Financial Model User Guide
Financial Model User Guide
Reporting Requirements
Section Page
1 Introduction................................................................................................................. 1
1.1 Discounted Cash Flow and Internal Rate of Return ............................................ 3
TM
1.2 The PSFM Model and the EPRI TAG ............................................................. 3
1.3 Constant (Real) and Current (Nominal) Dollar Basis.......................................... 4
1.4 Time Sensitive Model Parameters ....................................................................... 4
1.5 Organization of this Manual ................................................................................ 5
2 Operation of the Power Systems Financial Model (PSFM) .................................... 7
2.1 Basic Operating Steps .......................................................................................... 7
2.2 Running Scenarios ............................................................................................... 8
2.3 Model Directory Menu ........................................................................................ 9
2.4 Locked Data ......................................................................................................... 10
2.5 Printing Options ................................................................................................... 10
2.6 Troubleshooting ................................................................................................... 10
2.7 Cost of Electricity and Capital Charge Factor Calculation.................................. 11
2.8 Multiple Products in the PSFM ........................................................................... 14
3 Key Definitions and Assumptions.............................................................................. 16
Capital Costs and Operating Expenses ......................................................................... 16
Economic and Financial................................................................................................ 18
Engineering and Construction....................................................................................... 20
Appendix A: Plant Inputs and Scenario Inputs Sheets .................................................... 22
Plant Inputs Sheet ......................................................................................................... 22
Scenario Inputs Sheet.................................................................................................... 23
Appendix B: Glossary.......................................................................................................... 25
Appendix C: System Requirements .................................................................................. 32
Appendix D: Version History ............................................................................................ 33
Appendix E: Upgrades in Versions 5, 4 and 3................................................................... 34
This document provides an overview of the installation, start-up, and operation of the financial
model developed by Nexant, Inc. as part of the Integrated Gasification Combined Cycle (IGCC)
Economic and Capital Budgeting Practices program for NETL. The financial model calculates
investment decision criteria used by industrial end-users and project developers to evaluate the
economic feasibility of power systems, including (but not limited to) integrated gasification
combined cycle (IGCC), natural gas combined cycle, and coal systems. By conducting analysis
with the financial model, the DOE will be able to evaluate different power systems applications
on a uniform basis.
The Power Systems Financial Model Version 5.0 (references are also made in this manual to
previous versions of the model, the IGCC Financial Model Versions 3.0 and 4.0) consists of 22
spreadsheets that were created in Microsoft Excel 2003 workbook format, with interfaces and
supporting code developed in Visual Basic. The spreadsheets in the model are organized into
four main sections: data input sheets, supporting analysis sheets, financial statements, and project
summary result sheets. Figure 1-1, shown below, outlines the main sections of the model and
illustrates the process by which the model uses input data to perform the calculations required to
develop financial statements and summary results for power projects. Table 1-1 describes each
of the spreadsheets in the model.
Supporting
Supporting Analysis
Analysis
Data Input Sheets
Construction schedule
Construction schedule
Plant Input
Interest during construction
Interest during
construction
Scenario Input
Depreciation
Depreciation
Forecast Fuel Prices
Escalation
Escalation
Financing
Financing
Expenses
Expenses
Revenues
Revenues
Working capital
Working capital
EPC Escalation
EPC Escalation
Cost of Electricity Calculation
Cost
O&Mof
EPC Electricity Calculation
Calculation
Escalation
Financial Statements
Income statement
Cash flow
Balance sheet
Sources and uses
Worksheet Description
Overview User selects the active scenario on this sheet, overview of results are displayed
Results Key financial results are reported
Plant Performance A summary of plant capacity, outputs, and performance. No inputs on this page.
Cost Summary Summary of capital costs, construction costs by year, and operating expenses
Plant Inputs The input sheet for plant data. Up to seven plant cases can be entered.
Scenario Inputs The input sheet for financial, economic, fuels, products, tariff, and construction
parameters. The inputs are common for all plant scenarios defined in the Plant
Inputs sheet.
O&M Input sheet for Variable and Fixed O&M costs for each project. O&M costs can be
alternatively input as a percentage of EPC cost in the Plant Inputs sheet.
COE Calculation Calculates the Levelized Cost of Electricity and the Capital Charge Factor for a
given scenario
Fuel Forecasts Input of yearly forecasts for the cost of fuel inputs. The user can alternatively input
a single escalation factor for each fuel in the Scenario Input Sheet.
EPC Escalation Allows the user to escalate construction costs over the construction period
Income Statement Calculation of Operating Income, Income Before Taxes, Taxable Income, and Net
Income
Balance Sheet A balance sheet of liabilities, assets, and shareholders equity
Sources and Uses Accounting of fund sources (debt, equity, revenue) and uses (various expenses)
Cash Flow Calculates Operating Cash Flow, Net Cash Flow, and Net Cash Available for
Equity Distribution, upon which the IRR calculation is based. IRR is thus a
measure of available Return on Equity.
Revenues Accounting of all project revenues
Expenses Accounting of all project expenses
Financing Accounting of debt financing and repayment
Interest During Construction Calculates the interest expenses incurred during the construction period
Depreciation Accounts for the depreciation of construction and financing charges. Either the
Straight-Line (SL) or the Declining Balance (DB) methods are selected in the
Scenario Inputs sheet
Working Capital Accounts for the initial working capital and changes in working capital
Construction Schedule Accounts for the allocation of funds during construction. The allocation of Total
Required Capital is specified by percentage per construction year in the Scenario
Input sheet.
Escalation Set of escalation factors for each input and product by year. Typically inputted as
nominal values, since model dollars usually in nominal terms.
The RR and DCF methodologies differ in one important respect. Under RR, given the required
Return on Equity (ROE), Cost of Debt (COD), depreciation, and O&M expenses, the
methodology computes the necessary COE to support the capital investment and operating
expenses of the plant. The COE is then often levelized over a period of 10, 20, or 30 years.
Under a DCF analysis, given the COE, the COD, and depreciation and O&M expenses, the
methodology computes the ROE as the Internal Rate of Return (IRR) as the investment decision
criteria for equity investors.
The RR method charges each year of the book life (book life =x) with a book depreciation
charge equal to 1/x of the original investment (debt and equity portions,) charges corresponding
to the debt and equity return required on the non-book-depreciated portion of the original
investment, as well as operating expenses over the book life. (Tax depreciation could be done
over a different period.) This leads to a series of declining values to pay back the investment,
with the associated required returns. These values are used to calculate the yearly Cost of
Electricity to support the required returns on investment. The COE is then levelized over a 10,
20 or 30 year period.
By contrast in DCF, the debt portion of the project is a constant payment comprised of interest
and principle. As the loan is paid, the interest portion declines, and the principle portion
increases, exactly as is the case in the repayment of a home mortgage. The DCF method
computes the series of cash flows for the given cost of debt, revenues, and other costs. The IRR
of the net positive cash flows over the life of the project is calculated. This IRR can also be
thought of as the Return on Equity available to return to the equity investors.
The PSFM is designed to deal with cash flows on a Current, or Nominal basis. That is to say,
the dollars in any year represent the actual dollar figure in that year. The escalation rates for
prices should thus include both the inflation rate and the escalation rates for individual
commodity prices. Nominal dollars are the preferred basis for discounted cash flow analysis that
includes the affects of taxes and depreciation, because depreciation is not affected by inflation.
The IRR computed by the PSFM includes the general inflation rate embedded in the escalation
rates. The computed COE also is based on current dollars.
Table 1-2 contains a list of parameters that should be independently verified and periodically
updated by the user in the PSFM.
Variable and Fixed O&M cost as a Plant Inputs Variable is currently set to 1.5% of EPC
% of EPC cost; Fixed is set to 3.5% of EPC cost
Variable and Fixed O&M cost O&M If this option is used, the O&M costs
entered in base year dollars entered in the O&M sheet should be
verified to be in the base year of the
analysis
Debt Reserve Fund Scenario Inputs If this option is used, the default reserve
fund interest rate default is 5%, and the
percentage of total debt service used as
DRF is 50%
Allocation of EPC and financing Scenario Inputs The user should verify that the default
costs over the construction period allocations reasonably correspond to the
planned project funds outlay during
construction, or, equally allocate the
funds over the construction period
Fuel Price Forecasts Fuel Forecasts If forecast fuel prices, rather than
constant escalated prices, are used, the
forecast prices in the Fuel Forecast
sheet should be verified. Costs should
stated be in nominal dollars.
Guide to data input in the Plant Inputs and Scenario Inputs sheets
A glossary for all key model parameters and inputs
An instructions sheet on model installation and start-up procedures
Step 1
Enter plant
IGCC data
plantinto
datathe
into
Plant
the Input
Plantsheet
Input Sheet
Project summary
Plant output and operating data
Capital costs
Operating costs and expenses
Step 2
Enter scenario specific data into the Scenario
ScenarioInput
Inputsheet
Sheet
Financial and economic data Scenario Options
Fuel data - Debt Reserve Fund
Tariff assumptions - Depreciation Technique
- Forecast Fuel Prices
Construction schedule data - EPC Escalation
Step 3
Select plant
IGCC case
planton
case
theon
Overview
the Overview
Sheet Sheet
and click
andon
click
theon
Recalculate
the r efresh
button
button
Model Results
The model will generate the following key results:
Project summary report
Financial statements
Additional Analysis Supporting analysis sheets
Compute the Levelized Cost of
Electricity and the Equivalent
Capital Charge Factor
Step 2. Using the Directory, go to the Model Inputs menu option and select the Scenario Inputs
sheet. The Scenario Inputs sheet is the repository for key financial, economic, pricing, and
construction schedule data. Some data is specific to each plant (such as construction start date
and construction duration), but most other data is general to all plant configurations (such as
escalation factors, depreciation technique, and plant life.) Prior to conducting analysis, all
scenario specific data should be entered and/or reviewed by the user of the model. In particular,
the user of the model should ensure that the data contained in the plant construction section and
project debt terms is still valid.
Important It is important to note that sheets contain both input and calculation cells. Input cells
are designated by a blue color code and calculation (formula) cells are designated by a red color
code. The user must avoid entering any data in cells that are colored red (see troubleshooting
section). See Appendix A for detailed documentation and description of the Scenario Inputs
sheet.
Important The data in the Scenario Inputs sheet applies to all plant configurations input into the
Plant Inputs sheet. This is so that alternative plant configurations can be compared on an
equivalent basis. If the user wants to compare the same set of plant configurations based upon
different scenario data, a copy of the spreadsheet should be made and the Scenario Inputs data
should be changed.
Important The user should not rely upon any of the default values in the Scenario Inputs sheet
(such as yearly EPC cost allocations or fuel, EPC, or tariff escalation.) All data should be
independently developed and verified. Acceptable default values for financial analysis can be
found in the Quality Guidelines for Energy Systems Studies from NETL.
Step 3. Using the Directory, return to the Overview sheet. Using the drop-down box located in
the upper left-hand corner of the Overview sheet, select a plant case to be evaluated (the names
of projects entered in the Plant Inputs sheet will be displayed in this drop-down box). As a final
step after selecting a case, click-on the Recalculate button (also located in the upper left-hand
corner of the sheet) to ensure that any recently entered data is incorporated into the final analysis.
Very Important Each time data is entered or changed in the Scenario Inputs sheet, the user must
go to the Overview sheet and click Recalculate to ensure that the new scenario data is loaded.
There are several key input selections on the Scenario Inputs worksheet that should be noted.
The user must specify if each of these options is in effect in the current scenario with a yes/no
or selected choice in the Scenario Input sheet. See also Appendices A and B for further
information.
Debt Reserve Fund (Line 38): Yes/No to include a debt reserve fund in the scenario
Plant Ramp-up (Line 136): Yes/No to active a plant ramp-up, in which the plant phases
in capacity over two years, quarter by quarter
Depreciation Technique (Lines 42-43): Choice of straight-line or 150% declining
balance (15 or 20 years) depreciation techniques. The user enters SL (straight-line) or
DB (150% declining balance, 15 or 20 years.)
