Project: 2 Storey Residential: Site Preparation

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

PROJECT: 2 STOREY RESIDENTIAL

SITE PREPARATION
EVENTS ACTIVITIES PREDECESSOR/S DURATION ACTUAL/NORM ACCELERATIN
AL COST G COST
A CLEARING OF SITE 0 1
B PURCHASE OF INITIAL 0,H 7
MATERIALS
C TEMPORARY E 1
UTILITIES AND
SHELTER
D SURVEYING(BEARING B 1
LOCATIONS)
E FENCING OF SITE B,D 1
F MOBILIZATION B,D 5
G STAKE AND B,C 1
BATTERBOARDS
SITEWORKS
H EXCAVATION OF G 3
FOOTINGS
I SOIL POISONING G 3
J GRAVEL BEDDING I 2
K BACKFILLING V 3
L COMPACTING K,V 5
STEELWORKS/REINFORCEMENT (GROUND FLOOR)
M CUTTING,BENDING,T G 3
YING,LAYING,
(FOOTINGS)
N CUTTING,BENDING,T H 3
YING,LAYING,
(COLUMNS)
O CUTTING,BENDING,T J,W,D 3
YING,LAYING,
(BEAMS)
P CUTTING,BENDING,T H,U 3
YING,LAYING,(SLAB)
SECOND FLOOR (FRAMING)
Q CUTTING,BENDING,T Y 3
YING,LAYING,
(COLUMNS)
R CUTTING,BENDING,T J,W,D 3
YING,LAYING,
(BEAMS)
S CUTTING,BENDING,T J,W,D 3
YING,LAYING,(2ND
FLOOR SLAB)
STAIRS
T CUTTING,BENDING,T X 2
YING,LAYING
ROOF BEAMS AND GIRDERS
U CUTTING,BENDING,T X 2
YING,LAYING

CONCRETE WORKS (FOOTING)


V SEIVING,PROPORTIO M,J 3
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING
COLUMNS(GROUND FLOOR)
W SEIVING,PROPORTIO U,L,N 3
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING

COLUMNS(SECOND FLOOR)
X SEIVING,PROPORTIO H,R,G 3
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING
BEAM AND SLAB
Y SEIVING,PROPORTIO S,R,H 3
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING
STAIRS
Z SEIVING,PROPORTIO H 2
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING
ROOF BEAMS AND GIRDERS CONCRETING
A SEIVING,PROPORTIO U,H 2
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING
SLAB ON GRADE
B SEIVING,PROPORTIO P 2
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING
MASONRY
GROUND FLOOR
D CHB LAYING AND E 6
MORTARING
SECOND FLOOR
E CHB LAYING AND Y 6
MORTARING
CARPENTRY
G DOOR AND WINDOW E 2
FRAME INSTALLATION
H SHAPING AND I,I,J,T 1
PASTING OF
FORMWORKS
I REMOVING OF J,W,D,X 1
FORMWORKS
J ASSEMBLING OF 0,K, 1
SCAFFOLDING
K DISASSEMBLE OF Y 1
SCAFFOLDS
L INSTALLING OF P,M,N,Q,X 3
DRYWALL BOARD
M CUTTING OF LUMBER AF,O,AM,R,AK,Q,B 3
N TREATMENT OF M,L,O,Q,AC 3
LUMBER
O FRAMING OF CEILING AC,M 2
P WALL FRAMING N 2
Q CEILING BOARD AF,P,AM,N 3
INSTALLATION
R INSTALLING FASCIA AG 2
BOARDS
PLUMBING WORKS
S PLUMBING SUBSLAB H 2
T PLUMBING H
ROUGHING-IN
U INSPECTION S,T 1
ELECTRICAL WORKS
V SET ELECTRICAL W 1
BOXES
W INSTAL ELECTRIC AD 1
SERVICE PANEL
X SET ELECTRICAL Y 1
FIXTURES
Y SWITCH AND PLUG V 1
Z ELECTRICAL X 1
INSPECTION
PAINTING FINISHES
AA START ALL INTERIOR AB 3
PAINTING
AB START ALL EXTERIOR Z,AI,AK 3
PAINTING
ROOFING AND TINSMITHING WORKS
AC JOINERY OF RAFTERS Z 4
AND CEILING JOIST
AD INSTALL ROOF AC,M 2
SHEATHING
PLACE FLASHING
INSTALL GUTTERS
AF INSTALL AJ 3
DOWNSPOUTS
FINISHING
AG DOORS AND Y,Z, 2
WINDOW HARDWARE
AH BATHHARDWARE AI 2
AI PLASTERING OF ML,AI,AK 5
WALLS
AJ INSTALL OF CEILING N 2
EAVES
AK INSTALLATION OF N,Q,X,Y,Z 3
DOORS
INSTALLATION OF
WINDOWS
AL INTERIOR TRIMMING Z,AI,AK 2
AM GROUTING OF FLOOR AG 3
TILES
AN INSTALL AL,AI 2
CABINETRIES
AO CLEANING AN,AI 1
PROJECT TURNOVER

You might also like