Project Status Report Template
Project Status Report Template
This section of the project status report provides a quick executive overview of the status of the project. It is intended for high level management
so it should not get too much into the details of the project. However, it should highlight anything specific which should be brought to their
attention. The Scope/Schedule/Cost/Quality table above is a quick way to present a color coded dashboard for the status report. Typically a
variance of +/- 5% will warrant a yellow cautionary color and +/- 10% will warrant a red warning color. For a project which needs tighter control
+/- 2% and +/- 5% are used for these thresholds; whereas, other projects with less strict control may use 10% and 20% variances. The percent
complete here should be the percent completion of the entire project. For any constraint which is yellow or red this section should contain brief
explanation the reason why.
The project schedule is 7% behind schedule due to inclement weather which has affected the installation of the fiber optics throughout the
campus. This should not affect the project completion date as crews are planning to make up the time by working weekends and extended hours
next month.
The project risks is red due to the inclement weather and servers which were delivered last month weren't configured with the correct hardware
specifications. The impact of the inclement weather on the schedule will be mitigated by having crews make up the time by working weekends
and extended hours next month. Currently we are working with the server vendor to resolve the server hardware configuration problem. The
configuration delivered will not handle the work load of going live in two months; however, it is sufficient for development and testing activities
scheduled prior to going live.
Open Issues
This part of the project status report should contain a list of open issues along with their status.
Open Risks
This section should contain a list of all open risks (risks which have occurred, or are on the verge of occurring).
Add Redundant Servers CR55012 2/17/20xx Approved and Being Added to the Project Plan