505.47
1568.23
I I l ~ h r o u rate
~ h per cum
a+b+c
110
1568.23
Say Rs 1568.00 per cum
Shcct 16 of 7 1
Project: 416 1,aning of Tuni - .hakapUl Section of NH-5
Date: November, 2000
Dwommt: 99tlXXIKHIChsyJ Revision: RO
I t a n Rntr 411dyYs
A) 50 mm compacted thickness
with 4.5% bitumen content and
lead of mixed material 1 km
Unit = cum
(Taking output=40 cum) or
40~2.3=92tonne or 1000 sqm
a) Labour
Each 0.30 68.00 20.40 'A'
i) MatdSupewisor
Hot mix plant 40 Tonne per hour Hour 2.50 8220.00 20550.00
i) 770.00 1925.00
ii) Paver finisher 60 tonne Hour 2.50
Hour 9.00 275.00 2475.00 '8'
iii) TipperIDumpers 6 tonne
Hour 2.50 1095.00 2737.50
iv) Pneumatic roller
Hour 2.50 767.00 1917.50
v) F.E. loader (1.O cu.m)
29605.00
Sundries such as maintenance
of diversion, sign boards and
0.5% 148.03
for q u a l i control
L.S. 90.00
Miscellaneous items such as
tarring outfit, soap and Burnol etc.
C) Material
- Specification
---
4A.06 5 1 2 ~
prepared surface with specfied graded stone
Bituminous aggregate for wearing course including loading of
Concrete aggregates with F.E. loader and hot miring of
bitumen filler with aggregates in hot mix plant
transporting the mixed material with tipper to paver
and laying with mechanical paver finisher to the
required level. Grades and rolling with power roller
to achieve the desired density excluding cost of
primeltack coat 50 mm compactedthickness with
5% biutmen and 3% filler with lead 1 km
a) Labour
Mate Each 0.60 68.00 40.80
Skilled Mazdoor for alignment etc. Each 4.80 105.00 504.00 'A'
Hot Mazdwr with paver finisher Each 6.00 95.00 570.00
Hot Mazdoor with power roller Each 2.40 95.00 228.00
1342.80
i a) Coarse aggregates
cum 8.60 560.00 4816.00
26.5mm
cum 46.40 581 .W 26958.40
19mm
cum 29.20 417.00 12176.40
9.5mm
cum 26.50 329.00 8718.50
475mm
cum. 62.30 191.00 11899.30
b) Fine Aggregates
Tonne 7.92 3317.00 26270.64
ii) Supply of cement at site 3%
iii) Supply of bitumen at site
Tonne 13.20 8476.00 111883.20
=110x2.4~51100
202722.44
a+b+c 313156.31
Cost for 110 cum.
(a+b+c)/l 10 2846.88
Through rate per cum
Say Rs 2847.00 per cum
Overall rate
Shra 18 0115
Date: Noventher, 2000
Revision: RO
Type B
UNIT = Sqm
(Taking output = 500 Sqm)
i) Labour
MatelSupervisor Each 1.35 68.00 91.80
Mazdoor Each 21.00 68.00 1428.00 A
Hot MazdoorIBucketman for b i m e n Each 6.00 95.00 570.00
2089.80
Mini hot mix plant 6HO tonne Hour 4.00 1120.00 4480.00
Bitumen boiler oil fed 1500 litre capacity output
250 kgJhr. Hour 3.00 81.00 243.00 B
Power rbller 8-10 tonne Hour 6.00 340.00 2040.00
6763.00
Type A
UNIT = 1 Sqm
(Taking output = 500 Sqm)
i) Labour
MatelSupe~isor Each 1.40 68.00 95.20
Mazdoor Each 21.00 68.00 1428.00 'A'
Hot MazdoorlBucketman for bitumen Each 7.00 95.00 665.00
2188.20
Add contractor's prom and overhead charges @ 15%
on items marked 'A' i.e. 328.23
2516.43
ii) Machinery
Ownership, operational and running charges of
Mini hot mix plant 6HO tonne Hour 4.00 1120.00 4480.00
a k m " ~ d t e d l m * e ~ ~ m k * Hour 4.50 81.00 364.50
Power roller 8-10 tonne Hour 6.00 1095.00 6570.00
11414.50
~ d contractor's
d profit at 10% items marked 'B' i.e. 1141.45
Material
Cement including carriage Tonne 0.150 3317.00 497.55
Admixture Kg 0.450 100.00 45.00
Aggrgate (10-25 mm) Cum. 0.400 512.00 204.80
Aggrgate (610 mm) Cum. 0.470 373.00 175.31
Stone dust Cum. 0.210 191.00 40.1 1
Sand Cum. 0.40 300.00 120.00
Material Cost (A) 1082.77
T8P L.S. 60
Total = 1495.86
Unit = Cum
Material
Cement Tonne 0.450 3317.00 1492.65
Admixture Kg 1.2 100.00 120.00
Coarse Sand Cum. 0.40 300.00 120.00
10 mm aggregate Cum. 0.30 417.00 125.10
20 mm aggregate Cum. 0.85 581.OO 493.85
Joint Filling & Sealant M 20.0 10.00 200.00
water for curing Cum. 0.05 300.00 15.00
Dowel Bar Kg 4.75 16.00 76.00
celltex Board sqm 11.80 20.00 236.00
Tie Bar Kg 0.37 16.00 5.92
Material Cost (A) 2884.52
4.5(A) Culverts
Ordinary Soil
Unit 10 cum.
-
5A.01 .I Depth upto 3 m
Labour
i) Mazdoor Each 6.00 68.00 408.00
iii) Mazdoor for dressing sides, bottom, etc. Each 0.40 68.00 27.20
544.00
Extra for :-
Dewatering 0.20 of labour 108.80
Shoring 8 Shuttering 0.05 of labour 27.20
680.00
Labour
i) Mazdoor Each 7.00 68.00 476.00
ii) Mazdoor for refilling trenches in 250 mm layers.
ramming d watering etc. Each 2.00 68.00 136.00
iii) Mazdoor for dressing sides, bottom, etc. Each 0.50 68.00 34.00
646.00
Labour
i) Mazdoor Each 9.00 68.00 612.00
ii) Mazdoor for refilling trenches in 250 mm layen.
ramming 8 watering etc. Each 2.25 68.00 153.00
iii) Mazdwr for dressing sides, bottom, etc. Each 0.60 68.00 40.80
805.80
4.5(A) Culverts
Ref. To MOST
Description Unit Quantity Rate (Rs.) Cost (Rs.)
Specification
Unit 1 c u m
-
5A.02.1 a) Gravelly material
Material
Labour
Material
Sand Vc carriage
(assuming 20% voids) Cum 1.20 109.00 130.80
Labour
Mazdoor Each 1.00 68.00 68.00
Bhisti Each 0.04 68.00 2.72
70.72
Sundries L.S. 10.00
Unit 1 cum.
