Cutoff-grade analysis at Fazenda Brasileiro: mine planning for

declining gold prices

A. J. Wheeler and Ruy L. Rodrigues

Synopsis
Underground working at the Fazenda Brasileiro gold
mine started in 1988. Initially, surface declines served
both access and production needs, but as the mine
deepened the development of a central ore-hoisting
shaft became necessary. The effects of increased mining
costs in recent years have been made worse by falls in
the gold price. Steps that have been taken in response
to improve the long-term economic future of the mine
include the development of a declining cutoff-grade
strategy. The main objective of this strategy, for imple-
mentation over the life of the mine, is to increase its net
present value. Incorporation of an opportunity cost ele-
ment in cutoff-grade calculations has led to higher
cutoff grades than were previously adopted. The appli-
cation of a declining cutoff-grade methodology also
assists in short-term decision-making with respect to
major variations in the gold price. Additonally, opera-
tional cutoff grades have been calculated, for both
mine-limited and mill-limited situations, to aid the
evaluation of different situations. Finally, the overall
long-term planning model developed for the cutoff-
grade study provides a means to analyse the sensitivity
of other mining parameters.
Fig. 1 Location map of Fazenda Brasileiro

The Fazenda Brasileiro gold mine is in Teofilndia, Bahia,


Brazil, some 210 km northwest of the city of Salvador The build-up of gold production is charted in Fig. 2, which
(Fig. 1). Its development is summarized by the following clearly shows the increase in production during the past
noteworthy dates: decade.
Au, kg
1972 Exploration for base metals started 6000 CIP + Heap-leach
1974 Itapicuru Greenstone Belt outlined
5000
1976 Gold discovered
1984 Open-pit and heap-leach plant start-up; 4000
Heap-leach only
25 000 t/month oxide ore 3000
1985 Underground exploration started 2000
1988 Underground mine start-up (25 000 t/month);
1000
carbon-in-pulp (CIP) process commissioned
0
1992 Expansion to 80 000 t/month
1999 Cumulative production reached 1 500 000 oz
Fig. 2 Production of gold over mine life
The mine currently produces approximately 5000 kg gold
each year, which accounts for roughly 30% of the total
gold output of Companhia Vale do Rio Doce (CVRD). The Geology
underground operations produce 1 000 000 t/year of sulphide
ore, which is fed to a CIP plant. There are approximately The Itapicuri Greenstone Belt trends northsouth, extending
1000 employees at the mine, including CVRD workers and for 100 km with a width of approximately 40 km, in the
contractors. The mine has had a significant economic impact northwest of Bahia State, Brazil. This belt is composed of
on the region, which formerly depended on agriculture and three major lithological domains: mafic, felsicintermediate
the production of sisal fibre. and sedimentary. Granitic bodies intrude all of the sequence.
The Fazenda Brasileiro deposit is located in the southern part
of this structure, hosted within a sheared mafic unit of the
Manuscript first received by the Institution of Mining and
eastwest-trending Weber Belt. The deposit is mesothermal
Metallurgy on 6 January, 2001; revised manuscript received on 21 and extends for some 13 km.
February, 2002. Paper published in Trans. Instn Min. Metall. (Sect. A: The Weber Belt is composed of a basal mafic unit and an
Min. technol.), 111, JanuaryApril 2002. The Institution of Mining upper volcano-sedimentary unit. It is set locally between
and Metallurgy 2002. basaltic rocks, with carbonatic sedimentary lenses of the
A35
Metasediments Volcaniclastics
Metagabbro Chlorite schistsore zones
Pyroclastics Gneiss
Metabasalts Volcano-sedimentsCanto Sequence

Fig. 3 Plan of southern part of Itapicuru Greenstone Belt

Riacho do Inco Sequence on the footwall and felsic volcano- waste development is completed each year.
sedimentary rocks of the Canto Sequence in the hanging- As footwall development becomes available reserve defini-
wall. The Weber Belt is also characterized by the presence of tion is based on infill drilling, utilizing sections spaced at
intrusive rocks of gabbroic to felsic composition. These intru- 25-m intervals. In some cases the spacing between sections
sions are associated with large structures where hydrothermal is reduced to 12.5 m. Diamond-drilling results are supple-
alteration can be observed. Fig. 3 shows a plan of the south mented with scan-line maps of development drifts and
part of the Itapicuru Greenstone Belt. samples of development jumbo and production fan-drill cut-
The main host rock for the mineralization is a magnetic tings. Access ramps are driven in the footwall to provide drill
schist (quartzchloritemagnetite schist), which occurs in two bases for infill diamond drilling. Development of the stopes
horizons to the south and north of the gabbroic unit. The and other mine infrastructure is undertaken from the access
mineralization dips 4050 southwards. The mineralized ore ramps.
shoots also tend to have a plunge of approximately 10 east- Geological data processing and mine planning make exten-
wards. Six main ore shoots have been mined so far and sive use of the Vulcan software system. It is employed for
various minor satellite orebodies are known. These ore shoots the interpretation of exploration information as well as the
occur in a portion of the Weber Belt approximately 8 km in design and subsequent processing of infill drilling data. These
strike length. The ore shoots are 200800 m long and 230 m data are then utilized for the design of ore development. After
wide. At present, the underground workings are 500 m deep excavation the roofs of development headings are mapped in
and mineralization has been intercepted down to a depth of detail. Samples are also taken from the drill-holes of every
800 m. third development blast to confirm the grade of mineraliza-
Initial exploration was generally based on surface diamond tion. After the completion of development work all available
drilling, employing a section spacing of 400 m along strike. information is used to reinterpret the geological model of
Definition of the most promising areas is accomplished by the mineralization. Whenever necessary fan drill-holes are
systematic reduction in the interval between geological drill drilled at 25-m spacing and the final ore contour is defined
sections from 400 to 100 m. In addition, the section spacing and the final block model generated. The solid model and the
of 100 m provides information with which to undertake the block model are subsequently used by rock mechanics staff to
design of primary access and infrastructure. More recently, design the final stope, with the objective of minimizing dilu-
exploration drifts have been excavated to provide access to tion and maximizing recovery. Grades in the resource block
the mineralization found at depth. Currently about 6000 m of model are derived as interpolated drill-hole composite grades.
A36
The grades originally come from fire-assaying of the drill-hole trucks at loading points 100150 m apart. Modern tech-
samples. A kriging method of interpolation is employed. niques and state-of-the-art equipment are used, enabling high
Once the final stope design has been completed the design productivity and standards of safety to be achieved. Getman
of production drilling takes place, for subsequent execution and Nitronobel auxiliary service vehicles are employed.
by the operations department. As stoping proceeds stope con- The sulphide ore is fed to a CIP plant, where it is crushed
tours are surveyed using laser total stations to check the in three stages and subsequently fed to one of two ball-mills.
actual recovery and dilution achieved. In this way it is possi- The milled pulp is cycloned and fed to Knelson or Falcon
ble to predict stope dilution and recovery factors and so concentrators. The concentrate is cleaned on vibrating tables,
enhance future mining design and production plans. producing 50% of the final gold. Afterwards the concentrate
Mine geology and mine planning processes are accom- pulp is passed to a thickener, where process water is recov-
plished with the aid of the tools of the Vulcan software ered. Thereafter, thickened pulp is transferred to two
system. Rock mechanics work utilizes the software packages cyanidation lines where dissolution of the gold takes place.
Examine2D and 3D and Phases, developed by the University Gold is adsorbed on to activated carbon, which is screened in
of Toronto, for numerical modelling of mine designs. In elution columns, and the gold is released. The pregnant solu-
addition, customized spreadsheets are used for specific rock tion is pumped to an electrowinning section to recover gold
mechanics design functions. on cathodes. Gold bullion at 90% Au is subsequently pro-
duced in the form of 12-kg bars.
Underground mining operation
Cutoff-grade optimization
Access from the surface to the underground mine is provided
by ramps of 5 m 5 m cross-section with a gradient of 15%. The original mine layout was influenced by the surface out-
A vertical shaft was commissioned in early 1999 to facilitate crop of the deposit. Thus, development of the underground
ore extraction from a depth of 400 m. Hoisting of run-of- mine started with a ramp system for access, services and
mine ore is less costly than hauling it to surface via the access haulage. This configuration contained the capital expenditure
ramp system. The shaft development is the first phase of the on underground access and infrastructure, thereby increasing
long-term plan to extract minerals from depth and further cash flows during the early years of production. However, as
deepening of the shaft is planned. the shallower orebodies were exhausted, deepening of the
The mining method is longitudinal sub-level retreat min- mine workings led inevitably to extended haulage distances
ing, employing remote scooptram loading. Sub-levels are and increased costs for development, extraction, ventilation
generally driven at vertical intervals from 13 to 15 m. Two- and general infrastructure. At the same time, exploration
boom electric-hydraulic jumbos, typically HL205S Tamrock from surface became increasingly difficult and more costly.
rigs, are used for the development of stope access and sub- All these factors led to the development of the recently com-
levels. A schematic overview of the stoping operations is pleted ore extraction shaft.
shown in Fig. 4. In addition to these challenges mining costs have been
continuously increasing and the gold price has been declin-
ing. These pressures have created the need to focus on key
aspects of mine planning. In particular, with the long strike
length of the deposit, the selection of ore blocks to be stoped
has a critical effect on the amount of developmentfor
required infill drilling access as well as for stope preparation
and subsequent mining. These problems have been further
compounded by the large proportion of inferred resources at
the mine and how these are best considered with respect to
long-term mine-planning decisions.
It was realized that a key element in addressing many of the
mine-planning issues was the cutoff grade. Accordingly, an
initial cutoff-grade study was completed at the mine towards
the end of 1996. This enabled an assessment of the potential
Fig. 4 Longitudinal sub-level retreat mining impact of cutoff grade and was followed up by further work
on cutoff grades, the results of which are described here.
The mine applies a practical minimum mining width of Another initiative was started to gain a better understanding
3 m. The maximum stope width is approximately 30 m, of, and engineering control of, ore dilution. This, in turn, has
which relates to the true thickness of the orebody. If the ore is led to some of the results of the cutoff-grade study being
greater than 10 m in horizontal thickness, separate parallel analysed with respect to variations in dilution.
panels are mined at about 12 m width. Atlas Copco Simba The most significant aspects of this cutoff-grade project
H253 fan-drill rigs are used for production drilling. The were: (i) establishing maximization of the mine net present
diameter of production drill-holes depends on the width of value (NPV) as the principal objective in the calculation of
the ore and the ring pattern. Drill patterns vary from 1.50 m cutoff grades; (ii) use of an opportunity cost in cutoff-grade
2.25 m for 64-mm holes to 1.75 2.60 m for 76-mm dia- calculation; (iii) consideration of a declining cutoff-grade
meter holes. ANFO explosives are widely used. Emulsion strategy as part of the life-of-mine plan; and (iv) ensuring that
explosives are used for primers and wet holes. Non-electric cutoff grades were applied and tested against approximately
detonation caps are employed for the initiation of production stope-size units of potential ore.
blasts. The way in which this cutoff-grade analyis was considered,
Ore and waste loading is carried out by 6- or 9-yd3 Toro with respect to long-term mine planning, is presented
400D and 501 loadhauldump vehicles. Hauling is per- schematically in Fig. 5. The geological tonnage and grade
formed by 20-, 30- or 40-t trucks (Volvo A-25 and A-35 and data were prepared so as to form an available reserve base.
Tamrock 40D). Ore and waste are mucked directly from A cutoff-grade analysis was then applied to determine which
blast faces by loadhauldump vehicles and loaded into parts of the deposit would be included in the long-term
A37
Fig. 5 Overview of cutoff-grade optimization

mining plan. This, in turn, could be used to assess primary structures were modelled initially within three-dimensional
development requirements. On the basis of known mining wireframe envelopes. These wireframe structures stem from
parameters a mine-life cash-flow analysis was then developed. the interpretation of potential ore structures on geological
However, the cutoff-grade analysis itself is affected by the sections, which were defined on the basis of drill-hole com-
predicted mine-life cash flow, as described in more detail posites across structures having an average grade greater than
later. One approach to this chicken-and-egg situation, there- or equal to approximately 3 g/t. Block models were then
fore, was to make initial assumptions and then to improve the created within these wireframe envelopes. The individual
overall model through repetition of the different stages and blocks measure 12.5 m (along strike) 1 m (across strike)
refinement of the various parameters. The objectives of this 2 m (along dip). These blocks were also rotated so as to fit
project were to produce a life-of-mine plan and an accom- in the best way with the overall 45 dip of the mineralized
panying, optimized cutoff-grade strategy. structures.
For cutoff-grade purposes it is important that these defined
Preparation of geological data orebodies are broken down into approximately stope-size
units. Selection above or below a cutoff grade can then take
Blocking-out of resources place at the same scale of selection as is used during the
The general way in which resource data were handled in this mine-planning process. An efficient method was developed
project is shown in Fig. 6. The initial part is the processing of using a customized Excel macro for the blocking-out of
modelled geological resources. All the currently delineated resources on any supplied stope grid size. This was developed
measured and indicated resources at the mine have been using Excels Visual Basic for Applications (VBA). The way
modelled with the Vulcan software system. The mineralized in which orebodies were blocked out through this macro is
A38
VULCAN

EXCEL

Fig. 6 Resource data handling

shown diagrammatically in Fig. 7. The first step was to cut stope grid size of 50 m (along strike) 20 m (vertically) was
through the three-dimensional block model on the basis of a applied, with a stope threshold tonnage of 5000 t.
stope block grid with supplied vertical and along-strike incre- The stope block evaluation macro ultimately determined
ments. Within each stope block the total volume, tonnage, the following quantities for each stope block:
metal content and physical coordinate limits were calculated.
The macro also made checks for excessively small stope ton- ID: identifier of each stope block, based on the name of the
nages that may be created at the edges of each orebody. Such parent orebody
small stopes were identified by their evaluated tonnage EASTING: bottom left easting of stope block, on stope grid
being below a given threshold. It is incorrect to include such system
stopes in the database for ore/waste selection on the basis of ELEVATION: bottom left elevation of stope block, on stope
their own contents, but as they can still represent an appre- grid system
ciable tonnage, it is incorrect to exclude them altogether. In XMIN: minimum easting of model cells within stope block
practice the sub-level stoping method is flexible enough to XMAX: maximum easting of model cells within stope block
have longer strike or vertical dimensions to deal with local ore ZMIN: minimum elevation of model cells within stope block
variations. A procedure was, therefore, developed to fold the ZMAX: maximum elevation of model cells within stope block
contents of these small stopes into the main orebody. When TONNES: total in-situ tonnes of each stope block
these small stopes are encountered their contents are added AU: average in-situ gold grade of each stope block
to the next adjacent full stope. This ensures that the com- AREA: area of each stope block, as viewed from long section
plete orebody tonnage and metal content become available in in a vertical plane
potential stopes for subsequent selection, with a selectivity THICK: average horizontal thickness of the material in each
still based on stope-size units. In the cutoff-grade study a stope block
A39
CLASS: number indicating resource classification of parent Table 1 Summary of stope block data
orebody
Number of orebodies Number of stope blocks
The coordinate extents and the average stope block thick- Mined Unmined Total Mined Unmined Total
ness were determined to assist in the subsequent calculations
Measured 12 32 44 101 104 205
of dilution and mining recovery. During this study separate
Indicated 19 19 172 172
block models for 63 orebodies were output from Vulcan and Total 12 51 63 101 276 377
then blocked out by the process described previously. The

number of stope blocks produced is summarized in Table 1.


Several of the orebodies supplied had already been mined
out, but it was considered important to input these data as
well for consideration of gradetonnage proportions in the
VULCAN ore deposit as a whole and for extrapolation when considering
inferred resources. Another macro was set up to assign a
SECTOR number to different parts of the mine. This assign-
ment could then be used at a later stage to apply different
EXCEL cost and operational data to various regions.

Stope block data handling


Once a stope block resource table had been produced it was
important to be able to produce longitudinal sections (vertical
projections) of the mine that depicted these data, both for
application in this cutoff-grade study and for more general
use in long-term planning at the mine. An Excel macro was
developed to allow quick and efficient production of such
longitudinal sections. Input to this macro consists of the
stope block resource table, a colour map, easting limits for
the long section and elevation limits. All stopes were anno-
tated with tonnage, Au grade and thickness and could be
colour-coded according to any of: AU, in-situ gold grade;
TONNES, in-situ tonnes; CLASS, resource classification;
THICK, horizontal thickness; or AU_CONTENT, con-
tained Au metal in grams. Other data connected with
extracted stopes could also be used to shade stope blocks that
had already been mined out or those above or below some
applied criterion.
Various existing stopes were analysed with regard to the
planned and unplanned dilution ascertained from production
results. The findings were compared with respect to varia-
tions in thickness as well as the shape factor, used in the
Mathews method of stability assessment. For the purposes of
overall mine cutoff-grade analysis the following base case
parameters were determined: dilution = 33%; and mining
recovery = 89%. These figures enabled an in-situ cutoff grade
to be determined relative to the calculated at-plant cutoff
grades. Excel macros that provided evaluation against a single
supplied cutoff grade, evaluation against different cutoff
grades by sector, evaluation by stope list and the generation
of tonnagegrade curves and associated grade interval data
were developed to facilitate evaluation of the available stope
block resource data.

Cutoff-grade analysismethodology

Optimum cutoff grades


For the purposes of cutoff-grade optimization it is important
to consider any mining operation as being composed of three
distinct phases, as shown in Table 2 for an underground
mining operation.1 This is because the most appropriate type,
and therefore calculation, of cutoff grade depends on which
particular stage is limiting the operation. Cost data should be
allocated according to the logical stage to which they belong.
The first stage is related to access; it depends mainly on the
physical size and location of the mineralized material at the
mine. At an underground mine the shafts and primary devel-
opment come into this category. The principal ramp systems
Fig. 7 Stope block evaluation are focused on access to certain areas of mineralized material.
A40
Table 2 Main stages of underground mining operation, for f
V+
(1 + d)
cutoff-grade analysis A
In situ Gtend =
NSR r (3)
Stage Principal component Operations
Optimization methodology
Access Mineralized material Shaft sinking,
Under normal conditions the opportunity cost is given by
primary development

Treatment Ore Stoping, tramming, F = c PV (4)


and stoping hoisting
Crushing, grinding, where c is cost of capital (e.g. 12%) and PV is present value
separating of the mine.
This opportunity cost can be thought of as the interest that
Marketing Metal Smelting, refining, could have been earned if the mines present value had been
selling deployed elsewhere. As the optimum cutoff grade at the pre-
sent time is a function of the opportunity cost, which will
normally decrease from year to year, the optimum cutoff
The amount (and therefore cost) of the primary development grade will also decline with time. However, the initial oppor-
is not directly affected by the amount of ore. tunity cost will itself depend on the cutoff strategy adopted
The second stage contains all activities associated primarily through the life of the mine as the cutoffs affect both cash
with ore. This includes the mill treatment costs and for flows and how many years of production are possible.
underground mines also all stoping-related work, ore haulage To determine an optimum cutoff-grade strategy, therefore,
and hoisting. Most underground metal mines are usually an initial opportunity cost can first be estimated according to
limited by their ore-handling capacity, i.e. their production an estimated mine life. This enables cutoffs and mine pro-
efforts are normally directed at keeping the mill at full capa- duction data to be generated. From these the present value
city. The rate and amount of access work are varied as and stope reserves for the mine can be estimated and then
required to ensure that the mill and ore-hoisting facilities are
kept at capacity.
The third stage contains those activities associated with
metal after it has left the milling processes. Gold mines are
almost never limited by this stage as there is usually no limit
to the amount of gold that can be sold.
Cost data were collated for individual activities at Fazenda
Brasileiro corresponding to these stages of the overall mining
operation. These data, prepared in Excel spreadsheet form,
were also linked with cash-flow models. This enabled the
parameters used in cutoff-grade determination to be directly
applied for the equivalent cash-flow analysis. For a mill-
limited mine the optimum cutoff grade is given by the
equation1
f +F
V +
Gt = A
(1)
NSR r

where V is variable cost per tonne of ore for operations


directly associated with stoping, haulage and treatment; f is
fixed (time) costs per year, which are not directly affected by
the quantity of mineralized material, ore or metal produced;
F is opportunity cost, which is the change predicted over the
next year in the mines present value; A is mill capacity,
t/year; NSR is net gold price per gram (as the grade will be in
grams per tonne), after deduction of any required refining
and marketing costs; and r is recovery of the treatment plant.
This is the cutoff grade that should be used to decide whether
any potential stoping block should be brought into produc-
tion. The Gt quantity described above is calculated in terms
of mined ore that will arrive at the mill. To calculate the
equivalent cutoff grade that pertains to in-situ ore the overall
mining dilution needs to be taken into account. Therefore

In-situ Gt = Gt (1 + d) (2)

where d is overall planned and unplanned dilution, expressed


as a ratio between waste dilution and original ore material.
At the end of the mine life the present value of the mine
will be zero. Therefore, at that time the opportunity cost will
also be zero. The optimum cutoff grade at the end of the
mine life will therefore be Fig. 8 Cutoff-grade analysis and underground design

A41
used in another iteration for the cutoff-grade calculations.2 Initial stope selection
This procedure is depicted in Fig. 8. Another important part The optimum cutoff grade described above is used for initial
of this overall process is to ensure that the production data stope selection. The opportunity cost, F, used in its calcula-
correspond with the assumed mining and development para- tion should reflect current economic conditions, as already
meters. For example, the production capacity must be described.
achievable with respect to the amount of primary develop-
f+ F
ment scheduled. During this cutoff-grade analysis these V +
different types of data were linked together by carefully struc- Gt1 = A
(1 + d ) (6)
NSR r
tured spreadsheets so that changes could be made efficiently.
After a number of iterations the cutoff-grade strategy, reserve
base and corresponding economic parameters should all cor- Stope planning when secondary development already complete
respond. An optimum cutoff-grade strategy, therefore, will Sometimes mining operations may have ceased after initial
normally have a declining cutoff grade from year to year. (secondary) stope development has been completed. When
Addition of the opportunity cost in cutoff-grade calculations deciding whether or not such stopes should now be reopened
will normally suggest higher cutoff grades than would other- for production a different cutoff grade should be considered.
wise be the case. However, it will lead to the highest possible For this cutoff grade the component of the variable mining
mine present value. Another important advantage of using costs that accounts for stope development should be
the opportunity cost is in the handling of changes in cutoff removed. This is because this money will already have been
grade with price variations, as described below. spent, regardless of whether or not the stope actually goes
into production. Hence
Price change effects
f+ F
The present value calculated for the mine will normally be a V2 +
function of the principal gold price being used for the major- In- situ Gt2 = A
(1 + d ) (7)
NSR r
ity of the mine life. If, in practice, the short-term gold price
suffers a major change that is considered temporary, it is pos-
sible to determine the most effective change to the current where V2 is variable ore costs, $/t, after stope development
cutoff grade. For example, consider the effect of the drop in costs have been deducted. This variable cost should then
gold price in 1999, assuming it to be temporary: include drilling, blasting, mucking, extraction and treatment.

Long-term gold price = $320/oz In-stope caved muck


Price in 1999 = $285/oz After or near the end of the extraction of planned ore from
Forecast to be produced in 1999 = 150 000 oz any given stope additional caved muck may be present, which
Current PV assumed (based on $320/oz) = $70 000 000 could be left in place or extracted as ore. To make this deci-
Discount rate = 12% sion the cutoff grade used should have had all the drilling,
Drop in revenue = 150 000 (320285) = $5 250 000 blasting and other costs removed from the variable costs:
Current mine PV = 70 5.25/(1 + 0.12) = $65 310 000
f+ F
V3 +
If the present value of the mine is assumed to recover to the In- situ Gt3 = A
(1 + d ) (8)
NSR r
same level a year later (with no appreciable drop in reserves),
the change in PV, dV/dT, is 70 65.31 = $4 690 000 and
opportunity cost, F, equals DV dV/dT where DV is interest where V3 is variable ore costs after all direct stoping costs
that could have been earned elsewhere and dV/dT is decline in have been deducted. This variable cost should then include
value due to deteriorating economic conditions. Hence mucking, extraction and treatment.

F = 0.12 65.31 4.69 = $3 150 000 Development muck


Development muck is currently produced from a number of
Because of this lower opportunity cost the optimum cutoff different headings. Most of it is trucked to surface, regardless
grade, as given by equation 1, will also be lower. This is con- of its contents. Therefore, to determine whether or not
firmed by common sense. Periods with a lower gold price, a such material should be treated as ore, only treatment costs
lower cutoff grade and, consequently, a lower head grade will should be included in the variable costs for the cutoff-grade
result in less gold being sold. However, when the gold price calculation:
rises the cutoff grade should be raised (owing to the increase
f+ F
in opportunity cost), resulting in more gold being sold at a V4 +
higher price. In- situ Gt4 = A
(1 + d ) (9)
NSR r
Operational cutoff grades
The optimum cutoff grades described above relate most where V4 is variable ore costs associated with treatment only.
directly to medium- and long-term mine planning. These
cutoff levels should be used to help to determine which possi- Mine-limited cutoff grades
ble stopes should be prepared for extraction. However, in the All the operational cutoff grades described above are based
day-to-day production environment, when various stopes are on the assumption that the mill is always operated at full
already in production and muck is being produced in many capacity, i.e. it is a mill-limited operation. From time to time,
different development headings, there are also a number of owing to operational problems, the mill may be starved of
operational cutoff grades that can be applied in the pursuit of oreit will then be operating below capacity. This situation
maximum economic benefit (highest present value). Details is mine-limited and different (lower) optimum cutoff grades
of the important operational cutoff grades identified in the should apply. When calculating mine-limited cutoff grades
context of the different phases of mining operations at fixed and opportunity cost components do not apply. Such
Fazenda Brasileiro are given below. mine-limited cutoff grades will only apply to in-stope caved
A42
Fig. 9 Tonnagegrade curves

muck and development muck, as it is hoped that long- and tions. Following this strategy will lead to the highest possible
medium-term mine planning are aimed at the mill being kept present value of the mine.
at full capacity. The mine-limited optimum cutoff grade for
in-stope caved muck will be given by Cut-off grade analysisresults

Assessment of resources
(1 + d)
V3
In- situ Gb3 =
NSR r (10) Gradetonnage curves for the measured and indicated
resource stope blocks are shown in Fig. 9. The y axis of these
where V3 is variable ore costs after all direct stoping costs curves represents the total proportion of either the measured
have been deducted. This variable cost should then include or indicated tonnage above cutoff. There is clearly very little
mucking, extraction and treatment. measured material below a cutoff of 5 g/t. At cutoff grades
The mine-limited optimum cutoff grade for development higher than 6 g/t the measured tonnage falls quite steeply.
muck will be given by The increase in grade with increasing cutoff is more gradual
for the measured stope blocks. For indicated resource stope
(1 + d)
V4
In- situ Gb4 = (11) blocks there is a much sharper drop in available tonnage for
NSR r
any cutoff grade between 1 and 10 g/t. For the same range in
where V4 is variable ore costs associated with treatment only. cutoff grades there is a fairly uniform increase in the average
These different operational cutoff grades should therefore grade of stope blocks above cutoff. This information shows
be applied for the appropriate locations and operating situa- that any imposed cutoff-grade strategy will have its greatest

Fig. 10 Projected area versus cutoff grade

A43
effect on indicated stope blocks. was developed using the system described above for the
This is also supported by a combined graph of the total pro- assessment of opportunity costs. This resulted in a cutoff
jected area (vertical plane) of available stope blocks above a grade of 6.0 g/t being used for indicated stope blocks in year
range of cutoff grades, as shown in Fig. 10. The total area of 2, followed by a cutoff grade of 4.8 g/t in year 3. For the
indicated blocks available is smaller and declines over a much inferred stope blocks a declining cutoff-grade strategy ranging
wider range of cutoff grades. Fig. 11 shows the average (hori- from 5.8 to 4.8 g/t was developed. The result of this strategy
zontal) thickness of available stope blocks against cutoff grade. was an eight-year mine life, with approximately an extra
Fig. 12 shows the variation in total metal content (gold, g) with 2 500 000 t of resource material being rejected. However, the
cutoff grade. This shows, more clearly than any of the previous overall benefit of this approach was to increase the mine NPV
plots, how much more gold is contained in the indicated stope to $68 700 000an increase of 60%. The assumption was
blocks and how changes in cutoff grade potentially have a made that such stope blocks at the higher earlier cutoff grades
greater effect on the indicated blocks. can be made available in time, but even if practical difficulties
restrict the grade of stope blocks available, it is clear that
Optimum cutoff-grade strategy pursuing such a declining cutoff-grade strategy produces eco-
For the base case set of resource blocks, using an overall nomic benefits.
dilution of 33% and a mining recovery of 89%, a life-of-mine For the purposes of sensitivity analysis these two operating
reserve depletion and cash-flow analysis were calculated. In scenarios, with and without cutoff-grade optimization, were
this analysis the only imposed cutoff grade was 3 g/t on the repeated for a number of different modifications with respect
indicated resource blocks, consistent with the geological (and to the base case: Table 3 gives a summary of these results,
previous mine-planning) cutoff used at the mine. This gave a comparing cases with different amounts of dilution. Alongside
mine life of 10 years and a resultant NPV of $42 900 000. the calculated NPV the resultant average Au reserve grades are
For the same base case an optimum cutoff-grade strategy given. The runs show that for a decrease, to 26%, in mining

Fig. 11 Average thickness versus cutoff grade

Fig. 12 Metal content versus cutoff grade

A44
Table 3 Effect of cutoff-grade strategy on NPV, $106 Operational cutoff grades
A set of operational cutoff grades, which applied to the cur-
33% Dilution 26% Dilution rent economic and operational conditions at the mine, was
NPV Au, g/t NPV Au, g/t calculated in accordance with the theory presented above
(Table 4). The opportunity cost used was that which
Non-optimized cutoff grade 43 4.7 56 5.0
reflected the low gold price of $285/oz. When the current
Optimized cutoff-grade strategy 68 5.5 82 5.8

Table 4 Operational cutoff grades

dilution higher present values are possible. A combination of Type Description In-situ cutoff grade, g/t
this dilution change and an optimal cutoff-grade strategy Mill-limited Mine-limited
almost doubles the original, unoptimized base-case NPV.
Similar alternative cash flows were produced by varying other Initial stope Application of all 4.7 n.a.
parameters, which included pessimistic what-if projection of selection relevant stope
preparation costs
lower head grades; different dilutions for alternative mining
After stope Stope development 3.6 n.a.
methods; and corresponding costs for higher-capacity bulk- development costs removed from
mining methods. The results from this work highlighted the complete variable costs/t
importance of focusing mining engineering efforts on the In-stope caved Drilling and blasting 3.4 1.3
reduction of dilution. These need to be supported by the muck costs also removed
determination of any mining cost changes and a sound basis Development Only treatment costs 1.2 0.9
for the subsequent prediction of dilution and mining recovery muck in variable cost
for long-term planning purposes needs to be established.
The conclusions of this work to devise an optimized cutoff-
grade strategy were as follows. gold price changes appreciably the operational cutoff grades
(1) Following a carefully planned declining cutoff-grade stra- at the mine can and should be revised. These cutoff grades
tegy will enhance the mines present value. are shown diagrammatically in Fig. 13. It is important that
(2) A pessimistic scenario with respect to the mined grades the mine-limited cutoff grades are applied only in situations
from the inferred resources deemed to be available would when the mill is starved, i.e. operating at a level lower than its
render an optimized cutoff-grade strategy even more vital. capacity.

Surface
Shaft

In-stope caved muck After stope development

3.4 g/t 3.6 g/t

Variable costs, Variable costs, stoping,


Development muck transport and treatment transport and treatment
1.2 g/t
Variable costs,
treatment only Initial stope selection

4.7 g/t

Variable costs, stope development,


stoping, transport and treatment

Fig. 13 Operational cutoff grades

(3) A decrease in dilution will also have an extremely positive Further work
effect on the mines present value. Quantifying the potential An inferred resource was also used in the project, being based
benefits should lead to a much better understanding of on the assumptions of (a) a fairly uniform incidence of ore
the relationship between dilution control and mining costs occurrences with depth and (b) a distribution of minable
and stimulate an improvement in methods and engineering blocks similar to that of the existing measured and indicated
control. blocks.
(4) Compared with the previous mine policy, use of an opti- It is known by geologists on site that initial exploration
mized cutoff-grade strategy will lead to a decrease in the drilling may well have missed occurrences of ore within the
mined ore tonnage of approximately 30%, whereas the mined CLX horizon. Mining and geological experience at the mine
gold will only decrease by approximately 14%. supports the occurrence of many potential ore blocks at a
(5) Decreasing the mining cost, at the expense of higher dilu- spatial frequency similar to that found in the upper regions of
tion, does not appear greatly to affect the mine NPV. the mine. To improve assessment of this inferred resource
Testwork was also done to see whether different haulage base and its potential effects on the mines future the geo-
distances to different parts of the mine might require local logical department intends to apply conditional simulation
cutoff-grade variations. The calculated cost variations were techniques. Besides assisting in the development of cutoff-
small and when combined with the other cost components in grade strategies it is intended that this will enable testing of
the cutoff-grade calculations their effects were negligible. the primary development layout and schedule with reference
A45
to the locations of potential stope blocks. It is also aimed at
enabling an appraisal of the uncertainty associated with the
inferred resource estimation.
A detailed risk analysis of the parameters involved in this
cutoff-grade analysis and other aspects of the long-term min-
ing plan has already been completed.

References
1. Lane K. F. The economic definition of ore (London: Mining
Journal Books, 1988).
2. Border S. N. Optimization of cut-off grades during design of
underground mines. Paper presented to Mining industry optimiza-
tion conference, Sydney, June, 1991.

Authors

A. J. Wheeler Member graduated as a mining engineer from


Camborne School of Mines in 1981. He gained an M.Sc. in mining
at Queens University, Canada, and worked in Canada for five
years before returning to the United Kingdom to join Datamine
International. For the past eight years he has been an independent
mining consultant specializing in computer applications.

Address: Cambrose Farm, Redruth, Cornwall TR16 4HT, England;


e-mail [email protected]

R. L. Rodrigues graduated as a mining engineer from Ouro Prto


School of Mines in 1986. After initial experience with Companhia
Vale do Rio Doce (CVRD) and BP he worked as a mining contract
manager for five years before rejoining CVRD as chief engineer at
Fazenda Brasileiro, Brazil. E-mail [email protected]