DGCS Volume 1
DGCS Volume 1
DGCS Volume 1
Contents
ABBREVIATIONS ............................................................................................................................................... V
1 INTRODUCTION ..................................................................................................................................... 1-1
1.1 BACKGROUND ................................................................................................................................................ 1-1
1.2 SCOPE ........................................................................................................................................................... 1-1
1.3 PURPOSE ....................................................................................................................................................... 1-2
1.4 OVERVIEW ..................................................................................................................................................... 1-2
1.4.1 Volume 1 Introduction and Overview ............................................................................................... 1-2
1.4.2 Volume 2 Surveys and Site Investigation .......................................................................................... 1-2
1.4.3 Volume 3 Water Projects Design ...................................................................................................... 1-3
1.4.4 Volume 4 Highway Design ................................................................................................................ 1-3
1.4.5 Volume 5 Bridge Design .................................................................................................................... 1-3
1.4.6 Volume 6 Public Buildings and Other Related Structures Design .................................................... 1-3
2 DESIGN PREPARATION PROCESS ........................................................................................................ 2-1
2.1 LEGAL RESPONSIBILITIES ................................................................................................................................ 2-1
2.2 DESIGN PREPARATION PROCESS ...................................................................................................................... 2-1
2.2.1 New Infrastructure ............................................................................................................................... 2-2
2.2.2 Upgrading, Repairs and Retrofitting of Existing Infrastructure ........................................................ 2-2
2.3 DESIGN REVIEW ............................................................................................................................................. 2-3
2.3.1 Detailed Design Stage Review .............................................................................................................. 2-3
2.4 APPLICATION OF THE GUIDE ............................................................................................................................ 2-3
2.4.1 Context Sensitive Solutions .................................................................................................................. 2-4
2.5 RISK.............................................................................................................................................................. 2-5
3 DESIGN FOR EMERGENCY RESPONSE .................................................................................................. 3-1
3.1 EVALUATION.................................................................................................................................................. 3-1
3.2 TEMPORARY REPAIRS ..................................................................................................................................... 3-3
3.3 PERMANENT REPAIRS..................................................................................................................................... 3-3
4 SAFETY ................................................................................................................................................... 4-1
4.1 SAFE DESIGN ................................................................................................................................................. 4-1
4.1.1 Safety of Personnel and the Public....................................................................................................... 4-1
4.1.2 Working Environment.......................................................................................................................... 4-2
4.1.3 Particular Requirements for Site Investigation .................................................................................. 4-2
5 ENVIRONMENT ...................................................................................................................................... 5-1
5.1 LAWS, POLICIES AND PROCEDURAL REQUIREMENTS ON ENVIRONMENTAL PRESERVATION ................................... 5-1
5.2 ENVIRONMENTAL CONSIDERATIONS IN INFRASTRUCTURE DESIGN ...................................................................... 5-2
5.3 SOCIAL ENVIRONMENT CONSIDERATION IN INFRASTRUCTURE DESIGN ................................................................ 5-3
6 GENDER .................................................................................................................................................. 6-1
7 PROVISIONS FOR ACCESSIBILITY ........................................................................................................ 7-1
8 ENGINEERING PLANS/ DRAWINGS ...................................................................................................... 8-1
9 SCOPE AND LIMITATIONS OF THE DPWH DESIGN GUIDE ................................................................ 9-1
10 ALTERNATIVE DELIVERY METHODS ................................................................................................ 10-1
10.1 TRADITIONAL APPROACH .......................................................................................................................... 10-1
10.2 PERMITTED ALTERNATIVE METHODS ......................................................................................................... 10-1
10.3 NEW ALTERNATIVE METHODS ................................................................................................................... 10-2
10.4 DESIGN AND CONSTRUCT PROCUREMENT .................................................................................................... 10-3
10.5 PUBLIC PRIVATE PARTNERSHIP .................................................................................................................. 10-4
10.5.1 PPP in the Philippines ..................................................................................................................... 10-5
i
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
ii
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
Volumes
Volume 1 Introduction and Overview
Volume 2A GeoHazard Investigation
Volume 2B Engineering Surveys
Volume 2C Geological and Geotechnical Investigations
Volume 3 Water Projects Design
Volume 4 Highway Design
Volume 5 Bridge Design
Volume 6 Public Buildings and Other Related Structures
iii
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
TablesandFigures
Table 2-1 Qualitative Risk Analysis Matrix Level of Risk ...................................................................................................2-6
Table 2-2 Risk Assessment for Design ........................................................................................................................................2-6
iv
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
Abbreviations
Acronym Definition
AASHTO AmericanAssociationofStateHighwayandTransportationOfficials
CNC CertificateofNonCoverage
CSS ContextSensitiveSolutions
DENR DepartmentofEnvironmentandNaturalResources
DGCS DesignGuidelines,CriteriaandStandards
DOLE DepartmentofLaborandEmployment
DPWH DepartmentofPublicWorksandHighways
ECA EnvironmentalCriticalArea
ECC EnvironmentalComplianceCommitment
ECC EnvironmentalComplianceCertificate
EIA EnvironmentalImpactAssessment
EIARC EIAReviewCommittee
EISS EnvironmentalImpactStatementSystem
EMB EnvironmentalManagementBureau
IEE InitialEnvironmentalExamination
KPI KeyPerformanceIndicators
LRFD LoadandResistanceFactorDesign
MTPIP MediumTermPhilippineInvestmentPlan
NECA NonEnvironmentallyCriticalArea
OSHC OccupationalSafetyandHealthCenter
PDR ProjectDescriptionReport
PEIS ProgrammaticEnvironmentalImpactStatement
PHP PhilippinePesos
PICE PhilippineInstituteofCivilEngineers
PPE PersonalProtectiveEquipment
PPP PublicPrivatePartnership
RDIP RegionalDevelopmentInvestmentProgram
v
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
1 Introduction
1.1 Background
The six Volumes of the Design Guidelines, Criteria and Standards (DGCS) published
in the year 2015 replace the two Volumes of the DGCS published in 1984. This
guide will be the official guide for designs carried out within the Department of
Public Works and Highways (DPWH) or for DPWH.
The DPWH functions as the engineering arm of the Government of the Republic of
Philippines and as such is responsible for the establishment of appropriate design
standards for the purposes of ensuring the safety of public infrastructure and the
production of detailed designs for public engineering projects. The DGCS was
prepared to specify the design policies, standards and procedures that are used by
the DPWH and by consultants engaged by the DPWH.
1.2 Scope
The DGCS shall apply to the preparation of concept, preliminary and detailed
engineering for categories of infrastructure projects undertaken by DPWH
including stream and flood control, roads and bridges and buildings. It has not
been developed as a text book or a substitute for engineering knowledge,
experience or judgment. No attempt is made to detailed techniques for which
reference to appropriate technical studies and literature is required.
The DPWH DGCS also includes requirements for surveys, site investigations to be
undertaken for DPWH projects and shall be used as the basis for the preparation
of design and estimates of costs of projects.
The DPWH DGCS shall be used by all Regional Offices, District Engineering Offices,
Bureaus and Services of the DPWH and by consultants engaged by DPWH.
The design guidelines contained in the DPWH DGCS shall be governed by
applicable provisions of existing laws, codes (latest editions) and Departmental
issuances as identified in each of the Volumes.
Adherence to the provisions of the DGCS shall ensure that reasonably feasible and
economical designs should be developed for the preparation of detailed design of
projects.
In general, all structures shall be designed for all loads and loading conditions to
which they shall be subjected. Loads include dead loads, live loads, earth pressure,
wind loads, hydraulic loads, traffic loads, impact loads and seismic loads which act
on parts or the entire structures. The effects of temperature variations, shrinkage
and swelling, long-term loadings, repetitive loadings and impact shall be
considered. The stability analysis of structures shall allow for construction
sequences. The design method for structures shall be based on load and resistance
factor design (LRFD) principles, also called limit state design.
All design shall adopt the Metric System of units.
11
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
All computations shall contain the scope of work, the design criteria, a description
of the calculations, and an explanation of any computer program output, supported
with sketches and shall be independently checked and approved.
Special specifications, to be used in conjunction with the DPWH Standard
Specification, shall be prepared for each project, to provide details of any non-
standard materials, processes or control.
Quantity estimates for each project, based on the detailed design drawings, shall
be prepared based on the DPWH standard quantities, to show quantities of
different items of work and shall form the basis of a Bill of Quantities to be
incorporated in the Contract Drawings.
1.3 Purpose
The purpose of the DGCS is to provide unity and uniformity of design in the
preparation of design for all classes of infrastructure projects undertaken by the
DPWH in accordance with following overriding requirements:
Ensure the safety of all infrastructure users and third parties.
Provide an adequate level of service for all infrastructure to meet the design
requirements.
Provide design structures for appropriate loads and load combinations.
1.4 Overview
The DPWH DGCS consists of six volumes:
12
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
13
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
21
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
When the work load is excessive and there are no resources available internally,
then some design work is outsourced to external consultants after going through
a procurement process to engage them. Designs completed by external consultants
are usually sent to BOD for review and recommending approval.
UPMO manages large projects including all foreign funded projects and some
locally funded projects. The design work for UPMO managed projects is usually
outsourced to external consultants. Those designs are reviewed and
recommended for approval by the BOD to higher authority before procurement
commences.
The design preparation process is defined in the DPWH Design Procedures
Manual. .
22
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
prepared to show the preparation of the areas to be repaired or retrofitted and the
scope of the work.
In all cases, a detailed inspection of the damaged infrastructure and the original
design drawings shall be undertaken to establish the cause(s) of any damage, to
ascertain if the original design was inadequate, and to recommend design changes
in the new work to reduce the risk of similar future damage. This inspection and
outcomes shall be documented in an inspection report.
Any systematic design deficiencies in the DGCS that lead to the wide occurrence of
the same or similar defects shall be identified and an analysis of the deficiencies
shall be undertaken to put forward changes to the DGCS to reduce the occurrence
of such issues.
The scope of the design review should vary depending on the magnitude of the
project. Where a project has significant technical issues, the appropriate design
experts (for example, geotechnical engineer) may be included in the review to
confirm that the technical issues are adequately addressed in the design.
23
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
The characteristics of the CSS process that will contribute to excellence include:
Communication with all stakeholders is open, honest, prompt, and continuous.
24
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
2.5 Risk
All engineering design activity involves risk and there is a balance between the
costs of construction of infrastructure and the safety of the infrastructure users. In
general, guidelines, design codes and standards are the principal tools in the
management of risk as these documents provide surety that infrastructure
designed in accordance with these documents have a high probability of
satisfactory service and minimization of the risk to infrastructure users.
Nevertheless designers of infrastructure are required to manage the risk in design,
to ensure the correct application of the guidelines, codes and standards.
Risk management is the implementation of a deliberate strategy to identify
hazards, assess the risks they pose and the elimination or control of those risks to
acceptable levels.
A hazard is something that has the potential to cause harm.
Risk is an expression of the extent of adverse impact that might arise from the
occurrence of a particular hazard.
Risk assessment is an evaluation of the level of risk, based on the level of adverse
impact, following the occurrence of a hazard and the likelihood of that interaction
occurring.
To assess a hazard, three decisions need to be made:
1. What is the hazard?
Assessing the risk of a hazard can be achieved using the risk matrix included in
Table 2-1. The risk increase as the likelihood and consequences of a hazard
increase.
25
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
Table21 QualitativeRiskAnalysisMatrixLevelofRisk
Consequences
Likelihood
Insignificant Minor Moderate Major Catastrophic
Almostcertain M H H E E
Likely M M H H E
Possible L M M H E
Unlikely L M M M H
Rare L L M M M
Projects assessed as being at extreme-risk (E) shall require a detailed action plan
to demonstrate how the hazards will be addressed in the design.
Projects assessed as being at high-risk (H) shall include the attention of senior
management to ensure that the risks have been considered in the design.
Projects assessed as being at moderate-risk (M) require increased management
responsibility to ensure that appropriate designs are prepared.
Projects assessed as being at low-risk (L) may be managed using routine
procedures.
The project risk needs to be determined for each project as the extent of work
required to be undertaken for each project design will depend on the project risk.
More demanding projects or projects where the potential costs and impact of
failure are high require more oversight and assessment during the design process.
The assessment of project risk should consider the complexity, importance, safety
and cost of the project. Typical criteria that may be used in the assessment are
listed in Table 2-2.
Table22 RiskAssessmentforDesign
26
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
27
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
Temporary repairs
Permanent repairs
3.1 Evaluation
Evaluation of the requirements of any emergency response is critical to:
Recognize the scale of the disaster.
31
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
DPWH should maintain emergency response plans with contact details for
engineering staff in each Regional and District Engineering Office to enable staff to
be mobilized quickly and aware of their functions and responsibilities.
The evaluation is critical to determine the extent of damage to public
infrastructure, and to identify those parts of the public infrastructure that are
unusable and are hindering access into the disaster areas.
The general procedure would be:
Conduct rapid inspections by road, helicopter or boat to determine the general
extent of damage to infrastructure, record lists of observed damage.
Conduct quick inspection of standing structures such as bridges to confirm if
they are in a fit condition to carry traffic.
Conduct quick inspection of buildings to determine if they have suffered
damage, if they can be utilized albeit with damage, or if temporary repairs
would enable their use. This may require the use of tarpaulins, for example,
where rooks have been blown off by typhoons.
Conduct quick inspection of failed structures to determine option for
temporary replacement, for example use of Bailey bridges.
Conduct quick inspection of other listed infrastructure to type and scale of
necessary temporary works; for example, estimate the volume to restore a
slumped section of road.
Assess which infrastructure can be quickly returned to service or which have
to be returned to service. Prioritize the temporary repairs considering
availability of usable alternative routes, most important routes, and needs of
emergency response routes.
Design emergency repair works (matchbox design). Temporary designs would
normally be rule-of-thumb by the DPWH engineers on-the-ground to enable
work to commence. This could be followed-up later with design DPWH staff to
confirm the work underway and to incorporate appropriate modifications if
necessary.
32
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
The Engineers in the Regional and District Engineering offices where a disaster
occurs should be familiar with the local infrastructure to enable the evaluation to
be quickly undertaken.
The emergency works may be phased, for example the initial repair to a critical
bridge may be a simple earthwork to enable emergency response vehicles to cross
the bridge at low speed with follow-up earthworks later to enable the use of all
traffic lanes and/or higher speeds.
The only issue that may delay the temporary repairs would be the allocation of
funds which would be obtained through the emergency services.
The temporary measures are only intended to remain until permanent repairs to
or replacement of damaged infrastructure can be implemented. Where necessary,
temporary repairs would be closely monitored to detect any further deterioration
of damaged infrastructure. Damaged structures may have hidden damage that is
accelerated by normal working conditions and ongoing deterioration may increase
the risk to the infrastructure users and third parties. Some damaged infrastructure
may require ongoing work to maintain public safety.
Temporary repairs would be undertaken on an ad hoc basis using emergency
response funding.
33
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
Minor and major damage to infrastructure and the need to replace damaged
infrastructure should be identified.
All permanent repairs shall be undertaken in full compliance with the DGCS.
Priority in undertaking permanent repairs should be given to damaged
infrastructure that is essential to the local communities and to infrastructure that
has experienced significant damage.
34
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
4 Safety
Safety is a key parameter for the design of infrastructure to minimize the risk to
health and safety of all persons involved throughout the life of infrastructure,
including design, construction, operation, maintenance and eventual removal.
Materials to be used.
Subsurface investigation.
Geohazard assessment.
Safe design also applies during design development and detailed design to ensure
that all necessary safety features are included in the design, in accordance with the
requirement of the DPWH DGCS.
41
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
Rule 1080 of the provision contains the Personal Protective Equipment (PPE) and
Devices in which the following PPEs may be necessary:
Rule 1082 Eye and Face Protection
42
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
5 Environment
Designers must consider environmental factors in the design of infrastructure to
ensure that the adverse impacts on environment are minimized by adopting
suitable and appropriate design standards. Environmental considerations must
be identified, assessed and mitigation measures provided at early stages of design
to avoid major changes and costly variations in the future.
This Chapter only provides a brief description of environmental considerations in
relation to infrastructure design as a general guide only. For more information on
systematic Environment Impact Assessments and other environmental studies
and assessments, the readers should refer to other documents specialized in this
field. Some of the documents that the readers may refer to are provided in the
sections below.
51
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
Impacts on water resources around the area including both surface water and
ground water resources.
Impact of risk of flood and consequences of flood affecting the environment.
Impacts from energy use during construction and operation of machinery and
equipment, transportation, lighting and other electricity use.
Impacts due to possible contamination with construction materials and/or
construction waste.
Impacts on the local community, local and non-local economy and the built and
natural environment.
52
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
53
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
6 Gender
Gender shall be considered in the design all infrastructure projects to ensure that
adequate provisions are included in projects to improve the function of new
infrastructure for the users and third parties, especially women, and to address
gender issues included in policies and strategies for infrastructure development.
The incorporation of gender into the design process requires an understanding of
the different living conditions and needs of women and men at project planning
stage, and taking these requirements into account in the design and
implementation of projects.
Gender policies include:
Women and men must equally participate in climate change, disaster risk
reduction, decision-making processes and other government programs at
community, regional and nationwide levels.
Integration of gender-sensitive criteria into planning, design implementation,
monitoring and evaluation of programs, projects and initiative.
Allocation of adequate resources to address the needs of women, for example
by funding appropriate, environmentally sound technologies and supporting
womens grassroots initiatives in sustainable use of natural resources.
The implementation of these-policies requires the inclusion of appropriate
activities in the design process, including but not limited to the following;
Undertake environmental planning through public consultation and/or
stakeholders forums, and identify gender issues and concerns in the
involvement of women, youth, senior citizens and persons with disability in
infrastructure development. Women should constitute at least 30% of the total
participants.
Develop gender-based information within the influence area of the proposed
project.
Conduct social gender analysis such as trend of employment of women at all
levels (actual construction, technical and management) in infrastructure
projects or services, capacity of women to influence decisions about the
planning design, operation and maintenance of infrastructure facilities;
resettlement of women and their families as a result of the construction of
infrastructure; access of women to water, and health and transport services.
Maintain existing cross communication routes such as foot paths where
crossed by new infrastructure and maintain the amenity and usability of
existing infrastructure adjacent to new work.
Identify appropriate public infrastructure, for example access steps and
pathways to the water at dykes and bridges that may be included in
infrastructure projects to maintain and improve access for third parties.
Include appropriate works to enhance the safety of users and third parties
including pathways, guardrails, pedestrian bridges, and other safety facilities
and structures.
61
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
62
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
71
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
72
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
81
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
91
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
92
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
101
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
These forms of procurement are discussed in Section 10.4 and Section 10.5.
102
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
In this form of procurement, the contractor is responsible for the design and the
construction of the project.
The advantages of design and construct procurement are:
The design and construction are in the hands of the contractor, who is
responsible for design, quality, cost and schedule;
The contractor is able to submit a lower cost for the project as he has the ability
to tailor the design to suit his equipment, expertise, capability and resources;
The work can normally be completed earlier compared to the traditional
approach as the design and construction can overlap;
For complex infrastructure such as large bridges, this type of procurement is
essential as the design will depend on the method of construction of the
infrastructure; and
Innovative design solutions are developed that provide improved
infrastructure.
A successful design and construct contract does not happen by itself and will
require the DPWH to provide:
A detailed scope of work for the project that set out explicitly the performance
and requirements for the infrastructure; and
Adequate supervision of the contract to ensure that the completed works
comply with the requirements of the plans and DPWH DGCS.
Design and construct should be considered for the following types of
infrastructure projects:
103
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
Class C and Class D projects where the contractor may be able to offer lower
construction costs by tailoring the design to suit his equipment, expertise and
capability.
Large infrastructure projects that will be designed and constructed as a single
package where the component designs can be standardized to suit the project
requirements (this will already occur for road projects developed under a
PPP).
For a design and construct project, the DPWH shall undertake the design
development (preliminary design) but with the following modifications to the
requirements:
The design development drawings for the project shall be developed to show
the physical requirements of the project (for example, for bridges the
waterway area, design flood levels, deck level, number of lanes, walkways,
scour protection, river training) but will not define the form of the
infrastructure to be developed.
The project alignment shall be finalized.
104
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
- Initial preparation is on-going, for example the feasibility study has been
commenced.
Responsiveness to the sectors needs (for example, part of the transport
network system, water supply / sewerage, electric power capacity).
High implementability (bankable, no major issues).
The PPP process is a funding conduit for the development of infrastructure and the
form of implementation of the infrastructure included in a PPP project is a matter
for the developer. The most likely form would normally be a design, construct,
operate and transfer sub-project aligned to the PPP agreement under the aegis of
the developer based on the feasibility study report.
PPP project conditions should include compliance with all provisions of the DPWH
DGCS, including the submission of the design documentation to the DPWH, and
complying with all DPWH requirements. Design information that should be
supplied to DPWH includes:
Feasibility study reports.
105
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
All other reports and drawings prepared for the design and construction of the
projects.
106
DesignGuidelines,CriteriaandStandards:Volume1IntroductionandOverview
11 Revision
The DPWH DGCS is intended to be updated on a regular basis to reflect changes in
procedure, requirements, standards, materials and technology.
The Division Chiefs shall receive any comments on their discipline volumes of the
DGCS from BOD Divisions, Regional Offices, District Engineering Offices and
Consultants and shall maintain a register of comments and proposed
modifications.
A review should be undertaken by the Division Chiefs in the BOD of their discipline
volumes of the DGCS, on an annual basis and recommend revisions for
consideration by DPWH. The register of comments and proposed modifications
shall be the basis for the annual reviews.
Individual volumes or sections may be updated as required to incorporate
significant recommended revisions as developed from the annual reviews. It is
expected that individual volume may require revision at 5-year intervals.
111