Material
Filter medium like stone aggregate of required size cu.m 1.20 345.00 414.00
Labour
4.5(A) Culverts
Unit 1 cum
Material
a) Materials
Unit 1 cum
Material
Stone cum 1.10 191 210.10
Cement Mortar 1:3 cum 0.30 2514.00 754.20
964.30
Labour
Mason Each 2.00 95.00 190.00
Mazdoor Each 1.95 68.00 132.60
Bhisti Each 0.09 68.00 6.12
328.72
R d & Highways
4.5(A) Culverts
Unit = cum
Output=lO cum
i) Material
iii) Machinery
Unit = cum
Material
Dcrntled Pr,~ccrReport
I-!? IT'07WYYORR u,py-4 5 . 4 Sbl
-
Project: 416 Laning of Tuni h a l i a p l l i S d o n of NH-5
Dorun~ent:!BOllRIRH/Chapl
ltml R H ~.Cbalyds
4.5(A) Culverts
Unit = cum
Material
Cement including Tonne 0.33 3286.00 1084.38
Coarse Sand carriage Cum. 0.45 300.00 135.00
40 mm aggregate Cum. 0.52 379.00 197.08
20 mm aggregate Cum. 0.22 581.OO 127.82
10 mm aggregate Cum. 0.11 417.00 45.87
1590.15
Labour
Mason Each 0.10 95.00 9.50
Mazdoor Each 1.63 68.00 110.84
Bhisti Each 0.27 68.00 18.36
Mate Each 0.08 68.00 5.44
144.14
Sundries L.S. 10.00
154.14
Machinery
4.5(A) Culverts
5A.07.2 b) M 25 grade
Unit 1 cum.
i) Materials:
-
5A.07.3 c) Reinforced Cement Concrete in M30 grade
Say Rs 3257.00 per cum
in sub-structure
U n l = 1 Cum..
Material
4.5(A) culverts
Unit = ICum..
Material
Unit 1 cum.
iii) Machinely:
4.5(A) Culverts
Unit 1 Tonne
Material :
Labour :
For cutting, binding, tying and placing
in position
-
Unit per no.
Material
Cost of M.S grating 260 mm x 260 mm
including carriage No. 1.00 17.00 17.00
Cost of anti-corrosiveJbituminous
paint L.S. 54.00
399.00
Labour
Mason Il-class Each 0.10 95.00 9.50
Mazdoor Each 0.20 68.00 13.60
23.10
4.5(A) culverts
Unit 1 metre
4.5(A) Culverts
Unit 1 Cum.
Material
Cement Tonne 0.33 3286.00 1084.38
Coarse sand Cum. 0.45 300.00 135.00
40 mm aggregate Cum. 0.52 379.00 138.32
20 mm aggregate Cum. 0.22 581.OO 127.82
10 mm aggregate Cum. 0.11 417.00 45.87
1531-39
Labour
Mason Each 0.10 95.00 9.50
Mazdwr Each 1.63 68.00 110.84
Bhisti Each 0.27 68.00 18.36
Mate Each 0.04 68.00 2.72
141.42
Hire charges for concrete mixer
(0.2710.20 Cum) Out put 2 Cumhour Hour 0.50 500.00 250.00
a) Boulder
Unit - 1 Cum.
Material
Stone Cum. 1.00 235.00 235.00
Rmds B Ht8hw~l?s
Project: 116 Laning of TIU" - Analiapalli Section of NH-5 Sheel 33 of 71
D o a ~ t n m t :WWXiRHiChay4 Date: Novenlbcr, ZOO
Itrln Rnrr tn~lvsis Revision: RO
4.5(A) Culverts
Unit = 1 cum.
Material
Graded stone aggregate of required size cum. 1.20 379.00 454.80
Labour
Mazdoor (For carrying material from stacks1
stockpiles spreading and compacting etc. Each 1.20 68.00 81 6 0
LS . 1.00
Sundries
82.60
80.61
Contractor's proft and overhead @ 15%
618.01
Say Rs 618.00 per cum.
Rate per cum
5A.16 Clause Pitching on slopes complete as per
2502 (N) drawing and Technical Specification
a) Stone
Unit -1 cum.
Material
cum. 1.00 295.00 295.00
Stone at quarfy including carriage
cum. 0.40 197.00 78.80
Quarry spall at site
Labour 34.00
Masodstone packerlcutler Each 0.50 68.00
Mazdoor (for laying stones, filling of
Each 1.70 68.00 115.60
quarry spalls)
523.40
L.S. 2.62
Sundries at 0.5%
526.01 7
78.90
Contractor's protit and overhead @ 15% 604.92
Say Rs 605.00 per cum.
Rate per cum
5A.17 Clause Rubble flooring complete as per drawing and
2502 (N) . Technical Specihcation
Unit 1 cum.
Materials 295.00
Cum. 1.00 295.00
Stone at quarry
Cum. 0.33 3286.00 1084.38
Cement mortar (1:3) (As per sub analysis) 78.80
Cum. 0.40 197.00
Quarry spalls 1458.18
Labour 27.20
Each 0.40 68.00
MasodStone cutterlStone packer 115.60
Each 1.70 68.00
Mazdoor 142.80
L.S. 5.74
Sundries 1606.72
- 241.01
Contractor's profit and overhead @ 15% 1847.73
Say Rs 1848.00 per cum.
Rate per cum
-
Prajrtl: 4 6 Ltming of Tuni .b~akapalliSection of NH-I Sheel 34 of 75
Date: Novunhcr, ZOO0
Dncument: 99011X/RH/Chapl
Itera Rntr .&u1ls4s Revision: RO
4.5(A) Culverts
Unit - 1 mebe
Material
Unit=m
(Taking output=lOm)
Labour
Mate Each 0.35 68.00 23.80
Mason Each 0.75 95.00 71.25
Mazdwr Each 4.00 68.00 272.00
367.05
Sundries 1.39
Add contractor's proffi @15% 3861.04
4.5(A) Culverts
4.5(A) Culverts
-
Pr~dra:416 Laning of Turli h a l i a p U i Section of MI-5 Sheet 37 of 71
Docwmnt: 990XWIRHIChsp4 Dntr: Novcn~hcr,LOO0
Itall Kntr .An"ly\is
Revision: RO
Labour
Each 6.00 68.00 408.00
ii) Mazdoor for refilling trenches in 250 mm layers.
ramming and watering, etc.
iii) Mazdoor for dressing sides, bottom, etc.
Unit 10 cum
Labour
ChisellerlBreaker Each 37.47 90.00 3372.30
Mazdoor Each 18.74 68.00 1274.32
Black smith I1nd class Each 0.59 68.00 40.12
4686.74
Sundries (1% of labour cost) 46.87
Material
Gravel Material Cum 1.18 109.00 126.44
Labour
Mazdoor Each 1.00 68.00 68.00
Bhisti Each 0.04 68.W 2.72
70.72
L.S. 5.00
Sundries
Material
Filter medium like stone aggregate of required sue cu.m 1.20 345.00 414.00
Including carriage of filter medium.
Labour
Each 1.00 68.00 68.00
Mazdoor
Each 0.05 68.00 3.40
Bhisti
71.40
L.S. 5.00
Sundries
98.08
Contradots profit and ovehead @ 20% i.e..
588.48
Rate per cum
Say Rs 588.00 per cum
11.2 mm(1096) = 0.10 ' rate of 11.2mm aggregate
5.6 mm(lO%) =010 ' rate of 5.6 mm aggregate
2.8 mm(80%)=0.80 ' rate of sand
Total = 345.00
--
-
h,jm: 116 Lsning of T u d Anakaplli Section af NH-5
Shed 39 of 75
Dare: N o v m h r , 2000
h n l m t : 990WHIRHlChay4
Rrvlsim: RO
barn Rare .4nalyws
iii) Machinery
Hire charges for concrete mixer Hour 0.50 500.00 250.00
Hire charges for needle vibrator Hour 0.50 97.00 48.50
298.50
Contractol's prorit & overhead charges @ 35% 7023.8035
Rate for 10 cum. 27091.81
Rate per cum 2709.18
Say Rs 2709.00 per cum
58.06 2 b) P.C.C M 15 grade
Unit = 1 cum
Material
Cement including carriage Tonne 0.33 3286.00 1084.38
Coarse Sand Cum. 0.45 300.00 135.00
40 mm aggregate Cum. 0.52 379.00 197.08
20 mm aggregate Cum. 0.22 581.W 127.82
10 mm aggregate Cum. 0.11 41 7.00 45.87
1590.15
58.06.2 Labour
contd. Mason Each 0.10 105.00 10.50
Mazdwr Each 1.63 68.00 110.84
Bhisti Each 0.27 68.00 18.36
Mate Each 0.08 68.00 5.44
145.14
Sundries L.S. 5.00
Machinery
Hire charges for concrete mixer Hour 0.50 500.00 250.00
Hire charges for needle vibrator Hour 0.50 97.00 48.50
298.50
For Formwork add 5% of
cost of concrete (material & labour) 87.01
2125.80
Contractots pro13 8 overhead charges @ 35% 744.03
Rate per cum. 2869.84
Say Rs 2870.00 per cum
58.0153 C) R.C.C M 20 grade
Unit = 1 cum
Material
Cement including carriage Tonne 0.40 3286.00 1314.40
Coarse Sand Cum. 0.425 300.00 127.50
20 mm aggregate Cum. 0.57 581 0 0 331.1 7
10 mm aggregate Cum. 0.28 417.00 116.76
1889.83
Labour
Mason Each 0.18 1D5.00 18.90
Mazdoor Each 1.73 68.00 117.64
Bhisti Each 0.47 68.00 31.96
Male Each 0.08 68.00 5.44
173.94
Sundries L.S. 5.00
Machinery
Hire charges for concrete mixer Hour 0.50 500.00 250.00
Hire charges for needle vibrator Hour 0.50 97.00 48.50
298.50
For Formwork add 5% of
cost of concrete (material & labour) 103.44
Contractor's profit & overhead charges @ 35% 864.75
Rate per cum. 3335.46
Say Rs 3335.00 per cum
5806.4 d) R.C.C M 25 grade
Unit = I cum
Material
Cement including carriage Tonne 0.41 3286.00 1347.26
Coarse Sand Cum. 0.45 300.00 135.00
20 mm aggregate Cum. 0.63 581 .OO 366.03
10 mm aggregate Cum. 0.27 41 7.00 112.59
1960.88
-
PI-ojed:416 Lnning of Tuni hlalinpnlli Section of NH-I Sheet 41 of 75
Date: Noven~ha,ZOO0
Document: 9MXXlRHlChap4
I t a n Rstc Annlgsis Revision: RO
58.064 Labour
contd. Mason Each 0.18 105.00 18.90
Mazdoor Each 1.73 68.00 117.64
Bhisti Each 0.47 68.00 31.96
Mate Each 0.08 68.00 5.44
173.94
Sundries L.S. 5.00
Machinery
Hire charges for concrete mixer Hour 0.50 500.00 250.00
Hire charges for needle vibrator Hour 0.50 97.00 48.50
298.50
For Formwork add 5% of
cost of concrete (material & labour) 106.99
Extra For Controlled Concrete @ 1% 21.40
Contractots profit & overhead charges @ 35% 898.35
Rate per cum. 3465.08
Say Rs 3465.00 per cum
5B.06.5 e) R.C.C M 30 grade
Unit = 1 cum
Material
Cement including carriage Tonne 0.42 3317.00 1393.14
Coarse Sand Cum. 0.365 300.00 109.50
40 rnm aggregate Cum. 0.382 379.00 144.78
20 mm aggregate Cum. 0.304 581.OO 176.62
10 mm aggregate Cum. 0.299 417.00 124.68
1946.73
Labour
Mason Each 0.18 105.00 18.90
Mazdoor Each 1.73 68.00 117.64
Bhisti Each 0.47 68.00 31.96
Mate Each 0.08 68.00 5.44
173.94
Sundries L.S. 3.00
Machinery (Hire & Running charges for)
Batching Plant (30 cum1Hr) Hour 0.05 1750.00 87.50
Transit M i (4 cum.Hr) Hour 0.33 730.00 243.33
Needle vibrator Hour 0.50 97.00 48.50
379.33
For Formwork add 5% of
cost of concrete (material & labour) 106.28
Extra For Controlled Concrete @ 1% 21.28
ConWactots prom & overhead charges @ 35% 921.39
Rate per cum. 3553.93
Say Rs 3554.00 per cum
58.06.6 f) R.C.C M 35 grade
Material
Cement including Tonne 0.475 3317.00 1575.58
Coarse Sand carriage Cum. 0.40 300.00 120.00
20 mm aggregate Cum. 0.85 5810 0 493.85
2189.43
Labour
Mason Each 0.30 105.00 31.SO
Mazdoor Each 2.50 68.00 170.00
Bhisti Each 0.60 68.00 40.80
Mate Each 0.10 68.00 6.80
249.10
Sundries L.S. 3.00
Machinery (Hire & Running charges for)
Batching Plant (30 cum/Hr) Hour 0.05 1750.00 87.50
Transit Mixer (4 cum.Hr) Hour 0.33 730.00 243.33
Needle vibrator Hour 0.50 97.00 48.50
379.33
For Formwork add 5% of
cost of concrete (material & labour) 122 08
Extra For Controlled Concrete @ 1% 24.42
Contractor's profit & overhead charges @ 35% 1038.57
Rate per cum. 4005.92
Say Rs 4006.00 per cum
-
Hmds Q Highwnyr
-
Projcrt: 416 Laning of Tumi .haL-apnUi Section of NH-5 Shed 42 of 71
Date: Novanher, ZOO0
I>nuun~cnt:99(UIXIRHICliap4
l t c n ~Rntr Annlpis Revision: RO
P.C.C. M 25
(exclude form work) 2438.32
Add for 5% extra for providing extra proteti~e 121.92
works 6 dewatering
Contrador's profit 8 overhead charges @ 35% 896.08
Rate per cum. 3456.32
Say Rs 3456.00 per cum
58.07.5 e) Well Cap
Ref. To MOST
Description Unit Quantity Rate (Rs.) Cost (Rs.)
Specification
Labour
Mazdoor including sinkers Each 9.00 68.00 612.00
Machinery: (Hire& Running charges 00
Crane Hrs 12.00 3100.00 37200.00
Cornpresser (6cumlminute capacity) Hn 3.00 325.00 975.00
Unit = 1 cum
Material
Sand i/c carriage
(assuming20% voids) Cum 1.20 109.00 130.80
Labour
Mazdoor Each 0.25 68.00 17.00
Bhisti Each 0.04 66.00 2.72
150.52
Sundries L.S. 1.00
Contractor's profit and overhead @ 20% i.e.. 30.30
Rate per cum 181.82
Say Rs 182.00 per cum
58.10 Section Bored cast-in-situ R.C.C. vettical Piles with
1100.1600. M-35 Concrete including cost of
1700 Reinforcement
1000 mm dia pile
Unit per running metre
Details of cost for 25 m deep piles
Materials :
i) Concrete : M-35 cum 19.62 4006.00 78597.72
(Rate as per sub analysis)
ii) Bentonite @ 10% of concrete volume Tonne 2.00 1500.00 3OOC.00
Ref. To MOST
Description Unit Quantity Rate (Rs.) Cost (Rs.)
