Conservancy Gowdown
Conservancy Gowdown
Rate/
Sl.No. Description Quantity Cum
1.40 cum @
7 Brick work with Fly Ash bricks of size 23cmx11cmx8cm
and crushing strength not less than 75 kg/cm2 in C.M.
(1:4) in superstructure including all charges.
1.27 cum
qty = 1.27 cum @
w-
Amount in
Rupees.
99.88 = 1262.08
409.52 = 24037.08
3788.99 = 78173.49
7175.50 = 4197.67
151.47
5661.10 = 3974.09 39.57
4005.23 = 5623.34
4038.56 = 5143.11
237.60 = 55051.92
101.30 = 4449.10
86.00 = 197483.52
78.59 = 3450.10
46.77 = 1870.80
92.43 = 13265.55
397981.86
2000.00
399981.86
or say 400000.00
Asst.Exe. Engineer
.M.C ,Sambalpur
ve approved
000.00only
dministrator,
C ,Sambalpur
Estimate for the work:- Constn of Guard room at Rajghat,SMC,Sambalpur
O.H.C & departmental profit.
All Dimensions are in MKS,Estimate is on out to out / in to in method
Rate/
Sl.No. Description Quantity Cum
n method
Amount in
Rupees.
86.86 = 918.94
398.51 = 1568.12
3396.60 = 10121.02
6583.51 = 4947.51
8658.99 = 6507.23
### = 489.75
8879.34 = 14577.66
26522.15
151.47
5828.90 = 12946.41 39.57
3533.67 = 19512.50
3567.00 = 20502.98
208.84 = 1484.85
91.35 = 3010.39
127.11 = 2406.76
131.06 = 896.45
75.00 = 25824.00
74.66 = 2460.05
42.84 = 1215.80
83.55 = 570.65
129961.07
L.S 10000.00
139961.07
or say 140000.00
Asst.Exe. Engineer
S.M.C ,Sambalpur
dministrator,
M.C ,Sambalpur
RATE ANALYSIS WITH OUT DEPARTMENTAL PROFIT
SL No. Qnty Unit Rate Amount in R
1 3 4 5
1 Supplying all labour, T&P and earth work in excavation in Hard Soil or Gravelly Soil with in 50 m. initial lead & 1.50m. initial lift including
Rough dressing, breaking clods, & laying in layers not exceeding 0.30m in depth, leveling the bed & including sundries , supervision
charges, contractor profit & labour cess etc & as per the direction of Engineer- in-charge.
a) Materials
Sand ffor filling 100 cum @ 48.00 4800.00
4800.00 4800.00
a) Labour charges
i) Man Mulia (Unskilled) 12.36 nos @ 200.00 2472.00
2472.00 2472.00
7272.00
Cost of 100 cum 7272.00
Cost for 1 cum = 7272.00 / 100 cum 72.72
C) Lead & Royalty of Sand 321.84 321.84
Total (A+B+C) 394.56
Add 1 % Labour Cess 3.95
398.51
3 Supplying all materials, labour, T&P and providing cement concrete(1:4:8) with 40cm size hand broken black
hard granite metal including watering , curing, conveyance of all materials to work site, payment of royalty
taxes,contractor profit & labour cess etc. all complete as per specification and direction of Engineer-in-charge.
a) Materials
Metal 0.96 cum @ 634.00 608.64
Sand 0.48 cum @ 55.00 26.40
Cement 1.72 qntl @ 658.00 1131.76
1766.80 1766.80
b) Labour
Mason 2nd class 0.18 nos @ 240.00 43.20
Man Mulia (Un-skilled) 1.80 nos @ 200.00 360.00
Women Mulia(Un-skilled) 1.40 nos @ 200.00 280.00
Man Mulia for mixing stone,
sand and cement and getting
Water 0.70 nos @ 200.00 140.00
823.20 823.20
2590.00
c) Lead & Royalty
Metal 0.96 cum @ 512.78 492.27
Sand 0.48 cum @ 524.24 251.64
Cement 1.72 qntl @ 16.90 29.07
772.97 772.97
3362.97
Add Labour Cess 1% 33.63
Say 3396.60
4 Supplying all labour, materials ,T&P and providing Cement concrete (1:1:3) with crusher broken hard granite
chips of 12mm size for RCC works including cost of conveyance & royalty ,sundries , watering ,curing &lifting
&laying concrete at a height of 5mtr contractor profit & labour cess. Maximum complete etc. all
complete(Excluding cost of reinforcement & centering & shuttering)
a) Materials
Crusher broken Chips 12mm siz 0.90 Cum @ 1168.00 1051.20
Sand 0.45 Cum @ 55.00 24.75
Cement 4.29 Qntl @ 658.00 2822.82
3898.77 3898.77
b) Labour
Mason 2nd class 0.18 nos Each 240.00 43.20
Man Mulia (Un-skilled) 1.80 nos Each 200.00 360.00
Women Mulia(Un-skilled) 1.40 nos Each 200.00 280.00
5 Supplying all materials, labour, T&P and providing M.S. reinforcement for R.C.C. work including cutting,
bending, binding and laying the grill and position including cost of binding wire 18 to 20 gauge, conveyance of
all materials to Work site, payment of royalty taxes, contractor profit & labour cess etc. all complete as per
specification and direction of Engineer-in-charge(SAIL STEEL TMT-EQR 500/IS 1786 Fe 500 D)
Unit -1M.T
Taking output = 1M.T.
a) Materials
Hysd bar including 5 percent
overlaps(SAIL STEEL TMT-EQR
500/IS 1786 Fe 500 D) and
wastage 1.05 MT MT 51880.00 54474.00
Binding Wire 8 Kg Kg 73.00 584.00
55058.00 55058.00
b) Labour
Labour for cutting, bending, shifting to Site, tying and placing in position
Mate 0.44 nos Each 220.00 96.80
Blacksmith ( Spl) 3 nos Each 260.00 780.00
Man Mulia (U/S) 8 nos Each 200.00 1600.00
2476.80 2476.80
57534.80
COST OF CARRIAGE
Rod (5 km.) 1.05 MT MT 169.00 177.45
For M.T. 177.45 177.45
57712.25
Add Labour Cess 1% 577.12
Per M.T. 58289.37
Rate for Per Qntl 58289.37 / 10 5828.94 Say 5828.90
6 Supplying all materials, labour, T&P and providing Brick work with flyash Bricks 23cm x 11cm x 8cm size having
crushing strength not Less than 75kg/cm with dimensional tolerance 8 percent in Cement mortar in Cement
Mortar (1:6 ) foundation & Plinth including cost of conveyance & royalty ,sundries & watering for curing &
supervision charges,contractor profit & labour cess etc. all complete as per the direction of Engineer-in-charge .
(Data for per cum)
a) Labour Cost
Mason (Spl) 0.35 nos Each 260.00 91.00
Mason (2nd class) 1.05 nos Each 240.00 252.00
Man mulia(U/S) 1.41 nos Each 200.00 282.00
Women Mulia (U/S) 1.41 nos Each 200.00 282.00
Preparing mortar and getting
water 0.14 nos Each 200.00 28.00
935.00 935.00
K.B. Bricks 23cm x 11cm x 8cm
b) Materials
size having crushing strength
not Less than 75kg/cm with
dimensional tolerance 8
percent 400 nos 1000 nos 4300.00 1720.00
Sharp sand (screened and wash 0.28 cum cum 55.00 15.40
Cement-0.047 cum 0.672 qntl Qntl 658.00 442.18
2177.58 2177.58
3112.58
Lead & Royalty
2 For Superstructure
Rate same as Foundation & Pilnth 3498.69
For superstructre 33.00
3531.69
Add Labour Cess 1% 35.32
3567.00 Cum
6 Supplying all labour,T&P, materials and making 2.5 cm artificial stone flooring with cement concrete (1:2:4)
including punning using 12mm size crusher broken granites chips. including cost of conveyance & royalty
,sundries & watering for curing & supervision charges, contractor profit & labour cess etc. all complete as per
the direction of Engineer-in-charge.
(Data for per sqm)
a) Materials
Crusher broken granites chips 1 0.023 cum Cum 1168.00 26.86
Sand (Screened and washed) 0.012 cum Cum 55.00 0.66
Cement- ( 0.006 cum) or 0.0858 qntl Qntl 658.00 56.46
83.98 83.98
b) Labour charges
7 Supplying all labour,T&P, materials and making 12mm thick cement plaster in cement mortar(1:6) for brick work
including Cost of conveyance, sundries, watering for curing, racking out joints, rounding of corners ,scaffolding
& labour cess etc, all complete as per the direction of Engineer-in-charge.
Per 1 sqm
a) Materials
Sand (Screened & washed) 0.015 cum cum 55.00 0.83
Cement 0.0025 cum or 0.0358 qntl Qntl 658.00 23.56
24.38 24.38
b) Labour charges
Mason (2nd class) 0.14 nos Each 240.00 33.60
Man Mulia(U/S)
Women 0.05 nos Each 200.00 10.00
Mulia(U/S) 0.05 nos Each 200.00 10.00
Man Mulia (U/S)for mixing sand 0.02 nos Each 200.00 4.00
57.60 57.60
81.98
Sand
Add Lead & Royalty
(Screened
& washed) 0.015 cum cum 524.24 7.86
Cement 0.0358 qntl Qntl 16.90 0.61
8.47 8.47
90.45
Add Labour Cess 1% 0.90
91.35
8 Supplying all labour,T&P, materials and making 16mm thick cement plaster in cement mortar(1:6) for brick or
stone masonry work including Cost of conveyance, sundries, watering for curing, racking out joints, rounding of
corners ,scaffolding ,contractor profit & labour cess etc, all complete as per the direction of Engineer-in-
charge.
Per 1 sqm
a) Materials
Sand (Screened & washed) 0.018 cum cum 55.00 0.99
Cement 0.003 cum or 0.043 qntl Qntl 658.00 28.29
29.28 29.28
b) Labour charges
Mason (2nd class) 0.16 nos Each 240.00 38.40
Man Mulia(U/S)
Women 0.11 nos Each 200.00 22.00
Mulia(U/S) 0.11 nos Each 200.00 22.00
Man Mulia (U/S)for mixing sand 0.02 nos Each 200.00 4.00
86.40 86.40
Sand 115.68
Add Lead & Royalty
(Screened
& washed) 0.018 cum cum 524.24 9.44
Cement 0.043 qntl Qntl 16.90 0.73
10.16 10.16
125.85
Add Labour Cess 1% 1.26
127.11
9 Supplying all materials, labour, T&P and providing 6 mm thick cement plaster (1:4) to RCC surfaces finished
smooth including closed deep chiping and slury treatment including watering , curing conveyance of all
Materials , taxes , royalty etc all complete as per direction of Engineer in-charge
Per 1 sqm
a) Materials
Sand (Screened & washed) 0.0075 cum cum 55.00 0.41
Cement 0.003 cum or 0.0372 qntl Qntl 658.00 24.48
24.89 24.89
b) Labour charges
Mason (2nd class) 0.16 nos Each 240.00 38.40
Man Mulia(U/S) 0.11 nos Each 200.00 22.00
Women Mulia(U/S) 0.11 nos Each 200.00 22.00
Man Mulia (U/S)for mixing sand
and watering 0.02 nos Each 200.00 4.00
Labour for closed deep
chipping & cleaning 0.05 nos Each 200.00 10.00
96.40 96.40
Add Lead 121.29
& Royalty
Sand (Screened & washed) 0.015 cum cum 524.24 7.86
Cement 0.0358 qntl Qntl 16.90 0.61
8.47 8.47
129.76
Add Labour Cess 1% 1.30
131.06
10 Providing and fixing Iron Door/window Shutters with Angle Iron Frames including fixing of Hold Fasts, Aldrops,
Hinges etc. all complete including fixing with C.C. (1:2:4) complete.
