Design PHE
Design PHE
Design PHE
S. Sarkar
WASTEWATER MANUAL
http://cpheeo.nic.in/Sewerage.aspx
TREATED WATER
RAW WATER TREATMENT PLANT
WATER
TEATED
WASTEWATER WASTEWATER
Classification of Sewers
Storm Sewers
They are designed to carry off only stormwater and groundwater but excludes
sewage from domestic and/ or industrial source
Combined Sewers
They are designed to carry off stormwater, domestic and industrial
wastewater
Advantages and Disadvantages of Combined Sewers
It is initially economical to set up a combined sewer rather than
separately installing domestic sewers and stormwater sewers
During dry season lack of stormwater causes a low flow rate. Low
flow rate gives rise to low velocity of flow. At low velocities, due to
less turbulence, the deposition of sewage solids are more. Result is
siltation and consequent foul odor generation due to degradation of
the settled solids.
In contrast, during wet or rainy seasons, the flow rate is very high.
Therefore, pumping costs are more, causing high operation and
maintenance cost.
Pumps that are designed to operate at high flow rate to tackle the
wet season flow, runs in low flow condition in dry season which is an
inefficient operation that consumes more power than usual.
The sanitary sewers are designed to carry the wastewater from the above
sources to a sewage/wastewater treatment plants
Thus, it is important to estimate the design flow rate for the sewers to be
constructed.
Estimation of Sewage Flowrate
Two Parameters:
Both of these
quantities depend
1. The contributing population, and
on the design
2. Per capita (per person) flowrate of
period
sewage
Design period: The length of the time up to which the capacity of a sewer will
be adequate is called a design period.
Normally design period for a sewerage system is considered as 30 years
But, mechanical rotating equipment such as pumps are designed for 15 years
Forecasting the Population
Prospective population of the project area (may be a city, town or a
metropolitan area)
Methods:
Demographic population projection
Arithmetical increase method
Incremental Increase method
Geometrical Increase method
Growth rate
Graphical method
Logistic method
Method of density
1. From the city-plan find out the % of the total area available for residential
development
2. Actual total floor area = Area for residential development X Floor Space
Index (FSI)
3. Find out floor area required for one person or assume it depending on
the available data from the city. Normally it is 9 sqm/ person.
5. Multiply the density with the total area of the city to find out the total
population
This total population can be used for estimating the quantity of total sewage
flow.
Example: Finding out population density based on Floor Space Index method
A well-planned city has following areas earmarked for its development in the planning
stage: Roads- 20%; Gardens- 15%; Schools 5%; markets and Commerical places 2%;
Hospital and medical facilities 2% and rest is residential area. The Floor Space Index
(FSI) for the city is fixed at 2. If the floor area is 9 sqm/ person, find out the projected
population density of the city in numbers/ hecatare.
Population that can reside in the area= Actual Floor area / Area required by a person
= 0.56X2 /9 numbers / sqm
Design water consumption in India = 130 LPCD (litre per capita per day)
Flow rate
also are seasonal variations.
Average
For design purpose, sewers are always
designed to carry maximum or peak flow
rates, rather than designing it for average
flowrate. 4 8 12 16 20 24
Time of the day
Maximum wastewater flow rate
Peak Factor (PF) =
Average flow rate of wastewater
Usually, for a sanitary sewer below the groundwater table the following
values are taken,
Minimum Maximum
Liters/ha.d 5000 50000
Liters per day/ 250 500
manhole
RAINFALL
High volume of water on the surface,
More paved surface, higher
High runoff, needs quick evacuation
imperviousness, less absorption by soil
to avoid flooding/ inundation
How to evacuate this increased runoff?
BUILD EFFICIENT STORM SEWER SYSTEM
Finding Out of Runoff
Runoff quantity depends on:
Rainfall Characteristics (Intensity, Duration and space-
time distributions)
Characteristics of the watershed surface (nature,
permeability, slope, and landscaping)
Time of concentration (time required for flow to reach
the sewer)
Storm sewers are designed for a rainfall with particular frequency or return
period. The design rainfall is fixed after economic considerations involving
the Intensity-duration and frequency (IDF) curves in an area.
Time Runoff
Rainfall over a watershed draining at a single
t0= 0 Q0 = Q(t=0) =0
discharge point
t1= t Q1=A1IC1
t2=2t Q2=A2IC2 I = Intensity of the rainfall
A = Area
tn=nt Qn=AnICn C= Run-off coefficient
Case II Rainfall duration is 2t
Time Runoff
t0= 0 Q0 = Q(t=0)= 0
t1= t Q1=A1IC1
t2=2t Q2=A1IC1+A2IC2
t3=3t Q3=A2IC2+A3IC3
tn=nt Qn= An-1ICn-1+AnICn
tn=(n+1)t Qn+1 =AnICn
tn+2 =(n+2) t Qn+2 =0
Case III Rainfall duration is nt
Time Runoff
t0= 0 Q0 = 0
t1= t Q1=A1IC1
j
tj=jt Q j Ak ICk
k 1
n
tn=nt Qn Ak ICk
k 1
n
Qn 1 Ak ICk
tn+1=(n+1)t
k 2
T2n-1=(2n-1)t Q2n-1=A1IC1
t2n =2nt Q2n =0
A Few Observations
If the duration of the rainfall is tn and tn is the time necessary for the water
droplet to reach to the basin outlet from the hydraulically most distant place
in the basin, the entire surface area of the basin contributes to the flow rate
or the runoff observed from the basin.
If the duration of the rainfall is longer than tn, the runoff value remains equal
to the same as the case above, from the time tn until the end of the rainfall
duration.
If the duration of the rainfall is shorter than tn, the maximum runoff occurs at
the end of the rainfall and is smaller than the runoff obtained for a
precipitation of duration tn.
The maximum runoff flow is always reached at the latest by the end of the
rainfall.
The maximum runoff due to a precipitation of uniform intensity I falling all over the
drainage basin, and of duration tn (the longest time for water to travel to the
outfall from the basin), is thus given by n n
Qn Ak ICk I Ak Ck
k 1 k 1
Rational Equation
n n
Qn Ak ICk I Ak Ck
k 1 k 1
Q AIC
Q = Run-off in cum/hr
C= coefficient of run-off
I= Intensity of design rainfall, mm/hr
A = Area of drainage basin in hectares
Q = 10 CIA
Values of C
Absolutely impervious basin.1.0
Paved Areas0.9
Lawn and Gardens.0.15
Water-bound macadem roads0.45
Time of Concentration (tc)
DRAINAGE BASIN
The period of time after which the entire
basin area starts contributing to the run-off is
called the time of concentration. Varies from
3 to 30 minutes
tC
Maximum run-off is obtained from a rain having a
duration equal to the time of concentration. SEWER
OUTFALL
The duration of such a rainfall is called critical rainfall duration and the intensity of
such rainfall is known as critical rainfall intensity.
Sub-basin
tc te t f
te
te= time of entry
tf= time of flow tf
SEWER
OUTFALL
Time of entry is the longest time required for a water droplet in an urban sub-basin
to travel to a street inlet.
Time of flow is the time required for water to travel to a sewage outfall from the street
inlet in the urban sub-basin. It is always computed considering that the pipe is running
full. 1 2 3 12
v R s tf
L
n v
Rainfall Intensity, mm/hr Typical Rainfall Intensity-Duration-Frequency Curves The curves can vary
from place to place
and the shape of
the curve follows
different patterns.
a
I
tk
a
I n
t k
CN x
I
(b t ) n
Duration, minutes
I ( rainfall intensity) and T (duration) are variables; other terms are constants that can be
found out from fitting the curve with the field data obtained.
How to find out the
design maximum run-off
of a basin?
2. From the contour map of the area find out the time of concentration of the basin (say 15
minutes)
3. Find out the rainfall intensity corresponding to the time of concentration. (TOC = duration
of rainfall )
4. Apply Rational Formula to find out the maximum or design runoff
Find out the maximum design runoff at
/1.2 ha
the discharge point
Assume: C = 0.3 (Entire area), 5-year frequency, vel.
In sewers = 0.6 m/s
200
/120 m
175
/2.4 ha 125
100
75
50
/180 m 25
/1.8 ha
Flow time in sewer from MH 1 MH 2
= (120 m)/ (0.6 m/s) (60 s/ min) = 3.3 min
Objectives:
1. Carry the peak flow rate for which the sewer is designed
This is directly connected with the maximum achievable velocity in
the sewers. We do not want the sewage pipe materials to get worn
out. The wastewater manual recommends a maximum velocity of
3 m/s.
The generation of Self-cleansing velocity should occur within the sewer for at
least once in a day.
SELF-CLEANSING VELOCITY
Submerged Weight
submrged
Volume
1 W sin
(Vs * d * g buyoancy)
V
1
[(V - nV) * d * g (V nV ) w )]
V
(1 n)[ d w ] (1 n) w [ S s 1] W W cos
From the force balance, when the particle is on the verge of slipping down the plane,
W sin
If the block (Particle) has a unit length and unit width and thickness is dp , then
W sub *1*1* d p
w RS w (1 n)[S s 1]d p sin
k
S [ S s 1]d p Where, k (1 n) sin
R
1 2 3 12 1 2 1
vs R S R 3 k ( S s 1)d p 1 16
n n 1
R 2 vs R k ( S s 1)d p
n
Self-Cleansing Velocity
1
1 6
VS R k ( S S 1) D p
n
n = roughness coefficient
A
R = Hydraulic Mean Radius =
P
A= Area of the channel
P= Wetted perimeter of the channel
D D d 1
d [ cos ] [1 cos ]
2 2 2 D 2 2
1 D D
A D2 a D . 2
2 * * sin * cos
4 4 360 2 2 2 2 2
sin sin
a
[ a D [ 2
]
A 360 2
] 4 360 2
P D
/2 /2 D p D *
360
d
D *
p
360
P D 360
D 2
A 4 D a D 360 sin
R r [1 ]
P D 4 p 4 2
r 360 sin
[1 ]
R 2
1 2 / 3 1/ 2
V R S
n
/2 /2 D
1 2 / 3 1/ 2
v r s
d n
360 sin
2/3 2/3
r
2/3
v r
2/3 1
V R R 2
* 1
Q A.V A V 360 2 2
d 1
[1 cos ]
D 2 2
r 360 sin
[1 ]
/2 /2 D R 2
v 360 sin
2/3
1
d V 2
q sin 360 sin
2/3
1
Q 360 2 2
Population in the initial years of the design period are low compared to the
design population at the end of design period
Peak flow rate in the initial years is low compared to the designed peak flow
rate (ultimate peak flow)
Sizing should be such that it will attain the self-cleansing velocity at the
average design flow rate or at least at the maximum flow rate at the beginning
of the design period.
1 2 / 3 1/ 2
v r s
n
a D 360 sin
r [1 ]
p 4 2
s
1000
v 360 sin
2/3
Velocity at partially full flow
1
Velocity at full flow V 2
After finding the minimum slope required, the pipe size is decided on the basis
of ultimate design peak flow rate and the permissible depth of flow. Adoption
of the above slopes would ensure minimum flow velocity of 0.6 m/s
The slope and size of the sewer should be such that the velocity of flow shall
increase progressively or shall remain steady throughout the length of the sewer.
Sewers shall have slope steeper than or equal to the ground slope, otherwise the
minimum ground cover may not be maintained through out the length of the
sewer.
What will be the diameter of the sewer designed with the following
conditions:
a) Population to be served: Present = 50,000; Design= 100,000;
b) Water consumption: Present = 130 lpcd; Design = 180 lpcd
c) 80 % of supplied water appears as wastewater
d) Self-cleansing velocity to maintained in the sewer = 0.6 m/s;
e) Maximum velocity in the sewer 3 m/s;
f) Minimum size of the sewer = 150 mm;
g) Peak factor = 2.5
h) n=0.015 i) Average Ground Slope = 1 in 5000
D
2/3
1 D 2
Q A.V * * * s1/ 2
4 n 4
D
2/3
D
2
1
* * * (0.0008)1/ 2 0.380 D = 849 mm
4 0.015 4
Take D = 900 mm (next available size)
1 2 / 3 1/ 2
V R s
1
0.900 / 4 (0.0008)1/ 2 0.697 m/s
2/3
n 0.015
(0.85) 2
Q A.V * 0.697 0.395 cum/s
4
At ultimate peak flow,
q 0.375 d v
0.949 0.77 1.135
Q 0.395 D V
v 1.135 * 0.697 0.791 m/s >0.6 m/s [OK]
For a circular channel running under gravity,
Velocity is maximum when the depth of flow d = 0.8 D
At d/D = 0.8, v/V = 1.140
Hence, vmax = 1.140*0.697 m/s = 0.794m/s < 3 m/s (Maxm. Velocity allowable)
O.K.
At the ultimate average flow rate q,
q/Q =(0.167/0.395)=0.42
NOTE: If the velocity at the present peak flow rate is found to be below 0.6 m/s, then a
slight increase in the slope with the same diameter may help attain the minimum
required velocity of 0.6 m/s
Sewerage System
Preliminary Requirements
It is meant for the transport stormwater and wastewater from the generation
point to the treatment plant. So it should be laid as deep as possible so that all
wastewater or storm water flow can be collected and transported.
Aims of the design are: a) make the system operational and b) Economical to build
and c) make the system durable through out its entire design life
Layout of Sewer Lines
Steps followed for making the layout:
Selection of an outlet or disposal points
Fixing limits to the drainage area or zone boundaries
Network
L.3.1
Trunk Sewer
4
Outfall L1.R.3.1.2
2 3
L1.R.3.1.1
manhole
R.3.1
L2.R.3.1.1 L2.R.3.1.2
R.3.2
NOMENCLATURE IN CASE OF DESIGN OF SEWER
NETWORK USING COMPUTER PROGRAMME
In case of design of sewer
network using computer
programme, there is no
restriction in the
nomenclature of the sewers
and manholes as required
for the manual design.
House
Design Approach
1. On a map of the area locate all the sewer lines and measure the contributory
area to each of the sewer lines or points.
2. Also, draw the longitudinal section or profiles of the sewer lines. Mark on the
profile view the critical points such as basements of the low lying houses, levels
of existing sewers, disposal points, etc.
3. Design all the branch sewers, main sewers and trunk sewers, starting from
the farthest point in the network and based on the following considerations:
Brickwork HDPE
Typical circular manhole Arch type manhole for (1400 mm 900 mm)
DEEP MANHOLES
deeper than 2.5 m
Heavy cover is provided at the top
Size in the upper portion is reduced by offset: May be either square
or rectangular or circular
Access shaft: Minimum size is
0.75 X 0.6 m
It is used when a branch sewer joins a main sewer at a height more than 600 mm above the
main sewer or the drop is more than 600 mm.
Advantages: 1) Steep gradients in the branch sewer can be avoided ; 2) The sewage from
the branch sewers may fall on the person working; This is avoided.
Inspection Arm
Plug
FLUSHING MANHOLE
Gratings
Different Types of Street Inlets
GUTTER TYPE
Generally located near the sources which can generate oil and grease-
contaminated wastewater. Restaurants, garages, automobile repair workshops
Oil and grease in the sewer system can : a) sticks to the inner surface of sewers
and reduces the sewer capacity; b)entraps suspended matter, further reducing
the capacity; c) adversely affect the performance of wastewater treatment
plants
REGULATOR OR OVERFLOW DEVICES OR STORM-RELIEF WORKS
INCOMING FLOW
Intercepting Sewer
Air Line
Spillway
A
R
P
1 2 / 3 1/ 2
V R s
n
It is the most efficient section, among all possible variations
d) Structurally more stable (without any corners, hence load is evenly distributed all
around
e) Chances of deposition is less
d/D a/A v/V q/Q
1.00 1.00 1.00 1.00
0.9 0.949 1.124 1.066
0.8 0.858 1.140 0.988
0.7 0.748 1.120 0.838
0.5 0.5 1.000 0.500
0.4 0.373 0.902 0.337
0.3 0.252 0.776 0.196
0.2 0.143 0.615 0.088
Advantages of a circular sewer diminishes when the sewer is not running at least half-full
Lesser the discharge, poorer is the performance
OVOID OR EGG-SHAPED SEWER
2. Top horizontal diameter of the Ovoid-sewer = 0.84 X Diam. of the circular sewer
3. Find out the other dimensions from the following figures, according to the type of
sewer to be designed
Horse-Shoe Type of Sections
Open-Drain Sections
A
R
P
1 2 / 3 1/ 2
V R s
n
Q A *V
Design a gravity flow trunk sanitary sewer for
the area . The trunk sewer is to be laid
along Peach Avenue starting at 4th Street and
ending at 11th Street. Assume that the
that the following design criteria have been
developed based on an analysis of local
conditions and codes:
b. For commercial, industrial, and institutional areas also obtain the peak
infiltration values from the fig. (b). However, to take into account that the
total length of sewers in these areas will generally be < that in residential areas,
use only 50% of the actual area to compute the infiltration allowance.
7. For infiltration allowance Assume steady flow
8. Peaking Factors:
a. Residential Use the curve, fig. (c)
b. Commercial 1.8
c. Industrial 2.1
d. Institutional (school) 4.0
Peaking Factor
9. Hyd. Design Eq. Manning Eq. , n = 0.0013, Use Fig. 6 -10 (Nomogram)
10. Min. pipe size As per local Bldg. Code, 200 mm
11. Min. velocity 0.75 m/s
12. Min cover As per local Bldg. Code, 200 mm, 2.0 m
Solution:
Table 1
c. Column 14 18, Obtain cumulative peak commercial flows
d. Column 19 23, Obtain cumulative peak industrial flows
Table 2
e. Column 24 26, Obtain cumulative peak institutional flows
f. Column 27 28, Obtain cumulative average and peak flows
g. Column 29 32, Obtain infiltration allowance
h. Column 33 Total Cumulative Peak Design Flow Columns 28 + 32
Table 3
i. Columns 35 38 , Sewer Design, Mannings Eq., n = 0.013 , v > 0.75 m/s
j. Columns 39 42, Layout Data
Column s 39/40 Ground surface elevations obtained by interpolation from Fig. (a)
Column s 41/42 Sewer invert elevations (By Trial and Error from Work Sheet)
Table 4
0.0018
m/m
0.0009
m/m
0.330
0.121
m3/s
m3/s
Line 2-3:
q/Q=0.313/0.330
=0.95
d/D=0.86
v/V=1.04
WORK SHEET
(1) Plot ground surface elevations, working backwards
(2) Sketch invert and crown
(3) Line 1: Locate the invert of the upper end of the pipe
Upper Invert Elevation=Ground surface depth of cover pipe wall thickness pipe dia.
= 20.00 m - 2.00 m - 0.05 m - 0.45 m
=17.5 m
Lower Invert Elevation= Upper Invert Elevation-(Slope of sewer)x(Length of sewer)
17.5 m - (0.0018 m/m) x (707 m)
=16.23 m
Check: Depth of Cover Adequate/ Not adequate ?
=19.00 m (16.23 m + 0.45 m + 0.05 m)
= 2.27 m OK
Depth of cover
Wall thickness
Inside top Crown
Inside bottom Invert
Bottom
Some Other Important Considerations
(1) When a MH is located at a sewer junction:
Outlet sewer invert elevation is fixed by the invert level of the lowest inlet sewer
Sewer junction
16.23 m
16.23 m +0.45 m 15.93 m
-(0.0009 m/m)x(707 m)
-0.75 m
=15.29 m
=15.93 m
Example of a Profile of a Sewer Line
Small Bore Sewer System
They are designed to carry only the liquid part of the domestic sewage generated
for off-site treatment or disposal
The advantages:
Sewer a) The sewer can have less velocity and flowrate
Septic Tank or as it receives only settled wastewater
interceptor tank b) Economic as it requires less cost of
excavation, material and treatment
c) Upgradation from on-site treatment system to
conventional treatment system is easily done
d) Maintenance of strict sewer gradients is not
required as there is no self-cleansing velocity
requirement
The small bore sewer system outfall can be any of the following:
a)The conventional sewer system
b) Waste stabilization ponds
c) Any other low cost treatment systems followed by fish ponds or land-
based disposal with precautions
Limitations:
a) Interceptor tank requires periodical cleaning and disposal of solids
b) Any illegal connection without any interceptor tank shall ruin the
system. So, strict vigilance is required.
Shallow Sewer System
These are modification of surface drain with covers and consist of a network of
pipework laid in the areas away from the places where heavy sewage loads are
expected.
Pipes are laid in flat gradients following the natural slope of the ground. The
minimum depth is 0.4 m
System contains:
a) House connections
b) Inspection
chambers
c) Laterals
d) Street-collector
sewers
e) Pumping stations
Limitations:
a) It is suitable when suitable ground slope is available
b) Unless flushed out at peak flowrates, there is a possibility of solids
deposition if there is not enough ground slope available
c) May require frequent cleaning