Contract Negotiations
Contract Negotiations
Contract Negotiations
Contract Negotiations
Wendell C. Lawther
CONTENTS
28.1 Introduction........................................................................................................ 564
28.2 Negotiation during the Solicitation Development and Supplier Selection ........... 565
28.2.1 Planning for Negotiation ...................................................................... 565
28.2.1.1 Potential Changes in Key Management Personnel ............... 566
28.2.1.2 Additional Discussion of How Key Contract Goals
and Objectives Will Be Met ................................................. 566
28.2.1.3 Quality Assurance ............................................................... 566
28.2.1.4 Price/Cost ............................................................................ 566
28.2.1.5 Terms and Conditions ......................................................... 566
28.2.2 Choosing the Negotiation Team .......................................................... 567
28.2.2.1 Project Manager .................................................................. 567
28.2.2.2 Procurement Official ........................................................... 567
28.2.2.3 Technical Experts................................................................ 568
28.2.2.4 Financial Experts ................................................................ 568
28.2.2.5 Legal Experts ...................................................................... 568
28.2.3 Negotiation Approach .......................................................................... 568
28.2.4 Power Relationships during Negotiation .............................................. 569
28.3 Negotiation during the Contract Administration Phase ..................................... 570
28.4 Case Studies Illustrating Negotiation Approaches and Processes ........................ 571
28.4.1 Florida Master Leasing Procurement Approach .................................... 572
28.4.1.1 Negotiation Issues and Results: Cost ................................... 573
28.4.1.2 Negotiation Issues and Results: Space.................................. 574
28.4.1.3 Negotiation Issues and Results: Repair
and Maintenance ................................................................. 574
28.1 Introduction
Negotiations are applied in a variety of settings and experiences. They are valued when agreement
needs to be reached on issues where there is a divergence of opinion among affected parties. The
goal of an effective or successful negotiation should always be a result that is fair, based on objective
standards, and one that is concluded amicably and efficiently.
Downloaded by [RMIT University] at 21:50 09 February 2015
As public agencies enter into an increasing number of contracts with private and nonprofit
organizations, negotiation skills have become increasingly important for procurement officials and
program managers. For the purposes of this chapter, these skills include negotiation planning, cre-
ation of the negotiation team, and negotiation approach.
In addition, the advent of information technology (IT) has meant that public agencies are
entering into contracts of increasing complexity and sophistication. This trend has had at least two
profound impacts on contract negotiations: the complexity of negotiation content has increased
and the opportunity for program managers and procurement officials to gain knowledge through
negotiation has greatly expanded.
Government officials should have confidence that the contractor has the requisite skills and
knowledge to produce the contractual identified product or service. For noncomplex items, this
confidence can be based upon past work history, checking with other jurisdictions regarding past
performance, and industry standards. For complex products, those based on IT technology, for
example, it is expected that there will be a degree of customization1 needed for any given contract.
Negotiation can be a process in which the private contractor can educate and convince government
officials that the final product will be acceptable.
For many purchases of services and complex goods, negotiation skills are required throughout
the contact administration process. Traditionally, when making purchases that could be clearly
specified, negotiation was only required during the pre-contract award process. After contracts were
awarded, negotiation was required only when problems needed to be resolved.
Negotiations should take on different approaches depending on contract type, and depending
on the amount and type of information readily available. Depending on several factors, including
the amount of competition created in response to the invitation to bid (ITB) or request for pro-
posal (RFP), the closeness of the ratings for the offeror’s proposals, and the complexity of the final
product or service, a government negotiating team will spend a wide range of time in preparation
and in face-to-face negotiations.
The following discusses negotiation as it should be found in the public procurement cycle. Thai
(2004b) views this cycle as consisting of three phases:
For the purposes of this chapter, negotiation occurs primarily in the latter two phases. In
phase two, it is anticipated that negotiations during supplier selection may alter solicitation
© 2008 by Taylor & Francis Group, LLC.
and shape the final contract. Although negotiation needs and requirements differ in each
phase, the extent to which there is a complete understanding of how solicitation development
and supplier selection affects contract administration will greatly affect negotiation effective-
ness for each phase.
To further illustrate the negotiation approach and process, two case studies are provided that
provide some insights into how negotiation should occur throughout the public procurement pro-
cess. The state of Florida master lease procurement process illustrates the impact of supplier selec-
tion negotiations on a contract administration phase characterized by a high degree of customization.
The iFlorida conditions system procurement illustrates the need to negotiate rules, procedures, and
policies during solicitation development/supplier selection that anticipate the need for highly com-
plex negotiations during contract administration.
Downloaded by [RMIT University] at 21:50 09 February 2015
■ Identifying the key issues or questions that need to be resolved during negotiation
■ Choosing the negotiation team
■ Identifying whether negotiation training is required for any team members
■ Identifying weaknesses in knowledge and understanding among team members and other
key agency personnel, as well as ways by which this understanding can be increased before
negotiation
Ideally, the solicitation document should contain goals and objectives that then become evalua-
tion criteria during the offeror rating process. These same criteria should then furnish the basis for
some of the items that appear on a negotiation agenda. For example, negotiation issues should
appear from lower rated items and questions raised by members of the evaluation team that has
rated all responses. There may be aspects of the highest rated offering that were given low marks.
For example, if commitment to women minority enterprises in the offeror response is absent or
unclear, and it was stated in the RFP that this would be a criteria that would be evaluated, then the
© 2008 by Taylor & Francis Group, LLC.
negotiation team can gain assurances from the offeror that such a commitment will be present.
Issues to be resolved during negotiation include the following.
The RFP may specify that the winning contractor will have a specified amount of time (e.g., 90
days) to deliver drafts of specific policies (e.g., a procedures manual or training plan). Even though
a brief description of these deliverables may be part of the responses, the negotiation team may have
additional questions about what content is likely to appear in these deliverables.3
28.2.1.4 Price/Cost
For the acquisition of products that can be clearly specified, analyses of the cost of similar products
acquired by other government agencies may result in the need to negotiate the proposed cost as
stated by the winning offeror. Specified aspects of costs, such as the overhead rate, profit margins,
and administrative expenses may be analyzed (Karrass [1998] cited in Thai, 2004a).
Alternatively, there may be industry or marketplace standards. If an agency is negotiating a lease
with a landlord, and remodeling existing space is required, a comparison of the charges for specific
tasks to what other professionals may offer in the local labor market may lead to negotiations
(Lawther, 2007).
Also, to the extent that Harney’s statement is appropriate, the offeror may have artificially bid
the cost too high, expecting that the government agency may wish to negotiate for a more reason-
able cost (Dobler and Burt, 1996).
In contrast, however, it may be very difficult to negotiate price or cost in reference to other simi-
lar purchases or industry standards. To the extent that customization is required, for example, an
IT-based service that is specific to an agency’s needs, comparisons may be impossible. Also, a vendor
may offer software that has been developed for other clients, and charge the agency less because the
expertise gained by past efforts means the present response can be more efficient/cost less.
consultants accompany public officials filling team roles as discussed below, or consultants can
replace public officials in filling these roles.
negotiations. To some extent, this information can come from competing proposals.5 Although
specific competing proposals cannot be mentioned in the negotiation, prices mentioned in these
proposals can provide some insights into whether the prices of the top-rated offeror are fair and
reasonable. Information concerning market prices, however, may be best known by financial
experts. If a government is negotiating leases for building space with landlords, for example, knowl-
edge of the price per square foot in a given commercial market would best be conveyed during
negotiations by financial experts, who should become negotiating team members.
it should be agreed that any potential delays and unanticipated technical challenges should be
resolved within a specified time period.6
The existence and acceptance of a QC program as well as the resolution of implementation
difficulties can be negotiated during contract formation, but the rules, procedures, and unantici-
pated changes that may occur as the system is being built must be negotiated and resolved during
contract administration. This is true especially if proposed changes result in change orders and
higher costs. The negotiation process can employ the same processes and approaches as are pres-
ent in the contract formation phase, but there may be significant pressure to resolve differences
in shorter time frames.
decentralized, allowing specific issues to be negotiated between agency and landlord according to
industry standards. This process also gives DMS greater discretion to act as a landlord for all
state agencies, providing greater opportunity to colocate state agency personnel where possible
(Marsiglio, 2004).
The solicitation development phase begins with agencies requesting additional space from
DMS. If no unused space exists, then agencies are permitted to solicit responses from landlords.
Staubach company representatives provide an initial market analysis of all responses, and partici-
pate as a member of the negotiating team after all responses are rated. The following provides a spe-
cific example of this master lease approach.
In July 2004, DMS announced an intent to consolidate 1.5 million square feet of space needs
into government centers, areas containing a relatively short distance among all buildings housing
state employees. After a lengthy solicitation and negotiation process, several leases were signed. One
of the resulting leases, known as the Koger Center Master Lease, included over 570,000 square feet
of office space in nineteen separate buildings for seven different state agencies.
Solicitation for this space resulted in responses from four landlords. As part of the evaluation
process, an outside consultant rated all proposed building space using the BOMA (Building
Owners and Managers Association) approach. Buildings were rated as A, B, C, or D. The ratings
were based on a number of criteria, including the following:
■ Physical inspection
■ Buildings’ age
■ Assessment of original construction and any subsequent refurbishing
■ Any perceived management issues, compared to the market
■ Any amenities such as distance to restaurants, appearance of outside common areas, etc.
This information, along with Staubach provided market analysis, provided additional analysis for
both the response rating and the concurrent negotiation process that occurred with these four
landlords. These negotiations took place during September 27–30, 2004.
The goals discussed in the solicitation document constituted much of the response rating crite-
ria, and served as the basis for negotiations during supplier selection. Issues regarding price described
the intent of the state to include low-cost rental rates, more efficient planning and tenant improve-
ment allowances, and creative mechanisms that will provide immediate financial relief to the state.
Moving costs were also to be considered.
Negotiations depended on the amounts for each category identified by each respondent, as well
as how each issue impacted another. For example, during the negotiations with one offeror, the
Staubach representative identified the market rate of rental increase in the region as approximately
3 percent per year, in contrast to the 4 percent identified by the offeror. The response from the
offeror was a suggestion to lower the rental increase rate to 2 percent, but all increases in operating
costs would be paid by the state. The public negotiating team was not willing to accept this offer,
stating in fairness that all rate increases had to include operating costs, as this issue was identified
in the solicitation document.
Three aspects of the tenant improvement funds proved important:
■ Amount that depended on the perceived need for refurbishing as well as the amount of
occupied space
■ Control over the disbursement of these funds, that is, whether the landlord or agency
personnel would decide when funds would be spent for what purpose
■ Timing and the process by which these funds would be disbursed
In past leasing contracts, without negotiation, the landlord would determine the amount
needed for refurbishing depending upon the agency request. Landlords would also determine when
and how the funds would be spent, as long as agreed upon moving deadlines were met. However,
if there were delays, state agencies were often placed in uncomfortable positions of adjusting plans,
leading in some cases to lower service quality.
state and the landlord. If space becomes vacant, two actions are possible. First, DMS promised
to try to fill that space with employees from other state agencies. Second, the state of Florida can
sublet space to private companies. If this occurs, any profit from this subletting is split evenly
between the state and the landlord.
The FDOT District Five, the district with responsibility for serving central Florida, issued a solici-
Downloaded by [RMIT University] at 21:50 09 February 2015
tation document on September 30, 2003 (Florida DOT, 2003a). The document contained a quali-
fications questionnaire, composed of questions that were designed to not only determine and
evaluate offerors past performance and management and technical capabilities, but also served as
criteria that influenced negotiations.
The total of 21 questions (Florida DOT, 2003b, p. 1) included the following:
■ Has your firm been a developer or integrator of transportation systems and software systems of the
level and complexity as described [in the appendices] for a period of time of no less than five years?
If yes, how long … and describe the services. Also attach a list of software work references.
■ What software languages and operating systems does your firm have expertise in?
■ Please provide a proposed staffing chart and management plan for the project.
■ Please describe the software development environment and facilities your firm uses to
develop and manage software.
■ Does your firm have a formal, documented process for configuration management of your
products?
■ Does your firm have a formal documented software quality assurance program?
■ How will you test the subsystem software before final acceptance testing?
identifying when a problem occurred, when it was solved, and what methods were used to solve it.
Periodically, public technical representatives would review this log, categorizing problems as high
priority and low priority and assessing to what extent problems were solved. By implication, not
only did this approach ensure a quality check, but it also allowed for negotiation that would lead to
a satisfactory outcome for both CRC and public agency representatives.
Overall, negotiations conveyed a sense that public managers wished to work closely with CRC,
understanding that some requirements may need to change as the project evolved. It was stated that
as the condition interfaces were created, CRC should identify aspects of the functional requirements
that would be difficult to meet. In response, the FDOT managers would have the opportunity to
change or eliminate the requirement.
The negotiations were deemed a success by the public managers. On the second day of negotia-
tions, CRC provided draft language involving changes that were agreed upon during the first day.
A contract was awarded on January 12, 2004.
The complexity of the final product in this case meant that negotiations during the supplier
selection process also to some extent changed the scope of the solicitation. Negotiations during this
first phase identified some processes and procedures that were intended to govern future interac-
tions and negotiations as more specific parts of the system were created. Although the final product
could be adequately conceptualized by both public agencies and the private contractor before con-
tract award, all recognized that many of the final details would not become apparent until actual
system creation occurred.
28.5 Conclusion
In an era of increasing collaborative public management,7 in which public agencies enter into inter-
organizational relationships that help them better accomplish organizational goals, negotiation
skills are becoming far more necessary than in the past. Many public–private partnerships are based
on relationships that are framed by contracts (Klitgaard and Treverton, 2004). Choosing the best
partner(s) entails using negotiation skills in ways that are applicable to all supplier selection pro-
cesses. What is challenging for many public officials involved in procurement, however, is acting in
ways that effectively represent the public interest while interacting with partners over a much lon-
ger period of time in creating a complex product or service.
The contract administration phase, in many cases, requires the same negotiation skills that for
simple purchases only existed for solicitation development and supplier selection. Problem solving
Notes
1. Customization can be defined as the degree to which the service or product must be altered to meet the
unique needs of the client agency for purpose of increasing quality while decreasing price (Rothman, 2004).
2. In some cases, for example, in the state of Florida, using a concurrent form of negotiation means that more
than one offeror may be negotiated within a proscribed timeframe. See Lawther (2003) for more discussion.
3. Even when employing performance-based contracting, there should be some discussion of process to assure
agency personnel that contractors are capable.
Downloaded by [RMIT University] at 21:50 09 February 2015
4. This is especially true if the contract is among several public agencies, and one agency will be designated the
lead agency: the one given the most responsibility for postcontract award management.
5. Of course, no auction bidding is permitted. This is in violation of FAR (Federal Acquisition Regulation)
standards, and is viewed as an unethical practice.
6. See Lawther (2006) for more discussion.
7. The January 2007 issue of Public Administration Review contains further discussion of collaborative public
management.
References
Adler, J. 2007. Construction Contracting Methods. Unpublished manuscript.
Ashford, S. 2004. Commercial negotiation skills. Industrial and Commercial Training 36(6): 229–233.
Bingham, L.B. 1996. Negotiating for the public good. In: J.L. Perry (Ed.), Handbook of Public Administration.
San Francisco, CA: Jossey-Bass, pp. 647–664.
Brown, M.M. 2001. The benefit and costs of information technology innovations: An empirical assessment
of a local government agency. Public Performance & Management Review 24(4): 351–366.
Callendar, G., Jamieson, D., and Vincent, K. 2004. Software costing analysis model for evaluating value
for money. In: K.V. Thai, A. Araujo, R.Y. Carter, G. Callendar, D. Drabkin, R. Grimm, K. Jensen,
R.E. Lloyd, C. McCue, and J. Telgen (Eds.), Challenges in Public Procurement: An International
Perspective, Vol. 3. Boca Raton, FL: PRAcademics Press, pp. 81–103.
Dobler, D.W. and Burt, D.N. 1996. Purchasing and Supply Management: Text and Cases. New York:
McGraw-Hill.
Fisher, R. and Ury, W. 1991. Getting to Yes: Negotiating Agreement without Giving In, 2nd ed. New York:
Penguin Books.
Florida Department of Transportation, District Five (FDOT). 2003. Appendix A: Scope of Work for iFlorida
Conditions System. Deland, FL: Author.
Hall, L. (Ed.). 1993. Negotiation: Strategies for Mutual Gain. Newbury Park, CA: SAGE Publications.
Harney, D.F. 1992. Service Contracting: A Local Government Guide. Washington, DC: International City/
County Management Association.
Karrass, C.L. 1998. Tips for team negotiators. Purchasing Magazine 125(9): 24.
Kelman, S. 1990. Procurement and Public Management: The Fear of Discretion and the Quality of Government
Performance. Washington, DC: The AEI Press.
Klitgaard, R. and Treverton, G.F. 2004. Assessing partnerships: New forms of collaboration. In: J.M.
Kamensky and T.J. Burlin (Eds.), Collaboration: Using Networks and Partnerships. Lanham, MD:
Rowman & Littlefield Publishers, Inc., pp. 21–60.
Thai, K.V. 2004a. Developing and Managing Requests for Proposals in the Public Sector. Herndon, VA: National
Institute of Government Purchasing.
Thai, K.V. 2004b. Introduction to Public Procurement. Herndon, VA: National Institute of Government
Purchasing.
Van Slyke, D.M. 2003. The myth of privatization in contracting for social services. Public Administration
Review 63(3): 296–315.
Welch, B. 2003. Best Practices in Federal Acquisition. The Public Manager 32(3): 11–17.