Chapter 3 Check List
Chapter 3 Check List
CHAPTER 3
CHECK LIST
1 NAME OF THE PROJECT Songad Small Hydel Project
2. LOCATION
a. State Uttarakhand
b. District Uttarkashi
c. Tehsil Uttarkashi
3. CATEGORY OF THE PROJECT
a. Small Hydel Hydroelectric scheme with a total 2 x 3500 KW
installed capacity upto 25000 KW
4. PLANNING
Has the overall development of the stream/canal Yes
been prepared and stages of development
discussed ?
Have the alternative proposals been studied and Yes
their merits and demerits discussed ?
Have the detailed topographical surveys been
carried out for the following items and drawings Yes
prepared as per prescribed scales ?
a. Head work surveys (weir or diversion structure) Yes
b. Desilting tank (not required) Yes
c. Water conductor system Yes
d. Forebay Yes
e. Penstock. Yes
f. Power house, Tailrace etc. Yes
5. GEOLOGY Yes
6. FOUNDATION INVESTIGATIONS
Have the general surveys regarding construction Yes, as applicable and
materials like pervious and impervious soils, sands, necessary
aggregates, etc. been carried out ?
7. HYDROLOGICAL & METEOROLOGICAL INVESTIGATIONS
Have the hydrological investigations been carried Yes
out and status of discharge data of stream/canal
discussed in reports?
8. HYDROLOGY
Have hydrological studies been carried out to Yes
establish the availability of water for the benefits 50% Dependability
envisaged, and what is the dependability of the
potential ?
III-1
SONGAD SHP DPR
III-2
SONGAD SHP DPR
.
Are the major components of work proposed to be Through Contractor
done departmentally of through contractor ?
Have the quantities of the following items been Yes
worked out for various components of the project ?
a.Excavation soft & hard strata Yes
b.Earthwork in filling (wherever applicable) Yes
c.Stone for masonry Yes
d.Coarse aggregated for concrete Yes
e.Steel for reinforcement. Yes
f.Other materials P.O.L., Electricity Yes
13 ESTIMATE
.
a. Is the estimate prepared ? Yes
b. Have the analysis of rates for various major items
and the components of the project been furnished,
with basis of analysis & the price index ? Yes
14 ECONOMICAL & ENVIRONMENTAL ASPECTS
.
Is the area likely to the environmental and No Environmental and
ecological problems due to the altered surface ecological degradation
water pattern and preventive/corrective measures
discussed ? (wherever applicable)
15 CAMP AND BUILDINGS :
.
Has the planning of the camps/building been
done? Yes
16 SOIL CONSERVATION
.
Is the need for soil conservation measures in the Not applicable
project discussed ?
********
III-3