MEASUREMENT FORM OF AN T.W.

PANELLING
Name of work: PANELLING
No Description of work or No. UNIT Lengt Bread Height Quantit
. Material h th y
1 SEAL WOOD 30*35 MM
PARTITION
FRAME
(A) VERTICAL FRAME 5 R.M 3.0 15
(B)HORIZONTAL FRAME 4 R.M 1.8 7.2
(C)SEAL HORIZONTAL FRAME 2 R.M 0.9 6.4
(D) VERTICAL WINDOW 2 R.M 1.2 2.4
FRAME
(E) HORIZONTAL DOOR 2 R.M 1.2 2.4
FRAME
TOTAL 33.4

2 6 MM THK MARINE PLYWOOD


OF
CENTURY PLY USED FOR
PANELLING
(A) PLY AFTER FINISHING 4 SQ.M 1.8 0.9 6.48
THE
PANELLING FRAME
(B) PLY AFTER FINISHING 2 SQ.M 1.2 0.9 2.16
THE
PANELLING PARTITION .
FRAME
TOTAL 8.64

3 TEAK WOOD 9 MM THK


SKIRTING
(A)TEAK WOOD SKIRTING 2 R.M 3.0 0.1 0.6

4 WINDOW SHUTTER OF
GLASS
(A) SHUTTER 2 SQ.M 1.1 0.55 1.21

5 LIPPING PATTI
(A)LIPPING PATTI 30 *12MM 36 R.M 3.0 0.02 2.16
IN
VERTICAL
(B)LIPPING PATTI 30 *12MM 36 R.M 3.0 0.02 2.16
IN
HORIZONTAL
TOTAL 4.32

6 0.8 MM THK LAMINATE FROM


CENTURY PLY FOR
PANELLING
(A) PLY AFTER FINISHING 4 SQ.M 1.8 0.9 6.48
THE
PANELLING FRAME
(B) PLY AFTER FINISHING 2 SQ.M 1.2 0.9 2.16
THE
PANELLING FRAME .
TOTAL 8.64

ABSTRACT SHEET OF AN T.W.PANELLING


Name of work: PARTITION
No Description of work or Unit Rate Quantity Amount
. Material

1 SEAL WOOD 30*35 MM R.M 215 Sq/m 33.4 7181


PANELLING
FRAME

2 6 MM THK MARINE PLYWOOD SQ.M 738 Sq/m 8.64 6377


OF
CENTURY PLY USED FOR
PANELLING

3 TEAK WOOD 9 MM THK R.M 195 Sq/m 1.6 312


SKIRTING

4 WINDOW SHUTTER SQ.M 1245 1.21 1506


Sq/m

5 LIPPING PATTI R.M 62 R/M 4.32 267

6 0.8 MM THK LAMINATE FROM SQ.M 635 Sq/m 8.64 5486


CENTURY PLY

7 HARD WARE
TOTAL 28,541
SUMMARY SHEET OF AN T.W.PANELLING
Name of work: PANELLING

DESCRIPTION OF WORK OR AMOUNT


MATERIAL
TOTAL COST FOR PARTITION 21,129

HARDWARE FOR PARTITION 2,950

TOTAL 24,079
15%WASTAGE 3,611
TOTAL 27,690
LABOUR( 5 DAYS) 6,600
TOTAL 34,290
20% CONTRACTORS PROFIT 6858
TOTAL 41,148
5%CARTAGE 2,057
TOTAL 43,205
60% ON 43,205 25,924
13.5% VAT ON 25,924 3,500
TOTAL 29,424
40% ON 43,205 17,282
15%SERVICE TAX ON 17,282 2,592
TOTAL 19,874

OVER ALL TOTAL COST 49,298/-

OVER ALL TOTAL COST IN WORDS: FOURTY NINE THOUSAND TWO


HUNDERED AND

NINTY EIGHT RUPEES


ONLY/-