Microsoft Project - PMT

The document outlines a project schedule with multiple tasks over several years. It includes engineering, procurement, and construction activities with dependencies between tasks. The schedule shows timelines for procuring major equipment like compressors and heat exchangers as well as bulk materials.

Uploaded by

jk
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
88 views1 page

Microsoft Project - PMT

The document outlines a project schedule with multiple tasks over several years. It includes engineering, procurement, and construction activities with dependencies between tasks. The schedule shows timelines for procuring major equipment like compressors and heat exchangers as well as bulk materials.

Uploaded by

jk
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Name Duration Start Finish Predecessors

December 11 February 1 March 21 May 11 July 1 August 21 October 11 December 1 January 21 March 11 May 1 June 21 August 11 October 1 November 21 January 11 March 1 April 21 June 11 August 1
12/20 1/10 1/31 2/21 3/13 4/3 4/24 5/15 6/5 6/26 7/17 8/7 8/28 9/18 10/9 10/30 11/20 12/11 1/1 1/22 2/12 3/5 3/26 4/16 5/7 5/28 6/18 7/9 7/30 8/20 9/10 10/1 10/22 11/12 12/3 12/24 1/14 2/4 2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12
1 Project Milestone Summery 460 days Sun 11/6/16 Sun 8/12/18
2 Project start (Zero Date) 0 days Sun 11/6/16 Sun 11/6/16 11/6
3 Project engg, Completion 0 days Fri 9/1/17 Fri 9/1/17 21,30 9/1
4 Project Procurement Completion 0 days Fri 5/4/18 Fri 5/4/18 58 5/4
5 Project Mechanical Completion 0 days Fri 6/15/18 Fri 6/15/18 89 6/15
6 Project Completion 0 days Sun 8/12/18 Sun 8/12/18 96 8/12
7 Engineering 215 days Mon 11/7/16 Fri 9/1/17
8 Process Engineering 65 days Mon 11/7/16 Fri 2/3/17
9 Review Basic Engineering Package 20 days Mon 11/7/16 Fri 12/2/16 2
10 Prepare & Issue PFDs 10 days Mon 12/5/16 Fri 12/16/16 9
11 Prepare & Issue P & IDs 25 days Mon 12/19/16 Fri 1/20/17 10
12 Prepare & Issue Equipment Data S 10 days Mon 1/23/17 Fri 2/3/17 11
13 Mechanical Engineering 160 days Mon 1/23/17 Fri 9/1/17
14 Prepare & Issue Equipment Layout 20 days Mon 1/23/17 Fri 2/17/17 11,10
15 Prepare & Issue GAD 40 days Mon 4/3/17 Fri 5/26/17 23
16 Prepare & Issue ISO 60 days Mon 5/29/17 Fri 8/18/17 15
17 Prepare & Issue MR - Compressor 10 days Mon 2/6/17 Fri 2/17/17 12
18 Prepare & Issue MR - Heat Exchang 10 days Mon 2/6/17 Fri 2/17/17 12
19 Prepare & Issue Preliminary MTO 15 days Mon 5/29/17 Fri 6/16/17 15
20 Prepare & Issue MRs for Bulk Piping Items10 days Mon 6/19/17 Fri 6/30/17 19
21 Prepare Final MTO 10 days Mon 8/21/17 Fri 9/1/17 16
22 Civil Engineering 45 days Mon 2/20/17 Fri 4/21/17
23 Prepare & Issue Plot Plan 30 days Mon 2/20/17 Fri 3/31/17 14
24 Prepare & Issue Equipment Fdn. Dr 15 days Mon 4/3/17 Fri 4/21/17 23
25 Electrical & Instrumentation Enginee 160 days Mon 1/23/17 Fri 9/1/17
26 Prepare & Issue SLD 40 days Mon 1/23/17 Fri 3/17/17 11
27 Prepare & Issue Area Classification Drgs. 20 days Mon 5/29/17 Fri 6/23/17 26,15
28 Prepare & Issue E & I Cable Layouts 20 days Mon 6/26/17 Fri 7/21/17 27
29 Prepare & Issue MTO for E & I 10 days Mon 7/24/17 Fri 8/4/17 28
30 Prepare & Issue MRs for E & I Bulk i 20 days Mon 8/7/17 Fri 9/1/17 29
31 Procurement 315 days Mon 2/20/17 Fri 5/4/18
32 Procurement of Equipment 315 days Mon 2/20/17 Fri 5/4/18
33 Procurement-Compressor 265 days Mon 2/20/17 Fri 2/23/18
34 Prepare & Issue Inquiry 10 days Mon 2/20/17 Fri 3/3/17 17
35 Receive Bids 30 days Mon 3/6/17 Fri 4/14/17 34
36 Prepare TBA 15 days Mon 4/17/17 Fri 5/5/17 35
37 Prepare CBA 5 days Mon 5/8/17 Fri 5/12/17 36
38 Prepare & Issue LOI 10 days Mon 5/15/17 Fri 5/26/17 37
39 Prepare & Submit Vendor Drawi 30 days Mon 5/29/17 Fri 7/7/17 38
40 Procure - Raw Material 40 days Mon 7/10/17 Fri 9/1/17 39
41 Manufacturing 100 days Mon 9/4/17 Fri 1/19/18 40
42 Factory Acceptance Test (FAT) 10 days Mon 1/22/18 Fri 2/2/18 41
43 Packaging & Despatch 5 days Mon 2/5/18 Fri 2/9/18 42
44 Delivery at Site 10 days Mon 2/12/18 Fri 2/23/18 43
45 Procurement-Heat Exchanger 315 days Mon 2/20/17 Fri 5/4/18
46 Prepare & Issue Inquiry 10 days Mon 2/20/17 Fri 3/3/17 18
47 Receive Bids 30 days Mon 3/6/17 Fri 4/14/17 46
48 Prepare TBA 15 days Mon 4/17/17 Fri 5/5/17 47
49 Prepare CBA 5 days Mon 5/8/17 Fri 5/12/17 48
50 Prepare & Issue LOI 10 days Mon 5/15/17 Fri 5/26/17 49
51 Open L/C 10 days Mon 5/29/17 Fri 6/9/17 50
52 Prepare & Submit Vendor Drawi 30 days Mon 6/12/17 Fri 7/21/17 51
53 Procure - Raw Material 40 days Mon 7/24/17 Fri 9/15/17 52
54 Manufacturing 100 days Mon 9/18/17 Fri 2/2/18 53
55 Factory Acceptance Test (FAT) 10 days Mon 2/5/18 Fri 2/16/18 54
56 Packaging & FOB 15 days Mon 2/19/18 Fri 3/9/18 55
57 Shipping & Custom Clearance 30 days Mon 3/12/18 Fri 4/20/18 56
58 Delivery at Site 10 days Mon 4/23/18 Fri 5/4/18 57
59 Procurement of Bulk Items 155 days Mon 7/3/17 Fri 2/2/18
60 Procurement - Piping Bulk Items 145 days Mon 7/3/17 Fri 1/19/18
61 Prepare & Issue Inquiry 10 days Mon 7/3/17 Fri 7/14/17 20
62 Receive Bids 20 days Mon 7/17/17 Fri 8/11/17 61
63 Prepare TBA 15 days Mon 8/14/17 Fri 9/1/17 62
64 Prepare CBA 5 days Mon 9/4/17 Fri 9/8/17 63
65 Prepare & Issue LOI 5 days Mon 9/11/17 Fri 9/15/17 64
66 Manufacturing 40 days Mon 9/18/17 Fri 11/10/17 65
67 Packaging & Despatch 5 days Mon 11/13/17 Fri 11/17/17 66
68 Delivery at Site 10 days Mon 11/20/17 Fri 12/1/17 67
69 Repeat Order Final MTO Piping items 40 days Mon 9/4/17 Fri 10/27/17 21
70 Manufacturing & Delivery at Site 60 days Mon 10/30/17 Fri 1/19/18 69
71 Procurement - E & I Bulk Items 110 days Mon 9/4/17 Fri 2/2/18
72 Prepare & Issue Inquiry 10 days Mon 9/4/17 Fri 9/15/17 30
73 Receive Bids 20 days Mon 9/18/17 Fri 10/13/17 72
74 Prepare TBA 15 days Mon 10/16/17 Fri 11/3/17 73
75 Prepare CBA 5 days Mon 11/6/17 Fri 11/10/17 74
76 Prepare & Issue LOI 5 days Mon 11/13/17 Fri 11/17/17 75
77 Manufacturing 40 days Mon 11/20/17 Fri 1/12/18 76
78 Packaging & Despatch 5 days Mon 1/15/18 Fri 1/19/18 77
79 Delivery at Site 10 days Mon 1/22/18 Fri 2/2/18 78
80 Construction 300 days Mon 4/24/17 Fri 6/15/18
81 Construction of Civil Work 15 days Mon 4/24/17 Fri 5/12/17
82 Construct Fdn for Compressor 10 days Mon 4/24/17 Fri 5/5/17 24
83 Construct Fdn for Heat Exchanger 15 days Mon 4/24/17 Fri 5/12/17 24
84 Mechanical Work 95 days Mon 1/22/18 Fri 6/1/18
85 Install Compressor 20 days Mon 2/26/18 Fri 3/23/18 82,44
86 Install Heat Exchangers 20 days Mon 5/7/18 Fri 6/1/18 58,83
87 Fabrication & Erection of Pipe Rake & Pipe90 days Mon 1/22/18 Fri 5/25/18 16,68,70
88 Electrical & Instrumentation Works 60 days Mon 3/26/18 Fri 6/15/18
89 E & I Cabling & Erection Of E & I Item 60 days Mon 3/26/18 Fri 6/15/18 79,85
90 Hookup, Testing & Pre Commisioning 40 days Mon 3/26/18 Fri 5/18/18
91 Hookup, Testing & Pre Commisioning 40 days Mon 3/26/18 Fri 5/18/18
92 Hookup, & Tie-ins 10 days Mon 3/26/18 Fri 4/6/18 85
93 Loop Checking & Testing 15 days Mon 4/9/18 Fri 4/27/18 92
94 Precommissioning 15 days Mon 4/30/18 Fri 5/18/18 93
95 Commissioning & Startup 20 days Mon 5/21/18 Fri 6/15/18
96 Commissioning & Startup 20 days Mon 5/21/18 Fri 6/15/18 94

Project: Project1fgf Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Sun 12/18/16 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress