Basic Principles and Application Handbook: Project Scheduling Technique: Method
Basic Principles and Application Handbook: Project Scheduling Technique: Method
Basic Principles and Application Handbook: Project Scheduling Technique: Method
Basic
Principles
and
Application
Handbook
Project SCHEDULING
PROJECT Scheduling Technique:
TECHNIQUE:
METHOD
PRECEDENCE
DIAGRAM
METHOD
TABLE OF CONTENTS
INTRODUCTION ...................................................................... 2
PRECEDENCE DIAGRAM METHOD (PDM) ................................... 3
DEFINITION OF TERMS............................................................ 3
PDM LOGICAL RELATIONSHIPS ................................................ 6
Finish-to-Start (F-S) relationship ............................................ 6
Start-to-Start (S-S) relationship ............................................. 7
Finish-to-Finish (F-F) relationship ........................................... 8
Start-to-Finish (S-F) relationship ............................................ 8
LAG AND LEAD TIMES.............................................................. 9
ANALYZING PDM NETWORK ................................................... 11
Forward Pass Calculation .................................................... 11
For Finish-To-Start Relationship ........................................ 11
For Other Relationships aside from F-S ............................. 15
Backward Pass Calculation .................................................. 17
For Finish-To-Start Relationship ........................................ 17
For Other Relationships aside from F-S ............................. 21
THINGS TO REMEMBER ......................................................... 24
ANNEX .................................................................................. 28
BIBLIOGRAPHY ..................................................................... 31
FINISH
START
ITEM DESCRIPTION
Figure 1 shows the standard layout of PDM and the organization of its
attributes, which will be the standard format to be adopted by DPWH
for PDM.
DEFINITION OF TERMS
Bar Chart another term for Gantt chart; chart showing the
construction time schedule of project activities.
Late Finish (LF) latest point in time an activity can finish and not
delay the project
Late Start (LS) latest point in time an activity can start without delay
in the project
Lead period of time that must pass after the start of one activity
before the start of the following activity
Lag (+) and Lead (-) times are expressed as part of the immediate
predecessor notation. Lag time is defined as the delay between two
activities, that is, when one activity is completed and there is a waiting
period before the succeeding activity starts. In construction industry,
specifically in concreting, lag is most commonly used in situations that
require material to strengthen before the next activity can be
performed. Lag is also used to simplify the network diagram by
representing other subactivities related to the main activities (i.e.
curing period for concreting, removal of shoring, etc.)
Lead time, on the other hand, is an overlap between the first and
second activity, that is, when the second activity will start prior to the
completion of the first activity. This condition is used in cases which
allow succeeding activities to begin before preceding activities have
been completed.
In F-S relationship, lag and lead times are commonly used. As shown
in Figure 7a, since activities A and B can work subsequently without
any delays, the lag time is equal to zero (0), thus resulting to a total
duration of 8 calendar days (c.d.).
For S-S, F-F, and S-F relationship, lag time is also used to signify a
delay between two activities. Lead time, on the other hand, may be
used in these interdependencies to finish the project early and on time
but is best to be avoided, if possible, due to difficulties and complexity
in analysis of the logic diagram and computation of backward and
forward pass.
a) General Rule in Calculating Early Start & Early Finish dates based
on Finish-to-Start relationship without lag and lead time
EF = ES + Duration
STEP 2:
ESA = 0 (starting
activity)
STEP 2:
ESB = ESA + (Lag or
Lead Time); (S-S
relationship)
ESB = 0 + 1 = 1
or
Therefore; EFB = 5
a) General Rule in Calculating Late Start & Late Finish dates based
on Finish to Start relationship
STEP 1:
b) General Rule in Calculating Late Start & Late Finish dates based
on Backward Pass calculation for Finish to Start relationship with
Lag and Lead Times
STEP 2:
STEP 2:
LFA = LFB (Lag or Lead
time); (F-F relationship)
LFA = 5 0 = 5
or
Therefore; LSA = 0