Mizoram Tender 2016-11-18

Download as pdf or txt
Download as pdf or txt
You are on page 1of 212

Public Work Department

Government of Mizoram

Consultancy Services for


Feasibility Study and preparation of DPR for
Aizawl By-Pass on NH-54.

REQUEST FOR PROPOSAL (RFP)

October, 2016

Under Ministry of Road Transport & Highways


Government of India

1
INDEX
Sl. No. Content Page No.
1 Notice Inviting Tender (NIT) 3
2 Letter of Invitation 4-18
3 Annex -I : List of Projects along with Package Nos. 19
4 Annex-II : Procedure of Assessment of Least Cost to Chief
Engineer> 20-25
Engineer, Highways, Mizoram PWD under special circumstances

5 Data Sheet 26-36


6 Appendix - I : Terms of Reference 37-85
7 Supplement -I: Additional Requirements for Hill Roads 86-90
8 Supplement - II: Additional Requirements for Bridges 91-93
9 Supplement III : Additional requirement for safety audit 94-98
10 Enclosure - I : Manning Schedule 99
11 Enclosure - II : Qualification Requirements of Key Personnel 100-107
12 Enclosure - III: Schedule for Submission of Reports and Documents 108-109
13 Appendix II : Formats for Eligibility 110-115
14 Appendix - III : Formats for Technical Proposals 116-129
15 Appendix - IV: Formats for Financial Proposals 130-139
16 Appendix - V: Detailed Evaluation Criteria 140-158
17 Appendix - VI: Draft Contract Agreement 159-203

2
Public Works Department
Government of Mizoram
NOTICE INVITING TENDER (NIT)
Dt. 21.10.2016
E-Procurement NIT NO.2/RFP/CE_HW/2016_2017

1. Chief Engineer, Highways, Mizoram PWD has been assigned the work of Feasibility
Study and preparation of DPR for National Highways within Mizoram. The details of roads
are as follows:

Sl. NH Name of Work Bid security Period of Category of


No. No. (in `) assignment Consultant
1. 54 Feasibility study and preparation of 1,00,000/- 5 months Category
DPR for Aizawl by-pass on NH-54. I(A) & I(B)
(35.00Km)
2. 54 Feasibility study and preparation of 1,00,000/- 4 months Category IV
DPR for Restoration of continuous
Landslide at 176/500 Km and Sinking
Area at 179/500 on NH-54 in the State
of Mizoram.
3. 154 Feasibility study and preparation of 50,000/- 5 months Category
DPR for Bairabi bypass on NH-154. I(A) & I(B)
(7.00Km)
4. 54 Feasibility Study and Preparation of 2,00,000/- 6 months Category
DPR for 2-Laning with paved shoulder I(B)
of NH-54 for a stretch of km 40/00 to
118/00 and 147/00 to 170/00.
(101.00Km)
5. 150 Feasibility Study and Preparation of 2,00,000/- 6 months Category
DPR for 2-Laning with paved shoulder I(B)
of NH-150 of stretches from km 0/00 to
42/80 and from km 60/00 to 140/00.
(122.80Km.)
6. 102B Feasibility Study and Preparation of 2,00,000/- 6 months Category
DPR for 2-Laning with paved shoulder I(B)
of NH-102B within Mizoram. (100.00
Km)
7. 306A Feasibility Study and Preparation of 2,00,000/- 6 months Category
DPR for 2-Laning with paved shoulder I(B)
of NH-306A within Mizoram.
(100.00Km)

2. Proposals are hereby invited from eligible MoRT&H Empanelled Consultants, for
Feasibility Study and preparation of Detailed Project Report (DPR) for 2-lanning of various
National Highways within the State of Mizoram. (as per Annexure I).The Letter of Invitation
(LOI) and Terms of Reference (ToR) including Request for Proposal (RFP) is available online
on e-tender portal of MORT&H https://morth.eproc.in. Cost of the Document in the form of a
Non- refundable document fee of Rs.5,000 (Rupees Five Thousand only) in the form of
Demand Draft/ Bankers Cheque, in favour of Chief Engineer, Highways, Mizoram PWD and
payable at Aizawl, Mizoram must be furnished in a separate envelop while submitting the
proposal.

3
3. The RFP has been uploaded on (https://morth.eproc.in). As such before submitting the
proposal the Consultant shall mandatorily register and enlist themselves (the firm and all key
personnel), on the MoRTH portal https://morth.eproc.in and furnish registration details along
with its RFP. A copy of https://morth.eproc.in Operation Procedure is also enclosed for
bidders reference.

4. Bids must be accompanied by Scanned copies of Demand Draft of specified above for
cost of Bid and Rs.12,95.00 towards application processing fee (non-refundable) shall be paid to
M/s C1 India Pvt. Ltd against Tender Processing Fee through E-Payment gateway using Credit
Card/ Debit Card- Master Card and Visa Card only or net banking. In case of non submission of
the cost of bid and additional cost for processing fees of specified amount within the specified
time, the tenders shall be treated as invalid.

5. For any clarification with respect to online bidding process, the prospective bidders may
contact E-Tendering Cell and Help Desk Support on 0120-4746889 or Mr. Partha Ghosh on
08811093299. Additionally the bidders can email their issues to helpdesk at
[email protected]. Helpdesk Nos. are open between 1000 Hrs to 1830 Hrs IST
(Monday to Friday (Exclusions: MoRTH HOLIDAYS), or Office of the Chief Engineers,
Highways, Mizoram PWD., Aizawl, Mizoram, E-mail- [email protected].

6. Bid must be submitted online at e-tender portal of MORT&H https://morth.eproc.in on or


before 1000 IST, 18th Nov. 2016.

7. The following schedule is to be followed for this assignment:


i) Deadline for downloading of bid: 15:00 IST, 17th Nov. 2016.
ii) Last date for submission of queries: 12:00 IST, 7th Nov. 2016.
iii)Pre bid meeting: 13:00 IST, 8th Nov. 2016.
iv) Deadline for Submission of bids: 10:00 IST, 18th Nov. 2016.
v) Opening of bids: 13:00 IST, 18th Nov. 2016.

Tel: 0389-2326205; Fax: 0389-2323347


E-mail: [email protected]
Sd/-
Chief Engineer, Highways,
Mizoram PWD,
Mizoram: Aizawl

Memo No.NH-12038/14/RFP/CE-HW/PWD/___ A: Dated Aizawl, the 21st Oct., 2016.


Copy to:
1. P.S. to the Chief Minister, Mizoram, Aizawl for favour of information.
2. The Director General & Spl. Secretary, MoRT&H, Gate No. 3, Ground Floor, Jeevan
Tara Building, 5-Parliament Street, New Delhi-110 001, Govt. of India for favour of
information and necessary action. (Kind Attention: Chief Engineer, NER).
3. The Principal Secretary to the Govt. of Mizoram, PWD., for favour of kind
information.
4. The Engineer-in-Chief, PWD., Mizoram for favour of kind information.
5. The Regional Officer, Guwahati-3 for favour of information and necessary action.
6. The Chief Engineer, PWD., Road/Building, Mizoram for information and necessary
action. (2 Copies of NIT, 1 for Notice Board).
7. The Regional Pay and Accounts Officer (NH), H.R.PATH, 6th bye lane (West), R.G.
Baruah Road, Guwahati-3 for information and necessary action for release of payment
against the advertisement.
4
8. The Director, I&PR for favour of information and necessary action. He is requested to
publish the Short Notice (enclosed 3 copies) in two local news paper one in English
and the other in Mizo once each on separate but consecutive dates on or before
1.11.2016. It is also requested kindly to publish the advertisement of the Press Notice
in 2(two) Regional News Papers (North East), one in English and the other in local
language on or before 1.11.2016. The advertisement shall be published once only. All
advertisement bills should be as per DAVP rates and send to the undersigned for
payment without fail. It is further requested to furnish a list of the Newspapers in which
the advertisements are published and direct the publisher to furnish a copy each of the
News Papers publishing the Press Notice to the undersigned immediately after
publication for office record. Copy of newspapers publishing the press notice should be
furnished to this office within 10(ten) days from the date of publication, failing which
their bills shall not be entertained. (enclo: 5(Five) spare copies of Short Notice).
9. The All Superintending Engineer under Chief Engineer, Highways, PWD Mizoram,
for information and necessary action. (2 Copies of NIT, 1 for Notice Board).
10. The All Executive Engineer under Chief Engineer, Highways, Mizoram PWD, for
information and necessary action. (2 Copies of NIT, 1 for Notice Board).
11. Office Notice Board.
12. Concern file/Office Copy.

Chief Engineer, Highways,


Mizoram PWD,
Mizoram, Aizawl.

5
Public Works Department: Government of Mizoram
ABBREVIATED NOTICE INVITING TENDER (NIT)

Chief Engineer, Highways, Mizoram PWD., invited RFP vide e-Procurement NIT
NO.2/RFP/CE_HW/2016_2017dt. 21.10.2016, from eligible MoRT&H Empanelled Consultants for
Feasibility Study and preparation of Detailed Project Report (DPR) for National Highways in the State
of Mizoram. The Letter of Invitation (LOI) and Terms of Reference (ToR) including Request for
Proposal (RFP) is available online on e-tender portal of MORT&H https://morth.eproc.in with the
following important dates:-
1. Period of downloading: 24th Oct. 2016 to 17th Nov. 2016 (15:00IST)
2. Submission of RFP: 18th Nov. 2016 (10:00IST).

For details interested parties are requested to visit the e-procurement portal of
https://morth.eproc.in.

Chief Engineer, Highways,


Mizoram PWD,
Mizoram, Aizawl.

6
Letter of Invitation (LOI)

No. NH-12038/14/RFP/CE-HW/PWD : Dated Aizawl the 21st October, 2016.

Dear Sir,

Sub: Consultancy Services for Feasibility Study and preparation of DPR for Aizawl By-Pass
on NH-54 within Mizoram. (as per Annexure I ).

1. Introduction

1.1 The Chief Engineer, Highways, Mizoram PWD has been entrusted with the assignment
o f Feasibility Study and preparation of DPR for Aizawl By-Pass on NH-54 within
Mizoram. (as per Annexure I).Chief Engineer, Highways now invites proposal from
Technical consultants for carrying out detailed project report as per details given in
Annexure-1.

1.2 A brief description of the assignment and its objectives are given in the Appendix-I,
Terms of Reference.

1.3 The Chief Engineer, Highways, Mizoram PWD invites Proposals (the Proposals)
through e-tender (on-line bid submission) for selection of Technical Consultant (the
Consultant) who shall prepare DPR. A Consultant with a Particular Team may
submit proposals for more than one package. However, a Consultant is not allowed to bid
for a package with more than one team. For the sake of clarity, it is mentioned that one
consultant cannot submit two proposals/ bids for the same package. A consultant (either as
sole or as in JV/Association) can be awarded only upto 2 packages. Consultants are hereby
invited to submit proposals in the manner as prescribed in the RFP. A Consultant with a
Particular Team may submit only one proof of eligibility (Part 1) and Technical
Proposal (Part II) for any number of packages applied for by them. However, the
packages for which a Consultant with a Particular Team applies should be clearly
mentioned. Financial proposal for each package are to be submitted separately. Financial
proposal are only to be submitted online and no hard copy of the financial proposal
should be submitted. The most preferred bidder (H-1) for each package would be
determined on the basis of Quality and Cost as mentioned in the RFP. Award of work to
a Consultant with a Particular Team either as sole or as in JV/Association shall be
limited to one package only. In case, a Consultant with a Particular Team turns out to
be the most preferred bidder (H-1) in more than one package, the package which is to be
awarded to this Consultant with a Particular Team shall be determined on the basis of
least cost to Chief Engineer, Highways, Mizoram PWD considering the financial quote
of H-1 bidder and H-2 bidder limited to those packages, which shall be worked out as per
the procedure given in the RFP. The consultants are hereby invited to submit proposals in
the manner prescribed in the RFP.

1.4 The consultants shall submit proposals either in sole capacity or in JV or in Association.
Joint Venture/Association shall not have more than two firms. Any entity which has been
barred by the Ministry of Road Transport and Highways (MORTH) or its implementing
agencies for the works of Expressways, National Highways, ISC and EI Works and the bar
subsists as on the date of application, would not be eligible to submit the bid, either
individually or as a member of a Joint Venture.

7
1.5 To obtain first hand information on the assignment and on the local conditions, the
consultants are encouraged to pay a visit to the client, local State PWDs and the
project site before submitting a proposal and attend a pre-proposal conference. They
must fully inform themselves of local and site conditions and take them into account
in preparing the proposal.

1.6 Financial Proposals will be opened only for the firms found to be eligible and
scoring qualifying marks in accordance with Para 5 hereof. The consultancy services
will be awarded to the highest ranking consultant on the basis of Quality and Cost.

1.7 Please note that (i) costs of preparing the proposal and of negotiating the contract,
including visits to the Client, etc., are not reimbursable as a direct cost of the assignment;
and (ii) Client is not bound to accept any of the proposals submitted and reserve the
right to reject any or all proposals without assigning any reasons.

1.8 The proposals must be properly signed as detailed below:

1.8.1 i. by the proprietor in case of a proprietary firm


ii. by the partner holding the Power of Attorney in case of a firm in partnership
(A certified copy of the Power of Attorney on a stamp paper of Rs. 100 and
duly notarized shall accompany the Proposal).
iii. by a duly authorized person holding the Power of Attorney in case of a
Limited Company or a corporation (A certified copy of the Power of Attorney on
a stamp paper of Rs. 100 and duly notarized shall accompany the proposal).
iv. by the authorized representative in case of Joint Venture.

1.8.2 In case a Joint Venture/Association of firms, the proposal shall be accompanied by a


certified copy of legally binding Memorandum of Understanding (MOU) on a
stamp paper of Rs.100, signed by all firms to the joint venture confirming the following
therein:
i. Date and place of signing
ii. Purpose of Joint Venture/Association (must include the details of contract
works for which the joint venture has been invited to bid)
iii. A clear and definite description of the proposed administrative arrangements
for the management and execution of the assignment. Name of Lead Firm and
other partner of JV should be clearly defined in the MOU
iv. Delineation of duties/ responsibilities and scope of work to be undertaken by
each firm along with resources committed by each partner of the JV/Association
for the proposed services
v. An undertaking that the JV firms are jointly and severally liable to the Employer
for the performance of the services
vi. The authorized representative of the joint venture/Association

The Association firm shall give a Letter of Association, MOU as in i) to vi above


except v, letter of Authorization, copies of GPA/SPA for the person signing the
documents and a certificate of incorporation.

1.8.3 In case of Joint venture, one of the firms which preferably have relatively
higher experience, will act as the lead firm representing the Joint Venture. The duties,
responsibilities and powers of such lead firm shall be specifically included in the
MOU/agreement. It is expected that the lead partner would be authorized to incur
liabilities and to receive instructions and payments for and on behalf of the Joint
8
Venture. Payment to be made to the JV can also be made to the account of the JV.
For a JV to be eligible for bidding, the experience of lead partner and other partner
should be as indicated in data sheet.

1.8.4 A firm can bid for a project either as a sole consultant or in the form of joint venture
with other consultant or in association with any other consultant. However, alternative
proposals i.e. one as sole or in JV with other consultant and another in association / JV
with any other consultant for the same package will be summarily rejected. In such
cases, all the involved proposals shall be rejected.

1.9 Pre-proposal conference shall be held on the date, time and venue given in Data Sheet.

1.10 Bid Security

1.10.1 The applicant shall furnish as part of its Proposal, a Bid Security of Rs.1,00,000 (
Rupees 0ne lakhs only) in the form of a Bank Guarantee issued by one of the
Nationalized/Scheduled Banks in India in favour of the Chief Engineer, Highways,
Mizoram PWD payable at Tuikhuahtlang, Aizawl, Mizoram (the Bid Security)
valid for a minimum period of 150 days (i.e.30 days beyond the validity of the
bid) from the last date of submission of proposals. This Bid Security is returnable
not later than 30 (thirty) days from the date of Opening of the Financial proposals
except in case of the two highest ranked Applicants. Bid Security of the Selected
Applicant and the Second ranked Team shall be returned, upon the Selected Applicant
signing the Agreement.

1.10.2 Any Bid not accompanied by the Bid Security of the required value and
minimum required validity shall be rejected by the Authority as non-responsive.

1.10.3 The Chief Engineer, Highways, Mizoram PWD shall not be liable to pay any interest
on the Bid Security and the same shall be interest free.

1.10.4 The Applicant, by submitting its Application pursuant to this RFP, shall be deemed
to have acknowledged that without prejudice to the Chief Engineer, Highways,
Mizoram PWD any other right or remedy hereunder or in law or otherwise, the Bid
Security shall be forfeited and appropriated by the Authority as the mutually agreed
pre-estimated compensation and damage payable to the Authority for, inter alia the
time, cost and effort of the Chief Engineer, Highways, Mizoram PWD in regard to
RFP including the consideration and evaluation of the Proposal under the
following conditions:
(a) If an Applicant withdraws its Proposal during the period of its validity
as specified in this RFP and as extended by the Applicant from time to time

(b) In the case of the Selected Applicant, if the Applicant fails to reconfirm
its commitments during negotiations as required vide Para 6

(c) In the case of a Selected Applicant, if the Applicant fails to sign the Agreement

2 Documents

2.1 To enable you to prepare a proposal, please find and use the attached documents
listed in the Data Sheet.
9
2.2 Consultants requiring a clarification of the documents must notify the Client, in
writing, by 12:00 IST, 7th Nov. 2016. Any request for clarification in writing or by
tele-fax/e-mail must be sent to the Clients address indicated in the Data Sheet. The
Client will upload replies to pre-bid queries on its website.

2.3 At any time before the submission of proposals, the Client may, for any reason,
whether at its own initiative or in response to a clarification requested by a
Consulting firm, modify the Documents by amendment or corrigendum. The
amendment will be uploaded on Chief Engineer, Highways, Mizoram PWD website.
The Client may at its discretion extend the deadline for the submission of
proposals and the same shall also be uploaded on Chief Engineer, Highways website.

3. Preparation of Proposal

The proposal must be prepared in three parts


viz., Part 1: Proof of eligibility
Part 2: Technical Proposal
Part 3: Financial Proposal

3.1 Document in support of proof of eligibility

3.1.1 The minimum essential requirement in respect of eligibility has been indicated in
the Data Sheet. The proposal found deficient in any respect of these requirements will
not be considered for further evaluation. The following documents must be furnished
in support of proof of eligibility as per Formats given in Appendix-II:

(i) Forwarding letter for Proof of Eligibility in the Form-E1.

(ii) Firms relevant experience and performance for the last 7 years:
Project sheets in support of relevant experience as per Form-E2/T3
supported by the experience certificates from clients in support of experience
as specified in data sheet for the project size preferably in terrain of similar
nature as that of proposed project shall be submitted. Certificate should indicate
clearly the firms Design/DPR experience, in 2/4-/6- laning of highway,
structures like bridges, Viaducts, tunnels, hill slope stabilization, rock bolting,
ground improvement, etc. Scope of services rendered by the firm should
be clearly indicated in the certificate obtained from the client. The
information given in Form E2/T3 shall also be considered as part of Technical
Proposal and shall be evaluated accordingly. The Consultants are therefore
advised to see carefully the evaluation criteria for Technical Proposal and
submit the Project Sheets accordingly.

(iii) Firms turnover for the last 3 years: A tabular statement as in Form E3
showing the turnover of the applicant firm(s) for the last three years beginning
with the last financial year certified by the Chartered Account along with
certified copies of the audit reports shall be submitted in support of the
turnover.

(iv) Document fee: The fee for the document amounting to Rs. 5,000 (Rupees
Five Thousand only) in the form of Demand Draft favoring Chief
Engineer, Highways, Mizoram PWD payable at Tuikhuahtlang, Aizawl,
Mizoram must be furnished in a separate envelope while submitting the proposal.
10
(v) Bid Security: Bank Guarantee in support of bid security for an amount
specified in Data Sheet and having validity for a minimum period of 150
days (i.e.30 days beyond the validity of the bid), from the last date of
submission of proposals in the Form E4.

(vi) Power of Attorney on a stamp paper of Rs.100 and duly notarized authorizing
to submit the proposal

(vii) In case a Joint Venture/Association of firms, the proposal shall be


accompanied by a certified copy of legally binding Memorandum of
Understanding (MOU) on a stamp paper of Rs.100, signed by all firms to the
joint venture/Association as detailed at para 1.8.2 above

3.1.2 The minimum essential requirement in respect of eligibility has been indicated in the
data sheet, the proposal found deficient in any respect of these requirements will not
be considered for further evaluation.

3.2 Technical Proposal

3.2.1 You are expected to examine all terms and instructions included in the
Documents.
Failure to provide all requested information will be at your own risk and may
result in rejection of your proposal.

3.2.2 During preparation of the technical proposal, you must give particular attention to
the following:

Total assignment period is as indicated in the enclosed TOR. A manning schedule in


respect of requirement of key personnel is also furnished in the TOR which shall be
the basis of the financial proposal. You shall make your own assessment of support
personnel both technical and administrative to undertake the assignment. Additional
support and administrative staff need to be provided for timely completion of the
project within the total estimated cost. It is stressed that the time period for the
assignment indicated in the TOR should be strictly adhered to.

3.2.3 The technical proposal shall be submitted strictly in the Formats given in Appendix-
III And shall comprise of following documents:

i) Forwarding letter for Technical proposal duly signed by the authorized


person on behalf of the bidder, as in Form-T-1

ii) Details of projects for which Technical and Financial Proposals have been
submitted by a Consultant with a particular Team as in Form-T-2

iii) Firms references - Relevant Services carried out in the last seven years as per
Form- E2/T-3. This information submitted as part of Proof of Eligibility shall be
evaluated and need not be submitted again as a part of the Technical proposal

iv) Site Appreciation: limited to four A4 size pages in 1.5 space and 12 font
including photographs, if any (Form-T-4).

11
v) Comments on Terms of Reference: limited to two A4 size pages in 1.5 space
and 12 font (Form-T-5).

vi) The composition of the proposed Team and Task Assignment to individual
personnel: Maximum three pages (Form-T-6).

vii) Proposed methodology for the execution of the services illustrated with bar charts
of activities, including any change proposed in the methodology of services
indicated in the TOR, and procedure for quality assurance: Maximum 4 pages
(Form-T-7)

viii) The proposal should clearly identify and mention the details of Material Testing
lab facilities to be used by the Consultants for the project (Form-T-8). In this
connection, the proposals of the Consultants to use in-house lab facilities up to a
distance of maximum 400 km from the project site being feasible would be
accepted. For all other cases suitable nearby material Testing Laboratory shall be
proposed before Contract Agreement is executed.

ix) The proposal shall indicate as to whether the firm is having the facilities for
carrying out the following field activities or these are proposed to be outsourced
to specialized agencies in the Form- T-9.

a) Pavement Investigation
b) Geo-technical Investigation

In case the consultant envisages outsourcing any or all of the above services to the
expert agencies, the details of the same indicating the arrangement made with the
agencies need to be furnished. These agencies would however, be subject to
approval of the client to ensure quality input by such agencies during technical
negotiation before award of the work. For out-sourced services, proposed
firms/consultants should have such experience on similar projects

x) Details of office equipment and software owned by the firm in Form-T10

xi) CVs of Key Personnel in Form-T11.

3.2.4 CVs of Key Persons:

i) The CVs of the key personnel in the format as per Form T-11 is to be furnished.
It may please be ensured that the format is strictly followed and the
information furnished therein is true and correct. The CV must indicate the work
in hand and the duration till which the person will be required to be engaged in
that assignment. Experience certificates shall also be submitted. If any information
is found incorrect, at any stage, action including termination and debarment from
future Chief Engineer, Highways, Mizoram PWD projects upto 2 years may be
taken by Chief Engineer, Highways, Mizoram PWD on the personnel and the Firm.

ii. No alternative to key personnel may be proposed and only one CV may be
submitted for each position. The minimum requirements of Qualification and
Experience of all key personnel are listed in Enclosure-II of TOR. CV of a person
who does not meet the minimum experience requirement as given at enclosure-II of
TOR shall be evaluated and the marks obtained shall be taken into consideration
12
during evaluation of Technical Proposal (except Team leader). However if a firm
with such key personnel is declared the most preferred bidder for a particular
package , such key personnel should be replaced at the time of Contract
Negotiations with a person meeting requirements of Qualification and
Experience as given at enclosure-II of TOR and whose CV secures 75 % marks and
above. If a proposed key personnel does not possess the minimum (essential)
educational qualification as given at enclosure-II of TOR, Zero marks shall be
assigned to such CV and such CV shall not be evaluated further. The CV of the
proposed Team Leader should score at least 75 % marks otherwise the entire
proposal shall be considered to have failed in the evaluation of Technical
Proposals and shall not be considered for opening of Financial Proposals.

iii. Team Leader, Highway cum Pavement Engineer, Bridge Engineer, Geo-
technical cum material engineer and Senior Survey Engineer should be available
from beginning of the project. 3 Key Personnel namely Environmental Specialist,
Quantity Surveyor / Documentation expert and Traffic and safety expert are
allowed to be deployed/proposed in 2 teams at a time. If same CV is submitted by
two or more firms, zero marks shall be given for such CV for all the firms.

iv. The availability of key personnel must be ensured for the duration of the
project as per proposed work programme. If a firm claims that a key personnel
proposed by them is a permanent employee of the firm ( the personnel should
have worked in the firm continuously for a period of at least 1 year) , a certificate
to the effect along with pay slips are required to be submitted.
v. The age limit for key personnel is 70years as on the date of bid submission except
for Senior survey engineer in which case the age limit is 65 years. The proof
of age and qualification of the key personnel must be furnished in the
technical proposal.
vi. An undertaking from the key personnel must be furnished that he/she will be
available for entire duration of the project assignment and will not engage
himself/herself in any other assignment during the currency of his/her assignment on
the project. After the award of work, in case of non-availability of key
personnel in spite of his/her declaration, he/she shall be debarred for a period of
two years for all projects of Chief Engineer, Highways

vii. Age limit for supporting staff to be deployed on project is 65 years as on the date of
bid submission.
viii. A good working knowledge of English Language is essential for key
professional staff on this assignment. Study reports must be in English Language.

ix. Photo, contact address and phone/mobile number of key personnel should be
furnished in the CV.
x. Availability of few key personnel engaged for preparation of Detailed Project
Report for the envisaged project may be ensured during first 3 to 4 months after
start of the civil work at site during the period of survey and review of DPR by the
Supervision consultant/Authority Engineer. For this purpose, payment shall be
made as per actual site deployment of the key personnel at the man month rates
quoted by the firm in their financial proposal.

13
xi. It may please be noted that in case the requirement of the Experience of the
firm/consortium as mentioned in the Proof of Eligibility is met by any foreign
company, their real involvement for the intended project shall be mandatory. This
can be achieved either by including certain man-months input of key experts
belonging to the parent foreign company, or by submitting at least the draft
feasibility report and draft DPR duly reviewed by the parent firm and their paying
visit to the site and interacting with Chief Engineer, Highways. In case of key
personnel proposed by the foreign company, they should be on its pay roll for at
least last six months (from the date of submission).

xii) In case a firm is proposing key personnel for educational/research institutions, No


Objection Certificate from the concerned institution should be enclosed with the
CV of the proposed key personnel committing his services for the instant project.

xiii) Original Curriculum Vitae (CV) and photocopies of certificates shall be recently
signed in blue ink by the proposed key professional staff on each page and also
initialed by an authorized official of the Firm and each page of the CV must be
signed. The key information shall be as per the format. Photocopy of the CVs will
not be accepted. Unsigned copies of CVs shall be rejected.

3.2.5 The technical proposal must not include any financial information.

3.3 Financial Proposal

3.3.1 The Financial proposal should include the costs associated with the assignment.
These shall normally cover: remuneration for staff (foreign and local, in the field,
office etc), accommodation, transportation, equipment, printing of documents, surveys,
geotechnical investigations etc. This cost should be broken down into foreign and local
costs. Your financial proposal should be prepared strictly using, the formats attached
in Appendix IV. Your financial proposal should clearly indicate the amount asked
for by you without any assumptions of conditions attached to such amounts.
Conditional offer or the proposal not furnished in the format attached in Appendix-IV
shall be considered non- responsive and is liable to be rejected.

3.3.2 The financial proposal shall take into account all types of the tax liabilities and cost
of insurance specified in the Data Sheet.

3.3.3 Costs shall be expressed in Indian Rupees in case of domestic as well as for
foreign Consultant. The payments shall be made in Indian Rupees by the Chief
Engineer, Highways and the Consultant themselves would be required to obtain
foreign currency to the extent quoted and accepted by Chief Engineer, Highways,
Mizoram PWD Rate for foreign exchange for payment shall be at the rate established
by RBI applicable at the time of making each payment installment on items
involving actual transaction in foreign currency. No compensation done to fluctuation
of currency exchange rate shall be made.

3.3.4 Consultants are required to charge only rental of equipments/ software(s) use so
as to economize in their financial bid.

4 Submission of Proposals

14
4.1 The Applicants shall submit the proposal (Proof of Eligibility and Technical
Proposal) in hard bound form with all pages numbered serially and by giving and index
of submissions. Applications submitted in other forms like spiral bound form; loose
form etc shall be rejected. Copies of Applications shall not be submitted and
considered. A Consultant with a Particular Team may submit only one hard copy
(in original) of proof of eligibility (Part 1) and Technical Proposal (Part II) to
Chief Engineer, Highways for all the packages applied by them with a particular
team on or before the deadline of submission of bids. A consultant can apply for a
particular package with only one team. The package for which a Consultant with a
Particular Team applies should be clearly mentioned in their proposal. However,
Consultants are required to submit a copy of Proof of Eligibility and Technical
Proposal online separately for each package. Financial proposal for each package are to
be submitted separately. Financial proposal are only to be submitted online and no
hard copy of the financial proposal should be submitted.

4.2 You must submit original proposal as indicated in the Data Sheet. Proof of
Eligibility in original and hard bound should be enclosed in an envelope which should
be marked as Part-IProof of Eligibility. Similarly, Technical Proposal in original
and hard bound should be enclosed in an envelope which should be marked as Part-
IITechnical Proposal. The proposal will be sealed in an outer envelope which will
bear the address and information indicated in the Data Sheet and shall be submitted to
Chief Engineer, Highways on or before the deadline for submission of bids. The
envelope must be clearly marked:

Consultancy Package Nos. ..


Project Name ..
Do not open, except in presence of the evaluation committee

4.2.1 This outer envelope will contain three separate envelopes. The first envelope
containing Proof of Eligibility (which should be clearly marked), the second
envelope containing Technical Proposal (which should be clearly marked) and the
third envelope containing a demand draft of Rs. 5,000/- (cost of RFP), Bid Security of
required amount and validity as mentioned in the RFP and Proof of Payment of
application processing fees amounting to Rs.1295/- to M/s. C-1 India Pvt. Ltd. Only one
bid security and one DD of Rs 5000/ (as cost of Document) may be submitted by a
consultant applying with a particular team for a number of packages. However for
consultants applying with 2 teams, 2 nos of Bid Security of Rs 1.00 lakhs each and 2
nos of DD of Rs 5000/ each as mentioned in RFP have to be submitted.

4.2.2 The proposal must be prepared in indelible ink and must be signed by the
authorized representative of the consultants. The letter of authorization must be
confirmed by a written power of attorney accompanying the proposals. All pages of
the Proof of Eligibility and Technical Proposal must be initialed by the person or
persons signing the proposal.

4.3 The proposal must contain no interlineations or overwriting except as necessary to


correct errors made by the Consultants themselves, in which cases such corrections
must be initialed by the person or persons signing the proposal.

4.4 Your completed Proof of eligibility and Technical proposal (in hard copy) must
be delivered on or before the time and date at the address stated in Data Sheet. Proof
of Eligibility, Technical Proposal and Financial Proposal for each package shall have
15
to be submitted online also on or before the time and date at the address stated in Data
Sheet

4.5 Your proposal must be valid for the number of days stated in the Data Sheet from
the closing date of submission of proposal.

5 Proposal Evaluation

5.1 The proposals would be evaluated by a Committee constituted by Chief Engineer,


Highways, Mizoram PWD. A three- stage procedure will be adopted in evaluating the
proposal. In the first stage- Proof of Eligibility, it will be examined as to whether:

i) The proposal is accompanied by Document fee


ii) The Proposal is accompanied by Bid Security of required value and of validity
equal or more than the minimum required validity.
iii) The firms(s) have required experience.
iv) The firms(s) have required turnover.
v) The documents are properly signed by the authorized signatories and whether
the proposal contains proper POA as mentioned at para 1.8.1 above.
vi) The proposals have been received on or before the dead line of submission.
vii) In case a Joint Venture/Association of firms, the proposal shall be accompanied
by a certified copy of legally binding Memorandum of Understanding (MOU) on
a stamp paper of Rs.100, signed by all firms to the joint venture/Association as
detailed at para 1.8.2 above.

In case answers to any of the above items is No the bid shall be declared as non-
responsive and shall not be evaluated further.

A Consultant satisfying the minimum Eligibility Criteria as mentioned in the Data


sheet and who had submitted the above mentioned documents shall be declared pass
in Proof of Eligibility and the Technical Proposals of only those consultants shall be
opened and evaluated further.

5.2 In the second stage the Technical proposal shall be evaluated as per the
detailed evaluation criteria given in Data Sheet.

A proposal securing 75 points shall be declared pass in the evaluation of Technical


Proposal. The technical proposal should score at least 75 points out of 100 to be
considered for financial evaluation. The CV of the proposed Team Leader
should score at least 75% marks otherwise the entire proposal shall be considered
to have failed in the evaluation of Technical Proposals and shall not be considered
for opening of Financial Proposals.

5.3 Evaluation of Financial Proposal

5.3.1 In case for a particular package, only one firm is eligible for opening of Financial
Proposals, the Financial Proposal shall not be opened, the bids for that package shall
be cancelled and Chief Engineer, Highways shall invite fresh bids for this package. For
16
financial evaluation, total cost of financial proposal excluding Service tax shall be
considered Service Tax shall be payable extra.

5.3.2 The evaluation committee will determine whether the financial proposals are complete
(i.e. whether they have included cost of all items of the corresponding proposals; if
not, then their cost will be considered as NIL but the consultant shall however be
required to carry out such obligations without any compensation. In case, if client feels
that the work cannot be carried out within overall cost of financial proposal, the
proposal can be rejected. The client shall correct any computational errors and correct
prices in various currencies to the single currency specified in Data Sheet. The
evaluation shall exclude those taxes, duties, fees, levies and other charges imposed
under the applicable law & applied to foreign components/ resident consultants.

5.3.3 For a package, the procedure as mentioned at Clauses 5.3.4, 5.4 and, 5.5 as mentioned
below shall be followed for determining the most preferred bidder (H-1 bidder) for
this package.

5.3.4 The lowest financial proposal (FM) will be given a financial score (SF) of 100 points.
The financial scores of other proposals will be computed as follows:
SF = 100xFM/F
(SF = Financial Score, FM= Amount of lowest bid, F= Amount of financial
proposal converted in the common currency)

5.4 Combined evaluation of Technical and Financial Proposals. Proposals will finally
be ranked according to their combined technical (ST) and Financial (SF) scores using
the weights indicated in the Data Sheet:

S= STxT + SFxf
Where,
S= Combined Score,
ST= Technical Score out of 100
SF= Financial Score out of 100
T and f are values of weightage for technical and financial proposals respectively
as given in the Data Sheet.

5.5 For a particular package, a Consultant with a particular Team having the
maximum Combined score (S) shall be declared as the most preferred bidder (H-1).

5.6 In case work has to be awarded for multiple packages, award of work to a Consultant
with a Particular Team either as sole or as in JV/Association shall be limited to one
package only. At first, Consultants who become H-1 in one package each shall be
assigned the respective package. Then packages in which a Consultant with a
Particular Team turns out to be the most preferred bidder (H-1) in more than one
package shall be considered. In case, a Consultant with a Particular Team turns out
to be the most preferred bidder (H-1) in more than one package, the package which is to
be awarded to this team of a consultant shall be determined on the basis of least cost to
Chief Engineer, Highways considering the Financial Quote of H-1 bidder and H-2
Bidder limited to those packages. Procedure to be followed for awarding work based
on QCBS including assessment of least cost to Chief Engineer, Highways under
17
special circumstances i.e. When a Consultant with a Particular Team turns out to be
the most preferred bidder (H-1) in more than one package is given at given at Annex-
II.

6 Negotiations

6.1 Prior to the expiration period of proposal validity, the Client will notify the
most preferred Consultant/Bidder i.e. the highest ranking consultant in writing by
registered letter, e-mail, or facsimile and invite him to negotiate the Contract.

6.2 Before the start of negotiations, the most preferred Consultant/Bidder (H-1) shall
be asked to give justification for the cost quoted by them to the full
satisfaction of Chief Engineer, Highways, Mizoram PWD. Each key personnel of the
preferred consultant shall be called for interview at the time of negotiation at the cost
of consultant before the award of work.

6.3 Negotiations normally take two to three days. The aim is to reach agreement on all
points and initial a draft contract by the conclusion of Negotiations.

6.4 Negotiations will commence with discussion on technical proposal, the proposed
methodology (work plan), staffing and any suggestions made to improve the TOR, the
staffing and bar charts, which will indicate activities, periods in the field and in the
home office, staff months, logistics and reporting. The financial proposal is subject to
rationalization. Special attention will be paid to optimize the required outputs from the
Consultants within the available budget and to define clearly the inputs required from
the Client to ensure satisfactory implementation of the Assignment.

