1963 Report Royal Commision Failure Kings Bridge
1963 Report Royal Commision Failure Kings Bridge
1963 Report Royal Commision Failure Kings Bridge
VICTORIA
REPORT
OF
ROYAL COMMISSION
INTO THE
By Authority:
A. C. BROOKS, GOVERNMENT PRINTER, MELBOURNE.
No. 1.-6352/63
ROYAL COMMISSION OF ENQUIRY
INTO THE FAILURE OF KINGS BRIDGE
Report of the Hoyal Commission to His Excellency. Major-General Sir Rohan
Delacombe, Knight of the British Empire, Companion of the Bath, Companion of the
Distinguished Service Order, Governor of the State of Victoria and its dependencies in the
Corrunonwealth of Australia.
YouR ExcELLENCY,
In pursuance and execution of Letters Patent dated the Twenty-eighth day of August,
1!)62 under the Seal of the State of Victoria, whereby His Excellency, the Honourable
Lieutenant-General Sir Edmund Francis Herring, K.C.M.G., K.B.E., D.S.O., M.C., E.D.,
Lieutenant-Governor of the State of Victoria issued to us
His Honour Edward Hamilton Esler Barber, a Judge of the County Court;
Dr. James Adam Louis Matheson, M.B.E., M.Sc., Ph.D., M.I.E.Aust., Vice-
Chancellor o(the Monash University;
and
Professor John Neill Greenwood, D.Sc., M.Met.E., Dean of the Faculty of
Applied Science of the University of Melbourne ;
a Commission authorizing and appointing us to enquire into and report to Your Excellency
upon the following matters, namely, the cause or causes of the failure of the bridge known
as Kings Bridge, constructed pursuant to the King-street Bridge Act 1957 and in addition
and without derogating from the generality of the foregoing, the following matters:-
(I.) The terms, conditions, specifications and drawings in accordance with which
tenders for design and construction of the bridge were invited by the
Country Roads Board, and whether the same were adequate and reasonable
for the purpose ;
(II.) The tenders received, the action taken to investigate the same, the
circumstances surrounding the acceptance of the tender submitted by
Utah Australia Limited, and whether the acceptance thereof was
reasonable and proper and justified in the circumstances;
(III.) The design submitted and adopted for the bridge, and whether the same
was adequate and suitable or was in any and what respects defective or
inappropriate or deficient;
(IV.) The materials and processes and workmanship used in the construction
and erection of the bridge, the standard and suitability thereof for the
purposes for which they were used, whether they were in accordance with
the eontract specifieations and whether they were in any and what
respects defective or inadequate ;
(V.) The nature, extent and standard of supervision exercised over the
construction and erection of the bridge, and whether the same was
reasonable and adequate or was in any and what respects inadequate
or defective ;
(VI.) "Whether any and what negligent, culpable or improper aet or omission
directly or indireetly caused or contributed to the failure of the bridge,
and if so the party or parties responsible therefor ;
(VII.) \Vhether the construction and erection of the bridge in accordance with
the tender submitted by Utah Australia Limited was reasonable having
regard to the kno,vn state of engineering and scientific knowledge and
experience subsisting at the time the tender was accepted;
and His Excellency directed and appointed that His Honour, Judge Edward Hamilton Esler
Barber should be Chairman of the said Commission.
We, the undersigned, Chairman and Members of the Commission having duly
enquired into the several matters aforesaid, now have the honour to report to Your
Excellency as follows :-
The persons who gave evidence before the Commission did so on Oath and were
subject to examination and cross-examination by Counsel. The evidence given was reported
verbatim and embodied in a transcript of evidence which is respectfully presented with
this Report.
1 . l. Introductory Narrative
1 .1.1. Brief history of project
I .1 . 2. The parties
1.1. 3. Description of the bridge structure
1. 2. Collapse of bridge on lOth July, l!ltl2
1.3. Immediate cam;e of collapse
2. 5. The Specifications
2. 5 .1. General description
2. 5. 2. 'l'he design specification
2.5.3. High-ten~:~ile steel
2.5.4. Welding
2. 5. 5. General comments on the specifications
2.6. Design
2. 6 .1. General suitability
2. 6. 2. Design of the tension flanges of the girders
2. 6. 2 .I. Residual stresses resulting from previous welds
2. 6. 2. 2. Residual stresses resulting from the completion of a single weld
2. 6. 2. 3. Stresses at the ends of the cover caused mainly by superimposed loads on
the bridge
2. 6. 2 .4. Intensification of stresses by the ,;hape of the weld
2. 6. 2. 5. Tri-axial stresses
2. 6. 2. 6. Connection between the dangers of fatigue and of brittle fracture
2. 6. 2. 7. Consideration of residual stresses by designers
2. 6. 2. 8. Shape of the cover plate ends
2. 6. 3. The responsibility of the designer for specifying welding detailH
2. 7. Steel
2. 7 .1. The steel specified
2. 7 .1 .1. The justification for including B.S. 968 : 1H41
2. 7 .I. 2. Reasons for modifying B.S. 968 : 1941
2. 7. 2. The steel actually supplied
2. 7. 2 .1. Did the steel ompplied by B. H. P. meet the B.S. H68 : 1941 specification 1
2. 7. 2. 2. Submitted heats
2. 7. 2 .3. Did the steel meet the C.R.B. specifications ?
2. 7. 3. The steel as found in the failed ~irderr;
2. 8. Electrodes
CONTENTS-continued.
2. 9. Welding
2. 9. 1. The characteristics of a weld
2. \:l. 2. Influence of compositiou athl rate of cooling on the heat affected zone
2. H. 3. The coneept of thermal ;;everity
2. H.4. Standard recommendations for welding B.S. 968: 1941
2. 9. 5. Non-destructi \'C examination of welds
2.9.5.1. The penei,rant dye method
2. 9. 5. 2. The magnetic powder method
2. 9. 5. 3. Radiation examination
2. H.5 .4. Ultrasonic wave method
2. 9. 5. 5. Use of non-dest,ructi ve testing m the girder fabrication
2.9.6. Welding on the Kings Bridge project
2. 9. 6 .1. Weld sequence
2. 9. 6. 2. \Yeld defects in fabrication
2.9.6.3. Survey of cracks at cover plate ends
2. 9. 6. 4. Association of cover plate end cracking with heats of steel
2. 9. 6 .5. Association of cover plate end cracking with date of fabrication
2. 9. 6. 6. Association of cover plate end cracking with sequence
2.9.6.7. Cracks which have developed beyond the toe crack
2. \:l. 6. 8. Other cracks in the bridge
2. 9. 7. of views relating to welding
APPENDICES.
1. Alphabetical List of Witnesses
2. List of Exhibits
3. Relevant Extract from Report of Committee of
4. Extracts from Paper " How to Uee High Tensile Steel Effectively " by A. L. Elliott
5. Results of Tests on Samples from \V.l4 Girders, Extracted from D.S.L. Report, Exhibit 194
6. Photographs, Plans, Graphs, &c.
There are frequent references throughout the Report to rlauses 1Jf the C.R.B. specification and to
sections of the Report it~elf. To di:[Preutiate between the two sets of references the following scheme has
been followed :-
References to the C.R.B. specification are in the form
Clause x-y-z. e.g. 2-3-16.
References to the Report are in the form : -
Section x.y.z. e.g 2.3.[..
7
In the course of this Report it has been necessary to mention with great
frequency a number of corporate bodies and individuals. In order to save space and avoid
tedious repetition we have referred to such corporations using their full name where first
mentioned, and thereafter have used initials or short form of the name.
The following is a list of individuals who are frequently mentioned throughout this
Report. As this list sets out the initials and other relevant information, we have in general
used surnames only in the body of the Report.
BoNWICK, J. E. B.C.E., Office Engineer for Utah on the Project 1937-1958; Project
Engineer for Utah on Kings Bridge Project 1958-1960.
BuTLER, L. T. B.A. (Eng.) (Oxon.), B.Sc. (Eng.), C.E., M.I.E. Aust., C.R.B. Supervising
Engineer for King-street Bridge throughout the Project.
CAMPBELL, R. Welding inspector employed by J. & W., concerned with supervision and
inspection of welding on Project.
CLARKE, N. V. Resident Inspector for C.R.B. at J. & W.'s shop on Project from early 1959.
DARWI~, D. V. M.M., M.C.E., M.I.E. Aust., Chairman of C.R.B., 1949-1962.
EASTICK, R. F. M.B.E., C.E., A.M.I.E. Aust., Senior Constructional Engineer (Bridges) of
C.R.B. throughout the Project.
FARRAR, w. C. B.C.E., A.M.I.E. Aust., an Executive Director and the Manager of the
Structural Department of .T. & W. throughout the Project.
FERRIS, I. J. B.Met.E., A.R.A.C.I. Principal Scientific Officer, Defence Standards
Laboratories
FINK, G. w. Project Manager for Utah on the Project from August, 1957, until February,
1961.
FRANCIS, PROFESSOR A. J. l\f.Sc. (Birm.), Ph.D. (Birm.), M.I.C.E., M.I.Struct.E., Head ofthe Department
of Civil Engineering, University of Melbourne.
HARDCASTLE, B. T. A. B.C.E., A.M.I.E. Aust., Managing Director of K.S.B.D. since 1957.
HuDsoN, R. F. B.Met.E., Manager and Metallurgist for E.T.R.S. since 1957.
HYLAND, SIR HERBERT Member of Legislative Assembly, Victoria and the Leader State Parliamentary
Country Party.
JACKSON, F. 0 0 A.M.I.E. Aust., C.R.B. Assistant Engineer on the Project.
LoNGo, L. N. A Utah executive in charge of the preparation of tenders for the Project.
MASTERTON, C. A. M.C.E., A.M.I.E. Aust. During the Project was in turn C.R.B. Assistant
Engineer for Bridges and Engineer for Bridges.
MATHIESON, J. M.C.E., M.I.E. Aust., C.R.B. Chief Engineer throughout the Project.
MILLER, V. 0 0 A Utah civil engineer engaged on design aspects of the Project.
RALSTON, 0. B. Service Officer of B.H.P. attached to its Melbourne office throughout the
Project.
REEDY, L. Chief Engineer of Caterpillar of Australasia Pty. Ltd. 1959-1963.
RoDERICK, PRoFESSoR J. W. M.A., Ph.D., M.I.C.E., M.I.E. Aust., F.A.A., Head of the Department of
Civil Engineering, University of Sydney.
ScARLETT, K. F. A. An executive of .T. & W. engaged on the Project, 1958-1960.
STOCKER, w. R. B.Sc. (Engineering) (Glasgow), M.I.M.E. London, Assistant to the Managing
Director of .T. & W. since 1949.
THOMPSON, J. W. Executive Officer, Administration, at Port Kembla Steelworks of A.I.S.
WARD, F. A. Now Assistant Australasian Sales Manager of Murex. Was in turn the
Senior Technical Representative and the Assistant Branch Manager of
Murex during the Project.
WILSON, C. A. B.C.E., A.M.I.E. Aust., Senior Design Engineer in the Bridge Division of
C.R.B. since 1950.
8
PART 1.-INTRODUCTION.
1.1. Introductory NarrativE~.
1.1.1. Brief history of the project.
In November, 1954, the Parliamentary Public Works Committee recommended the
construction of a fixed bridge to cross the Yarra River at King-street and referred the
proposal to the Country Ro:tds Board for investigation and report.
In 1955, the C.R.B. recommended that the crossing should form part of a route with
freeway conditions for traffic bound for the centre of the City of Melbourne and originating
south of the Hanna-street-City-road intersection in South Melbourne. In April, 1956,
the Public Works Committee adopted the Board's proposal and made a further
recommendation for a structure generally on the lines of that ultimately erected. The
C.R.B. was recommended as the constructing authority with power to call tenders on a
world -wide basis.
During 1955 and 1956 the C.R.B. surveyed the site, investigated the foundation
conditions and prepared an outline scheme for the project which was to comprise two
low-level crossings of the Yarra River ; a high-level crossing continuing as an elevated
roadway for approximately one-third of a mile to the south; and an overpass to carry
Flinders-street traffic over King-street close to the northern ends of the river crossings.
The C.R.B. decided to invite tenders for the design and the construction of the
structures and, to this end, prepared an outline drawing showing the grades, clearances and
other limiting conditions within which the contractor was required to work. A specification
was prepared which laid down in some detail the design requirements (loading, permissible
working stresses, &c.) and also the standards required in materials and workmanship. In
particular the contractor was permitted to offer a superstructure in reinforced concrete,
pre-stressed concrete, mild steel, high-tensile steel or light alloy.
In September, 1956, tenders closing on the 29th January, 1957 were invited in
Australia, United Kingdom and U.S.A. Tenders were received from seven tenderers who
between them submitted fourteen different designs. After a full investigation of these
tenders, the C.R.B. decided to recommend acceptance of the tender from Utah Australia
Ltd. for the sum of 2,374,3130 16s., and on the 27th May, 1957, formal advice to this
effect was sent to the Minister--and was accepted by Cabinet. On 13th August, 1957, the
contract between Utah and the C.R.B. was executed.
Work on the bridge commenced on the 19th September, 1957. On the 18th December,
1957, the King-street Bridge Act was passed~appointing the C.R.B. as constructing
authority, conferring the necessary powers on the Board to construct the bridge for the
Government of Victoria, and validating such steps as had already been taken by the Board.
The work of construction was completed in various stages, the high-level bridge and
elevated roadway being opened to traffic on 12th April, 1961.
The matters concerned in this Enquiry, however, relate to the high-level bridge
roadway only, and the expression "the bridge" as used hereafter may be taken to refer
only to this portion of the above structure.
The bridge consists of two parallel structures forming eastern and western carriage-
ways. Each structure is constructed with four lines of main girders, supported by piers, and
with a reinforced concrete deck. In most spans the design was for four suspended girders
carried by cantilever girders, extending from supporting piers. Every girder consisted of
two flange plates, welded to a web plate and strengthened at intervals by vertical steel
stiffeners. It was necessary for the designers to overcome the problem arising from the
fact that the bending moments sustained by the suspended girders are at a maximum at
mid-span. One possible solution would have been to have used tension (lower) flanges vary-
ing in thickness so that the thickest portion was in the centre of the girder's length. The
alternative design, which was actually chosen, was to attach a cover plate on to the bottom
of the lower flange of the suspended girder terminating some 16 feet from each end of the
girder. The cover plates were tapered at each end from their maximum width to a square
end detail 3 inches wide. The cover plates were completely welded to the flange by fillet
welds running the entire length of each side of the cover plates, continuing along the side of
the taper and terminating in a transverse weld across the 3-in. end of the cover plate.
All steel in the structure relevant to the present Enquiry had been fabricated by
J. & W. from a high-tensile steel supplied by B.H.P. to B.S.968 : 1941. It is to be noted,
however, that the C.R.B. specifications required high-tensile steel, if used, to satisfy some of
the clauses of B.S.968 : 1941 and certain additional clauses notably one relating to the impact
strength of the steel.
The bridge was closed to traffic and very shortly after the lOth July, a Committee of
Investigation was set up to enquire into and report upon the causes of failure and measures
to be taken for the repair of the bridge. A copy of the portions of this Committee's report
relevant to this Enquiry appears in Appendix 3.
The reasons which influenced the Board in decision to choose the third method
are set out in detail in a paper by Darwin included in a collection of papers entitled " Kings
Bridge", published by the Institution of Engineers Australia, (Exhibit 22), and were
further discussed in his evidence.
The first method was rejected because it was said to entail a year longer for preparing
plans and specifications, the second because it similarly involved loss of time, and also
that there were no local experienced bridge design staffs of the necessary numbers outside
the Board's own staff.
This latter objection is a curious one, as the design ultimately accepted waR produced
by local designers, a number of whom had combined for the purpose.
The contract as finally executed between the Board and Utah was not in the sense in
which that description is usually understood, a "design and construct" contract, although
it was so described and referred to throughout the Enquiry. Usually the constructing
authority sets out the nature and extent of the required structure in wide general terms, and
leaves it to the contractor to create a detailed design. Doubtless, because of the desire
to have competitive tenders for construction as well as for design the Board found it
necessary to prepare quite detailed design and specifications. A " design and construct .,
contract as usually understood is very suitable in eases where it is desired to employ the
special expertise of some particmlar contractor, as for example where the contractor has some
patented method of construction unobtainable elsewhere. On the other hand, when used
in conjunction with competitive tendering, the true " design and constmct " form is
inappropriate, and must be modified, as in this case, to the extent where its advantages
may be lost.
Darwin advanced four main arguments in support of the form of contract adopted-
L That this system attracted the ideas of different designers.
2. That "with the contractor basically responsible for his own design
there should he especially good harmony in supervision ".
3. That a " similar procedure had been very successfully followed in the
invitation of tenders for Sydney Harbour Bridge ".
4. That if an overseas firm secured the contract some of the design work would
be done overseas thus " affording relief to hard-pressed local offices ".
None of these reasons, when examined, is really compelling. The first is tme only
up to a point. As a result of the Board's plans and specifications being drawn in considerable
detail, the field in which the tenderers were able to exercise their ideas of design was
comparatively lin1ited. To give one example, from many others, the specifications were
so drawn as to limit the thickness of flanges in welded constmctions to 1 inch, a factor
which proved restricting to designers. The second argm:nent has a theoretical attractiveness,
but in practice the hoped-for harmony soon gave way to discord.
12
As to the third argument, while the builders of the Sydney Harbour Bridge achieved
a notably satisfactory result, this may well have been rather in spite of than because of the
form of contract adopted, which was the suhjeet of serious criticism by eminent members
of the engineering profession (See Minutes of Proceedings of the Institution of Civil
Engineers, Volume 238, 1935).
The fourth argument again exhibits a pre-occupation \Vith the time element and the
supposed inadequacy of local design staff.
The most serious disadvantage was undoubtedly the absence of a design engineer
responsible not only for mattem of design in the first place but for general supervision and
control of the various aspects of the work in progress. Had a consulting engineer been
employed directly by the C.R.B. in the first instance to design the bridge and act in a
supervisory capacity he would have been responsible directly to the C.R.B. and would
have exercised supervisory functions for it,. 'fhis is in marked contrast to the position under
the system adopted, as the designers were responsible only to the main contractor and not
to the Board. Moreover, they could not be called upon to supervise the sub-contractors for
the Board. The contract ber;ween Utah and K.S.B.D. specifically provided that the
designers would be available for consultation hut would not be required to undertake any
job supervision. (Exhibit 39, Cl. 4 (e) ). In the result there was a complete separation
of the fTmctions of design and supervision.
This situation is well illustrated by the evidence of Hardeastle, one of the designers,
to the effect that had he become aware that .T. & W. was encountering a great, deal of
" cracking " during welding, he would have reconsidered the design, with a view to
eliminating any features which might have given rise to undesirable stresses. Under the
system adopted, the designers had no right to such information and no corresponding duty
to undertake any revision of design.
There existed a very noticeable gap between the constructing authority and the
sub-contractors. This gap might have been filled to some degree by the main contractor,
Utah, had the responsible offtcers of that company seen fit to undertake some aetive
participation in the work of supervision and inspection, or had tney felt it desirable to have
arranged conferences between the various parties including K.S.B.D. to resolve difficulties
as necessity arose, from time to time. It is fair to say that a]] of the parties relied on their
legal contractual rights and so meticulously avoided stepping outside their proper contractual
sphere, that a grave lack of liaison and eo-operation between them resulted. To a
considerable extent, this may be blamed on the parties themselves, but we feel that the
disastrous effect of it, would have been at least mitigated had the C.R.B. used a form of
contract which provided for a consulting engineer responsible for over-all supervision and
control.
It is true that witnesses from all part,ies when asked for their views on the suitability
or otherwise of the form of contract adopted, were in accord that it was a good arrangement,
which worked well. However, an over-all consideration of the evidence compels us to an
opposite conclusion.
It is our considered opinion that the C.R.B., while doubtless acting with the best
intentions, made what turned out to be a crucial error of judgment in deciding upon the
form of contract, which shaped the pattern of contractual relationships between the parties
and failed to provide the necessary over-all supervision. These factors contributed to the
troubles and difficulties encountered during construction and may have had a direct bearing
on the failure of the bridge.
18
2.2. The Tenders.
2.2 .1. The tenders received.
On the due date for the lodging of tenders, the 29th of January, 1957 the C.H.B.
received fourteen tenders and one offer (not a legal tender) from seven different companies.
It was quite apparent that the Board and the Government expected that from the
wide area in which the invitations to tender we1e published, there would be available a
very large number of tenderers, some of whom would be corporations of world reputation
in bridge building. Doubtless, there was disappointment that no tenderer which could
fairly be classed as of top-rank bridge-building reputation saw fit to seek the contract for
this important structure. Nevertheless, the actual number of tenderers was reasonable,
and amongst them were a number of companies of solid reputation and wide experience,
including Utah, whose reputation in general construction work stood very high.
The specifications (Clause 1~1-10) stated that the Board's officers in assessing these
various tenders, would take into consideration the following factors :--
(a) Total cost;
(b) Time to complete contract;
(c) Adequacy of design;
(d) Appearance ;
(e) Ease and cost of maintenance;
(f) The ability of tenderer to finance the contract.
In a letter to the Premier dated 12th March, 1957 (Ex. 10) Sir Herbert Hyland suggested
that " two good outside consultants should be employed to sit in with C.RB. officers when
they were considering the tenders". This suggestion was rejected, on the Board's advice
that such assistance was unnecessary, and the matter was pmsued no further. At this
date it is impossible to say what effect, if any, the assistance of such consultants \vould have
had, or even if there were available locally at the time any suitable persons not already
associated with one or other of the tenderers. The Board's reluctance to accept such outside
assistance is understandable. All that can be said now is that the presence of such
independent advisors lnight have changed the picture, particularly in relation to the use of
high-tensile steel. In any event, this might well have afforded some protection to the
C.R.B. against subsequent criticism. No positive finding is possible, and we do not feel
disposed to make any comment adverse to the C.H.B. on this matter.
The system adopted for the selection of the successful tenderer was designed to ensure
a proper examination of all tenders. Wilson described the process as follows :-
He and Niasterton were handed--not the actual tenders-but the preliminary
drawings and calculations and were unaware of the names of the tenderers or the amounts.
The two officers then checked the dra\Vi.ngs and calculations for any obvious contraventions
of the specifications or major errors in the design. At a later stage, the amounts of the
tenders were given to the examining officers and a full report made to the Chief Engineer
and the Board. rrhe tender received from Utah (2,374,360) was the third lowest valid
tender received. In fact, the actual amount paid to Utah including extras was
2,770,794 16s. Always leaving aside the question of the use of high-tensile steel we are
satisfied that there was no factor of superiority in any of the higher tenders, by comparison
with that of Utah, which should have required the C.R.B. to reject the latter in favour of
any of the higher tenders, or justified it in doing so.
The lowest tender, which was sublnitted by .John Holland and Co. Pty. Ltd. in the
sum of 1,793,658 was subjected to a critical examination. In his memorandun1 of the 27th
May, 1957 (Ex. 11) Darwin set out the reasons for rejection which were as follows
(a) The foundations were not designed in accordance with the specification.
This matter is discussed in Section 2.5.2.
(b) The appearance was said to be unsatisfactory.
14
(c) The financial strength of the company was subject to some criticism, mainly
because it sought certain concessions as to method and time of progress
payments and reduction in the amount of retention money which were
thought to indicate " apprehension on the part of the company itself as
to its ability i;o successfully finance a project of this magnitude".
(d) The tenderer's experience was mainly in the field of industrial building and the
staff and the e:r1gineers proposed to be employed was considered inadequate.
The amount of 45,000 allowed for design was low as compared with the
amount allowed by other tenderers.
(e) The tender figure was thought to be too low and indicated that the company
would be unable to carry out the project at this figure.
(j) Interference with traffic would have occurred over a longer period than
was the case with the proposals of other tenderers.
(g) There was said to be considerable risk of general public dissatisfaction due
to delay or even stoppages occasioned by deficiencies of this tenderer.
During the hearing a good deal of evidence was directed to show that the steel flanges
in this design were of greater thickness than the specified 1 inch and that, therefore, the
t'3nder was also outside the specification in this regard. (See Section 2.5.2.) Curiously,
this was not one of the grounds relied upon in 1957 for rejecting this tender.
r-rhe next tender, that of E. G. Olementson (Vie.) Pty. Ltd. (2,118,037) was rejected
for very similar reasons:-
(a) Financial structure of the company was not regarded as impressive.
(b) The disabilities regarding piles mentioned in relation to the John Holland
tender applied equally to this tender.
(c) A nominated sub-contractor had attached special conditions as to payments
which were in conflict with the specifications and unsatisfactory to the
Board.
In this case also it was said that taking the piles down to the mud-stone would involve
so much extra cost as to bring the total price above that of Utah.
It is true that the foundations designed by John Holland were outside the
specification, and it is evident that C.R.B. officers doubted their adequacy for the purpose
and rightly regarded the safety of the foundations as of paramount importance.
Nevertheless, we feel that this aspect of the John Holland tender perhaps merited a
more thorough investigation than it received.
The Board having made its choice of tender, the recommendation (Ex. 11) was
sent to the Minister.
The letter of advice to the Minister made no reference to what we have referred to
as one of the two outstanding features of the Utah tender, namely the fact that high-
tensile steel was to be used for the first time in Australia in a welded bridge. The Board's
then Engineer for Bridges, Masterton, had informed representatives of Utah at a meeting
before the acceptance of the tender that he doubted their ability to satisfactorily weld steel
of Australian origin, but was told that B.H.P. had given an assurance that the steel was
weldable. At the time the specifications were prepared he had no doubt that high-tensile
steel complying with the Board's specifications and supplied from the United Kingdom
could be welded, provided satisfactory welding procedures were used. The Premier expected
that the Board's report upon the tenders and its recommendations would deal with all
aspects of the project in a most satisfactory manner. We feel that the Board should have
advised the Minister that the Utah tender involved the use of high-tensile steel of
Australian origin for the first time in a welded bridge and that its own Engineer for
Bridges entertained doubts about the use of such steel.
At this point the Minister directed that the tender documents and other material
should be examined by Mr. V. G. Swanson, at that time Chief Engineer, Ports and
Harbours in the Public Works Department, so that he could " appraise " the tenders.
Swanson reported to the Minister by a memorandum dated 20th June, 1957 (Ex. 12). It
is a little difficult to understand precisely the object of this appraisal. Swanson's own
evidence suggests that he was mainly concerned to ensure that the tender accepted was
within the specifications. He did not advert in a critical way to such matters as the use
of high-tensile steel. Indeed, he disclaimed any competence to advise on this matter.
However, on the aspect of the business propriety of accepting the Utah tender, the
Board is entitled to rely on the Swanson memorandum as constituting contemporaneous
independent advice supporting its decision.
Two aspects of the Board's decision to accept the Utah tender must be kept
separate.
We criticize the Board for its too ready acceptance of the proposal to use high-
tensile steel in the bridge, and for its agreement to the award of the sub-contract for
fabrication to J. & W. without ensuring its competence to weld this unfamiliar steel. In
these matters of judgment we feel the Board was in error. On the other hand, setting
these matters aside, we are satisfied that the decision to accept the Utah tender was
honestly made.
16
Early in this Enquiry we became aware that rumours were current, the nature of which
led us to expect that some evidence would he forthcoming suggesting or alleging impropriety
relation to the tenders received and to the Board's action in dealing with them. No
witness prepared to give such evidence came forward, and none was discovered by those
assisting the Commission. \Ve have not found any evidence or any suspicious circumstances
suggesting impropriety on the part of any C.R.B. officer, tenderer or other person in this
regard. Any criticism made by us, on the matter of the assessment of tenders, is criticism
of judgment merely and is not intended to sugge::,;t impropriety or to impugn the integrity
of any of those persons involved.
2.3. Setting Up the Organization.
2.3.1. Arrangements for design.
Soon after the announcement of the decision to build Kings Bridge, the Melbourne
Division of the Institution of Engineers, Australia, became interested in the matter.
Because the project afforded a unique opportunity to the independent profession in
Melbourne, it was decided by the structural sub-panel of the Consulting Engineers Panel of
the Institution that a group consulting engineers be formed to prepare a design, and to
interest Victorian contractors in such design.
Messrs. Hardcastle and Richards, a firm of eonsulting engineers, paid the fee of
100 and obtained the Board's specifications. Subsequently, they were approached by
Utah with a view to assisting with the preparation of a tender. .Messrs. Hardcastle and
Richards informed that company of the existence of the Design Group and members of the
Design Group were then consulted. It v;as finally agreed between Utah and the Design Group
that the Design Group would prepare designs and drawings in sufficient detail to enable
Utah to submit a tender for the project.
The Design Group was incorporated on the 6th March, 1957 under the provisions
of the Companies Act, as "King-street Bridge Design Limited" a company limited by
guarantee. Hardcastle was appointed Managing Director. On the 25th March, 1957 a
letter was received from Utah setting out the terms and conditions upon which the company
was authorized to proeeed with the preparation of tender designs, drawings and
supplementary specifications for the King-street Bridge. Actually the. fonnal agreement
between the companies was not executed until the 19th January, 195\) but was deemed
to have commenced on 16th January, 1957. (See Exhibit 39).
It is clear under the comraet that the duties of K.S.B.D. were limited to preparation
of design and consultation on "Matters arising during construction which involve the
]'inal Drawings". Specifically it was not obliged to out job supervision or preparation
of schedules or material lists.
The designers prepared designs in both mild steel and high-tensile steel. Before
the final decision was made on the choice of these two materials, a conference was held on
the 28th November, 1956 between Mr. Farrar of J. & W., Mr. Longo of Utah and
Hardcastle. During this conference, Farrar telephoned Mr. Frankenberg, sales manager
of B.H.P. in the presence of the other parties and repeated to them his conversation.
