Chilled Water System Sequence of Operations
Chilled Water System Sequence of Operations
Chilled Water System Sequence of Operations
minimum (as described in sequence 33). This is because, lowering pump speed with the differential
pressure reset strategy (sequence 33) will save more energy than resetting the chilled water temperature
up, per ton of cooling. When the pump speed is at its minimum allowed, start the CHWST reset routine
and continue it until one or more pumps are above their minimum speed, then hold the CHWST
setpoint where it is until the pumps are at their minimums. Include a differential or time delay to
prevent hunting. When enabled, the CHWST reset sequence is: when all CCVs are less than 90%
open, the CHWST setpoint (SPt) is at its highest value of a proportional range (48F). When three or
more CCVs are 90% or more open, the CHWS SPt is at its lowest value (42F).
50 F
48 F
CHWST
Set
Point
and
Temp
42 F
0 1 2 3 4
Number of CCVs >= 90% Open
7. The CHWST reset will not increase when the return air relative humidity rises above 50% [BAS].
8. Chiller Staging. [All in BAS] There is no automatic chiller staging/selection optimization controls.
The first lag chiller will be called for whenever the secondary CHW flow exceeds the primary CHW
flow for 20 minutes (adjustable) as determined by flow meters AND the lead chiller is 95% loaded (by
% of rated current).1 For reference, each secondary CHW pump is design rated at 765 gpm. After a
call has been maintained for the 20 minutes, the first lag chiller and pump sequence start as described
above for the lead chiller. The second lag chiller will start under the same conditions and sequences.
Whenever a lag chiller starts, all running chillers load and unload as necessary to be running within 5%
of the same % load (based on rated current).
1
This 95% load parameter will allow CH-3 to operate as the lead chiller, if desired, up to its full load before the
much larger chillers (CH-1 and 2) start, since there is such a difference in primary CHW flow between CH-1 or
2 and CH-3, but no difference in the secondary CHW pump flows for the different chillers.
9. The last selected lag chiller and associated pumps stage OFF when the total primary CHW flow
exceeds the total secondary CHW flow by the capacity (flow) of the last selected chillers primary
CHW pump for a 20 minute duration (adjustable).
10. All chillers and pumps will turn OFF when OSAT is < 55F for ______ minutes [BAS], OR when all
CCVs are less than 15% open for 10 minutes [BAS], OR when all air handlers are OFF [BAS], OR
when an unoccupied schedule occurs (subject to night low limit conditions not being met) [BAS], OR
when failure alarms are registered (BAS and chiller controls).
13. Demand limiting. [BAS] Demand limiting setpoint adjustment may be made through building
automation system [BAS]. The demand limit (in sum of all chillers kW), when met will delay the start
of the next chiller for one hour (adjustable). This sequence is different than the disabled stock sequence
in the chiller packaged controls.
14. The BAS will monitor kW and calculate the load on the chiller using evaporator CHW flow and
temperature differentials [BAS].
15. Provide emergency stop switch located adjacent to chiller room mandoor exit to stop all equipment in
chiller room, except ventilation system. Ventilation fan to automatically operate on purge mode with
activation of emergency stop switch.
Primary Chilled Water Pumps (CHWP 1`, 2, 3 for CH-1 & 2 and CHWP 4; 5 for CH-3)
16. Each primary CHW pump is assigned to one chiller [BAS]. Lead primary CHW pump starts upon a
call for cooling per above chiller sequences. Lag primary CHW pump starts upon a call for the lag
chiller per above chiller sequences [BAS]
17. Primary CHW pumps to operate continuously when their associated chiller is running. Primary CHW
pumps provide constant flow through the chiller according to the manufacturers recommendations:
675 gpm for CH-1 and CH-2 and 180 gpm for CH-3. Check balancing report for finals.
18. A standby (redundant) primary CHW pump is provided for CH-1 and 2 together and can be operated
as active pumps after opening manual valves. A standby primary CHW pump for CH-3 will
automatically change over [detected by BAS and chiller controller; pump control by BAS].
19. a) CHWP 1, 2; 3: Alarm on pump failure detected via a motor current switch and flow switch. Upon
failure of lead pump, chiller shuts down and lag chiller should start automatically to meet load [BAS].
b) CHWP 4; 5: Alarm on pump failure detected via a motor current switch and flow switch. Upon
failure of lead pump, standby pump automatically starts [detected by BAS and chiller controller; pump
control by BAS].
23. CT Sequences. [All BAS] The CT during the normal cooling season rejects heat from the chillers and
returns as cool of water as possible to the chillers condenser, down to 65F. The CT will try and
maintain a 65F return temperature (ECDWT) by first modulating the normally open bypass valve,
with no water going over the top of the tower. When the valve is full open AND the ECDWT is greater
than the ECDWT setpoint (65F), the bypass valve begins to close and the normally closed CT control
valve associated with the respective CT and CDW pump, opens 100% and water goes over the
respective CT. The bypass valve continues to modulate open to try and maintain the ECDWT setpoint
without the CT fans. When the ECDWT reaches 69F, the bypass valve will be fully closed and the
pony motor CT fan turns ON. When the ECDWT reaches 73F, the main CT fan turns ON. As the
ECDWT decreases, the main fan turns OFF at 69F and the pony motor fan turns OFF at ECDWT of
65F. All parameters are adjustable. There is an eight minute delay between each stage.
ECDWT
Fan Spd ON (F) OFF (F)
OFF <69 ----
(modulation of bypass valve)
*Low 69 65
*High 73 69
* Bypass valve should be closed.
24. When a lag chiller comes on line, its condenser water pump and associated CT come on line [BAS].
25. A multiple position CT sump or basin level sensor provides the following information to the BAS:
a) High water alarm
b) Low water alarm
c) Open make up water valve
d) Closed make up water valve
e) System shutdown
Alarm on heater stage failure detected via current sensing switch.
26. Cooling tower sump two stage heaters shall be controlled to maintain a sump temperature of 45F with
the following schedule [BAS]:
ON (F) OFF (F)
Stage 1 45 43
Stage 2 47 45
Each CT basin has a temperature sensor and separate??? heaters.
27. Cooling tower makeup valve (one for all three CTs) to maintain sump water level. Upon sensing a
drop in water level, slowly open makeup valve in industrial cold water line [level sensor by BAS].
28. Alarm on pony and main motor upon motor failure detected via current sensing relay. Upon failure of
fan motor, lag CT starts automatically [BAS].
29. Alarm on excessive vibration detected via vibration limit switch. Upon failure of fan, lag CT starts
automatically [BAS].
30. The lead cooling tower operate during periods, when the chillers are OFF (even during winter) to
maintain a heat rejection source for the heat exchanger HE-1, which serves approximately 40 tons of
cooling from ACU-1 thru 10 and CRU-1. See sequences for CDP 6, 7, 8; 9.
32. Lead secondary CHW pump starts upon a call for cooling per above chiller sequences. Lag secondary
CHW pump starts upon a call for the lag chiller per above chiller sequences [BAS].
33. Differential pressure control. [All BAS] The objective is to always have one CCV 80% open so the
pumps operate at the lowest speed and pressure possible to satisfy the current load. Every 5 minutes
the CCVs are polled. A PI loop that changes the secondary pump discharge differential pressure
setpoint to maintain the remote (local on 8th floor) DP setpoint to maintain the most open CCV at 80%
open (with a deadband of +/-_________). For example: When the most open CCV is more than 80%
open, a PI signal is calculated and changes the local DP setpoint upward. When the local DP setpoint
is not being met, a PI signal is calculated and sent to the pump discharge pressure setpoint and it is
raised accordingly. Through another PI loop, the variable speed (frequency) drive (VFD) increases the
pump motor speed to meet the raised pump differential (discharge) pressure setpoint.
The remote DP setpoint will be maintained between maximum and minimum pressures. The maximum
pressure limit is the pressure required to provide full flow to all CCVs simultaneously (per TAB). The
minimum pressure limit is the pressure correlating to the lowest speed the pump motor is allowed to be
operated at (per motor manuf. and TAB). Maximum pressure limit:__________psi. Mininum
pressure limit:__________psi.
The VFD internal settings will allow the VFD to run the pumps to their minimums.
Number of remote DP sensors: _______. Locations: ________________________________
___________________________________________________________________________
34. Pump Staging. [BAS] With one secondary CHW pump running, when the total secondary CHW gpm
exceeds the lead secondary CHW pump design gpm AND the discharge differential pressure drops
more than 2 psi below the setpoint for 10 minutes (all adjustable), start the first lag pump. Both pumps
converge and run at similar speeds and gpm to maintain the common discharge pressure differential
setpoint and the remote DP setpoints. If the total secondary gpm exceeds the total design gpm of the
running pumps (lead and 1st lag) AND the discharge differential pressure drops more than 2 psi below
the setpoint for 10 minutes, start the second lag pump. All three pumps converge and run at similar
speeds and gpm to maintain the common discharge pressure differential setpoint and the remote DP
setpoints.
35. During reducing load as the DP increases: when the total secondary CHW gpm has reduced to be
equal to or less than the sum of the first two selected pumps gpm for 10 minutes (adjustable), the
second lag secondary CHW pump shuts OFF. Similarly, when the total secondary CHW gpm, with
two pumps ON, has reduced to be equal to or less than the gpm of the lead CHW pump for 10 minutes,
the first lag pump shuts OFF.
36. The controller shall monitor rpm and gpm of the pumps and shall not allow operation of the pumps at
or beyond their published End of Curve [BAS].
37. Alarm on pump failure detected via current sensing switch. Upon failure of pump, next lag pump
starts automatically (BAS and chiller controller).
38. Alarm on failure of VFD [BAS].
39. The rpm of secondary CHW pumps to be monitored by BAS.
40. For coil freeze protection during smoke exhaust system operation, pumps CHWP-6, 7; 8 to run under
NORMAL control and all cooling coil valves to open with operation of respective AHU when smoke
exhaust system (EF-10) is in operation AND outside air temperature is below 40F [BAS].
exchanger to the cooling towers. CDP 8 or 9 (one is redundant) services the ACUs and CRU-1 from
HE-1. The selected CD pump for each loop (CDP 6 or 7 AND 8 or 9) operate continuously [BAS].
42. During chiller OFF periods, the ECDWT setpoint and CT bypass valve and fan staging parameters
remain the same as during chiller ON periods (see above).
43. Alarm on pump failure detected via current sensing switch. Upon failure of any pump, standby pump
automatically starts [BAS].