6.5 Changes agreed upon will then be reflected in the financial proposal using proposed
unit rates.

6.6 Having selected Consultants, among other things, on the basis of an evaluation
of proposed key professional staff, the Client expects to negotiate, within the proposal
validity period, a contract on the basis of the staff named in the proposal and, prior to
contract negotiations, will require assurances that the staff will be actually available.
The Client may ask to give a replacement for the key professional who has scored
less than 75% marks by a person of at least 75% score. No reduction in
remuneration would be made on account of above change.

The Client will not consider substitutions during contract negotiations except in cases
of incapacity of key personnel for reasons of health. Similarly, after award of contract
the Client expects all of the proposed key personnel to be available during
implementation of the contract. The client will not consider substitutions during
contract negotiations/ contract implementation except under exceptional
circumstances. For the reason other than death/ extreme medical ground, where
replacement is proposed by the Consultant due to non availability of the originally
proposed key personnel or in cases where replacement has become necessary as a
key personnel proposed by the Consultant has been found to be unsuitable for the
project by Chief Engineer, Highways during contract negotiations/contract
implementation, the following shall apply (i) for total replacement upto 33% of key
personnel, remuneration shall be reduced by 5% (ii) for total replacement between
33% to 50%, remuneration shall be reduced by 10% (iii) for total replacement
beyond 50% and 66% remuneration shall be reduced by 15% (iv) for total

18
replacement beyond 66% of the total key personnel, the Client may initiate action for
debarment of such consultant for future projects of Chief Engineer, Highways for a
period of 6 months to 24 months. If for any reason beyond the reasonable control of
the consultants, it becomes necessary to replace any of the personnel, the
consultants shall forthwith provide as a replacement a person of equivalent or
better qualification and experience.

6.7 The negotiations will be concluded with a review of the draft Contract Agreement
attached at Appendix-V. The Client and the Consultants will finalize the contract
to conclude negotiations.
6.8 If a Consultant fails to conclude the negotiations with Chief Engineer, Highways,
Mizoram PWD or in case a consultant withdraws without starting / completing the
negotiations with Chief Engineer, Highways, Mizoram PWD it shall attract penalty
encashment of Bid Security submitted by the Consultant.

7 Performance Security

The consultant will furnish within 15 days of the issue of Letter of Acceptance (LOA),
an unconditional Bank Guarantee from a Nationalised Bank, IDBI or ICICI/ICICI
Bank/Foreign Bank/EXIM Bank/Any Scheduled Commercial Bank approved by
RBI having a net worth of not less than 500 crore as per latest Annual Report of the
Bank. In the case of a Foreign Bank (issued by a Branch in India) the net worth
in respect of Indian operations shall only be taken into account. In case of Foreign
Bank, the BG issued by Foreign Bank should be counter guaranteed by any
Nationalised Bank in India. In case of JV, the BG shall be furnished on behalf of the
JV or by the lead member of the JVs for an amount equivalent to 5 % of the total
contract value to be received by him towards Performance Security valid for a
period of three years beyond the date of completion of services, or end of civil
works contract, whichever earlier. The Bank Guarantee will be released by Chief
Engineer, Highways upon expiry of 3 years beyond the date of completion of
services, or end of civil works contract, whichever earlier, provided
rectification of errors if any, found during implementation of the contract for
civil work and satisfactory report by Chief Engineer, Highways in this regard is
issued. If a Consultant fails to submit the Performance Security (as specified above), it
shall attract penalty encashment of Bid Security submitted by the Consultant.

8. Penalty

The consultant will indemnify for any direct loss or damage that accrue due to
deficiency in services in carrying out Detailed Project Report. Penalty shall be
imposed on the consultants for poor performance/deficiency in service as expected
from the consultant and as stated in General Conditions of Contract.

9. Award of Contract
After successful Negotiations with the selected Consultant the Client shall issue letter
of award and ask the Consultant to provide Performance Security as in Para 7 above.
If negotiations (as per para 6 above) fail or the selected Consultant fail to provide
performance security within the prescribed time or the Consultant fail to sign
nd
the Contract Agreement within prescribed time the Client may invite the 2 highest

19
ranking bidder Consultant for Contract negotiations and follow the procedure outlined
in Para 6, 9 and 10 of this Letter of Invitation.

10. Signing of Contract Agreement


After having received the performance security and verified it, the Client shall invite
the selected bidder for signing of Contract Agreement on a date and time convenient
to both parties within 15 days of receipt of valid Performance Security.

11. The Client shall keep the bidders informed during the entire bidding process
and shall host the following information on its website:
i) Notice Inviting Tender (NIT)
ii) Request For Proposal (RFP)
iii) Replies to pre-bid queries, if any
iv) Amendments / corrigendum to RFP
v) List of bidders who submitted the bids up to the deadline of submission
vi) List of bidders who did not pass the eligibility requirements, stating
the broad deficiencies
vii) List of bidders who did not pass the Technical Evaluation stating the reasons.
viii) List of bidders along with the technical score, who qualified for opening the
financial bid
ix) Final Score of qualified bidders
x) Name of the bidders who is awarded the Contract

12. Confirmation
We would appreciate you informing us by facsimile/e-mail whether or not you
will submit a proposal

13. Consultant for Sl. No. 4 must tied up with Consultant for Sl. No. 1 before starting
Feasibility study.

Thanking you.

Yours sincerely,

(J.RAMMAWIA)
Chief Engineer, Highways,
Mizoram PWD
Mizoram:Aizawl.
Encl. as above.

20
Annex-1

Details of the stretch proposed for DPR preparation

Feasibility Study and preparation of DPR for Aizawl By-Pass on NH-54


within Mizoram.

Tentative
S. NH No. Section State Length (in Km.) Package
No1 2 3 4 (in5km) No. 6
.

1 54 Aizawl by-pass Mizoram 35.00 1

21
Annex-II

Procedure of Awarding Work based on QCBS including Assessment of Least Cost to


Chief Engineer, Highways, Mizoram PWD under Special Circumstances i.e. When a
Consultant with a particular team becomes H-1 bidder in more than one package

A Consultant with a particular Team can apply for any number of packages with one
team. However, Award of work to a Consultant with a Particular Team either as sole or as
in JV/Association shall be limited to one package only. Following procedure shall be
followed for the selection of the most preferred bidder for the consultancy assignment:

1. At first, Consultants who become H-1 in one package each shall be assigned the
respective package. Then packages in which a Consultant with a Particular Team
turns out to be the most preferred bidder (H-1) in more than one package shall be
considered. In case, a Consultant with a Particular Team turns out to be the most
preferred bidder (H-1) in more than one package, the package which is to be awarded to
this team of a consultant shall be determined on the basis of least cost to Chief Engineer,
Highways considering the Financial Quote of H-1 bidder and H-2 Bidder limited to those
packages which shall be worked out as per procedure illustrated with an example as
mentioned below.

2. Suppose there are 8 packages namely Package-1, Package-2, Package -3, Package-
4, Package -5, package -6, package-7 and Package-8 respectively. It is also assumed
that 10 consultants namely P, Q, R, S, T, U, V, W, X and Y has applied for these
packages. It is also assumed that three Consultants namely P, R and U has applied
with two Teams and the remaining Consultants have applied with only one team. It is
also assumed that the following is the position of various firms after opening of the
Financial proposals (and after arithmetic corrections if any of the Financial bids) of the
packages and after applying QCBS
H-1 H-2 H-3 H-4 H-5 H-6
Package no. Name of Consultants and Financial Quotes (Rs in lakhs)
Package-1 P (team-1) Q W X T Y
230 lakhs 200 lakhs 240 lakhs 220 lakhs 200 lakhs 230 lakhs
Package-2 V U(team-1) X P (team-2) T Y
240 lakhs 210 lakhs 240 lakhs 220 lakhs 200 lakhs 230 lakhs
Package-3 V P(team-1) U(team-1) R (team-2) X Y
200 lakhs 230 lakhs 250 lakhs 230 lakhs 220 lakhs 200 lakhs
Package-4 R (team-1) T U (team-2) P (team-2) Y X
250 lakhs 220 lakhs 250 lakhs 260 lakhs 220 lakhs 245 lakhs
Package-5 R (team-1) V S U(team-2) W T
220 lakhs 240 lakhs 260 lakhs 250 lakhs 220 lakhs 240 lakhs
Package-6 Q T S P (team-2) W U (team-2)
210 lakhs 240 lakhs 250 lakhs 220 lakhs 200 lakhs 230 lakhs
Package-7 R (team-1) U (team-1) Q S W Y
200 lakhs 220 lakhs 240 lakhs 255 lakhs 230 lakhs 240 lakhs
Package-8 V R(team-1) W S P (team-1) Y
190 lakhs 250 lakhs 220 lakhs 240 lakhs 255 lakhs 240 lakhs
22
The different packages shall be awarded to consultants as mentioned below.

2.1 Step-1 :
In this case, Consultants P (team-1) and Q are the H-1 in only one package
each namely package-1 and package-6 respectively. Consultant V is H-1 in 3
packages namely Package-2, Package-3 and Package-8 respectively. Consultant R (team-
1) is H-1 in 3 packages namely Package-4, Package-5 and Package-7 respectively. Since
Consultant P (team-1) is H-1 in Package-1 only and Consultant Qis H-1 in Package-6
only, Consultant P (team-1) shall be awarded Package-1 and Consultant Q shall be
awarded Package-6.

2.2 Step-2:
After Consultant P (team-1) is awarded Package-1 and Consultant Qis awarded
Package-6, the scenario for the remaining 6 packages is as given below .P (team-1)
and Q occurring anywhere else stands deleted as they have already been awarded one
work each

H-1 H-2 H-3 H-4 H-5 H-6


Package No. Name of Consultants and Financial Quotes (Rs in lakhs)
Package-2 V U(team-1) X P (team-2) T Y
240 lakhs 210 lakhs 240 lakhs 220 lakhs 200 lakhs 230 lakhs
Package-3 V U(team-1) R (team-2) X Y
200 lakhs 250 lakhs 230 lakhs 220 lakhs 200 lakhs
Package-4 R (team-1) T U (team-2) P (team-2) Y X
250 lakhs 220 lakhs 250 lakhs 260 lakhs 220 lakhs 245 lakhs
Package-5 R (team-1) V S U (team-2) W T
220 lakhs 240 lakhs 260 lakhs 250 lakhs 220 lakhs 240 lakhs
Package-7 R (team-1) U (team-1) S W Y
200 lakhs 220 lakhs 255 lakhs 230 lakhs 240 lakhs
Package-8 V R(team-1) W S Y
190 lakhs 250 lakhs 220 lakhs 240 lakhs 240 lakhs

Consultant V s h a l l be awarded only one package out of the 3 packages for which it is H-1
namely Package-2, Package-3 and Package-8 respectively. Similarly Consultant R (team-
1) Shall be awarded only one package out of the 3 packages for which it is H-1
namelyPackage-4, Package-5 and Package-7 respectively. The determination of package
to be awarded to Consultant V and Consultant R (team-1) shall be worked out in a single step
(i.e. one at a time) .New H-1 for the remaining packages (4 packages) shall be worked out
only after determination of packages to be awarded to the H-1 bidders at this stage [ i.e.
Consultant V and R (Team-1) in the instant case ] in one step . Determination of Package to
be awarded to each of Consultant V and Consultant R (team-1) shall be worked out as
follows

(i) After the award of Package-1 to Consultant P (team-1) and Package -6 to


ConsultantQ and also considering that a Consultant with a particular team can be
awarded only one work, the details of H-1 and H-2 / New H-2 in the remaining
6 packages are as mentioned below. Since V is H-1 in more than one package
23
and shall be awarded one of these packages, V has been deleted from all other
packages. Similarly, since R(Team-1) in more than one package and shall be
awarded one of these packages, R (Team-1) has been deleted from all other
packages
<
H-1 H-2 / New Remarks
H-2
Package-2 V U(team-1)
240 lakhs 210 lakhs
Package-3 V U(team-1) Since Consultant P( Team-1) is awarded
200 lakhs 250 lakhs Package-1, Consultant U(team-1) becomes
the new H-2
Package-4 R (team-1) T
250 lakhs 220 lakhs
Package-5 R (team-1) S
220 lakhs 260 lakhs
Package-7 R (team-1) U (team-1)
200 lakhs 220 lakhs
Package-8 V W Consultant-R(team-1) has not been considered
190 lakhs 220 lakhs as H-2 since Consultant C (team-1) is to be
awarded one package out of the packages 4,5 and
7 in which it is H-1. Hence Consultant W is
the new H-2

(ii) Package to be awarded to Consultant V who is H-1 in three packages namely Package -
2, 3 and 8 respectively shall be determined on the basis of least cost to Chief Engineer,
Highways considering the Financial Quote of H-1 bidder and H-2 Bidder limited to those
packages The situation for least cost to Chief Engineer, Highways shall be when the
firm with Consultant G is awarded the package for which Financial Bid of second
ranked team (H-2) minus Financial Bid of the first ranked team (H-1) is
maximum. The same is illustrated as given below

H-1 H-2 / New Financial Bid of H-2/ Remarks


H-2 New H-2 minus
Financial Bid of H-1
Package-2 V U(team-1) 210-240 = (-) 30 lakhs
240 lakhs 210 lakhs
Package-3 V U(team-1) 250 200 = (+) 50 H-2 minus H-1 is
200 lakhs 250 lakhs lakhs Maximum. Hence
Consultant V shall be
awarded Package-3
Package-8 V W 220 190 = (+) 30
lakhs

24
In a similar way, Package to be awarded to Consultant R (team-1) who is H-1 in three
packages namely Package -4, 5 and 7 respectively shall be determined as illustrated
below:

H-1 H-2 / New Financial Bid of H-2/ Remarks


H-2 New H-2 minus
Financial Bid of H-1
Package-4 R (team-1) T 220-250 = (-) 30 lakhs
250 lakhs 220 lakhs
Package-5 R (team-1) S 260 220 = (+) 40 H-2 minus H-1 is
220 lakhs 260 lakhs lakhs Maximum. Hence
Consultant R (team-
1) shall be awarded
Package- 5
Package-7 R (team-1) U (team-1) 220 200 = (+) 20
200 lakhs 220 lakhs lakhs

2.3 Step-3
(i) After the award of the above mentioned 4 packages namely, Package-1 to
ConsultantP (team-1), Package -6 to Consultant Q, Package -3 to Consultant V,
Package -5 to ConsultantR (team-1) and also considering that a Consultant with a
particular team can be awarded only one work, the details of new H-1 and New H-2 in
the remaining 4 packages are as mentioned below
H-1 (New H-2 (New Remarks
H-1) H-2)
Package-2 U(team-1) X Since Consultant V is awarded Package-3 ,
210 lakhs 240 lakhs Consultant U (team-1) becomes the new H-1
and Consultant X becomes the new H-2
Package-4 T U (team-2) Since Consultant -R(team-1) is awarded
220 lakhs 240 lakhs Package-5 , Consultant T becomes the new H-
1 and Consultant U (team-2) becomes the new
H-2
Package-7 U (team-1) S Since Consultant R(team-1) is awarded
220 lakhs 255 lakhs Package-5 , Consultant U (team-1) becomes the
new H-1 and Consultant S becomes the new H-2

Package-8 W S Since Consultant V is awarded Package-3 ,


220 lakhs 240 lakhs Consultant W becomes the new H-1 and
Consultant S becomes the new H-2

(ii) Consultant T is the new H-1 for only one package namely Package-4.
Similarly
Consultant W is the new H-1 for only one package namely Package-8. Accordingly
Package- 8 shall be awarded to ConsultantW and Package -4 shall be awarded to
ConsultantT

25
2.4 Step-4:
Consultant U (team-1) is the new H-1 for package- 2 and Package-7 respectively
and Consultant U (team-1) shall be awarded only one package out of this 2 packages.
Package to be awarded to Consultant U (team-1) shall be determined as illustrated
below
H-1 H-2 / New Financial Bid of H-2/ Remarks
H-2 New H-2 minus
Financial Bid of H-1
Package-2 U(team-1) X 240-210 = (+) 30
210 lakhs 240 lakhs lakhs

Package-7 U (team-1) S 255 220 = (+) 35 H-2 minus H-1 is


220 lakhs 255 lakhs lakhs Maximum. Hence
Consultant U (team-
1) shall be awarded
Package- 7

2.5 Step-5 :
(i) After the award of the above mentioned 7 packages namely, Package-1 to
ConsultantP (team-1) , Package -6 to Consultant Q, Package -3 to Consultant V ,
Package -5 to Consultant R (team-1), Package-4 to Consultant -T, Package -8 to
Consultant-W, package -7 to Consultant U (team-1) team and also considering that
a Consultant with a particular team can be awarded only one work , the details of new
H-1 and / New H-2 in the remaining package i.e. package -2 is as mentioned below

H-1 (New H-2 (New Remarks


H-1) H-2)
Package-2 X A (team-2) Since Consultant V is awarded Package-3 and
240 lakhs 220 lakhs Consultant U (team-1) is awarded package- 7 ,
Consultant X becomes the new H-1 and
Consultant P(team-2) becomes the new H-2

(ii) Consultant X is the new H-1 for only one package namely Package-2.
Accordingly,
Package -2 shall be awarded to Consultant X.

26
3. Thus as per the above mentioned procedure the 8 packages are awarded to
the following Consultant at the Financial Quoted (after arithmetic Corrections) by
them for the respective packages

Package No. Name of Consultants awarded packages


Package-1 Consultant- P (team-1)
Package-2 Consultant- X
Package-3 Consultant- V
Package-4 Consultant- T
Package-5 Consultant- R (team-1)
Package-6 Consultant- Q
Package-7 Consultant- U (team-1)
Package-8 Consultant- W

27
DATA SHEET

I (References to corresponding paragraphs of LOI are mentioned alongside)


1. The Name of the Assignment a n d description of project as mentioned in
Annex-I
(Ref. Para 1.1)
(The Name of project and Package No. should be indicated in the format given in
the technical proposal)

2. The name of the Client is : Chief Engineer, Highways, Mizoram PWD

3. Duration of the Project 5 months

4. Date, Time and Venue of Pre-Proposal Conference

Date: 7th November


Time:1300 hrs
Venue: Office of the Chief Engineer, PWD,Highways, Mizoram (Ref. Para 1.9)

5. The Documents are:


i. Appendix-I: Terms of Reference (TOR)
ii) Appendix-II Formats for Proof of Eligibility
iii. Appendix-III: Formats for Technical Proposal
iv. Appendix-IV: Formats for Financial Proposal
v. Appendix -VI Draft Contract Agreement

(Ref. Para 2.1)


6. Bid Security: Rs 1.0 Lakhs (Ref Para 1.10)

7. Tax and Insurance (Ref. Para 3.3.2)

(i). The Consultants and their personnel shall pay all taxes (including service tax),
custom duties, fees, levies and other impositions levied under the laws
prevailing seven days before the last date of submission of the bids. The
effects of any increase / decrease of any type of taxes levied by the
Government shall be borne by the Client / Consultant, as appropriate

(ii) Limitation of Consultants Liability towards the Client shall be as per Clause
3.4 of Draft Contract Agreement.

(iii) The risk and Coverage shall be as per Clause 3.5 of Draft Contract Agrement.

28
8. The number of copies of the proposal required to be submitted: 1 no. (ref. para 4.1)

9. The address is ---(Ref. para 4.2)


Chief Engineer,Mizoram PWD, Highways, Tuikhuahtlang, Aizawl, Mizoram.

The envelopes must be clearly marked:

i. Original Proposal;
ii. Documents in proof of eligibility and technical proposal as appropriate; and,
iii. Do not open, except in presence of the eval uat i on committee on the outer
envelope. iv. Consultancy Package No. :-1
v. Project Name: Feasibility study and preparation of DPR for Aizawl by-pass on NH-54
vi. Name and Address of Consultant

10. The date, time and Address of proposal submission are


Date: 7th November Time:1300 hrs Address: Office of the Chief Engineer,
PWD, Highways, Mizoram

(Ref. Para 4.4)

11. Proposal Validity period (Number of days): 120 days (Ref. Para 4.5)

12. Evaluation criteria: (Ref. Para 3 & 5)

12.1 First stage evaluation eligibility requirement. (Ref. Para 3.1 & 5.1)

29
Table-1: Minimum Eligibility Requirements
S.No. Minimum experience and performance Annual average turnover
of Preparation of DPR of Highways /
Bridges in the last 7 years
(NH/SH/Equivalent) (for past performance
attach undertaking for any litigation history/
and arbitration).

1 A Firm applying for a package should have Annual average turnover for
Experience of preparation of Detailed last 3 years of the firm should be
ProjectReport of two/four/six lane / Feasibility of equal to or more than Rs.2.00
Two/ four/ six lane projects of aggregate length
equal to the indicative length of the package (i.e. Crores.
100km if the indicative length of the package is
100 km). Firm should have also prepared DPR for
at least one project of 2/4/6laning of minimum
40% of the indicative length of the package (i.e.
40 km if the indicative length of the package is
100 km) or Feasibility Study of two/four/six
laning of minimum 60% of the indicative length
of the package (i.e. 60 km if the indicative length
of the package is 100 km )

Note: The experience of a firm in preparation of


DPR for a private concessionaire/contractor shall
not be considered

i) The sole applicant shall fulfill all the requirements given in Table-1.

(ii) In case of JV, the Lead Partner should fulfill at least 75% of all eligibility requirements and
the other partner shall fulfill at least 50% of all eligibility requirements.

(iii) If the applicant firm has / have prepared the DPR/FS projects solely on its own,
100%weightage shall be given. If the applicant firm has prepared the DPR/FS projects as
a lead partner in a JV, 75% weightage shall be given. If the applicant firm have prepared
the DPR projects as the other partner (not lead partner) in a JV 50% weightage shall be
given. If the applicant firm have prepared the DPR/FS projects as an associate,
25% weightage shall be given.

30
12.2 Second stage technical evaluation (Refer 5.2)

S.No. Description Points


1 Firm's relevant experience in last 7 years 25
2 Adequacy of approach and methodology 5
Material testing, survey & investigation, equipment and
3 20
software proposed to be used
Qualification and relevant experience of the proposed
4 50
key personnel
Total 100
Further break-up of each criteria has been detailed out below:

A. Firm's relevant experience in last 7 years

For standard highways, the following is the break-up:


S.No Description Maximum Sub-
Points Points

1 Specific experience of the DPR consultancy related 15


to the assignment for eligibility

1.1 Aggregate Length of DPR / Feasibility study of 2/4/ 7.5


6 lane projects

1.1.1 More than the indicative Length of the package applied 5.5
for

1.1.2 More than 2 times the indicative length of the package 6.5
applied for

1.1.3 More than 3 times the indicative length of the package 7.5
applied for

1.2 DPR for 2/4/6 laning projects each equal to or more 7.5
than 40 % of indicative length of a package applied
for (or Feasibility Study for 2/4/6 laning projects
each equal to or more than 60 % of indicative length
of a package applied for)

1.2.1 1 project 5.5

1.2.2 2 projects 6.5

31
S.No Description Maximum Sub-
Points Points

1.2.3 3 or more projects 7.5

2 DPR of Bridge having length more than 60 m 5

2.1 1 bridge 2

2.2 2 bridges 3

2.3 3 bridges 4

2.4 4 or more bridges 5

3 Specific experience of firms in terms of turnover 5

3.1 Firms Average Turnover of last 3 years >= 10 crore 5

3.2 Firm Average Turnover of last 3 years > = 5 crore but 4


< 10 crore

3.3 Firm Average Turnover of last 3 years < 5 crore 0

For special projects such as special bridges, tunnels and expressways that require
specialized capabilities and skill sets, the following is the break-up:

S.No Description Maximum Sub-


Points Points

1 Specific experience of the DPR consultancy related 12


to the assignment for eligibility

1.1 Aggregate Length of DPR / Feasibility study of 2/4/ 6


6 lane projects

1.1.1 More than the indicative Length of the package applied 4


for

1.1.2 More than 2 times the indicative length of the package 5


applied for

1.1.3 More than 3 times the indicative length of the package 6


applied for

32
S.No Description Maximum Sub-
Points Points

1.2 DPR for 2/4/6 laning projects each equal to or more 6


than 40 % of indicative length of a package applied
for (or Feasibility Study for 2/4/6 laning projects
each equal to or more than 60 % of indicative length
of a package applied for)

1.2.1 1 project 4

1.2.2 2 projects 5

1.2.3 3 or more projects 6

2 DPR of Bridge having length more than 60 m 4

2.1 1 bridge 1

2.2 2 bridges 2

2.3 3 bridges 3

2.4 4 or more bridges 4

3 Specific experience of firms in terms of turnover 4

3.1 Firms Average Turnover of last 3 years >= 10 crore 4

3.2 Firm Average Turnover of last 3 years > = 5 crore but 3


< 10 crore

3.3 Firm Average Turnover of last 3 years < 5 crore 0

4 DPR for special category projects (Special bridges/ 5


tunnels or expressways, whichever applicable). It is
to be noted that either 4.1 or 4.2 shall be applicable,
and not both.

4.1 DPR of number of special bridges/ tunnels (if 5


applicable)

4.1.1 1 project 1

4.1.2 2 projects 2

33
S.No Description Maximum Sub-
Points Points

4.1.3 3 projects 3

4.1.4 4 projects 4

4.1.5 5 or more projects 5

4.2 Aggregate length of DPR/ Feasibility study for 5


expressways

4.2.1 Upto 50km 2

4.2.2 50km to 100km 3

4.2.3 100km to 150km 4

4.2.4 More than 150 km 5

Note: In case feasibility study is a part of DPR services the experience shall be counted in
DPR only. In case bridge is included as part of DPR of highway the experience will be (1)
and (2)
B. Adequacy of approach and methodology

S.No Description Points


1 Site appreciation 2
2 Comments on TOR 1
3 Team composition and task assignment 1
4 Methodology 1
Total 5

C. Material testing, survey and investigation, equipment and software proposed to


be used

S.No Description Maximum Sub-


Points Points

1 Availability of in-house material testing facility 2

1.1 Available 2

1.2 Outsourced 1

34
S.No Description Maximum Sub-
Points Points

1.3 Not Available 0

2 Field Investigation Facilities 3

2.1 Available 3

2.2 Outsourced 1.5

2.3 Not Available 0

3 Office Equipment and Software 3

3.1 Available 3

3.2 Outsourced 1.5

3.3 Not Available 0

4 Experience in LiDAR or equivalent technology for 4


topographic survey

4.1 1 project 1

4.2 2 projects 2

4.3 3 projects 3

4.4 4 or more projects 4

5 Experience in using GPR and Induction Locator or 4


equivalent technologies for detection of sub-surface
utilities

5.1 1 project 1

5.2 2 projects 2

5.3 3 projects 3

5.4 4 or more projects 4

6 Experience in digitization of cadastral maps for 4


land acquisition

35
S.No Description Maximum Sub-
Points Points

6.1 1 project 1

6.2 2 projects 2

6.3 3 projects 3

6.4 4 or more projects 4

D. Qualification and relevant experience of the proposed key personnel


The weightage for various key staff is as under:

S.No Key personnel Points


1 Team Leader- Senior Highway Engineer 10
2 Senior Bridge Engineer 7
3 Highway cum Pavement Engineer 7
4 Material-cum-Geo-technical Engineer- Geologist 7
5 Traffic and Safety Expert 6
6 Senior Survey Engineer 5
7 Environment Specialist 5
8 Quantity Surveyor/Documentation Expert 3
Total 50

The number of points assigned during the evaluation of qualification and competence of
key staff are as given below:

S.No Description Maximum Sub-


Points Points

1 General Qualification 25

1.1 Essential education qualification 20

1.2 Desirable education qualification 5

2 Relevant experience and adequacy for the project 65

2.1 Total professional experience 15


(max)

37
S.No Description Maximum Sub-
Points Points

2.1 Experience in Highway Projects 25


(Bridge Projects for Senior Bridge (max)
Engineer )

2.2 Experience in Similar Capacity 25


(max)

3 Employment with the Firm 10

3.1 Less than 1 year 0

3.2 1 year to 2 years 5

3.3 > 2 years 10

12.3 Detailed evaluation criteria which is to be used for evaluation of technical bids
is as indicated at Appendix-V.

The Consultant should carryout self-evaluation based on the evaluation criteria at


Appendix-V. While submitting the self-evaluation along with bid, Consultant shall
make references to the documents submitted in their proposal which have been
relied upon in self-evaluation Result of technical evaluation shall be made
available on the website giving opportunity to the bidders to respond within 7
days in case they have any objection

12.4 Third stage Evaluation of Financial proposal

Financial Proposals of all Qualified Consultants in accordance with clause 5.2 and 5.3
of Letter of Invitation shall be opened.The consultancy services will be awarded to the
consultant scoring highest marks in combined evaluation of Technical and Financial
proposals in accordance with clause 1.3 and 5.4 hereof. The Factors are:
The weight given to Technical Proposal (T) = 0.80
The weight given to Financial Proposal (f) = 0.20
13. The common currency is Indian Rupee. (Ref. Para 3.3.3)

Consultant have to quote in Rupees both for domestic Consultant as well as Foreign
Consultant

14. Commencement of Assignment (Date, Location): The Consultants shall commence


the Services within fifteen days of the date of effectiveness of the contract at locations as
required for the project stretch stated in TOR. (Ref. Para 1.2 of LOI and 2.3 of GCC/SC)

39
APPENDIX I

TERMS OF REFERENCE (TOR)

Consultancy Services for Feasibility Study and preparation of DPR for Aizawl By-
Pass on NH-54 within Mizoram. (as per Annexure I ).

40
Terms of Reference for Consultancy Services (TOR)

1. General

1.1 The Chief Engineer, Highways has been entrusted with the assignment of Feasibility
Study and preparation of DPR for Aizawl By-Pass on NH-54 within Mizoram. (as per
Annexure I ).

Chief Engineer, Highways now invites proposal from Technical consultants for carrying
out detailed project report as per details given in Annexure-1.

1.2 Chief Engineer, Highways will be the employer and executing agency for the
consultancy services and the standards of output required from the appointed
consultants are of international level both in terms of quality and adherence to the
agreed time schedule.

1.3 Ministry has recently awarded works of consultancy services for construction of
ROBs for replacing level crossings in various states. In case a level crossing exists in a
project reach, consultant is required to co-ordinate with those consultants and finalise
the alignment & configuration of road accordingly. However, if the same is not
covered in the above assignment of DPR/feasibility study awarded by Ministry, the
consultant under this assignment shall be responsible for preparing DPR for such level
crossings.

2. Objective

2.1 The main objective of the consultancy service is to establish the technical,
economical, and financial viability of the project and prepare detailed project reports
for rehabilitation and upgrading of the existing road to 2-Lane configuration.

2.2 The viability of the project shall be established taking into account the requirements
with regard to rehabilitation, upgrading and improvement based on highway design,
pavement design, provision of service roads wherever necessary, type of
intersections, rehabilitation and widening of existing and/or construction of new
bridges and structures, road safety features, quantities of various items of works
and cost estimates and economic analysis.

2.3 The Detailed Project Report would inter-alia include detailed highway design, design
of pavement and overlay with options for flexible or rigid pavements, design of
bridges and cross drainage structures and grade separated structures, design of
service roads, quantities of various items, detailed working drawings, detailed cost
estimates, economic and financial viability analyses, environmental and social
feasibility, social and environmental action plans as appropriate and documents
required for tendering the project on commercial basis for international / local
competitive bidding.

2.4 The DPR consultant should ensure detailed project preparation incorporating aspects
of value engineering, quality audit and safety audit requirement in design and
implementation.

41
2.5 The consultant should, along with Feasibility Report, clearly bring out
through financial analysis the preferred mode of implementation on which the Civil
Works for the stretches are to be taken up. The consultant should also give cost
estimates along with feasibility report/ detailed Project Report.

2.6 If at feasibility stage, employer desire to terminate the contract, the contract will
be terminated after payment up to that stage.

3. Scope of Services

3.1 As far as possible, the widening/improvement work to 2-lane shall be within


the existing right of way avoiding land acquisition, except for locations having
inadequate width and where provisions of short bypasses, service roads, alignment
corrections, improvement of intersections are considered necessary and practicable
and cost effective. However bypasses proposals should also be considered, wherever
in urban areas, improvement to 2-lane of the existing road is not possible. The
Consultant shall furnish land acquisition details as per revenue records/maps for
further processing of land acquisition. Consultant shall also submit 3a, 3A and 3D
draft notification for acquisition of land.

3.2 The Consultant shall study the possible locations and design of toll plaza, if
applicable to the project. Wayside amenities required on tolled highway shall also be
planned. The local and slow traffic may need segregation from the main traffic and
provision of service roads and fencing may be considered, wherever necessary to
improve efficiency and safety.

3.3 The general scope of services is given in the sections that follow. However, the
entire scope of services would, inter-alia, include the items mentioned in the Letter of
Invitation and the TOR. The Consultant will also make suitable proposals for
widening/improvement of the existing road and strengthening of the carriageways, as
required at the appropriate time to maintain the level of service over the design
period. The Consultants shall prepare documents for EPC/PPP contracts for each DPR
assignment

3.4 All ready to implement good for construction drawings shall be prepared.

3.5 Environmental Impact Assessment, Environmental Management Plan and


Rehabilitation and Resettlement Studies shall be carried out by the Consultant
meeting the requirements of the lending agencies like ADB/ World Bank/JICA, etc.

3.6 Wherever required, consultant will liaise with concerned authorities and arrange
all clarifications. Approval of all drawings including GAD and detail engineering
drawings will be got done by the consultant from the Railways. However, if Railways
require proof checking of the drawings prepared by the consultants, the same will
be got done by Chief Engineer, Highways and payment to the proof consultant
shall be made by Chief Engineer, Highways directly. Consultant will also obtain
final approval from Ministry of Environment and Forest for all

42
applicable clearances. Consultant will also obtain approval for estimates for shifting
of utilities of all types from the concerned authorities and competent authority within
MoRTH and its implementation agencies, as applicable. Consultant is also required to
prepare all Land Acquisition papers (i.e. all necessary schedule and draft 3a, 3A,
and 3D, 3G notification as per L.A. act) for acquisition of land either under NH Act
or State Act.

3.7 The DPR consultant may be required to prepare the Bid Documents, based on
the feasibility report, due to exigency of the project for execution if desired by Chief
Engineer, Highways

3.8 Consultant shall obtain all types of necessary clearances required for
implementation of the project on the ground from the concerned agencies. The
client shall provide the necessary supporting letters and any official fees as per the
demand note issued by such concerned agencies from whom the clearances are
being sought to enable implementation.

3.9 The consultant shall prepare separate documents for BoT as well as EPC
contracts at Feasibility stage / DPR stage. The studies for financing options like BoT,
Annuity, EPC will be undertaken in feasibility study stage.

3.10 The consultant shall be guided in its assignment by the Model Concession/
Contract Agreements for PPP/ EPC projects, as applicable and the Manual of
Specifications and Standards for two/ four/ six laning of highways published by IRC
(IRC:SP:73 or IRC:SP:84 or IRC:SP:87, as applicable) (the "Manual") along with
relevant IRC codes for design of long bridges.

3.11 The consultant shall prepare the bid documents including required schedules
(as mentioned above) as per EPC/ PPP documents. For that it is suggested that
consultant should also go through the EPC/PPP documents of ministry before
bidding the project. The Consultant shall assist the Chief Engineer, Highways and
it's Financial Consultant and the Legal Adviser by furnishing clarifications as required
for the financial appraisal and legal scrutiny of the Project Highway and Bid
Documents.

3.12 Consultant shall be responsible for sharing the findings from the preparation stages
during the bid process. During the bid process for a project, the consultant shall
support the authority in responding to all technical queries, and shall ensure
participation of senior team members of the consultant during all interaction with
potential bidders including pre- bid conference, meetings, site visits etc. In addition,
the consultant shall also support preparation of detailed responses to the written
queries raised by the bidders.

4. General

4.1 Primary Tasks


General Scope of Services shall cover but be not limited to the following major tasks
(additional requirements for Preparation of Detailed Project Report for Hill Roads
and Major Bridges are given in Supplement I and II respectively):
43
i. review of all available reports and published information about the project
road and the project influence area;

ii. Environmental and social impact assessment, including such as related to


cultural properties, natural habitants, involuntary resettlement etc.

ii (a). Public consultation, including consultation with Communities located along


the road, NGOs working in the area, other stake-holders and relevant
Government departments at all the different stages of assignment (such as
inception stage, feasibility stage, preliminary design stage and once final
designs are concretized).

iii. Detailed reconnaissance;

iv. identification of possible improvements in the existing alignment and


bypassing congested locations with alternatives, evaluation of different
alternatives comparison on techno-economic and other considerations and
recommendations regarding most appropriate option;

v. traffic studies including traffic surveys and Axle load survey and demand
forecasting for next thirty years;

vi. Inventory and condition surveys for road;

vii. Inventory and condition surveys for bridges, cross-drainage structures, other
Structures, river Bank training/Protection works and drainage provisions;

viii. Detailed topographic survey using mobile/ aerial LiDAR or equivalent technology

ix. Pavement investigations;

x. Sub-grade characteristics and strength: investigation of required sub-grade and


sub-soil characteristics and strength for road and embankment design and
sub soil investigation;

xi. Identification of sources of construction materials;


xii. Detailed design of road, its x-sections, horizontal and vertical alignment and
design of embankment of height more than 6m and also in poor soil conditions
and where density consideration require, even lesser height embankment.
Detailed design of structures preparation of GAD and construction drawings
and cross- drainage structures and underpasses etc.

44
xiii. Identification of the type and the design of intersections;

xiv. Design of complete drainage system and disposal point for storm water

xv. Value analysis / value engineering and project costing;

xvi. Economic and financial analyses;

xvii. Contract packaging and implementation schedule.

xviii Strip plan indicating the scheme for carriageway widening, location of
all existing utility services (both over- and underground) and the scheme for
their relocation, trees to be felled, transplanted and planted and land
acquisition requirements including schedule for LA: reports documents and
drawings arrangement of estimates for cutting/ transplanting of trees and
shifting of utilities from the concerned department;

xix To find out financial viability of project for implementation and suggest
the preferred mode on which the project is to be taken up.

xx. Preparation of detailed project report, cost estimate, approved for construction
Drawings, rate analysis, detailed bill of quantities, bid documents for
execution of civil works through budgeting resources.

xxi. Design of toll plaza and identification of their numbers and location and office
cum residential complex including working drawings

xxii. Design of weighing stations, parking areas and rest areas.

xxiii. Any other user oriented facility en-route toll facility.

xxiv. Tie-in of on-going/sanctioned works of MORT&H/ NHAI/ other agencies.

xxv. Preparation of social plans for the project affected people as per policy of the
lending agencies/ Govt. of India R & R Policy.

4.2 While carrying out the field studies, investigations and design, the development
plans being implemented or proposed for future implementation by the local bodies,
should be taken into account. Such aspect should be clearly brought out in the reports
and drawings.

45
4.3 The consultant shall study the possible locations and design of toll plaza,
wayside amenities required and arboriculture along the highway shall also be planned.
4.4 The local and slow traffic may need segregation from the main traffic and provision
of service roads and physical barrier including fencing may be considered, wherever
necessary to improve efficiency and safety.

4.5 Standards and Codes of Practices


1. All activities related to field studies, design and documentation shall be done as per
the latest guidelines/ circulars of MoRT&H and relevant publications of the Indian
Roads Congress (IRC) and Bureau of Indian Standards (BIS). For aspects not covered
by IRC and BIS, international standards practices, may be adopted. The Consultants,
upon award of the Contract, may finalize this in consultation with Chief Engineer,
Highways and reflect the same in the inception report.
2. All notations, abbreviations and symbols used in the reports, documents and
drawings shall be as per IRC:71.

4.6 Quality Assurance Plan (QAP)


1. The Consultants should have detailed Quality Assurance Plan (QAP) for all field
studies including topographic surveys, traffic surveys, engineering surveys and
investigations, design and documentation activities. The quality assurance
plans/procedures for different field studies, engineering surveys and investigation,
design and documentation activities should be presented as separate sections like
engineering surveys and investigations, traffic surveys, material geo-technical and sub-
soil investigations, road and pavement investigations, investigation and design
of bridges & structures, environment and R&R assessment, economic & financial
analysis, drawings and documentation, preparation, checking, approval and filing
of calculations, identification and tractability of project documents etc. Further,
additional information as per format shall be furnished regarding the details of personal
who shall be responsible for carrying out/preparing and checking/verifying various
activities forming part of feasibility study and project preparation, since inception to
the completion of work. The detailed Draft QAP Document must be discussed and
finalised with the concerned Chief Engineer, Highways officers immediately upon the
award of the Contract and submitted as part of the inception report.

2. It is imperative that the QAP is approved by Chief Engineer, Highways before the
Consultants start the field work.

4.7 Review of Data and Documents


1. The Consultants shall collect the available data and information relevant for
the Study. The data and documents of major interest shall include, but not be
limited to, the following:
i. Climate;
ii. Road inventory
iii Road condition, year of original construction, year and type of

46
major maintenance/rehabilitation works;
iv. Condition of bridges and cross-drainage structures;
v. sub-surface and geo-technical data for existing bridges;
vi. Hydrological data, drawings and details of existing bridges;
vii Existing geological maps, catchment area maps, contour plans etc. for
the project area
viii Condition of existing river bank / protection works, if any.
ix. Details of sanctioned / on-going works on the stretch sanctioned
by
MoRT&H/other agencies for Tie-in purposes
x. Survey and evaluation of locally available construction materials;
xi. Historical data on classified traffic volume (preferably for 5
years or more);
xii. Origin-destination and commodity movement characteristics; if available
xiii. Speed and delay characteristics; if available;
xiv. Commodity-wise traffic volume; if available;
xv. Accident statistics; and,
xvi. Vehicle loading behavior (axle load spectrum), if available.
xvii) Type and location of existing utility services (e.g. Fibre Optical
Cable, O/H and U/G Electric, Telephone line, Water mains, Sewer,
Trees etc.)
xviii) Environmental setting and social baseline of the project.

4.8. Social Analysis


The social analysis study shall be carried out in accordance with the MORT&H/World
Bank/ADB Guidelines. The social analysis report will, among other things, provide a
socio- economic profile of the project area and address in particular, indigenous
people, communicable disease particularly HIV/AIDS poverty alleviation, gender,
local population, industry, agriculture, employment, health, education, health, child
labor, land acquisition and resettlement .
4.9 Traffic Surveys
All traffic surveys and studies will be completed in feasibility studies.

4.9.1 Number and Location of Survey Stations


1. The type of traffic surveys and the minimum number of survey stations
shall normally be as under, unless otherwise specifically mentioned.
Number of Survey
Sl.NR. Description
Stations
1. Classified Traffic Volume Count 3
2. Origin-Destination and Commodity Minimum 2
Movement Characteristics
3. Axle Loading Characteristics 2
4. Intersection Volume Count All Major Intersections
5. Speed-Delay Characteristics Project Road Section
6. Pedestrian/animal cross traffic count All major inhabitations
along the highway

47
2. The number of survey locations indicated in the table above are indicative only.
The Consultants shall, immediately upon award of the work, submit to Chief
Engineer, Highways proposals regarding the total number as well as the locations of
the traffic survey stations as put of inception report. Suitable maps and charts
should accompany the proposals clearly indicating the rationale for selecting the
location of survey Station

3. The methodology of collection and analysis of data, number and location of


traffic survey stations shall be finalized in consultation with Chief Engineer,
Highways
4.9.2. Classified Traffic Volume Count Survey

1. Consultant shall make use of traffic survey done by Indian Highways


Management Company Limited (IHMCL) using ATCC systems. If required,
especially in cases where a particular stretch is not covered by IHMCL, DPR
consultant should carry out classified traffic volume count survey using
ATCC systems or equivalent technologies.

2. Consultant shall use ATCC systems that can meet the following accuracy
levels after validation/ correction:

(a) Classification of vehicles: better than 95%


(b) Counting of vehicles: better than 98%

Before validation and correction, the ATCC system shall meet the
following accuracy levels:

(a) Classification of vehicles: better than 90%


(b) Counting of vehicles: better than 95%

For verification of above accuracy levels, audit of raw ATCC shall be done
on a sampling basis.

3. ATCC systems such as Pneumatic Tube Detector, Inductive Detector Loop,


Image Detection, and Infrared Sensor or equivalent technologies shall be
adopted.

4. The classified traffic volume count surveys shall be carried out for 7
days (continuous, direction-wise) at the selected survey stations. The vehicle
classification system as given in relevant IRC code may be followed.
However, the following generalised classification system is suggested in view
of the requirements of traffic demand estimates and economic analysis:

Motorised Traffic Non-Motorised Traffic


2-Wheeler Bi-Cycle
3-Wheeler Cycle-Rickshaw
Passenger Car Animal Drawn Vehicle (ADV)
Utility Vehicle (Jeep, Van etc.) Hand Cart

49
Other Non-Motorised Vehicle
Bus Mini Bus
Standard Bus
LCV LCV-Passenger
LCV-Freight
Truck MCV : 2-Axle Rigid Chassis
HCV : 3-Axle Rigid Chassis
MAV Semi Articulated
Articulated

5. All results shall be presented in tabular and graphical form. The survey data
shall be analysed to bring out the hourly and daily variations. The traffic
volume count per day shall be averaged to show a weekly average daily traffic
(ADT) by vehicle type. The annual average daily traffic (AADT) shall be
worked out by applying seasonal factors.

6. The consultant shall compile the relevant traffic volume data from
secondary sources also. The salient features of traffic volume characteristics
shall be brought out and variations if any, from the traffic census carried out by
the State PWD shall be suitably explained.

4.9.3. Origin-Destination and Commodity Movements Surveys

1. The consultants shall carry out 1-day (24 hour, both directions) O-D
and commodity movement surveys at locations finalized in
consultation with Chief Engineer, Highways, Mizoram PWD These will be
essentially required around congested towns to delineate through traffic. The
road side interviews shall be on random sample basis and cover all four-
wheeled vehicles. The location of the O-D survey and commodity movement
surveys shall normally be same as for the classified traffic count.

2. The location of origin and destination zones shall be determined in relation to


each individual station and the possibility of traffic diversion to the Project
Road from/to other road routes including bypasses.

3. The trip matrices shall be worked out for each vehicle type information on
weight for trucks should be summed up by commodity type and the results
tabulated, giving total weight and average weight per truck for the various
commodity types. The sample size for each vehicle type shall be indicated
on the table and also in the graphical representations.

4. The data derived from surveys shall also be analysed to bring out the lead
and load characteristics and desire line diagrams. The data analysis should
also bring out the requirement for the construction of bypasses.

50
5. The distribution of lead and load obtained from the surveys should be
compared The axle load surveys shall normally be done using axle load
pads or other sophisticated instruments. The location(s) of count station(s)
and the survey with those derived from the axle load studies.
6. The commodity movement data should be duly taken into consideration
while making the traffic demand estimates.

4.9.4..Turning Movement Surveys

1. The turning movement surveys for estimation of peak hour traffic for the design
of major and minor intersections shall be carried out for the Study. The details
regarding composition and directional movement of traffic shall be furnished by the
Consultant.

2. The methodology for the surveys shall be as per IRC: SP: 41-1994. The details
including location and duration of surveys shall be finalized in consultation with
Chief Engineer, Highways officials. The proposal in response to this TOR shall
clearly indicate the number of locations that the Consultants wish to conduct turning
movement surveys and the rationale for the same.

3. The data derived from the survey should be analyzed to identify requirements of
suitable remedial measures, such as construction of underpasses, fly-overs,
interchanges, grade- separated intersections along the project road alignment.
Intersections with high traffic volume requiring special treatments either presently or
in future shall be identified.

4.9.5. Axle Load Surveys

1. Axle load surveys in both directions shall be carried out at suitable location(s) in
the project road stretch on a random sample basis normally for trucks only (both
empty and loaded trucks) for 2 normal days - (24 hours) at special count stations to
be finalized in consultation with Chief Engineer, Highways However, a few buses
may be weighed in order to get an idea about their loading behavior. While selecting
the location(s) of axle load survey station(s), the locations of existing bridges with
load restrictions, if any, should be taken into account and such sites should be
avoided.

2. Axle load surveys shall normally be done using axle load pads or other
sophisticated instruments. The location(s) of count station(s) and the survey
methodology including the data formats and the instrument type to be used shall be
finalized before taking up the axle load surveys

51
3. The axle load data should be collected axle configuration-wise. The number of
equivalent standard axles per truck shall be calculated on the basis of results
obtained. The results of the survey should bring out the VDF for each truck type
(axle configuration, if the calculated VDF is found to be below the national average,
then national average shall be used. Furthermore, the data from axle load surveys
should be analysed to bring out the Gross Vehicle Weight (GVW) and Single Axle
Load (SAL) Distributions by truck type (axle configuration).

4. The Consultant shall ascertain from local enquiries about the exceptional live
loads that have used the highway in the past in order to assess the suitability of
existing bridges to carry such loads.

4.9.6. Speed-Delay Surveys

The Consultants shall carry out appropriate field studies such as moving car
survey to determine running speed and journey speed. The data should be
analyzed to identify sections with typical traffic flow problems and congestion. The
objective of the survey would be to recommend suitable measures for segregation of
local traffic, smooth flow of through traffic and traffic safety. These measures
would include the provision of bypasses, under-passes, fly-overs, interchanges, grade-
separated intersections and service roads.

4.9.7 Pedestrian / animal cross traffic surveys:

These may be conducted to determine if provision of viaduct for


pedestrians/animals is necessary to improve the traffic safety.

4.9.8 Truck Terminal Surveys

The data derived from the O-D, speed-delay, other surveys and also
supplementary surveys should be analysed to assess requirements for present and future
development of truck terminals at suitable locations en route.

4.10. Traffic Demand Estimates

1. The consultants shall make traffic demand estimates and establish possible traffic
growth rates in respect of all categories of vehicles, taking into account the past trends,
annual population and real per capita growth rate, elasticity of transport demand in
relation to income and estimated annual production increase. The other aspects
including socio- economic development plans and the land use patterns of the region
having impact on the traffic growth, the projections of vehicle manufacturing industry in
the country, development plans for the other modes of transport, O-D and commodity
movement behaviour should also be taken into account while working out the traffic
demand estimates.

2. The values of elasticity of transport demand shall be based on the prevailing practices i n
the country. The Consultants shall give complete background including references for
selecting the value of transport demand elasticity.

52
3. It is envisaged that the project road sections covered under this TOR would be
completed and opened to traffic after 3 years. The traffic demand estimates shall be
done for a further period of 30 years from completion of two/four lane. The demand
estimates shall be done assuming three scenarios, namely, optimistic, pessimistic and
most likely traffic growth. The growth factors shall be worked out for five-yearly
intervals.

4. Traffic projections should be based on sound and proven forecasting techniques. In


case traffic demand estimated is to be made on the basis of a model, the application of
the model in the similar situation with the validation of the results should be established.
The traffic projections should also bring out the possible impact of implementation of
any competing facility in the near future. The demand estimates should also take into
account the freight and passenger traffic along the major corridors that may interconnect
with the project. Impact of toll charges on the traffic estimates should be estimated.
5. The methodology for traffic demand estimates described in the preceding paragraphs is
for normal traffic only. In addition to the estimates for normal traffic, the Consultants
shall also work out the estimates for generated, induced and diverted traffic.

6. The traffic forecasts shall also be made for both diverted and generated traffic.

7. Overall traffic forecast thus made shall form the basis for the design of each pavement
type and other facilities/ancillary works.

4.11. Engineering Surveys and Investigations

4.11.1. Reconnaissance and Alignment


1. The Consultants should make an in-depth study of the available land width(ROW)
topographic maps, satellite imageries and air photographs of the project area,
geological maps, catchment area maps, contour plans, flood flow data and
seismological data and other available relevant information collected by them
concerning the existing alignment. Consultant himself has to arrange the required
maps and the information needed by him from the potential sources. Consultant
should make efforts for minimizing land acquisition.
2. The detailed ground reconnaissance may be taken up immediately after the study of
maps and other data. The primary tasks to be accomplished during the reconnaissance
surveys include;
i. topographical features of the area;
ii. typical physical features along the existing alignment within and outside
ROW i.e. land use Pattern;
iii. possible alignment alternatives, vis-a-vis, scheme for the construction of
additional lanes parallel to the existing road;
iv. realignment requirements including the provision of bypasses, ROBs
Flyovers and via-duct for pedestrian crossings with possible alignment
alternatives;

53
v. preliminary identification of improvement requirements including
treatments and measures needed for the cross-roads;
vi. traffic pattern and preliminary identification of traffic homogenous links;
vii. sections through congested areas;
viii. inventory of major aspects including land width, terrain, pavement type,
carriageway type, bridges and structures (type, size and location),
intersections(type, cross-road category, location) urban areas (location,
extent), geologically sensitive areas, environmental features:
ix. critical areas requiring detailed investigations; and,
x. Requirements for carrying out supplementary investigations.
xi. soil (textural classifications) and drainage conditions
xii. Type and extent of existing utility services along the alignment (within
ROW).
xiii. Typical physical features along the approach roads
xiv. Possible bridge locations, land acquisition problems, nature of
crossings, likely length of approaches and bridge, firmness of banks,
suitability of alignment of approach roads.

3. The data derived from the reconnaissance surveys are normally utilized
for planning and programming the detailed surveys and investigations. All field
studies including the traffic surveys should be taken up on the basis of
information derived from the reconnaissance surveys.
4. The data and information obtained from the reconnaissance surveys should
be documented. The data analysis and the recommendations concerning
alignment and the field studies should be included in the Inception Report. The
data obtained from the reconnaissance surveys should form the core of the
database which would be supplemented and augmented using the data
obtained from detailed field studies and investigations.
5. The data obtained from the reconnaissance surveys should be compiled in
the tabular as well as graphical (chart) form indicating the major physical
features and the proposed widening scheme for Chief Engineer, Highways
comments. The data and the charts should also accompany the rationale for the
selection of traffic survey stations.

4.11.2. Topographic Surveys

1. The basic objective of the topographic survey would be to capture the


essential ground features along the alignment in order to consider
improvements and for working out improvements, rehabilitation and
upgrading costs. The detailed topographic surveys should normally be taken up
after the completion of reconnaissance surveys.

2. The carrying out of topographic surveys will be one of the most important and
crucial field tasks under the project. Technologies which can meet the following
accuracy levels shall be adopted. For land based surveys (a) Fundamental horizontal

54
Accuracy of 2 cm or better (b) Fundamental vertical accuracy of 2 cm or better (c)
More than 50 points shall be measured per sq. m and for aerial based surveys (a)
Fundamental horizontal accuracy of 5 cm or better (b) Fundamental vertical
accuracy of 5 cm or better (c) More than 10 points shall be measured per sq. m. To
establish accuracy, a check point survey using DGPS (for horizontal accuracy) and
Auto Level (for vertical accuracy) shall be carried out to establish the fundamental
horizontal and vertical accuracy. A minimum of 25 check points, or check points
once every 4 km should be established, and these should be strictly different from
any geo-referencing or control network points.

3. The following are the set of deliverables which should be submitted after
completion of survey: (a) Raw DGPS data for the entire highway length and
adjoining areas of interest (b) Point cloud data/ Data of points captured for the
entire highway length and adjoining areas of interest (c) Topographic map of scale
1:1000 of the entire highway length and adjoining areas of interest (d) Contour map
of 50 cm of entire highway length and adjoining areas of interest (e) Cross section
of the highway at every 1 m in *.dwg format.

4. For land based surveys, Mobile LiDAR (Light Detection and Ranging) or
equivalent technology that can meet above requirements shall be adopted. For aerial
based surveys, Aerial Mobile LiDAR (Light Detection and Ranging) or equivalent
technology that can meet above requirements shall be adopted. In shadow areas
such as invert levels below culverts, where LiDAR or equivalent technologies
cannot survey accurately, traditional methods of Total Station/ Auto Level shall be
used to complete the study.

5. In case of mobile LiDAR or equivalent technology, 360 degree panoramic images


of the entire highway length and adjoining areas of interest shall be submitted. In
case of aerial LiDAR or equivalent technology, ortho-images of the entire highway
length and adjoining areas of interest shall be submitted.

6. The detailed field surveys would essentially include the following activities:
i. Topographic Surveys along the Existing Right of Way (ROW): Carrying
out topographic survey using LiDAR or equivalent technology along the
existing road and realignments, wherever required and properly
referencing the same with reference pillars fixed on either side of the centre-
line at safe places within the ROW
ii. The detailed field surveys would essentially include the topographic
surveys along the proposed location of bridge and alignment of approach
road.

iii. The detailed topographic surveys should be carried out along the
approach roads alignment and location of bridge approved by Chief
Engineer, Highways

55
vi.. Collection/ Extraction of details for all features such as structures (bridges,
culverts etc.) utilities, existing roads, electric and telephone installations (both
O/H as well as underground), huts, buildings, fencing and trees (with girth
greater than 0.3metre) oil and gas lines etc. falling within the extent of survey.

4. The width of survey corridor will generally be as given under:

i. The width of the survey corridor should take into account the layout of the
existing alignment including the extent of embankment and cut slopes and the
general ground profile. While carrying out the field surveys, the widening
scheme (i.e. right, left or symmetrical to the centre line of the existing
carriageway) should be taken into consideration so that the topographic surveys
cover sufficient width beyond the centre line of the proposed divided
carriageway. Normally the surveys should extend a minimum of 30 m beyond
either side of the centre line of the proposed divided carriageway or land
boundary whichever is more.

ii. In case the reconnaissance survey reveals the need for bypassing the
congested locations, the traverse lines would be run along the possible
alignments in order to identify and select the most suitable alignment for the
bypass. The detailed topographic surveys should be carried out along the bypass
alignment approved by <Agency>. At locations where grade separated
intersections could be the obvious choice, the survey area will be suitably
increased. Field notes of the survey should be maintained which would also
provide information about traffic, soil, drainage etc.

iii. The width of the surveyed corridor will be widened appropriately where
developments and / or encroachments have resulted in a requirement for
adjustment in the alignment, or where it is felt that the existing alignment can
be improved upon through minor adjustments.

iv Where existing roads cross the alignments, the survey will extend a
minimum of100 m either side of the road centre line and will be of sufficient
width to allow improvements, including at grade intersection to be designed.

5. The surveyed alignment shall be transferred on to the ground as under:

i. Reference Pillar and Bench Mark / Reference pillar of size 15 cm X 15 cm


X 45cm shall be cast in RCC of grade M 15 with a nail fixed in the centre
of the top surface. The reference pillar shall be embedded in concrete upto
a depth of 30cm with CC M10 (5 cm wide all around). The balance 15 cm
above ground shall be painted yellow. The spacing shall be 250m apart,
incase Bench Mark Pillar coincides with Reference Pillar, only one of the
two need be provided.

57
ii. Establishing Bench marks at site connected to GTS Bench marks at a
interval of250 metres on Bench mark pillar made of RCC as
mentioned above with RL and BM No. marked on it with red paint.

iii. Boundary Pillars- Wherever there is a proposal of realignment of


the existing Highway and/or construction of New Bypasses, Consultant
shall fix boundary pillars along the proposed alignment on the
extreme boundary on either side of the project Highway at 50 m interval.

4.11.2.1 Longitudinal and Cross-Sections

The topographic surveys for longitudinal and cross-sections shall cover


the following:
i. Longitudinal section levels along final centre line at every 1 m
interval, at the locations of curve points, small streams, and
intersections and at the locations of change in elevation.

ii. Cross sections at every 1 m interval in full extent of survey covering


sufficient number of spot levels on existing carriageway and adjacent
ground for profile correction course and earth work calculations. Cross
sections shall be taken at closer interval at curves.

iii. Longitudinal section for cross roads for length adequate for design
and quantity estimation purposes.

iv. Longitudinal and cross sections for major and minor streams shall
cover Cross section of the channel at the site of proposed crossing and
few cross sections at suitable distance both upstream and downstream,
bed level upto top of banks and ground levels to a sufficient distance
beyond the edges of channel, nature of existing surface soil in bed,
banks & approaches, longitudinal section of channel showing site of
bridge etc. These shall be as per recommendations contained in IRC
Special Publication No. 13 (Guidelines for the Design of Small Bridges
and Culverts) and provisions of IRC:5 (Standard Specifications &
Code of Practice for Road Bridges, Section 1 General Features of
Design).

At feasibility study stage cross sections at 50m interval may be taken.

4.11.2.2 Details of utility Services and Other Physical Features


1. The Consultants shall collect details of all important physical features along
the alignment. These features affect the project proposals and should
normally include buildings and structures, monuments, burial grounds,
cremation grounds, places of worship, railway lines, stream / river / canal,
water mains, severs, gas/oil pipes, crossings, trees, plantations, utility services
such as electric, and telephone lines (O/H & U/G) and poles, optical fibre
cables (OFC) etc. The survey would cover the entire right-of-way of the road
on the adequate allowance for possible shifting of the central lines at some of
the intersections locations.

57
2. Consultant shall also map out sub-surface utilities. The following criteria shall
be met by the process of sub-surface utility mapping: (a) Coverage and
mapping of all sub-surface utilities within project RoW, especially those under
additional carriageway width (b) Accurate mapping and resolution of all sub-
surface utilities up to a depth of 4 m (c) Differentiation between sub-surface
utilities such as live electric cables, metallic utilities and other utilities (d) Sub-
surface utilities radargrams further processed into utility maps in formats such
as PDF, JPEG and AutoCAD. To meet the accuracy levels, consultant shall
use Ground Penetrating Radar, Induction Locator or equivalent technologies.

3. The information collected during reconnaissance and field surveys shall be


shown on a strip plan so that the proposed improvements can be appreciated and
the extent of land acquisition with L.A schedule, utility removals of each type
etc. assessed and suitable actions can be initiated. Separate strip plan for each
of the services involved shall be prepared for submission to the concerned
agency.

4.11.3. Road and Pavement Investigations


The Consultants shall carry out detailed field studies in respect of road
and pavement. The data collected through road inventory and pavement
investigations should be sufficient to meet the input requirements of HDM-IV.

4.11.3.1 Road Inventory Surveys


1. Detailed road inventory surveys shall be carried out to collect details
of all existing road and pavement features along the existing road
sections. The inventory data shall include but not limited to the following:
i. Terrain (flat, rolling, mountainous);
ii. Land-use (agricultural, commercial, forest, residential etc ) @
every kilometer;
iii. Carriageway width, surfacing type @ every 500m and every
change of feature whichever is earlier;
iv. Shoulder surfacing type and width @ every 500m and every
change of feature whichever is earlier;
v. Sub-grade / local soil type (textural classification) @ every 500m
and every change of feature whichever is earlier;
vi. Horizontal curve; vertical curve
vii. Road intersection type and details, at every occurrence;
viii. Retaining structures and details, at every occurrence;
ix. Location of water bodies (lakes and reservoirs), at every occurrence;
x. Height of embankment or depth of cut @ every 200m and every
change of feature whichever is earlier.

58
xi. Land width i.e. ROW
xii. Culverts, bridges and other structures (type, size, span arrangement and
location)
xiii. Roadside arboriculture
xiv. Existing utility services on either side within ROW.
xv. General drainage conditions
xvi. Design speed of existing road

2. The data should be collected in sufficient detail. The data should be compiled
and presented in tabular as well as graphical form. The inventory data would
be stored in computer files using simple utility packages, such as EXCEL.

4.11.3.2 Pavement Investigation

1. Pavement Composition
i. The data concerning the pavement composition may be already
available with the PWD. However, the consultants shall make trial pits
to ascertain the pavement composition. The test pit interval will be
as per Para 4 below.
ii. For each test pit, the following information shall be recorded:
test pit reference (Identification number, location):
pavement composition (material type and thickness); and
subgrade type (textural classification) and condition (dry, wet)
2. Road and Pavement Condition Surveys
i. Detailed field studies shall be carried out to collect road and
pavement surface conditions. The data should generally cover:
pavement condition (surface distress type and extent);
shoulder condition;
embankment condition; and
drainage condition

Pavement Condition
cracking (narrow and wide cracking), % of pavement
area affected;
raveling, % of pavement area affected;
potholing, % of pavement area affected;
edge break, length (m); and,
rut depth, mm

Shoulder Condition
Paved: Same as for pavement
Unpaved: material loss, rut depth and corrugation,
Edge drop, mm.

59
Embankment Condition
general condition; and
extent of slope erosion

ii. The objective of the road and pavement condition surveys shall be to
identify defects and sections with similar characteristics. All defects
shall be systematically referenced, recorded and quantified for the
purpose of determining the mode of rehabilitation.

iii. The pavement condition surveys shall be carried out using visual means.
Supplemented by actual measurements and in accordance with the
widely accepted methodology (AASHTO, IRC, OECD, TRL and World
Bank Publications) adapted to meet the study requirements. The
measurement of rut depth would be made using standard straight
edges.

iv. The shoulder and embankment conditions shall be evaluated by


visual means and the existence of distress modes (cuts, erosion marks,
failure, drops) and extent (none, moderate, frequent and very frequent)
of such distress manifestations would be recorded.

v. For sections with severe distresses, additional investigations


as appropriate shall be carried out to determine the cause of such
distresses.

vi. Middle 200m could be considered as representative sample for each


one km. of road and incase all other things are considered similar.

Drainage Condition
General condition
Connectivity of drainage turnouts into the natural topography
Condition in cut sections
Condition at high embankments

The data obtained from the condition surveys should be analysed and the
road segments of more or less equal performance may be identified
using the criteria given in IRC: 81-1997.
3. Pavement Roughness
i. The roughness surveys shall be carried out using Bump Integrator
or similar instrument. The methodology for the surveys shall be as per
the widely used standard practices. The calibration of the instrument
shall be done as per the procedure given in the World Banks Technical
Publications and duly got authenticated by established
laboratory/institution acceptable to the client

ii. The surveys shall be carried out along the outer wheel paths. The
surveys shall cover a minimum of two runs along the wheel
paths for each directions.

60
iii. The results of the survey shall be expressed in terms of BI and IRI and shall
be presented in tabular and graphical forms. The processed data shall be
analysed using the cumulative difference approach to identify road
segments homogenous with respect to surface roughness.

5. Pavement Structural Strength

i. The Consultants shall carry out structural strength surveys for existing
pavements using Benkelman Beam Deflection technique in accordance
with the CGRA procedure given in IRC:81-1997 (Guidelines for
Strengthening of Flexible Road Pavements Using Benkelman Beam Deflection
Technique).
ii. It is suggested that the deflection surveys may be carried out as per the
scheme given below:
mainline testing; and,
control section testing.
iii. The deflection tests for the mainline shall be carried out at every 500 m
along the road sections covered under the study. The control section testing
shall involve carrying out deflection testing for each 100 m long
homogenous road segment along the road sections. The selection of
homogenous segment shall be based on the data derived from pavement
condition surveys. The total length of such homogenous segments shall not be
less than 100 m per kilometre. The deflection measurements for the control
section testing should be at an interval of not more than 10 m.
iv. Test pits shall be dug at every 500 m and also along each homogeneous
road segment to obtain pavement composition details (pavement course,
material type and thickness) so as to be able to study if a correlation exists
between deflection and composition. If so, the relationship may be used while
working out the overlay thickness for the existing pavement.
v. Benkelman Beam Deflection surveys may not be carried out for severely
distressed sections of the road warranting reconstruction. The Consultants,
immediately upon the award of the contract, shall submit to Chief Engineer,
Highways the scheme describing the testing schedule including the interval.
The testing scheme shall be supported by data from detailed reconnaissance
surveys.

vi. In case, the Consultants wish to use any acceptable method(s) other than
Benkelman Beam deflection technique for the evaluation of pavement
strength, viz. Falling weight deflectometer method etc. details of such
methods or innovative features for deflection testing using Benkelman Beam
technique along with the methodology for data analysis, interpretation
and the use of such data for pavement overlay design purposes using IRC or
any other widely used practices, such as AASHTO guidelines, should be got
approved by Chief Engineer, Highways The sources of such methods
should be properly referenced.

61
4.11.3.3 Subgrade Characteristics and Strength

1. Based on the data derived from condition (surface condition, roughness)


and structural strength surveys, the project road section should be divided into
segments homogenous with respect to pavement condition and strength. The
delineation of segments homogenous with respect to roughness and strength
should be done using the cumulative difference approach (AASHTO, 1993).
2. The data on soil classification and mechanical characteristics for soils along
the existing alignments may already be available with the PWD. The testing
scheme is, therefore, proposed as given under:

i. For the widening (2/- Laning) of existing road within the ROW,
the Consultants shall test at least three sub-grade soil samples for
each homogenous road segment or three samples for each
soil type encountered, whichever is more.
ii. For the roads along new alignments, the test pits for sub grade soil
shall be @5km or for each soil type, whichever is more. A minimum of
three samples should be tested corresponding to each homogenous
segment.

3. The testing for subgrade soil shall include:


i. in-situ density and moisture content at each test pit
ii. Field CBR using DCP at each test pit
iii. Characterization (grain size and Atterberg limits) at each test pit and,
iv. Laboratory moisture-density characteristics (modified
AASHTO compaction)
v. Laboratory CBR (unsoaked and 4-day soak compacted at three
energy levels) and swell.
4. For problematic soils, the testing shall be more rigorous. The characteristics
with regard to permeability and consolidation shall also be determined for
these soils. The frequency of sampling and testing of these soils shall be
finalised in consultation with the Chief Engineer, Highways officers after the
problematic soil types are identified along the road sections.
5. The laboratory for testing of material should be got approved from Chief
Engineer, Highways before start of work.

4.11.4 Investigations for Bridges and Structure

4.11.4.1 Inventory of Bridges, Culverts and Structures


The Consultants shall make an inventory of all the structures (bridges,
viaducts, ROBs,/RUB and other grade separated structures, culverts, etc.)
along the road under the project. The inventory for the bridges, viaducts and
ROBs shall include the parameters required as per the guidelines of IRC-
SP:35. The inventory of culverts shall be presented in a tabular form
covering relevant physical and hydraulic parameters.

4.11.4.2 Hydraulic and Hydrological Investigations


62
1. The hydrological and hydraulic studies shall be carried out in accordance
with IRC Special Publication No. 13 (Guidelines for the Design of Small
Bridges and Culverts) and IRC:5 (Standard Specifications & Code of
Practice for Road Bridges, Section I General Feature of Design). These
investigations shall be carried out for all existing drainage structures along the
road sections under the study.
2. The consultant shall also collect information on observed maximum depth
of scour.
3. In respect of major bridges, history of hydraulic functioning of existing
bridge, if any, under flood situation, general direction of river course through
structure, afflux, extent and magnitude of flood, effect of backwater, if any,
aggradation/degradation of bed, evidence of scour etc. shall be used to
augment the available hydrological data. The presence of flood
control/irrigation structures, if affecting the hydraulic characteristics like
causing obliquity, concentration of flow, scour, silting of bed, change in flow
levels, bed levels etc. shall be studied and considered in design of bridges. The
details of any future planned work that may affect the river hydraulics shall be
studied and considered.
4. The Consultants shall make a desk study of available data
on topography(topographic maps, stereoscopic aerial photography), storm
duration, rainfall statistics, top soil characteristics, vegetation cover etc. so as
to assess the catchment areas and hydraulic parameters for all existing and
proposed drainage provisions. The findings of the desk study would be further
supplemented and augmented by a reconnaissance along the area. All-
important hydrological features shall be noted during this field
reconnaissance.
5. The Consultants shall collect information on high flood level
(HFL),low water levels (LWL), high tide level (HTL),low tide level (LTL)
where applicable, discharge velocity etc. from available past records, local
inquiries and visible signs, if any, on the structural components and
embankments. Local inquiries shall also be made with regard to the road
sections getting overtopped during heavy rains.
6. Conducting Model studies for bridges is not covered in the scope of
consultancy services. If Model study is envisaged for any bridge,
requirement of the same shall be spelt out in the RPF documents
separately indicating scope and time frame of such study. Salient features of
the scope of services to be included for model study are given in the
supplement- II Terms of Reference.

4.11.4.3 Condition Surveys for Bridges, Culverts and Structures

1. The Consultants shall thoroughly inspect the existing structures and shall
prepare a report about their condition including all the parameters given in the
Inspection pro-forma of IRC-SP; 35. The condition and structural assessment
survey of the bridges / culverts / structures shall be carried out by senior
experts of the Consultants.

63
2. For the bridges identified to be in a distressed condition based upon the
visual condition survey, supplementary testing shall be carried out as per IRC-
SP:35 and IRC-SP:40. Selection of tests may be made based on the specific
requirement of the structure.
3. The assessment of the load carrying capacity or rating of existing bridges shall
be carried out under one or more of the following scenarios:
i. when the design live load is less than that of the statutory
commercial vehicle plying or likely to ply on bridge;
ii. if during the condition assessment survey and supplementary testing
the bridge is found to indicate distress of serious nature leading to
doubt about structural and / or functional adequacy, and
iii. Design live load is not known nor are the records and drawings
available

4. The evaluation of the load carrying capacity of the bridge shall be carried
out as per IRC-SP:37 (Guidelines for Evaluation of Load Carrying Capacity
of Bridges). The analytical and correlation method shall be used for the
evaluation of the load carrying capacity as far as possible. When it is not
possible to determine the load carrying capacity of the bridge using analytical
and correlation method, the same shall be carried out using load
testing. The consultant has to exhaust all other methods of evaluation of
strength of bridges before recommending to take up load testing of bridges.
Road closure for testing if unavoidable shall be arranged by Chief Engineer,
Highways for limited duration say 12 hours or so.
5. Consultant shall carryout necessary surveys and investigations to establish
the remaining service life of each retainable bridge or structure with and
without the proposed strengthening and rehabilitation according to acceptable
international practice in this regard.

4.11.4.4 Geo-technical Investigations and Sub-Soil Exploration

1. The Consultants shall carry out geo-technical investigations and sub-


surface explorations for the proposed Bridges / Road over bridges/ tunnels/
viaducts/ interchanges etc., along high embankments and any other location as
necessary for proper design of the works and conduct all relevant laboratory
and field tests on soil and rock samples. The minimum scope of geo-technical
investigations for bridge and structures shall be as under:

64
S.No. Description Location of Boring
1 Overall length = 6 30 m One abutment location and One abutment
location and at least one intermediate location
between abutments for structures having more
than one span
2 Overall length = 30 60 m One abutment location and at least one
intermediate location between abutments for
structures having more than one span.
3 Overall length >60 m Each abutment and each pier locations.

