Labour
Labour
SN
ITEM DESCRIPTION QUANTITY LABOUR ( 8 hours per day)
.
Note: For each additional storey, the strength should be increased by 6 nos. for
volume of 10 cu.m to lift the materials.
7. Brick on edge flooring with 100 m2 Head Mason 1/2, Mason 10, Labour
cement Mortar (1:3). 14, Bhisti 1
10. C.I. rain water pipe fixing. 9m Mason 1/2, Labour 2.5
11. 12mm thk cement plaster 100 m2 Head Mason 1, Mason 10, Labour
on brickwork in 1:6. 14, Bhisti 1
12. Ruled pointing (1:3). 100 m2 Head mason 1/2, Mason 10, Labour
9, Bhisti 1
16. Primer coat on wood 100 m2 Painter 2.5, Labour (Helper) 2.5
work/ steel work.
17. Panting two coats over 100 m2 Painter 5.5, Labour (Helper) 5.5
priming coat for new wood
work/steel work.
27. Wash Basin with C.I. 1 no. Plumber 1, Mason 1/2, Labour 1
brackets, brass taps, brass
plug with brass chain,
waste pipe Including
cutting walls and making
good the same.