Terms of Reference
Project Management & Integrated Collaboration System
Terms of Reference
Introduction
Background
From the first 18 months since its Entry Into Force in April 2013, most of MCA-Indonesias
work focused on designing and preparing the 3 key projects and meeting the requirements that
are necessary and imperative to allow those projects to enter into full implementation. As
such, the business processes and supporting systems used were rudimentary not designed to
support the projects management needs.
As such, the objectives of this integrated system is to streamline the internal business
processes of MCA-Indonesia in order to support:
Program execution and monitoring;
Fast deployment of resources;
Cost tracking
Work Breakdown Structure
Promote collaboration between team members;
Improve workflow and notification
Increase efficiency and effectiveness of program / project productivity by utilization
the use of integrated source of information,
Improve and assure information availability and accessibility;
Ensure compliance
Terms of Reference
Work
Resource
Breakdo
Scheduli
wn
ng
Structure
Tim
e
Work Budgetin
Breakdow
n
Proje g and
Forecasti
Structure
ct ng
Scop
Cost
e
Advanced
Project
billing
Contracts
rules
Timeshee Pay when
ts paid
Objective
In the longer-term, the system is expected to assist the MCA-Indonesia in achieving its
objective of becoming a pilot national trust find institution. The integrated system (which is
also called IMS Integrated Management System) should contribute to MCA-Indonesias
knowledge management and institutional development, by enhancing the organizations
capital: human, information, relationship, and social. The system ought to be able to capture
MCA-Indonesias experience, distilling the lessons learned and best practices which would be
an asset for the organizations future growth as well as learning resource for others.
Terms of Reference
Scope
The Project Management and Integrated Collaboration Systems will support Project
Management to plan, create, manage, control and complete projects for MCA-Indonesia.
Community / Customer-focused projects can be set up on a time and materials or fixed-price
basis. Also the module can be used to manage costs for internal and investment projects.
MCA-Indonesia can create project contracts with one or more funding sources that will be
invoiced for project costs and fees. Funding sources can include customers, internal
organizations, and grants. A project contract can have one or more projects assigned to it.
Each project that you create can have one or more subprojects and activities that comprise the
project work structure. For flexible project planning, MCA-Indonesia can integrate to
Microsoft Project Server existing system (Microsoft, SAP and GIS). Note that Project
Structure and project contracts are already created in SAP, therefore the System will just need
to gather the information from SAP and integrate it. Contract creation is not required under
this system.
MCA-Indonesia can create and monitor project budgets for cost control. Employees and
contractors can enter project timesheets and expense reports to record project-related time and
expenses.
Terms of Reference
MCA-Indonesia can create service industry-focused projects that consist primarily of worker
services by drawing on features such as contract management, quotations, budgeting, project
policies, project parameters, and categories.
MCA-Indonesia can assign attributes for project skills and experience to workers. MCA-
Indonesia can also search for and assign workers to a project based on worker skills and
availability, or based on the requirements for a project.
MCA-Indonesia can assign indirect costs, define the calculations for indirect cost amounts,
and allocate indirect costs to a project. Indirect costs are calculated based on worker hours that
are added to a project.
Project managers can view reports that provide project details and analyze project financials
from a variety of perspectives.
Project Management
Maintain comprehensive worker information from the day that they first apply for a
job to the day that they retire.
Define organizational benefit plans and options, enroll workers in benefits, assign
dependent coverage, and designate beneficiaries.
Implement and track profile-based clock in and clock out registrations for workers,
enable workers to register work time for specific activities, and generate pay
information that can be exported to a payroll system.
MCA-Indonesia Travel and expense management to create an integrated workflow where you
can store payment method information, import credit card transactions, and track the money
that employees are spending when they incur expenses.
After the completion of any project, the project management module should generate adequate
asset information for continuing the asset management throughout the life of the respective
asset. MCAI-Indonesia require at least 1 st and 2nd level of asset can be tracked inside the
project management system.
The Project management and Fixed assets should has the following integration points:
In the Projects form, you can specify a fixed asset for an investment project. Fixed
assets are defined in the Fixed assets module.
The scope of Project Management and Integrated Collaboration Systems is to develop a data
management, reporting and collaboration system that utilize existing hardware, software, and
licensed software in MCA-INDONESIA.
1. Summary of activities
The main tasks for the development and installation of the Project Management and
Integrated Collaboration Systems are as follows:
a) Developing, installing, and testing the required integrated system for MCA-
INDONESIAs.
b) Performing implementation and functional testing of software mentioned in the
scope.
c) Creating a culture of support for implementation mentioned in the scope with
support of MCA-INDONESIA management.
The Provider should produce document design business process for all activities that
affected during the implementation for this project, need to detailing methodology, tools
and aspects.
Terms of Reference
Prior to the development of the system, the Service Provider will be required too:
a) Installing the hypervisor Hyper-v required.
b) Installing the server operating system on a virtual machine required.
c) Installing SQL Server on one of separated virtual machine.
d) Installing and configuring New system Server in two different virtual machines. In
the first virtual machine, is configured as a front-end server. While in the second
virtual machine, configured as application servers. Database that will be used by
the virtual machine is on its own as mentioned in point (c).
e) Installing and configuring Project Server to all server.
f) Installing and configuring storage for SQL Server data storage on a separate
machine.
g) Installing and configuring regular backup process to maintain the data availability.
h) Configuring output data system existing (SAP) to be integrated with the latest
interface management system (IIMS).
i) Configuring ESRI/GIS to be integrated with the latest interface management
system (IIMS).
After the core supporting software is installed, the next stage is the development and
implementation of the integrated system to meet the following functions which can be
summarized in the diagram below. Each of system will be described in Functional
Requirement and Business Specification.
Document Management
Project Management
Human Resource Management
Financial/Procurement Management
Contract Management
Leave/Travel Management
Asset Management
Terms of Reference
System Overview
The expected scope of each of these management functions is illustrated in the diagram below.
Managing multiple projects that are under the control of MCAI requires good management in
terms of oversight the use of funds and human resources. Both of these factors are the key
success for all project held by the MCAI. Currently the utilization of human resource
management has not been well controlled resulting in the allocation of work and its use will
occur overlap. These conditions must be addressed by the implementation of Enterprise
Project Management concepts for controlled between planning and actualization for human
resources. The same thing will take effect for the use of funds between planning and its
actualization. By doing actual control over the use of funds and planning also can show how
far the project has been running.
In order to facilitate governance, it has become essential to be able to manage, monitor, and
assess the status of all projects (and other assets, of course) in the enterprise, through a set of
(preferably uniform) Enterprise Project Management processes, methods and application
packages. Typically, organizations that adopt an Enterprise Project Management way of
working, might set up a Project Management Office (PMO)/ Enterprise Project Management
Office (EPMO), which is said to be more successful than a traditional PMO in addressing the
priorities of the organization as its scope is enterprise-wide.
a. Project Scheduling
The project schedule is the tool that communicates what work needs to be performed,
which resources of the organization will perform the work and the timeframes in which
that work needs to be performed. The project schedule should reflect all of the work
associated with delivering the project on time. Without a full and complete schedule, the
project manager will be unable to communicate the complete effort, in terms of cost and
resources, necessary to deliver the project.
b. Project Baseline
In Project Management, Baseline refers to the accepted and approved plans & their related
documents. Project baselines are, generally, approved by project management team and
those are used to measure and control of project activities.
d. Project Budget
If your project contains cost information for budgeting or for tracking project
performance, this information is not doing you much good unless you can view and
analyze it. Without a solid understanding of where your costs are going in a project, the
project can quickly fail and become unprofitable. This tools should have control project
budgeting and actual cost from SAP regularly.
e. Project Procurement
Procurement process for project related should be linked to SAP procurement activities
report. This will integrate all purchase related project from SAP to related project actual
cost.
f. Project Portfolio
Project Portfolio is the centralized management of processes, methods, and technologies
used by project managers and project management offices (PMOs) to analyze and
collectively manage current or proposed projects based on numerous key characteristics.
All activities task related within project that need human effort should be include in the
project task. Every day actual activities from every single person that related within
project should be recorded and analyze in Project Dashboard. The activities is called
TimeSheet Management.
Projects are collaborative efforts, which is why having a centralized place for collaboration
and document sharing is so important. In Project Insight, you can upload and share project
related files and documents in the project documents repository so the whole team is always
on the same page. Post and share communication at the task or project level, and keep all
project information in one easy to access location.
Other Functionality
In order to manage operational projects and monitoring common daily employee request, this
system should comply 2 sub system such as :
a. Leave Online is a new system web-based Leave Management System that streamlines
communication between HR and employees and facilitates simple yet efficient
management of employee leave. this system allows them to easily determine their
vacation availability (from any point-in-time) and request leave online.
b. Travel Request. All Travel Authorizations and Reimbursements (except for team
travel) must be processed through this sub system. The Travel Request System
Mileage and per diem rates and lodging maximums are embedded in the system, and
calculations are performed based on travel dates and location(s) entered.
Terms of Reference
Functional Requirements
Document Management
Description:
The deliverables document for all project in MCAI should deploy on this document
management system that support versioning, security for files and folders, crawling
capabilites, sharing and collaboration, and other functionalities.
The Document Management should define on every project that MCAIs handle to define
collaboration between all project members.
Project Management
Description:
This the key central of implementation for this project, the service provider should
implement project management tools based on requirement and business process gathering
during project activities. This tools should provide scheduling, project base line, timesheet
activities, pra project activities and post project activites.
Terms of Reference
All reporting related with this project should have capabilities to generate dashboard and
produces data for utilitization of resources and all spending budget integrated with SAP
procurement data and cost expense that related to the project. The integration process does
not need real time process, it could be batch or schedule based.
In order to facilitate governance, it has become essential to be able to manage, monitor,
and assess the status of all projects (and other assets, of course) in the enterprise, through a
set of (preferably uniform) Enterprise Project Management processes, methods and
application packages.
Description:
The HR function consists of tracking existing employee data which traditionally includes
personal histories, skills, capabilities, accomplishments, salary and any other related activities.
To reduce the manual workload of these administrative activities, HR began to electronically
automate many of these processes by introducing human resource management systems.
All project activities of the project should integrated with human capital data, include personal
MCAI and 3rd parties. The service provider should also cater these additional functionalities :
Terms of Reference
How to generate performance report activites all personal related in all projects to lookup
corelation between plan and actual data.
Employee leave request application that should integrated with this new system
technology. The Employee leave request should maintain all activities.
Travel request application should implementing during this project activities to cover all
MCAIs personel travel request in board and out board.
Financial/Procurement Management
Description:
Budget management will manage budget lifecycle with preparation and monitoring tool that
provide real time access to budget information. The budget administrator can define plans,
track the progress and status of multiple budgets simultaneously, and make adjustments to
posted budgets within budget management tool.
o Display cash flow status and tracking activities to monitor how funds are
spent across various units more accurate.
4. Reporting & Analysis
o The ability to generate accurate balance sheets, profit and loss
statements, budget allocations, and other important financial reports.
o Other related reports
5. Other Related process
o Project Portfolio Management
o Project Related procurement integration with SAP (batch)
o Project Costing Integration with SAP (batch)
Output Financial/Procurement management database and functionality
Description:
Resource Contract management is the process to ensure that contract is structured properly
and reviewed appropriately, its provisions enforced and intent realized, and its weaknesses
recognized and corrected. The services provider should define resource contract management
for all personel and 3rd parties, to control expiry status and other things.
Description:
Schedule activities based on schedule that related with project or operation should be
published for each personel.
Asset Management
Description:
Asset management helps user to control spend, give ability to procure parts, material and
services effectively.
It should give positive impact on the performance of assets and the cost of operations and
maintenance.
Asset management manages internal requisitions and purchasing requests. It monitors
requisition status from beginning to end.
It is required that the asset management system to integrated with existing
ESRI/GIS system in MCAI Indonesia, for feeding information : asset/location,
project/work
Of all existing hardware and software, it is built a hybrid cloud system that integrates
infrastructure in MCA-INDONESIA Data Center with Cloud Office 365. The details are as
follows:
Active Directory is installed and configured in MCA-INDONESIA Data Center and
syncronizes to Cloud Office 365. By then users only need to have single account for
all applications.
Employees email installed in Cloud Office 365 with single account as mentioned
above.
All the users laptop have been installed Microsoft Windows operating system and
Microsoft Office 365 Professional Plus, with single account as mentioned above.
Current System
Hardware and software to support Project Management and Collaboration Intergated Systems
will be considered next based on providers suggestion, if any.
Terms of Reference
Other Requirements
Other requirements need to be considered as follows:
Change Management
Any change in work procedures requires a thorough process to prevent difficulties and
defensives. It is expected that changes preparation scheme to be realized in the form of
work culture to anticipate the use of invested supporting hardware and software, include
support and training.
Training
The Service Provider shall be responsible for complete maintenance of the Project
Management and Integrated Collaboration Systems software deployed in MCA-Indonesia
for the three (3) months maintenance period after deliverable. This shall include but is not
limited to:
Bug Fixing.
Minor changes, the changes which do not require a change in design.
Technical Support.
Terms of Reference
Deliverables
All reports must include an executive summary and must be submitted in both the English
language and Bahasa Indonesia and each version must be submitted in both hard copy (2)
and in electronic format.
Performance Period
The project is expected to take 6 (Six) months upon signature of the contract signed and
the place of activities will be in MCA-INDONESIA Office.
Terms of Reference
Key Personnel
The Key Personnel for this project, must meet the following requirements below:
1. 1 (one) Project Manager who is Project Management certified and had the
knowledge of Project Management and have strong knowledge about busiinss
process in Project Management with a minimum experience of 5 years.
2. 1 (One) Functional expert who has Trade and Logistic or Entreprise Asset
Management certification with a minimum experience of 3 years.
3. 2 (two) Technical experts who have technical certification with master level in
Business Application software, with a minimum experience of 5 years.
4. 1 one Technical person with master level in Business Application software, with a
minimum experience of 2 years.
Terms of Reference
1 Multilingual The system shall support multiple languages and/or have language conversion capability
2 (e.g. French, Spanish, and Portuguese).
1 Customizable The system shall have the capability to be customized to meet the particular needs of the
3 aid recipient program.
(i.e. Data model and workflows of the supporting applications (Finance, Procurement,
Project Management, Reporting) can be customized and/or expanded to support the
needs of the Program.)
1 Aid Recipient Program Hierarchy The system shall establish the Program Hierarchy (Project>Activity>SubActivity>Task
4 and below), which will be replicated in each functional module (Financial, Procurement,
M&E and Project Management). The Hierarchy shall align with the
Hierarchy established in the related Federal Government Agency application.
Terms of Reference
Though some values for Programs may not be defined in this model, it is expected that
at a minimum, for those elements that must be reported back to Federal Agency, that the
specific application Data Model reference must be followed.
1 Support Integration with Federal Agency The system shall have the technical capability to integrate with a specified Federal
8 Application Agency application, operating as a source system of Program data for Agency required
reports.
The system shall be able push data to the Federal Agency application and/or the Federal
Agency application shall be able to pull data from the system.
The objective is to avoid duplication of efforts between the development and of this
program system and the related Federal Agency Application.
Note: The related Federal Agency application is a .NET application built on a SQL
database, which is made available in an Agency collaboration zone. The application is
accessed via a web interface. Federal Agency resources have single sign on access via
their Active Directory accounts. Aid Program resources request an external Active
Directory account and are challenged to log into the application each time the resource
accesses the system.
Terms of Reference
Finance & Accounting Requirements (General Ledger, Chart of Accounts & Accounts Payable)SUM
# Short Name Description Core or Custom
2 Core Accounting and Finance The system shall provide specific functional capabilities for Core: SITACorp SwIFT
5 Functionality managing a general ledger, controlling funds, making payments, solution, except that
managing receivables, reconciling cash, forecasting and budgeting, some capabilities
and reporting. implemented as part of
SITA arrangement with
MCC (e.g. MCC
reporting requirements)
2 General Ledger for Double-Entry The system shall maintain a General Ledger that supports double- Core: SITACorp SwIFT
6 Accounting entry accounting. solution
2 Program-Specific Chart of Account The system shall capture the Program-specific Chart of Core: SITACorp SwIFT
7 Accounts, including assets, liabilities, income (revenue), expenses, solution
advances and retentions.
2 Additional Ledgers for Budget, The system shall maintain additional ledgers to manage the Program Core: SITACorp SwIFT
8 Obligations and Commitments budget, obligations (signed contracts) and commitments (planned solution, except that
future use of budget funds). some capabilities
implemented as part of
SITA arrangement with
MCC (e.g. MCC
reporting requirements)
2 Maintain Historical Versions of The system shall maintain current and multiple historical versions of Implemented as part of
9 Spending Plans spending plans. SITA arrangement with
MCC (e.g. MCC
reporting requirements)
3 Program Hierarchy Structure for All The system shall include for all financial transactions the Core: SITACorp SwIFT
0 Program Budget and Cost Transactions classification codes that define the Program Hierarchy (Project > solution
Activity > Sub Activity > Task and below).
3 Record Tasking at the Lowest Level of The system shall record Program Tasks at their lowest level of detail Core: SITACorp SwIFT
1 Detail and summarize and roll them up to higher levels (i.e. Sub-Task to solution
Task, Task to Sub-Activity, Sub-Activity to Activity, etc.) in a
Terms of Reference
(The system shall handle Purchase Orders -- the term used most often
for Goods procurements -- the same as contracts -- the term used for
works and consulting services. )
6 Integrate Contract Data with The system shall commit funds for contract values and Core: SITACorp SwIFT
9 Financial Application modifications in the financial application and check "funds solution
availability."
7 Associate Contracts to Established The system shall include for each contract the Core: SITACorp SwIFT
0 Program Hierarchy (Project > appropriate classification codes that define the Compact Hierarchy (i.e. solution
Activity >SubActivity> Task) Project > Activity >SubActivity> Task and below).
Terms of Reference
Reporting Requirements
# Short Name Description Remarks
12 Customized Reports The system shall support development of customized reports that Core: SITACorp SwIFT
2 integrate data from all modules (financial, procurement, and limited solution
PM).
12 Quarterly Disbursement Report The system shall be able to generate data for the compilation and Implemented as part of
3 Package (QDRP) submission of the QDRP to the Federal Agency. SITA arrangement with
MCC re: MCC reporting
requirements
12 Schedule A The system shall be able to generate the Financial, Schedule A report, in Implemented as part of
4 accordance with the Federal Agency pre-defined format. SITA arrangement with
Schedule A: This is a request to reallocate funding across Projects MCC re: MCC reporting
and/or Activities. This report includes the original Program budget, the requirements
current approved Program budget and the proposed increases or
decreases in Projects and/or Activities. This request for reallocation
must be submitted quarterly with the QDRP and can also be submitted
"out of cycle" if necessary.
12 Monthly Commitment and The system shall be able to generate the MCDR report, in accordance N/A
5 Disbursement Report (MCDR) with the Federal Agency pre-defined format.
Terms of Reference
Reporting Requirements
# Short Name Description Remarks
12 Schedule F The system shall be able to generate the Financial, Schedule F report, in Implemented as part of
6 accordance with the Federal Agency pre-defined format. SITA arrangement with
Schedule F: The Cash Reconciliation report provides a summary of the MCC re: MCC reporting
cash balance in the Program Permitted Account (local bank account). requirements
This report includes the cash balance in the Permitted Account at the
start of the period, the total amount of cash received into the account
and the total amount of disbursements paid out of the account during
the reporting period.
12 Detailed Financial Plan (DFP) - The system shall be able to generate the Financial, DFP - Commitments Implemented as part of
7 Commitments Plan/Report, in accordance with the Federal Agency pre-defined format. SITA arrangement with
Detailed Financial Plan (DFP) - Commitments: This report includes MCC re: MCC reporting
projected Commitments for future quarters (next period reported by requirements
month and future periods by quarter). The report also includes variances
for the Commitment projections provided the previous quarter and
actual commitments reported. Commitment data is structured according
to Program hierarchy (Project > Activity >SubActivity> Task, etc.)
12 Detailed Financial Plan (DFP) - The system shall be able to generate the Financial, DFP - Cash Implemented as part of
8 Cash Plan/Report, in accordance with the Federal Agency pre-defined format. SITA arrangement with
Detailed Financial Plan - Cash: This report includes actual Cash MCC re: MCC reporting
Disbursements previously reported, actual Cash Disbursements during requirements
the current reporting period and projected Cash Disbursements for
future quarters (next period reported by month and future periods by
quarter). Disbursement data is structured according to Program
hierarchy (Project > Activity >SubActivity> Task, etc.)
13 Procurement Performance Report The system shall be able to produce the mandatory Federal Implemented as part of
0 (PPR) Agency Procurement Performance Report (PPR), which is submitted to SITA arrangement with
Federal Agency with the Quarterly Disbursement Report Package. The MCC re: MCC reporting
PPR describes "Actions" against approved Procurement Items. Each requirements
Action is associated to a Procurement Item, and there may be multiple
Terms of Reference
Reporting Requirements
# Short Name Description Remarks
Actions associated to a single Item. Additionally, there may be multiple
amendments associated to each Action. In this instance, original and
amended data will be reported. The following information is reported
for each Action:
-Contract Award #
-Status (Procurement Phase, Open, Closed, Terminated or Canceled)
-Original Contract Amount
-Firm/Individual Name
-Firm/Individual Nationality
-Method of Procurement Used
-Expression of Interest: Date of Federal Agency Approval, Date of
Publication in UNDB DG and/or Local Newspaper, Deadline for
Responses
-Solicitation Data: Date of Federal Agency Approval and Date of
Publication in UNDB DG and/or Local Newspaper, Deadline to
Receive Responses
-Evaluation Data: Number of Bids Received, Date of Federal Agency
Approval of Evaluation Report, Date Financial Proposal Opened, Date
of Federal Agency Approval of Contract Award, Date of Contract
Award, Date of Notice of Award, Date of Eligibility Verification
Date of Last Contract Past Performance Report (CPPR)
Amendments will include the following information:
-Modification Description
-Modification Amount
-Completion Date of Contract
Terms of Reference
Reporting Requirements
# Short Name Description Remarks
13 Procurement Plan The system shall be able to generate the content of the Procurement Implemented as part of
2 Plan/Report, in accordance with the Federal Agency pre-defined format. SITA arrangement with
MCC re: MCC reporting
The system shall be able to produce the mandatory Federal Agency requirements
Procurement Plan, which is submitted for Federal Agency approval
every six months, at minimum. The Procurement Plan includes a list of
proposed Items for procurement valued at $25,000 or more. Items are
re-submitted for approval if there is an amendment to the original
request and the original request data is retained. Procurement Items are
associated to the Program hierarchy (Project > Activity >SubActivity>
Task, etc.) and they include the following attributes:
-Unique Item ID
-Status (Planned, Submitted for Approval, Approved, Rejected)
-Description
-Fund Type (609(g), CIF, Program)
-Requirement Type (Goods, Works, Consultant Service, Non-consultant
Service)
-Method of Procurement Planned (QCBS, CBS, SIC, ICB, NCB)
-Estimated Start Date
-Estimated Value (USD)
-Common Procurement Vocabulary (CVP) Code
13 Procurement Implementation Plan The system shall produce Work Plan data required for the Procurement Implemented as part of
3 (PIP) Implementation Plan (PIP), including timelines, required approvals and SITA arrangement with
proper sequencing of procurement activities. MCC re: MCC reporting
requirements
Terms of Reference
Reporting Requirements
# Short Name Description Remarks
13 Fund Accountability Statement The system shall generate data for the auditable Fund Accountability Implemented as part of
4 Statement (FAS) on a Cash Basis (recording income when received and SITA arrangement with
expenses when paid) by Project and Activity. MCC re: MCC reporting
requirements
13 Ad Hoc Reports The system shall have ad hoc reporting capabilities. Core: SITACorp SwIFT
5 solution - Canned reports
available through SAP
13 Export Report Data The system shall allow users to export report data to formats including Core: SITACorp SwIFT
7 but not limited to Microsoft Word, Excel, Adobe Acrobat/PDF, solution
HTML and CSV.
13 Report Filters The system shall allow the selection of report criteria and/or filters, Core: SITACorp SwIFT
8 such as reporting periods or posting dates. solution
13 Varied Levels of 'Report View' The system shall provide a public view and specific views for Program Core: SITACorp SwIFT
9 Permissions staff based on role-based access controls. solution