2. The deviation(s), if any, by the Consultants from the scheme presented


above should be approved by Chief Engineer, Highways, Mizoram PWD

3. However, where a study of geo-technical reports and information available


from adjacent crossings over the same waterway (existing highway and
railway bridges) indicates that subsurface variability is such that boring at the
suggested spacing will be insufficient to adequately define the conditions for
design purposes, the Consultants shall review and finalise the bore hole
locations in consultation with the Chief Engineer, Highways, Mizoram PWD
officers.
4. Geotechnical Investigations and Sub soil Explorations hall be carried out
to determine the nature and properties of existing strata in bed, banks
and approaches with trial pits and bore hole sections showing the levels,
nature and properties of various strata to a sufficient depth below the level
suitable for foundations, safe intensity of pressure on the foundation strata,
proneness of site to artesian conditions, seismic disturbance and other
engineering properties of soil etc. Geotechnical investigation and Sub-soil
Exploration will be done as per IRC 78.
5. The scheme for the borings locations and the depth of boring shall be prepared
by the Consultants and submitted to Chief Engineer, Highways, Mizoram
PWD for approval. These may be finalised in consultation with Chief
Engineer, Highways, Mizoram PWD.

6. The sub-soil exploration and testing should be carried out through


the Geotechnical Consultants empanelled by MORT&H The soil testing
reports shall be in the format prescribed in relevant IRC Codes.
7. For the approach road pavement, bore holes at each major change in
pavement condition or in deflection readings or at 2 km intervals whichever is
less shall be carried out to a depth of at least 2 m below embankment base or
to rock level and are to be fully logged. Appropriate tests to be carried out on
samples collected from these bore holes to determine the suitability of various
materials for use in widening of embankments or in parts of new pavement
structure.

65
4.11.5. Material Investigations

1. The Consultants shall identify sources (including use of fly-ash/ slag), quarry
sites and borrow areas, undertake field and laboratory testing of the
materials to determine their suitability for various components of the work
and establish quality and quantity of various construction materials and
recommend their use on the basis of techno-economic principles. The
Consultants shall prepare mass haul diagram for haulage purposes giving
quarry charts indicating the location of selected borrow areas, quarries and
the respective estimated quantities.
Environment friendly materials

As per MORTH circular No. RW /NH-33044/53/2013-S&R(R) dated 20th


November, 2013, alternative pavement materials and technologies for road
construction shall be assessed and compared in the design stage. The
alternative resulting in substantial reduction in GHG emission and with least
life cycle cost shall be recommended for implementation.

Technical and economic feasibility of using industrial byproducts, recyclable


and waste materials shall be assessed depending on their availability in the
concerned region.

2. It is to be ensured that no material shall be used from the right-of-way except


by way of leveling the ground as required from the construction point of view,
or for landscaping and planting of trees etc. or from the cutting of existing
ground for obtaining the required formation levels.
3. Environmental restrictions, if any, and feasibility of availability of these
sites to prospective civil works contractors, should be duly taken into
account while selecting new quarry locations.
4. The Consultants shall make suitable recommendations regarding making
the borrow and quarry areas after the exploitation of materials for construction
of works.
5. The Material Investigation aspect shall include preparation and testing
of bituminous mixes for various layers and concrete mixes of different design
mix grades using suitable materials (binders, aggregates, sand filler etc.) as
identified during Material Investigation to conform to latest MoRT&H
specification.

4.12 Detailed Design of Road and Pavements, Bridges, Structures


4.12.1. General
1. The Consultants are to carryout detailed designs and prepare working
drawings for the following:
i. High speed highway with divided carriageway configuration
complete in all respects with service roads at appropriate locations;
ii. Design of pavement for the additional lanes and overlay for
the existing road, paved shoulders, medians, verges;

66
iii. Bridges, viaduct/subways and other grade separated structures
including
ROBs/RUBs etc.
iv. At-grade and grade-separated intersections, interchanges (if required);
v. ROB for railway crossings as per the requirement and the
standards of the Indian Railways; and,
vi. Prepare ali gnment plans, longitudinal sections and cross-sections
@ 50mintervals;
vii. Designs for road furniture and road safety/traffic control features;
viii. Designs and drawings for service road/under passes/overpass /
cattle passes tree planting/fencing at locations where necessary /
required
ix.. Toll plazas and office-cum-residential complex for PIU (one for each
civil contract package)
x Short bypasses at congested locations
xi. Drainage design showing location of turnouts, out falling
structures, separate drawings sheet for each 5 km. stretch.
xii. Bridges and structures rehabilitation plan with design and drawings
xiii. Traffic amenities (Parking Areas, Weighing Station and Rest
Areas, etc.).
xiv Design of pavement for approach road
xv Design of river bank protection / training works. Innovative
type of structures with minimum joints, aesthetically, pleasing and
appropriate to the topography of the region shall be designed wherever
feasible.

4.12.2. Design Standards


1. The Consultants shall evolve Design Standards and material specifications
for the Study primarily based on IRC publications, MoRT&H Circulars
and relevant recommendations of the international standards for approval by
Chief Engineer, Highways, Mizoram PWD
2. The Design Standards evolved for the project shall cover all aspects of
detailed design including the design of geometric elements, pavement design,
bridges and structures, traffic safety and materials.

4.12.3. Geometric Design


1. The design of geometric elements shall, therefore, take into account the
essential requirements of such facilities.
2. Based on the data collected from reconnaissance and topographic surveys,
the sections with geometric deficiencies, if any, should be identified and
suitable measures for improvement should be suggested for implementation.
3. The data on accident statistics should be compiled and reported showing
accident type and frequency so that black spots are identified along the
project road section. The possible causes (such as poor geometric features,
pavement condition etc.) of accidents should be investigated into and suitable
cost-effective remedial measures suggested for implementation.
4. The detailed design for geometric elements shall cover, but not be limited to
the following major aspects:

67
i. horizontal alignment;
ii. longitudinal profile;
iii. cross-sectional elements, including refuge lane (50m) at every 2kms.
iv. iv. junctions, intersections and interchanges;
v. bypasses; and,
vi. service roads as and when require i.e built up area..
5. The alignment design shall be verified for available sight distances as per
the standard norms. The provision of appropriate markings and signs shall be
made wherever the existing site conditions do not permit the adherence to the
sight distance requirements as per the standard norms.
6. The consultants shall make detailed analysis of traffic flow and level of
service for the existing road and workout the traffic flow capacity for the
improved project road. The analysis should clearly establish the widening
requirements with respect to the different horizon periods taking into account
special problems such as road segments with isolated steep gradients.
7. In the case of closely spaced cross roads the Consultant shall examine
different options such as, providing grade separated structure for some of them
with a view to reduce number of at-grade crossings, services roads connecting
the cross-roads and closing access from some of the intersections and prepare
and furnish appropriate proposals for this purpose keeping in view the cost of
improvement, impact on traffic movement and accessibility to cross
roads. The detailed drawings and cost estimate should include the provisions
for realignments of the existing cross roads to allow such arrangements.
8. The Consultant shall also prepare design of grade separated
pedestrian crossings (viaducts) for large cross traffic of pedestrians and / or
animals.
9. The Consultant shall also prepare details for at-grade junctions, which may
be adopted as alternative to the grade separated structures. The geometric
design of interchanges shall take into account the site conditions, turning
movement characteristics, level of service, overall economy and operational
safety.
10. The Consultants shall prepare design and other details in respect of the
parallel service roads in urbanized locations and other locations to cater
to the local traffic, their effect of the viability of the project on commercial
basis if service roads are constructed as part of the project and the implications
of not providing the service roads.
11. The consultant shall prepare complete road and pavement design
including drainage for new bypass option identified around congested town en-
route.

4.12.4. Pavement Design


1. The detailed design of pavement shall involve:
i. strengthening of existing road pavement and design of the new
pavement if any, if the findings of the traffic studies and life-cycle
costing analysis confirm the requirement for widening of the road
beyond 2lane undivided carriageway standard;;

68
ii. pavement design for bypasses; and,
iii. design of shoulders.
2. The design of pavement shall primarily be based on IRC publications.
3. The design of pavement shall be rigorous and shall make use of the latest
Indian and International practices. The design alternatives shall include both
rigid and flexible design options. The most appropriate design, option
shall be established on life-cycle costing and techno-economic
consideration.
4. For the design of pavement, each set of design input shall be decided on the
basis of rigorous testing and evaluation of its suitability and relevance in
respect of in- service performance of the pavement. The design methodology
shall accompany the design proposals and shall clearly bring out the basic
assumptions, values of the various design inputs, rationale behind the selection
of the design inputs and the criteria for checking and control during the
implementation of works. In other words, the design of pavement structure
should take due account of the type, characteristics of materials used in the
respective courses, variability of their properties and also the reliability of
traffic predictions. Furthermore, the methodology adopted for the design of
pavement shall be complete with flowcharts indicating the various steps in
the design process, their interaction with one another and the input parameter
required at each step.
5. For the design of overlays for the existing 2-lane pavement, the
strengthening requirement shall duly take into account the strength of the
existing pavement vis- -vis the remaining life. The overlay thickness
requirements shall be worked out for each road segment homogenous with
respect to condition, strength and sub- grade characteristics. The rehabilitation
provisions should also include the provision of regulating layer. For existing
pavement with acceptable levels of cracking, provision of a crack inhibiting
layer should also be included.
6. Latest techniques of pavement strengthening like provision of geo-synthetics
and cold/hot pavement recycling should be duly considered by the
consultant for achieving economy.
7. The paved shoulders shall be designed as integral part of the pavement for
the main carriageway. The design requirements for the carriageway pavement
shall, therefore, be applicable for the design of shoulder pavements. The
design of granular shoulder should take into account the drainage
considerations besides the structural requirements.
8. The pavement design task shall also cover working out the maintenance
and strengthening requirements and periodicity and timing of such treatments.

4.12.5. Design of Embankments

1. The embankments design should provide for maximum utilization of


locally available materials consistent with economy. Use of fly ash wherever
available with in economical leads must be considered. In accordance with
Government instructions, use of fly ash within 100 km from Thermal Power
Stations is mandatory.

69
2. The Consultants shall carry out detailed analysis and design for all
embankments of height greater that 6 m based on relevant IRC publications.
3. The design of embankments should include the requirements for protection
works and traffic safety features.

4.12.6. Design of Bridges and Structures


1. The data collected and investigation results shall be analysed to determine
the following:
i. HFL
ii. LWL
iii. LBL
iv. Erodibility of bed/scour level
v. Design discharge
vi. Linear waterway and effective linear waterway
vii. Likely foundation depth
viii. Safe bearing capacity
ix. Engineering properties of sub soil
x. Artesian conditions
xi. Settlement characteristics
xii. Vertical clearance
xiii. Horizontal clearance
xiv. Free board for approach road
xv. Severity of environment with reference to corrosion
xvi. Data pertaining to seismic and wind load
xvii. Requirement of model study etc.

2. The Consultant shall prepare General Arrangement Drawing (GAD)


and Alignment Plan showing the salient features of the bridges and
structures proposed to be constructed / reconstructed along the road sections
covered under the Study. These salient features such as alignment, overall
length, span arrangement, cross section, deck level, founding level, type of
bridge components(superstructure, substructure, foundations, bearings,
expansion joint, return walls etc.) shall be finalized based upon hydraulic
and geo-technical studies, cost effectiveness and ease of construction. The
GAD shall be supplemented by Preliminary designs. In respect of span
arrangement and type of bridge a few alternatives with cost-benefit
implications should be submitted to

70
enable Chief Engineer, Highways, Mizoram PWD to approve the best
alternative. After approval of alignment and GAD the Consultant shall
prepare detailed design as per IRC codes guidelines and working
drawings for all components of bridges and structures.

3. The location of all at-grade level crossings shall be identified falling across
the existing level crossings for providing ROB at these locations. The
Consultants shall prepare preliminary GAD for necessary construction
separately to the Client. The Consultant shall pursue the Indian Railways
Authorities or/and any statutory authority of State/Central Government for
approval of the GAD from concerned Authorities.

4. GAD for bridges/structures across irrigation/water way channels shall


be got approved from the concerned Irrigation/Water way Authorities.
Subsequent to approval of GAD and alignment plan by Chief Engineer,
Highways, Mizoram PWD the Consultants shall prepare detailed design as
per IRC codes/guidelines for all components of the bridges and structures.

5. Subsequent to the approval of the GAD and Alignment Plan by Chief


Engineer, Highways, Mizoram PWD and Railways, the Consultant shall
prepare detailed design as per IRC and Railways guidelines and working
drawings for all components of the bridges and structures. The Consultant
shall furnish the design and working drawings for suitable protection works
and/or river training works wherever required.

6. Dismantling/ reconstruction of existing structures shall be avoided as far


as possible except where considered essential in view of their poor structural
conditions/ inadequacy of the provisions etc.

7. The existing structures having inadequate carriageway width shall


be widened/reconstructed in pat or fully as per the latest MoRT&H guidelines.
The Consultant shall furnish the detailed design and working drawings for
carrying out the above improvements.

8. Suitable repair / rehabilitation measures shall be suggested in respect of


the existing structures as per IRC-SP:40 along with their specifications,
drawings and cost estimate in the form of a report. The rehabilitation or
reconstruction of the structures shall be suggested based on broad
guidelines for rehabilitation and strengthening of existing bridges contained
in IRC-SP:35 and IRC-SP:40.
9. Subsequent to the approval of the GAD and the alignment plan by Chief
Engineer, Highways, Mizoram PWD detailed design shall also be carried out
for the proposed underpasses, overpasses and interchanges.
10. The Consultants shall also carry out the design and make
suitable recommendations for protection works for bridges and drainage
structures.
11. In case land available is not adequate for embankment slope, suitable
design for RCC retaining wall shall be furnished. However, RES wall
may also be considered depending upon techno-economic suitability
to be approved by Chief Engineer, Highways, Mizoram PWD
71
4.12.7. Drainage System

1. The requirement of roadside drainage system and the integration of the same
with proposed cross-drainage system shall be worked out for the entire length
of the project road section.
2. In addition to the roadside drainage system, the Consultants shall design
the special drainage provisions for sections with super-elevated
carriageways, high
embankments and for road segments passing through cuts. The
drainage provisions shall also be worked out for road segments passing
through urban areas.
3. The designed drainage system should show locations of turnouts/outfall
points with details of outfall structures fitting into natural contours. A separate
drawing sheet covering every 5 km. stretch of road shall be prepared.

4.12.8. Traffic Safety Features, Road Furniture and Road Markings


The Consultants shall design suitable traffic safety features and road furniture
including traffic signals, signs, markings, overhead sign boards, crash barriers,
delineators etc. The locations of these features shall be given in the reports
and also shown in the drawings.

4.12.9. Arboriculture and Landscaping


The Consultants shall work out appropriate plan for planting of trees
(specifying type of plantation), horticulture, floriculture on the surplus land
of the right-of way with a view to beautify the highway and making the
environment along the highway pleasing. The existing trees / plants shall be
retained to the extent possible. The Transplantation of trees shall also be
proposed wherever feasible.

4.12.10. Toll Plaza


1. The Consultants shall identify the possible toll plaza location(s) based on the
data and information derived from the traffic studies and a study of the
existing physical features including the availability of land. The location of
the plaza should keep in view that the project road is to be developed as a
partially access controlled highway facility and it is required to collect toll
on rational basis from as much of the vehicular traffic as possible consistent
with economy of collection and operations. The location of the toll plaza
should be finalised in consultation with Chief Engineer, Highways, Mizoram
PWD
2. Toll Plaza shall be designed as per IRC 84.

4.12.11. Weighing Station, Parking Areas and Rest Areas


The consultant shall select suitable sites for weighing stations, parking areas
and rest areas and prepare suitable separate designs in this regard. The common
facilities like petrol pump, first-aid medical facilities, police office, restaurant,
vehicle parking etc. should be included in the general layout for planning. For
petrol pump, the guidelines issued by OISD of Ministry of Petroleum shall
be followed. The
72
facilities should be planned to be at approximately 50 km interval. Atleast
each facility (1 no.) is foreseen to be provided for this project stretch. Weighing
stations can be located near toll plazas so that overloaded vehicles can be
easily identified and suitably penalized and unloaded before being allowed to
proceed further. The type of weighing system suitable for the project shall be
brought out in the report giving merits of each type of the state-of-the art
and basis of recommendations for the chosen system.

4.12.12 Office-cum-Residential Complex for PIU-Deleted


4.12.13 Miscellaneous Works
1. The Consultants shall make suitable designs and layout for miscellaneous
works including rest areas, bus bays, vehicle parking areas, telecommunication
facilities etc. wherever appropriate.
2. The Consultants shall prepare the detailed scheme and lay out plan for the
works mentioned in Para 1.
3. The Consultants shall prepare detailed plan for the traffic management and
safety during the construction period.
4.13 Environment and Social Impact Assessment
The consultant shall under take the detailed environmental and social impact
assessment in accordance with the standard set by the Government of India for
projects proposed to be funded by MORT&H/NHAI. In respect of projects
proposed to be funded by ADB loan assistance, Environmental Assessment
Requirements, Environmental Guidelines for selected infrastructure projects, 1993 of
Asian Development Bank shall be followed. Similarly, for projects proposed to be
funded by World Bank loan assistance, World Bank Guidelines shall be followed.
4.13.1 Environmental Impact Assessment
Environment impact assessment or initial environment examination be carried out in
accordance with ADBs Environmental Assessment Requirements of
ADB 1998guidelines for selected infrastructure projects 1993 as amended from
time to time /World Bank Guidelines / Government of India Guidelines, as applicable
1. The consultant should carry out the preliminary environmental screening to
assess the direct and induced impacts due to the project.
2. The consultant shall ensure to document baseline conditions relevant to
the project with the objective to establish the benchmarks.
3. The consultant shall assess the potential significant impacts and identify
the mitigation measures to address these impacts adequately.
4. The consultant shall do the analysis of alternatives incorporating
environmental concerns. This should include with and without scenario and
modification incorporated in the proposed project due to environment
considerations.
5. The consultant shall give special attention to the environmental
enhancement measures in the project for the following:

73
(a) Cultural property enhancement along the highways
(b) Bus bays and bus shelters including a review of their location,
(c) Highway side landscape and enhancement of the road junctions,
(d) Enhancement of highway side water bodies, and
(e) Redevelopment of the borrow areas located on public land.
6. The consultant shall prepare the bill-of-quantities (BOQ) and
technical specifications for all items of work in such a way that these may be
readily integrated to the construction contracts.
7. The consultant shall establish a suitable monitoring network with regard to
air, water and noise pollution. The consultant will also provide additional
inputs in the areas of performance indicators and monitoring mechanisms for
environmental components during construction and operational phase of the
project.
8. The consultant shall provide the cost of mitigation measures and ensure
that environmental related staffing, training and institutional
requirements are budgeted in project cost.
9. The consultant shall prepare the application forms and obtain forestry
and environmental clearances from the respective authorities including the
SPCBs and the MOEF on behalf of Chief Engineer, Highways,
Mizoram PWD The consultants will make presentation, if required, in
defending the project to the MOEF Infrastructure Committee.
10. The consultant shall identify and plan for plantation and Transplantation of
the suitable trees along the existing highway in accordance with IRC
guidelines.
11. The consultant shall assist in providing appropriate input in preparation
of relevant environment and social sections of BPIP.

4.13.2 Social Assessment


1 The consultant would conduct base line socio-economic and census survey
to assess the impacts on the people, properties and loss of livelihood. The
socioeconomic survey will establish the benchmark for monitoring of R&R
activities. A social assessment is conducted for the entire project to identify
mechanisms to improve project designs to meet the needs of
different stakeholders. A summary of stakeholder discussions, issue raised and
how the project design was developed to meet stakeholders need would be
prepared.
2 The consultant shall prepare Land Acquisition Plan and assist Chief
Engineer, Highways, Mizoram PWD in acquisition of land under various
Acts.
4.13.2.3 The consultant would prepare Resettlement and Rehabilitation Plan and
assess feasibility and effectiveness of income restoration strategies and
suitability and availability to relocation sites. The resettlement plan which
accounts for land acquisition and resettlement impacts would be based on a
25% socio-economic survey and 100 % census survey of project affected
people which provides the complete assessment of the number of affected
households and persons, including common property resources. All untitled
occupants are recorded at the initial stages and identify cards will be issued
to ensure there is no further influx of people
74
in to the project area. All consultations with affected persons (to include
list of participants) should be fully documented and records made available to
Chief Engineer, Highways, Mizoram PWD
Assessment on the impact of the project on the poor and vulnerable
groups along the project road corridor.
Based on the identified impacts, developing entitlement matrix for
the project affected people.
Assessment on social issues such as indigenous people,
gender, HIV/AIDS, labourers including child labour.
Implementation budgets, sources and timing of funding and
schedule of tasks.
Responsibility of tasks, institutional arrangements and personnel
for delivering entitlement and plans to build institutional
capacity.
Internal and external monitoring plans, key monitoring indicators
and grievance redress mechanism.
Incorporating any other suggestions of the Chief Engineer,
Highways, Mizoram PWD till the acceptance of the reports by the
Chief Engineer, Highways, Mizoram PWD

4.13.3 Reporting Requirements of EIA


The consultant would prepare the stand-alone reports as per the
requirement of the ADB/World Bank / Chief Engineer, Highways,
Mizoram PWD as applicable, with contents as per the following:
Executive Summary
Description of the Project
Environmental setting of the project.
Identification and categorization of the potential impacts (during pre-
construction, construction and operation periods).
Analysis of alternatives (this would include correlation amongst the
finally selected alternative alignment/routing and designs with the
avoidance and environmental management solutions).
The public consultation process.
Policy, legal and administrative framework. This would include
mechanisms at the states and national level for operational policies. This
would also include a description of the organizational and
implementation mechanism recommended for this project.
Typical plan or specific designs for all additional environmental
items as described in the scope of work.
Incorporating any other as per the suggestions of the ADB/ World
Bank / MORT&H Chief Engineer, Highways, Mizoram PWD till the
acceptance of the reports by the ADB/ World Bank / MORT&H/ Chief
Chief Engineer, Highways, Mizoram PWD , as applicable.
EMP Reports for Contract Package based on uniform methodology and
processes.The consultant will also ensure that the EMP has all the
elements for it to be a legal document. The EMP reports would include
the following:
Brief description of the project, proposed of the
EMP,commitiment on incorporating environmental consideration
in the design, construction and operation phase of the project and
institutional arrangements for implementing the EMP.
75
o A detailed EMP for construction and operational phases with
recourse to the mitigation measures for all adverse impacts.
o Detailed plans for highway-side tree plantation (as part
of the compensatory aforestation component).
o Environmental enhancement measure would be incorporated.
o Enhancement measures would include items described in the
scope of work and shall be complete with plans, designs, BOQ
and technical specifications.
o Environmental monitoring plans during and after construction
including scaling and measurement techniques for the
performance indicators selected for monitoring.
o The EMP should be amendable to be included in the contract
documents for the works.
o Incorporating any other as per the suggestions of the ADB/
World Bank Chief Engineer, Highways, Mizoram PWD, till
the acceptance of the reports by the ADB/ World Bank Chief
Engineer, Highways, Mizoram PWD as applicable.

4.13.4 Reporting requirements of RAP


Analysis on the resettlement plan be conducted based on ADBs Hand Book on
Resettlement, A Guide to Good practice 1998 as amended time to time/ World Bank
Guidelines / Government of India Guidelines, as applicable.

Executive summary
Description of project
Objectives of the project.
The need for Resettlement in the Project and evaluation of
measures to minimize resettlement.
Description and results of public consultation and plans
for continued participation of PAPs.
Definition of PAPs and the eligibility criteria.
Census and survey results-number affected, how are they
affected and what impacts will they experience.
Legal and entitlement policy framework-support principles
for different categories of impact.
Arrangements for monitoring and evaluation (internal and external)
Implementation schedule for resettlement which is linked to the
civil works contract
A matrix of scheduled activities linked to land acquisition procedures
to indicate clearly what steps and actions will be taken at different
stages and the time frame
The payment of compensation and resettlement during the
acquisition process
An itemized budget (replacement value for all assets) and unit costs
for different asset

76
5. Estimation of Quantities and Project Costs
1. The Consultants shall prepare detailed estimates for quantities
(considering designs and mass haul diagram) and project cost for the
entire project (civil packages wise), including the cost of environmental and
social safeguards proposed based on MoRT&Hs Standard Data Book and
market rate for the inputs. The estimation of quantities shall be based on
detailed design of various components of the projects. The estimation of
quantities and costs would have to be worked out separately for civil work
Package as defined in this TOR.
2. The Consultants shall make detailed analysis for computing the unit rates for
the different items of works. The unit rate analysis shall duly take into account
the various inputs and their basic rates, suggested location of plants and
respective lead distances for mechanized construction. The unit rate for each
item of works shall be worked out in terms of manpower, machinery and
materials.
3. The project cost estimates so prepared for Chief Engineer, Highways,
Mizoram PWD/ADB/WB projects are to be checked against rates for
similar on-going works in India under Chief Engineer, Highways,
Mizoram PWD / World Bank/ ADB financed road sector projects.

6. Viability and Financing Options

1. Project Road should be divided into the traffic homogenous links based on
the findings of the traffic studies. The homogenous links of the Project Road
should be further subdivided into sections based on physical features of road and
pavement, sub-grade and drainage characteristics etc. The economic and
commercial analysis shall be carried out separately for each traffic
homogenous link as well as for the Project Road.
2. The values of input parameters and the rationale for their selection for
the economic and commercial analyses shall be clearly brought out and got
approved by Chief Engineer, Highways, Mizoram PWD.

3. For models to be used for the economic and the commercial analyses,
the calibration methodology and the basic parameters adapted to the local
conditions shall be clearly brought out and got approved by Chief Engineer,
Highways, Mizoram PWD.

4. The economic and commercial analyses should bring out the priority of
the different homogenous links in terms of project implementation.

6.1. Economic Analysis


1. The Consultants shall carry out economic analysis for the project. The
analysis should be for each of the sections covered under this TOR. The benefit
and cost streams should be worked out for the project using HDM-IV or other
internationally recognized life-cycle costing model.
2. The economic analysis shall cover but be not limited to be following aspects:
i. assess the capacity of existing roads and the effects of capacity constraints
on vehicle operating costs (VOC);
77
ii. calculate VOCs for the existing road situation and those for the project;
iii. quantify all economic benefits, including those from reduced congestion,
travel distance, road maintenance cost savings and reduced incidence
of road accidents; and,
iv. estimate the economic internal rate of return (EIRR) for the project over
a 30-year period. In calculating the EIRRs, identify the tradable and
non- tradable components of projects costs and the border price value
of the tradable components.
v. Saving in time value.
3. Economic Internal Rate of Return (EIRR) and Net Present Value
(NPV), with and without time and accident savings should be worked out
based on these cost-benefit stream. Furthermore, sensitivity of EIRR and NPV
worked out forth different scenarios as given under:
Scenario I Base Costs and Base
Benefits
Scenario - II Base Costs plus 15% and Base
Benefits
Scenario - III Base Costs and Base Benefits minus
15%
Scenario - IV Base Costs plus 15% and Base Benefits minus 15%
The sensitivity scenarios given above are only indicative. The Consultants
shall select the sensitivity scenarios taking into account possible construction
delays, construction costs overrun, traffic volume, revenue shortfalls,
operating costs, exchange rate variations, convertibility of foreign
exchange, interest rate volatility, non-compliance or default by contractors,
political risks and force majeure.
4. The economic analysis shall take into account all on-going and future road
and transport infrastructure projects and future development plans in the project
area.

6.2. Financial Analysis


1. It is envisaged that the project stretch should be implemented on EPC/BOT
basis, therefore, the Consultant shall study the financial viability of the project
under a commercial format and under different user fee scenarios and funding
options. The Consultants shall submit and finalize in consultation with the
Chief Engineer, Highways, Mizoram officers the format for the analysis and the
primary parameters and scenarios that should be taken into account while
carrying out the commercial analysis. The financial model so developed
shall be the property of Chief Engineer, Highways, Mizoram
2. The Financial analysis for the project should cover financial internal rate
of return, projected income statements, balance sheets and fund flow
statements and should bring out all relevant assumptions. The sensitivity
analysis should be carried out for a number of probabilistic scenarios.
3. The financial analysis should cover identification, assessment, and
mitigating measures for all risks associated with the project. The analysis shall
cover, but be not limited to, risks related to construction delays, construction
costs overrun, traffic volume, revenue shortfalls, operating costs, exchange rate
variations, convertibility of foreign exchange, interest rate volatility,
non-compliance or default by
78
contractors, political risks and force majeure.
4. The consultant shall suggest positive ways of enhancing the project Viability
and furnish different financial models for implementing on BOT format.

7. Time period for the service


1. Time period envisaged for the study of the project is indicated in Annex-I
to LOI. The final reports, drawings and documentation shall be completed
within this time schedule.
2. Chief Engineer, Highways, Mizoram shall arrange to give approval on all
sketches, drawings, reports and recommendations and other matters and
proposals submitted for decision by the Consultant in such reasonable time
so as not to delay or disrupt the performance of the Consultants services.

8. Project Team and Project Office of the Consultant


1. The Consultants shall be required to form a multi-disciplinary team for
this assignment. The consultants team shall be manned by adequate
number of experts with relevant experience in the execution of similar detailed
design assignments.
2. List of suggested key personnel to be fielded by the consultant with
appropriate man-month of consultancy services is given in Enclosure I as per
client's assessment.
3. A Manning Schedule for key personnel mentioned above is enclosed
as Enclosure I along with broad job- description and qualification as Enclosure
II. The information furnished in Enclosures I & II are to assist the
Consultants to understand the clients perception about these requirements and
shall be taken by the Consultants for the purpose of Financial Proposal and
deployment schedule etc. in technical proposal to be submitted by them. Any
deviation proposed may be recorded in the comments on TOR. All the key
personnel mentioned will be evaluated at the time of evaluation of technical
proposal. Consultants are advised in their own interest to frame the technical
proposal in an objective manner as far as possible so that these could be
properly assessed in respect of points to be given as part of evaluation criteria
as mentioned in Data sheet. The bio-data of the key personnel should be
signed on every sheet by the personnel concerned and the last sheet of each
bio-data should also be signed by the authorised signatory of the Consultants.
4. The Consultants shall establish an office at the project site manned by
senior personnel during the course of the surveys and investigations. All the
project related office work shall be carried out by the consultant in their site
office unless there are special reasons for carrying out part of the office work
elsewhere for which prior approval of Chief Engineer, Highways shall be
obtained. The address of the site office including the personnel manning it
including their Telephone and FAX numbers will be intimated by the
Consultant to Chief Engineer, Highways, Mizoram before commencement of
the services.

79
5. The Consultant shall maintain an Attendance Register to be signed by
each individual key personnel at site as well as at Head Office. The
Consultant shall furnish certificate that all the key personnel as
envisaged in the Contract
Agreement have been actually deployed in the Projects at the time of
submission of their bills to the Chief Engineer, Highways, Mizoram from time
to time.

9. Reports to be submitted by the Consultant to Chief Engineer, Highways, Mizoram


9.1 All reports, documents and drawings are to be submitted separately for each of the
traffic homogenous link of the Project Road. The analysis of data and the design
proposals shall be based on the data derived from the primary surveys and
investigations carried out during the period of assignment. The sources of data and
model relationships used in the reports shall be indicated with complete details for
easy reference.
9.2 Project preparation activities will be split into six stages as brought
out below.
Preliminary design work should commence without waiting for feasibility study to
be completed. Stage 3, 5 and 6 shall run in parallel with Stage 2 and 4
Stage 1: Inception Report
Stage 2: Feasibility Report
Stage 3: LA & Clearances I Report
Stage 4: Detailed Project Report (DPR)
Stage 5: Technical Schedules
Stage 6: LA & Clearances II Report

9.3 Consultant shall be required to complete, to the satisfaction of the client, all the
different stages of study within the time frame indicated in the schedule of
submission in para 10 pertaining to Reports and Documents for becoming eligible
for payment for any part of the next stage.

10 Reports and Documents to be submitted by the Consultant to Chief Engineer,


Highways
1. The Consultant shall submit to the client the reports and documents in
bound volumes (and not spiral binding form) after completion of each stage of
work as per the schedule and in the number of copies as given in Enclosure
III. Further, the reports shall also be submitted in floppy diskettes / CDs
in addition to the hardcopies as mentioned in Enclosure-III. Consultant shall
submit all other reports mentioned specifically in the preceding paras of the
TOR.
2. The time schedule for various submissions prescribed at s.l.no.1 above shall
be strictly adhered to. No time-over-run in respect of these submissions will
normally be permitted. Consultant is advised to go through the entire terms of
reference carefully and plan his work method in such a manner that various
activities followed

80
by respective submissions as brought out at Sl.No.1 above are completed
as stipulated. Consultant is, therefore, advised to deploy sufficient number of
supporting personnel, both technical and administrative, to undertake the
project preparation activities in construction package (Section)
simultaneously. As far as possible, the proposal should include complete
information such as number of such persons, name, position, period of
engagement, remuneration rate etc. The Consultant is also advised to start
necessary survey works from the beginning so as to gain time in respect
of various other activities in that stage.

STAGE 1
10.1 Quality Assurance Plan (QAP) Document
1. Immediately upon the award, the Consultants shall submit four copies of the
QAP document covering all aspects of field studies, investigations design and
economic financial analysis. The quality assurance plans/procedures for different
field studies, engineering surveys and investigation, design and documentation
activities should be presented as separate sections like engineering surveys and
investigations, traffic surveys, material geo-technical and sub-soil investigations,
road and pavement investigations, investigation and design of bridges
&structures, environment and R&R assessment, economic & financial analysis,
drawings and documentation; preparation, checking, approval and filing of
calculations, identification and traceability of project documents etc. Further,
additional information as per format shall be furnished regarding the details of
personnel who shall be responsible for carrying out/preparing and
checking/verifying various activities forming part of feasibility study and project
preparation, since inception to the completion of work. The field and design
activities shall start after the QAP is approved by Chief Engineer,
Highways,Mizoram

2. The data formats proposed by the Consultants for use in field studies and
investigations shall be submitted within 14 days after the commencement of
services and got approved by Chief Engineer, Highways, MizoramPWD.
10.2 Inception Report (IR)
1. The report shall cover the following major aspects:
i. Project appreciation;
ii. Detailed methodology to meet the requirements of the TOR finalised
in
consultation with the Chief Engineer, Highways, MizoramPWD officers;
including scheduling of various sub activities to be carried out for
completion of various stages of the work; stating out clearly their
approach & methodology for project preparation after due inspection
of the entire project stretch and collection/ collation of necessary
information;
iii. Task Assignment and Manning Schedule;
iv. Work programme;
v. Proforma for data collection;
vi. Design standards and proposed cross-sections;

81
vii. Key plan and Linear Plan;
viii. Development plans being implemented and / or proposed for
implementation in the near future by the local bodies and the possible
impact of such development plans on the overall scheme for field work
and design for the study;
ix. Quality Assurance Plan (QAP) finalised in consultation with Chief
Engineer, Highways ,MizoramPWD Draft design standards; and
2. The requirements, if any, for the construction of bypasses should be identified on
the basis of data derived from reconnaissance and traffic studies. The available
alignment options should be worked out on the basis of available maps. The most
appropriate alignment option for bypasses should be identified on the basis of site
conditions and techno-economic considerations. Inception Report should include
the details regarding these aspects concerning the construction of bypasses for
approval by Chief Engineer, Highways,Mizoram PWD
STAGE 2:

10.3 Feasibility Report

1. The consultant shall commence the Feasibility Study of the project in accordance
with the accepted IR and the report shall contain the following:
i. Executive summary
ii. Overview of Chief Engineer, Highways organization and activities,
and project financing and cost recovery mechanisms
iii. Project description including possible alternative
alignments/bypasses and technical/engineering alternatives
iv. Methodology adopted for the feasibility study
v. Socioeconomic profile of the project areas
vi. Indicative design standards, methodologies and specifications
vii. Traffic surveys and analysis
viii. Environmental screening and preliminary environmental assessment
ix. Initial social assessment and preliminary land acquisition/resettlement
plan
x. Cost estimates based on preliminary rate analysis and bill of quantities
xi. Economic and financial analysis
xii. Conclusions and recommendations
2. In view of para 1 above the consultant has to submit the following
documents in six sets:
i. Technical Specifications: The MORT&Hs Technical Specifications for
Road and Bridge works shall be followed for this study. However, Volume
- IV: Technical Specifications shall contain the special technical specifications
which are not covered by MORT&H Specifications for Roads and Bridges
(latest edition / revision)and also specific quality control norms for the
construction of works.
ii. Rate Analysis: This volume will present the analysis of rates for all items of
works. The details of unit rate of materials at source, carriage charges

82
any other applicable charges, labour rates, and machine charges as considered in
arriving at unit rates will be included in this volume.
iii. Cost Estimates: This volume will present the each item of work as
well as a summary of total cost.
iv. Bill of Quantities: This volume shall contain the detailed Bill
of Quantities for all items of works
3. The basic data obtained from the field studies and investigations shall
be submitted in a separate volume as an Appendix to Feasibility Report.
4. The Final Feasibility Study Report incorporating comments, revisions
and modifications suggested by Chief Engineer, Highways, Mizoram
PWDshall be submitted within 15 days of comments from Chief Engineer,
Highways,Mizoram PWD on draft feasibility study report.

STAGE 3:

10.4 Strip Plan and Clearances


1. The Consultants shall submit the following documents:
i. Details of the center line of the proposed widened NH along with the existing
and proposed right-of-way limits to appreciate the requirements of land
acquisition;
ii. The information concerning the area including ownership of land to be
acquired for the implementation of the project shall be collected from the
revenue and other concerned authorities and presented along with the strip
plans;
iii. Strip plans showing the position of existing utilities and services
indicating clearly the position of their relocation;
iv. Details for various clearances such as environment and forest clearances;
v. Separate strip plan showing shifting / relocation of each utility services in
consultation with the concerned local authorities;
vi. The utility relocation plans should clearly show existing right-of-way and
pertinent topographic details including buildings, major trees, fences and
other installations such as water-mains, telephone, telegraph and electricity
poles, and suggest relocation of the services along with their crossings the
highway at designated locations as required and prepare necessary details for
submission to the Service Departments;
vii. Detail schedules for acquisition of additional land and additional
properties in consultation with the revenue authorities; and
viii. Land Acquisition Plan shall be prepared after digitization of cadastral /
land revenue maps. The digitized map shall exactly match the original map,
like a contact print, since the dimensions and area of plots, or the whole
village is to be extracted from the map itself. An accuracy of 1mm or higher in
a 1:1000 scale map shall be ensured, as this translates into an accuracy of 1
m or higher on ground.
2. The strip plans and land acquisition plan shall be prepared on the basis of data from
reconnaissance and detailed topographic surveys.
3. The Report accompanying the strip plans should cover the essential aspects as given
under:

83
i. Kilometre-wise Land Acquisition Plan (LAP) and schedule of
ownership thereof and Costs as per Revenue Authorities and also
based on realistic rates.
ii. Details of properties, such as buildings and structures falling within
the right-of way and costs of acquisition based on realistic rates.
iii. Kilometre-wise Utility Relocation Plan (URP) and costs for relocation
per civil construction package as per concerned authorities.
iv. Kilometre-wise account in regard to felling of trees of different type
and girth and value estimate of such trees based on realistic rates
obtainable from concerned District forest office.
4. The strip plans shall clearly indicate the scheme for widening. The views and
suggestions of the concerned State PWDs should be duly taken into account while
working out the widening scheme (left, right or symmetrical). The widening scheme
shall be finalised in consultation with Chief Engineer, Highways,Mizoram PWD
5. Kilometre-wise Strip Plans for section (Package) shall be prepared separately for
each concerned agency and suggested by Chief Engineer, Highways,Mizoram PWD

10.5 Land Acquisition Report


1. The Land acquisition report shall be prepared and submitted for section (package).
The report shall include detail schedules about acquisition of landholdings as per
revenue records and their locations in a strip plan and also the costs as per district
authorities. Details shall be submitted in land acquisition proforma to be supplied by
Chief Engineer, Highways, Mizoram PWD The land acquisition report shall be
submitted in both Hind and English
languages.
2. The land acquisition report should be prepared in consultation with affected persons,
non-governmental organisations and concerned government agencies and should
cover land acquisition and resettlement plan and costs of resettlement and
rehabilitation of such affected persons. It should also include plan of
compensating afforestation, its land requirement with specific locations and cost
involved for undertaking all activities in this regard.
10.6 Deleted

STAGE: 4
10.7 Draft Detailed Project Report (DPR)
1. The draft DPR Submission shall consist of construction package-wise Main
Report, Design Report, Materials Report, Engineering Report, Drainage Design
Report, Economic and Financial Analysis Report, Environmental Assessment
Report including Resettlement Action Plan (RAP), Package-wise bid Documents
and Drawings.
2. The Report volumes shall be submitted as tabulated in para 10 above.
3. The Documents and Drawings shall be submitted for the Package and shall be in
the following format:

84
Reports
i. Volume-I, Main Report: This report will present the project
background, social analysis of the project, details of surveys and
investigations carried out, analysis and interpretation of survey and
investigation data, traffic studies and demand forecasts designs, cost
estimation, environmental aspects, economic and commercial analyses
and conclusions. The report shall include Executive Summary giving
brief accounts of the findings of the study and recommendations.

The Report shall also include maps, charts and diagrams showing
locations and details of existing features and the essential features of
improvement and upgrading. The Environmental Impact Assessment
(EIA) Report for contract package shall be submitted as a part of the
main report.

The basic data obtained from the field studies and investigations and
input data used for the preliminary design shall be submitted in a
separate volume as an Appendix to Main Report.

ii. Volume - II, Design Report: This volume shall contain design
calculations, supported by computer printout of calculations wherever
applicable. The Report shall clearly bring out the various features of
design standards adopted for the study. The design report will be in two
parts. Part-I shall primarily deal with the design of road features and
pavement composition while Part-II shall deal with the design of
bridges, tunnels and cross- drainage structures. The sub-soil
exploration report including the complete details of boring done,
analyses and interpretation of data and the selection of design
parameters shall be included as an Appendix to the Design Report.

The detailed design for all features should be carried out as per
the requirements of the Design Standards for the project. However,
there may be situations wherein it has not been possible to strictly
adhere to the design standards due to the existing site conditions,
restrictions and other considerations. The report should clearly bring
out the details of these aspect and the standards adopted.

iii. Volume - III, Materials Report: The Materials Report shall contain
details concerning the proposed borrow areas and quarries for
construction materials and possible sources of water for construction
purposes. The report shall include details on locations of borrow areas
and quarries shown on maps and charts and also the estimated
quantities with mass haul diagram including possible end use with
leads involved, the details of sampling and testing carried out and
results in the form of important index values with possible end use
thereof.

The materials Report shall also include details of sampling, testing and
test results obtained in respect physical properties of subgrade soils.
The information shall be presented in tabular as well as in
graphical
85
representations and schematic diagrams. The Report shall present
soil profiles along the alignment.

The material Report should also clearly indicate the locations of areas
with problematic soils. Recommendations concerning the improvement
of such soils for use in the proposed construction works, such as
stabilization (cement, lime, mechanical) should be included in the
Report.

iv. Volume - IV, Environmental Assessment Report including


Environmental Management Plan (EMP) & Resettlement Action Plan
(RAP): The Report shall be prepared conforming to the Guidelines of
the Government of India, State Government and World Bank / ADB as
appropriate for construction package.

v. Volume - V, Technical Specifications: The MORT&Hs


Technical Specifications for Road and Bridge works shall be followed
for this study. However, Volume IV: Technical Specifications shall
contain the special technical specifications which are not covered by
MOST Specifications for Roads and Bridges (latest edition /
revision) and also specific quality control norms for the construction
of works.

vi. Volume - VI, Rate Analysis: This volume will present the analysis of
rates for all items of works. The details of unit rate of materials at
source, carriage charges, any other applicable charges, labour rates,
machine charges as considered in arriving at unit rates will be included
in this volume.

vii. Volume - VII, Cost Estimates: This volume will present the
contract package wise cost of each item of work as well as a summary
of total cost.

viii. Volume - VIII, Bill of Quantities: This volume shall contain the
package- wise detailed Bill of Quantities for all items of works.

ix. Volume - IX, Drawing Volume: All drawings forming part of this
volume shall be good for construction drawings. All plan and profile
drawings will be prepared in scale 1:250V and 1:2500H scale to cover
one km in one sheet. In addition this volume will contain good for
construction drawings for the following:

Horizontal Alignment and Longitudinal Profile.


Cross-section @ 50m interval along the alignment within ROW
Typical Cross-Sections with details of pavement structure.
Detailed Working Drawings for individual Culverts and
Cross
Drainage Structures.
Detailed Working Drawings for individual Bridges,
tunnels and Structures.
Detailed Drawings for Improvement of At-Grade and

86
Grade-Separated
Intersections and Interchanges.
Drawings for Road Sign, Markings, Toll Plazas, and
otherfacilities
Schematic Diagrams (linear chart) indicating but be not
limited to be following:
o Widening scheme;
o Locations of median openings, intersections,
interchanges underpasses, overpasses, bypasses;
o Locations of service roads;
o Location of traffic signals, traffic signs, road
markings, safety features; and,
o Locations of toll plaza, parking areas, weighing stations,
bus bays, rest areas, if any.
Drawings for toll plaza, Bus Bays, Parking areas, Rest
areas, weighing stations etc. All drawings will be prepared in
A2 size sheets. The format for plan, cross section and profile
drawings shall
be finalised in consultation with the concerned Chief Engineer,
Highways officers. The drawings shall also include details of all
BM and reference pillars, HIP and VIP. The co-ordinates of all
points should be referenced to a common datum, preferably GTS
referencing system. The drawings shall also include the
locations of all traffic safety features including traffic signals,
signs, markings, crash barriers, delineators and rest areas,
busbays, parking areas etc.
The typical cross-section drawings should indicate the scheme
for future widening of the carriageway. The proposed cross-
sections of road segment passing through urban areas should
indicate the provisions for pedestrian movements and suitable
measures for surface and sub-surface drainage and lighting, as
required.

10.8. Final Detailed Project Report, Documents and Drawings (6 Sets)

1. The Final package-wise DPR consisting of Main Report, Design Report, Drainage
Design Report and Materials Report, incorporating all revisions deemed relevant
following receipt of the comments from Chief Engineer, Highways, Mizoram
PWD on the draft DPR shall be submitted as per the schedule given in
Enclosure-III.
STAGE: 5
10.9. Technical Schedules

1. Civil Work Contract Agreement: A civil works contract agreement shall be


submitted

87
STAGE: 6
10.10. LA & Clearances II Report

1. Draft 3a, 3A, 3D notification shall be submitted by the consultant.

2. All the necessary project related clearances such as environment, forest and
wildlife clearance from MOEF, Railways in respect of ROB/ RUBs, Irrigation
Deptt and any other concerned agencies shall be obtained by the consultant. The
final approvals shall be obtained and submitted to Chief Engineer, Highways
, so that project can straight away proceed without any hold up. For utility
implementation
Mizora clearances, consultant shall prepare draft utility shifting estimates using the latest
m PWD
Schedule of Rates and obtain final approval from utility agency and Chief
Engineer, Highways, Mizoram PWD
11. Interaction with Chief Engineer, Highways, Mizoram PWD

1. During entire period of services, the Consultant shall interact continuously with
Chief Engineer, Highways, Mizoram PWD and provide any clarification as
regards methods
carryout being followed
modification and by Chief Engineer, Highways, Mizoram
as suggested
PWD A programme of various
activities shall be provided to Chief Engineer, Highways and prior intimation
shall be
Chief given toHighways, Mizoram PWD regarding start of key activities
Engineer,
such as boring, surveyEngineer,
inspections of Chief etc. so that
Highways, Mizoram PWD officials could be
arranged in time.

2. The Chief Engineer, Highways, Mizoram PWD officers and other Government
officers
time, may visit or
individually thecollectively
site at anyto acquaint/ supervise the field investigation and
survey works. Chief Engineer, Highways, Mizoram PWD may also appoint a
Proof of
work Consultant to supervise
the DPR consultant the
including inter-alia field investigation, survey work,
Design work and preconstruction activities

3. The consultant shall be required to send 3 copies of concise monthly Progress


Report by the 5th day of the following month to the designated officer at his Head
Quarter so that progress could be monitored by the Chief Engineer, Highways
These reports will
indicate
activitiesthe dates of by
performed induction and de-induction
them. Frequent meetingsofwith
various key personnel
the consultant at siteand the
office
or in Delhi are foreseen during the currency of project preparation.

4. All equipment, software and books etc. required for satisfactory services for this
project shall be obtained by the Consultant at their own cost and shall be their
property.

12. Payment Schedule

1. The Consultant will be paid consultancy fee as a percentage of the contract values
as per the schedule given in the Draft Contract Agreement.

88
13. Data and Software

1. The floppy diskettes/CDs containing all basic as well as the processed data
from all field studies and investigations, report, appendices, annexure,
documents and drawings shall be submitted to Chief Engineer, Highways,
Mizoram PWD at the time of the submission of the Final Report. The data can
be classified as follows:

i. Engineering Investigations and Traffic Studies: Road


Inventory, Condition, Roughness, Test Pit (Pavement composition),
Benkelman Beam Deflection, Material Investigation including test
results for subgrade soils, Traffic Studies(traffic surveys), axle load
surveys, Sub-soil Exploration, Drainage Inventory, Inventory data for
bridge and culverts indicating rehabilitation, new construction
requirement etc. in MS EXCEL or any other format which could be
imported to widely used utility packages.

ii. Topographic Surveys and Drawings: All topographic data would


be supplied in (x, y, z) format along with complete reference so that the
data could be imported into any standard highway design software. The
drawing files would be submitted in dxf or dwg format.

iii. Rate Analysis: The Consultant shall submit the rate analysis for
various works items including the data developed on computer in this
relation so that it could be used by the Authority later for the purpose of
updating the cost of the project.

iv. Economic and Financial Analysis

2. Software: The Consultant shall also hand-over to Chief Engineer, Highways,


Mizoram PWD floppies/CDs containing any general software including the
financial model which has been specifically developed for the project.
3. The floppy diskettes/CDs should be properly indexed and a catalogue
giving contents of all floppies/CDs and print-outs of the contents (data
from field studies topographic data and drawings) should be handed over to
Chief Engineer, Highways, Mizoram PWD at the time of submission of the
Final Report.

4. Consultant shall include editable soft copies of the final versions of all
documents, including but not limited to the strip plan, plan & profile drawings,
cross sections of right of way and details of structures as well as any cost
workings.

89
SUPPLEMENT I

ADDITIONAL POINTS TO BE CONSIDERED FOR HILL ROADS IN


ADDITION TO POINTS COVERED IN MAIN TOR
S. Clause No. Additional points
No. of TOR
1. 2.2 a) Provisions of tunnels if required.

2. 2.3 a) Design of tunnels, if required


b) Design of protective works, slope stabilization measures, erosion control
measures, land slide control/protection measures snow drift
control/snow clearance measures, avalanche protection measures, if
required
3. 3 Feasibility study and preparation of detailed project report for hill roads
shall be done in accordance with best international practices and wherever
practicable/feasible steep gradients and hair pin bends may be avoided by
realignments by provision of structures and provision of tunnels if required
4. 4.1 a) Inventory and condition survey for tunnels, if required.
b) Identification of faults in rock strata and impact of faults in design of
tunnels, if required
c) Detailed design of road considering and incorporating specific aspects
related to hill region like terrain, topographic conditions, extreme weather
conditions, altitude effects etc.
d) Design of protective works, slope stabilization measures, erosion control
measures, land slide control/protection measures, snow drift control/snow
clearance measures, avalanche protection measures, if required
e) Design of scenic overlooks/watering points etc.

5. 4.5 (1) All activities related to field studies, design and documentation shall be
done as per the latest guidelines/circulars of MORT&H and relevant
publications of the Indian Roads Congress (IRC)/Bureau of Indian Standards
(BIS) for hill roads. For aspects not covered by IRC and BIS, international
standard practices, such as, British and American Standards may be adopted.

6. 4.7 Review of data and documents pertaining to


a) Terrain and soil condition
b) Condition of tunnels, if required.
c) Sub-surface and geo-technical data for existing tunnels, if required.
d) Drawing and details of existing tunnels, if required.
e) Existing protective works, erosion control and land slide control/

90
protection works, slope stabilization measures, snow drift control
measures, avalanche protection measures
f) Existing land slide and snow clearance facilities
g) Geological details of rock strata in the area in case of tunnels

7. 4.11(1) The Consultant should make an in depth study of available geological and
meteorological maps of the area.
8. 4.11 (2) The primary tasks to be accomplished during the reconnaissance survey
shall also include:
a) details of terrain (steep or mountainous ), cliffs and gorges, general
elevation of the road including maximum heights negotiated by main
ascents and descents, total number of ascents and descents, hair pin
bends, vegetation etc.
b) Climatic conditions i.e. temperature, rain fall data, snow fall data, fog
conditions, unusual weather conditions etc.
c) Realignment requirements including provision of tunnels, if required.
d) Inventory of tunnels and geologically sensitive areas like slip prone areas,
areas subject to landslides, rock fall, snow drifts, erosion, avalanche
activity etc.

9. 4.11.2.1 (ii) Cross sections shall be taken at every 25 m. in case of hill roads and at
points of appreciable changes in soil conditions. While taking cross
sections, soil conditions shall also be recorded.
10. 4.11.3.1 (1) The inventory data shall also include:
a) General elevation of road indicating maximum & minimum heights
negotiated by main ascents & descents and total no. of ascents
&descents.
b) Details of road gradients, lengths of gentle & steep slopes, lengths &
location of stretches in unstable areas, areas with cliffs, areas with loose
rocks, land slide prone areas, snow drift prone areas, no. & location of
hairpin bends etc.
c) Details of tunnels
d) Details & types of protective structures, erosion & land slide
control/protection measures, snow drift control measures, avalanche
protection/control measures etc.
11. 4.11.3.2 (2) Pavement:

a) Location of crust failures along with their causes


b) Conditions of camber/cross falls/super elevations etc., whether affected
by subsidence
Embankment:
Extent of slope erosion on hill and valley side

91
12. -- Condition Surveys & Investigation for Slope Stabilization, Erosion
Control, Landslide Correction/Protection & Avalanche Protection
Measures:
a) Inventory & Condition Surveys of Existing Protective/Control
Measures:
The consultant shall make an inventory of all the structures related to Slope
Stabilization, Erosion Control, Landslide Control/protection, Avalanche
Protection etc. This shall include details of effectiveness of control
measures already done and condition of protective/control structures.
b) Landslide Investigation
This shall be carried out to identify landslide prone areas, to suggest
preventive measures or alternate routes that are less susceptible to landslide
hazard. Further in existing slide areas this shall help to identify factors
responsible for instability and to determine appropriate control measures
needed to prevent or minimize recurring of instability problems.
Initial preliminary studies shall be carried out using available contour maps
, topographical maps, geological/geo-morphological maps, aerial
photographs etc. for general understanding of existing slide area and to
identify potential slide areas. This shall be followed by further
investigations like geological/geotechnical/hydrological investigation to
determine specific site conditions prevailing in the slide area as per
relevant IRC specifications/publications, MORT&H circulars and relevant
recommendations of the international standards for hill roads. The result of
the investigations shall provide basis for engineering analysis and the design
of protection/remedial measures.
13. 4.11.4.4 a) For tunnels if required, geotechnical and subsurface investigation
shall be done asper IRC:SP:91.
b) Geotechnical and subsurface investigation and testing for tunnels shall
be carried out through the geotechnical Consultants who have the
experience of geotechnical and subsurface investigation in similar
project.
14. 4.12.1 (1) The Consultant shall also carry out detailed designs and prepare working
designs for the following:
a) cross sections at every 25 m intervals
b) Slope stabilization and erosion control measures
c) Design of protection/control structures in areas subject to subsidence,
landslides, rock fall, rock slide, snow drifts, icing, scour, avalanche
activity etc.
d) Design of protective structures in slip prone and unstable areas
e) Design of scenic overlooks, watering points etc.
f) Safety features specific to hill roads
15. 4.12.2 (1) The Consultant shall evolve Design Standards and material specifications

99
for the Study primarily based on IRC publications, MORT&H Circulars
and relevant recommendations of the international standards for hill roads for
4.12.2 (2) approval by Chief Engineer, Highways, Mizoram PWD

The Design Standards evolved for the project shall cover all aspects of
detailed design including the design of geometric elements, pavement design,
bridges and structures, tunnels if required, traffic safety and materials.

16. 4.12.3 Wherever practicable/feasible hairpin bends and steep gradients shall be
avoided by realignments, provision of structures or any other suitable
provisions.
17. 4.12.4 While designing pavement for hill roads specific aspects relevant to hill
regions like terrain & topographic conditions, weather conditions, altitude
effects etc. shall be duly considered and suitably incorporated in design so
that pavement is able to perform well for the design traffic and service life.
Effects of factors like heavy rainfall, frost action, intensive snow and
avalanche activity, thermal stresses due to temperature difference in day
and night, damage by tracked vehicles during snow clearance operations
etc. must also be considered along with traffic intensity, its growth, axle
loads and design life.
18. 4.12.5(3) The design of embankments should include the requirements for protection
works and traffic safety features including features specific to hill roads.
19. -- Design and Drawing of Tunnels:
The Consultant shall prepare design and drawings for tunnels, if required
as per the results of feasibility study, as per the relevant specifications of
IRC:SP:91/MORT&H and other international specifications.
20. 4.12.7 a) Topography of hills generates numerous water courses and this coupled
with continuous gradients of roads in hills and high intensity of rainfall
calls for effective drainage of roads. The drainage system shall be
designed to ensure that the water flowing towards the road surface may
be diverted and guided to follow a definite path by suitable provision of
road side drains, catch water drains, interceptors etc. and flow on valley
side is controlled so that stability is not affected.
b) Further, adequate provision shall be made for sub-surface/subgrade
drainage to take care of seepage through the adjacent hill face of the
road & underground water flows.
21. 4.12.8 The Consultant shall design suitable traffic safety features and road
furniture including traffic signals, signs, markings, overhead sign boards,
crash barriers ,delineators etc. including any feature specific to hill roads.
The locations of these features shall be given in the reports and also shown
in the drawings.
22. 4.12.3 (1) The Consultant shall make suitable designs and layout for miscellaneous

100
works including rest areas, bus bays, vehicle parking areas,
telecommunication facilities, scenic overlooks, watering points etc.
wherever appropriate.
23. 10.6 (1) Volume II: Design Report :
a) Inventory of protection measures and other structures
b) Inventory of tunnels, if required.
c) Proposed preliminary designs for tunnels, if required.
Volume III: Drawings
a) Drawings for protection/control measures and other structures
b) Drawings for tunnels, if required.
24. 10.7 (3) Volume II: Design Report (Part II)
Part II of Design Report shall also deal with design of tunnels, if required
and design of other protection/control structures.
Volume IX: Drawing Volume
This shall also include :
a) Detailed working drawings for tunnels, if required.
b) Detailed working drawings for protection/control structures

101
SUPPLEMENT II

S.No. Clause No. Additional points


of TOR
1 4.1 For stand alone bridge projects the scope of work shall include
detailed design of approach road extending at least up to 2 km on
either side of the bridge
1. 4.11.4.2(6) Model Studies for Bridges
1. Objective
Physical/ Mathematical Model study for detailed Hydraulic /
Hydrologic investigations regarding the proposed bridge for
hydraulic design of the bridge and assessment and hydraulic
design of required river training works.
2. Methodology

Physical/Mathematical Model study shall be carried out at a


reputed/recognized institution. The consultant will be
responsible for identifying the institution, supplying Information
/Documents /Data required for modal studies as indicated in para
4 below and coordinating the model study with the institution
concerned

3. Scope of Work
3.1 Physical Model study
Physical modeling with appropriate model scale for Hydraulic
and Hydrologic Investigations to :
i) Finalize span arrangement causing uniformity in flow
distribution, and work out the alignment and orientation
of river training works and bridge axis.
ii) Provide information on estimated/observed maximum
depth of scour.
iii) Provide information on required river training works for
proposed bridge
iv) Provide hydraulic design for the bridge and the required
river training works.
v) Quantify the general direction of river course through
bridge, afflux, extent and magnitude of flood, effect of
backwater, if any, aggradation/degradation of bed,
evidence of scour etc. shall be used to augment the
available hydrological data. The presence of flood
control/irrigation structures, if affecting the hydraulic
characteristics like causing obliquity, concentration of

102
flow, scour, silting of bed, change in flow levels, bed
levels etc. shall be studied and considered in
Hydraulic design of proposed bridge. The details of
any planned work in the immediate future that may
affect the river hydraulics shall be studied and
considered
3.2 Mathematical Model study
Mathematical modeling for detailed Hydraulic /
Hydrologic investigations regarding the proposed new bridge
to:
i) Finalize the site/location of the proposed new
bridge based on mathematical modeling.
ii) Provide information on estimated/observed
maximum depth of scour..
iii) Provide information on required river training works
for proposed bridge
iv) Provide hydraulic design for the bridge and the
required river training works.

v) Quantify the general direction of river course


through bridge, afflux, extent and magnitude of
flood, effect of backwater, if any,
aggradation/degradation of bed, evidence of scour
etc. shall be used to augment the available
hydrological data. The presence of flood
control/irrigation structures, if affecting the
hydraulic characteristics like causing obliquity,
concentration of flow, scour, silting of bed, change
in flow levels, bed levels etc. shall be studied and
considered in Hydraulic design of proposed bridge.
The details of any planned work in the immediate
future that may affect the river hydraulics shall be
studied and considered.
4. Information /Documents /Data required for
Physical/Mathematical Model study

i) Plan layouts showing the locations of the proposed


bridge as well as the existing bridges / barrages etc., in
the vicinity of the proposed bridge with the chainages
with respect to a standard reference marked on it.

104
ii) High flood discharges and corresponding flood levels
at the locations of the existing bridges in the vicinity
of the proposed bridge.
iii) General arrangement drawing (GAD) of the
existing bridges showing number of spans, pier and
well dimensions, founding levels, maximum scour
level, the design discharge and the HFL, guide bund
details. On this, the plan form of the river course with
the bridge alignment may also be shown as far as
possible.

iv) General arrangement drawing (GAD) of the proposed


new bridge showing number of spans , pier and
foundation dimensions. On this, the plan form of
the river course with the bridge alignment may also
be shown as for as possible.
v) River cross sections at 500m longitudinal
spacing (maximum) up to a distance of 2 times the
bridge total length on the upstream side and up to a
distance equal to the bridge total length on the
downstream with right bank and left bank clearly
marked on it. At least one cross section to be provided
at the location of the proposed bridge. At each cross
section, the bed levels to be taken at a maximum
lateral distance of 8 m in flow section and at 25 m
in non flow section respectively. The abrupt
variations in the bed levels to be captured by
taking measurements at closer locations both
in longitudinal as well as lateral directions.
vi) The cross sections, as for as possible, from high
bank to high bank.

vii) The longitudinal profile of the river along the length of


the proposed alignment.

viii) Size distribution of the river bed material and the


bore log data at different locations at the site of the
proposed bridge.

ix) The series of annual peak flood of the river for at


least 15 years period.

104
SUPPLEMENT-III
ADDITIONAL REQUIREMENT FOR SAFETY AUDIT

The use of checklists is highly recommended as they provide a useful aide memoire for
the audit team to check that no important safety aspects are being overlooked. They also give
to the project manager and the design engineer a sense of understanding of the place of safety
audit in the design process. The following lists have been drawn up based on the experience of
undertaking systematic safety audit procedures overseas. This experience indicates that
extensive lists of technical details has encouraged their use as tick sheets without sufficient
thought being given to the processes behind the actions. Accordingly, the checklists provide
guidelines on the principal issues that need to be examined during the course of the safety
audits.

Stage F-During Feasibility Study


1. The audit team should review the proposed design from a road safety perspective
and heck the following aspects

CONTENTS ITEMS

Aspects to be checked A. Safety and operational implications of proposed alignment


and junction strategy with particular references to expected
road users and vehicle types likely to use the road.
B. Width options considered for various sections.
C. Departures from standards and action taken.
D. Provision of pedestrians, cyclists and intermediate transport
E. Safety implications of the scheme beyond its physical
limits i.e. how the scheme fits into its environs and road
hierarchy

A1 : General Departures from standards


Cross-sectional variation
Drainage
Climatic conditions
Landscaping
Services apparatus
Lay-byes
Footpath
Pedestrian crossings
Access (minimize number of private accesses)

105
Emergency vehicles
Public Transport
Future widening
Staging of contracts
Adjacent development

A2 : Local Alignment Visibility


New/Existing road interface
Safety Aids on steep hills

A3 : Junctions Minimise potential conflicts


Layout
Visibility

A4 : Non-Motorised Adjacent land


road users Provision Pedestrians
Cyclists
Non-motorised vehicles

A5 : Signs and Lighting Lighting


Signs/Markings

A6 : Construction and Buildability


Operation Operational
Network Management

Stage 1 Completion of Preliminary Design

1. The audit team should review the proposed check the following aspects design from a road
safety perspective and check the following aspects

CONTENTS ITEMS

Aspects to be checked A. Safety and operational implications of proposed alignment and


junction strategy with particular references to expected road users
and vehicle types likely to use the road.
B. Width options considered for various sections.
C. Departures from standards and action taken.
D. Provision of pedestrians, cyclists and intermediate transport

106
E. Safety implications of the scheme beyond its physical limits
i.e. how the scheme fits into its environs and road hierarchy

B1 : General Departures from standards


Cross-sectional variation
Drainage
Climatic conditions
Landscaping
Services apparatus
Lay-byes
Footpaths
Pedestrian crossings
Access (minimize number of private accesses)
Emergency vehicles
Public Transport
Future widening
Staging of contracts
Adjacent development

B2 : Local Alignment Visibility


New/Existing road interface
Safety Aids on steep hills

B3 : Junctions Minimise potential conflicts


Layout
Visibility

B4 : Non-Motorised road Adjacent land


users Provision Pedestrians
Cyclists
Non-motorised vehicles

B5 : Signs and Lighting Lighting


Signs/Markings

B6 : Construction and Buildability


Operation Operational
Network Management

107
Stage 2 Completion of Detailed Design

1. The audit team should satisfy itself that all issues raised at Stage 1 have been resolved. Items
may require further consideration where significant design changes have occurred.
2. If a scheme has not been subject to a stage 1 audit, the items listed in Checklists B1 to B6 should
be considered together with the items listed below.

CONTENTS ITEMS

Aspects to be checked A. Any design changes since Stage 1.


B. The detailed design from a road safety viewpoint, including the
road safety implications of future maintenance (speed limits; road
signs and markings; visibility; maintenance of street lighting and
central reserves).

C1 : General Departures from standards


Drainage
Climatic conditions
Landscaping
Services apparatus
Lay-byes
Access
Skid-resistance
Agriculture
Safety Fences
Adjacent development

C2 : Local Alignment Visibility


New/Existing road interface

C3 : Junctions Layout
Visibility
Signing
Lighting
Road Marking
T,X,Y-junctions
All roundabouts
Traffic signals

C4 : Non-Motorised road Adjacent land


users Provision Pedestrians
Cyclists

108
Non-motorised vehicles

C5 : Signs and Lighting Advanced direction signs


Local traffic signs
Variable message signs
Other traffic signs
Lighting

C6 : Construction and Buildability


Operation Operational
Network Management

109
Enclosure-I

Feasibility Study and preparation of DPR for Aizawl By-Pass on NH-54within Mizoram.

110
MANNING SCHEDULE

SI. Key Personnel Total Project Assignment(5 months)

No At site At design Total

(mm) office Time Period (mm)

1 Team Leader Cum Senior Highway 2.5 2.5 5

2 Senior Bridge Engineer 1 2 3


3 Highway cum Pavement Engineer 1.5 2 3.5
4 Material-cum-Geo-technical 3 2 5

5 Senior Survey Engineer 3 2 5


6 Traffic and Safety expert 1 2 3.5
7 Environmental Specialist 1 1.5 2.5
8 Quantity Surveyor/ Documentation 1 3.5 4.5

Total 14 17.50 32.00

1. Consultants have to provide a certificate that all the key personnel as envisaged in the
Contract Agreement have been actually deployed in the projects. They have to furnish
the certificate at the time of submission of their bills to Chief Engineer, Highways,
Mizoram PWD from time to time.

2. In case Tunnels are to be constructed, necessary input of Tunnel Experts shall be


provided in addition to above mentioned Manpower requirement.

111
Enclosure-II

Qualification and Experience Requirement of Key


Personnel
Team Leader cum Senior Highway
Engineer
i) Educational Qualification

Essential Graduate in Civil Engineering or equivalent


Desirable Post graduate in Civil Engineering
(highways/structures/traffic and
transportation/soil mechanics and
foundation engineering/ Construction
Management /Transportation)
ii) Essential Experience

a)Total Professional Experience Min. 20 years


b) Experience in Highway projects Min. 15 years in Planning, project
preparation and design of Highway projects,
including 2/4/6 laning of NH/SH/
expressways. For hill roads, respective hill
roads experience is required
c) Experience in similar capacity In Feasibility of two / Four/Six Laning works
(Either as Team Leader or in and DPR/IC/ Construction Supervision of
Similar capacity ) Two/Four/six laning of major highway
projects(NH/SH/Expressways)/ feasibility
cum detailed project report of two/ four
laning projects of minimum aggregate length
of 80 km. For hill roads, respective hill roads
experience is required.

iii) Age Limit 70 years on the date of submission of


proposal

112
Enclosure-II(contd.)

QUALIFICATION AND EXPERIENCE REQUIREMENT OF KEY


PERSONNEL

Highway cum Pavement Engineer

i) Educational Qualification

Essential Degree in Civil Engineering


Desirable Masters in highway engineering/
Transportation Engineering
ii) Experience
a)Total Professional Experience Min. 15 years

b) Experience in Highway projects Minimum 10 years experience in pavement


design and maintenance of highways
c) Experience in similar capacity Pavement design for major highway projects
(2/4/6 lane NH/SH/ Expressways) of
minimum aggregate length of 80 km.
iii) Age Limit 70 years on the date of submission of
Proposal

113
Enclosure-II (contd.)

QUALIFICATION AND EXPERIENCE REQUIREMENT OF KEY PERSONNEL

Sr Bridge Engineer

i) Educational Qualification

Essential Graduate in Civil Engineering or equivalent


Desirable Masters in Bridge Engineering /
Structural Engineering
ii) Essential Experience
a)Total Professional Experience Min. 15 years

b) Experience in Bridge projects Min. 10 years in project preparation


and design of bridge projects.

c) Experience in similar capacity Bridge Engineer in highway design


consultancy projects (2/4/6 lane NH/SH/
Expressways)involving design of minimum
two major bridges (length more than 200 m)

iii) Age Limit 70 years on the date of submission of


Proposal

114
Enclosure-II (contd.)

QUALIFICATION AND EXPERIENCE REQUIREMENT OF KEY PERSONNEL

Traffic and Safety Expert

i) Educational Qualification

Essential Graduate in Civil Engineering

Desirable Masters in Traffic Engineering /


Transportation Engineering / Transport
Planning
ii) Essential Experience
a) Total Professional Experience Min. 10 years
b) Experience in Highway projects Min. 5 years on similar projects.
c) Experience in similar capacity Traffic Engineer in highway Projects
(NH/SH/Expressways) involving 2/4/6 laning
of minimum aggregate length of 80 km.

iii) Age Limit 70 years on the date of submission of


Proposal

115
Enclosure-II (contd.)

QUALIFICATION AND EXPERIENCE REQUIREMENT OF KEY PERSONNEL

Material Engineer cum Geotechnical Engineer cum Geologist

i) Educational Qualification

Essential Graduate in Civil Engineering


or M.Sc. Geology
Desirable Masters in Foundation Engineering / Soil
Mechanics / Phd in Geology /Geo Tech
Engineering
ii) Essential Experience
a) Total Professional Experience Min. 15 years
b) Experience in Highway Projects Min. 8 years on similar projects in design
and/or construction
c) Experience in similar capacity Material cum Geo-technical Engineer on
highway projects (2/4/6 lane
NH/SH/Expressways) of minimum aggregate
length of 80 km.
iii) Age Limit 70 years on the date of submission of
Proposal

116
Enclosure-II (contd.)

QUALIFICATION AND EXPERIENCE REQUIREMENT OF KEY PERSONNEL

Senior Survey Engineer

i) Educational Qualification

Essential Graduate or equivalent in Civil Engineering


or Diploma in Civil Engg or Diploma in
Surveying
Desirable Masters in Survey Engineering/
Surveying /Remote Sensing
ii) Essential Experience
a) Total Professional Experience Min. 15 years
b) Experience in Highway projects Min. 5 years on similar projects in project
preparation and construction & thorough
understanding of modern computer based
methods of surveying
c) Experience in similar capacity Survey Engineer for projects preparation of
highway project (NH/SH/Expressways)
involving 2/4/6- laning of minimum
aggregate length of 80 km.
iii) Age Limit 65 years on the date of submission of
Proposal

117
Enclosure-II (contd.)

QUALIFICATION AND EXPERIENCE REQUIREMENT OF KEY PERSONNEL

Environmental Specialist

i) Educational Qualification

Essential Graduate in Civil Engineering / Environment


Engineering / Masters in Environment
Science
Desirable Post Graduate in Environmental
Engineering
ii) Essential Experience
a) Total Professional Experience Min. 10 years
b) Experience in Highway Projects Min. 5 years in environment impact
assessment of highway projects (2/4/6
laning)
c) Experience in similar capacity Environmental Specialist in at least two
highway projects (2/4/6 laning)

iii) Age Limit 70 years on the date of submission of


proposal

118
Enclosure-II (contd.)

QUALIFICATION AND EXPERIENCE REQUIREMENT OF KEY


PERSONNEL

Quantity Surveyor/Documentation
Expert
i) Educational Qualification

Essential Graduate or equivalent in Civil Engineering /


Certificate course from Institution of
Quantity Surveying
Desirable
ii) Essential Experience
a) Total Professional Experience Min. 15 years
b) Experience in Highway Projects Min. 5 years in Preparation of Bill of
Quantities, Contract documents and
documentation for major highway projects
involving two/ four laning
c) Experience in similar capacity Quantity Surveyor / Documentation Expert
in highway projects (NH/SH/Expressways)
involving two/four/six laning of minimum
aggregate length of 80 km.
iii) Age Limit 70 years on the date of submission of
proposal

119
Enclosure-III
Schedule for submission of Reports and Documents

Stage Activity No. of copies Time Period in days from


No. date of commencement

1 Monthly Reports 3 by 10th day of every


month
2 Inception Report
(i) Draft Inception 3 21
Report including QAP
document
(ii) Inception Report 3 30
including QAP
document

3 F.S. REPORT
i) Draft Feasibility Study 4 60
Report including option
study report
ii) Comments of client 1 70

iii) Final Feasibility


Study Report 4 80
incorporating compliance
of comments of Client.

4 LA & Clearances I
Report

i) Draft LA & Clearances I 4 70


Report

ii) Comments of client 1 80

iii) Final LA & Clearances


I Report incorporating
compliance of comments 4 100
of Client

120
5 Detailed Project Report
i) Draft DPR 4 115

ii) Comments of client 1 125

iii) Final DPR 6 130


incorporating compliance
of comments of Client

6 Technical
Schedules

i) Draft
Technical 4 110
Schedules

ii) Comments of 1 120


client

iii) Final 125


technical 6
schedule

7 LA & Clearances II 6
Report

Approval of Project Original


clearances from letters
concerned agencies from the
e.g. from MOEF; Rly for concerned
approval of GAD and agencies and 5 150
detail engineering photocopies of
drawing of ROB/RUB; each.
Irrigation Dept.,

Land Acquisitions: 3(a), 3 copies


3(A), 3(D) Notifications each

121
APPENDIX-II

(Date and Reference) To, **********


*********
*********

122
Proof of Eligibility
Form-E1
Letter of Proposal (On Applicants letter head)

Sub: Appointment of Consultant for preparation


of Detailed Project Report for ...
Dear
Sir,

With reference to your RFP Document dated , I/we i.e M/s---------------------------------


----
--------------------------------------(Name of Bidder) h a v i n g examined all relevant documents
and understood their contents, hereby submit our Proposal for selection as Consultant. The
proposal is unconditional and unqualified.

2. All information provided in the Proposal and in the Appendices is true and correct and
all documents accompanying such Proposal are true copies of their respective originals.
3. This statement is made for the express purpose of appointment as the Consultant for
the aforesaid Project.
4. I/We shall make available to the Authority any additional information it may
deem necessary or require for supplementing or authenticating the Proposal.
5. I/We acknowledge the right of the authority to reject our application without assigning
any reason or otherwise and hereby waive our right to challenge the same on any
account whatsoever.
6. I/We certify that in the last three years, we or any of our Associates have neither
failed to perform on any contract, as evidenced by imposition of a penalty by an
arbitral or judicial authority or a judicial pronouncement or arbitration award against
the Applicant, nor been expelled from any project or contract by any public authority
nor have had any contract terminated by any public authority for breach on our part.

123
7. I/We understand that you may cancel the Selection Process at any time and that you
are neither bound to accept any Proposal that you may receive nor to select the
Consultant, without incurring any liability to the Applicants in accordance with Clause
1.7 of the RFP document.
8. I/We declare that we/any member of the consortium, are/is not a Member of any
other Consortium applying for Selection as a Consultant.
9. I/We certify that in regard to matters other that security and integrity of the country,
we or any of our Associates have not been convicted by a Court of Law or indicted or
adverse orders passed by a regulatory authority which would cast a doubt on
our ability to undertake the Consultancy for the Project or which relates to a grave
offence that outrages the moral sense of the community.
10. I/We further certify that in regard to matters relating to security and integrity of
the country, we have not been charge-sheeted by any agency of the Government or
convicted by a Court of Law for any offence committed by us or by any of our
Associates.
11. I/We further certify that no investigation by a regulatory authority is pending either
against us or against our Associates or against our CEO or
any of our Directors/Managers/employees.
12. I/We hereby irrevocably waive any right or remedy which we may have at any stage at
law or howsoever otherwise arising to challenge or question any decision taken
by the Authority [and/ or the Government of India] in connection with the selection of
Consultant or in connection with the Selection Process itself in respect of the above
mentioned Project.
13. The Bid Security of Rs. ***** (Rupees *****) in the form of a Bank
Guarantee is attached, in accordance with the RFP document.
14. I/We agree and understand that the proposal is subject to the provisions of the
RFP document. In no case, shall I/we have any claim or right of whatsoever
nature if the Consultancy for the Project is not awarded to me/us or our proposal is not
opened or rejected.
15. I/We agree to keep this valid for 120 (One hundred and twenty) days from the
Proposal Due Date specified in the RFP

16. A Power of Attorney in favour of the authorized signatory to sign and submit this
Proposal and documents is attached herewith.

124
17. In the event of my/our firm/consortium being selected as the Consultant, I/we agree to
enter into any Agreement in accordance with the form Appendix V of the RFP. We
agree not to seek any changes in the aforesaid form and agree to abide by the same.
18. I/We have studied RFP and all other documents carefully and also surveyed the
Project site. We understand that except to the extent as expressly set forth in the
Agreement, we shall have no claim, right or title arising out of and documents or
information provided to us by the Authority or in respect of any matter arising out of
or concerning or relating to the Selection Process including the award of Consultancy.
19. The Proof of Eligibility and Technical proposal are being submitted in separate
covers in hard copy and they are being submitted online also. Financial Proposal is
being submitted online only. This Proof of Eligibility read with Technical Proposal and
Financial Proposal shall constitute the Application which shall be binding on us.
20. I/We agree and undertake to abide by all the terms and conditions of the RFP
Document. In witness thereof, I/we submit this Proposal under and in accordance with
the terms of the RFP Document.

Yours
faithfully, (Signature, name and designation of the
authorized signatory) (Name and seal of the
Applicant/Lead Member)

125
Appendix- II
Form-E2/T3

FIRMS
REFERENCES
Relevant Services Carried out in the Last Seven Years (2009-10 onwards)
Which Best Illustrate
Qualifications

The following information should be provided in the format below for each reference
assignment for which your firm, either individually as a corporate entity or as one of the
major companies within a consortium, was legally contracted by the client:

Assignment Name: Country:


Location within Country : Professional Staff Provided
by your firm:
Name of Client : No. of Staff :
Address : No. of Staff Months :
Start Date Completion Date Approx. Value of
(Month / (Month / Year) Services : (in INR/current USD) :
Year)
Name of JV/Association Firm(s) if any : No. of Months of Professional
Staff provided by Associated Firm(s)
Status of your Company in the Assignment i.e., Sole/Lead Member/Other Member/Associate
Narrative Description of Project :
Description of Actual Services Provided by your Company:

Signature of Authorised Representative

(Certificate from Employer regarding experience should be furnished)

126
APPENDIX-II

Form- E3

Financial Capacity of the Applicant

Name of Applicant:

S.No. Financial Year Annual Revenue


(Rs/US $ in million)
1 2015-16
2 2014-15
3 2013-14
4 2012-13
5 2011-12

Certificate from the Statutory Auditor$

This is to certify that --------------(name of the Applicant) has received the


payments shown above against the respective years on account of Consultancy
Services.

Name of the audit firm Seal of the

audit firm Date

(Signature, name and designation of the authorized signatory)

In case he Applicant does not have a statutory auditor, it shall provide the certificate from
its chartered accountant that ordinarily audits the annual account of the Applicant.

Note:

Please do not attach any printed Annual Financial Statement

127
Form- E4

APPENDIX-II

BANK GUARANTEE FORMAT FOR BID


SECURITY
(To be stamped in accordance with Stamp Act if any, of the country of issuing bank)

Ref.: Tender No. , dated


Bank
Guarantee:
Date:

WHEREAS, (Name of Bidder) (hereinafter called "the bidder") has


submitted his bid dated (date) for the Tender No. _, dated
(hereinafter called "the Bid". KNOW ALL MEN by these presents that We,
[Name of Bank] of [Name of Country] having our registered office at
(hereinafter called "the Bank") are bound unto [name of employer] (hereinafter
called "the Employer") in the sum of Rs. (Rupees Lakhs only) for which payment
will and truly to be made to the said employer the bank binds himself, his successors and assigns
by these presents.
SEALED with the Common Seal of the said Bank this day of 201_.

THE CONDITIONS of this obligation are:


1. If the Bidder withdraws his Bid during the period of bid validity specified in the Bid
document; or
2. If the Bidder does not accept the correction of arithmetical errors of his Bid Price in
accordance with the Instructions to Bidder; or
3. If the Bidder having been notified of the acceptance of his Bid by the Employer during the
period of bid validity,
a. fails or refuses to execute the Form of Agreement in accordance with the Instructions to
Bidders, if required; or
b. fails or refuses to furnish the Performance Security, in accordance with the letter of invitation,
we undertake to pay the Employer up to the above amount upon receipt of his first written
demand, without the Employer having to substantiate his demand, provided that in his demand
the Employer will note that the amount claimed by him is due to him owing to the occurrence of
one or any of the conditions, specifying the occurred condition or conditions.

This Guarantee will remain in force up to and including the date 150 (one hundred and fifty) days
after the deadline for submission of bids as such deadline is stated in the Instructions to Bidders
or as it may be extended by the Employer, notice of which extension(s) to the Bank is hereby
waived. Any demand in respect of this Guarantee should reach the Bank not later than the above
date. Notwithstanding anything contained herein before, our liability under this guarantee is
restricted to
Rs. (Rs. ) and the guarantee shall remain valid till
. Unless a claim or a demand in writing is made upon us on or before all our liability
under this guarantee shall cease
DATE
SIGNATURE OF THE BANK SEAL OF THE BANK
SIGNATURE OF THE WITNESS Name and Address of the Witness
The bank guarantee shall be issued by a bank (Nationalized/Scheduled) located in India

128
Appendix III

(Form-T1)

TECHNICAL PROPOSAL

FROM: TO:

Sir:

Subject Consultancy Service for

Regarding Technical Proposal

I/We (name
of

Bidder) Consultant/ Consultancy firm herewith enclose Technical Proposal for selection
of my/our firm/organization as Consultant for .

Yours faithfully,

(Authorized Representative)
Signature Full Name Designation Address

129
(Form-T-2)

Details of projects for which Technical and Financial Proposals have been submitted

Sl.No. Name of Project Consultancy Package No. Names of Proposed


Key Personnel

1
2
3
4

130
Form-E2/T3

FIRMS
REFERENCES
Relevant Services Carried out in the Last SevenYears
Which Best Illustrate Qualifications

The following information should be provided in the format below for eachreference
assignment for which your firm, either individually as a corporate entity oras one of the
major companies within a consortium, was legally contracted by theclient:

Assignment Name: Country:


Location within Country : Professional Staff Provided
by your firm:
Name of Client : No. of Staff :
Address : No. of Staff Months :
Start Date Completion Date Approx. Value of
(Month / (Month / Year) Services : (in INR/current USD) :
Year)
Name of JV/Association Firm(s) if any : No. of Months of Professional
Staff provided by Associated Firm(s)
Status of your Company in the Assignment i.e., Sole/Lead Member/Other Member/Associate
Narrative Description of Project :
Description of Actual Services Provided by your Company:

Signature of Authorised
Representative

(Certificate from Employer regarding experience should be


furnished)

131
Form- T4

SITE APPRECIATION

Shall give details of site as per actual site visit and data provided in RFP and collected
from site supported by photographs to demonstrate that responsible personnel of the
Consultant have actually visited the site and familiarized with the salient
details/complexities and scope of services.

132
Form- T5

COMMENTS/ SUGGESTIONS OF CONSULTANT ON THE TERMS OF REFERENCE

1.

2.

3.

4.

5.

133
Form- T6

Composition of the Team Personnel and the task


Which would be assigned to each Team Member

I. Technical/Managerial Staff

S.No. Name Position Task Assignment

1.

2.

3.

4.

II. Support Staff

S.No. Name Position Task Assignment

1.

2.

3.

4.

134
Form- T7

APPROACH PAPER ON METHODOLOGY PROPOSED FOR PERFORMING


THE ASSIGNMENT

The approach and methodology will be detailed precisely under the following topics.
1) Composition of the team [not more than 1 page]
2) Methodology for services, surveying, data collection [not more than 2 pages]
and analysis
3) Quality Assurance system for consultancy assignment [not more than 1 page]

135
Form- T8

Details of Material Testing Facility

1. State whether the Applicant has in-house Material Testing Facility Available /
Outsourced / Not Available

2. In case answer to 1 is Available, attach a list of Lab equipment and facility for
testing of materials and location of laboratory

3. In case laboratory is located at a distance of more than 400 km from the project site,
state arrangements made/proposed to be made for testing of materials

4. In case answer to 1 is Outsourced/ Not Available state arrangements


made/proposed to be made for testing of materials

136
Facility for Field investigation and Testing

137
Form- T9

137
1. State whether the Applicant has in-house Facility for

a) Geo-technical investigation Available/ Outsourced/ Not


Available b) Pavement investigation Available/ Outsourced/
Not Available

2. In case answer to 1 is A v a i l a b l e a list of field investigation and testing


equipments available in-house

3. In case answer to 1 is Out sou rced/ Not A vail abl e arran gements made/proposed
to be made for each of above Field investigation and testing

4. For experience in LiDAR or equivalent technology for topographic survey, GPR


and Induction Locator or equivalent technologies for detection of sub-surface
utilities and digitization of cadastral maps for land acquisition, references need to
be provided in following format:

139
REFERENCES
Relevant Services Carried
Which Best Illustrate Qualifications

The following information should be provided in the format below for each reference
assignment for which your firm, either individually as a corporate entity or as one of the
major companies within a consortium, was legally contracted by the client:
Assignment Name: Country:
Location within Country : Professional Staff Provided
by your firm:
Name of Client : No. of Staff :
Address : No. of Staff Months :
Technology Used:
Start Date Completion Date Approx. Value of
(Month / (Month / Year) Services : (in INR/current USD) :
Year)
Name of JV/Association Firm(s) if any : No. of Months of Professional
Staff provided by Associated Firm(s)
Status of your Company in the Assignment i.e., Sole/Lead Member/Other Member/Associate
Narrative Description of Project :
Description of Actual Services Provided by your Company:

Signature of Authorised Representative

(Certificate from Employer regarding experience should be furnished)

139
Office Equipment and software

140
Form- T10

Attach a list of office equipment and software owned by the Applicant

140
Form- T11

Photo

Format of Curriculum Vitae (CV) For Proposed Key Staff

1. Proposed Position:

2. Name of Staff:

3. Date of Birth: (Please furnish proof of age)

4. Nationality:

5. Educational Qualification:
(Summarize college/university and other specialized education of staff
member, giving names of schools, dates attended and degrees obtained).
(Please furnish proof of qualification)

Contact Address with Phone and mobile


numbers:

6. Membership of Professional Societies:


7. Publication:
(List of details of major technical reports/papers published in recognized
national and international journals)
8. Employment Record:
(Starting with present position, list in reversed order, every employment held.
List all positions held by staff member since graduation, giving dates,
names of employing organization, title of positions held and location of
assignments. For experience period of specific assignment must be clearly
mentioned, also give client references, where appropriate).

141
9. Summary of the CV
(Furnish a summary of the above CV. The information in the summary shall
be precise and accurate. The information in the summary will have bearing on
the evaluation of the CV).
A)
Education:
i) Field of graduation and
year
ii) Field of post-graduation and
year
iii) Any other specific
qualification

B)
Experience
i) Total experience in highways:
Yrs.
ii) Responsibilities held: a)
Yrs.
b)
_Yrs.
c)
Yrs.
iii) Relevant experience: Yrs.

Certification:

142
C) Permanent Employment with the firm: Yrs.
If yes, how many years:
If no, what is the employment:
Arrangement with the firm?

1 I am willing to work on the project and I will be available for entire


duration of the project assignment and I will not engage myself in any
other assignment during the currency of this assignment on the project
2 I, the undersigned, certify that to the best of my knowledge and belief,
this bio data correctly describes myself my qualification and my experience.

Signature of the Candidate

Place Date

Signature of the Authorized Representative of the firm


Place
Date

Note: Each page of the CV shall be signed in ink by both the staff member and the
Authorized representative of the firm. Photocopies will not be considered for evaluation.

143
UNDERTAKING FROM THE PROFESSIONAL

I, . (Name and Address) have not left any assignment with the
consultants engaged by MORT&H/ contracting firm (firm to be supervised now) for any
continuing works of MORT&H without completing my assignment. I will be available for
the entire duration of the current project (named..). If I leave this assignment in the
middle of the completion of the work, I may be debarred for an appropriate period to be
decided by Chief Engineer, Highways, Mizoram PWD, I have also no objection if my services
are extended by Chief Engineer, Highways, Mizoram PWD for this work in future.

UNDERTAKING FROM CONSULTING FIRM

The undersigned on behalf of . (name of consulting firm) certify


that Shri(name of the proposed personnel and address) to the best of
our knowledge has not left his assignment with any other consulting firm engaged by
MORT&H / contracting firm (firm to be supervised now) for the ongoing projects. We
understand that if the information about leaving the past assignment with Chief Engineer,
Highways, Mizoram PWD without completing his assignment is known to , Chief Engineer,
Highways,Mizoram PWD would be at liberty to remove the personnel from the present
assignment and debar him for an appropriate period to be decided by Chief Engineer,
Highways, Mizoram PWD .

144
(Form-I)
Appendix IV

FINANCIAL PROPOSALS

FROM: TO:

Sir:

Subject: Consultants Services for

Regarding Price Proposal

I/We Consultant/consultancy firm herewith


enclose

*Price Proposal for selection of my/our firm/organization as Consultant for

Yours
faithfully, Signature

Full Name

Designation

Address

(Authorized Representative)

*The Financial proposal is to be filled strictly as per the format given in RFP.

145
(Form-II)

Format of Financial Proposal


Summary of Cost in Local Currency

No. Description Amount


(LC)*
(INR)
Local Consultants
I Remuneration for Local Staff (inclusive of per
diem allowance)
II Support Staff (inclusive of per diem allowance)
III Per diem allowance of expatriate personnel
IV Transportation
V Duty Travel to Site
VI Office Rent
VII Office Supplies, Utilities and Communication
VIII Office Furniture and Equipment (Rental)
IX Reports and Document Printing

X Surveys & Investigations

A Topographical Survey
B Investigations

Subtotal Local Consultants :


Foreign Consultants
F-I Remuneration for Expatriate Staff
F-II Mobilization and Demobilization
Total Cost Net of Tax :
Taxes I. Income Tax (Expatriate)
and II. Import duties
Duties III. Value added tax

Total cost net of service tax**


Service Tax
TOTAL COSTS (Including Service Tax)
LC* Local Currency
** Total Cost Net of Service Tax shall be considered for financial evaluation

Note: No escalation will be payable during the services


Insurances shall not be allowed separately .These will be incidental to main items.
Rates for all items shall be quoted in figures as well as in words.

146
(Form-III)

Estimate of Local Currency Costs

I. Remuneration for Local Staff (including per diem allowance)

I(a) Feasibility Study and preparation of DPR for Aizawl Bypass on NH-54 within Mizoram.

Rate SM Amt.(INR)
S.No. Position Name (INR)
Professional Staff
1 Team Leader cum Senior 7
Highway Engineer
2 Senior Bridge Engineer 3
3 Highway cum Pavement 3.5
Engineer
4 Material-cum-Geotechnical 5
Engineer- Geologist
5 Senior Survey Engineer 5
6 Traffic and Safety Expert 3.5
7 Environmental Specialist 2.5
8 Quantity Surveyor/ 4.5
Documentation Expert
Sub-Total:
Sub-Professional Staff (To be assessed by Consultant as per requirement
of assignment)
1
2
3
4
5
6
7
Sub-Total:

TOTAL

147
II.Support Staff

No. Position Name Staff Billing Amount


Months Rate( INR) ( INR)
1 Office Manager

2 Typist

3 Office Boy

4 Night Watchman

Total :

III. Transportation (Fixed costs)

S.No Description Qty. Nos. of Rate/ Amount


months Month (INR)
(INR)
1 The vehicles provided by the
Consultants shall include the cost for
rental, drivers, operation,
maintenance, repairs, insurance, etc.

A. For use of consultants

Total

IV. Duty Travel to Site (Fixed Costs)

Trips NO Rate (INR) Amount (INR)

V. Office Rent (Fixed Costs)

The rent cost includes maintenance, cleaning, repairs, etc.

months x
Total

148
VI. Office Supplies, Utilities and Communication (Fixed Costs)

No. Item Months Monthly Amount


Rate (INR) inINR.

1 Office Supplies Drafting

2 Supplies Computer

3 Running Costs

4 Domestic and International


Communication

TOTAL : ---------------------------

VII. Office Furniture and Equipment (Rental)

No Description Unit Quantity Rate Amount


. ( INR) (INR )
1 Office Furniture and Equipment LS
Total

149
VIII. Reports and Document Printing

No. Description No. of Rate per Amount


Copies Copy (INR.)
( INR. )
1 Monthly Report 3 Per
Month
2 Inception Report & QAP 3
3 Environment and Social Impact 4
Screening Report
4 Draft Feasibility Report 4
5 Final Feasibility Report 6
6 Strip Plan with L.A. Reports 6
7 Draft LA and Clearances I Report 4
8 Final LA and Clearances I Report 4

9 Draft Environmental Assessment 4


report & RAP
10 Final Environmental Assessment 6
report & RAP
11 Draft Detailed Design Report & 4
Drawings etc.
Draft EMP 4
12 Draft Bidding Documents 4
13 Final Detailed Project Report 6
with Bill of Quantities, Cost
Estimates, Updated Drawings etc.
Final EMP 6
14 Final Bidding Documents 6

15 Draft 3(a) ,3(A) and 3(D) 9


notification for land acquisition
( 3 copies each)
16 LA & Clearances II Report 6

Total

150
IX. Survey and Investigation
A. Topographical Survey (Fixed Rate)
No. Item Kms Rate per Amount
Km (INR)
(INR)
1 Topographic Survey including hire
charges for equipment and supply of
survey teams comprising of project
survey filed staff etc. inclusive of cost
of materials, labourer
2 Detailed topographic surveys using
mobile/ aerial LiDAR or equivalent
technology

B. Investigation (Fixed cost)

No. Description Quantity Amount


(INR)
1 Road and Bridge Inventory
2 BBD Test and Pavement Evaluation
3 Roughness Survey
4 Axle Load Survey
5 Material Survey and Investigation
6 Sub-grade Investigation
7 Traffic Survey
8 Socio-economic & Census
Survey/Studies
9 Land Acquisition Studies
10 Any other investigations/surveys
11 *Sub-Soil Rate Qty. Amount
Investigation (Rs)
(Boring)
a) Boring in all 1500m (for projects of
type of soils (other length < 110 km)
than hard rock) or
2000m (for projects of
length > 110 km)

200m (for projects of


length < 110 km)
b)Boring in hard or
rock 300m (for projects of
length > 110 km)
Total

151
Note: * Quantities of borings shall be taken from Financial Proposal Form No.V.
For financial evaluation, these quantities and rates quoted by the consultant will
be considered. However, Payment shall be made on the actual quantity of boring at
rates quoted above by the Consultant. which may be substantially more or less than the
estimated quantities.

152
(Form-IV)

Estimate of Costs for Expatriate Consultants (in Indian Rupees)

I. Remuneration of Expatriate Staff including per diem allowances

No. Positions Name Rate ( ) SM Amount ( )

Total :

II. Mobilization and Demobilization

1. International Airfares (Fixed costs)

Position Round Trips Rate Amount

Total

2 Inland Travel in Home Country (Fixed


Costs) Lump Sum

3. Other Miscellaneous expenses ( like DA, internal travel expenses


other incidentals)(fixed cost)
Lump Sum .

153
TENTATIVE QUANTITIES FOR SUB-SOIL INVESTIGATIONS
(BORING)

(Form V)

S. Stretch NH Approxi Package State Cumulative Tentative


No Proposed for DPR No. mate No. Quantities ( in m )
Length In Soils In hard
(in Km.) other than rock
hard rock
1 For projects of length < 110 As per As per List As per As per 1500 200
km List at at Annex-1 List at List at
Annex- Annex-1 Annex-
1 1

2 For projects of length > 110 As per As per List As per As per 2000 300
km - List at at Annex-1 List at List at
Annex- Annex-1 Annex-
1 1

154
Appendix-V

DETAILED EVALUATION CRITERIA

1. First Stage Evaluation -Proof of Eligibility (Para 12.1 of Data Sheet)

1.1 Eligibility criteria for sole applicant firm.


The sole applicant firm shall satisfy the following 3 (Three) Nos. of criteria.
(a) & (b) Firm should have experience of preparation of DPR/Feasibility of 4/6 lane of
aggregate length as given below. The firm should have also prepared DPR/Feasibility
of at least one project of 4/6 laning of minimum length as indicated below in the last
7 years (i.e. from 2008-09 onwards)

S. Package No. Tentative Minimum Minimum length of a Eligible Project (4/6


No. Length Aggregate Length lane)
required
DPR/ Feasibility = DPR = 0.4 x Feasibility = 0.6 x
Tentative Length Tentative Length Tentative Length
1 2 3 4 5 6

(c) Annual Average Turn Over for the last 3 years {In cases where, Audited/Certified copy of
Balance Sheet for the FY 2014-15 is available, last three years shall be counted from 2012-13 to 2014-
15. However, where audited/certified copy of the Balance Sheet for the FY 2014-15 is not
available (as certified by the Statutory auditor) then in such cases last three years shall be
considered from 2011-12 to 2013-14} of the firm from Consultancy services should be equal to more
than Rs 5 crore.

155
1.2 Eligibility criteria for Lead Partner/Other Partner in case of JV.

In case of JV, the Lead Partner should fulfill at least 75% of all eligibility requirements and the other
partner shall fulfill at least 50% of all eligibility requirements as given at 1.1 above. Thus a Firm
applying as Lead Partner/Other Partner in case of JV/Associate should satisfy the following
(a) & (b) Firm should have experience of preparation of DPR/Feasibility of 4/6 lane of
aggregate length as given below. The firm should have also prepared DPR/Feasibility of at least one
project of 4/6 laning of minimum length as indicated below in the last 7 years (i.e. from
2008-09 onwards

S. Package No. Minimum Aggregate Minimum length of a Eligible Project (4/ 6 lane)
No. Length required of
DPR/ Feasibility km)

DPR Feasibility

Lead in Other Lead in Other Lead in Other


JV Partner JV Partner in JV Partner
in JV JV in JV

156
c) Minimum Annual Average Turn Over for the last 3 years {In cases
where, Audited/Certified copy of Balance Sheet for the FY 2015-16 is available, last five years
shall be counted from 2012-13 to 2015-16. However, where audited/certified copy of the
Balance Sheet for the FY 2015-16 is not available (as certified by the Statutory auditor) then in
such cases last three years shall be considered from 2011-12 to 2015-16} of a firm
applying as Lead Partner/Other Partner in case of JV from Consultancy services should be as
given below:

No. Mode of Submission by a firm Annual Average Turn Over for the last 5 years

1 Lead Partner in a JV Rs 3.75 crore


2 Other Lead partner in a JV Rs 2.50 crore

Note: (i) Weightage to be given when experience by a Firm as Sole Firm/Lead Partner in a
JV/Other Partner in a JV/As Associate

No. Status of the firm in carrying Weightage for experience


out DPR/ Feasibility Study
1 Sole firm 100%
2 Lead partner in a JV 75%
3 Other partner in a JV 50 %
4 As Associate 25%

(ii) The experience of a firm in preparation of DPR for a private Concessionaire/contractor shall
not be considered

2. Second Stage Evaluation -Technical Evaluation (Para 12.2 of Data Sheet)

2.1. Firms Relevant Experience

For standard highways, the following is the break-up:

S.No Description Maximum Sub-


Points Points

1 Specific experience of the DPR consultancy related 15


to the assignment for eligibility

1.1 Aggregate Length of DPR / Feasibility study of 2/4/ 7.5


6 lane projects

1.1.1 More than the indicative Length of the package applied 5.5
for

1.1.2 More than 2 times the indicative length of the package 6.5

157
S.No Description Maximum Sub-
Points Points
applied for

1.1.3 More than 3 times the indicative length of the package 7.5
applied for

1.2 DPR for 2/4/6 laning projects each equal to or more 7.5
than 40 % of indicative length of a package applied
for (or Feasibility Study for 2/4/6 laning projects
each equal to or more than 60 % of indicative length
of a package applied for)

1.2.1 1 project 5.5

1.2.2 2 projects 6.5

1.2.3 3 or more projects 7.5

2 DPR of Bridge having length more than 60 m 5

2.1 1 bridge 2

2.2 2 bridges 3

2.3 3 bridges 4

2.4 4 or more bridges 5

3 Specific experience of firms in terms of turnover 5

3.1 Firms Average Turnover of last 3 years >= 10 crore 5

3.2 Firm Average Turnover of last 3 years > = 5 crore but 4


< 10 crore

3.3 Firm Average Turnover of last 3 years < 5 crore 0

158
For special projects such as special bridges, tunnels and expressways that require specialized capabilities and
skill sets, the following is the break-up:

S.No Description Maximum Sub-


Points Points

1 Specific experience of the DPR consultancy related 12


to the assignment for eligibility

1.1 Aggregate Length of DPR / Feasibility study of 2/4/ 6


6 lane projects

1.1.1 More than the indicative Length of the package applied 4


for

1.1.2 More than 2 times the indicative length of the package 5


applied for

1.1.3 More than 3 times the indicative length of the package 6


applied for

1.2 DPR for 2/4/6 laning projects each equal to or more 6


than 40 % of indicative length of a package applied
for (or Feasibility Study for 2/4/6 laning projects
each equal to or more than 60 % of indicative length
of a package applied for)

1.2.1 1 project 4

1.2.2 2 projects 5

1.2.3 3 or more projects 6

2 DPR of Bridge having length more than 60 m 4

2.1 1 bridge 1

2.2 2 bridges 2

2.3 3 bridges 3

2.4 4 or more bridges 4

3 Specific experience of firms in terms of turnover 4

159
S.No Description Maximum Sub-
Points Points

3.1 Firms Average Turnover of last 3 years >= 10 crore 4

3.2 Firm Average Turnover of last 3 years > = 5 crore but 3


< 10 crore

3.3 Firm Average Turnover of last 3 years < 5 crore 0

4 DPR for special category projects (Special bridges/ 5


tunnels or expressways, whichever applicable). It is
to be noted that either 4.1 or 4.2 shall be applicable,
and not both.

4.1 DPR of number of special bridges/ tunnels (if 5


applicable)

4.1.1 1 project 1

4.1.2 2 projects 2

4.1.3 3 projects 3

4.1.4 4 projects 4

4.1.5 5 or more projects 5

4.2 Aggregate length of DPR/ Feasibility study for 5


expressways

4.2.1 Upto 50km 2

4.2.2 50km to 100km 3

4.2.3 100km to 150km 4

4.2.4 More than 150 km 5

Note: In case feasibility study is a part of DPR services the experience shall be counted in DPR
only. In case bridge is included as part of DPR of highway the experience will be (1) and (2)

160
Note: (i) Weightage to be given when experience by a Firm as Sole Firm/Lead Partner in a
JV/Other Partner in a JV/As Associate

No. Status of the firm in carrying Weightage for experience


out DPR/ Feasibility Study

1 Sole firm 100 %

2 Lead partner in a JV 75%

3 Other partner in a JV 50 %

4 As Associate 25%

(ii) The experience of a firm in preparation of DPR for a private Concessionaire/contractor


shall not be considered.

2. 2. Adequacy of the proposed work plan and methodology in responding to the TOR

S. No. Description Max points

(i) Site Appreciation 2

(ii) Comments on TOR 1

(iii) Team Composition and Task assignment 1

(iv) Methodology 1

Total Points 5

Rating given below shall be applicable on all above

Below Average (50 %) Average (75%) Good


(90%) Excellent
(100%)

161
2.3 Material testing, Survey and investigation equipment and software proposed to be used

S.No Description Maximum Sub-


Points Points

1 Availability of in-house material testing facility 2

1.1 Available 2

1.2 Outsourced 1

1.3 Not Available 0

2 Field Investigation Facilities 3

2.1 Available 3

2.2 Outsourced 1.5

2.3 Not Available 0

3 Office Equipment and Software 3

3.1 Available 3

3.2 Outsourced 1.5

3.3 Not Available 0

4 Experience in LiDAR or equivalent technology for 4


topographic survey

4.1 1 project 1

4.2 2 projects 2

4.3 3 projects 3

4.4 4 or more projects 4

5 Experience in using GPR and Induction Locator or 4


equivalent technologies for detection of sub-surface
utilities

162
S.No Description Maximum Sub-
Points Points

5.1 1 project 1

5.2 2 projects 2

5.3 3 projects 3

5.4 4 or more projects 4

6 Experience in digitization of cadastral maps for 4


land acquisition

6.1 1 project 1

6.2 2 projects 2

6.3 3 projects 3

6.4 4 or more projects 4

163
2.4. Qualification and Competence of the Key Staff for adequacy of the Assignment. (Para
12.2 of Data Sheet and Enclosure II of TOR)

2.4.1 TEAM LEADER cum SENIOR HIGHWAY ENGINEER

S. No. Description Max.


I General Qualification Points 2
i) Degree in Civil Engineering or equivalent 5
2
ii) Post Graduation in Highway Engg./Structures/Traffic and Transportation/Soil 05
Mechanics and Foundation Engineering/Construction Management/Transportation
II Relevant Experience & Adequacy for the Project 6
a) Total Professional Experience 5
1
<20 years 0 4
20-25 years 11
>25-28 years 13
>28 years 14
(b) Experience in Highway Projects - Experience in Planning, project 2
preparation and design of Highway Projects (2/4/6 laning of 3
NH/SH/Expressways)
<15 years 0
15-20 years 17
>20 -25 years 21
>25 years 23
c) Experience in Similar Capacity 2
8
(i) In Feasibility of 2/4/6 laning works or DPR/IC/Construction Supervision of 1
major highway projects i.e. 2/4/6 laning of NH/SH/Expressways in Similar 9
Capacity ( Minimum Aggregate length of 80 km )
< 80km 0
80 km-150km 14
> 150km-250km 17
> 250km 19
(ii) In Feasibility of 2/4/6 laning works or DPR/IC/Construction Supervision of 9
major highway projects i.e. 2/4/6 laning of NH/SH/Expressways in Similar
Capacity- Number of Projects
2 projects 7
3- 5 projects 8
More than 5 projects 9
III Employment with Firm 1
0
Less than 1 Year 0
1-2 years 5
more than 2 years 10
Total 1
0
0

164
2.4.2 HIGHWAY cum PAVEMENT ENGINEER

S. Description Max.
No. Points
I General Qualification 2
i) Degree in Civil Engineering or equivalent 5
2
ii) Post graduation in Highway Engg/ 05
Transportation Engineering
II Relevant Experience & Adequacy for the Project 6
5
a) Total Professional Experience 1
4
<15 years 0
15-20 years 11
>20 -25years 13
>25 years 14
(b) Experience in Highway Projects - Experience in Design/ Pavement Design of 2
Highway Projects (2/4/6 laning of NH/SH/Expressways) 3
<10 years 0
10-15 years 17
>15-20 years 21
>20years 23
c) Experience in Similar Capacity 2
8
(i) In Design/ Pavement Design of Highway Projects (2/4/6 laning of 1
NH/SH/Expressways) in Similar Capacity (Minimum aggregate length 80 km) 9

<80km 0
80km-150km 14
>150km-250km 17
>250km 19
(ii) In Design/ Pavement Design of Highway Projects (2/4/6 laning of NH/SH/ 9
Expressways) in Similar Capacity Number of Projects
2 projects 7
3- 5 projects 8
More than 5 projects 9
III Employment with Firm 1
0
Less than 1 Year 0
1-2 years 5
more than 2 years 10
Total 1
0
0

165
2.4.3 SENIOR BRIDGE ENGINEER

S. Description Max. Points


No.
I General Qualification 25
i) Degree in Civil Engineering or equivalent 20
ii) Post Graduation in Structural Engineering/ Bridge Engineering 5
II Relevant Experience & Adequacy for the Project 65
a) Total Professional Experience 14
<15 years 0
15-20 years 11
>20 -25years 13
>25years 14
b) Experience in Bridge Projects 23
(i) Experience in project preparation and design of bridge projects 18
<10 years 0
10-15 years 13
>15 -20years 16
>20years 18
(ii) Experience of 2/4 lane configuration bridges 5
<2 Projects 0
2-4 Projects 4
> 4 projects 5
c) Experience as Senior Bridge Engineer or Similar Capacity in Highway 28
Design Consultancy Projects (2/4/6 laning of NH/SH/Expressways) involving
design of Major Bridges ( minimum 2 nos. of length more than 200m)
<2 numbers 0
2-4 numbers 22
5-6 numbers 25
> 6 numbers 28
III Employment with Firm 10

Less than 1 Year 0


1-2 years 5
more than 2 years 10
Total 100

166
2.4.4 TRAFFIC AND SAFETY EXPERT

S. No. Description Max. Points


I General Qualification 25
i) Degree in Civil Engineering 20
ii) Post graduation in Traffic Engineering /Transportation Engineering / 5
Transportation Planning
II Relevant Experience & Adequacy for the Project 65
a) Total Professional Experience 14
<10 years 0
10-15 years 11
>15-20 years 13
>20years 14
b) Experience in Highway Projects Experience on Similar Projects (2/4/6 23
laning of NH/SH/ Expressways)
<5 years 0
5-7 years 17
>7-10 years 21
>10years 23
c) Experience as Traffic and Safety Expert / Traffic Engineer or in Similar 28
Capacity in Highway Projects (2/4/6 laning of NH/SH/Expressways)
(Minimum aggregate length 80 km)
<80km 0
80km-150km 22
>150km -250km 25
>250km 28
III Employment with Firm 10

Less than 1 Year 0


1-2 years 5
more than 2 years 10
Total 100

167
2.4.5 MATERIAL ENGINEER cum GEOTECHNICAL ENGINEER cum GEOLOGIST

S. No. Description Max. Points


I General Qualification 25

i) Degree in Civil Engineering /M. Sc. in Geology 20

ii) Post graduation in Foundation Engineering / Soil Mechanics / Geo Tech Engineering 5
or Phd in Geology
II Relevant Experience & Adequacy for the Project 65

a) Total Professional Experience 14


<15 years 0
15-20 years 11
>20-25 years 13
>25 years 14
b) Experience in Highway Projects In Similar Projects (2/4/6 laning of 23
NH/SH/Expressways) in design and or Construction/ Construction Supervision
<8 years 0
8-10 years 17
>10 -12 years 21
>12years 23
c) Experience as Material cum Geo-technical Engineer or in Similar capacity 28
on Highway Projects (2/4/6 laning of NH/SH/Expressways) (Minimum aggregate
length 80 km)
<80km 0
80km-150km 22
>150km 250km 25
>250km 28
III Employment with Firm 10

Less than 1 Year 0


1-2 years 5
more than 2 years 10
Total 100

168
2.4.6 SENIOR SURVEY ENGINEER

S. No. Description Max. Points


I General Qualification 25
i) Degree or equivalent in Civil Engineering / Diploma in Civil Engineering / 20
Diploma in Surveying
ii) Post Graduation in Survey Engineering / Surveying / Remote Sensing 5
II Relevant Experience & Adequacy for the Project 65
a) Total Professional Experience 14
>15 years 0
15-20 years 11
>20-25 years 13
>25 years 14
b) Experience in Highway Projects 23
i) Experience in Similar Projects (2/4/6 laning of NH/SH/Expressways) in 18
project preparation/ Construction / Construction Supervision
<5years 0
5 -7 years 13
>7-10 years 16
>10 years 18
ii) Knowledge and understanding of Modern Computer based method of 5
Surveying
Yes 5
No 0
c) Experience as Survey Engineer or in Similar Capacity for project 28
preparation of highway project (2/4/6 laning of NH/SH/Expressways)
(Minimum Aggregate Length of to 80km)
>80km 0
80km-150km 22
>150km-250km 25
>250km 28
III Employment with Firm 10

Less than 1 Year 0


1-2 years 5
more than 2 years 10
Total 100

169
2.4.7 ENVIRONMENTAL SPECIALIST

S. No. Description Max. Points


I General Qualification 25
i) Degree in Civil Engineering / Environmental Engineering or Post Graduate in 20
Environmental Sciences
ii) Post Graduation in Environmental Engineering 5
II Relevant Experience & Adequacy for the Project 65

a) Total Professional Experience 14


<10 years 0
10-15 years 11
>15-20 years 13
>20 years 14
b) Experience in Highway Projects- Experience in Environment impact 23
assessment of Highway Projects (2/4/6 laning of NH/SH/Expressways)
<5 years 0
5 -7 years 17
>7-10 years 21
>10 years 23
c) Experience as Environmental Specialist or in Similar Capacity in Highway 28
Projects(2/4/6 laning of NH/SH/Expressways)
<2 projects 0
2- 4 projects 22
5-7 projects 25
>7 projects 28
III Employment with Firm 10

Less than 1 Year 0


1-2 years 5
more than 2 years 10
Total 100

170
2.4.8 QUANTITY SURVEYOR/DOCUMENTATION EXPERT

S. No. Description Max. Points


I General Qualification 25
i) Graduation or equivalent in Civil Engineering / Certificate course from Institution of 20
Quantity Surveying
ii) Graduation or equivalent in Civil Engineering 5
II Relevant Experience & Adequacy for the Project 65
a) Total Professional Experience 14
<15 years 0
15-20 years 11
>20-25 years 13
>25 years 14
b) Experience in Highway Projects- Experience in preparation of Bill of Quantities, 23
Contract documents and documentation for major highway projects (2/4/6 laning
of NH/SH/Expressways)
>5 years 0
5 -7 years 17
>7-10 years 21
>10 years 23
c) Experience as Quantity Surveyor / Documentation Expert or in Similar Capacity 28
in Highway Projects (2/4/6 laning of NH/SH/Expressways) (Minimum Aggregate
length of 80km)
>80km 0
80km-150km 22
>150km 250km 25
>250km 28
III Employment with Firm 10

Less than 1 Year 0


1-2 years 5
more than 2 years 10
Total 100

171
Assumptions to be made regarding Similar Capacity for various positions

1. Team Leader cum Senior Highway Engineer

i) On behalf of Consultant / Contractor: Team Leader/Senior Highway Engineer.

ii) In Government Organizations: Superintending Engineer (or equivalent) and

above

2. Senior Bridge Engineer

i) On behalf of Consultant: Senior Bridge Engineer/Bridge Engineer/Bridge

Design Engineer

ii) In Government Organizations: Executive Engineer (or equivalent) and above

3. Highway cum Pavement Engineer

i) On behalf of Consultant: Highway Engineer/Highway Design

Engineer/ Pavement Engineer.

ii) In Government Organizations: Executive Engineer (or equivalent) and above

4. Material Engineer cum Geo Technical Engineer- Geologist

i) On behalf of Consultant: Material Engineer/Material Expert/Geo

Technical Engineer

ii) In Government Organizations: Executive Engineer (or equivalent) and above

iii) On behalf of Contractor: Material Engineer/Material Expert/Geo

Technical Engineer/Manager (Material)

172
5. Traffic and Safety Expert

i) On behalf of Consultant: Traffic Engineer/Transportation Engineer/Road


Safety

Expert

ii) In Government Organizations: Executive Engineer (or equivalent) and above

iii) On behalf of Contractor : Traffic Engineer/Transportation

Engineer/ Road Safety Expert

6. Senior Survey Engineer

i) On behalf of Consultant: Senior Survey Engineer/ Survey Engineer/

Senior Surveyor

ii) In Government Organizations : Surveyor/Engineer (or equivalent)

iii) On behalf of Contractor: Senior Survey Engineer/Survey Engineer/

Senior Surveyor

7. Environmental Specialist

i) On behalf of Consultant /Contractor: Environmental Engineer/ Environmental

Specialist/ Environmental Expert

ii) In Government Organisation: Officers who has dealt environment/forest

matter.

8. Quantity Surveyor/Documentation Expert

i) On behalf of Consultant /Contractor: Quantity Surveyor

(ii) In Government Organizations : Assistant Engineer (or equivalent)

173
Appendix VI

DRAFT CONTRACT AGREEMENT

Between
Chief Engineer, Highways,Mizoram PWD
Tuikhuahtlang, Aizawl:Mizoram

and

M/s ..in JV with

M/s.

in Association with M/sand

For

Consultancy Services for preparation of Detailed Project


Report for Feasibility Study and preparation of DPR Aizawl By-
Pass on NH-54 within Mizoram.

(From km to km of NH in the State of )

174
CONTENTS

Sl. No. Description Page

No. I CONTRACT FORCONSULTANTS SERVICES

II GENERAL CONDITIONS OF CONTRACT

1. General Provisions
1.1 Definitions
1.2 Relation between the Parties
1.3 Law Governing the Contract
1.4 Language
1.5 Headings
1.6 Notices
1.7 Location
1.8 Authority of Member in Charge
1.9 Authorized Representatives
1.10 Taxes and Duties

2. Commencement, Completion, Modification and Termination of Contract


2.1 Effectiveness of Contract
2.2 Termination of Contract for Failure to Become Effective
2.3 Commencement of Services
2.4 Expiration of Contract
2.5 Entire Agreement
2.6 Modification
2.7 Force Majeure
2.7.1 Definition
2.7.2 No Breach of Contract
2.7.3 Measures to be Taken
2.7.4 Extension of Time
2.7.5 Payments
2.7.6 Consultation
2.8 Suspension
2.9 Termination
2.9.1 By the Client
2.9.2 By the Consultants
2.9.3 Cessation of Rights and Obligations
2.9.4 Cessation of Services
2.9.5 Payment upon Termination
2.9.6 Disputes about Events of Termination

3. Obligations of the Consultants


3.1 General
3.1.1 Standard of Performance
3.1.2 Law Governing Services3.2 Conflict of Interests

176
3.2.1 Consultants not to Benefit from Commissions,discounts etc.
3.2.2 Consultants and Affiliates not to be
otherwise interested in Project
3.2.3 Prohibition of Conflicting Activities
3.3 Confidentiality
3.4 Liability of the Consultants
3.5 Insurance to be taken out by the Consultants
3.6 Accounting, Inspection and Auditing
3.7 Consultants Actions requiring Clients prior Approval
3.8 Reporting Obligations
3.9 Documents prepared by the Consultants to be the
Property of the Client
3.10 Equipment and Materials furnished by the Client

4. ConsultantsPersonnel
4.1 General
4.2 Description of Personnel
4.3 Approval of Personnel
4.4 Working Hours, Overtime, Leave etc.
4.5 Removal and/or Replacement of Personnel
4.6 Resident Project Manager

5. Obligations of the Client


5.1 Assistance and Exemptions
5.2 Access to Land
5.3 Change in the Applicable Law
5.4 Services, Facilities and Property of the Client
5.5 Payment

6. Payment to the Consultants


6.1 Cost Estimates; Ceiling Amount
6.2 Currency of Payment
6.3 Mode of Billing and Payment

7. Responsibility for accuracy of the project document


7.1 General
7.2 Retention money
7.3 Penalty
7.4 Action for deficiency in services

8. Fairness and Good Faith


8.1 Good Faith
8.2 Operation of the Contract

9. SETTLEMENT OF DISPUTES
9.1 Amicable Settlement
9.2 Dispute Settlement

177
III. SPECIAL CONDITIONS OF CONTRACT IV.

APPENDICES

Appendix A: Terms of reference containing, inter-alia,


the Description of the Services and
Reporting Requirements

Appendix B: Consultants Sub consultants, Key Personnel and Sub Professional


Personnel, Task assignment, work programme, manning schedule,
qualification requirements of key personnel, schedule for
submission of various report.
Appendix C: Hours of work for Consultants Personnel
Appendix D: Duties of the Client
Appendix E: Cost Estimate
Appendix F: Minutes of Financial/ Contract Negotiations with the Consultant
Appendix G: Copy of letter of invitation
Appendix H: Copy of letter of acceptance
Appendix I(1): Format for Bank Guarantee for Performance Security for individual
work Appendix I(2): Format for Bank Guarantee for Performance Security for a number
of works Appendix J : Minutes of the Pre-bid meeting

178
DRAFT CONTRACT FOR CONSULTANTS SERVICES

179
INDIA

CONTRACT FOR CONSULTANTS


SERVICES

Consultancy Services for Feasibility Study and preparation of DPR


for Aizawl Bypass on NH-54 within Mizoram.
(From km to km Of NH.. in the State of .)

This CONTRACT (hereinafter called the Contract) is made on the ---------- day of the month of ---
--------------2016 , between, on the one hand Chief Engineer, Highways (hereinafter called the
Client) and, on the other hand,M/s ------------------------------------------ in JV with ---------------
------------------- and in Association with . (hereinafter
called the Consultants).

WHEREAS
(A) the Client has requested the Consultants to provide certain consulting services as
defined in the General Conditions attached to this Contract (hereinafter called the
Services);

(B) the Consultants, having represented to the Client that they have the required professional
skills, personnel and technical resources, have agreed to provide the Services on the
terms and conditions set forth in this Contract;

NOW THEREFORE the parties hereto hereby agree as follows:

1 The following documents attached hereto shall be deemed to form an integral


part of this Contract:

(a) The General Conditions of Contract (hereinafter called GC);

(b) The Special Conditions of contract (hereinafter called SC);

(c) The following Appendices:

Appendix A: Terms of reference containing, inter-alia, the Description of the Services


and Reporting Requirements

Appendix B: Consultants Sub consultants, Key Personnel and Sub Professional


Personnel, Task assignment, work programme, manning schedule,
qualification requirements of key personnel, and schedule for submission of
various report.

Appendix C: Hours of work for Consultants Personnel


Appendix D: Duties of the Client

Appendix E: Cost Estimate

Appendix F: Minutes of Financial/ Contract Negotiations with the Consultant

Appendix G: Copy of letter of invitation

180
Appendix H: Copy of letter of acceptance

Appendix I: Copy of Bank Guarantee for Performance Security

Appendix-J: Minutes of the pre-bid meeting

2. The mutual rights and obligations of the Client and the Consultants shall be as set
forth in the Contract; in particular:

(a) The Consultants shall carry out the Services in accordance with the provisions of
the Contract; and

(b) Client shall make payments to the Consultants in accordance with


the provisions of the Contract.

IN WITNESS WHEREOF, the Parties hereto have caused this Contract to be signed in
their respective names as of the day and year first above written.

FOR AND ON BEHALF OF Witness


(Chief Engineer, Highways)
1 Signature Name
Address
By
Authorized Representative 2. Signature
Name
Address

FOR AND ON BEHALF OF Witness


(Consultant)

1. Signature
Name
Address
By
Authorised Representative 2. Signature
Name
Address

181
GENERAL CONDITIONS OF CONTRACT

182
GENERAL CONDITIONS OF CONTRACT

1. GENERAL PROVISIONS

1.1 Definitions
Unless the context otherwise requires, the following terms whenever used in this
Contract have the following meanings:

(a) Applicable Law means the laws and any other instruments having the force of lawin
the Governments country as they may be issued and in force from time to time;

(b) Contract means the Contract signed by the Parties, to which these General
Conditions of Contract are attached, together with all the documents listed in Clause
1 of such signed Contract;

(c) Effective Date means the date on which this Contract comes into force and effect
pursuant to Clause GC 2.1;

(d) foreign currency means any currency other than the currency of the Government;

(d) GC means these General Conditions of Contract;

(f) Government means the Government of India;

(g) local currency means the currency of the Government;

(h) Member, in case the Consultants consist of a joint venture or consortium of


more than one entity, means any of these entities, and Members means all of these
entities;

(i) Personnel means persons hired by the Consultants or by any Sub consultant
as employees and assigned to the performance of the Services or any part thereof;
foreign Personnel means such persons who at the time of being so hired had their
domicile outside India; and local Personnel means such persons who at the time
of being so hired had their domicile inside India;

(j) Party means the Client or the Consultants, as the case may be, and Parties means
both of them;

(k) Services means the work to be performed by the Consultants pursuant to this
Contract for the purposes of the Project, as described in Appendix A hereto;

(l) SC means the Special Conditions of Contract by which these General


Conditions of Contract may be amended or supplemented;

(m) Sub consultant means any entity to which the Consultants subcontract any part
of the Services in accordance with the provisions of Clause GC 3.7; and

(n) Third Party means any person or entity other than the Government, the Client, the
Consultants or a Sub consultant

183
1.2 Relation between the Parties
Nothing contained herein shall be construed as establishing a relation of master and servant
or of agent and principal as between the Client and the Consultants. The Consultants,
subject to this Contract, have complete charge of Personnel performing the Services and
shall be fully responsible for the Services performed by them or on their behalf hereunder.

1.3 Governing Law and Jurisdiction


This Contract, its meaning and interpretation, and the relation between the Parties shall be
governed by the Applicable Laws of India and the Courts at shall have exclusive
jurisdiction over matters arising out of or relating to this Agreement.

1.4 Language
This Contract has been executed in the language specified in the SC, which shall be the
binding and controlling language for all matters relating to the meaning or interpretation of
this Contract.

1.5 Table of Contents and Headings


The table of contents, headings or sub-headings in this agreement are for convenience for
reference only and shall not be used in, and shall not limit, alter or affect the construction
and interpretation of this Contract.

1.6 Notices
1.6.1 Any notice, request or consent required or permitted to be given or made pursuant to
this Contract shall be in writing. Any such notice, request or consent shall be deemed
to have been given or made when delivered in person to an authorized representative
of the Party to whom the communication is addressed, or when sent by registered
mail, facsimile or e-mail to such Party at the address specified in the SC.

1.6.2 Notice will be deemed to be effective as specified in the SC.


1.6.3 A party may change its address for notice hereunder by giving the other
Party notice of such change pursuant to the provisions listed in the SC with
respect to Clause GC 1.6.2.

1.7 Location

The Services shall be performed at such locations as are specified in Letter of Acceptance
(Appendix-I) hereto and, where the location of a particular task is not so specified, at such
locations, whether in India or elsewhere, as the Client may approve.

1.8 Authority of Member in Charge


In case the Consultants consist of a joint venture of more than one entity, with or without
an Associate the Members hereby authorize the entity specified in the SC to act on their
behalf in exercising all the Consultants rights and obligations towards the Client
under this Contract, including without limitation the receiving of instructions and
payments from the Client.

184
1.9 Authorized Representatives
Any action required or permitted to be taken, and any document required or permitted to
be executed, under this Contract by the Client or the Consultants may be taken or executed
by the officials specified in the SC.

1.10 Taxes and Duties


Unless otherwise specified in the SC, the Consultants shall pay all such taxes, duties, fees
and other impositions as may be levied under the Applicable Law.

2. COMMENCEMENT, COMPLETION, MODIFICATION AND


TERMINATION OF CONTRACT

2.1 Effectiveness of Contract


This Contract shall come into force and effect on the date of the Clients notice to the
Consultants instructing the Consultants to begin carrying out the Services. This notice shall
confirm that the effectiveness conditions, if any, listed in the SC have been met.

2.2 Termination of Contract for Failure to Become Effective


If this Contract has not become effective within such time period after the date of the
Contract signed by the Parties as shall be specified in the SC, either Party may, by not less
than four (4) weeks written notice to the other Party, declare this Contract to be null and
void, and in the event of such a declaration by either Party, neither Party shall have any
claim against the other Party with respect hereto.

2.3 Commencement of Services


The Consultants shall begin carrying out the Services at the end of such time period after
the Effective Date as shall be specified in the SC.

2.4 Expiration of Contract


Unless terminated earlier pursuant to Clause GC 2.9 hereof, this Contract shall expire when
services have been completed and all payments have been made at the end of such
time period after the Effective Date as shall be specified in the SC.

2.5 Entire Agreement


This Contract contains all covenants, stipulations and provisions agreed by the Parties. No
agent or representative of either Party has authority to make, and the Parties shall not be
bound by or be liable for, any statement, representation, promise or agreement not set
forth herein.

2.6 Modification
Modification of the terms and conditions of this Contract, including any modification of the
scope of the Services, may only be made by written agreement between the Parties. Pursuant
to Clause GC 7.2 hereof, however, each party shall give due consideration to any proposals for
modification made by the other Party.

2.7 Force Majeure

185
2.7.1 Definition
(a) For the purposes of this Contract, Force Majeure means an event which is beyond
the reasonable control of a Party, and which makes a Partys performance of its
obligations hereunder impossible or so impractical as reasonably to be considered
impossible in the circumstances, and includes, but is not limited to, war, riots, civil
disorder, earthquake, fire, explosion, storm, flood or other adverse weather conditions,
strikes, lockouts or other industrial action (except where such strikes, lockouts or other
industrial action are within the power of the Party invoking Force Majeure to prevent),
confiscation or any other action by government agencies.
(b) Force Majeure shall not include (i) any event which is caused by the negligence
or intentional action of a Party or such Partys Sub consultants or agents or employees,
nor (ii) any event which a diligent Party could reasonably have been expected to both
(A) take into account at the time of the conclusion of this Contract and (B) avoid or
overcome in the carrying out of its obligations hereunder.
(c) Force Majeure shall not include insufficiency of funds or failure to make any
payment required hereunder.

2.7.2 No Breach of Contract


The failure of a Party to fulfill any of its obligations hereunder shall not be considered to be a
breach of, or default under, this Contract insofar as such inability arises from an event of
Force Majuere, provided that the Party affected by such an event has taken all reasonable
precautions, due care and reasonable alternative measures, all with the objective of carrying
out the terms and conditions of this Contract.

2.7.3 Measures to be Taken


(a) A party affected by an event of Force Majeure shall take all reasonable measures to remove such
Partys inability to fulfill its obligations hereunder with a minimum of delay.

(b) A party affected by an event of Force Majuere shall notify the other Party of such event as
soon as possible, and in any event not later than fourteen (14) days following the occurrence of
such event, providing evidence of the nature and cause of such event, and shall similarly give
notice of the restoration of normal conditions as soon as possible.

(c) The Parties shall take all reasonable measures to minimize the consequences of any event of Force
Majeure.

2.7.4 Extension of Time


Any period within which a Party shall, pursuant to this Contract, complete any action or task,
shall be extended for a period equal to the time during which such Party was unable to perform
such action as a result of Force Majeure.

2.7.5 Payments
During the period of their inability to perform the Services as a result of an event of Force
Majeure, the Consultants shall be entitled to be reimbursed for additional costs reasonably
and necessarily incurred by them during such period for the purposes of the Services and in
reactivating the Services after the end of such period.

186
2.7.6 Consultation
Not later than thirty (30) days after the Consultants, as the result of an event of Force Majeure,
have become unable to perform a material portion of the Services, the Parties shall consult
with each other with a view to agreeing on appropriate measures to be taken in the
circumstances.

2.8 Suspension

The Client may, by written notice of suspension to the Consultants, suspend all payments to
the Consultants hereunder if the Consultants fail to perform any of their obligations under this
Contract, including the carrying out of the Services, provided that such notice of suspension (i)
shall specify the nature of the failure, and (ii) shall request the Consultants to remedy such
failure within a period not exceeding thirty (30) days after receipt by the Consultants of such
notice of suspension.

2.9 Termination
2.9.1 By the Client
The Client may, by not less than thirty (30) days written notice of termination to the
Consultants (except in the event listed in paragraph (f) below, for which there shall be a written
notice of not less than sixty (60) days), such notice to be given after the
occurrence of any of the events specified in paragraphs (a) through (f) of this Clause2.9.1,
terminate this Contract:

(a) if the Consultants fail to remedy a failure in the performance of their obligations are
under, as specified in a notice of suspension pursuant to Clause 2.8 hereinabove, within
thirty (30) days of receipt of such notice of suspension or within such further period as
the Client may have subsequently approved in writing;

(b) if the Consultants become (or, if the Consultants consist of more than one entity, if
any of their Members becomes) insolvent or bankrupt or enter into any agreements
with their creditors for relief of debt or take advantage of any law for the benefit of
debtors or go into liquidation or receivership whether compulsory or voluntary;

(c) if the Consultants fail to comply with any final decision reached as a result of
arbitration proceedings pursuant to Clause 8 hereof;

(d) if the Consultants submit to the Client a statement which has a material effect on the
rights, obligations or interests of the Client and which the Consultants know to be false;

(e) if, as the result of Force Majeure, the Consultants are unable to
perform a material portion of the Services for a period of not less than sixty (60)
days; or

(f) if the Client, in its sole discretion and for any reason whatsoever, decides
to terminate this Contract.

187
2.9.2 By the Consultants
The Consultants may, by not less than thirty (30) days written notice to the Client,
such notice to be given after the occurrence of any of the events specified in paragraphs
(a) through (d) of this Clause 2.9.2, terminate this Contract:
(a) if the Client fails to pay any money due to the Consultants pursuant to this contract
and not subject to dispute pursuant to Clause 8 hereof within forty-five(45)
days after receiving written notice from the Consultants that such payment is
overdue;
(b) if the Client is in material breach of its obligations pursuant to this Contract
and has not remedied the same within forty-five (45) days (or such longer period
as the Consultants may have subsequently approved in writing) following
the receipt by the Client of the Consultants notice specifying such breach;
(c) if, as the result of Force Majeure, the Consultant are unable to perform a material
portion of the Services for a period of not less than sixty (60) days; or
(d) if the Client fails to comply with any final decision reached as a result of
arbitration pursuant to Clause 8 hereof.

2.9.3 Cessation of Rights and Obligations


Upon termination of this Contract pursuant to Clauses 2.2 or 2.9 hereof, or upon
expiration of this Contract pursuant to Clause 2.4 hereof, all rights and obligations of the
Parties hereunder shall cease, except (i) such rights and obligations as may have
accrued on the date of termination or expiration, (ii) the obligation of confidentiality set
forth in Clause 3.3 hereof, (iii) the Consultants obligation to permit inspection, copying
and auditing of their accounts and records set forth in Clause 3.6 (ii) hereof, and (iv) any
right which a Party may have under the Applicable Law.

2.9.4 Cessation of Services


Upon termination of this Contract by notice of either Party to the other pursuant to
Clauses 2.9.1 or 2.9.2 hereof, the Consultants shall, immediately upon dispatch or receipt of
such notice, take all necessary steps to bring the Services to a close in a prompt
and orderly manner and shall make every reasonable effort to keep expenditures for this
purpose to a minimum. With respect to documents prepared by the Consultants and
equipment and materials furnished by the Client, the Consultants shall proceed as
provided, respectively, by Clauses 3.9 or 3.10 hereof.

2.9.5 Payment upon Termination


Upon termination of this Contract pursuant to Clauses 2.9.1 or 2.9.2 hereof, the Client
shall make the following payments to the Consultants (after offsetting against these
payments any amount that may be due from the Consultant to the Client):

(i) remuneration pursuant to Clause 6 hereof for Services satisfactorily performed


prior to the effective date of termination.
(ii) reimbursable expenditures pursuant to Clause 6 hereof for
expenditures actually incurred prior to the effective date of termination; and
(iii) except in the case of termination pursuant to paragraphs (a) through (d) of
Clause 2.9.1 hereof, reimbursement of any reasonable cost incident to the prompt and
orderly termination of the Contract including the cost of the return travel of the
Consultants personnel and their eligible dependents.

188
2.9.6 Disputes about Events of Termination

If either Party disputes whether an event specified in paragraphs (a) through (e) of
Clause
2.9.1 or in Clause 2.9.2 hereof has occurred, such Party may, within forty-five(45) days
after receipt of notice of termination from the other Party, refer the matter to arbitration
pursuant to Clause 8 hereof, and this Contract shall not be terminated on account of such
event except in accordance with the terms of any resulting arbitral award.

3. OBLIGATIONS OF THE CONSULTANTS


3.1
General

3.1.1 Standard of Performance


The Consultants shall perform the Services and carry out their obligations here under with
all due diligence, efficiency and economy, in accordance with generally accepted
professional techniques and practices, and shall observe sound management practices, and
employ appropriate advanced technology and safe and effective equipment, machinery,
materials and methods. The Consultants shall always act, in respect of any matter
relating to this Contract or to the Services, as faithful advisers to the Client, and
shall at all times support and safeguard the Client's legitimate interests in any dealings
with Sub consultants or Third Parties.

3.1.2 Law Governing Services

The Consultants shall perform the Services in accordance with the Applicable Law and
shall take all practicable steps to ensure that any Sub consultants, as well as the
Personnel and agents of the Consultants and any Sub consultants, comply with the
Applicable Law. The Client shall advise the Consultants in writing of relevant local
customs and the Consultants shall, after such notifications, respect such customs.

3.2 Conflict of Interests

3.2.1 Consultants not to Benefit from Commissions, Discounts, etc.

The remuneration of the Consultants pursuant to Clause 6 hereof shall constitute the Consultants'
sole remuneration in connection with this Contract or the Services and the Consultants shall not
accept for their own benefit any trade commission, discount or similar payment in connection
with activities pursuant to this Contract or to the Services or in the Discharge of their obligations
hereunder, and the Consultants shall use their best efforts to ensure that any Sub consultants, as
well as the Personnel and agents of either of them, similarly shall not receive any such additional
remuneration.

3.2.2 Consultants and Affiliates not to be otherwise interested in Project

The Consultants agree that, during the term of this Contract and after its termination, the Consultants
and any entity affiliated with the Consultants, as well as any Sub consultant and any entity affiliated
with such Sub consultant, shall be disqualified from providing goods, works or services (other than
the Services and any continuation thereof) for any project resulting from or closely related to the
Services.
189
3.2.3 Prohibition of Conflicting Activities

Neither the Consultants nor their Sub consultants nor the Personnel of either of them
shall engage, either directly or indirectly, in any of the following activities:

(a) during the term of this Contract, any business or professional activities in the
Government's country which would conflict with the activities assigned to them under this
Contract; or

(b) after the termination of this Contract, such other activities as may be specified in the SC.

3.3 Confidentiality

The Consultants, their Sub consultants and the Personnel of either of them shall not,
either during the term or within two (2) years after the expiration of this
Contract, disclose any proprietary or confidential information relation to the Project, the
Services, this Contract or the Client's business or operations without the prior written
consent of the Client.

3.4 Liability of the Consultants

Subject to additional provisions, if any, set forth in the SC, the Consultants'
liability under this Contract shall be as provided by the Applicable Law.

3.5 Insurance to be taken out by the Consultants

The Consultants (i) shall take out and maintain, and shall cause any Sub consultants to take
out and maintain, at their (or the Sub consultants', as the case may be) own cost but on
terms and conditions approved by the Client, insurance against the risks, and for the
coverage, as shall be specified in the Special Conditions (SC), and (ii) at the Client's
request, shall provide evidence to the Client showing that such insurance has been taken
out and maintained and that the current premiums therefore have been paid.

3.6 Accounting, Inspection and Auditing

The Consultants (i) shall keep accurate and systematic accounts and records in respect of
the Services hereunder, in accordance with internationally accepted accounting principles
and in such form and detail as will clearly identify all relevant time charges and cost, and
the bases thereof (including the bases of the Consultants' costs and charges), and (ii) shall
permit the Client or its designated representative periodically, and up to one year from the
expiration or termination of this Contact, to inspect the same and make copies thereof as
well as to have them audited by auditors appointed by the Client.

3.7 Consultants' Actions requiring Client's prior Approval

The Consultants shall obtain the Client's prior approval in writing before taking
any of the following actions:

(a) appointing such members of the Personnel as are listed in Appendix B;

190
(b) entering into a subcontract for the performance of any part of the Services, it
being understood (i)that the selection of the Sub-consultant and the terms and
conditions of the subcontract shall have been approved in writing by the Client
prior to the execution of the subcontract, and (ii) that the Consultants shall remain
fully liable for the performance of the Services by the Sub-consultant and its
Personnel pursuant to this Contract;
(c) any other action that may be specified in the SC.

3.8 Reporting Obligations

The Consultants shall submit to the Client the reports and documents specified in Appendix A/E
here to, in the form, in the numbers and within the time periods set forth in the said Appendix.

3.9 Documents prepared by the Consultants to be the Property of the Client

All plans, drawings, specifications, designs, reports and other documents prepared by the
Consultants in performing the Services shall become and remain the property of the Client, and
the Consultants shall, not later than upon termination or expiration of this Contract, deliver
all such documents to the Client, together with a detailed inventory thereof. The Consultants
may retain a copy of such documents. Restrictions about the future use of these documents, shall
be as specified in the SC.

3.10 Equipment and Materials furnished by the Client

Equipment and materials made available to the Consultants by the Client, or purchased by
the Consultants with funds provided by the Client, shall be the property of the Client and shall be
marked accordingly. Upon termination or expiration of this Contract, the Consultants shall make
available to the Client an inventory of such equipment and materials and shall dispose of such
equipment and materials in accordance with the Client's I instructions. While in possession of such
equipment and materials, the Consultants, unless otherwise instructed by the Client in writing,
shall insure them in an amount equal to their full replacement value.

4. CONSULTANTS' PERSONNEL

4.1 General

The Consultants shall employ and provide such qualified and experienced Personnel as are
required to carry out the Services.

4.2 Description of Personnel

(a) The titles, agreed job descriptions, minimum qualification and estimated periods
of engagement in the carrying out of the Services of each of the Consultants' Key
Professional / Sub Professional Personnel are described in Appendix B.

(b) If required to comply with the provisions of Clause 3.1.1 of this Contract, adjustments
with respect to the estimated periods of engagement of Key Professional / Sub
Professional Personnel set forth in Appendix B may be made by the Consultants by
written notice to the Client, provided
(i) that such adjustments shall not alter the originally estimated period of engagement of
any

191
individual by more than 10% or one week, whichever is larger, and
(ii) that the aggregate of such adjustments shall not cause payments under this Contract to
exceed the ceilings set forth in Clause 6.1 (b) of this Contract. Any other such
adjustments shall only be made with the Client's written approval.

(c) If additional work is required beyond the scope of the Services specified in Appendix A, the
estimated periods of engagement of Key Personnel set forth in Appendix B may be
increased by agreement in writing between the Client and the Consultants.
4.3 Approval of Personnel

The Key Personnel and Sub consultants listed by title as well as by name in Appendix B
are hereby approved by the Client. In respect of other Key Personnel which the Consultants
propose to use in the carrying out of the Services, the Consultants shall submit to the Client
for review and approval a copy of their biographical data. If the Client does not object in
writing (stating the reasons for the objection) within twenty-one (21) calendar days from
the date of receipt of such biographical data, such Key Personnel shall be deemed to have
been approved by the Client.

4.4 Working Hours, Overtime, Leave, etc.

(a) Working hours and holidays for Key Professional / Sub Professional Personnel are set
forth in Appendix C hereto. To account for travel time, foreign Personnel carrying out
Services inside the Government's country shall be deemed to have commenced (or
finished) work in respect of the Services such number of days before their arrival in (or
after their departure from) the Government's country as
is specified in Appendix C
hereto.

(b) The Key Professional / Sub Professional Personnel shall not be entitled to be paid
for overtime nor to take paid sick leave or vacation leave except as specified in Appendix C
hereto, and except as specified in such Appendix, the Consultants' remuneration shall be
deemed to cover these items. All leave to be allowed to the Personnel is included in the
staff- months of service set for in Appendix B. Any taking of leave by Personnel shall be
subject to the prior approval of the Client by the Consultants, who shall ensure that
absence for leave purposes will not delay the progress and adequate supervision of the
Services.

4.5 Removal and/or Replacement of Personnel


Removal and/or replacement of Personnel shall be regulated as
under:

4.5.1 In case notice to commence services pursuant to Clause 2.1 of this Contract is not
ordered by Client within 120 days of negotiations the key personnel can excuse
themselves on valid grounds, e.g., selection on some other assignment, health problem
developed after contract negotiation, etc. In such a case no penalty shall be levied on
the Firm or on the person concerned. The firm shall however be asked to give a
replacement by an equal or better scoring person, whenever mobilization is ordered.

4.5.2 In case notice to commence services is given within 120 days of negotiations
the replacement shall be as below:

192
a. Replacement up to 33%: Replacement shall be by an equal or better scoring
person.Reduction in remunerations for the balance period shall be @ 5% of the
monthly rate.
b. Replacement of more than 33% and up to 50%: Replacement shall be by an
equal or better scoring person. Reduction in remunerations for the balance period
shall be @,10% of the monthly rate.
c. Replacement beyond 50% and upto 66% . Replacement shall be by an equal or
better scoring person. Reduction in remunerations for the balance period shall be @
15% of the monthly rate.
d. Replacement beyond 66 %shall normally not be considered. However in
exceptional circumstances, where it becomes absolutely essential the
remunerations of the substitute shall be reduced by 50 % of the original
person replaced. Replacement shall be by an equal or better scoring person, The
Department may initiate action for termination/debarment of such consultant for
future projects of Chief Engineer, Highways, Mizoram PWD for a period of 6
months to 24 months depending upon the severity of case.
4.5.3 Replacement after original contract period is over:

There shall be no limit on the replacements and no reduction in remunerations


shall be made. The replacement shall however be of equal or better score.

4.5.4 If the Employer (i) finds that any of the Personnel has committed serious misconduct or
has been charged with having committed a criminal action or (ii) has reasonable
ground to be dissatisfied with the performance of any of the Personnel, then the
consultant shall, at the Employers written request specifying the grounds therefore,
forthwith provide a replacement with qualifications and experience acceptable to him.

4.5.5 If the team leader or any other key personnel/ specialist considered pivotal to the project
is replaced, the substitute may be interviewed by Chief Engineer, Highways, Mizoram
PWD to assess their merit and suitability.

4.5.6 If any member of the approved team of a consultant engaged by Chief Engineer,
Highways, Mizoram PWD leaves that consultant before completion of the job, he shall be
barred for a period of 6 months to 24 months from being engaged as a team
member of any other consultant working (or to be appointed) for any other Chief
Engineer, Highways , Mizoram PWD projects.

4.5.7 In exceptional situations where the replacement with equivalent or better qualification is
not available, replacement with lower qualifications than the originally approved may be
accepted with reduction in remuneration as per the procedure prescribed below. This kind
of relaxation shall however, be limited to replacement of 2 key personnel only in one
consultancy contract package.

i) The new proposed personnel as a replacement has to be evaluated as per the criteria fixed
at the time of evaluation of original proposal and marks/rating and then:

-If the original personnel (included in the original proposal based on which the contract
was awarded) is to be replaced at the instruction of Chief Engineer, Highways, Mizoram
PWD and the new proposed personnel is having less qualification/ experience i.e
marks/rating (but

193
fulfilling the Minimum requirement as per TOR, his remuneration would be reduced by
15% over and above the stipulated conditions in the contract because of less qualified
personnelabove the stipulated conditions in the contract because of less qualified personnel

-If the original personnel (included in Contract Agreement) is to be replaced by the


Consulting firm and the new proposed personnel is having less qualification/ experience
(marks/rating), then his remuneration would be decreased proportionally in comparison to
the marks of the original personnel. This will also take into account the contract condition
and if the proposed reduction is less than that stipulated in contract condition, it would be as
per the contract provision.

