Profile On The Production of Jeans
Profile On The Production of Jeans
Profile On The Production of Jeans
TABLE OF CONTENTS
PAGE
I. SUMMARY
A. TECHNOLOGY
B. ENGINEERING
1
I. SUMMARY
This profile envisages the establishment of a plant for the production of jeans with a capacity of
150,000 pieces or 750 tons per annum. Jeans are now a days very popular article of casual dress
around the world.
The demand for jeans is met through import and domestic production. The present (2012)
unsatisfied demand for jeans is estimated at 3,324,161 pieces. The unsatisfied demand for jeans
is projected to reach 4,292,506 pieces and 5,908,767 pieces by the year 2017 and 2022,
respectively.
The principal raw materials required are fabrics dyed and finished with different colors which
have to be imported.
The total investment cost of the project including working capital is estimated at Birr 8.76
million. From the total investment cost the highest share (Birr 4.40 million or 50.18%) is
accounted by fixed investment cost followed by initial working capital (Birr 3.41 million or
38.87%) and pre operation cost (Birr 959.42 thousand or 10.95%). From the total investment
cost Birr 640.15 thousand or 7.30% is required in foreign currency.
The project is financially viable with an internal rate of return (IRR) of 21.31% and a net present
value (NPV) of Birr 5.96 million discounted at 10%.
The project can create employment for 46 persons. The establishment of such factory will have a
foreign exchange saving effect to the country by substituting the current imports. The project
will also create backward linkage with the textile manufacturing sub sector and also generates
income for the Government in terms of tax revenue and payroll tax.
Jeans is a type of read-made garments made from denim or dungaree cloth. Often the term
"jeans" refers to a particular style of pants called "blue jeans". Jeans are now a days very
popular article of casual dress around the world.
2
III. MARKET STUDY AND PLANT CAPACITY
A. MARKET STUDY
The demand for ready-made garments such as Jeans is met through imports and domestic
production. Customs data reveals that there has been export of ready-made garments since 2004.
Exports, on the average accounted for about 1.4% of domestic production during the period
2004-2011. The total supply of wearing apparel (ready-made garments), i.e. imported and
domestically produced garments net of exports, during 2000 - 2011 is depicted in Table 3.1.
Total supply varied from 1,203,936 pieces in 2000 to 16,487,293 pieces in 2008 and averaged
6,397,249 pieces during the period under reference.
Table 3.1
TOTAL SUPPLY OF WEARING APPAREL
(READY MADE GARMENTS)
Source: Report on Large and Medium Scale Manufacturing and Electricity Industries
Survey (CSA) for domestic production and Customs Data for imports and exports.
3
The country imports a variety of ready-made garments that are made of silk, wool, synthetic
fiber etc. Nevertheless, only selected products made of cotton has been analyzed for the purpose
of this project. The selected products are:
Men's or boys trousers & breeches of cotton,
Women's or girls trousers & breeches of cotton,
Men's or boy's jackets & blazers of cotton,
Women's or girls jackets & blazers of cotton, and
Skirts and divided skirts of cotton.
Imports of the above products compiled from the Customs data is presented in Table 3.2.
Table 3.2
IMPORT OF TROUSERS, JACKETS & SKIRTS OF COTTON (NO )
As could be seen from Table 3.2, the total import of Trousers, Jackets and Skirts of Cotton has
been generally rising during the period under consideration and stood at 3149911 in 2011. On
the average total imports of the products grew at the rate of 6.6% annually during the reference
period. On the average, imports of men's or boys trousers & breeches constituted the
overwhelming proportion (about 74.87%) of total imports. Imports of Women's or girls trousers
4
& breeches, men's or boy's jackets & blazers, women's or girls jackets & blazers, and skirts and
divided skirts on the average accounted for 7.09, 3.4, 12.6 and 2.04 percent of total imports,
respectively.
To determine the present unsatisfied demand for the four products under consideration the
average import of the period under consideration is first assumed to reflect the demand for the
year 2011. Then, an annual average growth rate of 6.6%, which is the observed average annual
growth rate during the reference period, is applied to arrive at the year 2012 demand. Thus, the
current total unsatisfied demand is estimated at 3,324,161.
The current unsatisfied demand estimated by type of product is worked out by taking their past
years share in the total import. Accordingly, the estimated demand for each product will be as
follows.
Table 3.3
THE PRESENT UNSATISFIED DEMAND FOR JEANS
Sr. Type Unsatisfied
No. demand (No.)
1 Men's or boys trousers & breeches of cotton,
2488799
2 Women's or girls trousers & breeches of cotton,
235683
3 Men's or boy's jackets & blazers of cotton,
113021.5
4 Women's or girls jackets & blazers of cotton, and
418844.3
5 Skirts and divided skirts of cotton.
67812.89
Total
3324161
2. Projected Demand
The demand for Jeans is mainly influenced by urban population growth and income rise. Hence,
an annual average growth rate of 6.6% is taken to forecast the future unsatisfied demand (see
Table 3.4)
5
Table 3.4
PROJECTED UNSATISFIED DEMAND FOR DIFFERENT TYPES OF JEANS
The price of jeans varies according to type such as trouser, jacket skirt etc. For the purpose of
financial analysis, an average factory gate price of Birr 120.68 is adopted based on previous
estimate for the price of the product and allowing for average annual price rise.
The products can find their market outlet through the existing ready-made garment distributing/
retailing enterprises.
1. Plant Capacity
The market study presented above indicates that the projected demand of jeans grows from
3,324,161 year 2013 to 5,908,767 by the year 2022. Jeans can be prepared in different sizes, and
are liked by all age groups, including children, adults, men and women. As the size of jeans
6
differs for different age groups, it would be necessary to take an average size to determine the
annual plant capacity. Accordingly, the envisaged plant will have annual production capacity of
750 tons corresponding to an estimated number of 150,000 pieces of jeans. The plant will
operate double shift of 16 hours a day, and for 300 days a year.
2. Production Programme
As it is the case for new plant, full capacity production can be attained by starting operations at
lower capacity in the initial year, and then building up production in the successive years.
Hence, production capacity will start at 75% in the first year, then grow to 85% the second year,
and reach of full capacity (100%) in the third year and then after.
Table 3.5
PRODUCTION PROGRAMME
Year 1 2 3
Capacity utilization (%) 75 85 100
Production (pcs) 112500 127500 150,000
Production(tons) 563 638 750
The major raw material required for the preparation of jeans is cotton fabrics dyed and finished
with different colours. The cotton fabric used for jeans preparation is usually a hard blue cotton
twill, also known as denion cloth. This material can either be imported or locally produced and
used for this purpose as long as it meets the required quality and specification.
Auxiliary materials consist of thread, zip fasteners, button, labels and packing materials. The
annual requirements of raw and auxiliary materials together with costs at full capacity production
of jeans production plant is given in Table 4.1.
7
Table 4.1
RAW AND AUXILIARY MATERIALS REQUIREMENT AND COST
B. UTILITIES
Utilities required by the plant consist of electricity and water. Electricity is required for lighting
purposes and running production equipment. Water is required for drinking and general
purposes. The total annual requirement of utilities is estimated at Birr 52,500 (see Table 4.2).
Table 4.2
TOTAL UTILITY REQUIREMENT AND COST
8
VI. TECHNOLOGY AND ENGINEERING
A. TECHNOLOGY
1. Production Process
To start with checking for proper width, color, texture and for possible faults are performed.
The fabric is, then, marked with the trace of the cutter and then lapped or folded into several
layers depending on the number of pieces needed. The lapping is done either by hand or by
using lapping trolley.
The material is, then, cut out, using various types of tools such as sword (long blade), the belt
saw or electric knives fitted with disc or vertical blades.
The pieces of material are then arranged and stitched together. Here, sewing machines are used.
The finishing operation includes inspection, ironing, folding and packing.
The production process involves masking, cutting, lapping as a major process. Such operations
do not have any negative environmental impact.
9
B. ENGINEERING
Total cost of machinery and equipment is Birr 721,150 of which Birr 640,150 is required in
foreign currency. Machinery and equipment required for the production of jeans is shown in
Table 5.1.
Table 5.1
MACHINERY AND EQUIPMENT REQUIRED BY JEANS PLANT
The total land area required is 1,000 m2 of which the built up area is 500 m2. This is supposed to
accommodate production hall, store for raw material and finished products, offices, and general
purpose building. Based on a unit area (per m2) of building cost of Birr 5000, the total building
cost will be Birr 2.5 million.
According to the Federal Legislation on the Lease Holding of Urban Land (Proclamation No
721/2004) in principle, urban land permit by lease is on auction or negotiation basis, however,
the time and condition of applying the proclamation shall be determined by the concerned
regional or city government depending on the level of development.
The legislation has also set the maximum on lease period and the payment of lease prices. The
lease period ranges from 99 years for education, cultural research health, sport, NGO , religious
10
and residential area to 80 years for industry and 70 years for trade while the lease payment
period ranges from 10 years to 60 years based on the towns grade and type of investment.
Moreover, advance payment of lease based on the type of investment ranges from 5% to
10%.The lease price is payable after the grace period annually. For those that pay the entire
amount of the lease will receive 0.5% discount from the total lease value and those that pay in
installments will be charged interest based on the prevailing interest rate of banks. Moreover,
based on the type of investment, two to seven years grace period shall also be provided.
However, the Federal Legislation on the Lease Holding of Urban Land apart from setting the
maximum has conferred on regional and city governments the power to issue regulations on the
exact terms based on the development level of each region.
In Addis Ababa, the Citys Land Administration and Development Authority is directly
responsible in dealing with matters concerning land. However, regarding the manufacturing
sector, industrial zone preparation is one of the strategic intervention measures adopted by the
City Administration for the promotion of the sector and all manufacturing projects are assumed
to be located in the developed industrial zones.
Regarding land allocation of industrial zones if the land requirement of the project is below 5000
m2, the land lease request is evaluated and decided upon by the Industrial Zone Development and
Coordination Committee of the Citys Investment Authority. However, if the land request is
above 5,000 m2, the request is evaluated by the Citys Investment Authority and passed with
recommendation to the Land Development and Administration Authority for decision, while the
lease price is the same for both cases.
Moreover, the Addis Ababa City Administration has recently adopted a new land lease floor
price for plots in the city. The new prices will be used as a benchmark for plots that are going to
be auctioned by the city government or transferred under the new Urban Lands Lease Holding
Proclamation.
11
The new regulation classified the city into three zones. The first Zone is Central Market District
Zone, which is classified in five levels and the floor land lease price ranges from Birr 1,686 to
Birr 894 per m2. The rate for Central Market District Zone will be applicable in most areas of the
city that are considered to be main business areas that entertain high level of business activities.
The second zone, Transitional Zone, will also have five levels and the floor land lease price
ranges from Birr 1,035 to Birr 555 per m2 .This zone includes places that are surrounding the city
and are occupied by mainly residential units and industries.
The last and the third zone, Expansion Zone, is classified into four levels and covers areas that
are considered to be in the outskirts of the city, where the city is expected to expand in the future.
The floor land lease price in the Expansion Zone ranges from Birr 355 to Birr 191 per m2 (see
Table 5.2).
Table 5.2
NEW LAND LEASE FLOOR PRICE FOR PLOTS IN ADDIS ABABA
Floor
Zone Level price/m2
1st 1686
2nd 1535
Central Market
District 3rd 1323
4th 1085
5th 894
1st 1035
2nd 935
Transitional zone 3rd 809
4th 685
5th 555
1st 355
2nd 299
Expansion zone
3rd 217
4th 191
12
Accordingly, in order to estimate the land lease cost of the project profiles it is assumed that all
new manufacturing projects will be located in industrial zones located in expansion zones.
Therefore, for the profile a land lease rate of Birr 266 per m2 which is equivalent to the average
floor price of plots located in expansion zone is adopted.
On the other hand, some of the investment incentives arranged by the Addis Ababa City
Administration on lease payment for industrial projects are granting longer grace period and
extending the lease payment period. The criterions are creation of job opportunity, foreign
exchange saving, investment capital and land utilization tendency etc. Accordingly, Table 5.3
shows incentives for lease payment.
Table 5.3
INCENTIVES FOR LEASE PAYMENT OF INDUSTRIAL PROJECTS
Payment
Grace Completion Down
Scored point period Period Payment
Above 75% 5 Years 30 Years 10%
From 50 - 75% 5 Years 28 Years 10%
From 25 - 49% 4 Years 25 Years 10%
For the purpose of this project profile the average i.e. five years grace period, 28 years payment
completion period and 10% down payment is used. The land lease period for industry is 60
years.
Accordingly, the total land lease cost at a rate of Birr 266 per m2 is estimated at Birr 266,000 of
which 10% or Birr 26,600 will be paid in advance. The remaining Birr 239,400 will be paid in
equal installments with in 28 years i.e. Birr 8,550 annually.
NB: The land issue in the above statement narrates or shows only Addis Ababas city
administration land lease price, policy and regulations.
Accordingly the project profile prepared based on the land lease price of Addis Ababa region.
To know land lease price, police and regulation of other regional state of the country updated
information is available at Ethiopian Investment Agencys website www.eia.gov.et on the factor
cost.
13
VI. HUMAN RESOURCE AND TRAINING REQUIREMENTS
The total human resource requirement of the plant, which includes both administration and
production workers, is 41 persons. Annual cost of labor is Birr 970,560.details of human
resource requirement by type of job and monthly and annual salary is indicated in Table 6.1.
Table 6.1
HUMAN RESOURCE REQUIREMENT AND LABOUR COST
B. TRAINING REQUIREMENT
Training of supervisor and production workers is required to upgrade the skill of jeans
production. For this local garment factories can provide the training in their premises. A total of
Birr 50,000 is sufficient to under take the training for a period of one month.
14
VII. FINANCIAL ANALYSIS
The financial analysis of the jeans project is based on the data presented in the previous chapters
and the following assumptions:-
The total investment cost of the project including working capital is estimated at Birr 8.76
million (See Table 7.1). From the total investment cost the highest share (Birr 4.40 million or
50.18%) is accounted by fixed investment cost followed by initial working capital (Birr 3.41
million or 38.87%) and pre operation cost (Birr 959.42 thousand or 10.95%). From the total
investment cost Birr 640.15 thousand or 7.30% is required in foreign currency.
Table 7.1
15
INITIAL INVESTMENT COST ( 000 Birr)
* N.B Pre operating cost include project implementation cost such as installation, startup,
commissioning, project engineering, project management etc and capitalized interest during
construction.
** The total working capital required at full capacity operation is Birr 4.56 million. However,
only the initial working capital of Birr 3.40 million during the first year of production is
assumed to be funded through external sources. During the remaining years the working
capital requirement will be financed by funds to be generated internally (for detail working
capital requirement see Appendix 7.A.1).
B. PRODUCTION COST
The annual production cost at full operation capacity is estimated at Birr 16.68 million (see Table
7.2). The cost of raw material account for 78.19% of the production cost. The other major
components of the production cost are cost of marketing and distribution, labour, administration
Costs, financial cost and depreciation, which account for 5.99%, 4.65%, 3.00%, 3.31%, and
3.16% respectively. The remaining 1.70% is the share of utility, repair and maintenance, labour
overhead and administration cost. For detail production cost see Appendix 7.A.2.
Table 7.2
16
ANNUAL PRODUCTION COST AT FULL CAPACITY (year three)
Items Cost
( 000 Birr) %
Raw Material and Inputs
13,042 78.19
Utilities
68 0.41
Maintenance and repair
22 0.13
Labour direct
776 4.65
Labour overheads
194 1.16
Administration Costs
500 3.00
Land lease cost
0 0.00
Cost of marketing and distribution
1,000 5.99
Total Operating Costs
15,602 93.54
Depreciation
526 3.16
Cost of Finance
552 3.31
Total Production Cost
16,681 100.00
C. FINANCIAL EVALUATION
1. Profitability
Based on the projected profit and loss statement, the project will generate a profit throughout its
operation life. Annual net profit after tax will grow from Birr 1.45 million to Birr 1.66 million
during the life of the project. Moreover, at the end of the project life the accumulated net cash
flow amounts to Birr 16.59 million. For profit and loss statement and cash flow projection see
Appendix 7.A.3 and 7.A.4 respectively.
2. Ratios
In financial analysis financial ratios and efficiency ratios are used as an index or yardstick for
evaluating the financial position of a firm. It is also an indicator for the strength and weakness of
the firm or a project. Using the year-end balance sheet figures and other relevant data, the most
important ratios such as return on sales which is computed by dividing net income by revenue,
return on assets (operating income divided by assets), return on equity (net profit divided by
17
equity) and return on total investment (net profit plus interest divided by total investment) has
been carried out over the period of the project life and all the results are found to be satisfactory.
3. Break-even Analysis
The break-even analysis establishes a relationship between operation costs and revenues. It
indicates the level at which costs and revenue are in equilibrium. To this end, the break-even
point for capacity utilization and sales value estimated by using income statement projection are
computed as followed.
Break Even Sales Value = Fixed Cost + Financial Cost = Birr 7,602,840
Variable Margin ratio (%)
Break Even Capacity utilization = Break even Sales Value X 100 = 43.62 %
Sales revenue
4. Pay-back Period
The pay-back period, also called pay off period is defined as the period required for recovering
the original investment outlay through the accumulated net cash flows earned by the project.
Accordingly, based on the projected cash flow it is estimated that the projects initial investment
will be fully recovered within 5 years
The internal rate of return (IRR) is the annualized effective compounded return rate that can be
earned on the invested capital, i.e., the yield on the investment. Put another way, the internal rate
of return for an investment is the discount rate that makes the net present value of the
investment's income stream total to zero. It is an indicator of the efficiency or quality of an
investment. A project is a good investment proposition if its IRR is greater than the rate of return
that could be earned by alternate investments or putting the money in a bank account.
Accordingly, the IRR of this project is computed to be 21.31% indicating the viability of the
project.
18
Net present value (NPV) is defined as the total present (discounted) value of a time series of cash
flows. NPV aggregates cash flows that occur during different periods of time during the life of a
project in to a common measuring unit i.e. present value. It is a standard method for using the
time value of money to appraise long-term projects. NPV is an indicator of how much value an
investment or project adds to the capital invested. In principle, a project is accepted if the NPV is
non-negative.
Accordingly, the net present value of the project at 10% discount rate is found to be Birr 5.96
million which is acceptable. For detail discounted cash flow see Appendix 7.A.5.
The project can create employment for 46 persons. The project will generate Birr 3.31 million in
terms of tax revenue. The establishment of such factory will have a foreign exchange saving
effect to the country by substituting the current imports. The project will also create backward
linkage with the textile manufacturing sub sector and also generates other income for the
Government.
19
Appendix 7.A
FINANCIAL ANALYSES SUPPORTING TABLES
20
Appendix 7.A.1
NET WORKING CAPITAL ( in 000 Birr)
Items Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11
Total inventory 2,445.38 2,771.43 3,260.50 3,260.50 3,260.50 3,260.50 3,260.50 3,260.50 3,260.50 3,260.50
Accounts receivable 995.98 1,117.67 1,300.20 1,300.20 1,300.91 1,300.91 1,300.91 1,300.91 1,300.91 1,300.91
Cash-in-hand 15.54 17.62 20.72 20.72 20.84 20.84 20.84 20.84 20.84 20.84
CURRENT ASSETS 3,456.90 3,906.71 4,581.42 4,581.42 4,582.25 4,582.25 4,582.25 4,582.25 4,582.25 4,582.25
Accounts payable 49.88 56.53 66.51 66.51 66.51 66.51 66.51 66.51 66.51 66.51
CURRENT
LIABILITIES 49.88 56.53 66.51 66.51 66.51 66.51 66.51 66.51 66.51 66.51
TOTAL WORKING
CAPITAL 3,407.02 3,850.18 4,514.91 4,514.91 4,515.75 4,515.75 4,515.75 4,515.75 4,515.75 4,515.75
20
Appendix 7.A.2
PRODUCTION COST ( in 000 Birr)
Item Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11
