2016 Chapter 3 Geotechnical Investigation and Sampling

Download as pdf or txt
Download as pdf or txt
You are on page 1of 23

2016 Geotechnical Manual

CHAPTER
THREE

GEOTECHNICAL INVESTIGATION AND


SAMPLING

3.0 GENERAL

All Geotechnical work performed by an approved consultant for the State of Indiana or Local Agencies,
such as any Indiana local municipalities and/or county government involving the use of State or Federal
funds, shall meet the requirements as described herein. All the dimensions of the equipment shall meet the
requirements of AASHTO, ASTM and/or Indiana Test Methods (ITM) s unless otherwise specified herein.

All work performed by the licensed Geotechnical Engineer for state and local agencies under these
requirements shall consist of making a complete foundation investigation for the adequate design and
construction of bridges, roadways and any other associated structures.

A complete foundation investigation shall consist of an adequate program of field sampling, laboratory testing
and engineering analysis and evaluation, with the results presented in report form. The investigation shall be
performed in compliance with the procedures outlined in this document and generally accepted principles of
sound engineering practice. The investigation shall be under the general supervision and subject to the
approval of the Manager, Office of Geotechnical Services of the Indiana Department of Transportation.
Unless otherwise subsequently noted, later references to as approved or directed will imply as approved or
directed by the INDOT Manager Office of Geotechnical Services.

3.1 GEOTECHNICAL SURVEY

The geotechnical survey is defined as the investigation of subsurface conditions along new or existing
highway alignments, as required for the adequate design and construction of bridges, roads and other
necessary structures. This investigation may be preliminary such as a corridor study or it may be more
specific such as the more frequently performed geotechnical surveys of roads, bridges, retaining structures,
landslides, etc. The survey details will depend upon the requirements of the individual project, except for
resurfacing existing pavement and minor maintenance; a Geotechnical Survey will be performed on all
projects.

3.2 PURPOSE OF GEOTECHNICAL SURVEY

The purpose of the geotechnical survey is to identify the existing conditions of the in-situ soils, rock types
and ground water in respect to the project requirements. It will also include the chemical and physical
properties of the soils and rock so as to better enable the engineers to design the most uniform, stable and
cost-effective road or bridge foundations. The survey will also be used to locate construction material for
building embankments along roadways.

3.3 OFFICE STUDIES

Indiana is exceptionally fortunate to have State organizations which have published geological,
agricultural, and water surveys for many years. These publications provide a wealth of information for
nearly every part of the State. Therefore, prior to initiating the field work for any project, a review of this
literature, as well as previous studies done for and by INDOT, should be undertaken. This literature
survey should be followed by an examination of any available boring logs and well drilling records, as
well as any other available information.
Page 1 of 23

2016 Geotechnical Manual

Also, this information gathering could include a review of aerial photography; USDA/SCS reports;
topographic, pedologic, bedrock surface, geologic, INDOT Data Bank, and quaternary deposits maps; and
other pertinent studies which have been completed for and near the project site.

The initial steps for conducting a geotechnical survey are done in the office, prior to going into the field.
First, the project is classified e.g. as an overlay, rubbilization, reconstruction, new construction, bridge
rehabilitation, bridge replacement, or landslide, etc. This will provide an indication of the extent and
complexity of the required geotechnical report. A review of currently available information needs to be
performed.

3.3.1 PRELIMINARY PLANS



The proposed route and grade are a part of the preliminary plans. By review of these plans and the
available literature, a Geotechnical Engineer can identify many of the conditions that could potentially
cause problems. These may include the extent of fill, cut, peat/marl deposits, landslides, sinkholes,
and abandoned mines, etc.

3.3.2 MAPS

Any available maps will be useful in determining the extent to which construction will influence or be
influenced by the physical site conditions. Listed below are types of maps that may prove useful.

Quaternary Geologic Map of Indiana.


1o x 2o Regional Geologic Maps.
7 1/2 Minute Topo Quadrangle Maps.
Topograph of the Bedrock Surface.
Thickness of Unconsolidated Deposits.
Soil Conservative Service County Soil Survey Map.
JTRP A-P Soil Survey.
Map for Seismic Design Specification.
Area Maps For Mines

These maps can be used as guides in planning the Geotechnical Investigation and defining areas of
concern for the site reconnaissance. Additional maps of different types are available through the
Geological Survey in Bloomington, Indiana.

3.3.3 PREVIOUS WORK

Studies and construction plans completed for the existing or nearby projects can be useful in
identifying the problem areas. In particular, previous investigations and construction records that give a
history of the roadway and bridge are useful in planning the investigation.

The INDOT Office of Geotechnical Services maintains many geotechnical reports from previous
projects. This includes preliminary plans, boring logs, test results, field observations, and
correspondence relating to the project. Because of limited space, occasionally older files are
eliminated, so not all projects are available.

Proper use of previous geotechnical data can sometimes reduce geotechnical work in some project
areas. It can help define soil types and pinpoint the areas of typical geotechnical problems even before
the first on-site field investigation.

Page 2 of 23

2016 Geotechnical Manual

3.3.4 AERIAL PHOTOGRAPHY



The first step in any site investigation should be an examination of the area geography. Easy and
quick resources for investigating are the various interactive map sites on the internet. Some examples
include, but not limited to the following sites:
http://maps.google.com
http://maps.yahoo.com
http://earth.goggle.com
Internet maps are more current than the photographs provided by the USD/SCS in their county soil
maps, and the internet maps are set up to be maneuverable to more closely observe features of the
site which are pertinent to the geotechnical investigation.

3.3.5 MAINTENANCE INPUT

It is important to get past performance, history, frequency and type of rehabilitation from the
maintenance engineer. This information can be found during the preliminary field check. Sometimes it
is noteworthy to ask questions about the maintenance history from the local INDOT or county
transportation workers to obtain more details about past problems.

3.3.6 ENVIRONMENTAL CONCERNS

Any available environmental information which could impact the Geotechnical design, should be
reviewed. The Pre-Engineering and Environment Division of INDOT performs environmental
assessment reports on all state projects. Included is the possible presence of old underground storage
tanks, hazardous or toxic spills, etc.

3.4 FIELD RECONNAISSANCE

The Geotechnical Engineer shall attend the preliminary field check and establish the boring locations, rig
type requirements, accessibility and record any existing problems such as pavement distresses, slope
failures or any other problems within the project limits. During the field check, the Engineer should
inquire about any details related to bridges, culverts, retaining structures and time restraints as well as local
ordinances about any construction activities. Environmental concerns should also be reviewed at this time.

3.5 LOCATIONS AND DEPTHS OF BORINGS

Locations and depths of soil borings are very important for the Geotechnical investigation of the proposed
structure. It should provide the maximum possible information about the subsurface conditions for the design of
the structure. The location and the depths of soil borings depend upon the existing topography, type of the
structure as well as shape, size and anticipated loads. The following are the guidelines for soil boring locations
and depths for various kinds of structures. For additional guidance AASHTO section10.4.2 as well as current
FHWA and NHI manuals should be considered. The following series of guidelines are presented to enable the
geologist, geotechnical engineer or others to prepare a subsurface drilling and coring program. However
engineering judgment should also be used to determine the subsurface profile based on known or mapped
geology, and regional geotechnical experience which could include the knowledge of karst areas, mines, rock
elevation extremes and boulder rich glacial sluice ways to name a few.

Page 3 of 23

2016 Geotechnical Manual

3.5.1 BRIDGE STRUCTURES

3.5.1.1 LOCATION OF BORINGS



The site Designer shall furnish plans of structure for which borings are to be made. Generally, the
plans shall consist of road plan and profile sheets, a situation plan showing the location of substructure
elements and cross-sections of the structures approaches. The plan and profile sheets will have
included on them the maximum high water elevation and the stream bed elevation. In general, there
shall be a boring made within 10 feet of each pier and end bent with the borings alternating right and
left of the center line of the structures. Twin structures shall be considered as separate structures.
For substructure units over 100 feet in width, a minimum of two borings per pier should be
performed. Additional borings may be required as described in the following sections, or as directed
by the Engineer. In the case of skewed structures, the borings should be located at the extreme end
of the end bents to better determine any subsurface variation at the maximum end limits of such
proposed structure. When the prescribed boring program does not reveal adequate information to define
various strata, additional borings may be required.

3.5.1.2 DEPTH OF BORINGS

Borings shall be drilled to a minimum depth of 90 feet below ground elevation, unless bedrock is
encountered at a shallower depth. However, if high pile loads are proposed, deeper borings may be
required. Engineering judgment shall be used to determine these additional boring depths. The first
boring performed should be at an interior pier.

In the case of stream crossings, the boring depth shall penetrate a minimum of 15 feet below the
maximum actual scour depth or to a depth below the maximum actual scour depth sufficient to carry
the pile loads with the scourable overburden materials removed, whichever is greater. The latter
depth shall extend 10 feet below the anticipated pile tip elevations. Engineering judgment shall be
required to establish the pile tip elevations required to carry the pile loads and should be handled on
an individual basis for each structure. Specific guidelines for the final depth of boring in soil and in
bedrock are outlined below.

3.5.1.3 BORINGS IN SOIL



Borings in any soil shall penetrate to the specified depth and penetrate a minimum of four
consecutive split spoon samples into material having a standard penetration blow count (N) of
fifteen (15) or greater. If this minimum penetration of fifteen (15) blows per foot material has not
been obtained at the proposed boring termination depth, the boring shall be extended until this
requirement is met or the project geotechnical engineer should be contacted for further guidance.

When ground water is encountered, water or other drilling fluids should be added to the hole to
maintain the water level in the hole at or above the ground water level to aid in avoiding a quick
condition when granular soils are encountered. This precaution will keep the sand from coming up in
to the casing. The ball check valve in the split-spoon sampler should not be removed, and washing
through the spoon will not be permitted.

Page 4 of 23


2016 Geotechnical Manual

3.5.1.4 BORING THROUGH ROCK



When rock is encountered in the boring, rock coring will be required in each boring. Rock coring
should not begin until auger refusal is obtained. When auger refusal as specified below is not
achieved within 10 feet of encountering bedrock, the project geotechnical engineer should be
contacted for guidance. Auger refusal shall be defined as auger penetration of less than 6 inches
under 500 psi of auger-feed down pressure for a period not less than 10 minutes. Rock coring
should not begin or end in weathered shale, weathered limestone, etc., unless absolutely necessary.
Coring and sampling shall not be terminated in coal seams or voids. Recovery and Rock Quality
Designation (RQD) shall be calculated and recorded before transporting core samples from boring
locations.

If rock is encountered in the course of conducting borings for a structure a minimum length of
coring of 10 feet into rock will be required at each substructure with a minimum recovery of
75% and a minimum RQD of 50%. If these values are not achieved an additional 5 feet of coring
shall be completed. This coring shall be conducted in 5 foot runs. 10 foot runs will only be
allowed in special cases and shall be pre-approved by the Office of Geotechnical Services. If the
project is in an area in which it is known that geologic conditions will not allow the above criteria to
be met engineering judgment must be applied. A sounding shall be performed at the opposite end
from the boring made for each pier and/or each bent. These soundings shall be terminated in sound
rock after achieving auger refusal. If there are layers of soft materials or voids in the cored rock, or
there are other geological uncertainties, a minimum length of 10 feet o f rock core shall be taken
from each boring and sounding at each substructure.

3.5.2 SEWERS, PIPES AND CULVERTS

3.5.2.1 TRENCHLESS PIPE INSTALLATION



A minimum of two borings per 150 ft of trenchless pipe shall be obtained. The depth of the boring
shall be a minimum of 5 feet or twice the pipe diameter below the invert elevation whichever is
deeper. The sampling shall be continuous. Where groundwater is encountered, consideration shall
be given to installing an observation well. Where rock is encountered within the required boring
depths a five (5) foot rock core shall be obtained.

3.5.2.2 STORM SEWERS

Borings shall be located over proposed sewer at points of maximum invert depths with a
maximum spacing of 500 feet. A minimum of two split spoon samples shall penetrate below the
invert elevation. When rock is encountered, coring shall be performed and a minimum 5 foot core
shall be obtained. In areas that are inaccessible to machine drilling, hand auger soundings shall be
performed to delineate the soils.

3.5.2.3 SMALL CULVERTS (LESS THAN 4 FEET DIAMETER)

A minimum of one sounding shall be made at each end of the pipe within the existing ditch, creek or
steam channel to determine the depth of any soft soils to be removed. The depth of soundings shall
extend a minimum of one pipe diameter below the proposed flow line, or into firm material.
Additionally, DCP tests shall be performed at each end of the proposed culvert to a depth of 5 feet
with blows recorded per each six inch increment.

Page 5 of 23


2016 Geotechnical Manual

3.5.2.4 LARGE CULVERTS (GREATER THAN 4 FEET DIAMETER)

For all drainage structures 4 feet or wider, the minimum number of borings and soundings required
depends on the structure length as summarized below:

Drainage structures less than 150 feet in length will require a minimum of one (1) boring
near the maximum proposed fill height. The depth of the borings should be a minimum of
twice the structure width below the invert elevation or twice the fill height whichever is deeper.
If rock is encountered within the proposed depth of excavation, coring shall be performed. A
minimum of one 5 foot core shall be taken for each structure. In areas that are inaccessible to
machine drilling, hand auger soundings shall be performed to delineate the soils.

Drainage structures greater than or equal to 150 feet in length will require one (1) boring near
each outside shoulder at the proposed maximum fill height. The depth of the borings should
be a minimum of twice the drainage structure width below the invert elevation or twice the
fill height whichever is deeper. If rock is encountered within the proposed depth of excavation,
coring shall be performed. A minimum of one 5 foot core shall be taken for each structure. In
areas that are inaccessible to machine drilling, hand auger soundings shall be performed to
delineate the soils.

In the event the proposed drainage structure crosses an existing ditch, creek, or stream channel,
the boring criteria above should be followed and an additional boring shall be located in the
existing channel. If the additional boring is inaccessible to machine drilling a minimum of one
(1) DCP test shall be performed at that location to a depth of 5 feet. Blow counts shall be
recorded for each 6 inch increment.

3.5.2.5 PLATE ARCHES ON FOOTINGS



Often large structures are proposed which are not considered to be bridges by the INDOT Division of
Design. An example of these structures is structural plate arches on footings (bottomless).
Borings should be located under the footing within the existing channel along the entire length of the
structures, at intervals not exceeding 100 feet and at the ends. The borings should alternate from
one side to the other. Soundings should be performed between the borings and at the ends within
the existing and the proposed channel. The depth of the borings should be a minimum of twice
the structure width below the invert elevation or twice the fill height whichever is deeper. If the
proposed channel borings are inaccessible to machine drilling DCP tests shall be performed at those
locations to a depth of 5 feet. Blow counts shall be recorded for each 6 inch increment.

3.5.2.6 CULVERTS ON FOOTINGS

Box culverts on spread footings (bottomless) are another example of large structures not
considered to be bridges. For box culverts wider than 10 feet, the minimum depth of the boring
shall be 30 feet below the invert of the proposed foundation. Borings shall penetrate to the
specified depth and penetrate a minimum of four consecutive split spoon samples into material
having a standard penetration blow count (N) of fifteen (15) or greater. If this minimum penetration
of fifteen (15) blows per foot material has not been obtained at the proposed boring termination
depth, the boring shall be extended until this requirement is met or the project geotechnical
engineer should be contacted for further guidance. If rock is encountered within the planned depth of
investigation a minimum of one 5 foot rock core should be taken for each structure. RQD and
recovery percentages should be as described in Section 3.5.1.4.

Page 6 of 23


2016 Geotechnical Manual

3.5.3 RETAINING STRUCTURES

Wall type, location and limits are often not delineated well enough at the early stage of planning and
development of the project. Therefore, preliminary engineering report, plans, visual inspection and
discussions with designers should be employed to develop a scope of subsurface investigation for
retaining structures.

3.5.3.1 CANTILEVER RETAINING WALLS



Borings should be located at the proposed extremities and along the proposed alignment of retaining
structures as closely as possible. Boring spacing along the alignment shall be no more than 100 feet
for walls less than 20 feet high and no more than 50 feet for proposed wall heights greater than 20
feet. Each proposed wall shall have a minimum of 2 borings completed along the proposed
alignment. Back borings shall be completed at a distance of 1 1.5 times the proposed wall height
behind the proposed alignment and at a spacing of 100 feet along the alignment. The depths of
borings shall be a minimum of twice the height of the wall.

Borings shall penetrate to the specified depth and penetrate a minimum of two consecutive split
spoon samples into material having a standard penetration blow count (N) of fifteen (15) or
greater. If this minimum penetration of fifteen (15) blows per foot material has not been obtained at
the proposed boring termination depth, the boring shall be extended until this requirement is met or
the project geotechnical engineer should be contacted for further guidance.

Where rock is encountered in the planned depth of investigation, a minimum of one 5 foot rock core
shall be taken for every 150 feet of wall length with a minimum of 2 cored boreholes for each wall.
Non-cored borings shall be terminated after achieving auger refusal and competent rock profile
developed.

3.5.3.2 ANCHORED WALLS

Borings should be located at the proposed extremities and along the proposed alignment of retaining
structures as closely as possible. Boring spacing along the alignment shall be no more than 100 feet
for walls less than 20 feet high and no more than 50 for proposed wall heights greater than 20 feet.
Each proposed wall shall have a minimum of 2 borings completed along the proposed alignment.
Back borings shall be completed at a distance of 1.01.5 times the proposed wall height behind the
proposed alignment and at a distance of 100 feet along the alignment. Front borings shall be
completed in front of the proposed wall at a distance of 0.75 -1.0 times the proposed height and at a
spacing of 100 feet along the proposed alignment.

The depths of borings shall be a minimum of twice the height of the wall. Borings shall penetrate
to the specified depth and penetrate a minimum of two consecutive split spoon samples into
material having a standard penetration blow count (N) of fifteen (15) or greater. If this minimum
penetration of fifteen (15) blows per foot material has not been obtained at the proposed boring
termination depth, the boring shall be extended until this requirement is met or the project
geotechnical engineer should be contacted for further guidance.

Where rock is encountered in the planned depth of investigation, a minimum of two 5 foot rock
cores shall be taken for every 150 feet of wall length with a minimum of 2 cored boreholes for each
wall. 10 feet of rock cores shall also be obtained from back borings for anchor design. Non-
cored borings shall be terminated after achieving auger refusal and competent rock profile developed.

Page 7 of 23


2016 Geotechnical Manual

3.5.3.3 MSE WALLS

Borings should be located at the proposed extremities and along the proposed alignment of retaining
structures as closely as possible. Boring spacing along the alignment shall be no more than 100 feet
for walls less than 20 feet high and no more than 50 feet for proposed wall heights greater than 20
feet. Each proposed wall shall have a minimum of 2 borings completed along the
proposed alignment. Back borings shall be completed at a distance behind the proposed wall of 1.0
1.5 times the proposed wall height and at a spacing of 100 feet along the alignment.

The depths of borings shall be a minimum of twice the height. Borings shall penetrate to the
specified depth and penetrate a minimum of two consecutive split spoon samples into material
having a standard penetration blow count (N) of fifteen (15) or greater. If this minimum penetration
of fifteen (15) blows per foot material has not been obtained at the proposed boring termination
depth, the boring shall be extended until this requirement is met or the project geotechnical
engineer should be contacted for further guidance.

Where rock is encountered in the planned depth of investigation, a minimum of one 5 foot rock core
shall be taken for every 150 feet of wall length with a minimum of 2 cored boreholes for each wall.
Non-cored borings shall be terminated after achieving auger refusal and competent rock profile
developed.

3.5.4 ROADWAY IMPROVEMENT



In general, borings for roadway improvements shall be dictated by the topography, geological
conditions, visible soil conditions, and other design considerations. Borings should be located at the
maximum cut or fill along the cross sections for new horizontal alignments. The borings should be
spaced at 300 foot to 500 foot intervals for each two lane roadway and drilled to a minimum depth of
10 feet below the proposed grade. In the instance of divided highways each bound should be
considered as a separate roadway when boring locations are considered. Engineering judgment
should be used in sections of roadway where deeper subsurface investigation may be warranted.
Sufficient borings in widening areas should be planned to cover proportionately the total widening
area with respect to total project length/area.

3.5.4.1 CUT SECTIONS



For cut sections where the proposed depth of cut is greater than 15 feet borings shall be spaced not
more than 200 feet along the length of the proposed cut. Borings shall be located at the point of
maximum cut and shall penetrate to a depth of 10 feet below the proposed grade line. Borings
shall not stop in soft, very loose or unsuitable soils but should be extended a minimum o f 3 feet
into firm material, unless otherwise approved. If rock is encountered below th e propo sed
subgrade elevation, the borings on the centerline shall extend at least 5 feet into the rock. Cut
section borings made in the ditch line shall extend 2 feet below the proposed flow line or 10 feet
below the proposed finished grade line, whichever is deeper. Core borings made in rock back
slopes shall be to a minimum depth of 2 feet below the proposed grade.

Soundings made to determine the limits of rock shall be discontinued at the rock surface or four
feet below proposed grade line, whichever depth is encountered first, or as otherwise approved.

Page 8 of 23


2016 Geotechnical Manual

3.5.4.2 FILL SECTIONS



Borings shall be located in areas of maximum fill at a spacing not greater than 400 feet for the fills
less than 20 feet for two lane highways. Borings shall be located at a spacing not greater than 200 ft
for fill heights greater than 20 feet unless otherwise approved. Roadway borings in fill sections shall
penetrate to a depth of 10 feet or to a depth 2 times the height of proposed embankment, whichever
is greater. Where fills cross stream flood plains, old lake beds, ponds, or other areas of suspected
compressible or low-strength foundation soils, the borings shall penetrate to a minimum depth equal
to the fill height into the firm ground regardless of fill height. Borings shall not be terminated in soft,
very loose or unsuitable soils but should be extended into firm material with the last two SPT N
values greater than 10.

If rock is encountered in p r o p o s e d fill sections, the borings shall be discontinued at auger


refusal or the proposed depth as determined above (whichever is shallower). One core boring shall
be made 5 feet into the rock to establish its quality.

3.5.4.3 SPECIAL CASES

Side Hill Cut Sections: A series of not less than two borings shall be conducted at each prescribed
station such that a geologic cross section can be created. One boring shall be located at the maximum
up-hill extent of the proposed cut and shall penetrate to a minimum depth of 10 feet below the
proposed final grade. A second boring shall be located at the proposed ditch line and shall penetrate
to the minimum depth described above. If the width of the proposed cut is greater than 100 feet from
ditch line to ditch line a third boring shall be conducted. The third boring shall be located in the
proposed ditch line opposite the first ditch line boring. The depth shall be as described in Sections
3.5.4.1 and 3.5.4.2.

Side Hill Cut To Fill Section: When one side of centerline is in cut and other side is in fill borings
shall be located in such way to capture the subsurface conditions of the cut section, the fill section
and the ground water conditions. Boring depths shall be as described in Sections 3.5.4.1 and 3.5.4.2
with the additional requirement that the vertical overlap between the two borings shall be a minimum
of 10 feet.

Side Hill Fill Section On Unstable Slope: When embankment fill is to be placed on slopes where
instability is predicted, a series of not less than 3 borings shall be conducted such that a geologic
cross section can be created. Locate a boring at the toe of downhill side and other at intersection of
the 1:1 slope from edge of pavement with ground line .The boring should be terminated twice the
height of the fill or into rock. A rock core of 5 feet shall be taken. A third boring shall be performed
at toe of the uphill slope to complete stratigraphy. All these three borings shall overlap vertically.

3.5.4.4 PAVEMENT REHABILITATION/FULL DEPTH RECLAMATION

Ground Penetrating Radar (GPR) and Falling Weight Deflectometer (FWD) testing shall be
performed prior to the proposal of boring locations. The anomalies discovered by these tests shall be
delineated and boring and ground water monitoring shall be planned. If the GPR and FWD testing is
to be completed by INDOT a request shall be submitted to the Office of Research by filling out the
on-line form found at: FIND LINK

GPR is a valuable tool for reducing the number of borings for a project by segmenting the project on
the basis of similar subsurface features or anomalies identified prior to subsurface investigation. GPR
may also be used to investigate the internal composition of many pavement layers and soils. Results
from the condition and GPR surveys could be used to prepare plan for FWD testing. Boring plans
will be prepared with condition survey, GPR and FWD testing to ensure that all the areas with
different physical features and characteristics have been investigated.
Page 9 of 23


2016 Geotechnical Manual

Borings shall be placed at approximately 600 to 800 foot intervals, alternate from left to right lanes
and in the case of divided highways, in the driving lanes alternating left to right sides. Borings shall
extend to a minimum depth of three continuous split samples below the proposed subgrade
material. Split spoon samples shall be taken recording various thicknesses of pavement and sub base
material. In the event of soft, (N < 6), organic or unsuitable soils, the INDOT Office of
Geotechnical Services should be contacted for additional instruction. Additional borings shall be
competed for the purposes of obtaining 24 and 48 hour water readings. These borings shall be placed
in at-grade and cut sections at a minimum frequency of 2 per mile and shall penetrate to a depth of 10
feet below the proposed grade. Measures shall be taken to insure that the borehole remains open to
the full depth for the required monitoring period. This may require the temporary placement of
slotted PVC pipe or similar measures.

3.5.5 HIGH MAST TOWER LIGHTS



High mast tower lights require a soil investigation at each location. These borings shall be drilled to a
minimum depth of 25 feet with an N value of fifteen (15) blows or greater for the last 15 feet of the
boring. If these criteria are not met drilling must continue until 15 continuous feet of greater than 15
blow material has been encountered. I f t h e above criteria cannot be met within a reasonable depth or
rock is encountered within the required depth the project geotechnical engineer should be contacted and
engineering judgment will be made as to the extent of additional drilling.

3.5.6 TRAFFIC-SIGNAL CANTILEVER STRUCTURE



Traffic-signal cantilever structures require a soils investigation at each intersection to be signalized.
These borings shall be drilled to a minimum depth of 25 feet with an N value of 15 blows or greater for
the last 15 feet of the boring. If these criteria are not met drilling must continue until 15 continuous
feet of greater than 15 blow material has been encountered. In case soil c o n d i t i o n s a r e
not encountered as noted above or rock is encountered within the required depth o f inv estig ation
the project geotechnical engineer should be contacted and engineering judgment will be made as to the
extent of additional drilling.

3.5.7 TRAFFIC SIGNS & LIGHT POLE FOUNDATIONS


Traffic sign or light pole foundations require a soils investigation at or near each proposed foundation. If
multiple foundations are proposed within approximately 75 feet of each other, such as at a small to
moderate sized intersection, one exploration point for the foundation group is adequate if conditions are
relatively uniform. If more variable site conditions are anticipated, one boring near each foundation should
be obtained. These borings shall be drilled to a minimum depth of 20 feet or 5 feet below the anticipated
bottom of the foundation, whichever is greater. Only a site review is required if the new structures are to
be founded in new or existing embankments known to be constructed of sands, b borrow or select backfill
and compacted in accordance with 203 of the INDOT Standard Specifications.

3.5.8 CABLE BARRIER SYSTEMS



Cable barrier systems require soil investigations for barrier termination anchor points. A minimum of
one boring should be completed at each proposed termination anchor point. These boring shall be
drilled to a minimum depth of 25 feet with an N value of 15 blows or greater for the last 15 feet of the
boring. If these criteria are not met drilling must continue until 15 continuous feet of greater than 15
blow material has been encountered. In case soil is not encountered as mentioned above or rock is
encountered within the required depth the project geotechnical engineer should be contacted and
engineering judgment will be made as to the extent of additional drilling.

Page 10 of 23


2016 Geotechnical Manual

3.5.9 SPECIAL GEOLOGIC CONDITIONS

3.5.9.1 PEAT, MARL OR ORGANIC DEPOSITS



Natural peat bogs often consist of a layer of peat or a combination of organic and mineral deposits
overlying stable soils. While the upper layers may vary markedly in composition and exhibit a
range of physical properties, they are entirely unsuitable as subgrade for highways. These
materials must be dealt with in such a manner that they do not cause detrimental settlement or
perhaps failure of the embankments or roads built upon them.

Careful attention must be taken when determining the extent of organic and marl deposits. Borings
should be completed on both sides of the roadway at a maximum spacing of 50 feet and shall
extend a minimum of 10 feet into firm material. Firm material shall be defined as mineral soils
with an N value of 10 blows or greater. Split Spoon samples shall be taken continuously for the
entire length of the boring and the complete sample shall be logged. The boring pattern at the
lateral limits of these deposits shall be such that the limit can be determined with an accuracy of less
than 10 feet.

3.5.9.2 LANDSLIDES

Landslides are most prevalent in the un-glaciated southern half of Indiana. Causes vary, but most
are caused by weak soil and rock in the upper strata and variability in groundwater conditions.
Landslides should not be confused with simple fill failures (which are easier to repair) or with
embankment erosion problems which result in sloughing of fill materials. Landslides are gravity
transported downward sliding or falling of soil and rock mixtures which have become loosened or
detached, with movement being along a plane. The landslide area will have obvious scarps and toe
bulges and if the slide has been a slow, continuous movement, trees growing in the slide will be
bent to compensate for the movement of their base. Quick movement can occur and is obvious by
the destruction caused by the falling materials.

Borings should be located so that geologic cross sections of the landslide can be constructed. The
cross section shall include borings above the scarp line, within the failure and beyond the toe bulge of
the failure. Cross sectional borings shall be completed at a maximum spacing of 100 feet
perpendicular to the direction of failure. All borings shall extend to bedrock and auger refusal shall be
achieved. Split Spoon samples shall be taken at 2.5 foot intervals for the entire length of the boring
to auger refusal unless otherwise specified. A minimum of one 5 foot rock core shall be completed
in critical borings to be determined by the geotechnical engineer.

3.5.9.3 MINE SUBSIDENCE

Underground mining occurs mainly in western and southwestern Indiana and has a long tradition.
There are many undocumented individual sites mined out prior to remediation where subsidence
may occur. The presence of underground mines is reflected in local areas of depression or
settlement of the ground surface which can occur gradually or in a very short period of time.

The Indiana Department of Natural Resources (IDNR) and the Indiana Geological Survey (IGS),
working with the states mining industry, have developed maps of the known surface and
underground mine locations. Mine locations are always to be considered during the planning phase of
any new construction. Undocumented mine locations and possible mine subsidence represent a
definite risk. Mine subsidence issues are handled on an individual basis because of the site specific
conditions affecting each mine Because they are familiar with their own areas, it is up to the
INDOT district personnel to inform the necessary contact person with the OGS and IDNR when any
subsidence problems are observed.
Page 11 of 23


2016 Geotechnical Manual

The scope of investigation should be determined on a case by case basis, and the boring layout
should be similar to the peat investigation pattern to help minimize the number of borings to draw
the required profile.

3.5.9.4 KARST

Like mine subsidence, sinkholes can be insidious. They can appear suddenly or develop slowly.
Sometimes pavement, especially concrete, can hide a developing sinkhole until the road surface
breaks from lack of subsurface support and a major problem can develop very rapidly.
Unfortunately, there are no maps of developing sinkholes except for old topographic maps, which
may show depressions, or known sinkholes which were plugged and covered up prior to
construction.

As with potential mine subsidence locations, karst areas should always be considered during the
planning phase of any new construction. A careful site investigation must be conducted in karst
areas to spot any potential settlement areas followed by a Geotechnical investigation.

The Geotechnical investigation should establish the depth to bedrock, the extent of the cavity and
the drainage pattern of the subsurface water.

The scope of Geotechnical investigation should be determined on a case by case basis, and the
boring layout should be similar to the peat or mine subsidence investigation patterns. Geophysical
techniques can be very helpful in targeting and refining the boring program proposed to investigate
karst areas.

3.5.9.5 LANDFILLS

A landfill is a man-made feature which generally provides unsuitable material for the roadway
substructure. INDOT policy is to suspend all geotechnical drilling and report the condition to
INDOT Office of Environmental Services. All applicable OSHAA safety precautions and
procedures should be followed in the completion of the geotechnical investigation. The limits and
depth of the landfill shall be determined to facilitate remediation recommendations in a manner
similar to the delineation of peat and marl deposits.

3.5.9.6 BUILDINGS

Each project is drilled on an individual basis depending upon the areas architectural design.
Commonly (but not limited to) Geotechnical soil borings are placed at areas of maximum stress
and extend a minimum of 15 feet into stiff soil.

3.5.9.7 WETLANDS AND DETENTION PONDS

Wetlands and swampy areas usually fall under the peat/organic category although not all wetlands
contain peat, they could have a sand or silt bottom. The boring pattern should be based on a case by
case basis. The boring should be extended to a minimum of 15 feet into firm material. Firm
material shall be defined as mineral soils with an N value of 10 blows or greater.

Wetlands are protected under established federal guidelines. Before any investigation is started, all
appropriate permits and a list of all work restrictions must be obtained from the Indiana
Department of Natural Resources through INDOTs Office of Environmental Services.

Page 12 of 23


2016 Geotechnical Manual

In General studies required for detention ponds and wetlands are site specific. Therefore, it is
difficult to generalize requirements for investigation of such sites. For very preliminary studies,
the best sources are USDA/SCS soil survey publications.

3.6 GEOTECHNICAL SAMPLING REQUIREMENTS

For geotechnical analysis Shelby tube samples and split-spoon samples should be taken, depending on the
soil type. Generally, in sandy soils, split-spoon samples are preferred. In cohesive silty and clayey soils,
the Shelby tube samples are more reliable. Other relatively undisturbed sampling systems, may also be
used at the discretion of the MOGS, (Manager Office of Geotechnical Services). If these systems are used,
the wall thickness of the tubes should result in an area ratio (Ar) which does not exceed 30%.

The area ratio is defined as the ratio of the volume of soil displacement, to the volume of the collected
sample, and it is expressed as:

2 2
D 0 DI
Ar (%) 100
DI 2

Where: Ar = Area ratio


D0= Outside diameter of tube
DI = Inside diameter of cutting edge

An area ratio of 100% means that the in situ soil was displaced by a volume equal to that of the collected
sample. Well-designed tubes have an Ar less than 10%.

Page 13 of 23

2016 Geotechnical Manual

3.6.1 SPLIT SPOON SAMPLES



Generally, all borings requiring samples will be taken with a split-spoon sampler to obtain the data for
the Standard Penetration Test, or SPT. The samples are taken at 2.5 foot intervals for the upper 10 feet
and at 5 foot intervals thereafter unless otherwise specified or requested.

The sampler shall be the standard 2 inch O.D. and 1 inch I.D., driven with a 140 lb. hammer,
dropped 30 inch. The number of blows required of the hammer to drive the split spoon 1 feet, in
6 inch intervals, shall be recorded. The penetration resistance, called the N-value, shall be defined in
AASHTO T-206 Standards and shall be the total of the last two intervals, or 1 foot of the 1 feet
drive.

Two jar samples, each approximately 6 inches long shall be obtained from each split spoon sample for
laboratory examination and/or testing. When required for subgrade or peat investigation, a full 18SPT
sample shall be taken and stored in jars. Sample would be designated as top, middle, and bottom.
Keeping the samples as intact as possible, they are to be seated in clean glass jars to prevent loss of
moisture, properly marked with the project number, boring number, sample number, blow count
and field identification number. As soon as possible after drilling, the samples should be delivered
to the laboratory for tests.

3.6.2 SHELBY TUBES



Undisturbed samples, if required by the engineer, shall be obtained by pressing a thin-walled tube into
the soil with a slow, continuous push. The Shelby Tube shall measure 2 to 3 inches O.D. and the
length shall be as recommended in Table 1 of AASHTO T-207 or longer to avoid overfilling of the
tube during sampling. The standard lengths for INDOT are: 30 to 36 inches. A recovery of 50% or
greater is required unless otherwise approved by the Manager, Office of Geotechnical Services.
Immediately upon retrieval, the tubes are to be trimmed and cleaned of excess soil on the ends, sealed
with approved air-tight expanders and/or sealing wax on both ends. A suitable filler shall be added to the
void at the top of the Shelby Tube to prevent movement of the sample within the tube. Both ends shall
be covered with plastic caps, then tape should be applied in such a manner as to seal the open bolt
holes and the lip of the cap. Samples shall be kept in a vertical position with the top up during
transporting and storage. Samples shall not be jarred or shaken, and shall always be protected from
temperature extremes, especially freezing. Each tube shall be properly tagged inside and out with all
the pertinent information; project and designation number, road, boring, station and offset, line,
depths, recovery percentage and date. It shall be delivered promptly to the laboratory for testing.

3.6.3 ROCK CORES



This involves using a drill rig to core through hard rock, which cannot be augured through. Core
barrels, double or triple-tucked, with diamond core bits, of "NX", "NWG", or "NWPAM" (2 inch)
sizes are suggested to obtain an approximate core size of 2 inches. The core barrel shall be 5 feet long
with an inside diameter of 2 inches to obtain the minimum size core, unless otherwise approved by the
MOGS. Longer barrels can be used, but the maximum allowable run is 5 feet. Wire-line coring shall
only be permitted in special cases and should be preapproved by the MOGS.

If shale or any other non-durable sedimentary rocks are encountered, the core samples shall be wrapped
tightly in a moisture-proof wrapping such as aluminum foil or plastic wrap to prevent drying of samples.
Cores shall be measured to determine % recovery and RQD and placed in core boxes with labels

Page 14 of 23

2016 Geotechnical Manual

Indicating top, bottom and depths. The core box shall be labeled with Des #, Station, line, offset,
Boring #, Depths of coring, RQD and % recovery.

3.6.4 BAG SAMPLES

3.6.4.1 RESILIENT MODULUS (MR)



Bag samples for Resilient Modulus (MR) testing shall be obtained for each project, usually from the
most predominant and critical soil found during the drilling. In addition to the bag sample a 24 inch
long Shelby Tube sample shall also be collected for each MR test to be performed. When
Rubblization, Full Depth Reclamation or other rehabilitation technique is recommended a minimum
of one MR bag sample shall be obtained for every 10 borings performed or one per mile if boring
spacing is greater than 600 feet. The sample shall consist of soil collected from auger cuttings taken
below the pavement and sub-base material. The sampling procedure shall be as described below:

A continuous flight auger shall be used to penetrate the existing pavement and pavement sub-base
material to a depth approximately 4-6 inches below the top of the subgrade
The flight auger shall then be extracted from the borehole
The borehole shall be inspected and cleaned to insure no sub-base material will interfere with or
contaminate sampling
A 24 inch long Shelby Tube sample shall be collected from the borehole
Upon completion of the Shelby Tube sampling the flight auger shall be reintroduced to the
borehole and advanced to a depth of approximately 4-5 feet
Approximately 25 pounds of auger cuttings shall be collected for the bag sample, care shall be
taken so that aggregate base material does not contaminate soil cuttings

An Unconfined Compression test shall be performed at 1% strain rate on two evenly spaced samples
among those 10 borings. The results of Unconfined Compression tests performed at 1% strain relate
well with MR at 95 % compaction. If the results of grain size and sieve analyses indicate that there is
little variability in the soils within the project the number of MR tests may be reduced.

For projects where Widening or New Alignment is proposed sampling frequency shall be as noted
above. Samples shall be collected as described below:

A continuous flight auger shall be used to penetrate topsoil to a depth of approximately 1.5 feet
The flight auger shall then be extracted from the borehole
A 24 inch long Shelby Tube sample shall be collected from the borehole
Upon completion of the Shelby Tube sampling the flight auger shall be reintroduced to the
borehole and advanced to a depth of approximately 4-5 feet
Approximately 25 pounds of auger cuttings shall be collected for the bag sample

Two (2) jar samples shall be included with each bag sample to be tested for in-situ moisture. All bags
shall be properly tagged, inside and out, with tags showing the project number, road, sample
number, station and offset, date, and field identification number and delivered to the lab in a timely
manner. Soil classification tests are also assigned for each MR bag sample/ unconfined test at 1 %
strain.

Page 15 of 23

2016 Geotechnical Manual

3.6.4.2 MOISTURE AND DENSITY TEST



A small bag sample, 24 lbs (11.0kg), is required for all cohesive soil types found during a subgrade
investigation. The sample shall be taken from directly under the pavement/subbase strata, from
the auger cuttings. A jar sample for moisture testing is not necessary if a split spoon sample was
taken.

All bags should be properly tagged on the outside as with the normal size MR bag sample and
delivered to the lab in a timely manner.

3.6.4.3 SUBGRADE SAMPLING

The horizontal and vertical variation in subsurface soil types, moisture, densities, strength, ground
water elevations and rock location should all be considered when performing subgrade investigations.
Pavement maintenance history, county soils map, GPR, and Falling Weight Deflectometer data are all
helpful in developing a thorough subgrade investigation. The purpose of a subgrade investigation is
to define the depth, thickness, and location of major soil and rock strata that may reduce the pavement
service life and to determine the need for any foundation improvement and strengthening that may be
required. The guidelines for drilling and sampling for subgrade investigation are as follows.

When the top of the subgrade soil is reached, split spoon samples shall be taken and logged. Borings
shall evaluate the upper approximate 4.5 feet of the proposed subgrade. Borings shall penetrate to a
depth that allows for three continuous split spoon samples to be collected below the pavement sub-
base. In the first split spoon sample if the N value is less than or equal to 10 blows, and the soil is
cohesive, a 24 inch long Shelby Tube sample shall be taken beside the split spoon sample
within the same pavement core hole. If a Shelby tube sample is required, it shall have a minimum
recovery of fifty percent. If this is not obtained from the first tube, a second tube will be required as
described previously depending on the soil encountered, so that a combined total of not less than
1 6 inches of undisturbed sample is obtained. If the N value is greater than 10 no Shelby tube
sample shall be required and the boring shall be extended to the bottom of the first split spoon depth
and the procedure repeated.

If the N value is less than six in either the second or third split spoon samples and the soil is cohesive
a Shelby tube sample is required at the corresponding depth. Again, a fifty-percent minimum
recovery is required. If the N value on the third split spoon is six or greater the boring is to be
terminated at this point.

The investigation program may include Dynamic Cone Penetration (DCP) and Cone Penetrometer
(CPT) testing. DCP and CPT test shall be performed in accordance with ITM 509 and ASTM D
5778. DCP tests shall be performed after removing pavement and sub-base material and blow counts
shall be recorded for each 6 inch increment. DCP tests shall penetrate to a depth of 5 feet. If rock or
hard strata are encountered, DCP test should be moved 2 feet away and restarted. CPT soundings
shall penetrate to a minimum depth of 10 feet.

Water level determination is prudent to roadway and other structure. Boring/sounding shall be drilled
and a 48 hour water level record shall be provided in geotechnical report. Frequency, depth and other
considerations shall be as described in Section 3.5.4.4. All the pavement rehabilitation projects
including overlay design, full depth reclamation (FDR), crack seat, break and seat and rubblization
shall have water level information.

Page 16 of 23

2016 Geotechnical Manual

3.6.4.4 TOPSOIL SAMPLING

Top soil is described as soil that facilitates grass growth and is defined in Section 629 of the Recurring
Special Provisions. Top soil consists of organic material, silt, sand, clay, gravel, and chemical
elements such as potassium and phosphorus. The top soil thickness shall also be determined during
the geotechnical investigation. Soils shall be sampled from the upper most strata of the
boring/sounding. Sampling and testing shall be performed within the proposed construction limits and
shall be representative of the surface soils within that area. Split spoon sampling shall be based on
AASHTO T 206 in borings. The entire off road borings shall have organic soils identification. If
drilling is not feasible bag samples shall be recovered and hand auger testing shall be completed in
accordance with AASHTO T 203. The bag sample shall be a minimum of 1.0 lbs (0.45 kg). Sampling
and testing shall be completed for all new road, bridge, box culverts, ditches, landslides, etc
projects which require a growth layer for grass germination. Engineering judgment shall be used to
determine the location of sampling unless specified below. Frequency shall be as follows:

Descriptions Testing Frequency

New Road / Reconstruction one test / 5 Acres

Bridge /Pipe Culvert one test / each quadrant

Samples shall be logged, placed in zip lock bags and labeled appropriately. Labels shall include
project ID (either Des number or Contract number), sample location and depth. Finally, topsoil
thickness shall be determined by either machine or hand auger sounding.

3.6.5 PITS

In areas such as gullies, ravines or in streambeds, where it is not feasible to place a drill rig and
information from a hand auger is inadequate, pits are dug to establish bedrock elevations and overburden
depths. Usually a series of 10 sq. foot pits, in an acceptable pattern as per the requirements of the
project, are dug by hand to confirm expected data. This method of data collection is limited to sites
where shallow bedrock is known or expected, usually within a 3 foot depth. G e n e r a l l y no samples
are taken although a representative bag or jar sample for grain size analysis and moisture tests may be
requested.

3.6.6 HAND AUGERS



Hand Augers are limited to soft cohesive soils and are preformed in areas where standard penetration
tests are not possible or necessary. They are used to obtain a profile of the existing strata, sometimes
with samples.

There are five types of hand augers; 1) the sample hand auger is a minimum of 1 inch diameter, 2)
the 1 inch retraction piston sampler, 3) a peat sampler, 4) hand guide power hand auger and 5) a 3 inch
diameter post hole type auger.

Hand augers shall not exceed 6 inch per increment of advancement, and are performed in accordance
with AASHTO T-203. If samples are obtained, they shall be placed in jars, sealed and labeled
appropriately.

Page 17 of 23

2016 Geotechnical Manual

3.6.7 PAVEMENT CORES/SUBBASE



Pavement cores shall be obtained from existing pavement when an analysis or test of the core is requested by
the Pavement Design Engineer. This core shall be 3 inches in diameter and 8 inches to 9 inches in
length and properly labeled.

If testing of the core is not required, then other methods of drilling through the pavement are acceptable. A
detailed log with full description of material type and thicknesses should be written for each pavement core.

Once the pavement core has been extracted, the boring shall be extended through the subbase to the
subgrade. Subbase material should be carefully logged; however no sample should be taken for testing
unless otherwise specified by the geotechnical engineer.

3.7 CONE PENETRATION TESTING (CPT)

The Cone Penetrometer Test consists of pushing an instrumented Penetrometer into the ground while
continuously recording sleeve friction, cone resistance and pore pressure in accordance with ASTM D 5778.
Shear wave velocities can also be measured at user defined depths. Cone penetration testing can be
performed in conjunction with SPT borings for all investigation types covered under Section 3.5 of this
document based on the engineering judgment of the geotechnical engineer and approval of the MOGS.

3.8 DYNAMIC CONE PENETROMETER (DCP)

This test shall be performed in accordance with ITM 509. DCP test of driving a steel rod with 60 steel cone at
one end into the soil by dropping a sliding hammer from a standard height (22.6 inches). The soils strength is
determined by counting blows for every six inches of penetration. The length of the bottom steel rods shall be
60 inches. Rods may be fabricated into different combinations of lengths for ease of use, however no length
shall be less than 24 inches. A disposable cone is highly recommended for easier extraction of the of the rods
at the completion of the test.

DCP strengths should be based on the following table:

Blows per 6 Consistency/Density

0 to 3 soft

4 to 6 medium stiff

7 to 12 stiff

Over 13 very stiff

3.9 GEOPHYSICS

Geophysical testing is becoming an increasingly important tool for geotechnical engineers and geologists in
the performance of subsurface investigations. There are multiple tests including Ground Penetrating Radar,
Soil Resistivity, and Seismic Reflection/Refraction which can be employed to aid subsurface profiling. The

Page 18 of 23

2016 Geotechnical Manual


appropriate test for the anticipated ground conditions and the intent of investigation should be determined on
a project by project basis.

3.10 PERFORMANCE OF FIELD WORK ON PRIVATE PROPERTY

3.10.1 ENTRY PERMISSION



When the State of Indianas employees and representatives must enter and work on private property,
they are required to follow Indiana Code 8-23-7-26-,27,28, which took effect on July 1st, 2008.

The usual information about the project and its impact on the property owner/tenant should start the
letter, along with an explanation of the type work, a timetable to expect entry and an estimate how
many days the work will take should be given, but a notice of survey (NOS) letter is required by law to
include the following:

1. Include both the occupant and the recorded owner of the property in the notification process.
2. A description of the aggrieved partys right to compensation for damages.
3. The procedure the aggrieved party must follow to obtain the compensation.
4. The name, address and telephone number of an individual or office where property owners may
direct questions about the investigation. (This would be the geotechnical consultants
information.)
5. The name, address and telephone number of an individual or office where property owners
questions about the rights and procedures for damage compensation may be directed. (This would
be the project areas INDOT District Office, to the attention of the districts Real Estate
Manager.)
6. A copy of the Indiana Code 8-23-7-26, 27, 28 should be included with the letter. This will assist
property owners with immediate answers to many of their questions.

After the field work is finished, Form IC-662 is to be immediately completed for crop damages.
(Property damages are handled by the district in a different manner and are not claimed on Form IC-
662.)
All Form IC-662 claims are to be promptly directed to the appropriate District Real Estate Manager
since a timetable of sixty (60) days for reimbursement of an agreed upon compensation is established in
the code.

3.10.2 CROP DAMAGE CLAIMS INCURRED ON PRIVATE PROPERTY



Crop damage claims are to e reported on Indiana Form IC 662. The forms should be filled out completely
and accurately, with a sketch (length and width) of the damaged crop areas, the location where the
damages occurred on the property in reference to a known point, and type crop planted. Acreage can be
easily converted once the square footage of damages is determined by using the following website:
http://www.metric-conversions.org/area/square-feet-to-acres.htm

After the forms are filled out, send immediately to the project locations District Real Estate Manager for
review and payment.

An example of a completed form as well as a blank IC 662 is in the Appendix.

It is also the sole responsibility of INDOT and the Consultant Geotechnical Engineer, acting as a
representative of the Indiana Department of Transportation or Local Public Agency, to compensate the
property owners for any damage incurred to their property because of the Geotechnical Investigation.
Page 19 of 23

2016 Geotechnical Manual


Damage compensation including crop damage should be handled as outlined in the aforementioned
Indiana Code, by completing Indiana form I. C. 662 as accurately as possible then transmitting the
information to the INDOT District Development office of the project area. Compensation of the damages

will be handled by the district personnel. If the property owner is not satisfied with the compensation as
determined by INDOT, the County Agricultural Agent will be asked to assist. (Appendix 3.1, I.C. 662.)
Compensation for the damages of local agency projects will be handled by the Design consultant and local
government.

3.11 EQUIPMENT

All drilling rigs which take split spoon samples shall be equipped with yearly calibrated automatic hammers.
Calibration records for each rigs hammer must be available for INDOT inspection upon request. Pile driving
analyzers are the method commonly used for calibration of SPT hammers. Catheads shall not be used for
sampling on INDOT projects.

Only approved equipment shall be mobilized to the project sites as determined by a pre-drilling field check. If it
is deemed necessary to change or add rigs during the process of drilling the project due to unforeseen
circumstances at the site, the mobilization of the additional rig must be approved by the Office of Geotechnical
Services prior to the move if additional payment for Mobilization is to be requested.

3.12 UTILITIES

Buried utilities must be located prior to the start of all geotechnical investigations. Most Indiana companies
subscribe to the Indiana 811 network at 1-800-382-5544. Companies which are not members, in most cases
municipal utilities, need to be contacted individually. Failure to contact these companies could result in injury or
death to geotechnical drill crew members and the public and/or a loss of utility services.

Before contacting the utility companies to locate their buried lines, it is helpful if all soil test boring locations
are marked in a distinctive manner (laths, flags, paint, etc.) in order to expedite the process. If the roadwork
involves extensive roadwork over several blocks or miles, it is recommended that a meeting be planned,
onsite, with the utilities locators so that no boring locations are missed. If a meeting is not feasible, maps of
the project with the soil test locations clearly marked (to be given to the locators) are an excellent alternative.

Overhead utilities, although in plain sight, are sometimes forgotten. Drilling crews with high mast rigs should
work within the guidelines established by the affected utilities and it is recommended that insulators or
boots be placed on the wires to protect the workers. If it is imperative that data be obtained from directly
under power lines, then an alternative to drilling with a high mast rig must be used such as a tripod, hand
auger, pit, etc. Consider all overhead lines to be alive and dangerous.

Older, urbanized areas can have abandoned utility lines or tanks, which could be encountered during drilling.
Getting information about these lines prior to drilling from the utilities and street departments could help
prevent anxious moments if one is accidentally hit. All utility hits should be treated as active lines, and
follow the safety guidelines set down for such an emergency, until the utility company can confirm the
abandoned line as such.

Page 20 of 23

2016 Geotechnical Manual

The American Right-of-Way Association has established color codes to surface mark buried utilities. These
color codes are in compliance with the Occupational Safety and Health Acts (OSHA) standards.

Table 3.1 Color Code Identification

Orange Telephone
Red Electric
Yellow Gas
Blue Water
Green Sanitary Sewer
White New Construction

INDOT commonly uses pink and/or white markers for locations where geotechnical drilling is to be done.

3.13 DRILLING SAFETY

3.13.1 TRAINING

Drilling safety begins with an introductory safety course for all new drillers, inspectors, engineers and
others who are in the field with the drill rig operators. The Drilling Safety Guide published by the
International Drilling Federation and the Drilling Safety film produced by Mobile Drill Co., and ATC
Associates are good examples of the industry safety guidelines.

3.13.2 PERSONAL SAFETY GEAR



Every person around the drilling operations is required to use personal protection equipment, which
includes, but is not necessarily limited to, a safety hardhat, safety shoes and hearing protection. Those
working in close proximity to the augers are required to have no loose-fitting clothing with straps,
drawstrings, belts, loose ends or otherwise which might become entangles in the rotating augers. Rings
and other types of jewelry should not be worn at any time and long, loose hair should be pulled back and
secured.

In cases where there is known contamination i.e., (chemical, biological and radioactive) and special
protection is required, it becomes the responsibility of each consultant to provide their drilling crew with
the appropriate equipment and clothing for the project.

3.13.3 SITE MAINTENANCE



The drilling supervisor is responsible for good housekeeping on the drill rig and around the drilling
site. There must be suitable storage for all tools, materials and supplies to avoid placing them in areas
where they cannot be safely handled or secured. Heavy rods, pipe, casings, augers, cables and other
drilling tools should be stored in an orderly fashion to prevent movement when not in use. Work areas
should be free of debris and obstructions and hazardous substances such as grease, oil or ice which
could cause surfaces to become slick and hazardous.

When leaving the testing site, it is everyones responsibility to make sure all holes have been backfilled
Page 21 of 23

2016 Geotechnical Manual


properly, dirt mounds scattered and sod replaced if necessary. All debris should be removed and the drill
site returned to the condition it that was in before drilling operations began. If possible, a follow-up
inspection to inspect and correct any settlement of the test holes should be done.

3.13.4 TRAFFIC CONTROL



This work shall consist of providing traffic control services in accordance with the INDOT Worksite
Traffic Control Manual, when traffic flow must be restricted in order to conduct drilling or coring
operations.

3.14 NATURAL AND MANMADE HAZARDS

3.14.1 RIVERS AND STREAMS



Drilling on a river requires a barge set-up if it is not possible to access through the existing bridge deck.
The drilling needs to be done at a time when flash floods are not likely and should never be done in flood
conditions. Drillers should be equipped with life vests or personal floatation devices while working on the
water and, because icy conditions could develop quickly, it is not advisable to work on a barge in the
winter cold.

3.14.2 UTILITY LINES



Always have buried utility lines located before drilling at the Indiana 811 number 1-800-382-5544.
See section 3.11 for more information.

3.14.3 TOXIC OR HAZARDOUS AREAS



Most projects have an environmental assessment prior to any geotechnical survey which identifies
hazardous areas. If a site previously thought to be clean is found to be hazardous, then the INDOT
Office of Environmental Services should be immediately notified and all drilling operations ceased
until guidance from the regulatory agency has been provided.

3.14.4 NATURAL GAS POCKETS



In Indiana, naturally occurring gas pockets have been opened up several times by standard
geotechnical drilling methods over the years. Due to the volatility of the trapped gas, which
can escape at high pressures, immediate action must be taken to make the situation as safe as
possible for all involved at the drill site as well as the public safety concerns.

Actions to be taken if a trapped natural gas pocket (not piped gas) is opened during drilling
operations:

1. Immediately shutdown of all equipment being used on order to prevent electrical sparks
from igniting the gas and all on-site workers move away from the equipment.
2. All traffic must be stopped and or rerouted away from the scene. Local emergency
personnel should be contacted about the situation.
3. Contact the Indiana Department of Natural Resources Division of Oil and Gas Assistant
Director (office: 317-232-4055, directly: 317-232-6961) and IDNR will then contact their
field personnel about the situation and send someone to the site to assist.
Page 22 of 23

2016 Geotechnical Manual


4. As per directions from the IDNR personnel on site, observe the pressure and amount of
gas being expelled and determine when the situation is safe enough to close up and
abandon the hole.

Page 23 of 23