It will be ensured that the new proposed personnel should score at least 75% of the marks of
the originally approved key personnel. Both the Consulting firm and the proposed personnel
should give the undertaking in the format available in Form VII of Appendix II along with
the replacement CV.

ii) The CV should be signed by personnel and the consulting firm in every page. If the CV
is found incorrect at later date, the personnel accepted would be removed from the
assignment and debarred from further Chief Engineer, Highways, Mizoram PWD works
for an appropriate period to be decided by Chief Engineer, Highways, Mizoram PWD and
the new proposed personnel in place of removed personnel would be paid 15% less salary
than the original personnel. 15% reduction in the salary will be imposed as penalty
for submitting the incorrect information. This penalty will be imposed only once. If the
same consulting firm submits incorrect information again second time, necessary action will
be taken by Chief Engineer, Highways , Mizoram PWD to blacklist the firm.

4.6 Resident Project Manager

If required by the SC, the Consultants shall ensure that at all times during the Consultants'
performance of the Services in the Government's country a resident project manager,
acceptable to the Client, shall take charge of the performance of such Services.

5. OBLIGATION OF THE CLIENT

5.1 Assistance and Exemptions Unless otherwise specified in the SC, the Client shall use its
best efforts to ensure that the Government shall:

(a) provide the Consultants, Sub consultants and Personnel with work permits and such
other documents as shall be necessary to enable the Consultants, Sub consultants or
Personnel to perform the Services

(b) assist for the Personnel and, if appropriate, their eligible dependents to be provided
promptly with all supporting papers for necessary entry and exit visas, residence permits,
exchange permits and any other documents required for their stay in India;

(c) facilitate prompt clearance through customs of any property required for the Services;

(d) issue to officials, agents and representatives of the Government all such instructions as
may be necessary or appropriate for the prompt and effective implementation of the
Services;

194
5.2 Access to Land.

The client warrants that the consultant shall have , free of charge, unimpeded access to all
land in the Governments country in respect of which access is required for the performance
of the Services. The Client will be responsible for any damage to such land or any property
thereon resulting from such access and will indemnify the Consultants and each of the
Personnel in respect of liability for any such damage, unless such damage is caused by the
default or negligence of the consultant or any Sub-Consultant or the Personnel of either of
them.

5.3 Change in the Applicable Law

If, after the date of this Contract, there is any change in the Applicable Law with respect to
taxes and duties which increases or decreases the cost or reimbursable expenses incurred
by the Consultants in performing the Services, then the remuneration and reimbursable
expenses otherwise payable to the Consultants under this Contract shall be increased or
decreased accordingly by agreement between the Parties hereto, and corresponding
adjustments shall be made to the ceiling amounts specified in Clause
6.1
(b)
,

5.4 Services, Facilities and Property of the Client

The client shall make available to the Consultants and the Personnel, for the purposes of
the Services and free of any charge, the services, facilities and property described in
Appendix D at the times and in the manner specified in said Appendix D, provided that if
such services, facilities and property shall not be made available to the Consultants as and
when so specified, the Parties shall agree on (i) any time extension that may be
appropriate to grant to the Consultants for the performance of the Services, (ii) the manner
in which the Consultants shall procure any such services, facilities and property from other
sources, and (iii) the additional payments, if any, to be made to the Consultants as a result
thereof pursuant to Clause 6.1(c) hereinafter.

5.5 Payment

In consideration of the Services performed by the Consultants under this Contract, the
Client shall make to the Consultants such payments and in such manner as is provided by
Clause 6 of this Contract.

6. PAYMENT TO THE CONSULTANTS

6.1 Cost Estimates ; Ceiling Amount

(a) An abstract of the cost of the Services payable in local currency (Indian Rupees) is set
forth in Appendix E.

(b) Except as may be otherwise agreed under Clause 2.6 and subject to Clause 6.1(c), the
payments under this Contract shall not exceed the ceiling specified in the SC. The
Consultants shall notify the Client as soon as cumulative charges incurred for the Services
have reached 80% of the ceiling.

195
(c ) Not withstanding Clause 6.1(b) hereof, if pursuant to Clauses 5.4 hereof, the Parties shall
agree that additional payments shall be made to the Consultants in order to cover any
necessary additional expenditures not envisaged in the cost estimates referred to in Clause
6.1(a) above, the ceiling set forth in Clause 6.1(b) above shall be increased by the amount or
amounts, as the case may be, of any such additional payments.

6.2 Currency of Payment

(a) The payment shall be made in Indian Rupees.

6.3 Mode of Billing and Payment

Billing and payments in respect of the Services shall be made as follows:-

(a) The Client shall cause to be paid to the Consultants an advance payment as specified in the
SC, and as otherwise set forth below. The advance payment will be due after provision by
the Consultants to the Client of a bank guarantee by a bank acceptable to the Client in an
amount (or amounts) and in a currency (or currencies) specified in the SC, such bank
guarantee (i) to remain effective until the advance payment has been fully set off as
provided in the SC, and ii) in such form as the Client shall have approved in writing.

(b) Payment Schedule


The Consultant will be paid stage-wise as a percentage of the contract value as per the
schedule given below:

Payment as %
S.No Item of contract
value
1 Submission of final Inception Report 15%
2 Submission of final Alignment Report 10%
3 Submission of final Feasibility Report 5%
Submission of final Land Acquisition
4 10%
Report
5 Submission of clearance proposals 5%
6 Submission of Draft DPR 10%
7 Approval of Final DPR 10%
8 Approval of Technical Schedules 5%
9 3D publication 10%
10 Clearance Stage I Approval 5%
11 Clearance Stage II/Final Approval 5%
12 Retention to be released after 3 years 10%
Total: 100%
Bonus on submission of draft 3A within 1
13 2.5% bonus
month of alignment finalization
Bonus on submission of draft clearance
14 proposals within 1 month of alignment 2.5% bonus
finalization

196
Note: Consultants have to provide a certificate that all key personnel as envisaged in the
Contract Agreement has been actually deployed in the project. They have to submit this
certificate at the time of submission of bills to Chief Engineer, Highways, Mizoram PWD from
time to time.

(c) No payment shall become eligible for the next stage till the consultant completes to
the satisfaction of the client the work pertaining to the preceding stage. The payment
for the work of sub-soil investigation (Boring)will be as per plan approved by the client
and will be paid as per actual at the rates quoted by the consultants .The payment for the
quantity given by the client for boring will be deemed to be included in the above mentioned
payment schedule. Any adjustment in the payment to the consultants will be made in the
final payment only.

(d) The Client shall cause the payment of the Consultants in Para 6.4 (b) above as
given in schedule of payment within thirty (30) days after the receipt by the Client of
bills. Interests at the rate specified in the SC shall become payable as from the above due
date on any amount due by, but not paid on, such due date.

(e) The final payment under this Clause shall be made only after the final report and a
final statement, identified as such, shall have been submitted by the Consultants and
approved as satisfactory by the Client. The Services shall be deemed completed and
finally accepted by the Client and the final report and final statement shall be deemed
approved by the Client as satisfactory one hundred and eighty (180) calendar days after
receipt of the final report and final statement by the Client unless the Client, within
ninety(90) day period, gives written notice to the Consultants specifying in detailed
deficiencies in the Services, the final report or final statement. The Consultants shall
thereupon promptly make any necessary corrections, and upon completion of such
corrections, the foregoing process shall be repeated. Any amount which the Client has
paid or caused to be paid in accordance with this Clause in excess of the amounts actually
payable in accordance with the provisions of this Contract shall be reimbursed by the
Consultants to the Client within thirty (30) days after receipt by the Consultants of
notice thereof. Any such claim by the Client for reimbursement must be made
within twelve (12) calendar months after receipt by the Client of a final report and a final
statement approved by the Client in accordance with the above.

(f) All payments under this Contract shall be made to the account of the Consultants
specified in the SC.

7. Responsibility for Accuracy of Project Documents

7.1 General

7.1.1 The Consultant shall be responsible for accuracy of the data collected, by him
directly or procured from other agencies/authorities, the designs, drawings, estimates
and all other details prepared by him as part of these services. He shall indemnify the
Authority against any inaccuracy in the work which might surface during implementation
of the project. The Consultant will also be responsible for correcting, at his own cost
and risk, the drawings including any re-survey / investigations and correcting layout
etc. if required during the execution of the Services.

197
7.1.2 The Consultant shall be fully responsible for the accuracy of design and drawings of the bridges
and structures. All the designs and drawings for bridges and structures including all their
components shall be fully checked by a Senior Engineer after completion of the designs. All
drawings for bridges and structures shall be duly signed by the (a) Designer, (b) Senior Checking
Engineer, and (c) Senior Bridge / Structure Expert. The designs and drawings not signed by
the three persons mentioned above shall not be accepted. The Consultant shall indemnify the
Client against any inaccuracy / deficiency in the designs and drawings of the bridges and
structures noticed during the construction and even thereafter and the Client shall bear no
responsibility for the accuracy of the designs and drawings submitted by the Consultants.

7.1.3 The survey control points established by the Consultant shall be protected by the Consultants till
the completion of the Consultancy Services.

7.2. Retention Money

An amount equivalent to 10% of the contract value shall be retained at the end of the contract for
accuracy of design and quantities submitted and the same will be released after the completion of civil
contract works or after 3 years from completion of consultancy services, whichever is earlier. The
retention money will however be released by the Client on substitution by Bank Guarantee of the
same amount valid up to the period as above.

7.3. Penalty

7.3.1. Penalty for Error/Variation

i) If variation in any of the main quantities of work like earth work including sub grade,
GSB, WMM, Bituminous works (BM/DBM/AC/BC),drains, total concrete quantities and
reinforcing steel in bridge works or overall project cost, found during execution is more
than +/- 15%, the penalty equivalent to 5% of the contract value shall be imposed. For this
purpose retention money equivalent to 5% of the contract value will be forfeited. This
shall exclude any additional/deletion of items/works ordered during the execution

ii) For inaccuracies in survey/investigation/design work the penalties shall be imposed


as per details given in Table below:

198
Sl. Penalty (%age of
Item
No. contract value)
Topographic Surveys 0.5 to 1.0
a) The horizontal alignment does not match with ground
condition.
1
b) The cross sections do not match with existing ground.
c) The co-ordinates are defective as instruments of
desired accuracy not used.
Geotechnical Surveys 0.5 to 1.0
a) Incomplete surveys
2 b) Data not analysed properly
c) The substrata substantially different from the actual
strata found during construction.
Traffic data found to be varying by more than 25% on 0.2 to 0.5
3 resurvey at a later date, unless there are justifiable
reasons.
Axle load data found to be varying by more than 25% on 0.20 to 0.5
4 resurvey at a later date, unless there are justifiable
reasons.
Structural Designs found to be unsafe or grossly over 1.0 to 2.0
5
safe.

7.3.2 Penalty for delay

In case of delay in completion of services, a penalty equal to 0.05% of the contract price per
day subject to a maximum 5% of the contract value will be imposed and shall be recovered
from payments due/performance security. However in case of delay due to reasons beyond the
control of the consultant, suitable extension of time will be granted.

7.3.3 Total amount of recovery from all penalties shall be limited to 10% of the Consultancy Fee.

7.4 ACTION FOR DEFICIENCY IN SERVICES

7.4.1 Consultants liability towards the Client

Consultant shall be liable to indemnify the client for any direct loss or damage accrued or
likely to accrue due to deficiency in service rendered by him.

7.4.2 Warning / Debarring

In addition to the penalty as mentioned in para 7.3, warning may be issued to the erring
consultants for minor deficiencies. In the case of major deficiencies in the Detailed Project
Report involving time and cost overrun and adverse effect on reputation of Chief Engineer,
Highways, Mizoram PWD other penal action including debarring for certain period may
also be initiated as per policy of Chief Engineer, Highways, Mizoram PWD

199
8. FAIRNESS AND GOOD FAITH

8.1 Good Faith

The Parties undertake to act in good faith with respect to each others rights under this
Contract and to adopt all reasonable measures to ensure the realization of the objectives of this
Contract.

8.2 Operation of the Contract

The Parties recognize that it is impractical in this Contract to provide for every contingency
which may arise during the life of the Contract, and the Parties hereby agree that it is their
intention that this Contract shall operate fairly as between them, and without detriment to the
interest of either of them, and that, if during the term of this Contract either Party believes that
this Contract is operating unfairly, the Parties will use their best efforts to agree on such action
as may be necessary to remove the cause or causes of such unfairness, but no failure to agree on
any action pursuant to this Clause shall give rise to a dispute subject to arbitration in
accordance with Clause 9 hereof.

9. SETTLEMENT OF DISPUTES

9.1 Amicable Settlement

The Parties shall use their best efforts to settle amicably all disputes arising out of or in
connection with this Contract or the interpretation thereof.
9.2 Dispute Settlement
Any dispute between the Parties as to matters arising pursuant to this Contract which cannot
be settled amicably within thirty (30) days after receipt by one Party of the other Partys
request for such amicable settlement may be submitted by either Party for settlement in
accordance with the provisions specified in the SC.

10. Change of Scope


The change of Scope on account of variation of total length as well as 4 laned length of project
Highway from the indicative length as given at Annex-1 of Letter of Invitation of the RFP shall
be dealt as follows

i) During the course of consultancy services in case it is considered necessary to


increase/decrease the scope of services ( of total length or 4 laned length as compared to
indicative Length as given in the RFP) by the client the same shall be notified by
Change of scope notice. Similarly, if the Consultant determines that change of scope is
needed, he shall inform of the same to the Client. The Client will examine and shall
either reject the proposal or issue change of scope notice.

ii) The Consultancy fee shall be revised on account of change of scope as below:

- In case the total length of project increase/ decrease up to more 10% of indicative
length given in the RFP: No change in Consultancy Fees
- In case the increase/ decrease in total length of project is more than 10 % of the
indicative length as given in the RFP: The consultancy fee shall be increased
decreased in the same proportion in which the length of the project road is increased/
decreased beyond 10%.

200
- In case the length of 4 lane road is increased up to 10% of the length as indicated in
the RFP: No change in Consultancy Fees
- In case the length of 4 lane road is increased by more than 10% of the length as
indicated in the RFP: The consultancy fee shall be increased by 0.25 times the
average quoted rate (Rs per km) for the increased length of 4 lane beyond 10%

iii) Length of Bypass / realignment shall not be treated as additionality to the existing
length of the highway for the purpose of change / variation in length. Increase/decrease
in length on account of bypasses shall not be considered as change of scope.
However, the total length of the project highway (including bypasses and
realignment) along the finally approved alignment shall be compared with the
indicative length in the RFP for the purpose of variation.

201
SPECIAL CONDITIONS OF CONTRACT

Number of
GC Clause

A. Amendments of, and Supplements to, Clauses in the General Conditions

1.1(a) The words in the Governments country are amended to read in INDIA

1.4 The language is: English

1.6.1 The addresses are:

For the Client : Chief Engineer, Highways,Mizoram PWD Tuikhuahtlang, Aizawm,


Mizoram

Attention : Chief Engineer, Highways, Mizoram PWDTuikhuahtlang, Aizawm,


Mizoram
Fax 0389-2323347

For the Consultants:

Attention: Name
Designation
Address
Tel: Fax: E-mail address

1.6.2 Notice will be deemed to be effective as follows:

(a) in the case of personal delivery or registered mail, on delivery;


(b) In the case of facsimiles, 24 hours following confirmed transmission.
(c) In case of E mail, 24 hours following confirmed transmission.

1.8 Entity to Act as Member in charge (In case of Joint Venture of Consultants) with or without
an
Associate:

- ..
1.9 The Authorized Representatives are:

For the Client: ( -- )


Director, Chief Engineer, Highways, Mizoram PWD

For the Consultant: Name


Designation

1.10 The Consultants and the personnel shall pay the taxes, duties, fees, levies and other
impositions levied under the existing, amended or enacted laws (prevailing 7 days before
the last date of submission of bids) during life of this contract and the Client shall perform
such duties in regard to the deduction of such tax as may be lawfully impose

202
2.1 The effectiveness conditions are the following:

a) The contract has been approved by Chief Engineer, Highways, Mizoram PWD

b) The consultant will furnish within 15 days of the issue of letter of


acceptance, an unconditional Bank Guarantee from a Nationalised Bank, IDBI or ICICI/ICICI
Bank/Foreign Bank/EXIM Bank / Any Scheduled Commercial Bank approved by RBI having a
networth of not less than 500 crore as per latest Annual Report of the Bank. In the case of a Foreign
Bank (issued by a Branch in India) the networth in respect of Indian operations shall only be
taken into account. In case of Foreign Bank, the BG issued by Foreign Bank should be counter
guaranteed by any Nationalised Bank in India. In case of JV, the BG shall be furnished on behalf
ofthe JV or lead partner of JV for an amount equivalent to 10 %of the total contract value to be
received by him towards Performance Security valid for a period of three years beyond the date
of completion of services.

2.2 The time period shall be fourmonths or such other time period as the parties may
agree in writing.

2.3 The time period shall be fifteen days or such other time period as the Parties may
agree in writing.

2.4 The time period shall be 5 months or such other time period as the parties may agree
in writing.

3.4 Limitation of the Consultants Liability towards the Client

(a) Except in case of negligence or willful misconduct on the part of the Consultants or on
the part of any person or firm acting on behalf of the Consultants in carrying out the
Services, the Consultants, with respect to damage caused by the Consultants to the
Clients property, shall not be liable to the Client:

(i) for any indirect or consequential loss or damage; and


(ii) for any direct loss or damage that exceeds (A) the total payments for Professional

Fees and Reimbursable Expenditure made or expected to be made to the Consultants


hereunder, or (B) the proceeds the Consultants may be entitled to receive from any
insurance maintained by the Consultants to cover such a liability, whichever of (A) or (B)
is higher.

(b) This limitation of liability shall not affect the Consultants liability, if any, for
damage to Third Parties caused by the Consultants or any person or firm acting on
behalf of the Consultants in carrying out the Services.

3.5 The risks and the coverage shall be as follows:


(a) Third Party motor vehicle liability insurance as required under Motor Vehicles Act, 1988 in
respect of motor vehicles operated in India by the Consultants or their Personnel or any Sub
consultants or their Personnel for the period of consultancy.

203
(b) Third Party liability insurance with a minimum coverage, for Rs. 1.00 million for the
period of consultancy.

(c) (i) The Consultant shall provide Chief Engineer, Highways, Mizopram PWD Professional
Liability Insurance (PLI) for a period of Five years beyond completion of Consultancy
services or as per Applicable Law, whichever is higher.

(ii) The Consultant will maintain at its expense PLI including coverage for errors and
omissions caused by Consultants negligence in the performance of its duties under this
agreement, (A) For the amount not exceeding total payments for Professional Fees and
Reimbursable Expenditures made or expected to be made to the Consultants
hereunder OR (B) the proceeds, the Consultants may be entitled to receive from any
insurance maintained by the Consultants to cover such a liability, whichever of (A) or (B) is
higher.

iii) The policy should be issued only from an Insurance Company operating in India.

iv) The policy must clearly indicate the limit of indemnity in terms of Any One
Accident (AOA) and Aggregate limit on the policy (AOP) and in no case should be for
an amount less than stated in the contract.

v) If the Consultant enters into an agreement with Chief Engineer, Highways, Mizoram
PWD in a joint venture or in association, the policy must be procured and provided to
Chief Engineer, Highways, Mizoram PWD by the joint venture/in association entity and
not by the individual partners of the joint venture/ association.

vi) The contract may include a provision thereby the Consultant does not cancel the
policy midterm without the consent of NHAI. The insurance company may provide an
undertaking in this regard.

(d) Employers liability and workers compensation insurance in respect of the Personnel of
the Consultants and of any Sub consultant, in accordance with the relevant provisions of the
Applicable Law, as well as, with respect to such Personnel, any such life, health, accident,
travel or other insurance as may be appropriate; and all insurances and policies should start
from the date of commencement of services and remain effective as per relevant requirements
of contract agreement.

3.9 The Consultants shall not use these documents for purposes unrelated to this Contract without
the prior written approval of the Client.

4.6 The person designated as Team Leader cum Senior Highway Engineer in Appendix B
shall serve in that capacity, as specified in Clause

6.1 (b) The ceiling amount in local currency is Rs Excluding

Service Tax)

6.3 (a) No advance payment will be made.


6.3 (e) The interest rate is : @ 12% per annum
6.3 (f) The account is :

204
9.2 Disputes shall be settled by arbitration in accordance with the following provisions:

9.2.1 Selection of Arbitrators


Each dispute submitted by a Party to arbitration shall be heard by a sole arbitrator or an
arbitration panel composed of three arbitrators, in accordance with the following provisions:

(a) Where the Parties agree that the dispute concerns a technical matter, they may agree
to appoint a sole arbitrator or, failing agreement on the identity of such sole arbitrator
within thirty (30) days after receipt by the other Party of the proposal of a name for
such an appointment by the Party who initiated the proceedings, either Party may apply to
the President, Indian Roads Congress, New Delhi, for a list ofnot fewer than five nominees
and, on receipt of such list, the Parties shall alternately strike names therefrom, and the last
remaining nominee on the list shall be the sole arbitrator for the matter in dispute. If the last
remaining nominee has not been determined in this manner within sixty (60) days of the
date of the list, the president, Indian Roads Congress, New Delhi, shall appoint, upon the
request of either Party and from such list or otherwise, a sole arbitrator for the matter in
dispute.

(b) Where the Parties do not agree that the dispute concerns a technical matter, the Client and
the Consultants shall each appoint one arbitrator, and these two arbitrators shall jointly
appoint a third arbitrator, who shall chair the arbitration panel. If the arbitrators named by
the Parties do not succeed in appointing a third arbitrator within thirty (30) days after the
later of the two arbitrators named by the Parties has been appointed, the third arbitrator
shall, at the request of either Party, be appointed by Secretary, the Indian Council of
Arbitration, New Delhi.

(c) If, in a dispute subject to Clause SC 9.2.1 (b), one Party fails to appoint its arbitrator
within thirty (30) days after the other Party has appointed its arbitrator, the Party which has
named an arbitrator may apply to the Secretary, Indian Council of Arbitration, New Delhi, to
appoint a sole arbitrator for the matter in dispute, and the arbitrator appointed pursuant to
such application shall be the sole arbitrator for that dispute.

9.2.2 Rules of Procedure

Arbitration proceedings shall be conducted in accordance with procedure of the Arbitration


& Conciliation Act 1996, of India unless the Consultant is a foreign national/firm, where
arbitration proceedings shall be conducted in accordance with the rules of procedure for
arbitration of the United Nations Commission on International Trade Law (UNCITRAL)
as in force on the date of this Contract.

9.2.3 Substitute Arbitrators

If for any reason an arbitrator is unable to perform his function, a substitute shall
be appointed in the same manner as the original arbitrator.

9.2.4 Qualifications of Arbitrators

The sole arbitrator or the third arbitrator appointed pursuant to paragraphs (a)through (c) of
Clause
8.2.1 hereof shall be an internationally recognized legal or technical expert with
extensive experience in relation to the matter in dispute.

208
9.2.5 Miscellaneous

In any arbitration proceeding hereunder:

(a) Proceedings shall, unless otherwise agreed by the Parties, be held in DELHI

(b) the English language shall be the official language for all purposes; and
[Note: English language may be changed to any other Language, with the
agreement of both the Parties.]

(c) the decision of the sole arbitrator or of a majority of the arbitrators (or of the third arbitrator
if there is no such majority) shall be final and binding and shall be enforceable in any
court of competent jurisdiction, and the Parties hereby waive any objections to or claims
of immunity in respect of such enforcement.

(d) The maximum amount payable per Arbitrator in Arbitration clauses shallbe as under

S.No Particulars Maximum amount payable per


Arbitrator/ per case
Arbitrator fee Rs 15,000/- per day subject to a maximum of Rs 4
1 lacs orRs 2.5 lacs (lump sum) subject to publishing
the award within 12months.
2 Reading charges Rs 15,000/-
Secretarial Assistance and Incidental Rs 20,000/-
3 charges(telephone, fax, postage etc)
Charges for publishing/ Rs 20,000/-
4 declaration of the award
Other expenses (As per actual against bills subject to maximum of the prescribed celling
given below)
Traveling expenses Economy class (by air), First class AC
(by train) and AC Car (by road)
5
Lodging and Boarding a) Rs 15,000/- per day (in metro cities)
b) Rs 7,000/- per day (in other cities)
c) Rs 3,000/- per day if any Arbitrator makes their
own arrangements.
6 Local travel Rs 1,500/- per day
Extra charges for days other Rs 3,500/- per day
7 than hearing/ meeting days
(maximum for 2 days)
Note:- 1. Lodging boarding and traveling expenses shall be allowed only for those members who
are residing 100 kms. Away from place of meeting.
2. Delhi, Mumbai, Chennai, Kolkata, Bangalore and Hyderabad shall be considered as
Metro Cities.

In exceptional cases, such as cases involving major legal implications/ wider ramifications/ higher
financial stakes etc., a special fee structure could be fixed in consultation with the
Contractor/ Supervision Consultants and with the specific approval of the Chief Engineer,
Highways, Mizoram PWD before appointment of the Arbitrator,

209
Appendix A

Terms of reference containing, inter-alia, the Description of the Services and

Reporting
Requirements

210
Appendix B

Consultants Subconsultants, Key Personnel and Sub Professional Personnel

211
Appendix C

Hours of work for Consultants Personnel

The Consultants personnel shall normally work for 8 hours in a day and six days a week.
Normally Sundays shall be closed for working. In addition they shall also be allowed to
avail holidays as observed by the Clients office in the relevant state without deduction of
remunerations. In case any person is required to work on Sunday or Holiday due to exigency
of work, he/she shall be given compensatory leave within the next 15 days.

212
Appendix D

Duties of the Client

213
Appendix E

Cost Estimate

214
Appendix F

Minutes of Financial/ Contract Negotiations with the Consultant

215
Appendix G: Copy of letter of invitation

216
Appendix H: Copy of letter of acceptance

217
Appendix - I

Format for Bank Guarantee for Performance Security (For individual work)
BANK GUARANTEE FOR PERFORMANCE SECURITY
To,
Chief Engineer, Highways, Mizoram PWD Tuikhuahtlang, Aizawl, Mizoram.

In consideration of Chief Engineer, Highways (hereinafter referred as the Client, which


expression shall, unless repugnant to the context or meaning thereof include its successors,
administrators and assigns) having awarded to
M/s.having its office at
.. (Hereinafter referred to as the Consultant which expression shall repugnant
to the context or meaning thereof, include its successors, administrators, executors and
assigns), a contract by issue of clients Contract Agreement no. / Letter of
Acceptance No.
..
dated
and the same having been unequivocally accepted by the Consultant,
resulting in a Contract valued at Rs../- (Rupees..) excluding
service tax for Consultancy Services for preparation of Detailed Project Report of
Feasibility study and preparation of DPR for Aizawl by-pass on NH-54. (35.00Km)
(Total Length -.) on NH-..in the states
of
.under Contract Package No. . (Hereinafter called the Contract), and the
Consultant
having agreed to furnish a Bank Guarantee to the Client as Performance Security as stipulated
by the Client in the said contract for performance of the above Contract amounting to
Rs../- (Rupees.).

We, ..having registered office at .., a body


registered/constituted under the .(hereinafter referred to as the
Bank), which expression shall, unless repugnant to the context or meaning thereof,
include its successors, administrators, executors and assigns) do hereby guarantee and
undertake to pay the client immediately on demand any or, all money payable by the
Consultant to the extent of Rs.
..(Rupees....) as aforesaid at any time up to ..without
any demur, reservation, contest, recourse or protest and/or without any reference to the
consultant. Any such demand made by the client on the bank shall be
conclusive and binding notwithstanding any difference between the Client and the
Consultant or any dispute pending before any Court, Tribunal, Arbitrator or any other
authority. We agree that the Guarantee herein contained shall be irrevocable and shall
continue to be enforceable till the Client discharges this guarantee.

The Client shall have the fullest liberty without affecting in any way the liability of the
Bank under this Guarantee, from time to time to vary or to extend the time for performance of
the contract by the Consultant. The Client shall have the fullest liberty without affecting this
guarantee, to postpone from time to time the exercise of any powers vested in them or of
any right which they might have against the consultant and to exercise the same at any time
in any

218
manner, and either to enforce or to forbear to enforce any covenants, contained or implied, in
the Contract between the Client and the Consultant any other course or remedy or security
available to the Client. The bank shall not be relieved of its obligations under these
presents by any exercise by the Client of its liberty with reference to the matters aforesaid or
any of them or by reason of any other act or forbearance or other acts of omission or
commission on the part of the Client or any other indulgence shown by the Client or by any
other matter or thing whatsoever which under law would but for this provision have the effect
of relieving the Bank.

The Bank also agrees that the Client at its option shall be entitled to enforce this Guarantee
against the Bank as a principal debtor, in the first instance without proceeding against the
Consultant and notwithstanding any security or other guarantee that the Client may have
in relation to the Consultants liabilities.

Notwithstanding anything contained herein,

a) Our liability under this Bank Guarantee is limited to


Rs.
.(Rupees) and it shall remain in force up
to and including and shall be extended from time to time for such period
as may be desired by M/s., on whose behalf this guarantee has
been given.

b) This Bank Guarantee shall be valid up to ..

c) We are liable to pay the guaranteed amount or any part thereof under this
Bank Guarantee only and only if you serve upon us a written claim or demand
on or before (date of expiry of Guarantee).

(Signature of the Authorised Official)

(Name & Designation with Bank Stamp)

NOTE:
(i) The bank guarantee(s) contains the name, designation and code number of
the officer(s) signing the guarantee(s).
(ii) The address, telephone no. and other details of the Head Office of the Bank as
well as of issuing branch should be mentioned on the covering letter of issuing
Branch.
(iii) The bank guarantee for Rs. 10,000 and above is signed by at least two officials
(or as per the norms prescribed by the RBI in this regard).

219
Appendix J : Reply to Queries of the Bidder

220
A. PROCEDURE UNDER E-TENDERING- INSTRUCTION TO BIDDERS

DEFIFINITIONS
a. C1 India Pvt Ltd: New Service provider to provide the e-Tendering Software and
facilitate the process of e-tendering on Application Service Provider (ASP) model.
b. MORTH e-Procurement Portal: An e-tendering portal of Ministry of Road Transport &
Highways (MORTH) introduced for the process of e-tendering which can be accessed on
https://morth.eproc.in.

1. Accessing/ Purchasing of RFP documents

i) It is mandatory for all the bidders to have class-III Digital Signature Certificate with
signing & encryption facility (in the name of person who will sign the proposal) from any
of the licensed Certifying Agency (Bidders can see the list of licensed CAs from the link
www.cca.gov.in) to participate in e-tendering of Ministry of Road Transport & Highways.

ii) Users may test the working condition of their class-III Digital Signature Certificate
(Both DSC Components, i.e. Signing & Encryption) at https://morth.eproc.inunder Test
Digital Signature Certificate link.

iii) To participate in the E-Bid submission, it is mandatory for the bidders to register their
firm with e-tendering portal of Ministry of Road Transport & Highways
(htpps://morth.eproc.in) to acquire a user ID & password which has to be obtained by
submitting an annual registration charges of INR 2247/- (Inclusive of all taxes) to M/s C1
India Pvt Ltd through e-payment gateway using Credit Card / Debit Card (Master Card and
Visa Card only) or net banking. Validity of the online registration is 1 year.

iv) After completing the profile, Vendors have to send an email intimation to MoRTH
Helpdesk for their profile activation at [email protected]. All profile
activations will be done only during MoRTH working days. In order to submit the bid
response the activation of the vendor profile is mandatory.

v) The SBD / Bid document can be viewed/downloaded free of cost from e-tender portal
of MoRTH http://www.morth.nic.in or htpps://morth.eproc.in from 24/10/2016 to
17/11/2016 (up to 1000 Hrs. IST).

220
vi) To participate for bidding, bidders have to pay Rs.5000/- (One thousand five hundred)
towards fee for SBD document (non-refundable), in the form of Demand Draft issued from
a scheduled Bank in India in favour of Chief Engineer, Highways, Mizoram PWD payable
at Aizawl, Mizoram and Rs. 1295/- <Tender Processing Fee>/-(i.e. @0.007% of Estimated
cost put to tender plus 12.36% service tax which is minimum of INR 450/- and maximum of
INR 1295/-)towards application processing fee (non-refundable) shall be paid to M/s C1
India Pvt. Ltd against Tender Processing Fee through E-Payment gateway using Credit
Card/ Debit Card- Master Card and Visa Card only or net banking.

vi) Bidders can participate in the tender using the e-tender portal of MoRTH
https://morth.eproc.in from 24/10/2016 to 18/11/2016 (up to 1000 Hrs. IST).

vii) Following may be noted


(a) Registration should be valid at least up to the date of submission of proposal.
(b) Proposals can be submitted only during the validity of their registration.
(c) The amendments / clarifications to the SBD document, if any, will be hosted
on the MoRTH website (http://www.morth.nic.in or https://morth.eproc.in ).
(d) If the firm is already registered with e-tendering portal of MoRTH at
https://morth.eproc.in and validity of registration is not expired, the firm is eligible to
apply without fresh registration.

2. Preparation & Submission of proposal:


i) The response to the SBD document should be submitted online only along with the
Hard copy of the supporting documents as mentioned in <ITB accordingly>.

ii) SBD document may be downloaded from e-tender portal of MoRTH


http://www.morth.nic.in or https://morth.eproc.in from 24/10/2016 to 17/11/2016
(up to 1500 Hrs. IST) and tender may be submitted online following the instruction
appearing on the screen. A bidder manual containing the detailed guidelines for e-
tendering system is also available on e-tender portal of MoRTH
(https://morth.eproc.in ).

iii) All the documents as mentioned below which has to be submitted shall be prepared
and scanned in different files (in PDF or ZIP format such that file size is not more than
10 MB) and uploaded during the on-line submission of proposal. These documents
shall also be submitted in ORIGINAL along with the Technical proposal as mentioned
in ITB accordingly to Chief Engineer, Highways, Mizoram PWD Office before the
prescribed date & time for submission of proposals.
220
iv) The Hard Copy of the Technical Proposal in hard bound form(hard bound implies
binding between two covers through stitching or otherwise whereby it may not be
possible to replace any paper without disturbing the documents spiral bound form,
loose form, etc. will be not accepted) ,shall be placed in a sealed envelope. This
envelope shall bear the submission address, SBD/Bid reference number with the
heading as Technical Proposal for Feasibility study and preparation of DPR for
Aizawl by-pass on NH-54.for assisting MoRTH in conducting Comprehensive Audit
of the E-Procurement System being used by the NHAI & NOT TO BE OPENED BEFORE
7/11/2016 on 1300hrs.

Envelope shall be addressed to:


The Chief Engineer, Highways
Mizoram PWD, Aizawl, Mizoram.

v) The Financial consisting of the quoted lump-sum fees excluding of all taxes as per
Annexure F should only be submitted online in the e-tendering portal and not as a
hard copy. Taxes will be paid as applicable on relevant date of payment. Bidders
submitting the financial proposal as hard copy would be disqualified.

vi) For any assistance about MORTH e-Tendering, please contact E-Tendering Cell and
Help Desk Support on 0120-4746889 or Mr. Partha Ghosh on 08811093299.
Additionally the bidders can email their issues to helpdesk at
[email protected]. Helpdesk Nos. are open between 1000 Hrs to 1830 Hrs
IST (Monday to Friday (Exclusions: MoRTH HOLIDAYS).

3. Modification / Substitution / Withdrawal of proposals


i) The Bidder may modify, substitute or withdraw its e- bid after submission prior to the
proposal due date. No proposal shall be modified, substituted or withdrawn by the
Bidder after the proposal due date & time.

ii) Any alteration / modification in the proposal or additional information supplied


subsequent to the proposal after the due date, unless the same has been explicitly
sought for by the Ministry of Road Transport & Highways/Mizoram PWD (NH Works)
shall be disregarded.

iii) For modification of e-bid, bidder has to replace its old proposal from e-tendering
portal and upload / resubmit digitally signed modified proposal.

220
iv) For withdrawal of proposal, bidder has to click on withdrawal icon at e-tendering
portal and can withdraw its e-bid.

v) For any assistance about MoRTH e-Tendering, please contact E-Tendering Cell and
Help Desk Support on 0120-4746889. Additionally the bidders can email their issues to
helpdesk at [email protected]. Helpdesk Nos. are open between 1000 Hrs
to 1830 Hrs IST (Monday to Friday (Exclusions: MORTH HOLIDAYS).

DISCLAIMER
The Applicant must read all the instructions in the TENDER and submit the same accordingly.
For any support/ assistance they may contact helpdesk officers.

B. Details of documents to be furnished for online bidding

1. Scanned copies of the following documents to be up-loaded in .pdf format on the


website https//:morth.eproc.in in Technical Bid Folder

i. D.D. towards Cost of bidding document and additional cost of bidding


document.
ii. Bid security in the form specified in Section-8 of SBD
iii. Qualification information and supporting documents as specified in Section-2
of SBD
iv. Certificate, undertakings, affidavits as specified inSection-2 of SBD
v. Any other information pursuant to Clause-4.2 of ITB
vi. Undertakings that the bid shall remain valid for the period specified in Clause-15.1 of
ITB.
vii. Acceptance / non-acceptance of Dispute Review Expert proposed in
clause36.1.

2. Scanned copies of the following documents to be uploaded on the website


https//:morth.eproc.in in Financial Bid Folder.
i) Form of bid has specified in Section-6 in pdf format
ii) Duly filled in & digitally signed Bill of Quantity (BOQ) specified in section-7.
3. Uploaded documents of successful bidder will be verified with the original before signing
the agreement. The successful bidder has to provide the originals in hard bound copy to the
concerned authority on receipt of such a letter, which will be sent though registered post or
speed post or delivered by hand.
4. Each uploading shall be digitally signed by the bidders.

220

You might also like