Raw Material and Inputs 9,782 11,086 13,042 13,042 13,042 13,042 13,042 13,042 13,042 13,042
Utilities 51 58 68 68 68 68 68 68 68 68
Labour direct 582 660 776 776 776 776 776 776 776 776
Labour overheads 146 165 194 194 194 194 194 194 194 194
Administration Costs 375 425 500 500 500 500 500 500 500 500
Total Operating Costs 11,952 13,412 15,602 15,602 15,611 15,611 15,611 15,611 15,611 15,611
Depreciation 526 526 526 526 526 125 125 125 125 125
Total Production Cost 12,478 14,569 16,681 16,602 16,532 16,051 15,972 15,894 15,815 15,736
21
Appendix 7.A.3
INCOME STATEMENT ( in 000 Birr)
Year Year Year Year Year Year Year Year Year Year
Item 2 3 4 5 6 7 8 9 10 11
Sales revenue 13,577 15,387 18,102 18,102 18,102 18,102 18,102 18,102 18,102 18,102
Less variable costs 10,952 12,412 14,602 14,602 14,602 14,602 14,602 14,602 14,602 14,602
VARIABLE MARGIN 2,625 2,975 3,500 3,500 3,500 3,500 3,500 3,500 3,500 3,500
in % of sales revenue 19.34 19.33 19.33 19.33 19.33 19.33 19.33 19.33 19.33 19.33
Less fixed costs 1,526 1,526 1,526 1,526 1,535 1,134 1,134 1,134 1,134 1,134
OPERATIONAL MARGIN 1,099 1,449 1,973 1,973 1,965 2,366 2,366 2,366 2,366 2,366
in % of sales revenue 8.09 9.41 10.90 10.90 10.85 13.07 13.07 13.07 13.07 13.07
Financial costs 631 552 473 394 315 237 158 79 0
GROSS PROFIT 1,099 818 1,421 1,500 1,570 2,051 2,130 2,208 2,287 2,366
in % of sales revenue 8.09 5.32 7.85 8.29 8.68 11.33 11.76 12.20 12.64 13.07
Income (corporate) tax 0 0 0 0 0 615 639 663 686 710
NET PROFIT 1,099 818 1,421 1,500 1,570 1,436 1,491 1,546 1,601 1,656
in % of sales revenue 8.09 5.32 7.85 8.29 8.68 7.93 8.24 8.54 8.84 9.15
22
135 - 23
Appendix 7.A.4
CASH FLOW FOR FINANCIAL MANAGEMENT ( in 000 Birr)
Item Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Scrap
TOTAL CASH INFLOW 4,784 17,607 15,394 18,112 18,102 18,102 18,102 18,102 18,102 18,102 18,102 6,616
Inflow funds 4,784 4,030 7 10 0 0 0 0 0 0 0 0
Inflow operation 0 13,577 15,387 18,102 18,102 18,102 18,102 18,102 18,102 18,102 18,102 0
Other income 0 0 0 0 0 0 0 0 0 0 0 6,616
TOTAL CASH
OUTFLOW 4,784 15,982 15,281 17,617 16,864 16,794 17,330 17,275 17,219 17,164 16,321 0
Increase in fixed assets 4,784 0 0 0 0 0 0 0 0 0 0 0
Increase in current assets 0 3,457 450 675 0 1 0 0 0 0 0 0
Operating costs 0 10,952 12,412 14,602 14,602 14,611 14,611 14,611 14,611 14,611 14,611 0
Marketing and
Distribution cost 0 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 0
Income tax 0 0 0 0 0 0 615 639 663 686 710 0
Financial costs 0 573 631 552 473 394 315 237 158 79 0 0
Loan repayment 0 0 788 788 788 788 788 788 788 788 0 0
SURPLUS (DEFICIT) 0 1,625 113 495 1,238 1,308 772 827 883 938 1,781 6,616
CUMULATIVE CASH
BALANCE 0 1,625 1,738 2,233 3,471 4,779 5,551 6,378 7,261 8,198 9,980 16,595
23
135 - 24
Appendix 7.A.5
DISCOUNTED CASH FLOW ( in 000 Birr)
Inflow operation 0 13,577 15,387 18,102 18,102 18,102 18,102 18,102 18,102 18,102 18,102 0
TOTAL CASH OUTFLOW 8,191 12,395 14,077 15,602 15,603 15,611 16,226 16,250 16,273 16,297 16,321 0
Operating costs 0 10,952 12,412 14,602 14,602 14,611 14,611 14,611 14,611 14,611 14,611 0
Marketing and Distribution cost 0 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 0
NET CASH FLOW -8,191 1,182 1,310 2,500 2,499 2,491 1,876 1,852 1,829 1,805 1,781 6,616
CUMULATIVE NET CASH FLOW -8,191 -7,009 -5,698 -3,199 -700 1,791 3,667 5,519 7,348 9,153 10,934 17,550
Net present value -8,191 1,075 1,083 1,878 1,707 1,547 1,059 950 853 765 687 2,551
Cumulative net present value -8,191 -7,116 -6,033 -4,155 -2,449 -902 157 1,108 1,961 2,726 3,413 5,963
25