Specification
Machinery :
Hire and running charges of piling rig, bentonite
pumpDiesel,tremie pipe, mixer, tripod and
accessories ilc repair and renewal, muck removal.
mobilisation,shirting pile rigs Hour 80.00 500.00 40000.00
Total 149917.12
Sundries i.e. coffer dam, extra quantity of water, repair
requirement etc. @ 2% of total cost 2998.34
152915.46]'A'
Unit = cum
i) Material
Cement including Tonne 0.475 3317.00 1575.58
Coarse Sand carriage Cum. 0.40 300.00 120.00
20 mm down coarse aggregate Cum. 0.85 581.OO 493.85
' 2189.43
ii) Labour
Mason Each 0.30 95.00 28.50
Unskilled labour Each 2.50 68.00 170.00
Bhisthi Each 0.60 68.00 40.80
Mate Each 0.10 68.00 6.80
246.10
iii) Machinery
Hire charges for concrete batching plant Hour 0.05 1750.00 87.50
Hire charges for trans# mixer Hour 0.33 730.00 243.33
Hire charges for needle vibrator Hour 0.50 97.00 48.50
379.33
Material :
HYSD bars including 5% Wastage Tonne 1.05 16966.00 17814.30
Binding wire Kg. 5.00 28.00 140.00
Cover blocks L.S. 100.00
18054.30
Labour :
For cuning, binding. tying and placing in position
Head Blacksmith Each 5.00 105.00 525.00
Ordinaly Blacksmith Each 5.00 95.00 475.00
Mazdoor Each 10.00 68.00 680.00
1680.00
Material :
Mild Steel bars including 5% wastage Tonne 1.05 16966.00 17814.30
Binding wire Kg. 5.00 28.00 140.00
Cover blocks L.S. 10.00
17964.30
Labour :
For cutting, binding, tying and placing in position
Head Blacksmii Each 5.00 105.00 525.00
Ordinary Blacksmith Each 5.00 95.00 475.00
Mazdoor Each 5.00 68.00 340.00
1340.00
56.14.1 a) M15Grade
Unit = cum
Material
Machinery
Unit 1 cum.
i) Materials:
Cement Tonne 0.41 3286.00 1347.26
Coarse sand cum 0.45 300.00 135.00
20 mm aggregate cum 0.63 581.OO 366.03
10 mm aggregate cum 0.27 417.00 112.59
1960.88
ii) Labour
Unit = 1 Cum..
Material
Cement with addition of 10% Tonne 0.45 3286.00 1478.70
Coarse sand i/c carr cu.m 0.43 300.00 129.00
20 mm aggregate cu.m 0.58 581.OO 336.98
10 mm aggregate cum 0.28 417.00 116.76
- 2061.44
Labour
Mason Each 0.18 105.00 18.90
Mazdoor Each 1.73 68.00 117.64
Bhisti Each 0.47 68.00 31.96
Mate Each 0.08 68.00 5.44
173.94
Hire and running charges
Concrete mixer Hour 0.50 500.00 250.00
Needle vibrator Hour 0.50 97.00 48.50
298.50
Sundries L.S. 10.19
I unit= 1 cum,.
Material
Cement with addit~onof 10% Tonne 0.475
Coarse sand cu.m 0.40
20 mm down coarse aggregate cu.m 0.85
Labour
Mason Each 0.30
Mazdoor Each 2.50
Bhisti Each 0.60
Mate Each 0.10
Sundries L.S.
a) M 25 grade
Unit I cum.
i) Materials:
Cement Tonne
Coarse sand including cum
20 mm aggregate carriage cum
10 rnm aggregate cum
ii) Labour
Mason Each
Mazdoor Each
Bhisti
Mate
-
1'1.ojcct: 416 I.nning ofTuni AnaliapUi Section of NH-5 Sheet 51 of 75
Date: Novenlher. 2000
I)or.un~ent:990HHlRHlChay4
Revision: RO
ltrnl Rate .Analysis
2434.32
Add extra labour for working at height @ 5 % of
cost of labour 8 materials 106.74
2541.ffi
I=
Formwork for solid slab supenbudure, add 20%
of cost of concrete
486.86
3053.34
1068.67
ContracWs profit 8 overheads @ 35 %
4122.00
Say Rs 4122.00 per cum
58.15.1.1 a) For Solid Slab Super Structure cost is
58.152 b) M 30grade
Unit 1 cum.
i) Materials:
iii) Machinery:
of cost of concrete
.
Forrnwork for T-Beam &Slab add 30%
760.46
3433.58
Contractor's profit 8 overheads g 35 % 1201.75
4635.33
For T-Beam 8 SLAB cost is Say Rs 4635.00 per cum
58.15.2.2 b)
58.15.3 c) M 35grade
Unit 1 cum.
i) Materials:
Cement Tonne 0.475 3317.00 1575.58
Coarse sand including cum 0.40 300.00 120.00
20 mm aggregate carriage cum 0.85 581.OO 493.85
2189.43
ii) Labour
Mason Each 0.30 105.00 31.50
Mazdoor Each 2.50 68.00 170.00
Bhisti Each 0.60 68.00 40.80
Mate Each 0.10 68.00 6.80
249.10
iii) Machinery:
Hire 8 running charges for :
56.15.3
contd. .
Formworkfor T-Beam 8 Slab add 30%
of cost of concrete
I
15815.3.21
I II b)
Contractor's profit 8 overheads @ 35 %
M 40 grade
Unit 1 Cum.
Material :
Cement
Coarse sand
Coarse aggregate
(20rnm and down grade)
Admixture
) Labour:
Mason
Mazdoor
Bhisti
Mate
iii) Machinery :
Hire 8 running charges for :
Material :
HYSD bars including 5% wastage Tonne 1.05 16966.00 1781430
Binding wire Kg. 10.00 28.00 280 00
L.S. 10000
Cover blocks
18194.30
Labour :
For cutling, binding, tying and placing in position
Head Blacksmith Each 5.00 105.00 525 00
Olrdinary Blacksmith Each 5.00 95.00 475.00
Mazdoor Each 10.00 68.00 680.00
1680.00
Unit 1 Tonne
Material :
i) H.T. Strand
40m @ 9.42 kglm = 376.8 kg
wastage @ 2% = 7.6 kg = 384.4 kg
Tonne 0.385 45250.00 17421.25
Say. 385 kg
5 8 18 Machinery
contd Jack for prestressing Hour 1.50 82 00 123.00
Grouting pump Hour 1.50 93 00 139.50
Sundrles ~nclud~ng electric charges L.S. 100.00
362.50
Unit 1 Cum.
Material
Taking density as 2.4 tonnelcum.
the weight of mix=lIOx2.4=264 tonnes
Labour :
Mate Each 1.00 68.00 68.00
Mazdoor for hotmix plant, paver.
rollers, for taking levels and
providing security to plants Each 14.00 68.00 952.00
1020.00
309434.72
Machinery :
contd
Add 5% of cost of material for quality
control. testing, miscellaneous items such
as joint paper. Tarring ouifit. Burnol.
soap. cocunut oil, traffic control, sing
boards, maintenance of diverslon, etc.
Unit = Isq.m
I
Details of cost for surface area of 17.4 sq.m for
single layer of 25 mm finished thickness
I
Material :
Taking weight of wearing coat as 1 tonne
I I
(Density of fine aggregate 1.55Tlcum.)
Unit - per no
Material
Cost of anti-corrosivelbituminous
paint L.S. 50.00
Labour
Materials:
Neoprene Kg. 13.81 220.00 3038.20
M.S. Plate including 20% wastage
= 4 5 4 5 ~ 1 . 2 ~ 7=842540 gm. Kg. 42.54 27 00 1148.58
(Sp. Gravity of steel is 7.8 gmlcc) 4186.78
Labour
(@I0096 of cost of material) 4186 78
Unit = Iton
Materials:
Cast steel including 20% wastage Kg. 280.02 27.00 7560.00
M.S. Plate including 20% wastage Kg. 20.00 27.00 540.00
Chloroprene C.C. 6000.00 2.00 12000.00
Stainles steel including 20% wastage Kg. 26.00 150.00 3900.00
PTFE nodules cm. 960.00 20.50 19680.00
Carriage of steel ton 0.33 204.00 66.50
43746.50
Unit = 1 metre
Assume the joint to be designed to cater for
50mm movement
Materiais:
Steel inserts with stainles steel bolts & nuts Kg. 30.00 35.00 1050.00
Eiastometric slab with m.s. plates inserted inside c.c 14000 0.54 7531.45
Polysulphide compound filling space
around bolts 8 nuts L.S. 500.00
9081.45
Labour
(@loo% of cost of material) 9081.45
Contractor's prom and overhead Q 35% 6357.02
Cost of Im expansion joint = 24519.92
Say Rs 24520.00 per lm
Ref. To MOST
Description Unit Quantity Rate (Rs.) Cost (Rs.)
Specification
Unit 1 Cum.
a) Boulder
Unit - 1 Cum.
Material
Stone Cum. 1.00 161.00 161 00
Through and bond stone sue 100no. 7.00 25.00 175.00
7 no. x 0.24 x 0.24 x 0.39 m = 0.16 cum.
336.00
Labour
Mason Each 0.45 105.00 47.25
Mazdoor Each 1.50 68.00 102.00
149.25
Contractots profd and overhead @ 35% 169.84
655.09
Say Rs 655.00 per cum
58.28 Section Filtter material underneath pitching
2500 (N) in slopes complete as per drawing and
Technical specification
Unit = 1 cum
Material
Graded stone aggregate of required size cum. 1.20 306 00 367.20
367.20
Labour
Mazdoor (For carrylng material from stacks1
stockpiles spreading and compacting etc. Each 1.20 68.00 81 60
Sundrles LS 1 00
82 60
a) Stone
Unit -1 cum.
Material
Stone at quarry including carriage cum. 1.00 389 00 389.00
Quarry spall at site cum. 0.40 150.00 60.00
Labour
MasonlStone packerlcutter Each 0.50 105.00 52 50
Mazdoor (for laying stones, filling of
quarry spalls) Each 1.70 68 00 1 15 60
617.10
Unit 1 cum.
Materials
Unit - I melre
Material
Cost of 100 mm dia AC pipe including cartag m 1.05 100.00 105.00
Collar average Each 0.33 25.00 8.25
M S . clamp Each 100 18.00 18 00
Cement mortar I 3 LS 20.00
151.25
Labour
as on
Il-Class Each 0.03 95 00 3.14
Mazdoor Each 003 68.00 2.24
5.38
Sundries L S. 100
157.63
Unit = 1 tonne
Unit = 1 sq.m
Material
Cement Tonne 0.15 3286.00 492.90
Graded Sand cum 0.6 300.00 180.00
Wire mesh 100mrnx100mm size of 3mm wire Kg. 1.O 28.00 28.00
Epoxy Kg. 0.25 400.00 100.00
Diesel Lit. 4.0 17.00 68.00
Miscellaneous consumables like nozzles. L.S. 45.00
wire brush. cotton waste etc. 913.90
Labour
Skilled Labour Each 0.33 95.00 31.35
Mazdoor Each 1.00 68.00 68.W
99.35
Equipment Charges for compressor etc.. L.S. 5000
Contractor Profit 8 overhead charges & 20% 174.24
1237.49
Say Rs 1237.00 per sqm
58.34 Applying epoxy mortar over leached, honey
combed and spalled concrete surface and exposed
steel reinforcement complete as per Technical
specifications (Unit = Isq.m)
-
6.01
Rectangular covered Lined Drain
6.011 i)
Unit =l m
Unlt =I m
cum. 0.13 235.00 29.85
Stone pitching
Unlt = 1 no.
cum. 0.45 2709.00 1221.76
M 10 PCC
L S.
7 50
Sundries such as cost of water at source 472 00
~ d contractor's
d profit 6 overhead charges 42 19
at 151 on ~temsmarked 'A' 795 44
4.6 Drainage and Protection Works
8.00 'A'
MatelSuperv~sor
unlt = I s q m
unit = Nr
unit = 1 m
Material:
Aggregare 20mm & down cum 0.185 358.00 66.23
=(0.45'0.45 - (Pl'O.l5"2/4)} = 0.185 cum
Material.
Cost of 300 dia Plpe
Unit = Lm
Unit: Nr
Cum 0.11 3335.00 366.85
M-20 grade
[(3.14/4)x0.3x0.3~1.5]
Say Rs 367.00 per Nr.
..................................................................................
7.03 409 Constructing footpath separator complete
as per technical specificationclause 409.
Unit = Sqm.
Unit = I 0 0 sqm.
Labour
Each 0.016 68.00 1.09
Matelsupe~isor
Each 0.320 95.00 30.40
Dresser
31.49
Contractots profit and overhead charges
4.72
@ 15% on items marked 'A' i.e..
L.S 0.12
Sundries
24.41
0.24
Rate per sqm
cum. 0.15 332.00 49.80
2) Granular sub-base l5Omm thick
As per sub analysls ( l x l x o 15)
I
floorlng
211.55
Overall rate
........................................................... ............... ...sa.X.R* ...........?l*:%...~e/sq.~
........
. . . . . . . . . . . ................................................
Sltrel (I crf 75
I)HI~:
Novsmlrer. 2lHNl
Hevldo~~: KO
Labour
Each 0.50 68.00 34.00
a) Mate
Each 4.00 95.00 380.00
Dresser
Skilled Mazdoor Each 4.00 95.00 380.00 'A'
Each 2.00 68.00 136.00
Unskilled Mazdoor for ramming
930.00
Add contradots profit and
overhead charges @ 15% on
139.50
items marked 'A' ie..
106950
b) Machinery
L.S. 60.00
c) Cost of water
5.65
Sundries 0.5%
1135.15
Material
Supply of gravel at site including loading,
unloading and stackinglstock piling
cum 29.00 361.00 10469.00
22.4mm to 90 mm
cum 30.00 454.00 13620.00
5.6 to 22.4 mm
Natural sand 5.6mm to 75 micron cum 73.00 109.00 7957.00
32046.00
33188.00
331.88
Rate per cum.
Say Rs 332.00 per cum
7.03.2 Sedon 1500 Subanalysis
& 1700 M-20Grade
Unit = cum
Material
Tonne 0.40 3317.00 1326.80
Cement
Cum 0.42 300.00 126.00
Coarse sand
Cum 0.57 581.00 331 .I 7
20 mm aggregate
Cum 0.28 417.00 116.76
10 mm aggregate
1900.73
Labour
Each 0.09 125.00 11.25
Mason Iclass
Each 0.09 95.00 8.55
Mason I1class
Each 1.73 68.00 117.64
Mazdoor
Each 0.47 68.00 31.96
Bhisthi
Each 0.08 68.00 5.44
Mate
174.84
Machinely
Hour 0.50 500.00 250.00
Concrete mixer
Hour 0.50 97.00 48.50
Needle vibrator
298.50
L.S 1000
Sundries
81.33
For formwork add 5% of cost of concrete
2465.40
369.81
Contractor's proffi & overhead charges
2835.21
@ 15%
say RS. 2835.00 per cum
4.7 Miscellaneous and O t h e r s
Material
Li 4.00 273.00 1092.00
1st quality Paint
L.S 100.00
Material for filling
1192.00
119.20
Contradots profit of 10%
1311.20
7.04 Labour
Each 2.00 125.00 250.00
Painter 1st Class
Each 2.00 95.00 190.00
Skilled Majdwr
440.00
66.00
Contradots profit of 15%
506.00
L.S. 20.00
Sundries
1837.20
Cost for 40 sqm
45.93
Rate per sqm
Say Rs 46.00 per sqm
Material
Li 0.70 273.00 191.10
1st quality Paint
19.11
Contradots profit of 10%
210.21
Labour
Each 0.35 68.00 23.80
Supe~isorlMate
Each 5.00 105.00 525.00
Painter 1st Class
Each 2.00 95.00 190.00
Skilled Majdoor
738.80
Contractofs profit of 15%
110.82
849.62
L.S. 10.00
Sundries
1069.83
Cost for 1600 cm
0.67
Rate per cm height per letter
Say Rs 0.70 per letter
Unit = 1 Number
Unit = 1 Number
Unit = 1 Number
Unit = INumber
i) Material
Bag of
50kg 34.00 3317.00 112778.00
Cement
Cum. 4.70 300.00 1410.00
Sand
Cum. 8.90 581.00 5170.90
20 mm aggregate
119358.90
ii) Labour
Each 1.00 95.00 95.00
Mason
Each 17.00 68.00 1156.00
Mazdoor
Each 2.70 68.00 183.60
Bhisti
Each 1.00 68.00 68.00
Mate
1502.60
L.S. 48.67
Sundries
18181.30
Contractor's profit LL overhead charges @ 15%
139389.97
Rate for 10 cum.
13939.00
Rate per cum
Say Rs 13939.00 per cum
Unit = Icum
Material
Tonne 0.33 3317.00 1094.61
cement
cum 0.45 300.00 135.00
coarse sand
cum 0.52 379.00 197.08 '
40 mm aggregate
cum 0.22 581.W 127.82
20 mm aggregate
cum 0.11 417.00 45.87
10 mm aggregate
1600.38
160.04
Contractor's profit 8 overhead charges @ 10%
Labour
Each 0.05 125.00 6.25
Mason 1st class
Each 0.05 95.00 4.75
Mason 2nd class
Each 1.63 68.00 110.84
Mazdoor
Each 0.27 68.00 18.36
Bhisti
Each 0.08 68.00 5.44
Mate
145.64
L.S 20.00
sundries
24.85
Contractor's profit 8 overhead charges @ 1 5 1
Machinew
0.50 500.00 250.00
Hire charges for concrete mixer Day
0.50 97.00 48.50
Hire charges for needle vibrator Day
298.50
29.85
Contractor's profit 8 overhead charges @ 10%
87.30
for form work add 5% of cost of
concrete (material 6b Labour)
2366.56
cost per cum 2367.00 per cum
Say Rs
-
I'ndcd: 416 I m f n z of Tunl Annknlullll Sn.tlel1 of till-5 Shcrl 72 of 75
Ilnfe: Neve~rlrcr.2OMWI
I)ea~~nenl: Y9IWHiHlli~.lla[r4
Iten) Hale A~~onlysix Revidon: KO
Material
M 15 concrete cum 0.04 3317.00 132.68
Unit = 1 m
(taking 1.90 m length)
concrete ( 1:2:4)
= 1.425'.525'.525 = 0.39 cum cum 0.39 2498.00 974.22
ISHB Metal Beam Kg 149.2 16.97 25319 2
a) ISHB @! 43.10 kgim. @ 1.90 m clc per
central past = 1.90- 43.10 = 77.6 kg
Metal beam for two sides (6mm X 400 mm flat)
I
b)
.
= 1.9 2 = 3.80 m @ 18.84 kg/m = 71.6 kg
Total = 77.6 + 71.6 = 149.2 kg
c)
Ref. To MOST
SI.Nr Description Unit Quantity Rate (Rs.) Cost (Rs.)
Specification
7.13 Clause Painting on kerbs in Black & Yellow alternate
803 hands complete as per drawing & Technical
Specification
Unit = Isq.m
Sundries 25.00
631.82
Contractor Profit 6 overhead charges 8 20% 126.36
Cost for 10 sq.m 758.18
Cost for 1 5q.m 75.82
Say Rs 76.00 per sqm
7.14 805 Providing and fixing R.C.C Guard Post
complete as per Drawing and Technical
Specifications
Unit = 1 Number
Un, = Each
Labour
MateISupervisor Each 0.25 68.00 17.00
Unit = Each
Labour
I Chapter 5
Chapter-5
Summary of Item Rate
1.01 201 Clearing and grubbing road land including uprooting rank vegetation.
grass, brush shrubs, saplings and trees of girth upto 300 mm, removal
l.M) 13594
of stumps, disposal of u n ~ e ~ i c e a bmaterial
le and stackingof serviceable
material upto 100 m from roadboundary
1.02 202 Dismantling structure and pavement upto 1.5 metre in foundation
and/orl.5 m above ground level including T&P and scafolding
whereever necessary, sorting the dismantled material, disposal of un-
serviceable material and staking the setviceable material within a lead of
1.02.1 I Concrete Work
1.02.1.3 (c) Cement concrete plain 1:2:4 mix and precast cement concrete
cum 416
blocks
1.02.1.4 (d) Reinforced Cement concrete with cleaning,strengthening and cum 930
cutting of bars and separating out from R.C.C
1.02.3 202-04 111 Dismantling Flexible Pavement with BAuminious courses, without
cum 251
disturbing the base
5.2 Earthwork
-
2.01 301 to 305 Earthwork for excavation with combined lead of 15m in ordinary soil by
2.01.1 Manual means cum 28
For Carriage
v
2.01.2.1 (i) Lead one km cum 40
2.02.3 305.3.5 b) Extra for laying earth as per specificationfor compaction in 250 mm
thick loose layers and dressing but excluding rolling and watering cum 21
305.3.5 c) Extra for watering the earth to bring the earth upto required O.M.C. cum 7
1 2'02'4
2.02.5 305.3.5 d) Extra for rolling to specification withthe use of vibratory roller when
earth is atsuitable moisture contents with desired field density not 15
less than 95% of maximum density (modified heavy proctor test)
2.03 305.3.4 Compaction of original ground with maximum of six passes of 8-10
tonnes power roller including filling in depression occuring during rolling Scv" 2
2.04.1 Loosening and rewmpacting of original ground upto depth of 1SOmm sqm 9.00
2.07 407 Filling Mediadlsland complete as per Technical specification clause 407
cum 44
with soil
3.01 401 Providing, laying, spreading and compacting specified graded sand.
gravel or any other course material in subbase course including
premixing the material at OMC in mechanical mixer, carriage of mixed
material, spreading in uniform layers with Motor Grader on a prepared cum 768
base and compacting with power roller to achieve the desired density
including all material, labour, machinery, lighting, guarding, barricading
and maintenance of diversion complete.
3.02 406 Providing, laying, spreading and compacting graded stone aggregate to
wet mix macadam specifications including premixing the material with
water to OMC in mechanical mix(Pug Mill), carriage of mixed material
by tipper to site laying in uniform layers in sub-basehase course on cum 969
I well prepared underbase and compacting with power vibratory-roller to
I achieve the desired density including lighting, guarding, barricating and
maintenance of diversion etc.
4A.01 502 Providing and applying prime coat over prepared surface of granular
base with bitumen heated in boiler fitted with spray set (excluding sqm 10
cleaning of road surface)
4A.02 502.4.2 Cleaning the existing WBM road surface including removing of binding
4A.02.1 503.3.1 material and other foreign matter with wire brushes and small picks,
sweeping with brooms or soft brushes and finally dusting with old gunny Sqm 3
bags andlor compressed air to receive bituminous treatment
4A.02.2 Cleaning of the existing black topped surfaces with brooms,soR brushes
and finally dusting with old gunny bags and/or compressed air to receive sqm 1
I bituminous treatment
4A.03 503 Providing and applying tackcoat on the prepared surface, heating
bitumen in boiler and spraying the bitumen with spray set fitted on
Bitumen Boiler.
4A.04 504 Providing and laying bituminous macadam on prepared surface with
specified graded crushed aggregates for baselbinding course including
loading of aggregates with F.E. loader and hot mixing of stone aggregate
and bitumen in hot mix plant transporting the mixed material in tipper to 1568
paver and laying mixed material with paver finisher to the required level
and grade, rolling by power roller to achieve the desired density but
excluding cost of primeltack coat with 3.25 % bitumen
4A.05 507 Providing and laying dens; bituminous macadum on prepared surface
with specified graded crushed crushed aggregates for baselbinder
course including loading of material with F.E. loader, heating of binder
aggregates and filler in hot mix plant, transporting the mixed material by cum 2564
tippers 8 laying with paver finkher to the required level and grade, rolling
by power roller to achieve the desired density but excluding the cost of
primellack coat with 4.5 % bitumen
4A.06 512 Providing and laying biuminous concrete on prepared surface with
specified graded stone aggregate for wearing course including loading
of aggregates with F.E. loader and hot mixing of bitumen filler with
aggregates in hot mix plant transporting the mixed material with tipper to
cum 2847
paver and laying with mechanical paver finisher to the required level,
I Grades and rolling with power roller to achieve the desired density
excluding cost of primellack coat 40 mm compacted thickness with 5%
biutmen and 3% filler with lead 1 km
4A.07 510 Providing and laying open graded premix carpet of 20mm thick on
prepared surface in a single course composed of specified graded
crushed aggregates premixed with a bituminious binder in mini hot mix sqm 45
plant 6-10T laying manually and rolling with power roller 8-10 tonne but
excluding cost of primehack coat.
4A.08 Providing renewal coat wilh mix seal surfacing to the areas of existing
sqm 62
carriageway as per technical specification.
Drtailrd Projrrr R e p u ~ i
I'l>S i ~ ~ ~ - l l l l ~ \ Y Y l N * ' c , ~ p $,,,,,!,,X~
y-~,5,
I'rojst: 416 IAUI~II~ -
of Tuni Aneknlnlli SEdioa of Nll-5
Shed S of 14
Ilnte: Nove~~d~er,
ZIOO
I)I,RI~II~II~:')'HIXXIHIIIC~~I*S
Kevidsn: HI)
S u ~ t ~ s ~of
a r 11e111
y Knte Ann1yui.i
5A.01 Clause 304 Earth work in excavation of foundation for structures complete as per
drawings & specifications.
-
5A.01 1 Depth upto 3 m cum 78
5A.03 Clause Filter medium behind abutment, wing wall and return wall complete as
cum 568
305 per drawing and technical specification
5A.04 Section1300 Brick masonry work in cement mortar 1:3 in Technical Specifications
cum 2131
I 5A.05 Section Stone masonry work in cement mortar 1:3 in foundation complete as per
1300 drawing and Technical Specifications cum 1487
- Coursed Rubble Masonry (first sort)
5A.06 Section Cement Concrete for Plain Concrete1 Reinforced Concrete in open
1500 & 1700 foundation complete as per drawing and Technical Specifications
5A.07 Section Cement concrete for plain concretelreinforced concrete for substructure
1500 & 1700 complete as per drawing 8 Technical Specification
1 5A.7.3 1 Ic) Reinforced Cement Concrete in M30 grade in sub-structure I cum 1 3477 1
Ref. To MOST
Description Unit Unit Rates (Rs.)
Specification
5A.09 Section HYSD bar reinforcement complete as per drawing and Technical tonne 22110
1600 (N) Specification
5A.12 Section 1500. Reinforced Cement Concrete approach slab including reinforcement and
cum 5747
1600, 1700 8 form work complete as per drawing and Technical Specification
5A.13 Section 1700 8 Plain cement concrete M 15 ordinary grade levelling course below cum 2341
2200 approach slab complete as per drawing and Technical specification
Section 2500 (N) Laying apron complete as per drawing and Technical Specification
a) Boulder cum 463
Section Filtter material underneath pitching in slopes complete as per drawing cum 618
2500 (N) and Technical swcification
7.r
Clause 2502 (N) Pitching on slopes complete as per drawing and Technical Specification
Stone I cum 1 605
I 5Al7 ( I
Clause 2502 (N) Rubble floorinp compiete as per drawing and Technical Specification
I
5A.18 Clause 2205 (N) Providing weep holes in Plain Concrete1 Reinforced Concrete abutment,
wing waillreturn wall complete as per drawing and Technical m 181
Specification.
Laying RCC Pipes NP 3 For culverts including pointing ends, and fixing
collar with cement mortar.
5A.20 1000/1300 Brick on edge flooring with 1st Class bricks including cement slurry in
177
cement sand mortar 1:4
5.5(B) Bridges
58.01 304 Earth work in excavation of foundation for structures complete as per
drawings and Technical Specification
50.02 305 Back filling behind abutment, wing wall and return wall complete as per
drawing and Technical Specification
50.03 305. 2504 Filter medium behind abutment, wing wall and return wall complete as
cum 588
per drawing and technical specification
i
58.04 Section Brick masonry work in cement mortar 1:3 in foundation/sub structure
1300 complete as per drawing and Technical Specifications cum 1927
-
58.04.1 Sub-analysis
Cement mortar 1:3 (1 cement : 3 Coarse sand) cum 2514
58.05 Section Stone masonry work in cement mortar 1:3 in foundationlsub structure
cum 1566
1400 complete as per drawing and Technical Specifications
58.06 Section Cement Concrete for Plain Concrete1 Reinforced Concrete in open
1500 & 1700 foundation complete as per drawing and Technical Specifications
WELL FOUNDATIONS
58.07 Section 1200. Cement concrete for PlainIReinforced as per drawing & Technical
1500 8 1700 Specification
58.08 Section Sinking of Well(6m dia) through all types of Soil & Rock (Other than
1200 (N) Pneumatic method of sinking) complete as per drawing & Specifications
58.08.1.2 ii) Depth from 3-10 m: Add the following to the rate of sinking up to 3
m depth.
a) Kentledge (supports, loading arrangement etc.) m 872
I
b) 4 % for every additional metre depth of sinking over the rate
of sinking of the previous metre.
58.09 Section Sand Filling in Wells complete as per drawing and Technical cum 182
1207 (N) Specifications
I
1 58.10 Section 1100, Bored cast-in-situ R.C.C. vertical Piles with M-35 concrete including
1600. 1700 cost of reinforcement.
58.10.1 Cost per wnning metre for 1000 mm dia pile m 8257
cum 3990
58.11.1 Reinforcedconcrete M-35
I
55.12 sectlon 1 6 0 0 ( ~ ) HYSD bar reinforcement in foundationls~b-structurecomplete as Per tonne 22694
drawing and Technical Specification
56.13 Section 1600(N) Mild Steel reinforcement in foundationlsub-structure complete as Per tonne 19304
drawing and Technical Specification
Ref. To MOST
SI.Nr Description Unit Unit Rates (Rs.)
Specification
5.5(B) Bridges (contd.)
58.14 Section Cement Concrete for plain cocretelreinforced concrete for Sub Structure
1500 8 1700 complete as per drawing & Technical Specification
50.15 Section Cement concrete for Reinforced concrete in Super Structure complete
1500 & 1700 as per drawing and Tech. Specf,
58.15.1 A) M 25 grade
1 5815.2 B) M30grade
58.15.2.4 c) For Box Girder & Balanced Cantiliver cost is cum 4845
58.15.3 C) M 35 grade
58.15.3.3 c) For Box Girder & Balanced Cantiliver cost is cum 5848
50.16 Section Cement concrete for prestressed concrete in Super structure complete
1500(N) & as per drawing and Tech. Specf.
1700(N)
a) M 35grade cum 6895
l
58.17 Section HYSD bar reinforcement in superstructure complete as per drawing and 22855
tonne
1600(N) Technical Specifications
5818 Section High tensil steel wireslstrands including all accessories for stressing.
stressing operations and grouting complete as pe rdrawing and 90557
1800 (N)
Technical Specifications
58.20 515 Bitumen mastic wearing coat excluding Tack coat sq.m 158
58.21 2204(N) Drainage spouts complete as per drawing and Technical Specification
Nr 448
58.22.1 Section Supply~ng,fitting and fixing in position true to line and level elastometer
2000 (N) bearings confirming to IRC:83 (Part-11) Section IX, complete with all
1 c.c 0.60
accessories as per drawing and Technicla Specifications
58.22.1 Section Supplying, f i i n g and fixing in position true to line and level POT-PTFE
2MX) (N) bearings suitable for biaxial movement as per drawing and Technicla ton 1000
Specifications
58.23 Section Elastometric Slab Seal type of expansion joint complete as per drawing
2100 (N) 8 Technicla Specifications including acceptance testing as specified, to
m 24520
be installed under supervision of a speciaist manufacturer
58.24 Section Reinforced Cement Concorete ailing complete as per drawing and
m 805
1500,1600, Technical Specification
58.27 Section Laying apron complete as per drawing and Technical Specification
2500 (N)
a) Boulder cum 655
58.28 Section Filter material underneath pitching in slopes complete as per drawing
2500 (N) and Technical Specification cum 607
58.29 Clause Pitchsing on slopes with stones complete as per drawing and Technical
cum 834
2502 (N) Specification
58.30 Clause 2502 (N) Rubble flooring complete as per drawing and Technical Specification
a) Rubble stone laid in cement mortar 1:3 cum 1972
58.31 Clause Providing weep holes in Plain Concrete1 Reinforced Concrete abutment.
2205(N) wing walllreturn wall complete as per drawing and Technical m 213
Specification
58.34 Applying epoxy mortar over leached, honey combed and spalled concrete
surface and exposed steel reinforcement complete as per Technical 5628
sqm
specifications (Unit = 1 sq.m)
Roads B t l i g l ~ ~ ~ o j s
-
I'ntjcct: 416 I,~mingofTuni A n t ~ k ~ ~Sedion
~ n ~ l l iof NII-5
I)oa~~nrnt: ~'HIXX/KII/(:II~~S
Sllmrnnry I B ltcrn Kntc Analysis
6.02 Turfing slopes of new banks, with rough grassing preparation of ground.
Suplying and planting doob grass roots at 15 cm apart, supplying and
spreading farm-yard manure at the rate of 0.18 cum. per 100 Sqm and 'qm 8
loosening soil with kassi. Rate per sqm
6.02.1 Sub Analysis: Earthwork ian excavation in foundation trenches etc. not
exceeding 2 metres depth including dressing of bottom and sides of
trenches, stackaing the excavated and subsequent filling around hume cum 39
pipelmasonry, in 15 cm layers with compaction including disposal of all
surplus soil, as directed within a lead of 30m.
' 6.03 Providing 75mm thick brick lining on drain faces complete as per
drawing 8 Technical Specification. Sqm 100
6.04 Supplying & fixing of pre-cast slab unit size 940mm X 1500mm X
lOOmm in M 20 concrete including cost of all materials, labour,
operations etc. and also including the cost of HYSD Reinforcement Nr 777
complete as per drawing 8 Technical specificationsfor covered drains
6.06 Providing. laying 8 joining 600 mrn dia. NP4 hume pipes for median
drains including the cost of laying 8 compacting backfill providing m 1195
bedding of cement concrete
Roads & H i g l r ~ ~ a y s
Ref. To MOST Description Unit Unit Rates (Rs.)
SI.Nr
Specification
7 01 408 Provlding plain cement concrete M-20 grade kerbs (cast in situ) as per
Im 434
drawing and technical specifications clause 408.
7.04 800 Paintlng Two coats after filling the surface with synthetic enamel paint in
sqm 46
all shades on new plastered surface
7.05 800 Painting New Figures and Letters with synthetic enamel paint in all Per cm per
0.70
shades letter
I
7.06 800 Providing and fixing R.C.C 5th Kilometre Stone complete as per
Nr 1203
Drawing and Technical Specifications
7.07 800 Providing and fixing Ordinary Kilometre Stone complete as per Drawing
Nr 762
and Technical Specifications
7 08 800 Providing and fixing 200 Metre Stone complete as per Drawing and
Nr 182
Technical Specifications
7.90 800 Provid~ng RCC M-15 Boundary Stone complete as per Drawing and
Nr 144
Technical Specifications
1 7.11 Supplying, fixing & erecting pedestrian guard railing with rolled steel
m 542
section as per drawing and technical specification
7.13 Clause Palntlng onkerbs in Black &Yellow alternate hands complete as per 76
sqm
803 drawlng 8 Technical Specification
7 14 805 Providing and fixing R C C Guard Post complete as per Drawing and
Nr 545
Technical Specificat~ons
Ref. To MOST
SI.Nr Description Unit Unit Rates (Rs.)
Specification