L2 Schedule For Dinhata 132Kv Gis Substation Under Wbsetcl (Package - 38)

This document outlines the schedule for the 132kV GIS substation project in Dinhata, West Bengal, India. Key milestones include receiving the Letter of Award in July 2016, obtaining site clearance by October 2016, and supplying two 50MVA transformers by September and October 2017. The overall project is scheduled to be completed by April 2018 and involves engineering, procurement, construction, testing, and commissioning phases over 589 days.

Uploaded by

Rashmita Sahu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
737 views1 page

L2 Schedule For Dinhata 132Kv Gis Substation Under Wbsetcl (Package - 38)

This document outlines the schedule for the 132kV GIS substation project in Dinhata, West Bengal, India. Key milestones include receiving the Letter of Award in July 2016, obtaining site clearance by October 2016, and supplying two 50MVA transformers by September and October 2017. The overall project is scheduled to be completed by April 2018 and involves engineering, procurement, construction, testing, and commissioning phases over 589 days.

Uploaded by

Rashmita Sahu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

L2 SCHEDULE FOR DINHATA 132kV GIS SUBSTATION 16-08-2016

UNDER WBSETCL (PACKAGE - 38)


ID Task Name Duration Start Finish Predecessors 2017 2018
Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
1 WBSETCL DINHATA- GIS 603 days 22-07-16 05-04-18

2 MILESTONES 583 days 22-07-16 16-03-18

3 Customer Milestone 447 days 22-07-16 30-10-17

4 LOA 0 days 22-07-16 22-07-16 22-07

5 Cleaarance for LUP 90 days 22-07-16 26-10-16 4

6 Drawing & Details of 50MVA Transformer 0 days 10-04-17 10-04-17 122 10-04

7 Supply of 50MVA Transformer-1 0 days 30-09-17 30-09-17 484 30-09

8 Supply of 50MVA Transformer-2 0 days 30-10-17 30-10-17 488 30-10

9 S&W Milestone 569 days 05-08-16 16-03-18

10 SUBSTATION MILESTONE 569 days 05-08-16 16-03-18

11 Civil Engineering Milestone 349 days 30-09-16 26-09-17

28 Electrical Engineering Milestone 340 days 05-08-16 22-07-17

37 Supply Milestone 449 days 05-08-16 15-11-17

53 Civil Erection Milestone 525 days 05-08-16 31-01-18

70 Electrical Erection Milestone 569 days 05-08-16 16-03-18

91 SUBSTATION WORK 589 days 05-08-16 05-04-18

92 ENGINEERING 393 days 18-08-16 26-09-17


216 PROCUREMENT 474 days 05-08-16 10-12-17
423 CONSTRUCTION 521 days 09-08-16 31-01-18

510 TESTING & COMMISSIONING 78 days 18-01-18 05-04-18

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Dinhata Schedule Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress