Clerk of Works Project Report

This project report summarizes the progress of the Friends Apartment Ltd project over 28 weeks. Key details include: 1) Main construction began on September 1st, 2016 with a planned completion date of February 28th, 2018. 2) Work completed includes the basement, ground floor, and first floor structures along with plumbing and electrical rough-ins. 3) Current work focuses on the second floor and unit wall framing, with Unit A nearing plaster and Unit C just starting framing. The project is tracking 2 weeks ahead of schedule at this point.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
288 views11 pages

Clerk of Works Project Report

This project report summarizes the progress of the Friends Apartment Ltd project over 28 weeks. Key details include: 1) Main construction began on September 1st, 2016 with a planned completion date of February 28th, 2018. 2) Work completed includes the basement, ground floor, and first floor structures along with plumbing and electrical rough-ins. 3) Current work focuses on the second floor and unit wall framing, with Unit A nearing plaster and Unit C just starting framing. The project is tracking 2 weeks ahead of schedule at this point.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 11

PROJECTREPORT

PROJECT:friendsapartmentltd
REF:456111560546
ADDRESS:
_______________________________ nca:
456111560546
Architect;tarus/steve
Week:28outof75+addedworkhowmanyweeks?
ContractStartDate:1/9/2016
ContractcompletionDate:28/2/2018
Maincontractor:_kensteel_constructionltd
Clerkofworks/zachariah
+toprogramme2weeksaheadof
Progress

Store Activity stat Start/fini changes verificat REMARK


y us nish ion
level
base Formwork 100 15/9/16
ment 1.bases/beams/colu % To
mns 06/10/16
2 suspended slab &
beams
3 staircase starters
4. lift shaft base
Reinforcement- 100 20/9/16 Basement Structura
1.bases/beams/colu % added l
mns work arch
2 suspended slab &
beams
3 staircase starters
4. lift shaft base
Concretes 100 7day-
1.bases/beams/colu % 28/9/16 to Bases 28days
mns 20/10/16 collumn bas18.7-
2 suspended slab & 26.7
beams slab18.7-
3 staircase starters 25.6
4. lift shaft base
Substructure 100 15/10/16
walling %
Plaster 100
%
flooring 0%
subst Retaining wall 100
ructu %
re
Retaining bases & 100
columns %
Concrete to 100
Retaining bases & %
columns
Walling to ditto 100
%
Plaster & 100
masterseal %
application to
external walls
Plumbing
electrical 1.AC
provinsions
on the
basement
2 provide
power point
and allow for
trunking
provinsion to
contain the
cables
3

Grou formwork 100


nd %
floor
Reinforcement- 100
%
Concretes 100
collumns % Col-18.7-
Suspended slab 11/11/16 25.7
Stairs Slab17.0-
lift 24.9
Superstructure 100 26/1/17 Client
walling % approval
on
setting
Precast lintel 100
%
Electrical -changes
1-Change in bed
switches heights
2-dp relocation
3-additional AC switch to
-lounge
-m/br
-br o2
4 relocation of switch to
o1
light at br
5. agreed on the
positioning of
metering panel-
switch board l-
4.0mx2.0m wx
height 2.7m

plumbing
Plaster to ground
unit ceiling 100
Walls %
Plaster to parking 0%
bay
ceilling 9/24
flooring 0%
1st Formwork to 100
floor column, suspended %
slab, staircase ,lift
rcc
Reinforcement- to 100 Col-17.3-
column, suspended % 26.6
slab, staircase ,lift Slab-18.7-
rcc 26.0
Service s to ditto 100
%
Concretes 100
collumns % 20/28th/1/1
Suspended slab 7 16/12/16
Staircase 1 13/12/16&
2
Lift shaft wall 1
2
unit A
Superstructure 100 25th week Architectural
walling % 2/2/17 Review 6 to
9
Precast lintel 100
%
electrical 100 1st fix
% ongiong
plumbing 100 1.Relocation 1st fix
% of stack pipe ongoing
for kitchen
sink whb
shifted to h
to f
2.location of
drain pipe for
air
conditioner
machine at
balcony front
& rear
Plaster to ceiling 0%
Beams

Walls/collumns

Rendered floor 0%
Tiles to floor

Sample unit
Unit B
Superstructure 100 complete
walling %
Precast lintel 100 complete
%
electrical 1st fix
plumbing 1st fix
Plaster to ceiling 100 6/3 to complete
Beams % 24/3/17

Walls/collumns

Rendered floor Hacking


ongoing
Tiles to floor
Superstructure 100 27th wk Architectural
Unit walling % -18/3/17 Review 9 to
C 12
Precast lintel 100
%
electrical Nil
Plumbing nil
Plaster to ceiling
Beams

Walls/collumns

Rendered floor
Tiles to floor

2nd Formwork to 100


floor column, suspended %
slab, staircase ,lift
rcc
Reinforcement- to 100
column, suspended %
slab, staircase ,lift
rcc
Service s to ditto 100
%

Concretes 100 Col-17.0-


Columns-20/2/17 % 25.1
17th&23rd /
Suspended slab Dimension Client-fl
1/17
17/2/17- alternation 1,2,7,8 & slab18.7-
at 3,4,5,6 26.2
washrooms
to dinning to
create space
for washing
machine
1st fl Staircase 1 28/1/17
to 2nd 2 29/1/17
fl
1st fl Lift shaft wall 1
to 2nd 2
fl
unit A
Superstructure 100 28th wk-
walling % 21/3/17 to
Precast lintel 100 ongoing
%
electrical 100
%
plumbing 100
%
Plaster to ceiling 0%
Beams

Walls/collumns

Rendered floor 0%
Tiles to floor

Unit B
Superstructure 100 20/3/17 to
walling %
Precast lintel 0%
electrical
plumbing 1.Initially wc
s were close
couple and
later
changed to
wall hang
2.additional
stack pipe
for wc
belonging to
bedroom 01
Plaster to ceiling 100
Beams %

Walls/collumns

Rendered floor
Tiles to floor
Superstructure 100 21/3/17 to
Unit walling %
C
Precast lintel 0%
electrical
Plumbing
Plaster to ceiling
Beams
Walls/collumns

Rendered floor
Tiles to floor

3rd Formwork to 100 1. Client/ar


floor 1.column, % 2. ch/desig
2.suspended slab, 3.13 to ner
3.staircase ,4.lift rcc 18/3/17
4.
Reinforcement- to 100 1
1.column, % 2
2suspended slab, 3-
3.staircase 4,lift rcc 4
Service s to ditto 100
%
Concretes 100 -
collumns %

Suspended slab 100 17&24 of


% feb
3rd fl Staircase 1
to 4th 2
fl
3rd fl Lift shaft wall 1 100 9&10/3/17
to 4th 2 % 13&14/3/1
fl 7
unit A
Superstructure 0%
walling
Precast lintel 0%
electrical
plumbing Added water Client/ar
filter and ch
located at
utility area-
15th/3/17
Plaster to ceiling 0%
Beams

Walls/collumns

Rendered floor 0%
Tiles to floor
Unit B
Superstructure 0%
walling
Precast lintel 0%
electrical
plumbing Washroom
RELOCATION
OF WC at
unit A -m/br
& br o1-14th
3/17
Plaster to ceiling 0%
Beams

Walls/collumns

Rendered floor 0%
Tiles to floor 0%
Superstructure 0%
Unit walling
C
Precast lintel 0%
electrical
Plumbing
Plaster to ceiling 0%
Beams

Walls/collumns

Rendered floor
Tiles to floor
4th Formwork to 100
floor column, suspended %
slab, staircase ,lift
rcc
Reinforcement- to 100
column, suspended %
slab, staircase ,lift
rcc
Service s to ditto 100
%
Concretes 0%
collumns
Suspended slab O 100 23/3/17 & E TO A
TO E % remains
Staircase 1
2

Lift shaft wall 1


2
unit A
Superstructure
walling
Precast lintel 0%
electrical
plumbing
Plaster to ceiling 0%
Beams

Walls/collumns

Rendered floor 0%
Tiles to floor 0%

Unit B
Superstructure 0%
walling
Precast lintel 0%
electrical
plumbing
Plaster to ceiling 0%
Beams

Walls/collumns

Rendered floor 0%
Tiles to floor 0%
Superstructure 0%
Unit walling
C
Precast lintel 0%
electrical
Plumbing
Plaster to ceiling 0%
Beams
Walls/collumns

Rendered floor
Tiles to floor DATE

1 EHS OSHWAL 2007


2 SCALPFOLD
3 DUST SCREEN
4
DRAWING
/INFORMATION
RECEIVED ON SITE
1 Safety first
2 Safty leads to clean
work
DRAWING/INFORM
ATION REQUIRED
ON SITE
1 Gym layout plan awaited
2 Tile layout plan awaited
Invertor location /
Soft drw i
DELAYS
INCLUDING
DEFECTIVE WORK
[ACTION TAKEN]
Ferry of bldg stones
introduced pulley
machines 2no
STOPPAGES 0hrs
[HOURS]
TOTAL TO DATE

VISITORS DATE
INCLUDES STATORY
INSPECTORS
1 Municipal engineer 21/3/17
2 Project civil 21/3/17
engineer

PLANT/MATERIALS
DELIVERED TO
SITE
1 Ceramic tiles for 413
sample unit B1 cartoons
finishes
2 Wall hang cistern no 4 cartoons
wc/fittings

WORKS: dates
MATERIALS
TESTED OR
COMMISSIONED
1 4th floor concrete 23/3/17
slab grid o to eb----2 24/3/17
days

CLERK
PREPARED BY
OFWORKS
:-----zachariah

SIGN:-----

DATE:-----28/3/2017