Abb Reb650 Busbar High Imp

This document is a commissioning test form for a 87B HIGH IMP. BUSBAR ABB REB650 panel. It contains sections to record (1) general data and information about the panel, (2) results of mechanical checks and visual inspections, (3) results of electrical tests, and (4) results of testing the inputs and outputs. The tests are to check that the panel is functioning properly and as expected according to the design drawings.

Uploaded by

hizbi7
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
501 views6 pages

Abb Reb650 Busbar High Imp

This document is a commissioning test form for a 87B HIGH IMP. BUSBAR ABB REB650 panel. It contains sections to record (1) general data and information about the panel, (2) results of mechanical checks and visual inspections, (3) results of electrical tests, and (4) results of testing the inputs and outputs. The tests are to check that the panel is functioning properly and as expected according to the design drawings.

Uploaded by

hizbi7
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Commissioning Service

Department
Commissioning Standard Test
Formats
Description: 87B HIGH IMP. BUSBAR ABB
REB650
Equip. No. Drawing ref.: Page 1 of 6
Contractor : Contract no.: Substation No :

1. GENERAL DATA AND INFORMATION:

Panel No. Designation 87B/95B


Serial No. Rated Voltage 125 VDC
Make Aux. Voltage 110 250 VAC/DC
CT Ratio 2000/1A Frequency 50 60 Hz

2. MECHANICAL CHECKS AND VISUAL INSPECTION:

ITEM DESCRIPTION CHECKED


1 Inspect for physical damage / defects. Yes N/A
2 Verify Connections as per approved drawings. Yes N/A
3 Check tightness of all connections. Yes N/A
5 Check apparatus lists. Yes N/A
6 Check ferrules Yes N/A
7 Test Switch checked for correct function. Yes N/A
8 Check case earthing. Yes N/A
9 Watchdog contact (X319:3 , X319:2) Yes N/A

3. ELECTRICAL TESTS: With relay energized condition

ITEM DESCRIPTION CHECKED


1 Measured auxiliary supply. Yes N/A
2 Clock set at local time. Yes N/A
3 Time maintained when auxiliary supply removed. Yes N/A
5 Relay healthy (green) LED working. Yes N/A
6 Trip (red) LED working. Yes N/A

Tested by: ENG. Witnessed by:

Signature & Date: Signature & Date:


Commissioning Service
Department
Commissioning Standard Test
Formats
Description: 87B HIGH IMP. BUSBAR ABB
REB650
Equip. No. Drawing ref.: Page 2 of 6
Contractor : Contract no.: Substation No :

4. INPUTS AND OUTPUTS TESTS:

INPUT OPTO-ISOLATORS CHECKS (With Relay Energized):

Go to CONFIGURATION - MONITORING,
I/O STATUS,
then go to BINARY INPUTS VALUES ( X120 (AIM) X110 (BIO) )
to check the values after giving pulse on each BI.

OPTO TEST METHOD RESULT


INPUT (Energize only one at a time with Display FALSE to REMARKS
NO. 125V DC Station Battery voltage) TURE

