Detailed Scheduling and Planning (DSP) Practice Questions - APICS CPIM
Detailed Scheduling and Planning (DSP) Practice Questions - APICS CPIM
One year
Three month
1) How long should the planning horizon in master scheduling be?
One year
Three month
Explanation
The planning horizon represents a time span for which plans are made and should at least
be equal to the time needed to fulfill the plan.
2) Available to promise (ATP) is best described through which of the following definitions?
The promised orders that are currently in a queue and await processing
A number of goods a firm can promise to its customers taking inventory and available
capacity into account
The portion of a firm's inventory and planned production that is not committed and
available to the customer
2) Available to promise (ATP) is best described through which of the following definitions?
The promised orders that are currently in a queue and await processing
A number of goods a firm can promise to its customers taking inventory and available
capacity into account
The portion of a firm's inventory and planned production that is not committed and
available to the customer
Explanation
An MPS time fence can be categorized into three zones, liquid, slushy and frozen which
represent the cost and disruption to manufacturing caused by changes. The extent of the
slushy zone is defined by the planning time fence, and it is a zone where computers will
not automatically reschedule orders due to required tradeoffs.
4) Which of the following production planning activities is typically performed first?
Production planning
Production planning
Inventory
Capacity
Production plan
Inventory
Capacity
Production plan
The production plan is not a direct input to material requirements planning (MRP). It is,
however, a direct input to master production scheduling which again is a direct input to
material requirements planning (MRP).
Certico
CPIM Exam Prep