1-Field Life Cycle

Download as pdf or txt
Download as pdf or txt
You are on page 1of 18
At a glance
Powered by AI
The key takeaways are the different phases of a field's life cycle including exploration, appraisal, development, production and decommissioning.

The main phases of a field's life cycle are exploration, appraisal, development, production and decommissioning.

The objectives of the appraisal phase are to accurately assess the size and producibility of the hydrocarbon accumulation by carrying out additional appraisal programs or proceeding with development.

Schlumberger Confidential

The Field Life Cycle

Amine Ennaifer
RE & CSV Training Manager
ELC, Schlumberger
Sketch of the Life Cycle of a Field

Schlumberger Confidential
Fig. Production profile throughout the field lifetime and a simplified business model
(Courtesy of Jahn et al., 2007)

Q: Phases of Field Life Cycle?


2
Overview

1. Exploration

Schlumberger Confidential
2. Appraisal

3. Development

4. Production

5. Decommissioning

3
1- Exploration Phase
High risk activity. Before commitment to exploration
venture, various factors are required:
Promising geological conditions

Schlumberger Confidential
Favorable political and fiscal conditions
Distance to potential markets
Existence of infrastructure and skilled workforce

4
1- Exploration Phase (Cont.)

It is common

Schlumberger Confidential
to study a
prospective
area for several
years before
spudding the
first well.

Fig. Phasing and expenditure of an exploration program


(Courtesy of Jahn et al., 2007)

5
2- Appraisal Phase
Once an exploration well has encountered hydrocarbons,
the finding potential need to be accurately assessed
(shape, size and producibility of the accumulation).

Schlumberger Confidential
2 possible scenarios:
Proceed with the development
Carrying out an appraisal program

Objective: reduce uncertainty on producible volumes not


finding additional hydrocarbons

6
2- Appraisal Phase: Feasibility Study
Various technical options are documented,

including:
Subsurface development options

Schlumberger Confidential
Process design
Equipment sizes
Proposed locations
Crude evacuation
and export system
Cost estimate
Planning schedule

The most economically viable option is retained for


development.
7
3- Development Planning: FDP
A Field Development Plan (FDP) includes:
Objectives of the development

Schlumberger Confidential
Petroleum engineering data

Description of engineering facilities

Operating and maintenance principles

Project planning

Cost and manpower estimates

Budget proposal

8
3- Development Planning
1. Field Development Plan (FDP)

2. Detailed design of facilities

Schlumberger Confidential
3. Procurement of construction
materials

4. Fabrication of facilities

5. Installation of facilities

6. Commissioning of all plants and equipments

9
4- Production Phase
Starts with production of first commercial quantities of
hydrocarbons (first oil)

Schlumberger Confidential
Turning point for cash flow.
Used to pay back prior investments or fund new projects

The expected production profile depends strongly on the


drive mechanism

The production profile determines the sizing of the


facilities and the number of wells to be drilled

10
4- Production Phase: 3 Periods
1. Build-up: newly drilled
producers are progressively
brought to stream

Schlumberger Confidential
2. Plateau: maintaining
constant production rate
typically 2-5 yrs for oilfields
(and longer for gas fields)

Fig. The field life cycle and a simplified business model


3. Decline: all producers exhibit (Courtesy of Jahn et al., 2007)
production decline (longest
period)

Q: Onshore or Offshore profile?

11
Onshore/Offshore
Development

Same physics

Schlumberger Confidential
Difference in
decision-making
Fig. Production profiles for onshore and offshore oilfields
(Courtesy of Dake, 2001)

Onshore: discoveries are tied back to nearest production facilities


providing cash and dynamic inspection of reservoir

Offshore: appraisal wells cannot be produced from day 1 due to


lack of production and transportation facilities

12
5- Decommissioning: Deferring
< +

Though, production may still be technically possible


Decommissioning procedures should:

Schlumberger Confidential
Minimize environmental effects
while limiting incurred costs

Deferred through:
Increase in hydrocarbon
production (EOR)
Developing nearby reserves
through the existing facilities
Reduction in maintenance
and operating cost
Tax concessions

13
5- Decommissioning: Costs
Includes:
Steel platforms cut off to an agreed depth below sea level
Platforms toppled over in deep waters
Concrete structures refloated, towed and sunk in deep ocean

Schlumberger Confidential
Pipelines flushed and possibly left in place
Platforms used as artificial reefs
Onshore, wells plugged and processing facilities dismantled
gradually enabling to spread costs

Costs are ensured through:


Prior provision
Assets management
Taxation rules

14
Course Overview

Day 1 (pm):
I. Field Life Cycle
II. Exploration

Schlumberger Confidential
III. HSE

Day 2 (am):
IV. Drilling
a. Drilling Overview
b. Mud Density Calculation

15
Course Overview

Day 2 (pm):
V. Reservoir Description

Schlumberger Confidential
a. Data Gathering
b. Reservoir Geology
c. Rock Properties

Day 3 (am):
d. Fluid Behavior

16
Course Overview

Day 3 (pm):
VI. Dynamic Behavior

Schlumberger Confidential
a. Reservoir
b. Well
VII. Field Management
a. Project & Contract Management
b. Petroleum Economics
VIII. Decommissioning

17
Course Overview

Schlumberger Confidential
Day 4 (am):
VIII. Quiz

18

You might also like