EPC Cost Escalation (Line 121): Yes/No to escalate EPC costs over the construction
period
Forecast or Escalated Fuel Prices (Line 94): Yes/No option to use forecasted vs.
escalated prices. Fuel price can be escalated from a base by a constant escalation factor,
or forecast prices (from EIA, for example) can be used
Investment Tax Credit (Lines 85-86): Yes/No option to include the Investment Tax
Credit. The ITC is applied to the EPC cost, and credited in the first year of start-up. A
maximum allowable ITC can be specified. The ITC cannot be carried over into future
years.
Reminder The user should not rely upon any of the default values in the Scenario Inputs sheet
(such as yearly EPC construction cost allocations or fuel, EPC, or tariff escalation factors.) All
data should be independently developed and verified.
Important Reminder Any time that changes are made to any data input sheet, including the
Scenario Inputs, the Plant Inputs, or the Fuel Forecast Prices sheets, the user must return to the
Overview sheet and press the Recalculate button to obtain the current scenario results.
A plant scenario description is included at the top of each printed page. This description is
entered in Line 48 of the Plant Inputs sheet for each plant profile.
2.6 TROUBLESHOOTING
Table 2-1 contains a list of solutions to potential problems that a user may encounter when
operating the PSF Model.
The RR and DCF methodologies differ in one important respect. Under RR, given the required
Return on Equity (ROE), Cost of Debt (COD), depreciation, and O&M expenses, the
methodology computes the necessary yearly COE to support the capital investment and operating
expenses of the plant. The COE is then often levelized over a period of 10, 20, or 30 years.
Under DCF, given an initial COE (with nominal escalation), the COD, and the depreciation and
O&M expenses, the methodology computes Internal Rate of Return (IRR), which is the ROE that
is available to return to equity investors. The IRR is used as an investment criteria as follows: if
the IRR is greater than the minimum required ROE, the project is potentially an attractive
investment option.
Internal Rate of Return (IRR) refers generically to that rate of return corresponding to a specific
cash flow that yields in a net present value (NPV) of zero. In the PSFM, the projects cash flow
is determined by accounting for all costs and financial obligations and revenues for the project.
The financial obligations include service on the project debt. The remaining positive cash flows
are available for return to equity investors. Thus, in the PSFM, the IRR corresponds to the
projects Return on Equity.
In order to compute the COE for a given DCF scenario, the following steps are executed in the
COE Calculation sheet.
STEP 1
The user first inputs the plant and scenario data for the power systems under study. Of
particular importance are the definitions of Bare Erected Cost (BEC), Engineering Procurement
and Construction Cost (EPC), Total Plant Cost (TPC) and Total Required Capital (TRC).
BEC is the sum of all process equipment, supporting facilities, and direct and indirect labor.
BEC is the most fundamental cost estimate and is used as the basis for calculating engineering
and home office fees.
EPC includes the BEC, plus detailed design and construction and project management. EPC is
the basis for calculating process and project contingencies, on a percentage basis of EPC. The
EPC cost should be entered consistent with the Base Year reflected on the Scenario Inputs tab.
TPC includes EPC plus process and project contingencies, and technologies fees.
Finally, the TRC is includes the TPC, plus startup costs, owners costs, financing costs, and the
time value of money over the construction period, calculated as the Interest During Construction
(IDC).
In the Cost Summary sheet, TPC is the sum of EPC Costs, Owners (Project) Contingency, and
Process Contingency. These parameters are input in the Plant Inputs sheet. The TRC includes
all other capital items, including Start-up, Owners Cost, Financing Fees, and IDC
The COE and levelized COE are computed on the basis of the TRC. The levelized CCF is
computed on the basis of the TPC, the O&M charges, and the levelized COE.
STEP 2
In the COE Calculation sheet, the user inputs the required Return on Equity and the Levelization
Basis. The levelization basis must be 10, 20, or 30 years. Note here that the model assumes that
the equity must be returned within the levelization period but that the debt term is not changed to
equal the levelization period. The COE Calculation sheet reports the other key input parameters,
which are input in the Plant Inputs and Scenario Inputs sheets. These include the Weighted Cost
of Debt, COE Escalation, Tax Rate, Debt and Equity ratios, TEC and TRC.
