Matindok Gas Development Project (MGDP) Check List System Dehydration Unit
Matindok Gas Development Project (MGDP) Check List System Dehydration Unit
Matindok Gas Development Project (MGDP) Check List System Dehydration Unit
(MGDP)
2 All piping has been pressure tested, clean, and/or flushed, drained
and dried.
9 All safety relief valves have been tested and are in service. All block
valves around relief valves are locked in the correct positions for
startup.
3 Ensure that the auxiliary equipment are available for the TEG
transfer from the source to the glycol accumulator including
Page 1 of 7
MATINDOK GAS DEVELOPMENT PROJECT
(MGDP)
3 Start the loading transfer pump and monitor the level of the glycol
by 350-LG-1141
7 Fill glycol to the Glycol Accumulator (350-D-1002) to HLL (850 mm)
by monitoring both 350-LG-1141 and 350-LT-1141 to avoid over-
filling.
350-GAT-7045
350-GAT-7046
350-GAT-7047
350-GAT-7046
350-GAT-7056
350-GAT-7057
350-GAT-7006
350-GAT-7059
5 Once the necessary setup for the glycol charging has been
completed, the following activities can be proceed. If feed gas or
fuel gas is unavailable, plant nitrogen may be used:
Page 2 of 7
MATINDOK GAS DEVELOPMENT PROJECT
(MGDP)
8 Line up the pump suction and recycle line back to the accumulator.
Open the manual valves on the PSV bypass lines (350-GLO-7008
for pump A and 350-GLO-7009 for pump B). The globe valve should
be fully opened while the globe valve is used to regulate the flow
back to the accumulator. Ensure that the discharge isolation valves
are closed since glycol will not yet be changed to the contactor.
Ensure also that the valves on the contactor bypass line going to
the glycol reflux condenser are closed during the recycle operation.
12 Start the glycol recirculation pump and slowly adjust the flow rate
up to 50% capacity by slowly closing the bypass recirculation valve.
Flow should be monitored with 350-FT-1154. The glycol solution
flows into the Glycol Contactor, the Glycol Flash drum, the filters,
heat exchangers, Glycol Reboiler and back to the accumulator and
piping associated using level controller (350-LIC-1002) of the Glycol
Contactor.
14 Repeat batch process (2) and (4), until all the glycol lines and
vessels are filled to the proper levels.
Page 3 of 7
MATINDOK GAS DEVELOPMENT PROJECT
(MGDP)
Initial Start-Up
Note that although the Activated Carbon Filter has been filled with
glycol during the charging operation, this equipment will be
Page 4 of 7
MATINDOK GAS DEVELOPMENT PROJECT
(MGDP)
2 After pressurizing the Glycol Contactor, the Glycol Flash Drum and
the filters, start glycol circulation without heating. During this cold
circulation, the following conditions must be ensured.
4 Ignite main burner after pilot burner after stable operation can be
achieved at pilot burner
Page 5 of 7
MATINDOK GAS DEVELOPMENT PROJECT
(MGDP)
2 Slowly introduce wet feed gas into the contactor by increasing the
pressure in steps of 100 psi every 5 minutes until the required
operating pressure is achieved.
3 Keep the pressure at the required value and perform a leak test
around the contactor.
6 Feed the wet gas to the contactor at 25-40% of design gas flow
rate while heating up the glycol. Customer shall provide detailed
procedure for off-spec dry gas disposal from the contactor during
start-up.
7 When the operating gas rate becomes stable, the feed gas rate can
be slowly increased to 100%.
350-SC-1001
Page 6 of 7
MATINDOK GAS DEVELOPMENT PROJECT
(MGDP)
11 Sample and analyze the treated gas, and transfer the treated gas
to the pipeline when it meets the specification.
Note: Feeding feed gas to contactor and Gas Glycol Heat Exchanger
also intended to cool down the glycol during hot circulation
otherwise built-up glycol temperature during hot circulation will
occur and cause trip glycol circulation pump due to high-high
temperature protection.
Injection of pH Controller
Note: the pH should not be raised above 8.0 to 8.5 because glycol
tends to foam and emulsify more easily
Injection of Antifoam
Glycol Make-Up
The glycol volume between the HLL and LLL corresponds to a 30-
day glycol inventory before make-up is required.
Page 7 of 7