X324
BI 1 ENERGIZE TB NO. X324 : 2 1 Yes N/A BB-CH PROT OUT

BI 2 ENERGIZE TB NO. X324 : 5 4 Yes N/A BB-CH PROT IN

BI 3 ENERGIZE TB NO. X324 : 6 4 Yes N/A BB-CH CT SHORTED


BB-CH IN/OUT DC
BI 4 ENERGIZE TB NO. X324 : 9 - 8 Yes N/A FAIL
BI 5 ENERGIZE TB NO. X324 : 10 8 Yes N/A RESET DC FAIL

BI 6 ENERGIZE TB NO. X324 : 13 12 Yes N/A INDICATION DC FAIL

BI 7 ENERGIZE TB NO. X324 : 14 12 Yes N/A AC SUPPLY FAIL

BI 8 ENERGIZE TB NO. X324 : 17 16 Yes N/A SPARE

BI 9 ENERGIZE TB NO. X324 : 18 16 Yes N/A SPARE

X329
BI 10 ENERGIZE TB NO. X329 : 2 1 Yes N/A SPARE

BI 11 ENERGIZE TB NO. X329 : 5 4 Yes N/A SPARE

BI 12 ENERGIZE TB NO. X329 : 6 4 Yes N/A SPARE

BI 13 ENERGIZE TB NO. X329 : 9 - 8 Yes N/A SPARE

BI 14 ENERGIZE TB NO. X329 : 10 8 Yes N/A SPARE

BI 15 ENERGIZE TB NO. X329 : 13 12 Yes N/A SPARE

BI 16 ENERGIZE TB NO. X329 : 14 12 Yes N/A SPARE

BI 17 ENERGIZE TB NO. X329 : 17 16 Yes N/A SPARE

Tested by: ENG. Witnessed by:

Signature & Date: Signature & Date:


Commissioning Service
Department
Commissioning Standard Test
Formats
Description: 87B HIGH IMP. BUSBAR ABB
REB650
Equip. No. Drawing ref.: Page 3 of 6
Contractor : Contract no.: Substation No :
BI 18 ENERGIZE TB NO. X329 : 18 16 Yes N/A SPARE

OUTPUT RELAYS CHECKS (With Relay Energized):

Test Procedure:
Go to IED CONFIGURATION,
TESTS, IED TEST, TEST MODE : ON,
then go to BINARY OUTPUTS-CHANGE THE POSITION OF EACH BO FROM FULSE TO TURE FROM
HMI,
then check contact resistance.

TEST METHOD RESULT


OUTPUT
(Energize only one relay at a time by Contact Checked REMARKS
RELAY No.
Test ON in IED TEST) 0.2

X317
BIO1 CONTACT OPERATED X317 : 1 2 (N/O) Yes N/A SPARE

BIO2 CONTACT OPERATED X317 : 3 4 (N/O) Yes N/A SPARE

BIO3 CONTACT OPERATED X317 : 5 6 (N/O) Yes N/A SPARE

BIO4 CONTACT OPERATED X317 : 7 8 (N/O) Yes N/A CT SUPVN. ALARM

BIO5 CONTACT OPERATED X317 : 9 10 (N/O) Yes N/A BB-CH OPTD

BIO6 CONTACT OPERATED X317 : 11 12 (N/O) Yes N/A SPARE

BIO7 CONTACT OPERATED X317 : 13 14 (N/O) Yes N/A SPARE

BIO8 CONTACT OPERATED X317 : 15 16 (N/O) Yes N/A SPARE

BIO9 CONTACT OPERATED X317 : 17 18 (N/O) Yes N/A SPARE

X321
BIO10 CONTACT OPERATED X321 : 1 2 (N/O) Yes N/A SPARE

BIO11 CONTACT OPERATED X321 : 3 4 (N/O) Yes N/A SPARE

BIO12 CONTACT OPERATED X321 : 5 6 (N/O) Yes N/A SPARE

BIO13 CONTACT OPERATED X321 : 7 8 (N/O) Yes N/A SPARE

BIO14 CONTACT OPERATED X321 : 9 10 (N/O) Yes N/A SPARE

BIO15 CONTACT OPERATED X321 : 11 12 (N/O) Yes N/A SPARE

BIO16 CONTACT OPERATED X321 : 13 15 (N/C) Yes N/A SPARE

BIO17 CONTACT OPERATED X321 : 14 15 (N/O) Yes N/A SPARE

BIO18 CONTACT OPERATED X321 : 16 18 (N/C) Yes N/A SPARE

BIO19 CONTACT OPERATED X321 : 17 18 (N/O) Yes N/A SPARE

Tested by: ENG. Witnessed by:

Signature & Date: Signature & Date:


Commissioning Service
Department
Commissioning Standard Test
Formats
Description: 87B HIGH IMP. BUSBAR ABB
REB650
Equip. No. Drawing ref.: Page 4 of 6
Contractor : Contract no.: Substation No :