There can be no doubt that at this point all parties understood that ample supplies of steel
to B.S. ~)68: 1941 would be available from B.H.P. and further that this steel was weldable
if proper \velding procedures were adopted and executed with skill. The effect of their
understanding is summarized in letters passing between J. & W. and Utah dated 1st
December, 1956 and 7th December, 1956. On the basis of this understanding and for
economic reasons discussed elsewhere in this Heport (Section 2.7.1.1.), the decision was
made to proceed with the final design in high-tensile steel.
2.3.2. Utah contract with. J. & W.
Unlike the contracts executed between C.H.B. and Utah, and Utah and K.S.B.D.,
Utah's contract with J. & \V. was never reduced into a formal document, but is to be f01md
in a series of letters. (See Ex. 15). By the 4th September, 1957 these letters had
resulted in the contract for the fabrication of the steel work. (Tr. 1209).
On the 11th August, 191)8 a contract was made for the erection of the steel and for
the field paint work.
In its tender to Utah, J. & \V. did not include any particular item for the cost of
testing material.
17
2.3.3. Approval of J. & W. as sub-contractor.
By a letter dated 8th November, 1957, Utah, as required by clause 1.2.14 of the
specification, submitted to C.R.B. names of several proposed sub-contractors, including
J. & W. as fabricator of structural steel and the C.R.B. replied on the 11th November,
1957, accepting these sub-contractors. Subsequently, by letters dated the 12th and 15th
May, 1958, J. & \V. was submitted and accepted as sub-contractor for the erection of the
steeL The high reputation of J. & W. as a fabricator of mild steel was of course well
known to the C.R.B. However, the comment is made elsewhere that it was readily
aecepted as a fabricator in high-tensile steel without adequate enquiry as to its experience
of this material or competence to make the necessary adjustment of its fabrication
methods. (See 2.7.1.1 and 2.4.0).
A factor which eonditioned the whole of the early negotiations was that nobody
in J. & W. comprehended the real significance of these tests. They just did not realize
that these tests were specified to ensure the production of something differing in quality
from steel manufactured to B.S. 968 simpliciter, as a safeguard against brittle fracture.
Farmr's evidence was to the effect that, in the tender to Utah for the fabrication of steel,
J. & W. failed to include any allowance for these tests by "an oversight". ~o doubt,
however, thi.s " oversight ., occurred because of the mental attitude of J. & \V. arising from
previous experience that " the production of B.H.P. certificates usually satisfied the
clients ". \Ve interpret this as meaning that tests such as those specified by the C.RB. were
not always insisted upon by the customers who were usually content to accept fabricated
mild steel which had been certified by the steelmakers.
Between the time of tendering to Utah, (25th January, 1957), and the time when
orders for steel were placed with B.H.P., (20th May, 1958), the ,J. & W. management had
a number of conversations with B.lLP. officers and as a result were convinced of two
matters-firstly, that B.H.P. was adamant in its refusal to supply steel with additional
tests, and secondly, that B.H.P's attitude to Izod tests was that they were of little or no
use.
o:J52/u3-2
18
The evidence of the B.H.P. witnesses, Ralston and Thompson shows that in fact,
neither of these two conceptions was completely accurate. If B.H.P. had been pressed with
sufficient determination, it is probable that it could have been persuaded to accept orders
for steel in full accordance with the C.R.B. specifications~though, no doubt, at a higher
price. Further, the B.H.P. attitude to lzod tests was less unequivocally condemnatory
than J. & W. understood it to be. It is probable that at this stage, the J. & \V. officers
did appreciate their responsibility to Utah and the C.R.B. to ensure that the tests would
be carried out, but felt confident that they could arrange for the tests to be done by testing
authorities in Melbourne. Also, they doubtless realized that if B.H.P. had agreed to supply
the steel in accordance with specifications, the cost would have been so much greater, that
in a competitive tender it would have been prohibitive. They, therefore, took a
" commercial risk " hoping that most of the heats of steel would comply with the C.R.B.
tests and that such as did not, would be useable for other purposes. They were comforted
also by the opinion which they then held, but which turned out to be misleading, that the
C.R.B. would not insist on the tests being carried out to anything like the extent provided
for in the specifications. In all these cireumstanees it now seems highly probable that
whatever may have been the situation at the time of the tender to Utah, the orders to
B.H.P. were given without the additional tests as a deliberate act and not as any sort of
oversight.
The importance of this matter cannot be overemphasized. When J. & W. became
convinced that B.H.P. would not supply steel in aceordance with the C.R.B. specifications,
its plain duty was to have informed Utah and through Utah the C.R.B. The whole matter
could then have been brought into the open before any orders were lodged. No one can
now say what would have been the result of such disclosure, or even if the other parties
would in fact have treated the matter with sufficient seriousness. If they had done so,
however, the whole story could have changed-even to the extent that the use of the
specified steel might have been abandoned in favour of some other material, with
consequent alterations to design.
At the Enquiry it was urged against J. & "\V. that its failure to order in strict
accordance with the specifications and the terms of its contract with Utah eonstituted a
serious breach of its eontraetuaJ obligations. The answer made was that the speeifieations
required J. & \V. to fabrieate in steel manufactured to B.S. 968 which would be submitted
to, and pass, the Izod and other tests, but that nothing in the speeifieations required these
tests to be carried out by the steelmaker, and that J. & W. was perfeetly entitled to order
as it did, and at its own expense, have the tests earried out by other suitable testing
authorities.
We are unable to aecept this argument, although it appears to have been at least
tacitly accepted by the other parties at the time. A perusal of the speeifications, section
2~3, and in particular dause 2-3-16 (h) shows plainly that the obligation of Utah, and
therefore of J. & W., was to arrange for the weldability test specimens to be prepared by
the steelmaker and tested at its works or at an approved testing laboratory at its cost.
The subsequent history of the matter discloses that J. & "\V. did not carry out the
procedure with strict regard to the onerous obligation undertaken, which was to ensure the
proper testing of all steel, and the setting aside without demur of any steel which did not pass
the tests on the strictest basis. In fact, there was a failure to carry out all the tests to the
full extent of the specification requirement, and J. & W. is found resisting testing by every
available means, constantly urging reduction in testing, and finally ever-persuading C.R.B.
to relax the testing. In this respect we feel that J. & \V. was clearly at fault.
The question then arises was Utah to blame for not overseeing the orders given by
J. & W. to B.H.P. ? Utah had made clear to J. & W. that the sub-contract must be
carried out within the terms of the main contract and had arranged for C.R.B. specifications
to be made available. Utah, no doubt, assumed that a company which had been
purchasing steel for 100 years was capable of giving a relatively simple order. Moreover,
even if it had occurred to Utah to request a sight of the orders for the purpose of
checking them before they were placed by J. & W., this would have been greatly resented
by J. & W., as being out of accord with usual practice. In the light of the misleading letter
of 5th September, 1958, it would be scarcely fair to say that Utah should have discovered
the situation sooner, although this might well have been ascertained by a careful perusual by
Utah of the J. & W. tender which made no mention of the additional tests. When the
situation was discovered, the C.R.B. as well as Utah, accepted the position. We, therefore,
feel that no adverse finding should be made by us against Utah on this matter whatever
ultimate vicarious liability may be found to exist in law.
At this stage there was correspondence between Utah and J. & W. on the matter,
and at the request of C.R.B., J. & W. wrote to B.H.P. on lOth March, 1959, asking for a
reconsideration of its attitude, which was refused in a letter of 7th April, 1959.
On the other hand, the evidence of Eastick makes it quite clear that he knew as the
result of conversations with Thompson early in 1957, that B.H.P. was unwilling to
undertake these additional tests, and it is equally clear that he was quite unconcerned about
this. He was interested only in seeing that efficient arrangements would be made for
testing in Melbourne.
Whether Eastick ever passed this information on to his superiors at that time
(1957) is uncertain. However, Eastick claimed that at a conference on 21st March, 1958,
at which Butler and Eastick represented C.R.B. and Miller and Fink, Utah, he made the
position clear to all present, and the notes of the conference (Part of Ex. 51) bear this out.
In any event, Eastick was the Board's Officer in charge of testing, among other things,
and his knowledge must be taken as that of the Board. It is abundantly plain that Eastick
and probably other C.R.B. officers except Wilson, shared with J. & W. the lack of
understanding of the significance of the impact tests.
Whatever be the time at which the C.R.B. had knowledge of the form of order placed
by J. & W., there is no doubt that it accepted the situation with very little protest. Apart
from urging J. & W. to make a belated appeal to B.H.P. for reconsideration, in March, 1959,
no other action was taken. Perhaps at that stage nothing else could have been done.
20
The real criticism of the C.R.B. arises from its subsequent actions. Because of the failure
to appreciate the importance of the impact tests, they were never carried out to the full
extent of the specifications, and the least onerous of the extra tests were relaxed to a
" random " basis.
While inspection in general was being maintained with such rigorous insistence on
detail as to seriously irritate the J. & W. personnel, the impact tests were allowed to be
greatly reduced. An even mo:re serious error was to permit, or at least to acquiesce in, the
practice of J. & W. of proceeding to fabricate girders from steel which had not been tested,
subject to a satisfactory result being ultimately obtained. This was, we feel, very bad
practice which the Board should have refused to accept. A further criticism must be added,
of breakdown in communication within the Board's own establishment. Wilson, the
man mainly responsible for the specifications, who had added these additional tests in
order to protect the bridge from brittle fracture, was the one witness from the Board's
staff whom we consider to have understood the significance of these tests. He was never
informed, much less consulted, about these matters. Had this been done, we feel that a very
different course would have been followed.
The organization of the C.R.B. during the relevant period, in so far as it directly
concerned Kings Bridge, was as follows :-
Chief Engineer J. Mathieson
Engineer for Bridges I. J. O'Donnell (when speci-
fications were being prepared)
C. A. Masterton
Senior Design Engineer C. A. \Vilson
Supervising Engineer, King-street Bridge L. T. Butler
Senior Constructional Engineer (Bridges) R. F. Eastick
Assistant Engineer F. Jackson
Welding Inspector N. V. Clarke (with two assiS-
tants)
A great deal of the information that we obtained about the conduct of the job came
from the evidence of Wilson, Eastick and Clarke although Mathieson, Masterton, and Butler
also appeared briefly at the Enquiry. A paper by Masterton (Exhibit 22) presented to the
Institution of Engineers, Australia, gives what must be presumed to be the official account
of the construction procedure and contains a number of statements that are worthy of
comment. It should perhaps be mentioned that we do not know for certain how much of
the paper was written by Masterton of his own knowledge and how much was based on
information supplied to him by his subordinates.
At any rate the early part of the paper indicates that Masterton, possibly advised
by Wilson, had a very lively appreciation of the inherent difficulties of welding, of the sort
of failures of welded structures that had taken place previously, and of residual stresses
and their implications. The introduction of the additional clauses into the specification, to
try to cover the danger and difficulties, are then described and are followed by an account
of Jackson's experiments, described in Section 2.4.3, to improve the knowledge of the C.R.B.
officers in welding this material.
During the construction of the bridge the regular inspection of the welding was carried
out by Clarke and his assistants working under the immediate supervision of J ackson :
Eastick was the officer in general charge of the fabrication of the girders from the C.R.B.
point of view while Butler was in charge of the project as a whole.
21
f t is difficult to believe, in view of their actions, that Butler, Rastick and .T ackson
really appreciated the situation properly or that the knowledge that Wilson and Masterton
possessed was effective at the time the contract was awarded. For example we read in
Masterton's paper, under the heading " Welding High Tensile Steel'', the following:-
" 1t was not known if steel made to specification B.S. 968 had previously been
fabricated by welding for girder construction. ft had not been so used to any appreciable
extent in Australia.
From experimental results in the U.K. it was ascertained that an effective welding
procedure had to be established, maintained and constantly checked to ensure trouble-free
welding.
Tn these circumstances it was, therefore, necessary for the Board to satisfy itself:--
(i) that high-tensile steel of Australian manufacture could be satisfaetorily
welded manual1y;
(ii) that welding procedure and controls were developed suitable for mass
production under workshop conditions;
(iii) that a procedure was established suitable for the fabrication work being
performed by automatic and semi-automatic processes; and
(iv) that the non-destructive testing of this welding could be satisfactorily
arranged.
\Ve can only comment that the Board allowed itself to be all too easily satisfied.
There are several other passages in the paper which describe what might have
happened rather than what actually did happen. For example :-
" 'fhe contractor supplied test certificates from the manufacturer which gave the
physical properties and the chemical composition of each plate for each heat.'" This was
never done, as Masterton admitted in evidence. " The test certificates and the check
analysis, together with the Izod and weldahility test results, were entered in the record
hook, and if they fulfilled the requirements specified then the contractor would he officially
informed of the approval to the plates covered by the Board's stamped number."
It may appear to be a small point hut we think it significant that there was no proper
record hook. There was a chart (Exhibits 71 and 72) hut we found that many plates were
approved that did not conform to the C.R.B. specifications. Nor were weldahility Izod
tests ever carried out at the lower temperature, although it would appear from Appendix I.
of the paper that 1\'Iasterton thought they had been. On the other hand Appendix TIT.
describes Jackson's experiments and makes it clear that testing was not carried out at the
lower temperature.
From Masterton's paper and from the evidence we heard we conclude that there was
a failure of communication within the C.R.B. organization. On the one hand important
background information did not reach the officers on the job ; on the other the aetions of
these officers were not always fully realized at appropriate levels in the C.R.B. In
particular, Wilson did not know until the ]~nquiry that the weldability Izods had not been
carried out at :32]'. and waH manifestly shocked by the information.
In this eonnection we find a gap in our knowledge. \Ve know that Wilson and
.Masterton visited England and the Continent of Europe in 1956 partly to answer enquiries
from possible tenderers-and also, perhaps, to stimulate such enquiries, and partly to make
a general survey of eurrent bridge-building practice. 'Ve do not know whether a full report
of this visit was ever made to the Board as there was no evidence on this point. If no such
report was made a great opportunity was missed, for Masterton's diaries contain a great deal
of excellent information, some of it highly relevant to the subject of our Enquiry.
The value of such a report would have been two-fold. In the first place Wilson and
1\'Iasterton themselves would have benefited by the act of reducing to an orderly sequence
the heterogeneous notes and impressions of hurried visits to many offices and works. And,
secondly, the circulation of their report could not have failed to improve the understandina
of all concemed with Kings Bridge. e
22
2.4. Competence and Experience of the Parties to Undertake the Project.
2.4.1. Relationship betWE!en the parties.
Throughout the Enquiry it has been evident that there was a complex interplay
in the relationship between the various parties concerned. \Ve address ourselves, therefore,
to a consideration of the competence and experience of the parties on the one hand and
of their responsibilities on the other. \Ve are acutely aware of the difficulties besetting
any definition of moral standards in this connection and will, therefore, so far as possible,
confine our attention to the responsibilities as defined in the several contracts or stated
in the C.R.B. specifications. At the same time we recognize that many companies
assume responsibilities, of a professional character, that transcend their contractural
obligations. It is good that this should be so.
I
Broken Hill Proprietary Jfurex (Ajusla)
Company Ltd. Pty. Ltd.
Hteel plates and bars. ElectrodeH ancl Huxes.
It is clear from this that the contractor came between the constructing authority
and the sub-eontractors. This does not appear to have restrained direct discussion of
design aspects between C.R.B. and K.S.RD., as is evidenced by the numerous design
conferences held. On the other hand, official contact was maintained between C.R.B.
and J. & W. only through l7tah. It will be realized from the above diagram that B.H.P.
and Murex had official contaet only with J. & W.
Although C.R.B. was the final authority for aceepting steel, there was no discussion
with B.H.P. at any stage of the contract regarding the quality of the steel supplied or
difficulties associated with its fabrication, apart fron1 some informal discussions between
Eastick (C.R.B.) and Ralston (B.H.P.) in the early stages. Whether this was an inevitable
eonsequence of the type of co:r.traet, or not, there is no doubt that discussions between
C.R.B. and B.H.P. at the appropriate level, could have had important and beneficial
consequences.
In setting out our views on the competence and experience of the parties it must
be realized that our sole concern is to establish whether, in the eircumstanccs related to
the initiation and fulfilment of the contract, the parties were familiar with the low-alloy
steel selected for fabrication of the superstructure. Thit> matter relates to all the
parties mentioned except Murex.
At the Enquiry it soon became evident that he had played an informal but important
role before and during the construction of the bridge ; he participated in the work of the
committee of investigation immediately after the failure; he subsequently carried out
a detailed study of the failed girders (Ex. 194) ; and finally he assisted the Commission
by giving very valuable evidence.
At the time the specifications were being written he gave much advice to Wilson
on the steel specifications generally, and on B.S. 968 in particular. He confirmed the
desirability of introducing Izod tests and of limiting the thickness of the steel to 1 inch.
He gave advice which led to the introduction of the welding procedure described
in the B.W.R.A. booklet; advised the C.R.B. to employ an independent organization for
the inspection and testing of the welding; gave Jackson (C.R.B.) some training in welding
techniques so that he might undertake inspection; gave advice on radiographic inspection
and the interpretation of radiographs; and finally, advised "\Vilson to recommend that
the bridge should be closed after the failure of span W.14.
During the fabrication period there seem to have been several occasions on which
he was consulted by one or other of the parties who turned to him for advice.
Apart from a payment by C.R.B. to D.S.L. for the training of Jackson, there was
no payment made either to D.S.L. or Ferris by any of the parties.
In the early stages of our proceedings the impression could have been gained that
he was the man on whom the main responsibility for the failure must rest, for it seemed
that many decisions of importance were only taken after visiting, or telephoning him.
As the evidence unfolded, however, it became abundantly clear that he at least was one
man who really knew what he was talking about. With the one exception that the Izod
value (of 20 ft.jlb. at 32 F.) he suggested should have been higher (and he explained the
authoritative basis of his figure) his advice was absolutely sound. We were finally left
with the opinion that, far from being held responsible for the failure, he must be given
full credit for trying to get the various parties working on the right lines.
~While we are more than satisfied that Ferris gave excellent advice we are not sure
that he was always wise to give it especially to people who might not fully understand
the significance of what he was saying. Nor can he always have been certain that he was
being asked the right questions. We do not blame him for his ready willingness to help
but we very much blame those who put him in such a difficult position.
In particular we blame the C.R.B. which leaned most heavily on him and which
should have had a competent metallurgist on its own staff. No doubt there would still
have been problems where Ferris's great experience would have been of value but the
questions would then have been asked, and the replies received, with understanding.
If the bridge had been built of mild steel it is quite possible that no great difficulties
would have arisen with this familiar material; in that case no exception could be taken
to the occasional use of Ferris to help with special problems. With the high-tensile steel
that was actually used it was essential to have experts fully involved in, and in daily
contact with, the problems of fabrication. In spite of all his knowledge and experience,
Ferris just could not do what was required as a part-time consultant at the far end of a
telephone line.
The only effort the C.RB. appears to have made to become acquainted with the
material it was decided to adopt, is described in the paper by }Vfasterton (Exhibit 22). In
this he states inter alia " It was not known if steel made to specification B.S. ~)68 had
previously been fabricated by welding for girder construction ., . This statement refers
to the state of knm.vledge of the C.R.B. at the time of writing the specification. In view
of this, our opinion is that the C.R.B. did an absolute minimum of testing on the properties
and weldability of the steel. From the experiments done, however, there could have been
extracted the following pieces of information which should have warned of diffieulties
ahead:~-
(a) This steel sometimes does not show a yield point. This feature should have
been discw;sed with K.S.B.D.
(b) The composition of the samples of Australian steel used was variable and
sometimes above the maximum limits specified in B.S. 968. This should
have alerted C.R.B. to require J. & W. to have checks made on the
steel delivered and to have had direct discussion with B.H.P.
(c) In an experiment to determine the magnitude of residual stresses in the
flange-web welding, although appreciable stresses were indicated the
matter was not followed through. '!;he experiment was made on thinner
plate than w.as subsequently used in flanges and there was no evidence
that consideration was given to the use of pre-heating or of vmiability
of welding sequence on residual stresses.
Considering the importance placed by Wilson on the need for notch ductility in the
steel, one of the most remarkable aspects of the preliminary testing programme is the
omission of a survey of this property on the samples investigated. ln 1\Iasterton's paper
only two plate Izod tests are mentioned and these were carried out at room temperature.
Even at this early stage the significance of variation of notch ductility with temperature
appears to have been overlooked. To be able to assess this property it was essential to have
a series of Izod speeimens over a range of temperatures from 0 F. to at least 120 F., from a
series of thicknesses of plate covering the range to be used in fgbrication of the girders.
By comparison, this procedure was followed by l\1ott, Hay and Anderson, consulting
engineers for the Runcorn-Widnes Bridge being fabrieated in England from similar steel
at about the same period. Without this knowledge obtained from several heats there
was no certainty regarding the possible notch brittle behaviour of this steel.
In view of the fact that the C.R.B. had retained authority to approve the steel and
all fabrication procedures, we eonsider that with the staff available it was not competent
to carry out these functions.
Another matter is the ability of C.R.B. officers to undertake the inspection during
fabrication of the girders. Admitting that they were working with a new material, they
took the view that it would be better to avoid using inspectors who were familiar with the
inspection of mild-steel welding, and preferred to train a new group.
The first step was to send Jackson, Eastick's assistant, to D.S.L. for a few weeks
(See Exhibit 21) to acquaint himself with the characteristics of B.S. 968 steel and with
the techniques of welding it. ]'erris felt confident that Jackson understood what he was
taught but that when he left D.S.L. he did not have sufficient knowledge to supervise
25
adequately the fabrication of the bridge. (Tr. 263B). Nevertheless, he did produce hvo
reports (Exs. 53 and 54), on the welding of B.R. 968 steel, which are competent pieces of
work as far as they went.
Incredible as it may now seem, this was the only direc.t experience that any C.R.B.
officer had of welding B.S. 968 steel before they began the \York of inspection.
J ackson 's knowledge doubtless grew on the job but it is to be questioned whether he
was really capable of training the inspector:,; even though they were competent welders of mild
steel. He did, however, produce a sensible instruction sheet (Ex. 59) for the inspectors.
Jackson was abroad at the time of the Enquiry and was not available to give evidence.
From what others said of him, and from the exhibits mentioned above, we formed the opinion
that he was capable and conscientious, but whether he had enough experience to do what
was expected of him, or whether he was adequately supervised himself, are very different
matters.
We believe, therefore, that the C.R.B., in spite of its long experience in bridge
building, was not competent to undertake the supervisory role it had assigned to itself in the
specifications ; it did not fully realize the implications of the change to high-tensile steel
and the steps it took to prepare itself for the job were inadequate.
In view of the opinions expressed above we think it worth '.Yhile to inelude an account
of the careful and considered steps by which, over a period of several years, the California
Division of Highways moved into the field of welded high-tensile steel bridges. Appendix
4, therefore, consists of extracts from a paper by the Bridge Engineer in Planning of that
authority.
The paper itself was included by Bonwick in his report to Utah (Ex. 24) following
his visit overseas in early 1960.
Although Utah had had no experience of bridge building its proposal to construct
the foundations itself, and to sub-contract the design and the fabrication and erection of
the steel work, while maintaining over-all responsibility for the job, seemed to make
the best of both worlds.
The only weakness of this plan proved, in the event, to be a fatal one: neither Utah
nor the C.R.B. nor, for that matter, J. & W. itself realized that J. & W. was not competent
to handle the problems inherent in the use of high-tensile steeL It is unfortunate that the
American company, to which the designs and, presumably, the arrangements as a whole were
submitted, did not ask some pertinent questions on this point.
As the general contractor, responsible for the job as a whole, Utah had a clear duty,
first to satisfy itself that its sub-contractors were suitable and, when experience showed
that they were running into difficulties, to do something about it.
It is obvious that the Utah personnel in Australia knew nothing about high-tensile
steel and, like almost evervone else, took B.S. ~)68 on its face value. When Hardcastle's
investigations in 1956 show~d that it would save weight there does not seem to have been anv
t};ought that a full study should be made of the possibility of using it on a big scale i.iJ.
Australia. Enquiries in California-and the Executive Headquarters of the Utah
26
Construction Company are in San Francisco~would have shown that the successful and
extensive use there of welded mild. and high-tensile steel for bridges has involved. what amounts
to a transformation of the steel construction industry. Radiographic inspection of welds,
which was so much resented by J. & \V., is recognized as essential not only to check the
work produced but to develop techniques and train welders. Beaton writes of " shops ...
being subject to the discipline of radiography" and the papers that Bonwick included in the
report of his visit to U.S.A. and U.K. in 1960 (Ex. 24) reveal a technical awareness that was
pathetically lacking on the Kings Bridge.
At the Enquiry, Counsel for Utah was at pains to show that the responsibility for
ensuring the competence of the sub-contractors rested exclusively on the shoulders of the
C.R.B. "The authority at least is satisfied, and that was all that any reasonable contractor,
in our submission, would be required to do ". (Tr. p. 190). We do not accept this view.
One ofthe purposes that the C.ltB. had in mind, in advertising the contract on a world-wide
basis, was that a contractor 1night emerge who would bring to Victoria expertise that was not
locally available. C.R.B. thought it had such a contractor in Utah but was disappointed
in the event. We do not exonerate the C.R.B. from a share of the blame but we do not
think that Utah did all that could reasonably have been expected ofit. The resources that
were readily available to Utah from its American principals were not brought to bear on the
fabrication of the steeL
In the event four engineer;:;, each from one of the constituent firms but none experienced
in the use of high-tensile steel, were mainly concerned and of these Hardcastle seems to have
played an important, if not the leading, part; at any rate, he came forward at the Enquiry
as the spokesman for the group.
By 1957, Hardcastle had. had some eight years in practice as a structural designer
and had won for himself a good reputation in this field. He had not previously designed a
bridge, however, and it is therefore necessary to ask whether he should have taken on, or
been entrusted with, a bridge project of this magnitude; to the layman it might appear not.
But the principles of structural design are very much the same whether a bridge is being
designed, or a crane, or the framework of a building. \Ve can find no evidence whatever
that Hardcastle himself, or the team of which he was apparently the leader, should not have
been entrusted with this work. We discuss, in Section 2.6.2., the only two features of the
design that were open to criticism. It is now only necessary to point out that although
Hardcastle said (Tr. 480) that the final decision to use high-tensile steel was made by Utah
and K.S.B.D. jointly, and, although K.S.B.D. had reported, on the strength of a trial design,
that B.S. 968 appeared to offer the most economical solution, the ultimate responsibility is
that of Utah. It must be realized that the position of the designers in this contract was a
subordinate one. 1'hey were employed by, and were responsible to Utah, whose engineers,
Miller and Longo, who were regularly in contact with Hardcastle and who, after considering
the matter and consulting J. & W., finally made up their minds to submit a tender based
on B.S. 968 steel. \Ve think that within the limits of the responsibility assigned to it,
K.S.B.D. was competent to carry out the work for which it was engaged.
\Ve retain our preference for a different arrangement, as discussed in Section 2.1.,
under which C.R.B. would have engaged a consulting engineer to design a bridge for the
construction of which contracto:rs would have been invited to tender. It would then have
been his duty to have investigat~~d the suitability of B.S. 968. As it was, as far as we know,
Utah never called upon K.S.B.D. to make any real investigation or to give any technical
advice on this matter at all.
\Ve also think it important to comment, at this point, on the influence that the
competitive situation, in which the designers were working, had on the deeision to use high-
tensile steel. It was necessary for them to produce not only a satisfactory design but also
one which would be acceptable on price. Hardcastle's trial design showed a saving in weight
and the very sketchy investigation, which was all that was practicable at the tender stage,
suggested that it would also show a Raving in cost. \Ve cannot, naturally, know what
27
Hardcastle would have done if he had been retained as a consultant by C.R.B. to design
the bridge, but he would at least not have been under pressure to produce a competitive design
and could have had a full investigation of B.S. 968 made before choosing it.
1'his consideration underlines the objections to this form of contract which we have
described in Section 2.1.
Although it is not our function to offer advice to the parties concerned in this project
we feel that an opportunity for preventing similar mishaps in the future will be missed unless
we draw attention to organizational defieieneies which eontributed to the bridge failure.
Whilst it is evidently possible for a fabricator in mild steel to work without a
metallurgist it is not possible with a1loy steel. Had J. & w. been used to examining
welds rnetallurgically, and been aware of all the technical pitfalls which beset the fabrieator
in alloy steel, the whole character of the organization eould have been changed. A
metallurgist would have aided the training of welders ; checked the chemical analysis of the
plates so that the inevitable variations in composition could be assessed; carried out the
lzod tests; helped with the assessment and control of pre-haat; and supervised the use of
2R
On the face of it, therefore, one would suppose that B.H.P. would have been well
able to play its part adequately in the Kings Bridge contract. It had enough qualified
staff and laboratory and plant resources to do all that was required. Yet we find that the
production of some 2,000 tons of steel involved the diversion to other uses of far more steel
than was sent to the b1idge, while of that which was sent, several heats could, with
advantage, also have been diverted. The reasons for this are not clear either to us, or, we
feel, to B.H.P. itself. We understand that the two plants used different techniques for
producing this material and we wonder whether there was any collaboration or discussion
between them on the metallurgical aspects of the problem.
29
Although much good steel was delivered to the bridge the steel as a whole must be
regarded as unsatisfactory for three reasons
(a) lt \vas too variable in quality.
(b) Much of it wa::> found to be difficult to weld because of the high carbon,
manganese and chromium content.
(c) Some of it. notably heats 35 and 56, was notch brittle.
Brittle fracture is a problem that has caused anxiety in recent years to the designers
of large plate structures, such as ships, storage tanks and bridge girders, especially when they
are welded. It is a problem that is still not completely solved but a good deal of progress
has been made ; the influence of stress raisers and low temperatures is recognized, suitable
acceptance tests are being devised and so on. But, in the last resort, it is to the steelmaker
that we must look to produce steel that is notch tough.
In other countries much progress has been made in this direction and, to this end,
extensive experimental and steel production programmes have been carried through. Such
work as was done in B.H.P. laboratorieg was on a much smaller scale and would be classed
as " testing '' rather than " investigation ". The apparent lack of interest in a topic that is
of sufficient importance to justify a place in forefront of the research programme is
disappointing, particularly as there have been several brittle fracture failures in Australia,
in recent years, in some of which B.H.P. steel must have been involved. \Ve have full details
of only mie of these failures which is described in Report of the Proceedings of the Fourth
Conference of Professional Officers, representing the Controlling Authorities of the Water
Supply and Sewerage Services of the Capital cities and of the States of Australia. rrhe
conference was held in October, 1949 and one paper describes the :33 brittle fractures that had
occurred up to that time during the fabrication of some 6 miles (out of 2:3 miles total) of
69-in. diameter pipes. Some of the remarks made during the discussion of that paper might
almost have been made at out own Enquiry and are worth quoting :--
" B.H.P. had been approached in the matter but unfortunately they had not
been very helpful. Their attitude seemed to be that is our standard grade of
If you dmd huy it there are plenty of other customers who are willing t.o
take it._.,
.... if it could get a steel corresponding to B.K ~)68 difficulties would
he overcome. B.H.P. were prepared to make such steel if sufficient orders were
forthcoming,._ 'One thing they (B.H.P.) did ask and that was that the British
Rtandard should be relaxed somewhat in the tolerances .
We quote these remarks because they indicate an attitude that apparently still
prevails in B.H.P. To be fair, 1948 was a time when steelmakers were hard-pressed to meet
the demand for steel, and B.H.P. has since made a great deal of B.S. n68 steel, as we know ;
moreover, B.S. 968 : 1941 has not been as successful a specification as had been hoped and
has since been replaced by B.S. 968 : 1!)62. On the other hand, B.H.P."s attitude to its
customers and to tolerances has scarcely changed and it still has much to learn about brittle
fracture.
lt may perhap:s be argued that if research on this topic is being actively pursued in
various places elsewhere, there would be no point in B.H.P. duplicating it. This may he so,
but we think that there is a need for a strong technical group directing continuing
investigations on basic problems associated with the steel-making, pit practice and mill
practice of quality steels. Such a group might have resolved that, in view of work
proceeding elsewhere, its own efforts should be concentrated on other problems, but there
would at least have been people in the company reading current scientific literature with
comprehension, and ensuring that up-to-date knowledge permeated the whole organization.
We describe elsewhere some incidents, among several that came to our notice, which
suggest that there was room for an improvement also in the flow of information between the
plant and the service department. Problems of communication of this kind are inevitable
in a big organization and, unfortunately, they are seldom brought to notice except when
something goes wrong. The system of internal communications operating at that time
in B.H.P. should have been adequate, we think, and the incidents referred to were more the
results of errors by the officers who used it than of the system itself. This matter is discussed
again later, but for the present, we simply remark that it would have been better if more of
what went on between Ralston and J. & W. had been recorded in memoranda and circulated
'\\.-jthin the company so that a project of this importance might have received closer attention
by all concerned, especially in the early stages.
In June, 1958, the Melbourne office of Murex was asked to recommend an electrode
for the manual welding of B.S. 968 steel and, after certain investigational work at Hobart,
a " low-hydrogen " electrode, Fortrex 35, was recommended. This electrode consists
of a central wire coated '\\.-jth a flux which is specially designed so that the amount of
hydrogen liberated during welding is kept to a minimum ; this makes it particularly suitable
for use with low-alloy steel of the B.S. 968 type.
Electrode acceptability tests were carried out to the C.R.B. specifications by Murex
under C.R.B. supervision ; the welded plates were examined by Royal Melbourne Technical
College and, as a result, Fortrex 35 electrodes were approved and used throughout the
project for manual welding. "Murawire" and " Muraflux" were later approved by the
C.H.B. for automatic welding.
When J. & W. started t.he fabrication of the girders it ran into trouble because it
was quite unprepared to weld B.S. 968 steel to the required standard. An arrangement
was then made under which Mr. F. A. Ward of Murex was seconded to J. & W. to instruct
welders in the use of welding techniques necessary to obtain good X-ray results when using
low-hydrogen electrodes.
It is apparent that \Yard set about the task of transforming the J. & W. shop so as to
make it capable of producing work of adequate standard and he certainly improved the
standard of welding. Ward i8 an experienced and intelligent man who holds a number
of certificates which testify to his competence and had spent some thirteen years as a
part-time welding instructor at Royal Melbourne Technical College. As well as relying on
his own experience he was constantly in touch, through the Melbourne office, with the research
department in Hobart.
The correspondence to and fro (Exs. 151 and 180) gives a very clear and convincing
picture of a well-organized company with experienced metallurgists at the centre, constantly
providing their technical representatives in the field with valuable advice and information.
We have no doubt that l\Iurex was well able to do what was required of it and, indeed,
it was asked to undertake, and achieved, far more than one would have expected in the
circumstances. The reorganization that Ward brought about at .J. & W. went some way
to bringing it to the standard required for this class of work.
31
2.4.9. Conclusion on the competence and experience of the parties.
We discuss in Section 2.7.1.1 the question whether C.RB. was justified in including
B.S. 968 in the bpecifications but, in any event, in the light of our discussion of the
competence and experience of the parties, it is evident that C.R.B. should have taken
eertain additional steps which were not taken.
Clausb' 1-1-10, Assessment of Tenders, lists the factors which the C.R.B. announced
that it would take into account in assessing the tenders. Among these is :~
(f) Ability of tenderer to finance contract.
There should, in addition have been a clause-
" (g) Ability of tenderer to carry out the contract."
'l'he C.R.B. had, in fact, made provision for obtaining the information on which
(g) might be assessed for, among the documents which the tenderer was required to
complete, was Form G, which included :-
(l) List of Major Bridge and other Civil Engineering Works designed and
constructed by Tenderer.
(a) Design (four columtL''l with headings, Description, Constructing Authority,
Amount, Design Time).
(b) Construction (four similar cohunns).
]<"'urther parts of the form enquired about the major items of plant used, the number
of design engineers and draughtsmen or workmen employed per week at peak of design or
construction, and the technical literature in which projects are described.
Utah's answer to all the questions was "See accompanying brochure labelled ' Utah
Construction Company '." This brochure (Ex. 19) is an impressive accmmt of the
achievements of this great company in the construction of many important projects,
including several that are of world renown. Its inclusion as part of Utah (Australia)
Limited's tender clearly implied that the full resources of the American principal were to
be thrown behind the Kings Bridge contract, and the C.R.B. appears to have left the
matter there.
The specified tender docun1ents did not require, and the actual tender did not
supply, any details of the competence of the sub-contractors although clause 1-2-14 states
that " The contractor shall not without the prior written consent of the Board (which
may be given upon such conditions as the Board deems fit and which shall not relieve the
contractor from liability under this contract)-
(a) sub-let any portion of the works; or
(b) enter into any sub-contract for the execution of any portion of the works ".
It is clear, therefore, that the C.R.B. relied on the general competence of Utah
and, later, of J. & W., and did not pursuP any adequate enquiries on their specific
competence to weld low-alloy steeL
Moreover, the C.R.B. did not take adequate steps to fit itself for its task as
J~ngineer"as described in the specifications. (See Section 2.3.5.)
These initial mistakes on the part of the C.H.B. had serious consequences for they
led to a series of assumptions that had, in actual fact, little or no basis.
Thus : C.RB. believed that B.S. 968 steel, if capable of passing the additional
. . J. & W.
tm;ts, could and would be satisfactorilv \Velded by
K.S.B.D. believed that C.R.B. would not have included B.S. 968 as a permissible
material unless satisfied that it was suitable.
Utah was assmed by J. & W. that it could do the job and, not being required by
the ;,pecifieation to submit evidence of J. & W.'s experience and not itself realizing the
full in1plication of working with high-tensile steel, aecepted these assurances without
making adequate enquiries.
32
J. & W.'s officers were told by B.H.P. that the steel was weldable ; did not realize
that for " weldable " they should have read " weldable by firms that have reorganized
themselves to a new level of technical competence''; thought that C.R.B. would not have
included B.S. 968 without due consideration; and finally, knew that C.R.B. would be
inspecting the fabrication procedure and the finished work and expected that this would
suffice to ensure a satisfactory job.
All these parties must share the blame for embarking on a project for which they
were not fully competent. Only Ferris and Murex played their parts properly.
We believe that C.RB. rather expected that the successful tenderer would have
been an overseas contractor, experienced in the design and construction of the particular
type of bridge offered, and, in that event, C.R.B.'s own limited experience might have
been of less significance.
The first welded high-tensile steel bridge built of Australian steel by a Victorian
firm should have been a much smaller structure on which all concerned could have served
an apprenticeship in a new craft.
It may be remarked th2ct no ~:;pecification at all was provided for aluminium alloy.
The O.R.B. explained that had the successful contractor offered this material, a supplementary
specification would have been issued in accordance with clam>e 1-:3-9.
Division 3 of the specification dealt with design and in it were laid down the loads
which the bridge was to be capable of carrying, the permissible working stresses in the
various materials, the permitted limiting dimensions of various components and, generally,
the great many conditions to whieb the designB had to conform. The total effect of all
these elauses was to leave the designer very little freedom of manceuvre for the exercise of
his own judgment. Clauses l-i:l~4 to 1--3-8 inclusive laid down the arrangements by which
the C.R.B. were to check the drawings and computations; in practice these arrangements
were supplemented by design conferences at which the C.R.B. indicated the corrections
that were to be made to the drawings. Exhibit 157 is the fiJc of the minutes of these
conferences, 119 in number, and it is clear that, while it may be going too far to describe
the C.R.B. as "the real designers of the bridge'', the C.R.B. certainly approved every
ealculation, drawing and detail, and required to be changed anything of which it did not
approve, or which did not conform to the specifications.
There wore in the specifications a number of clauses the existenee of which seem to
have been overlooked or ignored by the parties, or compliance with which was waived.
Some examples are:
Clause 2-l-l. (Particularly as it defines the word "' purchases ").
Clause 2-3-9. (Drillings for analysis).
Clause 2-3-24. (Despatch of material).
As to the former, Hardca::;tle stated in evidence that he did not feel himself restricted
by the specification but he also stated t.l1at it was much more detailed than other tmch
specifications to which he had v;orked and that it " certainly controlled our approach to
design".
On the other hand, there were two respects in which Professor A. J. Francis, who
assisted John Holland and Co. with their design, disagreed \vith the terms of the specification.
The first of these is of sufficient interest to merit a brief discussion. Clause 3-4-10 stated
that " in designing piles to resist lateral loading, and for design as a column, no lateral
support from surrounding materials shall be taken iuto account where these materials are,
filling, silt, or elay ". It would be not unfair to describe this clause as being completely
safe hut somewhat conservative even in view of the very poor foundation material adjacent
to the Yarra River.
Francis, relying on experimental and other evidence that need not concern us,
attempted to take advantage of clause 3-1~~10, which stated that" a rational analysis based
on a theory acceptable to the Board ... will he considered as compliance with the
specifications ", and designed a piled foundation \vhicl1 took some accmmt of l::tteral support
from the silt and clay of the river bed.
Utah, on the other hand, made enquiries from the C.R.B. as to how tenders which
departed from the specifications would he received, and was told, in substance, that they
would not be entertained. Accordingly, it was decided as n matter of policy to adhere
strictly to the specifications and to submit a design including Benoto cylinders for the
foundations. The tender letter of 29th January, 1957, however, includes these \vords :-
" If the C.R.B. ean furnish further information concerning lateral support
to the piles and also aetailed properties of the silt, it8 locat-ion and extent at each
of the pier locations, then based on such further information, on the assumption
that lateral support of piles f'an he assumed above the gravel layer it is believed
that a foundation using piles could he designed, which, if acceptable to the
C.ILB., could result in a substantial money saving".
The C.RB. did not pursue this suggestion but accepted the tender based on Benoto
eylinders which were eventually snccessfulJy used. Lta.h and the designers were, therefore,
more accurate than John Holland and Co. in its assessment of the C.R.B.'s views on piles ;
by tendering on the basis of Benoto cylinders, and content.ing themselves wit.h merely
drawing attention to the economic a.dvantages of piles, they went. a long way to securing the
6352/63-3
34
contract without doing violence to their engineering eonscience ; while the intended use
of piles was one of the reasons given for the rejection of John Holland's tender t:>pite
of its lower price.
We do not blame the C.H.B. for its attitude. As a public authority, responsible
for public safety, it was perfectly entitled to take this decision. We simply point out
that other responsible and experienced engineers held a different view. Such a eonflict
of judgment is inevitable in any engineering project.
The second matter in which Francis held different views from the C.R.B. was in
relation to the thickness of flanges briefly discussed previously in Section 1.1.3. Although
there is a rather unfortunate confusion with clauses 3-4-13 and 3-6-14 of the specification,
elause 3-10-6, where one reads that " no plates greater than 1 inch in thickness shall be
used in welded construction ", is 1mambiguous. 'rhis elause led straight to the use of
cover plates.
Here again we are involved in a question of judgment. The necessary thickness
of the flange plates in the cent:re of the span can be achieved either by having a single plate
of, say, 1-!-in. thickness, or by welding a cover plate on to the main flange plate. In this
case the combined thickness would be somewhat less than 1! inches because the thinner
plates in B.S. 968 can be used at a somewhat higher working stress than the thicker.
Both methods have their advantages and disadvantages. The O.R.B., relying on
Ferris's advice, reasoned as follows :~" The thicker the plate the greater is the risk of
brittle fracture because of the inherent properties of steel. It is therefore better to use two
or three thiimer plates welded together and to rely on our tests to ensure good steel and
sound welding. Cover plates are well recognized and widely used devices and, if carried far
enough towards the end of the girder to guard against fatigue, provide the best solution ".
The opposite view can be stated thus :-" Thick plates in the centre of the girder
"VY'ili be joined to thinner plates towards the ends by butt welds which are inherently better
than fillet welds because they are more easily X-rayed, and are not so liable to residual
stresses arising from the welding process nor to stress concentrations under applied loads.
Provided we take care to avoid notches and other discontinuities which will produce local stress
concentrations we can reduce 11he risk of brittle fracture to a reasonable leveL Moreover,
we will eliminate long runs of fillet welding and, in particular, avoid the termination of
the cover plate which, although often used, is not a good design feature ".
Expert opinion is divided on which is the better view to adopt and the O.R.B. cannot
be blamed for preferring one to the other. We simply point out that Francis disagreed, but
we must not fall into the error of saying that the bridge would still be standing if it had
been built to his design rather than to Hardcastle's; we have no means of knowing how
the thicker steel would have tmned out in actual practice nor how it would have fared in
the hands of the fabricators.
It must be pointed out, though, that the specification both required satisfactory
Izod results as a guarantee of adequate notch-toughness and also limited the thickness
of the steel for the same pmpose. This left the designer with no scope to apply his own
mind to the risk of brittle fractme and the best means of avoiding it.
In conclusion, we think it can be said that opinion is swinging away from eover
plates towards the use of thicker plates and especially towards the use of special steels
and techniques in critical regions. Thus Messrs. Mott, Hay and Anderson, when designing
the Huncorn-\Vidnes Bridge (See Ex. 93) in 1956, used plates in B.S. 9681! inches thick with
butt welds, but arranged for the completed girders to be subjected to a stress-relieving heat
treatment. They seem to have got the best of both worlds for their bridge is still standing,
at the time of writing, after one of the most severe winters on record.
In the Izod test a specimen of the steel to be examined is machined so that its
cross-section is a square of side 10 n1.1n. A groove or notch of specified dimensions is cut
in one side of the specimen which is then mounted in the anvil of a pendulum impact
machine. The pendulum \veight is swung so as to hit the specimen which breaks at the
notch ; the energy absorbed by the steel in fracturing is measured by the subsequent height
of the swing of the pendulum. It is generally considered that this test gives a good
indication of the notch toughness of the steel and is thus a fair guide to its liability to
brittle fracture.
An alternative test of a 1-limilar kind is the Charpy test in which the specimen
rests as a beam between two supports instead of projecting as a cantilever from a single
anvil as in the Izod test. The Charpy test is replacing the Izod mainly because the
temperature of the specimen can be more easily maintained at the desired value.
In clause 2-3-7 the required Izod values are given as 32 ft.jlb. at 70 F. and
20 ft./lb. at 32 F.
The weldability tests were quite elaborate and required two plates to be butt-welded
together in a certain manner and then cut up into slices, by machine cuts at right angles
to the weld, so as to provide a number of specimens each containing a central weld. Four
of these specim.ens had to withstand being bent round a former without cracking ; two
were subjected to tensile tests and four were prepared for Izod testing by machining
notches ; in two of the Izod specimens the notch was located in the centre of the weld and
in the other tvvo in the heat-affected zone (H.A.Z.) of the plate adjacent to the weld.
The specification leaves much to be desired at this point. Only four Izod specimens
were called for, two with a notch in the weld and two with a notch in the H.A.Z. Thus
if tests had been conducted at two temperatures there would have been but a single test
under each condition. This is not good practice ; \vhenever possible three tests should be
made. It is unfortunate, too, that the lower temperature was the one to have been discarded
for this was the more critical from the point of view of brittle fracture.
It can well he argued that if the reason for including these tests had been
unequivocally stated in the specification the C.R.B. inspectors, at least, would have been
able to approach this task \vith more understanding.
Some ingenuity is required to discover the results that were to be attained in all these
tests for the clauses just referred to were under the general heading of "Mild Steel" and
the values quoted presumably referred to tha,t material. However, B.S. 968 gives values
of the ultimate tensile stress and yield stress for plates and sections of various
thicknesses ; no values for the Izod tests are given, of course, since these tests are not part
of that specification.
The final result of all this was to produce a steel specification with many clauses in
addition to those of B.S. \")68. The intention oft,he C.R.B. in so doing was naturally, to secure
a steel with appropriate qualities, espeeially in respect of notch toughness, but the confused
way in which the speeification was actually written and the ambiguous use of the term
B.S. 968 undoubtedly contributed to the unfortunate series of misunderstandings, or whatever
they were, that surrounded the supply of steel for the bridge.
been quite different if the C.R.B. specifications had made no mention of B.S. 968 but had
included a full specification, ab initio, for the steel that was desired. This could have forced
Utah and .J. & W. to have negotiated a contraet with B.H.P. for the supply of a special
steel and many lamentable ineidents, whieh oceupy much spaee in this Report, might not
have taken place.
The following table summarizes the mam differences between the C.R.B. steel
specifications and B.S. 968 :--
-~---
2.5.4. Welding.
The elauses dealing with welding were carefully dmwn with the intention of producing
a high standard of workmanship. The difficulties that were actually encountered arose,
in the main, from the following :-
(a) At the time of writing this specification, \.Vilson was not fully aware of the
complications of welding B.S. 968 steel, and it therefore became necessary
to issue supplementary specifications.
(b) The nature of the welding process and the defects that <-an occur are such
that the production of an unambiguous document describing what
is, and what is not, aeeeptable is inherently difficult.
(c) J. & W. did not expect that the very high standard of welding described in
the specification would be insisted on by the C.R.B.
The clauses that gave rise to special diffieulty are now briefly discussed.
J. & \V. maintained that previous experience of C.RB. contracts had led to the
expectation that radiographic ins:pection, if used at all, would be used to a small extent only,
and that the amount insisted upon required the welding to be of " pressure vessel
standard ".
The C.R.B. maintained that the elause meant exaetly what it said and it proceeded
to set up a team of inspeetors whose duty was to inspect every inch of welding using
whatever method was thought appropriate. Penetrant dyes were used extensively on
fillet welds and radiography mainly on butt welds.
Clause 4-6-60 (a) reads: "\Veld metal shall be solid throughout except that any small
gas poekets and smal1 inclusions of oxide or slag may he over looked if well dispersed and if
none exeeeds -k inch in greatest dimension, and if the sum of the greatest dimensions of
all sueh defects in any square inch of weld met-al does not exceed i inch ''. The
37
interpretation of this elause, and the insistence by the C.R.B. on what was regarded
by J. & W. as being a standard higher than \Vas implied in the phrase " equal to the best
general practice in modern bridge shops " (Clause 4~6~7), led to continual friction.
Eventually, a new radiographie standard (Ex. 58) was adopted based on the work of
Beaton of the California Division of Highways. Objection was taken to this new standard
on the grounds that, as Beaton's work had not been published at the time when the
contract was signed, the contractor could not possibly have expected it to be used.
Nevertheless, it was used apparently for the remainder of the construction period.
Clause 4-6-61 prescribed the procedures to be used to eorrect any defects found as a
result of the inspection procedure just described. There is no doubt that a large amount
of repair work was in fact carried out (See Ex. 103 and 222) and subsequently passed by the
C.R.B. The evidence supports the contention of J. & vV. that, in spite of the difficulties
which were admittedly encountered in welding, every repair demanded by the C.R.B.
was carried out to the satisfaction of the C.R.B.
Clause 4-6-56 required care to be " exercised to prevent weld cracking ". " If
required by the engineer" the parts to be joined were to be "pro-heated to a temperature
of at least 130 F " Tables 1 and 2 and Appendix D of B.S. 2642 give the
relationship between the pre-heat temperature and the welding conditions for rutile and
low-hydrogen electrodes. This specification was itself superseded, on the instmctions of
the C.R.B., by a booklet (Ex. 23) written by B. J. Bradstreet and published by the
British \Velding Research Association entitled "Arc-Welding Lo\v-Alloys Steels" which
described a fairly elaborate procedure for determining the degree of pre-heat and resulted
in different temperatures being required from those given by either clause 4-6-56 or B.S.
2642. This topic is discussed further in Section 2.9.4.
The pre-heat temperatures actually used were the subject of argument throughout
the hearings of the Commission. In clause 4-6-55 instructions are to be found on the welding
proeedures to be used to minimize distortion and shrinkage stresses, while clause 4~6~12 (a)
states that " completed work shall be of the correct dimensions, square and free from
twists, bends, and open joints. No member at any time during fabrication shall depart
from the straight or from the specified profile by more than i inch in any length of 10
feet". These requirements were apparently later replaced by those in clause 507 of the
American ~Welding Society's Standard Specification for ~Welded Highways and Railway
Bridges, which are somewhat less severe.
While the J. & \V. and C.R.B. witnesses were all unanimous that at least the pre-heat
specified by the C.R.B. was always used, it was admitted by the senior officers of J. & W.
that they were reluctant to use the full pre-heat required by the B.,V.R.A. booklet referred
to above. One reason for this was undoubtedly the fact that the greater the preheat the
greater the difficulty of controlling distortion. It was never satisfactorily established
that the permissible deviations of the finished girders from t,he nominal dimensions were
compatible with the pre-he.at required.
The writer is, or should be, concerned to describe the materials and workmanship
in such terms as will ensure adequate, serviceable quality but not such perfection as
would be unduly expensive. It must be confessed that specifications usually err on the side
of perfection and call for work of such flawless virtue as no contraetor could achieve without
going bankrupt. It is then left to resident engineers, clerks of works, and inspectors
to temper the written word with the wisdom and experience of long practice.
By this criterion the C.R.B. speeifieations were, in general, good but the clauses
covering steel were scattered about in an unfort1mate manner and were not as clear as
could have been desired. We have criticized some of these elauses because they were
38
not free from ambiguities and especially heeause the ambiguity over the nomenclature
of the steel had such unfortunate COih'>equences. However, the C.R.B., while admihing
these criticisms, claimed that no reasonable person could really have been misled; any
deficiencies in the speeification provided a useful excuse for--hut could not possibly have
caused~-the events that led to the failure of the bridge.
Our only criticism of the substance of the steel clauses, at~ distinct from their form,
relates to the Izod value required and the lower temperature specified; these were taken
by Ferris from B.S. 1500 : 194'9 for unfired pressure vessels. We now think that the
value of 20 ft.jlb. was too low and that the temperature of i32o F. was too high ; the
lowest temperature recorded in Melbourne is 27c F. (See Sections 2.7.1.2. and 3.4.3.)
There remains only the question of whether the form of the specification was
suitable for this type of contraet. \Ve make no firm deeision on this point hut content
ourselves -vvith the remark that the full advantage of a design and construct contract may
not be realized unless a petjorrnanoe speeifieation is written. We think that such a course
would allow the contractor more scope to offer an ingenious solution and wm1ld force him
to bring his designer more closely into partnership \vitb his construction team. But we
concede that the writing of such a 8peciflcation would pose many problemR for the
construction authority especially in devising suitable acceptance tests.
2.6. Design.
2.6.1. General suitability.
\Ve are agreed that, 1:1peaking generally, the dm;ign was a good one. It employed
a large number of plate girders, which are very commonly used in steel bridge eonstruction,
arranged alternatively in cantilever and suspended spans. The details were arranged in
such a way as to make the progressive erection of the completed girders a straightforward
and systematic process. The girder::-; themselves had clean and simple lines, ea.sy to
maintain and attractive in appearance.
Criticism of the design must, therefore, be confined to the u~:~e of high-tensile steel
and to the details of the design of the tension flangm; of the girders. The latter are
discussed below. In proceeding as they did on both those features the designers, who
were represented at the Enquiry by Hardcastle, were supported by the confirmatory
opinions of many other engineer,s and they certainly cannot be held solely, or even mainly,
responsible for what went wrong.
It is customary, for reasons of economy, for the cover plates to extend only over
such regions of the flanges as need to be strengthened. rrhe points of termination have
to be settled and, in this case, clause 3-10~2~ (d) and Table 2 of Division 3 of the
specifications laid dovvn the procedure. The object of this procedure was, very properly,
to ensure that the ends of the eover plates were located in regions where the general stress
level was low enough for the danger of fatigue to be discounted.
39
We understand, however, that the formulae given in Table 2 were modified after
it had been decided to use high-tensile steel. This would imply that the fatigue strength
of this steel is higher than that of mild steel in the same proportion as the ultimate tensile
strength is higher. We do not think that this is so and, in our opinion, it would have
been \viser to uEte the same fatigue formulae for high tensile as for mild steel. The result
of this would l1ave been that the cover plates would have been longer and their termination
nearer the ends of the girders; \Ve do not think, however, that this change, although
beneficial, would have significantly altered the subsequent train of events.
The shape of the cover plate end had also to be deeided and here a detail was used
that has been successfully used in thousands of instances. It is shown in Fig. 11. In its
report (Ex. 1) the Committee of Investigation criticized this detail, saying : " This is
known to produce high local concentration of stress and is considered an undesirable
feature". The Committee can hardly have been unanimous on thi8 matter, for Exhibit
36 (U.S. Bureau of Public Roads drawing SB--2~53 slwwing standard Composite I-beam
Bridges) shows a cover plate detail almost identical with that used in Kings Bridge and
is signed by J\:Ir. E. L. Erickson, a member of the Committee.
The stress situation in the main flange plate adjacent to the end of the cover plate
is very complicated and is affected by several cireumstances. These are discussed below
in some detail, but it should first be pointed out that the attention of investigators in the
past has mainly been concentrated on the magnitude and significance of the stresses
induced by the superimposed loads on the structure. The residual stresses left in the
structure by tl1e processes of manufa.cture have not received anything like the same
attention, partly because they are far more difficult to investigate satisfactorily, but also
because they are usually considered to be of less importance. This view can only be
justified if it is certain that tlw steel is sufficiently duetih~ to allow high local stresses to
be dispersed into surrounding regions by local yielding. The various sources of stress are
now discussed.
2.6.2.2. Residual stresses resulting from the progressive completion of a single weld.
It will be apparent from the foregoing that the final state of stress is liable to be
affected by the way in which a single weld is bnilt up. The Interim Code for Manual Metallic
Arc welding in Building Construction, published by the Standards Association of Australia
as S.A.A. Int. 352, has this to say : "The di1ection of the general progression in welding
on a member shall be from points where the parts are relatively fixed in position with respect
to each other, toward points where they have a greater relative freedom of movement."
In attaching the cover plates to the flanges the long fillet welds were automatically
welded first and the welds along the tapers and across the transverse ends were then done
manually. This operation was some times carried out as the last step in attaching the cover
plate to the flange but before the web to flange fil1ets were made, and sometimes as a final
operation after the web and flanges had been welded together.
So far as the order of making the taper and transverse manual welds was concerned,
much time was spent at the Enquiry in trying to establish what actually happened and in
discussing what should have happened. rraking the evidence as a whole we conclude that
some welders did one thing and some another and that the records now available do not
enable us to say whether there is any correlation between the mder of procedure and the
subsequent appearance of craeks.
There was no evidence that the transverse end weld was ever completed before the
welds clown the tapers were beglm but experiments by A.I.S. (Ex. 184, Section 7) suggest that
this might have been the best way to proceed.
2.6.2.3. Stresses at the ends of the cover plates caused mainly by superimposed loads.
It is to be expected that at the cover plate end there were residual stresses produced,
in the manner described above, both by the welding of the cover plate to the flange and
also by more remote welding operations.
We now come to the main stresses for which the bridge \vas designed-those caused
by the dead load of the girders and deek and those caused by the incidence of traffic. In
addition, mention must be made of the attachment of the concrete deck to the upper flanges
of the girders by means of shear connectors. The shrinkage of the concrete, as it hardened
and matured, would impose a compressive stress on the upper flange and a corresponding
tensile stress on the lower flange. Professor Francis' estimate of the increased tensile stress
in the lower flange from this cause was 2,HJO lb.jsq. in. (Ex. 30).
The stresses caused in the tension flanges by the load effective at any moment can
be estimated by conventional bending theory, but this does not take into account the
concentration of stress at the ends of the cover plate caused by the sudden change of stiffness
of a flange to wbich a partial length cover plate is attached.
The first report of the Steel Structures Research Committee (ILM.S.O. 1931) contains
theoretical and experimental evidence about the stresses in welded joints which, if extended
to the cover plate problem, indicates clearly that the stresses in the welds connecting the
cover plate to the flange will be different from those given by conventional theory. In
particular it is to be expected that the elastic force transmitted by unit length of the end
welds will be intensified.
It is known that the behaviour of steel is greatly affected by the magnitude and sense
(i.e., tension or compression) of these stresses and that, in particular, the existence of
component tensile stresses that are nearly equal in magnitude is conducive to brittle fracture.
While the subject is far from being fully explored it now seems certain that a steel which
is quite ductile under a tmiaxial stress can become brittle if sufficiently large perpendicular
stresses are also present. It is also thought that all steels will fail in a brittle manner under
sufficiently high triaxial stresses, i.e., when the three perpendicular components are equal.
It also appears that the transition temperature, at which a change from ductile to
brittle behaviour takes place, is raised by the action of component tensile stresses perpendicular
to the direction of the main stress. This may account for the fact that the transition
temperature obtained from Izod or Charpy tests is not always the same as experience of the
same material in an actual structure '"ould indicate.
The phenomena just described make it particularly dangerous to weld across the
tension flange of a girder for residual stresses can be set up in three perpendicular directions.
Since the main stress (longitudinal) is tensile the tendency to brittle fracture is increased
and the transition temperature raised at points where the other component residual stresses
are tensile.
For these reasons, and also because any undiscovered weld defect in this position
is a special source of weakness, some designers prohibit the use of transverse fillet welds
at any point on a tension flange ; others permit them only towards the ends of the girder
where the bending stress is low. The specifications for Kings Bridge were based on the
latter view.
We find it difficult to say whether, at the time of writing the specifications, the C.R.B.
should have decided differently but we are of opinion that, on the basis of lmowledge now
available, transverse fillet welds should be prohibited on tension flanges.
This danger is naturally more acute in machines with reciprocating or rotating parts
than in bridges where only the live load, due to traffic, fluctuates ; the dead load, due to
the self-weight of the structure, is constant. The extent of the fluctuation of total load
depends on the ratio of live to dead load and is usually greater in railway than in road bridges.
42
At any point in a structure the likelihood of fatigue failure depends on the maximum
stress and on the range of stress experienced there ; on the number of fluctuations likely
to be experienced during the life of the structure ; and on the inherent resistanee of the
material to the phenomenon of fatigue. The eonneetion between fatigue aild brittle fracture
is that both are most likely to occur at points of high stress especially if the inherent stress
is intensified by stress raisers such as unfavourable geometry, poorly shaped or defective
welds, surface and other defeet8 produced in the steel-making process or notches or cracks.
Residual stresses, especially when tensile and in perpendicular directions, seem to add to the
risk of both types of failure.
The Kings Bridge specifications took account of the possibility of brittle fracture. They
also gave recognition to the susceptibility of the cover plate end to fatigue failure by fixing its
position in a region of low bending stress. It was argued at the Enquiry that, because of the
above connection between fatigue and brittle fracture, the designer should have been alerted
to the danger of the latter occurring at the same point. This may well be so but the C.R.B.,
whose officers compiled the specifications should have been even more alert. However,
Eastick's evidence suggests thar he did not realize that the Izod tests had been included
to try to guard against brittle fracture.
It will perhaps be apparent from what has already been said that the precise
estimation of the magnitude of residual stresses is really a hopeless task; the most that
can be said is that they will certainly be present in a welded structure and that they may
well approaeh or reach the yield point of the material. On the other hand they are usually,
but not always, local in character. Fina1ly it must be said that their effeet becomes more
serious as the size of the strucilure increases.
With these facts in mind, therefore, and in the present state of knowledge, the
designer proeeeds qualitatively rather than quantitatively. He can do his best, by eareful
detailing, to ensure that the inevitable concentrations of stress are kept to as low a level
as possible ; he should ensure that the fabricator adopts satisfaetory procedures during
welding; in order that loeal yielding may disperse high stresses by redistribution, he must
ensure that only steels of adequate ductility and notch toughness are used; and finally
he may deeide to resort to a stress-relieving heat treatment.
One of the features of the Kings Bridge project that most disturbed us was that
the designer was not in elose eontact with, nor responsible for, the actual fabrication.
Hardcastle told us, for example, that he was not aware that some of the steel used did not
exhibit a clear yield point. We have no means of knowing ho>v he would have reacted to
this knowledge if it had reached him at the time but it is certain that this information would
have had more significance for him, whose knowledge of the anatomy of the structure
was so intimate, than for anyone else.
In the foregoing we have been mainly eoncerned with residual stresses from the
point of view of their local effcet at special points. There remains the question of any
effects that are greater in scale:; one such matter did receive very dose attention during
the construction of the bridge.
It was known that welding the stiffeners to the web plate would have the effect of
shortening the web and it was therefore intended that the operation of attaching the
stiffeners to the web should be completed before the web to flange welds were made.
However, it would not then have been possible to use an automatic welding process for
the long web to flange fillets.
Roderick, of Sydney, whose view was that the arrangement would he satisfactory provided
that the possibility of buckling could be eliminated from consideration. Aecordingly,
Hardcastle made some calculations which showed that the danger of buckling was remote
and the arrangement was approved and used throughout the fabrication.
It is evident from a perusal of Roderick's report, and of the reeords of the eonferenee
with him, that he mainly considered the possibility of a reduction of the so-ealled plastic
moment of resistance of the girder by the residual stresses. In so doing he implicitly relied
on the capacity of the girder to develop a full plastic moment by yielding, as he was
entitled to do because of the specification of the steel. He 'vas not asked for an opinion
on the possibility of brittle fracture intervening before yielding could take place and did
not himself advert to this possibility.
The results of these investigations are somewhat conflicting; thus the Welding
Handbook, 4th Edition, Volume 1, says that " No practical arrangement or detail has been
found which is quite as good as simply cutting the end of the cover plate square without
any taper". On the other hand Munse and Stallmeyer (British \Velding Journal, March,
1960), came to exactly the opposite conclusion and found that a design similar to that used
in Kings Bridge, but with the transverse weld omitted, was the hest under some conditions.
However the difference between these designs was not very marked and no detail using cover
plates was as satisfactory as the alternative approach of butt-welding the thinner plate to the
thicker one and tapering the latter, in v>idth or thickness or both, to match the former at
the weld.
It is not to he assumed from this that this last design, by itself, is sufficient to guard
against failure. The Duplessis Bridge, in Canada, (Highway Research Abstracts, June,
1951) and an unnamed bridge described by Campus (Osgood: loc. cit. p. 8) both
suffered brittle fractures initiating at butt welds connecting tension flange plates of different
thicknesses. The steel used in the first of these bridges was, however, of poor quality
while weld defects were found in the second case.
Nevertheless, while it seems that designers are now tending to avoid cover plates it
cannot be said that the practice is tmiversal nor that the designers of Kings Bridge can
he blamed for using them in 1957. As has been said, they have been successfully used in
thousands of instances.
No doubt this procedure is quite satisfactory on routine jobs in mild steel hut it
seems to us to he inadequate in some circumstances. It is not difficult to think of structures,
even in mild steel, where the order in which the welds are made is important from the
designer's point of view. When more difficult materials are being welded the development
of satisfactory teehniques and the assessment of their significance in the final structure
seem to us to require considerations of a somewhat sophisticated nature on which the
designer's mind should he brought to hear.
An important advantage of the design and construct type of contract is that there
need be no obstacle to full collaboration bet1veen the fabricator and the designer in such
matters ; the latter can hardly be expected to have a close, detailed knowledge of the
metallurgical and other implications of welding techniques but he can well be expected
to realize how the final results of those techniques may effect his structure.
\Ve are therefore astonished that it should have been agreed, a;.; ;.;tated by Wilson,
that "the welding procedureE . would be determined by the fabricators and there
would be no reference on the drawings in that regard." This is to throw away one of the
advantages mentioned by Da:rwin for this ty7e of contract. (Section 2.1.).
We believe that the Kings Bridge project shows that if designers do not take some
responsibility for welding procedures then they are taking 8erious ri8ks. The extent to
which ~his is necessary on a particular job, and the way in which responsibility is best to be
exercised are outside the scope of this Heport but they merit careful consideration by the
engineering profession.
2.7. Steel.
2. 7 .1. The steel specified.
2.7 .1.1. The justification of including B .S. 968 : 1941.
Steel to B.S. 968 : 1941 mcluded by the C.R.B. as one of the options for use in
the superstructure of the bridge, is knowll as a low-alloy steel and it is designated as
" high-tensile (fusion welding quality) structured steel for bridges, &c.". It was a war
emergency specification. The C.H.B. specifications clearly implied that if welded girders
were to be included in the construction they could be fabricated either in mild steel or in
high-tensile steeL The main advantage in the use of the latter was that higher design
stresses could be used becau:ge this steel was stronger than mild steeL Consequently,
the girders would be lighter, thus reducing the load on the foundations. As the foundations
were the cause of much anxiety in the early considemtions of the C.RB., any feature
reducing the dead load of the superstructure could from that point of view be considered
desirable. Nevertheless, in assessing the economy of high-tensile steel it is necessary to
look beyond the mere saving of weight. This material costs more than mild steel per ton
and it is more difficult to fabricate. For these reasons we were surprised at Bonwick's
statement that its use resulted in a saving of 175,000.
Since all conditions for the 8atisfaetory welding of low-alloy steel were well known
and since economies in the dead load on the foundations could be produced thereby it was
reasonable for the C.RB. when drawing the specifications to include B.S. 968 : 1941
steel as an optional material.
However, there are certain implications which follow from this. It was known to
the C.RB. that no major welded structure had been constructed in this material in
Australia (See 1\lasterton's article on " Kings Bridge ", Ex. 22). It was not sufficient to
know that other fabricators including the Hoyal Australian Navy had used this steel. If
the girders were to be fabricated in Australia it was necessary to know that there was a
fabricator with the organizational and technical ability to make the change from mild steel
to low-alloy steel construction, and that the steel as made in Australia would have the
necessary properties-for it is well kno1vn that many manufacturing features enter into
the production of a satisfaetory steel.
Wc conclude that the C.RB. was justified in including steel to B.::). 968 ; 1941 as an
optional material for constructing the superstructure, provided the specifications ensured
that it would be fabricated by a firm having adequate experience with its characteristics.
For this purpose there should have been inserted in the specifications a clause providing
that where a tenderer proposed the use of B.8. H68 : 1941 or for that rnatter pre-stressed
concrete or aluminium alloy, he should be required to demonstrate his ability and
competence to handle such material.
It follows that before accepting a tender based on B.S. !J68 : 1941 the C.RB. should
have been satisfied that the above condition relating to the fabricator and the steel supplier
could be fulfilled. The C.R.B. neither adequately investigated the properties of B.S. 968
steel as made by B.H.P., nor the ability of the sub-contractor to reorganize along the
necessary lines.
In the absence from the specifications of a special clause as suggested, clause 1-2-14,
which pro'hibited the contractor from sub-contracting any part of the work without the
prior written consent of the C.H.B., could have been invoked in relation to J. & W. It
appears that J. & W. and B.H.P. were accepted as sub-contractors and steelmakers,
respectively, on the strength of their general reputation without any special enquiry about
their experience in fabricating or manufacturing B.S. 968. The C.R.B. should have
required this competence to have been adequately demonstrated.
We arrive, therefore, at one of those many curious situations which have been a
feature of this Enquiry. While the C.RB. was justified in permitting steel to B.S. 968 : 1941
as an option, it was not justified in accepting without further enquiry the tender of Utah
including B.S. 968 : 1941.
We are eonvinced that the C.RB. failed to make the necessary experiments and
enquiries because (with the, exception of Wilson) no officer of the Board realized their
importance. They accepted the title of the British Standard Specifieation as implying
that the steel could be welded satisfactorily by an established fabricator irrespective of
whether he had had experience with low-alloy fabrication or not.
It was said that the temperature of 32o F. was chosen because it was the lowest
operating temperatme to which the steel work of the superstructure would be exposed
under Melbourne climatic conditions. However, enquiry at the ~Ieteorologieal Bureau
would have elicited the information that the n:Unimurn temperature ever recorded in
Melbourne was 2T ]f. and engineering eaution would have reduced this to 22o F. Indeed
at another part of the specifitation this was done: Clause 3-6-46 requires that the
provision for expansion and contraction of the girders should cover the range of temperature
20 F. to 120 F. It is obvious that 32 F. was ehosen because it is easily reproduced,
being the melting point of ice. To understand the significance of this requirement needs
a brief deseription of the phenomenon of brittle fracture. It should be understood that,
as mentioned above, this phenomenon is associated with mild steel as with low-alloy steel,
so that in what follows no distinction is made.
46
when steel is subjected to load it deforms : at low stresses the amount of deformation
is small and, if the load is removed, the deformation disappears. At higher stresses the
deformation is more marked and is permanent in the sense that a high proportion of it
remains even after the load is removed. The transition from one stage to the other takes
place gradually in some steels while in others it is characterized by " yielding " when a
comparatively large amount of deformation takes place under nearly constant stress.
Steels in which a large amount of deformation takes place before fracture are ductile.
The presence of notches creates an entirely different situation, and in this connection
a notch may be merely a sudden change of section associated with a design feature, a defect
in the plate resulting from steel works practice, a crack resulting from defective welding
practice or from flame cutting a plate to dimensions, an under cut in a weld, a nick caused by
a sharp blow in handling and any similar sharp change of contour on the surface, or even
a sudden change in physical properties sueh as occurs in the immediate vicinity of a weld.
In such cases, under tensile stress, a fracture is liable to start at the apex of the notch,
and once started it may be either arrested or propagated according to the properties of the
steel. The property of arresting the development of a crack is kno\\'11. as notch ductility.
A notch ductile steel will arrest a crack already started ; a notch brittle steel will allow
the crack to propagate with substantially no deformation at low stress and the steel
fractures as though it were a piece of pottery.
Notch ductility depends on many features associated with the chemical composition
and manufacturing conditions of the steel, the sharpness of the notch, the speed with which
load is applied and the temperature of the steel when the stress is applied.
It will be seen therefore that to ensure notch ductility in any plate of steel it is
essential to test it to check ii1s behaviour to stress in the presence of a notch, and to do
this at different temperatures. It is found that Rteels of the t)'}Je considered change
regularly from a notch brittle state at low temperatures to a notch ductile state at higher
temperatures. This is known as the transition range and this determines, in so far as it can
be determined, the response to stress of steel containing notches of the type described. For
any given quality of steel such as mild steel or low-alloy steel the transition range may vary
according to the steel manufacturing conditions, so that it by no means follows that steel
of a given chemical composition, will have a defined degree of notch ductility at a given
temperature. For this reason, it is essential to apply a test and the one most favoured is
a Charpy or an Izod test which has already been described.
The result,s obtained are a valuable guide to the suitability of the steel, but its
actual transition charaeteristics in a given structure may not be identical with those shown
lmder the simple conditions of the test.
The C.R.B. should have ,,;peeified and insisted upon the carrying out of a complete series
of tests of the kind described until it became familiar with the properties of the steel,
instead of specifying two temperatures only, 32 ],. and 70 F.
All low-carbon steels are i-mbjected to this phenomenon of changing with temperature
from a ductile to a brittle state.
This kind of embrittlement was not envisaged by the C.R.B. and no test to cover
t,his feature was written into the specification. Apparently also the steelmaker did not
advert to this possibility, for it is possible to " fix " residual nitrogen by small additions to
the steel in the ladle. It does not then cause strain ageing.
(b) The Weldability Test.-A further materials test included in the CUtE.
specification was a weldability test intended to ensure that the properties of the steel as
supplied were maintained during the welding operation, and also to test the properties of
the weld metal deposited from the electrode. Again, this test was to be applied whatever
the steel used, i.e., it was not restricted to B.S. 968. It was a complicated test involving
a lot of machining, and it was probably this feature which gave rise to the impression that
exce:-:;sive testing was involved in the contract, an impression which ultimately led to a
relaxation of testing about the middle of 195n.
This series of weldability tests included Izod tests (a) on the weld metitl, and (b) on
the heat-affected zone of the weld. Two tests 'vere to be made on each, and at p. 83, book 1
of the specification it is stated (by implication) that t,hey should be made at 32 F. and 70 F.
However, in fact, both were tested at "ambient., temperature, and none at 32 F.
SU:YIMARY.
1n view of the unknown behaviour of B.S. 968: 1941, steel in conditions leading
to brittle fracture :-
(a) It was reasonable and right to specify a notched bar test. at. the lowet':lt
temperature to which the bridge would he subjected.
The question as to whether the value chosen for the lzod impact
value 'vas the right one is discussed elsewhere (Section 3.4.3. ).
(b) As the weldability tests were designed to test both the weld metal and the
heat-affected zone of the parent plate these tests also were reasonable and
should have been carried out on each individual heat of steeL
(c) In view of the very limited experin1ental work which had been done on the
properties of this steel by either C.R.B. or J. & W. before fabrication
commenced, it would have been advisable for the preparation of the test
weld to have been done by one of J. & W.'s own welders. This would
have given them a better kno,vledge of the welding characteristics of the
steel. Instead, the preparation of the test welds was given to the most
expert welders of Murex, which \vas quite permissible 1mder the C.R.B.
specifications but J. & W. learned nothing from these regarding weldinu
~~~. D
(d) In view of the ultimate failure of the bridge by brittle fracture there can be
no doubt that, in the light of present knowledge, the additional tests
imposed by the specification were justified, though in certain respects
inadequate.
(e) lt must be realized that even the best specification is useless unless its
conditions are complied with. This necessarily involves carrying out the
procedures specified and subjecting the results to intelligent scrutiny.
This was not done.
It is sufficient to say here, that because of the two different standards created, it is
necessary to consider the steel vis-d-vis the two specifications.
48
2.7.2.1. Did the steel supplied by B.H.P. meet the B.S. 968: 1941 specification?
The evidence on which this ean be answered is partly in Exhibit 72, a. compilation
of acceptance tests by the C.B.B.
\Vithout going into detail it can be said that, from a eommereial point of view the
steel supplied was in our view largely in accordance with B.S. 968 : 1941 in so far as tests
were carried out.
This statement must be qualified in several ways :-"-
(a) The speeifications call for extra tensile tests when more than one thickness
is rolled from a heat. This was not always done.
(b) Similarly, the number of bend tests, and the type, whether longitudinal or
transverse was not always as specifted.
(c) On the original B.H.P. eertificate showing heat analysis no mention was
made, in general, of the chromium content. The B.S. 968 speciftcation
limits manganese to 1 8 per cent. and the combined manganese and
chromium content to 2 0 per cent. As the manganese was frequently
near the upper limit, this feature of the specification eould not be checked
from the certificate unless the chromium content was guaranteed less
than 0 2 per cent.
So long as the steel was made by the open-hearth process, the only chromium present
was about 005 per cent.--a residual from the steel-making conditions. However, Balston
claimed that B.H.P. was justified in leaving up to 0 35 per cent. ehromium as residual.
If this were so then it was definitely necessary to report chromium on the certificate in order
to check against the specification. In actual fact, when in February, 1959, B.H.P. (Port
Kembla) switehed production from open hearth to electric furnace, it deliberately added
0 25 per cent. chromium and still did not report this on the test certificate.
Even, however, with this addition, the chemical analysis taken from the ladle test
ingot which purports to give as nearly as possible the average composition of the heat was,
by and large, within the specified limits, though frequently at the maximum permissible
limit.
It must be borne in mind that the fabricator has to deal with steel as it is, and not
as it might be or as it purports to be on an analysis certificate. In other words either he
should be able to accept the certificate as giving the true composition of the steel plates
he receives, or he should do some systematic checking. In many cases \Vhen plates were
checked (Table 3, Section 2.9.6.4.) the results were found to differ from the ladle analysis.
There are well-known reasons why a difference may occur between the "ladle
analysis " and the "plate ::malysis ". These are all controllable metallurgically.
Steelmakers vary in their attention to detailed practice, and this constitutes part of the " art "
of steel-making.
Briefly there are three sources of variation of composition throughout a given mass
of steel. The first relates to the size of charge. Open-hearth heats may be several hundred
tons. Towards the end of the process finishing additions of various alloys are made to adjust
the carbon and manganese. There is a. sheer physieal difficulty in getting such a mass of
steel uniform.
At Port Kembla the open-hearth charges were of about 250 tons and this was tapped
into two ladles of 125 tons. The electric furnace heats, however, \vere only 17 tons and did
not, or should not, present the same difficulty, i.e., they would be expected to be more uniform
on tapping.
The second source of variation is concerned with the ladle. Sometimes final additions
of alloys are made and the churning action of the molten metal is relied on to mix the whole
uniformly.
A.l.S. is in accord with these views for in Exhibit 184, section 1, it is stated " the
electric furnace at 17 tons presented a much simpler operation and the advantage of being
able to remove slag and re-form slag of controlled composition and conditions, made
specification control more regular ".
49
The third source of variable composition is the natural phenomenon of ingot
segregation. The molten steel is teemed from the ladle into ingot moulds. The ingots
solidify from the outside and the concentration of such elements as carbon, manganese,
sulphur and phosphorus increases towards the centre and top of the ingot. By suitable
practice this segregation can be localized and can be removed by cropping in the rolling
mill. In this way ingot segregation differs from ladle and furnace segregation. It is
regular and can be removed in normal mill practice. The other two would give steel which
varies from ingot to ingot and the chance of the test ingot of about 2 lb. being representative
of the many tons of metal is remote if the charge is not uniform.
Heats 55 and 56 have been the subject of exhaustive checking during this li1nquiry
and it has been shown definitely by all the laboratories concerned (D.S.L., McPherson's,
and A.I.S.) that there were differences between the ladle analysis and the plate analysis
taken from the failed girders. ']'his is not the place for a detailed consideration of this
problem. Sufficient to say that the following order of variation has been found by D.S.L.
& McPherson' s :-
Analyses.
Ladle ! Plate (max.) Difference
I i
Heat No. Type I I
I e. Mu. c. Mn. c. Mn.
~---------~----~----~--------~-
I
38 .. .. .. O.H. 22 156 25 167 03 11
40 .. .. .. , 23 175 26 203 03 28
55 .. .. .. E. F. 21 170 28 180 07 10
56 .. .. .. 23 158 27 175 04 17
"
I I
It will be noticed that the difference between ladle and plate analysis, as far as carbon
is concerned, is rather greater with the two electric furnace heats than with the two open-
hearth heats. The differences are not great except with heat 55 and would not have been
serious if the ladle analysis had not already been at the maximum permissible limits of the
specification. The regularity with which high carbon and manganese have been found in
heats 55 and 56 suggests ladle segregation rather than ingot segregation.
However, two of the heats (Nos. 55 and 56) were incorporated in the tension flanges
of the group of girders which collapsed on July lOth, 1962.
Before following this matter further, it is necessary to look at the steel supplied from
the point of view of the C.R.B. specifications.
6352/63--4
50
2.7.2.3. Did the steel meet the C.R.B. specifications?
As has been pointed out, the C.R.B. design engineer, Wilson, wrote some additional
clauses into the specifications covering Jzod impact tests and weldability tests thereby
modifying the B.S. 968 : 1941. The Izod tests were included to protect the bridge from
brittle fracture.
One of the factors which affects notch duetility is the thickness of the plates.
Consequently, the specifications called for Izod tests at two temperatures on each thickness
of plate from each heat of steel. The reeords, however, disclose that when there was more
than one thickness of plate in a given heat only one thickness was subjected to Izod tests
and there is nothing to indicate to which thickness the actual tests were applied.
It was a term of the C.R.B. contract with Utah (See Clause 2~3~24) that material
should not be despatched from the maker's works or from stock until Utah had certified that
it complied with the requirements of the C.R.B. specification. In fact, during the Enquiry,
no party has adverted to this dause and it must be pre~:mmed that no attempt was made
by the C.RB. to enforce it. J. & \V. looked upon C.RB. as the authority to give the final
approval, but did not hesitate to fabricate steel before this approval had been given. Utah
took no part in the assessment of tests, but merely passed on the certificate from J. & \V.
to C.R.B.
Of the 58 open-hearth heats supplied, 54 were tested, not in accordance with the
strict requirements of the C.H.B. specifications, but to the extent of the actual require-
ments of the C.RB. They all passed the Izod test at 32 F., most of them easily
complying. Curiously some of them (Heats 4, 9, 20, 25, 26, 30 and 31) failed at 70 F.,
but on retesting (not strictly according to the specifications) were passed. Most of the
heats passed the weldability tests at first attempt and all on retesting.
It has been very evident during the Enquiry that those concerned with the Izod testing
programme did not understand its significance and went through the motions merely to
comply with the specifications. This particularly applies to Scarlett (J. & W. and Utah),
Bastick and Jackson (C.R.B.). This attitude was engendered by a defect in internal
communication in the C.R.B., for apparently \Vilson ceased to be associated with this
aspect once fabrication started, and was never aware that the conditions of the specifications
had not been completely fulfilh!d. He does not appear to have passed on his enthusiasm
for the additional tests to those subsequently responsible for carrying them out. The
controlling personnel of J. & W. had no interest in testing of any kind, and B.H.P. had
persuaded them that in any case the lzod tests were futile. Utah personnel simply had
no interest in the quality of material being fabricated for the contract. " vvny "' they
said in effect, " do something \vhich C.R.B. is sure to do ? "
When it became kno>vn to Eastick and Jackson that the remainder of the steel
would be supplied from relatively small electric furnace heats of 17 tons instead of from
125-ton open-hearth heats, they decided to test heats selected at random.
In actual fact, there was little change in the position from this aspect, for from the
58 open--hParth heats only 1,200 tons was delivered to J. & W. This is an average of
approximately 20 tons per heat and is not much larger than the average of 15 tons per heat
from the electric furnaces.
The total number of heats actually supplied was, however, far greater than had been
originally anticipated by J. & W. \vnen the order was being discussed with B.H.P.,
J. & vV. understood that it would have to accept quantities from the one heat of not less
than 150 tons at a time, and J. & W. placed its orders, with insignifieant exceptions,
accordingly. If the steel had been supplied in 150-ton lots there would only have been
fifteen or so heats involved instead of the llO or so actually used in the bridge. The
testing programme was correspondingly enlarged. In addition the amolmt of retesting
requi1ed, especially in the electric furnace heats, turned what would have been a quite
reasonable testing programme---even if it had been carried out completely in accordance
with the C.R.B. specifications~--into a very extensive one.
By contrast with the steel from open-hearth heats the over-all picture of the steel
from the electric furnace heats is not good. Because of the changed attitude of the C.R.B.
to testing they were not tested as thoroughly as the open-hearth heats. Weldability tests
51
were carried out on 29 heats and of these 26 failed in one respect or another, but most of
them passed on a first retest. This was a much higher proportion of failure than had
occurred in the weldability tests on the open-hearth heats, namely 18 out of 58.
This is an indication that the electric furnace steel produced was inferior to the open-
hearth steel. One of the reasons given for changing to electric furnace steel-but which we are
by no means convinced was the compelling reason-was that the fully-killed steel produced
in the electric furnace would be of better quality and would aid J. & W. to meet the more
exacting specifications of C.R.B.
From the time that random testing was adopted the story of acceptance testing
is a sorry one, and we feel no good purpose would be served by analysing the reported tests
in detail. Several of the heats failed in the weldability Izod test and were never retested
(Heats 49, 50, 51, 79 and 80). Several failed, were retested and failed again. In fact, it
was admitted by Scarlett that testing was continued until satisfactory values were
obtained (See heats 54, 55, 70, 74 in Ex. 72).
The climax of the testing story comes with the group of 8 "submitted heats" (See
Sections 2.7.2.2 and 3.4.1). The results of the first tests on these heats were so bad that
J. & W. and C.R.B. should have been not only alerted but alarmed. Regrettably, these heats
were treated as part of the general run. No plate Izods were carried out, and the
weldability tests were first made four months after the submission. Of the 8 heats, 5 failed
in the tests, 4 of them badly. Heats 52, 53, 54 and 55 failed on the first retest but were
again retested,
Heat 55 still failed, so was tested a fourth time. Almost a year elapsed before
these tests were completed, but although in September, 1959, these four heats were still
showing "fail" on retest, and should in fact have been rejected, J. & W. wrote to B.H.P.
requesting delivery.
There is, however, an interesting fact to which we attach some signifieance. The
flange in girder W.14-2 which first fractured (some months before the final failure) was
made from heat 56 (if the records are reliable), which passed the weldability tests at the
first attempt. It was not subjected to plate Izod tests at the time, but in tests since the
failure has given quite variable results.
The records show that the tension flanges (bottom) of all four girders at the
location of the fracture were constructed from steel from heats 55 and 56 (electric
furnace-" submitted heats "). The webs of the girders at the same location were
recorded as being made from heat 40 (open hearth) though there is internal evidence that
in fact the web of girder W.14-1 was made from heat 38 (open hearth).
Chemical analyses have shown that the carbon and manganese contents of much
of the steel from heats 40, 55, and 56 were outside specification-ranging as high as 028
per cent. carbon and (heat 40) 2.0 per cent. manganese (See Exs. 155, 184, and 194). The
maximum allowed by specification is 0 23 per cent. carbon and 1 8 manganese. The
manganese plus chromium figure is, however, close to or above the maximum permissible
in heats 55 and 56 because of the presence of 025 per cent. chromium (intentionally
added), (See Ex. 170).
52
Much has been made by B.H.P. of a table of toleranceti sponsored by the American
Iron and Steel Institute. From this it is claimed that for steel of this quality tolerances
over the maximum specified carbon of 04 per cent. and of manganese of 05 per cent.
were permissible, and acceptable as grounds for rejection. There is no mention of any such
tolerance in B.S. 968 : 1941.
vVe are of the opinion that a competent fabricator should have carried out check
analyses on at least some of the heats received, and amongst these would surely have
been included the " submitted heats "-
(a) because attention had been drawn to them by the supplier, and
(b) because of the high incidence of failure under the specified tests.
Undoubtedly, some of this steel, including heats 55 and 56, was out of specification
with regard to chemical composition, and should have been rejected. There was ample
time to attend to this as the W.l4 girders were not fabricated for more than a year after
the steel was received.
The Izod tests made on the failed girders have revealed an interesting patteru. In
general, heat 55 shows very low value though occasionally, as happened when it was tested
to exhaustion fOT acceptance, it turns up with a good record. Such a case is found at the
southern fracture in girder W.l4--4. These values (31 ft.jlb. at 32 F. and 40 ft./lb. at
70o F.) are so surprising in view of the testing history of this heat that it is suspected a
plate from some other heat ha,g been wrongly marked.
The samples of heat 5{) from the girders show mixed Izod values, sometimes
conforming with the C.R.B. specification and sometimes not.
It could not have been rejected on the acceptance tests which were made, and it
is futile to guess whether, had Izod tests been made on the plate, the low values or the
high values would have been found. We are certain, however, that under the procedure
of testing till satisfactory results were obtained, this heat would have been accepted.
In fact, no single heat was rejected throughout the contract. We are faced with
the situation that a specification written by 'Vilson of C.R.B. in a form well ahead of its
time, was made futile by the failure to apply it critically. The value of a specification is
determined by the rigour of the inspection system used to implement it.
We are of the opinion t,hat heat 55, along with several others of the submitted
heats should have been rejected. We cannot, on the evidence, say that heat 56 should
have been rejected. On the tests made it was justifiable to include it but whether this
could be said if the full tests had been applied we have no means of knowing.
2.8. Electrodes.
Three welding processes were used, manual, automatic, and semi-automatic. All the
welding at the cover plate ends, both the taper welds and the transverse weld was manual.
The electrode used was Fortrex 35 made by Murex. This electrode is of the low-hydrogen
type recommended for use with low-alloy steel.
There has been no evidence that the electrodes per se were other than entirely
satisfactory. However, the flux surrounding the metal core is Jiable, as with all fluxes,
to absorb moisture from the atmosphere. This moisture is decomposed in the arc at the
melting temperature of the steel, releasing hydrogen which is absorbed by the weld. It
is weH established that such hydrogen is a main cause of cold cracking in the heat-affected
zone of the weld. Because of the nature of the flux covering, the low-hydrogen type of
electrode contains a minimum of inherent hydrogen and any absorbed water can be
entirely eliminated by drying. This involves the use of hot boxes in which the electrodes
are placed prior to being used by the welders. (See Section 2.9.1.)
This procedure was new to J. & W. and, just as it never appreciated. the
metallurgical difficulties associat,ed V\'-ith low-alloy steel, so it never really understood the
need for meticulous care in the drying of electrodes. It was another example of the
organization failing to rise to the occasion.
53
The packets in which the electrodes are delivered carry instructions for use
including a recommended drying temperature of 150 C. to he maintainetl for lmlf an hour.
It is interesting to note that in experiments conducted by A.J.R. (Ex. 184) it was found
that 350 C. was necessary to ensure that all water was driven off. Although the hot
boxes used by the welders were thermostatically controlled, there was no evidence of any
instruction given to anybody regarding the length of time the electrodes should be in the
box before being used. Since adequate drying of the electrodes is essential for avoiding
cracking in welds, any failure in this respect could have been an important contributory
cause of the failure. If the electrodes used for the welding of the cover plate ends were not
effectively dried, and used whilst in tlle dry condition, they could have been a cause of
the toe cracking which developed at the transverse weld at the end of the cover plates.
The vV.14 girders were fabricated towards the end of the contract, i.e., October, 1960, by
which time, it might be thought, all the essential technical controls would have been
established. However, about this time Clarke mentions in his diary a number of occasions
when he found it necessary to request J. & vV. supervisors to collect odd electrodes lying
around and return them to the hot box. The fact that he made a note of this is an
indication that J. & W. personnel were not seized of the necesRity for attending
scrupulously to this matter.
As against the record in Clarke's diary the evidence of all the J. & W. witnesses,
and Ward (Murex), was to the effect that electrodes were properly treated. However,
Ward left J. & \V. about April, 1960, and we strongly suspect that after his departure,
by the time Clarke made the notes referred to above, the treatment of electrodes had
become somewhat lax.
We are compelled to the opinion, therefore, that laxity in shop organization in the
treatment of electrodes may have contributed to the failure of the bridge.
In so far as the weldability tests were carried out, the quality of the weld metal was
invariably satisfactory, and we are quite satisfied that the electrodes per se played no part
in the failure of the bridge.
2.9. Welding.
2.9 .1. The characteristics of a weld.
vVhen two pieces of steel A and B are to be welded together, this can be done either
by a butt weld or a fillet weld. This latter type, shown at C in Fig. 1, will be used to
illustrate the characteristics of welds as it was this kind which was concerned in the failure.
The weld shown is a three-bead weld. No. 1 bead is the root run. It is run first and
subsequently is covered by and partially incorporated in the two subsequent runs. In
a similar way the second nm is partially incorporated in the third run. It is an essential
feature of a satisfactory weld of this kind that the first run shall fuse into the two plates
and that the subsequent runs shall fuse into the first run and into one or other of the two
plates. In this way there is formed a continuous metallic union between A and B. Each
run or bead is laid down by striking an arc between an electrode and the work being welded.
The steel electrode melts and provides the metal of the weld. In general, it is of a different
composition from the plates being joined.
\Ve thus get two plates A and B, knO\vn as the parent metal and C, the weld metal.
Although A and B difl'er in chemical composition from C, the physical properties should be
very similar, so that there is a "bridge., between A and B which will behave under stress
as though the whole was continuous.
There are, however, some physical differences between the parent and the weld
metal. It is for this reason that the composition of the weld metal is different. Since the
latter is placed in position in the molten state it has the characteristics of a casting-in
particular the grain size is very coarse. The two plates, which in the ingot stage were in
a similar condition, have been hot rolled. This has had two major effects: (a) the crystal
size was considerably reduced and (b) the plate acquired a laminated structure due to the
elongation of segregates. This kind of structure is highly developed in low-alloy steels
of the B.S. 968 type. In effect, the molten electrode is "cast " into a cavity made in the
parent metal by the high temperature developed in the electric arc, and the heat developed
is sufficiently intense to melt also part of the parent metaL
54
From this brief description it will be evident that in the immediate vicinity of a weld
there is a sharp temperature gradient. The molten steel produced has a temperature of
about 1,700 C., whilst the parent metal may be at ordinary temperatures, or if it has been
"pre-heated" it may be, say, 200 C. Over a short distance there is a fall of about 1,500 C.
This is the heat affected zone (H.A.Z.) of the weld indicated by shading in Fig. 1.
The kind of difference in hardness which can be expected with B.S. 968 is a follows (hardness
expressed on Vickers Diamond Pyramid scale) :-
Parent JJ!Ietal Heat Affected Zone Weld Metal
180/200 300/500 200/250
There is another effect of the temperature gradient. When heated, steel expands,
and if this expansion is resisted by reason of the fact that the hot zone is surrounded by
steel at a lower temperature, a eompressive stress will arise which will deform the hot zone.
On cooling, this same zone '"'ill try to return to its previous dimensions. The return will
also be resisted and this will cause a complex stress pattern in the neighbourhood of the
weld. (See Sections 2.6.2.1. and 2.6.2.2.).
The heat-affected zone, being harder than its surroundings, is more brittle and is,
therefore, not so amenable to sbress relief by yielding as is the surr01mding metal.
To this situation a third element is added if the welding is done under conditions
where hydrogen can be generated in the arc. This condition is found when the flux
covering contains hydrogen or when the flux covering is not dry. Thus, for this project,
a "low-hydrogen electrode" was used, i.e., one containing little combined hydrogen in
the flux. It \vas, however, essential to dry the electrodes immediately before using.
If hydrogen is liberated in the arc, it is absorbed by the molten metal and some of
it remains dissolved in the solid. As the weld metal cools, the solubility of hydrogen in
the solid steel decreases, and some of it diffuses into the H.A.Z. which thereby becomes
saturated. As cooling proceed!'! this zone reaches a temperature range (4000 C. to 200 C.)
in which it transforms to the low-temperature condition. During this transformation
hydrogen is expelled from solution since it is less soluble in the low-temperature state.
It is this expulsion of hydrogen which sets up very localized internal stress, causing cracking
in the relatively hard and brittle heat-affected zone. It is considered that a hardness of
350 (V.D.P.) is the maximum permissible to avoid H.A.Z. cracking.
This was at fir:::~t adopted by C.R.B. It control:::; the quality of electrode:::~ to be used
by cross-reference to B.S. 2549: 1954, and abo lays down details relating to butt and fillet
welding.
In an Appendix (c) details are given relating to the various factors which prescribe
the welding conditions using low-hydrogen electrodes to produce crack-free welds. Charts
show the relationship between gauge of electrode, run length per electrode (butt weld)
t~ize of fillet, thermal t~everity of the joint and the neces8ary pre-heating temperature.
Earlv in 1959. i.e., before fabrication had commented. C.R.B .. J. & \V. and Utah
agreed to sl'Ibstitute for B.S. 26,12, a brochure produced by B.\V.R.A. ~ntitled " Arc welding
low-alloy steel ". This was, threfore, used as the welding control guide throughout the
project.
This booklet " is for welding engineers, shop and site supervisors and those
responsible for drafting specifications, and summarizes the practical results of a considerable
volume of research work done by B.W.R.A." It is mueh more descriptive and discursive
than B.S. 2642 and could well have been adopted as a textbook to supplement the training
of welders for this type of steeL
It highlights the features of the H.A.Z. of welds and draws attention to those factors
which affect the formation of cracks. These are listed as :--
Cooling rate of the heat-affected zone-size of weld run, size of joint, temperature
of joint.
Composition of the steel.
Type of electrode.
Stress in the heat-afl~cted zone.
Two methods are then described for determining the " weldability " of any piece
of steel, i.e., the ease of fabrication of a given steel under the imposed conditions available
to the fabricator. One method., and the one recommended, is an experimental one in
which welds are made in a stand:ud way using the actual steel to be employed on the project.
This is called the controlled the:cmal severity (C.T.S.) test. The objective is to determine
those welding conditions which will avoid heat-affected zone cracking, without unduly
restricting the fabricator. The complete test needs three test assemblies using three plate
thicknesses-! inch, t inch, and 1 inch giving joints with thermal severity numbers of 2 to 12,
and the same electrode is to be used as will be used on the project. As a result of this
test a "weldability index" can be allotted to a given heat of steel, and this index, denoting
a characteristic of the steel, can then be used to determine the pre-heat required, using a
57
given size of a given type of electrode. The great advantage of this experimental
approach is that the fabricator learns a lot about the particular features required for tlw
successful welding of this steel. The weldability index is in seven grades designated A to G
with the difficulty of welding without cracks increasing in that order.
Weldability in this sense is largely governed by the composition of the ::;teel and
particularly by the carbon, manganese and chromium contents in B.S. 968. By
experience it has been found that the weldability index can be estimated by using a formula
which takes into account the kno-w'"ll facts that crack-free welding is more difficult the
higher the carbon content and that manganese and chromium can be allotted a "carbon
equivalent " since they act in the same direction but are less potent. The total percentage
carbon plus this carbon equivalent is spoken of briefly as the "carbon equivalent" of the
steel. A relationship has been found between the weldability index as determined from
the C.T.S. test and the carbon equivalent as expressed by the formula. The weldability
of a given steel must be associated \vith a given t,ype of electrode. Since hydrogen is a potent
cause of H.A.Z. cracking the low-hydrogen class of electrodes can tolerate a higher carbon
equivalent than other classes. The correlation between the two methods for determining
the weldability index, using low-hydrogen electrodes is~
Wr:hlability Index Ca.rbon Equivolenl
Percenta{}e
A Up to 025
B 026 to 030
c 031 to 035
D 036 to 040
The booklet points out that the weldability index can be calculated with a fair
degree of accuracy, usually within one index letter, by using the formula. Obviously to
have even this degree of accuracy it is necessary to 1.'1!ow the composition of the actual
plates to be welded. As pointed out (2.7.2.1) there may be an appreciable difference between
the plate analysis and that shown on the analysis certificate from the steelmaker. This
difference could be sufficient to change the weldability by one index letter. The booklet
states that when only the steel specification is available, it must be assmned that the steel
eomposition is at the high end of the permissible composition range. For B.S. 968 this
would mean 023 per cent. carbon, 18 per cent. manganese, and 02 per cent. chromium,
giving, from the established formula a carbon equivalent of 0 34 per cent., near the top
end of the range for weldability index C. The necessity for the fabricator to check the
actual plate analyses for himself is shown in Section 3.4.2 in which it is revealed that
some steel for the Kings Bridge project had a carbon content 0 26 to 0 28 per cent.
Having decided the index, the booklet then describes how to determine the pre-heat
temperature which for a joint of given thermal severity and using a given size run-length
combination of a given type of electrode will give crack-free welds.
Clarke (C.R.B.) had made some abstracts from it in his notebook and this appears
to have been the only source of information relating to the B.W.R.A. booklet which J.
& vV. personnel saw.
It follows that careful inspection of all welds on which the strength of a structure
depends is an essential feature of welding construction.
It is, however, essential that the final structure shall be examined, and for this,
non-destructive methods must be used.
The most obvious method is a simple visual examination of the whole weld, with
perhaps a magnifying glass as a visual aid. This constitutes a first rapid survey and
serves to detect categories of defects under (c) and (d) above, and also some of those
under (e).
It is, however, the hidden flaws covered by (a), (b), and (e) that give rise to the
need for more sophisticated methods of inspection. We need " eyes " which will see what
is below the surface or even what is at the surface though not readily visible. Four main
methods are in use.
The cover plate end weld was a difficult one for instrumental examination, though
possibly the ultrasonic method could have been developed for this purpose. The type
of defect which in our opinion led to the failure, namely, the toe crack in the flange at the
transverse weld, was amenable to detection by the penetrant dye method.
Our views on whether this was used or not are expressed elsewhere. (See 3.3.3.).
But nobody at J. & W. recognized that there was an educational problem involved
in the contract, and so nothing was done in this direction.
The J. & W. inspector and supervisor, Campbell, who gave instructions to the
welders, admitted that he himself had never read the B.W.R.A. booklet and had onlv
copied a table from it out of Clarke's notebook. "
Because of the design of the cover plate it was not possible to complete the welding
to the flange automatically. At each end there was a tapered part which reduced the width
of the cover plate from 14 inches to 3 inches (See Fig 11). These tapered sides and the
bransverse 3-in. end were welded manually generally using three runs. For this work the
Fortrex 35 low-hydrogen type electrode made by Murex was used.
There was no evidence at the Enquiry that J. & W. made any experimental replicas
to determine the thermal severity of this joint. There was, however, evidence that the
end weld was made sometimes before and sometimes after the web was welded to the flange
and further that this important sequence was determined by shop organization expediency
rather than as a result of pre-determined principles. The importance of the web/flange
sequence so far as the cover plate end weld is concerned is two-fold.
(a) The presence of the web weld increased the thermal severity of the
joint in a peculiar way in that an extra heat-conduction path was located
only across the centre of the transverse weld. This increased the
complexity of the internal stress condition. There is evidence of the
increased thermal severity at this location in the A.I.S. investigations
where it is shown that the hardness of the H.A.Z. of the transverse weld
is greater under the web weld than elsewhere-indicating a higher cooling
rate.
(b) The weld, already restrained laterally by the two taper welds, was restrained
in thickness as well if the web was already in position.
The main information relating to cracking during the fabrication lies in two
sources :---
(a) The C.R.B. statistical analysis of details of inspection of the defects in the
main g:i:rders (Ex. 222) ; and
(b) the various reports (chiefly by Murex and A.I.S.) relating to diffieulties
whieh developed during the progress of the contract.
The C.R.B. survey relates to both visual and radiographie examination of the main
fillet welds and butt welds-both automatic and manual.
From this survey we conclude that in the fillet welds there are possibly fifteen
serious undetected transverse cracks and in the butt welds of tension members (flange and
cover plates) there are possibly ten serious undetected transverse eracks. The difference
between deteeted and repaired cracks, and undetected cracks is that the latter are still in
the bridge.
The important question remains, as to whether all cracks were present at the time
of inspection. It is the view of several witnesses (Ferris and Professor H. Muir ineluded)
that weld cracking can occur up to three days after the weld has been made. This time
is determined partly by the welding conditions, partly by the ambient temperature and
partly by the stresses applied to the girder during handling. There is no evidence to
indieate that the C.R.B. inspectors knew of this delayed cracking. It is possible therefore
that cracks formed in some of these welds after they were examined, and these (if any) will
also still be in the bridge.
61
Attention is drawn to the fact that these eracks were not deteeted by the C.R.B.
inspectors, although 35 of them were at the toe of the transverse weld (the remainder were
mostly at the toe of the root weld and so were not detectable by the penetrant dye method).
The M.lVI.B.W. observation raised the previously stated possibility regarding undetected
cracks in fillet and butt welds to the level of strong probability.
TABLE 2.
2 I O.H.S.K . . . .. I E.F. 4
Hi 15 O.H.F.K . . .
'E.F.
2tl 1
I " ! "
2\l .. f
15 .. I ., l
:
2
.. I
E.F. fj
I
50 .. I , .. I .,
.. I , I .. 3
!
Total86
Altogether the lVLM.B.W. has given us results from the examination of 160 cover plate
ends from the suspension girders. We thus have :-
Total ends examined 168. Cracked 86. Not cracked 82, or approximately
50 per cent. are cracked.
The ends containing cracks were made from seven semi-killed open-hearth heats,
one fully-killed open-hearth heat and twelve fully-killed electric furnace heats, and the
composition shown in the related heat certificate is as given in Table 3.
62
TABLE 3.
Analyses of Heats Concerned with Cover Plate End Cracks.
These analyses have been taken from the A.I.S. test certificates (Ex. 20). The
figures in brackets refer to plate analyses made either before or after the steel was delivered
to J. & W. and represent the maximum values reported during the Enquiry.
I I
Heat Type c. i
Mn. Cr. Heat Type c. Mn.
I Cr.
----- .i
NoTE.-The heat analyses show carbon to be in the range from 19 per cent. to 23 per cent. and
manganese from 15 per cent. to 17 pHr cent. If these were a reliable indication of the composition of the steel
supplied it would be an indication thab steel composition could be discounted as a source of welding difficulty.
It will be noticed, however, that wherever the plates as delivered have been analysed there is invariably an
appreciably higher content of carbon and manganese than shown on the test certificate. It would seem therefore
that where composition is critical the analysis should always be checked.
The semi-killed steel hea1is account for 43 of the cracked ends, i.e., 50 per cent. It
will be noticed that three of these heats-Nos. 16, 22 and 29 account for 38 of the 43 cracked
ends, i.e., 88 per cent. This suggests that the steel of these three heats was defective or of
low weldability. It is on record that heats 16 and 22 had given trouble during fabrication
and had been the subject of metallurgical investigation.
However, there is anotheJ: factor to be taken into accmmt. Of the 93 tension flange
plates associated with cover plate ends in suspended girders (Ex. 143) which were made from
open-hearth steel, 77 were from the 3 heats mentioned. If we eliminate these 77 from the
total of 168 we get 91 cover plate ends of which 48 were cracked. We thus have:-
Approximate perceniiage of all ends examined which show cracks .. 50
Approximate percentage of all ends examined which show cracks
other than from heats 16, 22 and 29 .. 52
so that it is evident that the inelusion of the three heats reduces rather than increases the
percentage of cracked ends. \Ve conclude that so far as weldability was concerned the
three heats concerned were nei1;her better nor worse than the others.
Accepting that 50 per cent. of all cover plate ends show cracks of one kind or another,
there is no reason why similar defects should not be found in other than the suspended
girders.
From Ex. 143 we find that there are 187 tension flanges (top) in the cantilever girders.
It is possible therefore that about 100 of these show cracks. rrhey are under the concrete
deck, but we understand that of those examined several have been found to be cracked.
We point out, however, that whilst all cracks in tension members are dangerous,
some are worse than others. From the M.M.B.vV. records we believe that 41 cracks in the
suspension girders were serious toe cracks before they were removed and possibly 50 similar
ones }'emain in the cantilever tension members.
analyses came to light as a result of J. & W. taking action itself. It had plate checks made
early in March, 1960-presumably because of welding difficulties in December, 1959 to
February, 1960. Having got the results, J. & W. was not alerted to the source of the
troubles, in spite of similar reports from Murex about the same time (See letter 5th March,
1960, Murex to J. & W.) showing the analysis of a cracked plate:-
Carbon lli anganese Chromi,um
28 19 38
and from heat 22 . . 24 .. 18 .. 56
Murex warned J. & W. that particular care would be needed with pre-heating
temperatures in order to avoid cracking with material of this type.
The information we have relates to girders fabricated in the thirteen months from
December, 1959, to December, 1960. The cracks are found to be fairly regularly
distributed in girders fabricated throughout the year as follows :-
Cracked Welds
December, 1959-March, 1960 25
April-June 22
July-September .. 19
October-December 20
We find also that the three heats 16, 22, and 29 were used throughout the year.
2.9.6.6. Association of cover plate end cracking with web4lange welding sequence.
It has been mentioned that the transverse weld at the cover plate end, although
only 3 inches long and an easy weld to lay, either by down-hand or vertical-up procedure,
can be difficult to weld without cracking, unless precautions are taken with respect to
pre-heat and sequence. Two sequences were involved-
(a) whether it was laid before the web was welded to the flange, and
(b) whether it was welded before or after the taper welds. Whenever the
questions regarding these sequences was asked in the Enquiry, whether
of K.S.B.D., the C.R.B., or J. & W., we got the same amrwer: "Nobody
gave it a thought, and it \Vas done just when it was most convenient
for shop practice."
Regarding the major sequence web-flange end of cover plate we have some data
in Ex. 89 from C.R.B. records, but the information is not suflicient for us to make a clear
analysis in conjunction with Exhibit 218. 'Ve only know defmitely that on certain girder&
the cover plate end was the last weld to be made. Regarding the minor sequence it seems
that the transverse weld was probably always done after the two taper welds. J.1~rancis
considered that this \vas the worst sequence to use.
Assembling the available data from the M.M.B.W. operation we get the following
result:-
(a) Of the cover plate ends completed with the transverse weld the last to be
made on the girder, approximately 65 per cent. showed cracks.
(b) Of the remaining 67 cover plate ends, for which we have no record of the
web/flange cover plate end sequence, 37 (55 per cent.) showed cracks
and 30 (45 per cent.) were free.
Since about 75 girders had been made before the period covered by this survey,
it is possible that most of the second group above were fabricated by the same sequence
as the first group. In this case we reach the conclusion that the chances in favour of
producing a cracked weld if the transverse weld is the last made was about 3 to 2.
64
2.9.6.7. Cracks which have developed beyond the toe crack stage.
In analysing above the data from Exhibit 218 (plus the additional information which
has come to light since that was tendered) we have not distinguished cracks which have
remained as toe cracks and those which have developed into partial brittle fractures. It
is not possible to do this without making an assumption regarding the average depth of
toe cracks.
In order to examine the question of the general liability of the steel to brittle
fracture we now assume arbitrarily that a crack which is deeper than! inch has propagated
from an initial weld crack. Ex:amples are shown in Table 4.
TABLE 4.
Girder End Heat Depth Location
in eh.
E.3S3 .. .. . . North .. .. .. 29 Ji.
11 Toe
E.14S4 .. .. .. , .. .. .. 50 ,
" "
E.lS4 .. .. .. "
.. .. .. 80 Through ! Toe
Combining this with Section 2.7.6.4 it will be seen that 13 of the 86 welds showing
cracks, have developed into partial brittle fractures. Most of these were from toe
cracks or cracks closely associated with the toe. Seven different heats of steel (including
heats 55 and 56) are involved compared with 23 heats (three of which showed no cracks)
in the cover plate end survey. Another way of expressing this is to say that of 86 transverse
cracks, 73 have not developed into brittle fractures, and as these are distributed through
eighteen heats it is an indication that the general run of steel was sufficiently notch-ductile
to resist propagation of brittle fractures under the conditions to which it had been subjected.
E.T.R.S. undertook to examine cover plate to bottom flange fillet welds of the E.l4
span, and also the manual fillet. welds at the taper ends of these cover plates. The survey
could only be done on a sampling basis as far as the longitudinal welds were concerned.
Four lengths of l foot each were selected on each of the eight welds, and the sixteen taper
welds were also examined. No cracks were detected by the magnetic particle method,
which reveals cracks reaching the surface. The ultrasonic method was then applied
(Ex. 232) and cracks from 4 inches to 15 inches long were indicated in five of the eight
taper welds at the north end, of the girders. The ultrasonic method used was then
checked jointly with D.S.L. on the taper welds of W.l4. As a result (Ex. 237) Hudson
"has little doubt . . that the ultrasonic indications found in the northern end
taper welds of the E.14 series of girders are in fact indications of cracking in the
flange. It is concluded, therefore, that quite extensive timer run toe (or possibly
root) cracking is present in the E.l4 girder flanges under some of the taper welds".
From these examinations and our analysis of the welding defects survey, we
conclude that the cracking at the cover plate ends which we have so carefully examined
throughout our Enquiry, is characteristic of the whole of the welding of this detail in
the bridge and is not a unique feature associated with these particular welds in the W.l4
girders which dramatized the effects resulting from steel quality and welding procedures
because all factors were operating at_ once.
In the present section, the attempt is to paint a picture of what went on during the
progress of the project. In so doing, we have found it necessary to indulge in a certain
amount of recapitulation-not so much, we hope, as to be tedious-but sufficient to convey
an accurate impression of the scene.
Even so, this does not pu.rport to be a complete account of all the matters that
emerged during the hearing but it does, we believe, bring together the most important
matters with which we are concerned.
The design drawings give only the main dimensions and so it was necessary for
,T. & W. to prepare from them a series of shop drawings carrying every dimension necessary
for the fabrication of the girders. These drawings were also checked by the C.R.B.
6352/63-5
66
It is at this point that we see the need for someone who, for want of a better term,
we call a " welding engineer ". We visualize him as a man, skilled both in the technique of
welding and in the art and science of structural design, whose duty it would be to ensure
both that what was being asked. for by the designer could, in fact, be satisfactorily fabricated,
and also that the proposed fabrication procedures would fulfil, or at least not frustrate, the
designer's intentions. We think that the shop drawings should carry a schedule showing
the welding procedures to be .::tdopted at each joint, the order of laying down the welds,
the requ.lxed pre-heat, any special points to be noted by the inspectors and, indeed, all the
details required to carry out i;he work.
Whether or not this be the best way of filling the gap between the designer and the
fabricator, the fact remains that in this case nothing of the sort was attempted with the
results described below.
The evidence of Ralston and Thompson led us to think that the decision not to accept
an order including the extra requ.lxements of the C.R.B. specification (i.e., additions to
B.S. 968: 1941) had been made at too low a level in the organization. However, after
seeing a letter of 25th August, 1959 from the General Manager, Newcastle Steel works, to
the Managing Director, B.H.P.J and other communications in Exhibit. 204, we realize that
the policy of not accepting additions to specifications had been discussed at higher levels.
\Ve also conclude from these internal communications that the full requirements of the
O.R.B., in this connection, were quite well known and appreciated, though the witnesses
we heard gave the impression that the full specification had never been received by B.H.P.
This was not a minor matter : what was involved was a specification for an important
metropolitan highway bridge in a capital city with difficult traffic problems, and the
designers of a public authority had decided that it was necessary to protect the bridge from
possible failure by brittle fracture.
Brittle fracture had been before the public eye in connection with welded ship and
other failures and the views of the O.R.B. engineers merited discussion rather than categorical
rejection. This situation is not; unconnected with the type of contract which was drawn
up for this project. It is evident that, as the C.R.B. reserved to itself the final approval
of the steel, there should have been a much closer association between O.R.B. and B.H.P.
in these matters.
It is quite clear to us that J. & \V. had unlimited faith in B.H.P.'s ability to supply
satisfactory steel for the project. To tell such a fabricator, knowing that it had no
metallurgical department to use as a check, that Izod testing of this steel was, to all intents
and purposes, wasting time, was to play on its faith, and to confirm it in an attitude to
testing in general which we now know to be characteristic of J. & W. The issues were
much larger than could be dismissed in this way, although we appreciate that J. & W. was
told in good time (i.e., before tendering) that the steel could not be guaranteed to pass the
stipulated Izod test. However,, we also appreciate that having ordered to one specification
and contracted to another more stringent one, J. & \V. could have been left to sort out
material which would pass the O.R.B. specifications from among what was received.
Before leaving this matter of policy on notched bar testing we must point out that
U.K. steehnakers had given a great deal of attention to the brittle fracture problem in the
early 1950's; much research effort was directed to the theoretical and manufacturing
aspects of the problem. One firm made a statistical analysis of 60 heats of steel, relating
the rolling conditions to the notch ductility by applying the Charpy test to determine the
ductile/brittle transition range for several thicknesses of bar.
67
Om views on the lack of this type of technical research are based on the opinions
and attitude of witnesses for B.H.P., not one of whom suggested that such work had been
done or had ever been contemplated, and who were rather on the defensive to prove that
the B.H.P. attitude had been a correct one.
We will endeavour, therefore, to sort out those aspects of the steel supply which
relate to general company policy (B.H.P.) from those which relate to the particular plant
where the steel was produced. (A.I.S., Port Kembla).
We assume that this decision was related to technical considerations associated with
the characteristics of the two plants and this matter is of no concern to the Commission.
We do not know whether the steel would have been better if it had been made at Newcastle
and we simply observe, as has been mentioned before, that the practice of the two plants
was not the same.
The second general matter~that the company would not undertake to produce
steel to the full C.R.B. specifications-has already been discussed in Section 2.10.2.
Finally we come to some questions of B.H.P.'s relations with its customer which
we presume to be company matters and not specific to the plant producing the steeL
On several occasions during the project J. & vV. were in difficulties of several kinds
relating to defects which developed in welding. Port Kembla officers on such occasions
made helpful investigations and suggestions. At one stage, they even offered to send
expert welders to J. & W. to demonstrate what they considered to be proper techniques.
J. & W. did not accept the proffered help, apparently because in the meantime Ward
(Murex) had been seconded to it for this purpose.
There was one matter which was apparently decided at too low a level. This
related to C.R.B. heat 22, which was first mentioned in correspondence from J. & vV. to
B.H.P. early in 1959; this was an open-hearth heat to which chromium had been added.
In the investigation report of 12th March, 1959 no mention was made of chromium but it
was suggested that material from some other heat might have been inadvertently delivered
with heat 22. However, in the report which went to J. & vV. (16th March, 1959) this
information was not passed on. The same heat gave welding trouble during 1959 and on
18th }larch, 1960 there was a further report from Port Kembla in which it was revealed
again that some other heat had been mixed with heat 22. Chromium was now mentioned
as it had been found by the consulting chemists, Sharp and Howell, to whom J. & W. had
submitted samples for analysis. The cryptic comment is made in this report : " To
completely eliminate the (mixed) material it would be necessary to sample each bar
marked 267607 (C.R.B. 22) and analyse for chromium content".
68
. Again the evidence is that this information was not passed on to J. & W. We are
therefore faced with an established fact that wrong material, which was not covered by
the test certificate, had been sent to the fabricator. This possibility of mixing is well known
in any steel mill. When it is discovered, every effort should be made to trace the wrong
material, particularly in an important project like Kings Bridge. It was the plain duty
of B.H.P. to check every plate of this heat for J. & W., but it did not do this.
~We point out (Ex. 143) that there are 35 girders in the bridge in which heat 22 ha8
been used for tension flanges at locations involving cover plate terminations.
but it is not satisfactorv for B.H.P. to say that, "We told J. & W. of these tolerances".
J. & W. was known not"to have a metalhirgical department and was therefore not likely
to--and, in the event, did not--establisL a. set of check tests on the plate as received.
We think, in fact that the practice of B.H.P. in providing metallurgical service
for its customers, may have had the effect of causing fabricators such as J. & W. to rely
too much on them. In the long run B.H.P. can give better service by encouraging its
customers to set up their own service departments. If this were done the valuable
information given by B.H.P. would fall on more receptive ears and better informed
minds.
This concludes our survey of those aspects of general B.H.P. policy which would
apparently have applied equally to both the Newcastle and Port Kembla steel plants.
However, we would point out that like many other matters at our Enquiry these matters
do not fall into neat classifications. For example, whilst there was a policy relating to
composition tolerances, the individual plant personnel determined what influence this should
have on their practice and what limits they would adopt to obtain the specified physical
properties.
Certificates from Newcastle that we have seen carry a printed column in which the
chromium content can be entered; we were told that this was because Newcastle regularly
manufactures alloy steels.
The only exoneration we can find for the steelmaker m this respect Is that it
followed an established convention.
Another feature of the steel supply, which has been mentioned earlier and which has
given the Commission considerable trouble to understand relates to the decision of A.I.S.,
early in 1959, to change from semi-killed open-hearth steel to fully-killed electric furnace
steel. This was represented to us by Ralston and Thompson as an attempt by A.I.S. to help
,J. & W. out of their contractual difficulties with respect to the C.R.B. specification. This
view was confirmed in a letter of 8th February, 1961, from General "!\1anager, Port Kembla,
to Managing Director, B.H.P. which reads as follows:-
"Because of the severity of the C.R.B.'s requirements, accepted by J. & W.
but not ourselves, it was decided, in an effort to assist J. & ~W. to meet the C.R.B.
demands, to produce the steel in the electric furnace. \Ve have since produced
B.S. 968 heats in the open hearth to the satisfaction of various customers but
would no doubt encounter similar difficulties again if requirements additional to
B.S. 968 were imposed.
We would emphasize that J. & W. were told quite definitely that we were
not prepared to accept requirements over and above the B.S. 968 specification.
However, J. & W. encountered some difficulty in fabrication through failure to
observe eorrect welding practice for this grade and this did not assist them in the
over-all problem of dealing with the C.R.B.
It would be true to say that our reason for manufacturing this material in
the electric furnace was attributable to the severity of the Board's requirements
and our desire to assist J. & W. as far as possible in meeting those requirements.
70
The failure and rejection of a full open-hearth heat on the basis of the
C.R.B.'s tests would have disrupted deliveries far more than the failure of a single
electric furnace heat. We were also forced to narrow our specification range
and this was more practical in the electric furnace.
We also refer you to the other reasons quoted to you in our letter dated
15th January, 1960."
If these were the main reasons for the change, they represented a belated change of
view on the part of the Port Kembla staff, and an admission that they were under some
obligation to help J. & W. to meet the C.R.B. requirements. It was, however, a curious
decision. The change to fully-killed steel was likely to result in improved notch ductility,
but up to this time no difficulty had been found in this respect with the semi-killed open-
hearth steel being supplied. What was really needed by the fabricator was an improvement
in weldability and this required a lowering of the carbon and managanese contents.
However, two of the " submitted heats " (55 and 56) were on ladle analysis at the maximum
for carbon and two others (58 and 59) only 01 per cent. below it. In addition 0 25 per cent.
chromium had been added. Several of the heats examined since the failure have shown
carbon contents between 025 per cent. and 028 per cent. In fact there was a marked
deterioration in the properties of the steel (See Section 2.7.2.3.), both as regards notch
ductility (in some heats) and weldability in general.
The first intimation that any change had taken place appeared in a letter of
27th February, 1959, from A.I.S. relating to the "submitted heats" (See Section 3.4.1.),
in which it was stated that " tesi; failure occurred in a number of fully-killed electric furnace
and open-hearth heats".
As the change took J. & W., Utah, and C.R.B. by surprise it is evident that A.I.S.
took this decision entirely independently, although neither the C.R.B. specifications nor
B.S. 968: 1941, mention electric furnace steel. When J. & W. referred these "submitted
heats" to the C.R.B., the latter consulted Ferris and Hudson who both considered that the
change should result in an improved steel whieh could be accepted if it fulfilled all other
requirements. We now know that, far from ensuring that the requirements were fulfilled,
the C.R.B. relaxed testing at this time.
The change to smaller heats led to Eastick and the C.R.B. deciding to resort to
"random" testing of heats. (Bee also Section 2.7.2.3.). . Eastick felt justified in this
because of the verbal assurances from Ralston that fully-killed steel would be more ''notch
tough", and up to this stage, the heats of open-hearth steel had passed the applied tests in this
respect. The still better performances that he had been led to expect seemed to Eastick
to be good grounds for relaxing the frequency of testing.
71
In view of all the circumstances we conclude that the decision to change from open-
hearth semi-killed steel to electric furnace fully-killed steel was largely determined by
internal considerations at Port Kembla. In particular, it was to reduce the amount of
diversion of steel which did not comply with the requirements of B.S. 968: 1941 and had
little to do with the extra tests required by the C.R.B. specifications.
We consider that the change in steel making practice early in 1959 was detrimental
to the quality of the steel supplied, and was a direct cause of the failure in that the tension
flange plates in the failed girders were made from steel in heats 55 and 56 which were both
made in the electric furnace.
Several of these tests have already been discussed but there remain a number of general
matters which require consideration.
The question of whether the steel should have been inspected before it left Port
Kembla was discussed before us at some length. It transpired that Ferris advised Wilson
to get Lloyd's Register of Shipping, Land Division, to inspect the steel at the steel works
and that Wilson discussed the matter with Butler who, in turn, asked for the Board's
direction. Butler's letter (Ex. 32) includes the sentence "It would appear doubtful whether
the Board would benefit by 10s. per ton" (a reference to the cost of Lloyd's inspeetion)
and carried the following handwritten note signed by Wilson : " This was considered
verbally by the Chief Engineer and/or the then Chairman and not agreed to. There is no
official written record". However, the C.R.B. apparently did >vrite in 1960 to suggest
the use of Lloyd's inspectors but J. & \V. refused and the matter was not pressed.
\Ve are quite clear that it would have been far better if the steel had been
unambiguously identified, tested, and cleared for despatch by an independent inspector at
Port Kembla works. As it was, the steel was only inspected and tested after delivery and
the first requirement of a testing programme, proper identification of the specimens, was
not satisfied. This not is an easy requirement to fulfil ; one piece of steel looks very like another
and it is, therefore, important to have very systematic arrangements for stamping heat
numbers on specimens and for recording the results. It must be realized that it was
intended that " two tension, two cold bend, and two impact tests shall be made from each
size of section or plates rolled from any one heat of steel or identifiable batch from stock "
(Clause 2-3-15.); and that four bend tests, two tensile butt-weld tests, four impact tests,
and a macrographic test were required for weldability (Clause 2-3-16 (f)). This was a
formidable programme to organize and carry out. It was never fully implemented and
was ultimately relaxed.
In practice, the specimens were machined by J. & W. and tested by E.T.R.S. or at
Royal Melbourne Technical College in the presence of Scarlett and J ackson. A curious
feature of the testing was the procedure adopted for retesting failed samples. The
specification is tmambiguous : Clause 2-3-15. states that "should any of the test specimens
first selected not fulfil the test requirements for the material being tested, two additional
specimens of the type which did not fulfil the test requirements shall be taken, and should
either of these fail to fulfil such tests, all the material so represented shall be rejected."
It is perhaps not surprising that J. & W., having accepted the material from B.H.P. before
the tests were made, took the view that what did not pass the first time would pass if it
was tested a sufficient number of times; but it is indeed very surprising that the C.R.B.
concurred.
On the other hand, tests are not prescribed without reason. Quite apart from their
discriminatory value-to reject faulty material-they can be an invaluable guide to
production. B.H.P. knew this and in actual fact carried out, for its own purposes, many
more tests than it reported (See Ex. 186) ; but J. & \V. did not realize that the weldability
tests, if intelligently used, could have helped to determine fabrication procedures. Instead
of this it was constantly pressing the C.R.B. to relax the testing programme.
72
'While we do not regard the matter as of crucial importance we think it is
symptomatic that many of t:h.e Izod tests at the higher temperatures were tested at
"ambient temperature" and not at 70 F. as specified. With this steel the Izod value
changes rapidly with temperature and so a few degrees up or down can make the difference
between success or failure.
In some heats (e.g., 1, 4, 9; see Sec. 2.7.2.3.) the Izod value at 32 P. was higher than
that at the upper temperature ; this can only be explained if the samples were wrongly
identified or the tests improperly conducted or recorded, or if the steel was very variable.
The specifications are not absolutely clear on the point although it certainly seems
that the intention was that the steel should have been inspected before it left the maker's
works (See Clauses 2-3-16 (h) and 2-3-25.). Further it was not to be despatched from the
maker's works or stock until U1iah had certified that it complied with C.R.B. specifications.
The C.R.B. also had ample powers to ensure that the steel was fully tested and approved
before it was used (Clause 2-1-l.). In spite of all this, J. & W. insisted that it was nothing
more than a "commercial risk" to use steel before it had been tested and Eastick apparently
did not insist.
'Ve have most difficulty of all in understanding the decision to change to "random"
testing. The average tmmage of steel per heat was not greatly reduced (See Section
2.7.2.3.) by the change to electric furnace production although everyone expected the new
process to give better control of steel-making. But if it was essential to reduce the number
of tests, selective tests on samples shown by the certificates to be high in carbon and
manganese should have been chosen, and the "submitted heats" should have been
thoroughly tested.
All the matters mentioned above illustrate the advantages that could have been gained
from the presence of a competent metallurgist in J. & W.'s works. In particular, we
again draw attention to the reckless way in which the "submitted heats" were accepted;
the importance and significance of this matter could not have escaped a metallurgist.
We summarize our views on the inspection and testing of the steel as follows :-
J. & W.---
(a) having failed to order the steel to C.R.B. specifications failed to inspect
it properly prior to fabrication ;
(b) was under press1rre from Utah to complete the fabrication and erection
of the girders on time and, in turn, constantly pressed C.R.B. to relax
testing;
(c) did not understand, and had no respect for, the importance of a sound
and comprehensive testing programme.
C.R.B.-
(a) did relax the i:utensity of testing without proper thought;
(b) did approve steel which did not come within its specification;
(c) did not apply its full rights as to testing.
As a result of all this, several heats of steel were accepted that should have been
rejected.
It soon became apparent to J. & ,V. that without outside help it would never succeed
and so Ward of l\iurex was installed " to put their house in order ". It was not at all easy
to obtain, train and examine enough welders to keep the work rmming smoothly but we
think that this difficulty was eventually overcome. We formed the impression that the
welders who came before us could, with proper direction, have done a first-class job.
73
We do not think that instructions were given to the men in a satisfactory manner;
indeed we never really found out what, if any, was the system in use. It appears that the
calculation of the neeessary pre-heat was a very haphazard business, to say the least, and
the pre-heat temperature eventually reached the men by word of mouth. This in itself is
not necessarily reprehensible but proper records should have been kept so that the reason
for any faults subsequently detected might have been traced.
The following extract from " Memorandum on Faults in Arc Welds in Mild and Low
Alloy Steels", published by the B.W.R.A. in 1950, is of interest in this connection:-
" Full information as regards weld sizes and details, plate preparation,
assembly and fit-up, welding procedure, sequence and so on should be given on
the drawings, or by separate charts or other suitable means, to ensure that the
works staff is fully conversant with the requirements of the drawing office, and
of the planning or production departments.
During fabrication, all welding should be carried out under coiL.<>tant
supervision, by welding operators trained and tested to weld 1mder conditions
and on the type of welds appropriate to the class of work on which they are employed.
It is advisable that identification and record systems be used by which
responsibility for the execution and supervision of welding can be established
at any tinw during or following completion of the work ''.
On the other hand the excellent records kept by C.R.B. have been of great value to
U8. They have enabled us to learn the heats of steel incorporated in every girder of the
bridge, and the welding sequence used in most cases. Unfortunately, on the transfer of
C.R.B. to new headquarters, records relating to the work of individual welders were destroyed.
Had these records been available we would ha.ve known which \Velders had made the welds
which failed and some of the doubts we have on procedures used could have been resolved.
'rhe fabricators kept no such records.
In Section 2.9.3. we have dealt with the question of pre-heat. We were told that
J. & W. would have preferred to use bigger electrodes and heavier currents but this matter
was never properly explored with the C.RB.
Metallurgical opinion is unanimous on the importance of heat in-put but, on the other
hand, we have evidence that some experienced fabricators like to keep the initial temperatures
as low as possible consistent with the prevention of weld cracking. This is not just a matter
of expense although the cost of pre-heating is not negligible ; nor is it that a good rate of
production may be maintained. The aim is rather to reduce both distortion and the
production of high residual stresses. 'Ve do not presume to adjudicate on a matter that is
doubtless only to be resolved by careful compromise. But we whole-heartedly agree with
Eastick's view that if J. & ,V. had spent the period between the award of the contract and the
beginning of fabrication in systematically investigating these matters and preparing
themselves for the job the whole history of Kings Bridge would have been different.
Experiments conducted during the Enquiry have cmrvinced us that the determination
of the proper welding procedure for the various girder joints in this steel is not at all easy
and merits n:mch more careful study than was possible once fabrication was under way. The
method used by J. & W. was just not good enough, especially when the steel delivered was
as high in carbon as eventually turned out to be the case. The culminating point was
reached when, towards the end of the contract (September, 1960), for reasons that are not
clear, the "weldability index" was lowered for a few weeks. This meant that the pre-heat
temperature would be lowered. It was apparently during this period that theW. 14 girders,
which eventually failed, were fabricated. As we now know, the carbon content of these plates
was exceptionally high so that the pre-heat temperature should have been raised rather
than lowered. We consider that the resulting inadequate pre-heat was one of the causes
of the toe cracks at the cover plate end weld8 in the failed girders.
Two further illustrations will suffice to demonstrate .J. & W.'s tmpreparedness to
undertake the contract : if pre-heat is to be used properly the temperature of the steel must
be checked but J. & W. welders had no means of doing so. It was only when Clarke told
74
them about temperature-sensitive thermocrayons that they were able to check pre-heat
temperatures at alL Finally, in this context, we refer again to the fact that it was only
on Ward's advice that J. & W. installed hot boxes in which to store and dry the electrodes
before use.
We now turn to the incident of the 500-ton press, which occupied more time at the
Enquiry than it deserved, but which does illustrate rather vividly the attitude of some of
the parties. It came to light only because of the rather underhand activities of Fisher
who had been installed by Utah in the J. & W. works as an observer. We do not think
very highly of Utah for this manamvre, even though Fisher apparently went beyond his brief
in his enthusiasm to detect and. report any misdemeanours on the part of J. & W., and we
commend Bonwick for putting the arrangement on a proper basis.
It seems that J. & W. was having difficulty in ensuring that the camber of the completed
girders was in accordance with the drawings. It occurred to Stocker that if he were to
subject them to a suitable force in a big press he eould bend them into the correct shape.
C.R.B. was asked for its approval but, before this was received (complete with a number of
precautions that were to be observed), Stocker conceived the idea of a private trial by night.
The idea was, no doubt, that if it succeeded C.R.B. would accept the procedure as having
been justified by the result. No measurements of the strain were made, nor any thought
given to the consequences of cold work on steel of this kind, but apparently the attempt
was abandoned before it went very far.
The question of the inspection of the girders by C.R.B. is discussed in Section 2.10.6
below and we now turn to the attitude of Utah to the difficulties encountered by their
sub-contractor. "\:Ve are not concerned here with the question of legal liability, but simply
with whether Utah should have intervened or could have done so to good effect.
In actual fact they did practically nothing beyond transmitting letters from C.R.B.
to J. & W. and vice versa. They did take action, on occasions, to try to iron out differences
but they were deliberately careful not to become closely involved themselves. Having
awarded the sub-contract to J. & W. who were, so far as anyone knew at the time, competent
and experienced fabricators they left them to get on with it.
The Utah engineers concerned were :Fink and Bonwick, whose work in this context
was described as follows : " The most important thing as far as we were concerned was
to administer the sub-contract in respect of payment, measurement of work, timing of
when girders were going to arrive, scheduling, programming, and so on, and give them
any technical assistance we coU:ld give them if they asked for it ".
75
The incidence of cracks at the cover plate ends is described in Section 2.9.6.1 et seq.
but the question of whether this location, which is now known to have been of critical
importance, should have been the subject of a special examination remains to be discussed.
We think that they should have been picked out for special examination by the
C.RB. when the intensity of inspection to be imposed was being settled.
We do not agree with this view. Any .system of inspection that is not 100 per cent.
complete involves selection and among the criteria for selection must surely be the possible
consequences of a crack remaining undetected. As soon as this has been said it becomes
obvious that transverse cracks in tension flanges must be sought with special care and
eliminated.
The final inspection apparently often took place with workmen swarming over
the girder putting the finishing touches to the work. It seems that J. & W. insisted that
production should not be delayed because inspection and testing were incomplete and
maintained that any defects in the girders would eventually be corrected; they regarded
it as merely a commercial risk that this might involve removing completed girders from
the bridge. As a consequence the final inspection was carried out in very unsatisfactory
circumstances and it is quite likely that the cracks which eventually caused the bridge
to fail were missed for this reason.
We hardly know whom to blame the more, J. & W. for its cavalier attitude or C.R.B.
for putting up with it.
We now propose to consider in detail the nature of the failure, using the information
acquired during the Enquiry, including the results of the former Committee of Investigation
and the investigations which have been made for us by the Defence Standards Laboratories
and the various parties concerned.
Fig. 3 shows a typical cover plate end transverse weld. It can be seen that the
fracture in the flange starts at the toe of this transverse weld, of which two of the three weld
beads can be seen. The root bead is of course covered.
Figure 4 shows the longitudinal weld of the cover plate to the flange and the welding
at the end of the cover plate. It can be seen that the taper weld started after gouging
back 3 or 4 inches into the longitudinal weld. Two weld beads are evident.
Figure 5 shows in more detail the nature of the fracture in W.l4-2 at the south end.
From the bottom is seen-
(a) the cover plate and two of the transverse weld beads.
(b) a dark area which in effect is composite. First the toe crack about l inch
deep, then a primary brittle fracture, rusted, and terminating at the
two web/flange fillet welds showing that these welds arrested the first
fracture.
(c) The web/flange welds.
(d) The web and flange secondary brittle fracture (rusted).
We consider this girder fractured through the flange to point B. (i.e., 44 inches up
the web) in Fig. 2, months before the final collapse, because it was the only fracture which
was rusted.
In trying to fix the time for this fracture we have several significant features :-
(a) There is no indication of the final coat of paint which was applied during
January, 1961. This coat, having an aluminimum base was readily
distinguishable, and was in fact found in at least one fracture (W.l4.-3
south end). There is little doubt also that the fracture would have been
so obvious that the painter would have noticed it. Nobody has
mentioned this to us.
(b) The surface of the fracture is rusty. It is considered that this would
have required several months to reach the condition noted at the time.
80
(c) The fatigue fracture at B. {Fig. 2) indicates a response to traffic loads because
of the presence of characteristic markings showing the progress of fatigue.
{d) The temperature at the time of the failure (11 a.m. lOth July, 1962) was
about 45 F. following a minimum of 36 F. during the previous night.
The only lower temperature to which the bridge was subjected was in
1961, when a minimum of 33 F. was recorded in July.
The only definite limits for the time of fracture of W.l4-2 are therefore January,
1961, and July, 1962, with a possibility, judging by the rust and the low temperature that
it occurred in July, 1961. It is possible, therefore, that this fracture was present on
18th October, 1961, when the bridge was taken over by M. & M.B.W. If there had been
an inspection this fracture, if present, would have been noticed.
\Vnen the actual fractme is examined it is evident that the progre~:>s of the fracture
up the web took place in several stages.
3.2. The Condition of the W.l4 Span just prior to the Collapse.
Before considering the failure in detail, and trying to trace the ultimate causes, it is
appropriate to describe the condition of the failed span, and in fact of the whole bridge as we
now know it to be. This is illustrated by reference to Fig. 6. 'he following features are
noted:-
(a) At all seven cover plate transverse welds where the main fractures were
found there was a toe crack about ! inch deep x 3 inches long.
(b) Red primer paint had penetrated six of these toe cracks.
(c) In the following positions the toe cracks had developed into primary brittle
fractures which had passed through the flange plate: W.14-1 (south),
W.14~2 (nor1;h), W.14-3 (south), whilst at W.l4-2 {south), a similar
fractme had developed but had been arrested by the fillet welds at the web.
(d) Red primer paint had penetrated three of these brittle fractures from the
top side of the flanges: W.l4-l (south), w.l4-2 (north) and W.l4-3
(south).
(e) The final coat of nluminimum paint penetrated also the primary brittle fracture
in W.l4~3 (south) from the top side of the flange, showing that this fracture
had broken through the primer coat, and the second coat of paint which
was applied after the girder had been erected. This means that this
fracture was opening up under traffic loads before January, 1961.
(f) Sometime after ~fanua.xy, 1961, i.e., after the final coat of paint was applied,
the primary brittle fracture at the south end of W.l4~2 passed through
the two fillet welds which had first arrested it and stopped 44 inches up
the web, leaving only a few inches of the web intact. The primary
brittle fracture at the south end of W.l4-3 about the same time spread
4 inches up the web. It is suggested that these extensions occurred
during the winter of 1961.
(g) During the succr~eding year the south ends of W.l4--2 and W.14-3 were
flexing under traffic loads to an extent which resulted in fatigue fracture
developing for about t inch further up the web in each case.
In addition the north end of \V.l4-2 had a fracture 1 inch up the web as seen in
Fig. 7.
It can be seen, therefore, that during the twelve months from about July, 1961, to
July, 1962, these two girders (W.l4--2 and W.l4--3) were carrying no appreciable part of the
traffic load.
'fhe ultimate collapse of this span was therefore inevitable for the condition was
getting continually worse due to the presence of fatigue fractures in these two girders.
These points are mentioned, not because they had any direct connection with the
failure, but in order to indicate that the condition which caused .span W.14 to collapse is
not by any means unique in the structure a.s a whole.
It will therefore be seen that a complex set of circumstances was involved and we
have no means of sorting out the part played by these factors other than by trying to interpret
the evidence.
We have reason to think that at the time these W.14 girders were fabricated there
had been a reduction of pre-heating temperatures. J. & \V. was never impressed with the
need for pre-heating and at the end of September, 1960, it issued instructions for the weldability
index to be lowered. This meant a lower pre-heating temperature. As previously mentioned
(Sec. 2.7.3.) the .steel u.sed for these girder :flanges was out of specification-being high in
carbon. The pre-heat temperature .should therefore have been raised, rather than lowered.
The electrode used for the manual welding of the end of the cover plate was a low-
hydrogen electrode Fortrex 35 designed for welding low-alloy steel. It has been established
that the welds were actually made from such electrodes. The maker, however,
recommended that such electrodes be " stored in a warm place and re-dried at 150 C. for
30 minutes immediately before use". The object of this wa::; to remove any mo:h<;ture which
may have been absorbed from the atmosphere.
There is evidence that about the time the W.14 girders were fabricated there was
some slackness regarding the shop practices relating to electrodes. This is one of the
features of low-alloy steel welding which J. & \V. had to take into account for good fabrication.
It had not been used to this refinement but it was introduced by \Vard of Murex in 1959.
Our reasons for thinking that this may have had a bearing on the failure are as follows:-
(a) Clarke (C.R.B.) in his diary mentioned several occasions in September and
October, 1960, when he issued warnings about electrodes not being tidied
up and welders using cold electrodes.
6352/63-6
82
(b) At no time during the Enquiry ha::> J. & W. mentioned for how long the
electrodes were heated. \Ve presume therefore that this feature of the
welding was left to the judgment of individual welder~>.
(c) With a view to assisting the Commission, A.l.S. carried out some experiment::>
in which it was indicated that all moisture was not driven off from the
electrodes until a temperature of 350 C. was used.
The importance of this drying is that moisture from any source decompo::>es in the
welding arc and releases hydrogen which is absorbed by the weld metal. This is one of
the most important causes of the type of cracking fOlmd at the toes of the transverse weld.s.
It is in this connection also that the " fit " of the plates being welded is of importanee.
The gas used for the pre-heating burners wa~:> either aeetylene or propane. Each of these
produees water which at first condenses on the cold metal, hut evaporates as the temperature
rises. If there is a had fit, water can condense between the two plates. This could be
a source of hydrogen. We considered this as a possible cause of the failure, hut finally
rejected it for the following reasons :-
(a) This source of hydrogen could only affect the root weld head whereas the
toe cracks ea using the fractures occur at the second head run, i.e., after
all access to any cavity between the plates had been closed.
(b) The fit of the pla.tes at W.l4-2 (south end), where the first failure occurred,
was particularly close.
Cracks are caused by loeal stresses acting on material which is too brittle to yield,
or which is restrained from yielding because stresses are acting in several different directions.
These stresses are due to the eontraetion during cooling after welding and are said to be
"internal stres~>es" because they develop inside the weldment without any external load
being a pp lied.
These W.14 girders were fabricated in such a way that there was a maximum of
re~:>trai:nt
on this transverse weld. It was, in fact, the final weld done on the girders. It
was restrained by the two tapeT welds at the end of the cover plate and by previous weld~>
rUlllling at right angles to it on t;he opposite side of the flange plate, i.e., the web/flange welds.
No record is available for many of the girders, particularly those eonstructed in the early
stages of the eontract, hut at least half were welded in the manner of the vV.l4 girders.
Clarke said this was done hecauJ:le manual welders were not available at the time when the
automatie cover plate flange longitudinal welds were eompleted. In other words there
was no rational or pre-determined sequence for this weld~to which nobody attached any
special importanee-it was jus1; a matter of shop expediency.
Ji'rom these considerations we eondude that the following factors were eoncerned in
causing the toe eracks which, being stress raisers, set off the train of events whieh led to
the failure of span "\V.l4 :-
(a) The pre-heating of the weld loeation wa~>insuftieient beeause the carbon content
of the steel was higher than was known at the time, and the pre-heat had
been lowered by decision.
(b) The electrodes may have been insufficiently dry due to slackness in shop
praetice.
(c) The restraint on bhe transverse weld caused by the sequence of welding used.
We cannot, however, say whether one of these factors was more important than the
others.
and chemical composition, including nitrogen and hydrogen content. The precise degree
of notch ductility revealed is, however, also a function of the geometry of the part in the
neighbourhood of the notch, of the size of the weldment and of the rate of application of
the external load. The essential characteristic is the pre8ence of a notch--in this case
the toe cracks.
In our thinking on this feature of the failure we have been influenced by the
appearance of the partial brittle fractures in the failed girders. They are always discoloured
and generally rusty. This discolomation we think was caused by the phosphoric acid used
for cleaning the weld prior to painting and if this is so the fractures must have been present
at this stage. These W.l4 girders were painted in the fabrication bay (Hardcastle
Tr. 2070) and from the description we have had of this operation it is evident that little time
would elapse between the finish of manual welding at the end of the cover plate and the
application of acid for cleaning. This latter was left on for about half an hour.
These partial brittle fractures occurred therefore almost certainly within two hours
of the welds being made. There is evidence also that internal cracks were formed in the
fillet welds connecting the tapered part of the cover plate end to the flange as well as the
transverse weld itself. 'fhe former eracks have not propagated by brittle fracture so far
as we know and this inclines us to the view that local internal stresses, probably aided by
handling stresses as the girders were turned over for painting, were most severe at the
transverse end and caused the cracks there to develop. Scarlett (Tr. 1480) said there was
much flexing of girders during handling.
We have asked ourselves the question, " vVhy did these partial brittle fractures
occur at five of the eight welds and not at the other three ~ " No satisfactory answer has
been found. Four of them, including three of the worst fractures at this stage, involved
heat 55 which had a bad record for notch ductility when tested. The fourth occurred in
heat 56 which has given mixed notehed bar results on the whole, but never so bad as those
from heat 55. It is possible that these erratic results in heat 56 are due to strain ageing
but we are not satisfied that this is the answer. We note that heats 55 and 56 were
rather higher in nitrogen ('008 per cent. to 011 per cent.) than is fixed as an upper limit in
the 1962 amendment of B.S. 968. We earuwt rule out the possibility that some mixing
of these two heats has occurred during fabrication.
We have also considered the possibility of hydrogen embrittlement arising from the
pickling process to which all plates were subjected. We are aware that some authorities
consider that there is a permanent effect resulting from the absorption of hydrogen. We
have, however, rejected this possibility because the condition would be found in all plates,
and because at the location of the fractures the steel had been heated by the welding
operation. Hydrogen in this sense must be distinguished from hydrogen introduced by
the use of undried electrodes. This latter hydrogen is confined very locally to the heat-
affected zone of the weld and may be partially responsible for the toe cracks.
We conclude that the primary brittle fractures in these girders were due to the
brittle nature of the steel. They were "triggered" by the cracks present at the toes of the
transverse weld at the cover plate end. The stress needed to cause the brittle fractures was
partly internal (resulting from the close restraint of this weld) and partly external due to the
handling of the girders for painting. This latter feature was probably the variable which
decided whether partial brittle fractures occurred or not, coupled with the notch ductility
of individual plates of steel.
'Vhilst we cannot satisfy ourselves that it had any part in the failure we would draw
attention to what we consider a bad practice, and one fraught with danger. This is, the
method used for cleaning welds prior to painting, by swabbing with either 15 per cent.
hydrochloric acid or 15 per cent. phosphoric acid. The practice was to leave this acid in
contact for half an hour or so. Under such circumstances the acid would penetrate into
any cracks which had remained undetected and would generate hydrogen which would be
absorbed by the steel in the immediate neighbourhood. Thus the cracks would be
surrounded by embrittled steel, and this might lead to brittle fracture due to handling
stresses. Another bad feature, particularly if hydrochloric acid is used, is that the
~orrosion products formed would be a continuing source of corrosion even under the paint.
84
The W.14-3 south fracture also contains the final coat of aluminium paint which
penetrated from both sides of the flange. This means that owing to the flexing which
occurred during transportation and erection this crack had opened again through the
priming paint and was visible. It must also have been flexing under traffic loads between
November, 1960 and January, 1961, because the second coat of paint applied after
erection must also have cracked through.
The evidence of Clarke {Tr. 957-8) was that if these end welds were done last it was
not the general practice to examine them for cracks by the penetrant dye method. Such
an inspection should have been made. We have been told by witnesses from K.S.B.D.,
C.R.B. and J. & W. that nobody gave a second thought to this weld as being of any
special importance. We cannot agree with that view-(a) because a sharp change of
section in a flange creates a position of stress concentration, and (b) because it is a transverse
fillet weld on a tension flange. We think, therefore, that special attention should have
been drawn to it.
We conclude that the transverse welds of the \V.14 girders were not adequately
inspected for cracks and that this omission is a direct cause of the failure of the W.14 span
of the bridge. vVe find that failure to inspect these welds was due to a combination of
circumstances :-
(a) No particular attention had been dra\\'11 to the importance of these
cover plate end welds.
(b) The inspection of final details on the girders was carried out in such an
atmosphere of hurry and bustle that no inspectors could be expected to
do this important work satisfactorily.
(c) ll'or the same reason, that is, speeding to complete the painting operation,
a sufficient period was not allowed for cracks to develop. It is accepted
that cracks of the kind found in the failed girders can occur up to two
or three day:~ after the welding operation. We consider therefore that
painting should not have started until this lapse of time had occurred.
The fact thai;, in the circumstances, the cracking of these welds occurred
within an hour or two of the end of welding is not relevant to this
argument.
In our opinion the parties responsible for the lack of inspection which should have
discovered these cracks are-
(a) K.S.B.D. for no~ realizing and drawing attention to the importance of this
weld.
(b) J. & W. for creating the circumstances which made adequate inspection
impossible.
(c) The C.H.B. for not insisting on adequate time elapsing between the final
weld and the painting operation, and on adequate facilities for final
inspection be:ing provided by the fabricator.
85
3.4. The Chemical Composition and Physical Properties of the Steel in the W.14
Girders.
Since the collapse numerous sampler; have been taken from the failed girders in
order to find any anomalies which would help to decide the cause of the failure. To clarify
the situation at this stage we repeat that the immediate caul)e of the collapse was---(a) the
presence of toe cracks at the transverse weld at the end of the cover plates; (b) the
development from these of partial brittle fractures. It is our opinion that the toe cracks
should not have been there if suitable welding practices had been employed, and should
not have developed into brittle fracture if suita.ble steel had been used. In other word.s
we agree with the opinion expressed in American \Velding Hesearch Council Bulletin
No, 16, of November, 1953 (p. 41) :-"The arresting of a crack is primarily the responsibility
of the material ; the prevention of crack initiation on the other hand depends on a
combination of geometry, fabrication and material".
It will be noticed that the steel enters into both aspects. This is because the
chemical composition of the steel determines the welding characteristics and response to
stress is determined by the physical characterit;tics.
We now proceed to examine the material of the failed girders from these points of
VIeW.
Only two heats of steel are concerned in the ten,'>ion flanges of the four girders.
These are the fully-killed electric furnace heats 7890 (C.R.B. No. 55) and 7892 (C.R.B.
No. 56) made at the Port Kembla plant of A.LS. For convenience these will be designated
by the C.R.B. Nos. 55 and 56.
From the point of view of weldability the significant elements are earbon, manganese
and chromium. Attention will be paid later to some more detailed analyses which we
had made to help solve some of the problems. The B.S. 968 specification defines the
composition of this steel as follows
Carbon (C.) 23 per cent. maxnnum
Manganese (:1\'In.) 18 ,
Chromium (Cr.) 10
" "
" " "
Manganese +
Chromium 20
" " "
From this it i.s seen that on the cast or ladle analysis heats 55 and 56 fall within the
specification. Heat 55 is on the upper limit of manganese plus chromium and heat 56 on the
upper limit of carbon. For reasons already discussed (Section 2.7.2.1) analysis of the plates
delivered to the fabricator may vary appreciably from that of the ladle sample shown
on the analysis certificate. The reasons for this are well known. Some depend on
86
the skill of the steelmaker, others are just natural phenomena to be coped with. It is,
however, essential for the fabricator to understand these matters and for the steelmaker
by his skill to minimize the difference between what he purports to supply and what he
actually does supply.
Since we have to deal with the facts of the ease analvses have been made on material
taken from various parts of the failed girders. The re~ults of these investigations arc
summarized in Tables 5 and 6 and in A.ppendix 5.
It will be recalled that heats 55 and 56 were two of the " submitted heats " about
which B.H.P. wrote to J. & W. on the 27th February, 1959 {Ex. 76), as follows:-
" In the latest rolling of B.S.S. 968 girder plate for your good selves,
test failures occurred in a number of fully-killed electric furnace and open-hearth
heats.
In the ease of heat 243241, the meehanieal tests were satisfactory for
}-in. girder plate, bu1; due to the reduction in tensile strength from 35j4( t.s.i.
to 33/39 t.s.i. in the heavier sections, the 1-in. girder plate failed to meet the
specification.
\Ve have asked our works to forward samples from each heat involved
as we understand it will he necesl'\ary to conduct weld tests on this material
before any decision can be reached.
The letter implied that a complete metallurgical investigation had been made to
determine why these heats were high in tensile. From Ex. 186 (check tests) it appears
that no cheek analyses were made on plates of some of these heats prior to despatch. It
is difficult to understand, therefore, the basis of the confidence expressed in the letter that
"despite the high tensile, the steel would be weldable". At this stage, it was essential
that A.I.S. should have made check analyses of plates. Since the failure, many such
analyses have been made on heats 55 and 56, and these are summarized in Tables 5 and 6.
From these we see that the average of sixteen analyses of heat 55 is carbon 25 per cent.
and manganese plus chromium 2 0 per cent. and of fifteen analyses of heat 56 is carbon
26 per cent. and manganese plus chromium 2.0 per cent.
It is evident, therefore, that in these two cases, the pit sample was not representative
of the heat, and had A.I.S. made the thorough investigation necessary it would have been
disclosed that these heats were out of specification as regards composition.
This featme was of much greater importance than the slightly high-tensile strength
to which attention was drawn. It raised the weldability index (as calculated from the
composition) to D and, therefore, made the task of the fabricator still more difficult. It
reduced the notch ductility and thereby weakened the second line of defence against brittle
fractme.
87
ThiB is not the case which is confused by the claim of the steelmaker to a tolerance
on a ladle analysis. In our opinion the ladle analyses were not representative of heats 55
and 56 and the bulk of the steel of t.hese heats was clearly out, of specification.
Composition
Uirdcr No.
W.l4/S ].oration
Cr.
Composition
Girder No. I,oeation ~ample No.
W.!4/S
I
Heat 56-~D.S.L. Ana.lyse8
1 Near north end C.R.B./50 25 173 24 20 010
N.I.F. 26 170 25 20
" end" south of fracture
North C.R.B./51 26 175 24 20
2 Centre plate north end O.R.B./52 26 172 24 20
Centre plate south end C.R.B./.53 27 172 25 20
North end of south phtn C.R.B./54 26 173 24 20
Near south fracture C.R.B./55 25 172 24 20 009
3 Nnar north end C.R.B./56 25 173 2J 20
South of north fracture N3/F 26 173 23 20 008
Near north end C.R.B./57 2.5 17;3 24 20
North of north fracture C.R.13.j58 26 174 24 20 009
Samples of steel from the failed girders and from a U.K. source have been analysed
spectrographically in three laboratories namely :-~-D.S.L., B.\V.R.A. and A.I.S. The
results are given in Table 7 for heats 55 and 56 which showed no differences.
ND: Not detected. NS: Not sought. Not identified by heat number but probably heat 55.
rrhe only trace element found in significant concentration is nitrogen, which will be
considered in the section on strain ageing. (3.4.4).
From this enquiry it can be stated that no element has been discovered to be present
in the Australian steel which is n.ot also present in the sample of steel made in lJ.K. This
result, with the exception of the nitrogen value, is completely negative in helping us to solve
the problem of the brittleness of heats 55 and 56.
The accepted standard for protection from brittle fracture in the case of mild steel
ship plates is 15ft.;'lb. Charpy at the lowest operating temperature. whether we accept
32 F. (0 C.) as proposed by the C.R.B. or 22 F. (~5o C.) as more realistically based on
meteorological observation in Melbourne it is evident that neither of the two heats concerned
approaches the required Charpy values. Based on the Izod test and using the C.R.B.
criterion, heat 55 still shows poor results and although on the average heat 56 just fails, it will
be seen from Table 9 that four of the six samples fail to reach the specified value, one of them
failing badly. In reverting again to the variability of results obtained in these investigations
it should be pointed out that B.H.P., during the Enquiry, maintained that the evidence
of this variability as shown by the acceptance tests was dubious because of lack of knowledge
of the preparation of the test pieces. We accept that criticism but this can not apply to
the values quoted in Table 9, the preparation of the specimens in this case being done under
laboratory control for the purposes of this Enquiry.
We conclude that the steel in the flanges of the failed girders was of low and variable
notch ductility and that as a result the steel was not able to resist the propagation of brittle
fracture from the toe cracks at the transverse weld at the end of the cover plates.
We have plotted all the results available to us relating to Charpy and Izod values
taken for comparison from the same plates of steel to B.S. 968 of~ inch and! inch thickness
supplied to this contract. There is a wide scatter as has been indicated, and only
twenty observations. Assmning that zero energy is the same point for both machines, the
best relationship is
Izod = 2 Charpy
but the values scatter between Izod = 4 Charpy and Izod 4/3 Charpy. The range of
values included was 5 to 55 Izod and 4 to 30 Charpy.
If we accept the above relationship we conclude that the 20 ft./lb. Izod specified
by the C.R.B. was approximately equivalent to 10 ft./lb. Charpy, and was therefore not
equivalent to the value accepted as protecting mild steel, ship plate, i.e., 15 ft./lb. Charpy.
This would be equivalent to 30 ft./lb. Izod. If we look at Table 9 it is seen that this value
was recorded in only one case, at 8.2/1 (heat 56). This was the location of the first major
brittle fracture.
Although the evidence is slender, we conclude that a value higher than 30 ft./lb.
Izod (15 Charpy) was necessary with this steel to protect the bridge from brittle fracture,
and tentatively suggest that 40 ft./lb. Izod (20 ft./lb. Charpy) would have been necessary,
though this can only be an informed guess. However the information on which this view
is based was not available when the C.R.B. specifications were written.
The question then arises whether in 1956, steelmakers would have accepted such a
value in a specification, using B.S. 968 as a basis. We have seen the reaction of B.H.P.
to the value of 20 ft.jlb. at 32 F. Yet, when we look at the plate acceptance tests which
were carried out on 61 heats of steel to this contract we find that 40 of them would have
satisfied the 40 ft.jlb. Izod criterion. Of these, 34 were semi-killed basic open-hearth steel
and six fully-killed electric furnace steel.
We have for comparison some results from bridge steel made in U.K. at about the
same time (1956~57) as the C.R.B. specifications were being written (Ex. 93). For the
four thicknesses of steel below 1 inch the values at 0 C. are all above 20 ft.jlb. Charpy.
Since this is the one valid comparison between B.S. 968 made contemporaneously in U.K.
and Australia respectively we have reproduced the results in Figs. 9 and 10. It is at once
evident that the transition temperature of the U.K. steel is appreciably lower than that of
Port Kembla steel, and the liability to brittle fracture is correspondingly less.
------~-~-----------------------
55 D.S.L. S.4F 8 22 43 57
A.I.S. 2N 5 10 13 22
A.I.S. S.3/1 4 4 10 10
--- --------------~---~ --------------------
Average 6 14
------ -----~---------------------
56 D.S.L. 14/2 4 8 25 42 68 72
A.T.S. IN 16 27 30 41
A.I.S. 3N 8 19 30 35
A.I.S. 4N 13 17 38 47
------- ---------------------------
Average 6 24
------------------------ ----------------
55 D.S.L. S.4F .. 12 25 36 53
A.I.S. 2N .. 8 23
A.I.S. S.3/l 4 8
Average 12 22
-------- ---------------
56 D.S.L. 14j2 .. 17 41 55 65
A.I.S. IN . . 25 33
A.I.S. 3N . . 10 14
A.I.S. 4N . . 17 39
A.I.S. S.2/l 30 33
A.I.S. S.2/2 16 17
Steel supplied for the contract was tested for strain ageing characteristics both by
D.S.L. and A.I.S. laboratories. A synopsis of the results is given.
D.S.L. confined their experiments to a flange plate from heat 55. The treatment
and the results are shown below. (Ex. 194, App. 9).
Another sample was taken from within 2 feet of the last ones and was subjected
to a normalizing treatment with the following result :-
Average of 'l'hree Tests
The A.I.S. results on strain ageing were made on material from J. & W. stock and are
reeorded in Table 10.
The results are not sufficiently extensive to draw firm conclusions but it would seem
that strain ageing is a general eharaeteristic of A.I.S. steel made to B.S. 968.
Other steels investigated at the same time show that imported B.S. 968 and other
heats made by A.I.S. are liable to the same eharacteristic.
vVe eonclude that the steelmaker should give special consideration to this problem
particularly as the addition of "scavenger" elements in the ladle would probably reduce
its incidence.
92
lzod ft./lb.
The basic fact of the whole Enquiry i.s that a large and important public structure,
which cost the community overall .some 4,000,000 failed dramatically and embarrassingly
within fifteen months of its coming into service, and failed moreover, by reason of inherent
defect, and not from the action of some natural force of unforseen magnitude, or other
external factor.
Such a failure should not have occurred. It cried out for explanation, and for the
a,'lses.sment of responsibility among those whose duty it was to create a safe and patisfactory
structure, and we reject the theory, .somewhat diffidently suggested to us at one stage, that
the failure was due to .sheer misfortune occurring in such circumstances that no blame can
be attached to any of those associated with the project.
We accept the argument addressed to us by Counsel, that our task, .so far as it
relates to fixing blame and responsibility, is to do so as a matter of fact simply, and not
to concern ourselves with legal liability, direct or vicarious. We have made every endeavour
to avoid any findings out.side our proper sphere, particularly having in mind the existence
of litigation currently proceeding between some of the parties, and the possibility of
future litigation.
We refer to some minor matters of controversy which arose during the sittings of the
Enquiry, and which are to be found scattered over the 4,000 pages of transcript. These
matters were relevant, and at the time appeared important, but are not vital to our findings,
and reference to them is omitted in the interest of avoiding intolerable length in this Report.
We have also asked ourselves whether we have been judging these incidents by
standards that are too high for ordinary mortals to reach and whether we are demanding
higher standards of competence from engineers than we would from doctors, lawyers or other
professional men. It is, of course, undeniable that a doctor or lawyer who makes a mistake
which causes his client to lose life or liberty normally escape~:> public censure although he
may have to aMWer a charge of negligence in the courts. But engineers generally-and in
thi.s case certainly~-do not work as individuals in a con.sultan~client relationship, they
work as a team. This certainly brings with it problems of communication and organization
but it also means that individual engineers are supported by others who can help and check
their work.
From this standpoint we do not think that we have been too har~:>h on individuals.
It is the various organizations within which they were working that we regard as being
collectively responsible for the unhappy state of affairs that we have been investigating.
(c) The cracks remained in the girders because they were not discovered either by
Johns and Waygood Limited or by the Country Roads Board inspectors.
(d) The steel supplied by the Broken Hill Proprietary Company Limited for the
tension flange pla1:es on the span concerned, accepted by the Country Roads
Board, and used. by Johns and Waygood Limited without adequate
examination, was low in notch ductility and was thus unable to resist the
propagation of bnttle fractures from the toe cracks.
Term 11.-The tenders received, the action taken to investigate the same, the
circumstances surrounding the acceptance of the tender submitted by Utah
Australia Limited, and whether the acceptance thereof was reasonable and
proper and justified in the circumstances.
The number of the tenders received was reasonable, but we feel that
the C.H.B. must have been disappointed that the names of some bridge builders
of world reputation were conspicuous by their absence.
The aetion taken to investigate the tenders was reasonable and proper
from the point of view of business propriety. \Ve, however, make some
criticism of the C.R.B. in Section 2.2. of our Report : in particular we feel that
the use of high-tensile steel in the Utah tender should have been specifieally
drawn to the attention of the Government before the decision to use this
material was finally made.
The acceptance of the Utah tender was reasonable from the point of
view of business propriety. However, it should not have been aceepted without
far more enquiry and investigation, because the material to be used in the
superstructure was one of which neither the C.RB. nor Utah had any experienee.
We found no evidem~n or any circumstances giving rise to any suspicion of
impropriety in relation to these matters.
95
Term Ill.--The design submitted and adopted for the bridge, and whether the same
was adequate and suitable or was in any and what respects defective or inappropriate
or deficient.
(a) The general design wa~ adequate and suitable. We are of the opinion,
however, that the choice by Utah of high-tensile steel as specified was
unfortunate for the reasons stated hereafter.
(b) The use of cover plates, and the design of the end detail of cover plates was
criticized in the report of the Committee of Investigation (Appendix :3)
and a great deal of evidence and discussion was directed to this matter.
We are not prepared to find that, in 1957 this feature was undesirable,
but on the basis of knowledge now available, we are satisfied that any
feature involving transverse fillet welds in tension flanges is undesirable.
Term IV .--The materials and processes and workmanship used in the construction
and erection of the bridge, the standard and suitability thereof for the purposes
for which they were used, whether they were in accordance with the contract
specifications and whether they were in any and what respects defective or
inadequate.
(1) M ateTials.
Steel.
(a) At the stage at which the specifications were drawn we are agreed that
on balance the C.R.B. was justified in including high-tensile steel as an
optional material for the superstructure. However, we are quite satisfied
that this material should not have been used for the whole of the super-
structure in a project of such magnitude, in the circumstances existing in
1957, where neither Utah, J. & W., nor the C.R.B. itself, had any
experience in the use of the material for welded bridge building.
(b) Some of the steel used in the bridge and particularly in the girders of the
W.14 span did not comply with the C.R.B. specifications as regards
composition and notch ductility and should have been rejected by
J. & \V. and the C.R.B.
(c) J. & W. while bound to supply steel to the specifications (B.S. 968 with
additional clauses) ordered the steel from B.H.P. as B.S. 968: 1941
simply without the additional tests. J. & W. with the knowledge of the
C.R.B. failed to carry out sufficient tests to ensure the notch ductility
of some of the steel wmd, and failed to make check analyses of the steel
supplied to ensure its correct chemical composition.
(d) J. & W. and the C.R.B. accepted delivery of certain "submitted heats"
to which their attention had been drawn by B.H.P. No proper
consideration was given to these heats before acceptance, and some of
them should have been rejected, in particular heat 55, which was used in
the failed girders.
(e) All these parties failed to hold sufficient discussion on the subject of the
quality of the steeL
Electrodes.
The electrodes used--Fortrex 35 for manual welding and Murawire and
Mnraflux for automatic welding-supplied by Murex were suitable, in accordance
with specifications, and in no way defective or inadequate.
Term V.-The nature, extent, and standard of supervision exercised over the construction
and erection of the bridge, and whether the same was reasonable and adequate or
was in any and what respects inadequate or defective.
Utah.
Utah, the head contractor, which might have been expected to undertake
considerable supervision of the work of J. & W., deliberately refrained, as a
matter of policy, from any such supervision or inspection, on the basis that doing
so would only duplicate and interfere with the work of C.RB. inspectors.
Utah did appoint Scarlett of J. & W. as its representative on matters of
testing and inspection or acceptance of steel, but did little else. vVe do not
make any adverse comment on this attitude, as it was accepted by C.RB.
O.R.B.
The system of acceptance testing of the steel was deficient in several
respects and whilst never utilizing its full right of testing, C.R.B. ultimately
gave way to pressure exerted by J. & W. and Utah and relaxed its testing
requirements without adequate consideration. The C.R.B. also set up an
inspection system designed to effect a satisfactorily high standard of
workmanship. However, it was carried out by people who lacked any
experience in the technique of inspection or in the welding problems associated
-with the steel being fabricated. As a result, the control was in some regards
too rigorous, so that the personnel at J. & W. were made resentful at what
they regarded as " pin pricking ". On the other hand, while many defects were
discovered and remedied, the system failed lamentably to uncover some crucial
defects including the cracks associated with the vV.l4 girders which failed.
For reasons given in Section 2.10.6, these defects should have been discovered.
J. & w.
The fabricator never understood the need for meticulous inspection of
welding when the material being fabricated was high-tensile steel. This
attitude, combined with the suspicion that the inspectors knew no more than
they did, engendered a strong feeling of resentment, which led to constant
arguments over standards of workmanship. Harassed by the inspectors on
the one hand, and on the other pressed by Utah for production on schedule,
the J. & W. management continually sought some relaxation of inspection.
All this militated against the efficiency of the system. It is fair to say,
therefore, that J. & \V.'s attitude contributed to the failure by the C.R.B.
to discover important defects which passed into the bridge structure.
Term VI.-Whether any and what negligent, culpable, or improper act or omission
directly or indirectly caused or contributed to the failure of the bridge, and if so
the party or parties responsible therefor.
The determination of the questions arising under the first head of this
term of reference, required us to undertake the difficult task of fixing some
standard of negligence which can fairly be applied to the matters which we
have found necessary to criticize in the conduct of many of those associated
97
with the Kings Bridge project. We accept the argument that not every act
or omission should be held to be " negligent " within the meaning of that word
in this context, even though they might be negligent from the standpoint of
legal liability. For the purpose of this term of reference we have, therefore,
adopted the standard that any course of action, resulting from a considered
judgment exercised after proper enquiry, is not negligent even though in the
event it proved to be wrong. Nor do we class as negligent some instances
of lack of competence arising simply from inexperience, under circumstances
in which the party concerned has acted to the best of its skill and ability. On
the other hand, we treat as negligent such instances of error as we are satisfied
occurred because those responsible entirely failed to give reasonable consideration
to the particular decision.
Applying this somewhat restricted test we are of the opinion that the
following matters of importance do constitute negligence :-
1. The failure by J. & W. to carry out its clear obligation to test and
select, from the material supplied by B.H.P., steel which
would have come within the full requirements of the C.R.B.
specification.
2. The decision by C.H.B. to abandon the full programme of acceptance
testing and to carry out testing on a random basis.
3. The acceptance by the C.RB. and J. & W. of the "submitted
heats" which B.H.P. had given them the opportunity to reject
or accept.
4. The offer by B.H.P. to J. & W. of the "submitted heats" by
means of a letter (Ex. 76) which declared that " our metallurgical
investigation . . . indicated that the steel quality is good
. . . also . . . the steel would be weldable ". A proper
investigation could not have supported such a statement
(See Sec. 3.4.1.).
Term VII.-Whether the construction and erection of the bridge in accordance with
the tender submitted by Utah Australia Limited was reasonable having regard
to the known state of engineering and scientific knowledge and experience subsisting
at the time the tender was accepted.
The general knowledge in the engineering profession of the quality and
behaviour of B.S. 968 : 1941 steel has greatly increased since January, 1957.
Nevertheless, there was ample information in the literature generally available
at that date, and in the minds of metallurgical engineers like Ferris, to have
provided the parties involved in the bridge project with a clear warning that
this steel required very special care and skill in manufacture and fabrication.
All the parties except Ferris and Murex failed to realize that in essaying
the construction of a large and important welded structure in this material,
they were taking a very long step from the familiar processes of mild -steel
construction into an unfamiliar situation where more elaborate techniques were
required. Because of this lack of appreciation, the proper programme of test
and experiment which alone would have justified the use of this steel was not
undertaken.
6352/63-7
98
4.3. Condition of the Superstructure.
Although it is not within our terms of reference, we cannot conclude our Report
without recording our very grave concern about the future of the steel work of the bridge.
We know that it contained a great many cracks that have been found and removed but
from all we have learnt, we are certain that there must be many more. Some of these may
be in critical and highly-stressed regions. Such cracks must be a continuing source of
danger, either of brittle fracture or fatigue, unless some means is found to reduce the
tensile stress concentrations to negligible amounts. We wish to point out that we do not
know of any determination of the fatigue properties of this steel even at this late stage.
\Ve desire to record our thanks to those who have rendered us very great assistance
during the course of this Enquiry.
Counsel assisting the Commission, Mr. S. T. Frost, Q.C., and Mr. Gordon Just,
displayed great industry and capacity.
Their skill in presenting the evidence, and in advising us on procedural and other
matters, was of the greatest possible assistance.
We also wish to thank the other Counsel appearing at the Enquiry, who, while
never losing sight of their paramount duty to advance and protect their clients' interests,
so conducted their cases as to greatly assist our investigation.
Many of the organizations directly and indirectly concerned with the Enquiry
provided us with valuable information, and some of them devoted much time and expense
to scientific experiment and the compilation of extensive records.
In particular, we thank the Defence Standards Laboratories, and the Melbourne and
Metropolitan Board of \Vorks. Two organizations directly concerned with the Enquiry-
the Country Roads Board and the Broken Hill Proprietary Company Ltd.-each provided
us with much material of great importance beyond that which was necessary for their
own purposes.
Engineering, Testing, and Research Services Pty. Ltd. carried out certain tests and
investigations for our information, and its Manager and Metallurgist, Mr. Hudson, rendered
us extremely valuable assistance.
E. H. E. BARBER, Chairman.
J. A. L. MATHESON, Member.
Melbourne,
3rd June, 1963.
99
APPENDICES.
2 List of Exhibits.
Extracts from the Paper "How to Use High Strength St{>el Effectively", by
A. L. Elliott.
5 Results of Tests on Samples from W.l4 Girders, extracted from D.S.L. Report,
Exhibit 194.
l
CLARKE, Norman Victor
3159-3160
DARWIN, Donald Victor 170-225
{ 555942
EASTICK, Robert Frank
In Camera, 1-7
2881-2908
l!'ARRAR, William Crisp
{ 3062--3141
2616-2776
3622-3
1216-1257
FISHER, Eugene Peter 2343-2373
Fox, Edward William 1651-1683
FRANCIS, Professor Arthur James 1881-2008
2073-2085
GARDEN, Kenneth Alexander ..
{ 2146-2147
GRAHAM, David Gordon 1683-1703
HARDCASTLE, Phillip Alfred 2053-2073
423-509
HARDCASTLE, Roy Thomas Andrew
{ 2012-2037
HoFFMANN, Siegfried .. 1628-1649
515--55]
HUDSON, Robert Frederick
{ 3218-3230
2777-2787
HUNTER, Joseph
{ 2791-2801
3039-3058
3212-3217
J AEGER, Ernest
{ 3243-3251
"MAIN, Allen Bennie 1780-1844
~!ASTERTON, Cli:fford Alexander 2085-2130
MATHIESON, John 1845-1849
MOLL, Victor Raymond 551-555
{ 3252-3259
MoRRIS, David Owen
In Camera, 8-42
101
APPENlliX 1-contimted.
3175-3194
1705-1780
3327-3337
WrLUAMS, Ronald Trethewey .. 2373-2400
229--254
WILSON, Cecil Alexander
{ 259-423
1857--1881
102
APPENDIX 2.
LIST OF EXHIBITS.
Page at which
Exhibit Number Description Tendered
---~i---------------~-----------------------1----~------
Report of Professor Frank Bertram Bull and a letter written by Professor 1462 and 1470
Bull
133 Letter dated 16th November, 1962, from Dr. Week to the Commission 1464
134 I Letter dated 8th November, 1962, from Freeman Fox and Partners to
1 1465
the Commission
135 Certificates of additional tests produced by J. & W. {including weldability 1472
test certificates given by E.T.R.S., weldability test certificates given by
Royal Melbourne Technical College and miscellaneous certificates and
reports given by B.H.P., E.l\LF. Electric Co. Pty. Ltd., the University
of Melbourne and Sharp and Howells)
136 Summary of plate weldability tests carried out by E.T.R.S. for J. & W. 1484
137 File relating to heat 5.5 certificates (compiled by C.R.B.) 1.532
138 List of plates in which suspected laminations occur .. 1536
139 Photographs of cover plate of girder E6S3, over \Vlliteman-street 1583
14-0 Reproduction by Mr. Campbell of pre-heat chart 1589
141 Reproduction by Mr. Campbell of notebook entry 1593
142 A box of thermal crayons 1599-1600
143 Ust of location of heats in flanges at points of termination of cover plates 1657
144 Copy of Mr. Norman Clarke's diary from 23rd April, 1959, to lOth 1658
February, 1961, and the original thereof
145 Sketch by witness Edward William Fox as to order of welding of 1675
cover plate end
146 Minutes of meeting held on 1st December, 1962, at J. & W.'s Sandringham 1729
premises re weld tests
106
APPENDIX 2-continued.
LisT OF ExHmrrs-continued.
-------;-------------~----~-----~-----~--
--------------------------~------------------------------------------1~-------
147 Extract from Engineering News Record of 18th October, 1962, "Crystals 1730
cause failures ? ", being a letter from Douglas 8. Laidlaw to the editor
148 Report No. I.R. 551 dated 4th November, 1959, by :Jiurex Research 1733-4
Department, Hobart, to the Melbourne Branch of :Jlurex
149 M:emomndum dated 12th October, 1959, from the M:urex Research 173fi
Department, Hobart
150 Memorandum dated 7th October, 1960, from .:\ielbourne Branch of Murex 1735
to :Jlurex Research Department, Hobart, and reply thereto da.ted
14th October, 1960
151 Murex file, including Exhibits 148, 149, and 150 l738
152 Memorandum dated :lrd December, 1962, from Mr. R. T. A. Hardcastle, 1916
being his comment~ on Professor Francis's report
153 Report dated 18th May, 1960, by Mr. C. A. Wilson, "Effect of Weld 1918
Defects on Strengt:n of Girders "
154 Report on type of welds at cover plattJ ends 1918
155 Results of tests conducted on behalf of C.R.B. by D.S.L. ou sections of 1978
failed girders
156 Graph of Charpy Impl>ct Tests appended to Exhibit 93 Hl94
157 Minutes of 119 design CQnferences held between 21st August, 1957, and 2011
12th May, 1960
158 Copies of Acier Stahl Steel, January, 1961, and April, 1961 .. 2034
159 Report to J. & W. hy Professor Bull 2045
160 Report by Professor H. W. Worner 2045
161 Letter dated 28th November, 1962, from Dr. Week to the Commission 2045
162 Photographs (taken off Ex. 4) which, according to the witness P. A. 2058
Hardcastle, show red lead paint
163 Two samples of B.S. 968 steel showing welding using different gauges of 2088
electrodes and varying runs
164 File of correspondence produced by the witness 0. E. Ralston and report 2133 and 213\l
from Port Kembla with attached photographs
165 Schedule showing deta.ils of supply of steel to B.S. 968: 1941 by B.H.P. 2145
to Australian users
166 List. of heats supplied to J. & W. together with a table showing customers 2148
other than .J. & W. supplied with steel from these heat.s
167 Record showing t.ot~l deliveries of steel by B.H.P. to S. & W. to 25th 2148
June, 1959
168 Notes of conference held on 26th :May, l9fi8, at J. & W. between B.H.P.
and .J. & W. and original notes of t,his conference, containing red ink 2190 and 3106
additions
169 Letter dated 6th January, 1961, from J. & W. re B.H.P. and reply 2217
thereto dated 14th February, 1961
170 American Iron and Steel Institute, Steel Products Manual, pages 18 and 2221
following
171 Murex report dated 11th December, 1962, showing analyses, &e., of :Nlurex 2241
welding materials
172 1957 Edition "B.H.P.-A.L & S. Steels" .. 2247
173 1962 Edition "B.H.P.~A.I. & 8. Steels" .. 2247
174 Drawing showing suggested weld sequence for termination of cover plates 2300
175 Photograph showing lzod testing machine with vice blocks, &c. 2:33()
176 File containing reports of witness E. P. Fisher to Utah 2343
177 Report on automatic welding of steel to B.S. 968, by E. P. Fisher 2347
178 l\llemo of German publications on strength of steel 2368
179 Experience record of E. P. Fisher .. 2373
180 Second Murex file 2379
181 I.etter dated 26th November, 1962, from Dr. 1\-iatheson to Dr. Week, and 2401
reply thereto dated 4th December, 1962
182 Table from the A.I.S.L Steel Products Manual 2401
183 Seven samples of British B.S. 968 st.eel 2405
184 A.I.S. experimental re port on B.S. 968 2410, 3365, and
3563
185 Two copy letters dated 6th December, 1962, and 12th December, 1962, 2433
to B.H.P. covering supply of imported British B.S. 968 steel
186 B.H.P. file on chemical, mechanical, and metallurgical checks on B.S. 9()8 247l
steel supplied for the bridge
187 Mr. Farrar's notebook on conference on 19th May, 1959, at Sandringham 2528
188 Pamphlets from Murex, E.M.F. and Lincoln re handling and care of 2535-6
electrodes
189 Optical and electron micrographs t.aken of welds in heat 55 .. 2540
190 Data on edges of plates and sections as supplied to J. & W. by B.H.P. 2550
191 Letter dated 21st November, 1962, from the Department of the Navy 2570
to C.R.B. with enclosures re D.W. steel
107
APPENDIX 2-----.continued
LIST oF ExHIBITS ~continued.
192 Photo of special girder showing "U" shaped cover plate end 2582
193 Note of additional clauses to Standard Specifications 2595
1!H Report dated 23rd .January, HH\:3, by lVIr. Ferris, on metallurgical 2fi03
investigations into the failure of four welded low-alloy steel girders
(being the W.l4 girders) referred to nR D.S.L. report
195 Report issued 21st December, 1962, by B.W.R.A. "An Investigation of 21\03
the Weldahility of a Steel PIMe Removed from a Failed Girder in the
Kings Bridge "
196 Summary showing incidence of cracks in transverse weld discovered up 2695
to 25th January, 1963
197 I,etter dated 30th Januarv, 19fl3, from C.R.B. tn the Commission re 2724
Mr. F. E . .Jackson
198 Second statement by Professor Bull 2803
199 Summary of test results carried out at Adelaide University 2804
200 Two samples of steel being off'cuts from steel supplied for t,he bridge, 2810
marked R1 and 7
201 Two pieces of mild steel marked MS2 and MS6 2810
202 Piece of steel, sample marked 8 (flame-cut edge) 2811
203 Boyd diagram produced by Professor Bull (relating to the bridge steel) 2833
21H Internal correspondence of B.H.P. 2879
205 Extracts from Exhibit 187 2894
206 Notes on testing from 1\'Ir. Farrar 2908
207 }feteorological information 2909
208 Method of sampling bridge material for chemical analysis (produced by 2~l29
lVlr. Ferris)
210 Paper "Thermal Gradients during Welding of Sin1ulated Kings Bridge 2972
Girders", by H. C. Coo and G. G. Brown of B.H.P., Research Division
211 Questions for. consideration by B.H.P. 3037
212 Table showing Navy pre-heats 3040
213 Plate mill specification sheet (issued by B.H.P. to it.s service oftieers) 3142
214 Statement, with annexnres, of Anna Miconiatis (of J. & W.) 3Hi2
215 Mr. Clarke's notebook, containing pre-heat tables 3160
216 Sample of steel supplied by Mr. Thompson .. 3194
217 Mr. Wilson's private notes on steel thickness 3196
218 Charts relating to 1\I.l\Jl.B.W. milling operation on cover plate ends of 3196 nnd 3432
Kings Bridge
219 Correspondence between the Secretary to the Commission and Caterpillar 3201
of Australia Pty. Ltd.
220 Sheet showing typical example of welding procedure, issued by Caterpillar 3203
of Australia Pty. Ltd. to its welders.
221 Izod impact test pieces from E.T.R.S. 3229
222 Statist,ical analyses of the details of inspection of main girders (compiled 3231
by C.R.B.)
223 Report of witness D. 0. Morris (received "in camera") In Camera, 8
224 Letter dated 26th February, 1963, from Norman W. Hutchinson and 3260 and 3430
Sons Pty. Ltd. t.o Mr. Peter Johns enclosing cast analyses of B.S. 968
in Forth-Road Bridge
225 Drawings by Mr. Williams of the transverse weld nt the end of the 3336
cover plate on W482, north end
226 Letter dated 7th February, 1963, from Professor Bull to Dr. Matheson .. 3357
227 American Welding Society's Standard Specifieations for Welded Highway 3357
and Railway Bridges, 1950
228 Pages 4 and 5 from a paper by Hatfield "The Work of the Heterogeneity 3358
of Steel Ingots Committee "
229 B.H.P. sales enquiry report and reply 3359
230 Correspondence between C.R.B. and the British Ministry of Transport 3364
231 D.S.L. supplementary report. dated 8th March, 1963, on examination of 3428
failed girders
232 E.T.R.S. report dated 7th March, 1963, on tapered welds in girder E.14 3429
233 Memorandum dated 5th March, 1963, from Mr. Ferris re incidence of 3429
cracking
234 Further reports from Testing nnd Rest>.'l.rch Department of lVIePherson's 3429
Ltd.
235 Statistics compiled by M.M.B.W. of cracking after 111 ends of cover plates 3432
had been milled
236 Signed report of Professor Roderiek 3439
237 Report dated 14th March, 1963, by E.T.R.S., supplementary to Ex. 232 3552
108
APPENDIX 3.
The Investigation.
The matters examined by the Committee are related to the known or probable factors concerned.
Responsibilities have not been considered by the Committee.
The items of the investigation were :~
1. The cause of the failure.
2. Tests and examinations to ascertain, as far as possible, the presence of any other points or potential
points of weakness.
3. The degree of risk in re-opening parts of the bridge to traffic and restrictions desirable.
4.. Remedial measures.
1. The Cause.
Examination and inspection of the fractures show that the failure was of a type known as " brittle
fracture " in the steel. This is a condition brought about by the combination of several principal factors,
namely:-
(a) The nature of the steel ;
(b) low temperatures;
(c) the process of fabrication, in this case, welding ;
(d) design details.
Brittle fracture is a mode of failure which may occur in any steel if a critical combination of condition
exists. These are principally :-
(1) The presence of a notch or indentation, crack, or other flaw;
(2) temperature in the range critical for the particular steel concerned ;
(3) a stress sufficient to cause a crack or flaw to extend.
Under the most unfavourable combination of these factors, a collapse may occur whilst the structure has
no load on it other than that due to its own weight.
The critical temperature in the steel used in the construction of this bridge is relatively high and
brittle fracture could, therefore, occur at temperatures commonly experienced in Melbourne, particularly in the
winter. Minimum night temperatures a.t the time of the failure were in the order of 35 F. to 40 F. and this
is considered to have been a factor contributing to the failure.
The steel used in these girders was of a kind commonly known as high-tensile steeL The specification
required that it should conform to British Standard No. 968: 1941, and contained additional conditional
conditions relating to impact properties.
109
APPENDIX 3---continued
It is known that steel of this description presents certain difficulties in welding and that this was
understood at the time of the preparation of the specification. Extensive precautions were taken to ensure a
satisfactory structure; however, it is the opinion of the Committee that the nature of the steel used,
although so far as is known at present, conforming in general to the specification, was such that even these
precautions proved inadequate.
Careful and extensive recorcls were kept by the Country Roads Board of certificates supplied by the
sub-contractors fabricating the girders certifying the quality of mueh of the steel.
'rhere are gaps, however, in the information relating to some of the "heats'' or batches of steel
included in the girders which failed.
The fractures occurred in each case at the short tranver8e weld at the end of the cover plates and the
examinations and tests made show that an excessively hardened zone was created in the flange plate at this
weld so that "locked-up " stresses caused cracks to oecur in these zones. In the girders which failed, it is
clear that the cracks led to the fractures and failure.
Four of the seven fractures have been examined closely by the removal of parts of the girders and there
is little doubt that at least one girder was fractured over a considerable portion of its depth not lesH than
three months and possibly much longer, prior to the failure. Two other fractures show that some craeking
existed before the failure. These fractures also show traces of red lead paint indicating that some cracking
was present either before the girders left the fabrication shop or before a second coat of similar paint was applied
after erection.
The failures aTe associated with a specific design feature, namely the stopping of cover plates. This is
known to produce high local concentration of stress and is considered an undesirable feature.
Whilst the Committee ha;; not been able to ascertain whether the fabrication procedures actually employed
weTe in accordance with those laid down in the specification, the existence of heat-affected zone cracks
suggests that these may have been insufficient. It may have been that no pro-heat was used in making the
end welds of the cover plates or that there may have been excess hydrogen present either from a pickling
process or electrode coatings; further that the rate of heat input to the joint in making the manual welds
was insufficient.
ln general, automatic or semi-automatic welding methods were used but at certain points, including
the ends of cover plates, manual welding was employed.
Any one of these tests may not be reliable but a positive indication by two can be taken as being
of fair order of reliability.
Visual inspection has been made throughout the bridge but instrument examination has been confined
to sections where a high degree of public risk existed or as necessary elsewhere to obtain information.
The coverage of tests and the information gained has been sufficient to justify the conclusion that defects
probably exist in all girders.
110
APPENDIX 4.
'l'he following extracts are taken from the paper ''How to use high-strength steel effectively" by A. L.
Elliott, Bridge Engineer in Planning, Bridge Department of the California Division of Highways, which appeared
in the "Engineering News Record" for 18th February, 1960.
Adding carbon to steel, for example, increases strength, but as m.ore and m.ore carbon is added,
the steel becomes hard and brittle. Soon a point is reached where the steel is virtually useless for
structural applications.
'l'his carbon limit is rather low. Exceeding it may lead to disaster: steel might crack in cold
weather or be shattered by vibration.
'l'o be weldable without brittleness, steel must have a carbon content less than 0 25 per cent.
Manganese also is critical and should be below 1 25 per cent.
Adoption of welding caused some nmjor changes in steel use in California. Before 1951, use of
rolled beams had been increasing steadily. For long spans, cover plates were riveted on, and sometimes
the webs were split and plats inserted to increase the depth of the beams. But these were expensive
solutions to the long-span problem.. After a short period of working with welded beams, California
began to utilize welding to the fullest extent in 1954. Since then, use of rolled beams has tapered off
to a mere 21 tons in 1958.
!.1eanwhile, use of welded beams has been increasing ::;teadily (18,500 tons in 1958). With this
background of experience in \velding, California was well prepared to make effective use of the high-
strength steels when they became available.
When alloy structmal ,steels were introduced about 20 years ago, California started to use them in
bridges. In 1939, two large truss bridges were designed with over 2,200 tons of high-strength steel. Two
years later, this new steel wa.3 covered by an AS'l'M tentative specification, A242 for alloy steel. After
that, California used it extensively.
Well over 100,000 ton;' of A242 steel have been used in the past ten years in welded California
highway bridges alone. 'l'his experience prepared the State's engineers for the next step to a higher
stress grade.
When the early designs for the second Carquinez Straits Bridge were beginning to take shape
about 19.53, the new HO,OOO lb./sq. in. yield-point steel had not yet been used in large quantity in any
structure. Since engineers are traditionally conservative, the normal procedure would have been to
wait ten or fifteen years until the new steel was well tested before specifying it for a bridge. But the
potential economies, the saving in weight and the reduction in size of members that this higher-strength
steel could effect, were too attractive to permit its adoption to be postponed.
So California engineers undertook a thorough investigation of this Rteel, which the maker, U.S.
Steel Corp., called T-1. After testing more than 3,000 lb. of it, they decided to use it in a substantial
portion of the Carquinez b1-idge. During fabrication of the trusses, some defects in welding were
discovered, ~md during erection, some transverse cracks were found in longitudinal welds (E.N.R. Sept.,
4, 1958, p. 42). 'l'he cracks frequently were close together, but in widely spaced groups.
All welds were rechecked and those that had cracks were removed and repaired. Less than 60
members were found to lli'tve cracks.
Since then, much time and money has been spent to duplicate the cracks deliberately and discover
the cause. But duplication has not been possible. 'l'he cause can be deduced only from circumstantial
evidence.
Part of the trouble seems to be attributable t.o the difficulty of getting welding rods that match the
strength of the alloy steel. If this is true, special care should be taken to insure quality. A tack
weld should be treated as meticulously as a major weld.
Use, care, and handling of low-hydrogen rods and proper selection of combinations of wire and
flux become very important with higher-strength steels. So does general house-keeping in the shop;
dirt and moisture must be excluded. Welding high-strength steel is a precision operation, not to be
undertaken casually or haphazardly. With proper care and attention to detail, successful welds are
assured".
111
APPENDIX 5.
Results of Tests on Sampfegfrom W.l4 Girder.,, Extmctedjiom D.S.L. Report, Ex. 194.
These surveys were made using an adaption of the B.W.R.A. method with a 5 kg. indenting load. A
number of traverses from parent plate to weld pool were made through the H.A.Z. of representative welds. Peak
hardness values of each traverse were noted and from these aYerage peak Hv. for each weld was determined.
The maximum Hv. obtained in each H.A.Z. is also quoted.
Hardnes
Girder Sample Zone
Av. 11!ax.
Parent Weld
Peak Plate Deposit
W.l4~S1~ Automatic Weld Web to Flange H.A.Z. (Western 370 385 205 210
North end Flange Side)
W.14-S3- Automatic Weld Co,er Flange H.A.Z. .. .. 410 425 195 235
North end Plate t.o Flange
Cover Plate H.A.Z. .. .. 400 205 235
1-
Manual Transverse Weld Flange H.A.Z. (2nd Fillet) .. 370 ]95 230
Cover }>]ate to Flange
I
Cover Plate H.A.Z. (3rd 365 385 205 230
Fillet) i I
i-
Manual Taper Weld Cover Flange H.A.Z. (3rd Fillet) 475 485 180 230
Plate to Flange (Eastern i
Side) Cover Plate H.A.Z. (2nd .. 325 205 230
Fillet)
Manual Taper Weld Cover Flange H.A.Z. (3nl Fillet) 470 485 HlO 235
i
Plate to Flange (Western
Side) Cover Plate H.A.Z. (2nd .. 345 205 235
Fillet)
W.14-S2~ Manual Transverse Weld Flange H.A.Z. (2nd Fillet) .. 390 185 235
South end Cover Plate to Flange
Cover Plate H.A.Z. (3rd .. 350 181'> 240
l!'illet)
Manual Taper Weld Cover Flange H.A.Z. (3rd Fillet) .. 435 210 240
Plate to Flange (Eastern
Side) Cover Plate H.A.Z. (2nd .. 255 190 240
Fillet)
I
112
APPENDIX 5-continued.
" "
North of S. ll'mcture S1F .. 2!} 176 25 34 o:n 020 ..
1~-
-1 -
s 2 Plate 1, Xorth end '' CRB/44 2.~ 178 24
Plate 1, above Xorth end of N2F 27 177 25 33 034 021 011
Cover
I j~-
I
s 3 Plate 2, North end .. CRB/45 I 28 180 25 !
1
Cinlel' <Hrd1r Loeatio11 in (;jnltt' ~amvk
rompntunt . \\'.I+ (from :X. ewl) So.
!
F'lan.g<' ;)(} Plate I. near Xort.h end <'H 8. ;;u
(Bottonl)
.. Jl('<ll' Xorth cnd XIF
I'H8/til
:-; }
Plate I Xorth I'H.B/:i:!
"'"'
.. So nth l~:w I . <~H 8;.-,;~ ~7 l i~ 2'i
:-.; !l Pi at< I. !H':tl' Xorth end ('j{B, ;)H . :! ;""~ . 7:~ :!4
Konlh oi'X. l:'rntt !ll'P x:w :!f\ I I 7:~ . :.!:> ::!~ O:H 018 0(18
(Jorcw PJatr ~.t)7 ,:tl) 1\i H I PlatP l, North end :\"f{' OI!l
I
CCt\-er Pial<' ~.J:U41 :)8 . s !'In t (' :~. South PJld {neur H. Hit' I !12 OH tH 021 01:! '(l(kj
Fractur<> l
:\L\XGAXEi"lE PLUS CHROMlUM TOTALS, C:\LCl'LA.TED C...\.RBOX -r;Ql~l L\Ll<~XTS (C. E.)*
AND DF~RI\'J<JD WELDABI1Xl'Y lXDICEf:l (W.T.)*
::\In. \1'.1.
.\ PPEXI HX fi.
Fig. I. C'i'OiiS-~Pcti< lll thmngh a l)'Jii(al li!let WPld and 1hot.ogra J>li,.;,
Fig. 4. FraetJJr!' of ginhr W.14 4, nort lwrn I'll< [, Nhowing {'0\'Pl' plah nrl.
li. FPature~ of t.]l(e ~("\.Pll fmdnrf'> Ill thP fai I!'Cl \\'.14 SJI1tll.
i, Fmet-un ,,f girder \\'.14 -2, nort hrn !'JH[, lookinu,., sont.]J.
H. Jluctility tmn~ition Clll'\'!':< for B.~. !~tiS: 1!l+ I ;;tppj lWM[e m tlw l'nitt.!l Kingdom l !l:\ti I.
l<'ig. W. nnetilitr tran"ition ('11I'YP~ for B.N. !HiS: I !t11 stPel ~ll ppli<'<l for Kings Bridge.
~ 6"0
WE\..0
Fig. 1 - (continued} .
Fig. 2.
Fract ure in gird er W.l4- 2, so uth ern end, look ing south.
Fig. 3.
Fracture in girder W . l4- l , southern end, looking north .
Fig. 4.
Fracture of girder W.l4-4, northern end, showing cover plate end.
Fig . 6.-" Features of t he seven fractures in the fai Ied W . /4 span "
The legend app licable thereto is : -
Black .. Toe crack.
Red .. . . Priming paint.
Brown .. Pr imary brittle fracture.
Green Extens ion of primary brittle fracture pr ior to lOth Ju ly, 1962.
Yellow .. Fatigue fracture.
Blue .. Final fracture associ ated with the collapse .
STAC 2. -
FLA.NctE COMPo51T10N AND
'/ 1Z.oD'/ VALUES NEA.~ ~EA\ N'?55 !ZoD.~.\b.~j t1EAT N9 5G !ZOO J"t '~sf HEAl' NC? S~ IZOD . /_t. l\.~ .;
10t~2oF C. o 25/., 70f:~2. f= C. 0 2Gj. 70f:'.~7'F
T+-1 E .f='RA C. TUR E s . C . o-2Sf.. - -
Mrv. I?B/. 12.- 4 Mn.-. I 731 0
D. S.L-. 3 1 13 M~. 1 74% D.S.L. 37 1...<0
+-1 E-A.'T N 9 5 G . rzoojt.l k f c .... o'24-j.. c.-..
o24-f: 0
C.R-.B - Cif', 0 2A-1o C . R.. . B . oS '2-0
C, 02Gi., 700F. 32F: N. OOII% N. oooez N. ooo9%
M""-. 170% D .S .L
Cr- . 0 25/.. C ."D.,.'B . 44 2>0
N. ooio%
W\4:'1 Ul'{e.R.oi.<:.Et-1 NORI~ -r-I"D .
~EAT W ? 55 l l=o_.ll.lbsf "EAT N 5G I \=o.ft_1bsj HEAT N<'55 1 1ZOO.,It.llo,; "EA> N'? 55 1 \ZOO.,ilo. 1\.s .j.
G 0-25~ 70F.32F C. 025% 70~32F c. 02<0% 70.F.3'2f C . 0<2'2% J0F. 32F
M~.
Cr. 0 .2S%
N 0 12_%
J. 7Gj 0
0
le""
D.SL .
1'2.. 7 .
M... I 72 ;.
Cr. o 24-J.
N. o.oo9%
I OSl.-.
eR s.
'27
44 :2..4-
14 Mw. IBO f.
c..
N.
o 2 5%
ooll%,
I DSL
CP.e . 24
- -
B
Mw.
Cw.
N
\72/
024%
oooez
0
I DSL.
CP.B. 40
~7 26
'0\
'N'\41 S. f'P..S. SVP.F,._, CE. ~\4-2: S .F P...S.'SVA.~A.CE. W\4--3. S FR--S.SVP.FACE ''-'/14 4: 5 -f'R .sSuP.F,.._C
Fig. 5
Fig. 7
Fig. 8
T-tilCKNESS
---\-
--A 41'1
o--o B 5
Y.---')(, c . 7"
.a.-- e. tz'
c---c F \4!'
0 L-----------~----------------------------
0
-10. -20"' OCENT. +20" +eo +so"'
Temperature
Fig. 9.
HEA.T N9 T+-t!CKNE.SS
- 4 ~~~--
7j,t:il>ll
-
0--0 38
5~ s;s''
80
)(---')( 'o/4.
l-Et()
u..
I
>-
a..
0:::
<(40
I
u
Fig. 10.
fl-IO Cl
~ J::Ul)f\'1
~
~
1'1 )> )> (Jl
Cl n n :f Gi
m z
"m o z
""
-=
rr1
I
0 ~ \:l::, Cl
~"
11
F /anse P(ale 14
~~~ r- 1- -t-Sitf/eners 6'.f/@ 1-~1" c,_ .10
~h
, z 11
V Ni!6, 59 K 1/6 V
., .i! I
m ,Plate 16 K ~
I I
r
I
;s o"
A L 1----.:::f A.
12' o: } / :Y
1
10~0
11
Cover f'lal<?, Ou/s;'c/., CtiderJ W;4-1&4 ... ,.. tS! 0 V __.________. J
l- 17! 6' I 4 !J( f,~
1
J( 6.!'! 0" ,, , Ins/d.. (f J1. .:1 1- ;7.'6' ~
~I I
''
CIRJ)ER ELEVATION
::~;:-;af'1 ~==~~;~"::} f
~ 1l
~~ ~ ~
~C)~~
~~Cl
~ ~
I
0~::6~ ftc {on/ 17!14 ;v,..;,;
tu~So:>;
,
f.
1--' Si')
\.,] If']
I:>;
~~ fU
.. (,)
... ""\) .:(JETA!L, !NVfRTEb PLAN_~_L!L
'1 ~ ~~
,
-" <:)
.'N.:--..:~'
~ ~ ~
~ ~ Ul
!:') ~ ~
~ ~ ~ fra.:lured
~~
~ ~==~~==~====~
0 {j)
~
-
z'
Gl
fT1
~
0
""
NoJ Tram
lint'.;- .t S-t> -t 9-6
f
~t -1
I
9-6
'
~
<'oi> z
0 ~~ CI?OSS SECTIONAL ELEVATION THROIJCH - SPAN E /4 ANJ W 14 LtJOKINC SOUTII. Fig. ll
~ ~
Fig. 12.
SPAN N"
fA f7
~]ff[.::---,,-s--.,..."~~"-ffir--r~--
ELEVATION, ffLINDERS ST OVERPASS
I'IRS A ,_11.-- I ~- - 2 -;/ B
-]J:, ::, J -
,~
se s.s 71:
r-
IJC
c
""' 8S !JS s
I
10 ~ 11
IZ
~ I I I
sMIV 1.3
W'HfTI!'MAN ST. CITY ,!;/), INTERSECT/ON -1 ts--r
PIERS A -2~ 3 li.. -I 6 7 I() /I 12 13 I-I IS' /{j
t~ fA r;
!
~
SMNIV"r?TH
PlUS A'~- -I -
ITS
l!.- --:["
H~---
~C
i I A
(J) '!!;
ELEVATION I w. LOW LEVEL BRIDGE
Ul
-:. ~
1:\: 11'/1
ffi
>
II
0
'I)
I .,..:
-
' (J)
~ (J)
KIN&
i
(!
ST. 0::
LLI
c
z
l
lii
...J
LL
f'I.FR
~"'
-8-
z
<(
~ ~
~
....I
~ ~
<le
a.. ~ ~I
f'IF#
-9- ~
I f
...
~
~
!
\i
"'
<I:
(}rrd#r Nos.
I I I Il I I I
.IS/ 2 .I ~ 4 .I 1 IY.fSI.
E/6 51
I I I I II I I II I I II I I I I
Z .5 ~ 5 6 7 8 9 9 8 7 6 S 4 :J 2 /YIG.SI ;'17SI 2 5 + .l 2 /'V!lSI
CHECKED I I
DRAWING NO
1
B I I eoo'PL_AN~N~o'~-------1
KEY PLAN R23 00 120
A
INDIIEX DATE REVISION APPb. CHIEF PlANNER I I SUPERVISING ENGINEER
FJ!!t t...B.