Layered Audit
Layered Audit
Relay all other unsatisfactory items If unsatisfactory items have the potential to
to the responsible personnel and place the product quality at risk, immediate
note who was contacted on the action must be taken by manufacturing to
checklist correct the situation. Issues that cannot
be corrected immediately should be
tracked throughout the plant corrective
action process or through the internal audit
process and escalated as required.
Communicate non-conformances to
Manufacturing Engineering for feedback
into FMEAs if appropriate.
Monitor and report layered audit Layered audit results will be reviewed by
results management on a periodic basis. The
effectiveness of the layered audit process
will be evaluated by tracking/reviewing
layered audit schedule adherence and first
time conformance results (number of items
conforming during the audit vs number of
items checked
C). Repeat issues should be identified
and addressed.