X326
BIO20 CONTACT OPERATED X321 : 1 2 (N/O) Yes N/A SPARE

BIO21 CONTACT OPERATED X321 : 3 4 (N/O) Yes N/A SPARE

BIO22 CONTACT OPERATED X321 : 5 6 (N/O) Yes N/A SPARE

BIO23 CONTACT OPERATED X321 : 7 8 (N/O) Yes N/A SPARE

BIO24 CONTACT OPERATED X321 : 9 10 (N/O) Yes N/A SPARE

BIO25 CONTACT OPERATED X321 : 11 12 (N/O) Yes N/A SPARE

BIO26 CONTACT OPERATED X321 : 13 15 (N/C) Yes N/A SPARE

BIO27 CONTACT OPERATED X321 : 14 15 (N/O) Yes N/A SPARE

BIO28 CONTACT OPERATED X321 : 16 18 (N/C) Yes N/A SPARE

BIO29 CONTACT OPERATED X321 : 17 18 (N/O) Yes N/A SPARE

INDICATION LED TEST


LED Checks:
Go to hardware test to view the physical position of the LED.

Result Display On or
OPTO Input Number Function
Of
LED 1 Yes N/A PROT IN/OUT
LED 2 Yes N/A CT ALARM
LED 3 Yes N/A R-PHASE ALARM
LED 4 Yes N/A Y-PHASE ALARM
LED 5 Yes N/A B-PHASE ALARM
LED 6 Yes N/A 87BB-CH TRIP
LED 7 Yes N/A R-PHASE TRIP
LED 8 Yes N/A Y-PHASE TRIP
LED 9 Yes N/A B-PHASE TRIP
LED 10 Yes N/A SPARE
LED 11 Yes N/A SPARE
LED 12 Yes N/A SPARE
LED 13 Yes N/A SPARE

Tested by: ENG. Witnessed by:

Signature & Date: Signature & Date:


Commissioning Service
Department
Commissioning Standard Test
Formats
Description: 87B HIGH IMP. BUSBAR ABB
REB650
Equip. No. Drawing ref.: Page 5 of 6
Contractor : Contract no.: Substation No :
LED 14 Yes N/A SPARE
LED 15 Yes N/A SPARE

5. SERIES & SHUNT RESISTOR MEASUREMENTS:

SERIES RESISTOR SHUNT RESISTOR


PHASE
SETTING () MEASURED () SETTING () MEASURED ()
RN
YN
BN

6. PICK UP & DROP OFF TEST FOR CT SHORTING:

R PHASE Y - PHASE B -PHASE


CURRENT
SETTING
Pickup V Drop-off V Pickup V Drop-off V Pickup V Drop-off V

7. OPERATING TIME TEST FOR CT SHORTING:

TIME APPLIED R PHASE Y - PHASE B -PHASE


SETTING VOLTAGE
Pickup (sec) Pickup (sec) Pickup (sec)

8. PICK UP & DROP OFF TEST FOR HIGH IMPEDANCE


DIFFERENTIAL:

CURREN R PHASE Y - PHASE B -PHASE


T

Tested by: ENG. Witnessed by:

Signature & Date: Signature & Date:


Commissioning Service
Department
Commissioning Standard Test
Formats
Description: 87B HIGH IMP. BUSBAR ABB
REB650
Equip. No. Drawing ref.: Page 6 of 6
Contractor : Contract no.: Substation No :

Pickup Drop- Pickup Pickup Drop- Pickup Pickup Drop- Pickup


SETTING
mA off mA V mA off mA V mA off mA V

9. OPERATING TIME TEST FOR HIGH IMPEDANCE DEFFIERENTIAL:

TIME APPLIED R PHASE Y - PHASE B -PHASE


SETTING VOLTAGE
Pickup (msec) Pickup (msec) Pickup (msec)

1 Communication with PC

2 Event Record Check

3 Disturbance Record Check

AL-BABTAIN

Tested by: ENG. Witnessed by:

Signature & Date: Signature & Date: