Bus Bar Differential Protection Relay Test Procedure
Bus Bar Differential Protection Relay Test Procedure
1. Physical checks, wiring connection & data of busbar differential relay to be verified as per
the drawings.
2. Setting of the relay to be done such as overcurrent monitoring, trip value and timer etc.
3. Test switch of the relay to be turned from SERVICE to TEST position of busbar 1A or 1B
or 2A or 2B.
4. Omicron Test Equipment to be connected to the Test switch of the relay, by the test plug.
5. Omicron test equipment to be switched ON by using PC.
6. Current should be applied just below the set value and then gradually to be increased till the
relay picked up and the value to be recorded.
7. Operating time to be recorded for monitoring of the relay.
8. Scheme of busbar differential protection to be tested as per drawing.
9. Breaker failure start to be observed by the operation of the differential relay.
10. Selective trip to be checked as per configuration.
11. With monitoring alarm blocking of the relay to be observed.
12. Isolator image to be confirmed as per configuration.
13. All LEDs on the relay to be checked for its correct operation.
14. All alarms of the relay to be observed as per the drawing.
15. All the readings to be recorded on the BusBar Differential Protection Relay test report