Unit = Sft. Taking Output = 6'-5''x3'-0'' = 19.26 Sft
Frame Angle of size 35x35x6 mm 17.220
Shutter An 29'-8" = 9.04 Mtr @ 1.80 Kg/Mtr = 16.272
Flat of siz 33'-5" = 10.19 Mtr @ 0.78 Kg/Mtr = 7.948
Aldrop, Hinges, Handle etc. L.S. 4.000
G.P. Sheet 24 gauge(0.63 mm) 1.79 Sqm @ 4.27 Kg/Sqm 7.643
Total Weight of shutter 53.084
a) Cost of Angle, Flat etc. 45.440 kg @ Rs 48.42 /Kg Rs 2200.21
b) Cost of G.P. Sheet 7.643 kg @ Rs 52.60 /Kg Rs 402.04
Materials
Weather coat-2.50 kg for 10
sqm per sqm 0.25 Kg 0.25 Kg Kg 192.00 48.00 48.00
73.92
Add Labour cess 1% 0.74
74.66
12
Supplying all labour, T&P materials and two coat of Distempering with any approved shades including cost of
Conveyance, taxes of, brushes, sundries& labour cess all complete as per the direction of Engineer-in-charge.
Data for 10 sqm
cum
ed and rammed
fit & labour cess etc.
cum
/CUM
broken hard granite
g ,curing &lifting
c. all
Cum
Cum
Cum
Cum
ing cutting,
uge, conveyance of
omplete as per
/Qtl
CC surfaces finished
g conveyance of all
/Sqm
/Kg
/Kg
/Kg
/Kg
/Kg
/Kg
/Kg
es including cost of
of Engineer-in-
/Sqm
s including cost of
gineer-in-charge.
/Sqm
/Sqm
Detailed statement of L
Costn.of shed for Aahar outlet at Head quarter Hospital campus,Sambalpur.
Total= 2.86
ABSTRACT
Masson (special class) 2.86 Nos @
Masson (second class) 17.24 Nos @
Mate 0.09 Nos @
Man Mulia 41.58 Nos @
Women Man Mulia 25.52 Nos @
Painter (Special class) 3.28 Nos @
Black smith (Special class) 0.67 Nos @
led statement of Labours
s,Sambalpur.
0.49 Nos
Nos 17.24 Nos 0.09 Nos 41.58 Nos 25.52 Nos 3.28
2.58 Nos
0.67 Nos
Nos
plinthbend
0.75 cum 3.22 Qntl 0.34 cum 0.68 cum
chajja
0.04 cum 0.18 Qntl 0.02 cum 0.04 cum
lintel
0.75 cum 3.22 Qntl 0.34 cum 0.68 cum
roofslab
1.64 cum 7.04 Qntl 0.74 cum 1.48 cum
4 M.S reinforcement
2.22 qtl
5 B/W (1:6)
11.27 cum 7.57 Qntl 3.16 cum
6 A.S flooring
7.11 cum 0.61 Qntl 0.09 cum 0.16 cum
7 12 mm C.P (1:6)
32.95 Sqm 1.18 Qntl 0.49 cum
8 16 mm C.P (1;6)
18.93 Sqm 0.81 Qntl 0.34 cum
9 6 mm C.P (1;4)
6.84 Sqm 0.25 Qntl 0.05 cum
10 M.S door /window
344.32 Kg
11 Weather coats
32.95 Sqm
12 Destemper
28.38 Sqm
13 Eneamel paints
6.83 Sqm
ABSTRACT
Cement 29.23 Qtl @ Rs. 658.00 = 19232.62
Sand(filling) 3.93 Cum @ Rs. 48.00 = 188.64
Sand 6.99 Cum @ Rs. 55.00 = 384.54
Metal 2.86 Cum @ Rs. 634.00 = 1813.60
Chips 3.03 Cum @ Rs. 1168.00 = 3541.11
Bricks 4507.94 Nos @ Rs. 4.30 = 19384.13
Rod 0.51 Qtl @ Rs. 5188.00 = 2648.99
door window 344.32 Kg @ Rs. 75.00 = 25824.00
Weathercoats 8.2375 Kg @ Rs. 192.00 = 1581.60
Destemper 7.095 Kg @ Rs. 66 = 468.27
Eneamel paints 0.85375 Ltr @ Rs. 193 = 164.77
75232.28
94577.14
7.515 sqm
0.7851 sqm
10.521 sqm
16.418 sqm
0.5106 Qtl kg
4507.937 nos
344.32 Qtl
8.2375 Kg
7.095 kg
0.85375 ltr
4507.937 nos 0.5106 nos 0 nos 344.32 nos 8.2375 nos 7.095 nos 0.85375 nos