STEP 3
The user inputs an initial guess of the electricity charge ($/kWh) for the first year that is
escalated by a uniform rate. This escalation rate is input on the Scenario Inputs sheet; typically,
a nominal escalation rate is entered, for the model is designed to calculate IRR and NPV on
nominal cash flows. The user iterates by pressing the Calculate ROE button until the resulting
Return on Equity is achieved to within 1% of the required ROE. This ROE is equivalent to the
computed IRR in the Discounted Cash Flow (DCF) analysis for the first N years, where N is the
levelization basis for Revenue Requirements-based analysis.
The iterative discounted cash flow analysis solves for the COE that meets the specified ROE
over the levelization period while keeping the debt term cash flows unchanged. For example, the
debt may not be retired for thirty years, even if the levelization period is ten years. As such, the
debt service payments are treated the same as all other operating expense, and would be
terminated if the asset were sold at the end of the levelization period.
In order for the IRR on the Overview and Results sheets to be equivalent to the ROE on the
COE Calculation sheet, the economic project life on line 53 of the Scenario Inputs sheet
must equal the COE levelization basis on line 4 of the COE Calculation sheet.
STEP 4
Press the Calculate Levelized COE button. The COE iterated in Step 2 is levelized over the
specified levelization period, with a discount rate set to the After-tax Weighted Cost of Capital
(ATWCC) ,where:
STEP 5
where:
The CCF allows the analyst to use a simple equation to calculate a levelized COE instead of
performing a full DCF analysis. When used in this way, all assumptions built into the DCF
analysis also apply to the CCF that was derived from it, including the levelization period.
Year Dollars All costs should be expressed in first-year-of-construction year dollars, and the
resulting LCOE is also expressed in first-year-of-construction year dollars. For example, if the
first year of plant construction was 2007, the TPC and operating costs should be entered in year
2007 dollars and the resulting LCOE would be expressed in year 2007 dollars.
Levelization Period Capital charge factors and levelization factors are tabulated for levelization
periods of ten, twenty and thirty years. Although their useful life is usually well in excess of
thirty years, a twenty-year levelization period is typically used for large energy conversion
plants.
Many studies will report tenth-year COE, which are non-levelized values that reflect the
nominal cost of electricity in the tenth year of operation. These tenth-year COE values are
typically very close to a twenty-year levelized cost of electricity (since the tenth year is the
midpoint of the twenty-year levelization period).
Steam,
Hydrogen,
Carbon Dioxide,
Sulfur,
Ash,
Fuels,
Chemicals,
Environmental credits
Other
These entries were included because they are common co-products, but if desired, the model can
be modified to include other items simply be renaming each of the entries for the relevant
flowrate, escalation, and tariff values.
In order to properly include co-products in a power system, the following steps should be taken:
The Primary Output (Plant Inputs sheet, row 7) should be defined as Multiple Outputs. The
user then inputs the feedstock in terms of daily fuel consumption (lines 28 and 29) instead of
heat rate. While heat rate can be used, this is value has less meaning when co-products are
produced, because their energy requirements are usually not included in the heat rate calculation.
Entries then should be made for the flow-rate of the co-product, the tariff value, and the
escalation rate. Entering these items will assure that they are included in the cash flow
calculations. Note that the model typically does not allow negative values for tariffs; in order to
include negative values, the user must go into the Validation section in the Data dropdown
menu and allow negative values to be included.
The PSFM model has been used and validated for a number of co-product cases, including
steam, Fischer-Tropsch (FT) liquids, ammonia, and urea. Examples of model inputs with co-
products can be seen in the FT and hydrogen cases in the Appendix of the Nexant/DOE report
Gasification Plant Cost and Performance Optimization, DE-AC26-99FT40342, September
2003.
The following definitions and assumptions are included to provide the user with a more detailed
explanation of the models inputs and parameters. The same definitions can also be founding
Appendix B, organized alphabetically.
Bare Erected Cost (BEC): BEC is the sum of all process equipment, supporting facilities, and
direct and indirect labor. BEC is the most fundamental cost estimate and is used as the basis for
calculating engineering and home office fees.
Engineering, Procurement, and Construction (EPC) Costs The EPC cost category includes all
relevant direct costs, indirect costs, and design services. It can be defined as the BEC plus all
detailed design, construction, and project management costs. In the financial model, EPC costs
should be entered as a lump sum amount (in thousand dollars), consistent with the model Base
Year.
Direct cost elements include: process equipment, on-site facilities and infrastructure that
support the plant, and the direct labor required for their installation and/or construction at
the site.
Indirect cost elements cover all field costs (materials, subcontracts, manual and non-
manual labor), which cannot be specifically assigned to items in the direct cost category.
The indirect field costs include temporary facilities, construction equipment, labor, field
office costs, and consumable supplies.
Design costs include labor and material costs associated with the completion of project
design services.
EPC Cost Escalation Normally, the lump sum EPC cost should account for escalation over the
construction period. In the Scenario Inputs sheet, EPC costs are allocated across each year of
construction (for 3-5 year periods.), and this allocation should reflect increases in costs.
In Version 3 of financial model, an EPC Cost Escalation calculation sheet was added to
explicitly escalate EPC costs and adjust the cost allocations, and a Yes/No option has been added
to the Scenario Inputs sheets in order to employ EPC escalation. See Appendix E for a detailed
description.
Owners (Project) Contingency The owners or project contingency category covers all
unforeseen costs that may impact the construction cost of a project. Contingency funds are
expected to be spent. In the model, owners contingency costs are calculated as a percentage of
total EPC costs. Although contingency factors vary by project, a fifteen percent contingency
factor is set as an initial default value based on the results of private power developer interviews.
Technology Fee Technology fee costs include all licensing costs, pre-paid royalties, and know-
how fees. Similar to owners contingency, the development fee is calculated as a percentage of
total EPC costs. Based on the results of market interviews, a four percent technology fee is used
as a default value for calculating fee costs.
Start-up Costs Start-up costs include labor, materials, and consumable items directly linked to
the start-up of a plant. This includes all start-up capital cost items (including chemicals and
catalysts). For the purposes of analysis conducted using this model, the start-up cost of a project
is calculated as a percentage of total EPC costs. As an initial default value, start-up costs were
set equal to two percent of total EPC costs.
Owners cost Owners cost includes separate costs that are directly incurred by the owner of a
project. Potential owners cost items include labor, land, project permitting, environmental
reporting, and facilities. In the financial model, owners cost items should be entered as a lump
sum amount (in dollars thousand).
Initial Working Capital An initial fund established and capitalized to fund expenses of ongoing
operations. (Refer to the Initial Working Capital section below.)
Initial Debt Reserve Fund A fund required by some financial institutions to secure debt payments.
(Refer to the Debt Reserve Fund section below.)
Interest During Construction Interest charges accumulated during the construction period
Financing Fees Additional fees associated with the debt portion of financing
Ongoing Expenses
Ongoing expenses included in the financial model are fuel (see engineering assumptions),
Variable operation and maintenance (O&M), and Fixed O&M costs.
Variable O&M. Variable costs are dependent on the output level at a given plant. Variable
O&M costs include all consumable items, spare parts, and labor that fluctuate with the actual
plant output. Variable costs are calculated as a percentage of total EPC costs, and are adjusted
according to the Guaranteed Availably factor specified in the Plant Inputs sheet. As an initial
default value, variable O&M costs were assumed to equal 1.5% of total EPC costs. Variable
O&M costs can also be directly input, or calculated using key cost components.
Fixed O&M. Fixed costs include labor and other costs that are independent of the plant output
level. Fixed cost items must be paid whether or not the plant produces any output. Fixed costs
are calculated as a percentage of total EPC costs. As an initial default value, fixed O&M was
assumed to equal 3.5 %of total EPC costs. Fixed O&M costs can also be directly input, or
calculated using key cost components.
Investment Tax Credit can be used to reduce the tax burden of the project in the startup
year. The project or corporation must have sufficient taxable income to take the full ITC
in the startup year. The ITC cannot be carried forward into future years.
Project Loan Options The financial model evaluates a wide range of financing options for
projects, including the following:
Multiple Sources of Debt The financial model can assess projects using a maximum of three debt
sources. If multiples sources of debt are used, the user must specify one loan as senior and the
others as subordinated debt. Subordinated debt has a claim on the assets of a project in the event
of bankruptcy only after senior debt has been paid.
Debt Reserve Fund The option to use a debt reserve fund is included for projects on which
lenders require added debt service assurance. To use the Debt Reserve Fund option, the user
should enter Yes in the designated input cell located in the Scenario Inputs sheet (in the
Financial Assumptions section). To exclude the Debt Reserve Fund option, the user should enter
No.
The debt reserve fund is available to pay debt service requirements in the event that the general
funds available to the project are inadequate. Based on interviews conducted with financial
lending organizations, the debt reserve fund amount is estimated to be equal to fifty percent of
total first year debt service. The owner of a project using a debt reserve fund is entitled to
interest earnings on the fund. An initial interest rate of five percent on the reserve fund is used as
a default value. For analysis conducted using this model, debt reserve funds can only be used for
senior debt (i.e., Project Loan 1).
Grace Period Lenders often grant projects a grace period on the initial repayment of principal.
Therefore, the model contains an option for using a grace period (in years) on the repayment of
principal for each loan.
Depreciation
Construction costs can be depreciated using a straight-line method (variable number of years) or
a 150% declining balance method over a period of 15 or 20 years. Financing charges are can be
separately depreciated using either method.
Discount Rate
All discount rates are assumed to be in nominal form.
Working Capital is calculated in each year as the sum of accounts receivable, inventories,
operating cash, less accounts payable. It reflects the amount of capital that is tied up in
receivables, money invested in inventories, and payables, plus cash on hand.
The Operating Cash default in the model is set at $50,000, and maintained at that level,
accounting for inflation. The user should input an Operating Cash level appropriate to the
project.
Initial Working capital, at 7% of first year revenues, is the fund that is set up in the year prior to
operations to initially fund the Working Capital account.
1 Working capital is included in this analysis because changes in working capital are relevant to the investment
decision. In addition to increases in fixed assets, investments require increases in working capital items, such as
inventories and receivables.
The increase in working capital from year to year is subtracted from the operating cash flow to
reflect how it is used in funding operations, and to maintain the fund at the desired level. At the
end of the project life, the Working Capital fund is returned to equity investors as a positive cash
flow.
For multiple fuels, the heat rate of each fuel type is pro-rated by the percentage of time operating
on each fuel. The units of heat rate are then Btu of primary fuel/total kWh produced and Btu of
secondary fuel/total kWh produced, so that the sum of the heat rates is a weighted average heat
rate of the whole plant for an operating year.
This fraction is applied the total Variable O&M costs to calculate the actual O&M for the period
for which the plant will actually be in service.
To use the plant ramp-up option, the user should enter Yes in the designated input space
located in the Scenario Inputs sheet (in the Construction Assumptions section). To exclude the
plant ramp-up option, the user should enter No.
This section refers the user to specific lines in the Plant Inputs and Scenario Inputs worksheets
noting important plant profile data and scenario data and scenario options, particularly those
scenario options new in Versions 4 and 5 of the Power Systems Financial Model. Line numbers
from the worksheets note each item. Also see Section 3 for additional descriptions of
assumptions behind the data and options in the worksheets.
Note: the category Other/Waste can be used to represent three fuels in a plant profile. For
example, if the plant is to be run on coke and coal as a primary fuel and gas as a secondary fuel,
the Other/Waste category could be used to represent coke and coal by using a weighted
average (based on BTU content and percentage of each fuel used) for the heat rate, HHV, fuel
consumption, and price.
In Version 4.0 and 5.0, the user has the option to directly enter or to calculate O&M costs, rather
than specify O&M as a percentage of EPC. Cells A45 and A47 provide this option.
This discount rate is only used on the Results sheet to display the corresponding Net Present
Value at that discount rate. It is not used as a parameter in any other calculation.
The user inputs the ITC rate (default is 0%, but 10% is a reasonable assumption if the ITC is in
place), and the maximum amount of the ITC that is available in the startup year, based upon
sufficient taxable income for the project or owner. ITC cannot be carried forward.
A category for user defined capital costs in the Plant Inputs sheet
BEC is the sum of all process equipment, supporting facilities, and direct and indirect labor.
BEC is the most fundamental cost estimate and is used as the basis for calculating engineering
and home office fees.
Base Year
The earliest start year of construction for all scenarios considered in a single PSFM spreadsheet
model. This is the year used as the base year for discounting cash flows. Base year is illustrated
in Figure C-1.
This fraction is applied the total Variable O&M costs to calculate the actual O&M for the period
for which the plant will actually be in service.
Figure B-1 Illustration of Base Year, Construction Period, and Plant Life
The option to use a debt reserve fund is included for projects on which lenders require added
debt service assurance. To use the Debt Reserve Fund option, the user should enter Yes in the
designated input cell located in the Scenario Inputs sheet (in the Financial Assumptions section).
To exclude the Debt Reserve Fund option, the user should enter No.
The debt reserve fund is available to pay debt service requirements in the event that the general
funds available to the project are inadequate. Based on interviews conducted with financial
lending organizations, the debt reserve fund amount is estimated to be equal to fifty percent of
total first year debt service. The owner of a project using a debt reserve fund is entitled to
interest earnings on the fund. An initial interest rate of five percent on the reserve fund is used as
a default value. For analysis conducted using this model, debt reserve funds can only be used for
senior debt (i.e., Project Loan 1).
Depreciation, Straight Line (SL) and Declining Balance (DB)
Construction costs can be depreciated using a straight-line method (variable number of years) or
a 150% declining balance method over a period of 15 or 20 years. Financing charges are can be
separately depreciated using either method.
Discount Rate
All discount rates are assumed to be in nominal (current) form.
The EPC cost category includes all relevant direct costs, indirect costs, and design services. In
the financial model, EPC costs should be entered as a lump sum amount (in dollars thousand).
Direct cost elements include: process equipment, on-site facilities and infrastructure that
support the plant, and the direct labor required for their installation and/or construction at
the site.
Indirect cost elements cover all field costs (materials, subcontracts, manual and non-
manual labor), which cannot be specifically assigned to items in the direct cost category.
The indirect field costs include temporary facilities, construction equipment, labor, field
office costs, and consumable supplies.
Design costs include labor and material costs associated with the completion of project
design services.
Normally, the lump sum EPC cost should account for escalation over the construction period.
In the Scenario Inputs sheet, EPC costs are allocated across each year of construction (for 3-5
year periods.), and this allocation should reflect increases in costs.
In Version 3 of financial model, an EPC Cost Escalation calculation sheet was added to
explicitly escalate EPC costs and adjust the cost allocations, and a Yes/No option has been added
to the Scenario Inputs sheets in order to employ EPC escalation. See Appendix E for a detailed
description.
Financing Fees
Fixed O&M
Fixed costs include labor and other costs that are independent of the plant output level. Fixed
cost items must be paid whether or not the plant produces any output. Fixed costs are calculated
as a percentage of total EPC costs. As an initial default value, fixed O&M was assumed to equal
Working Capital is calculated in each year as the sum of accounts receivable, inventories,
operating cash, less accounts payable. It reflects the amount of capital that is tied up in
receivables, money invested in inventories, and payables, plus cash on hand.
Loan Options
The financial model evaluates a wide range of financing options for projects, including the
following:
Multiple Sources of Debt The financial model can assess projects using a maximum of
three debt sources. If multiples sources of debt are used, the user must specify one loan
as senior and the others as subordinated debt. Subordinated debt has a claim on the assets
of a project in the event of bankruptcy only after senior debt has been paid.
2 Working capital is included in this analysis because changes in working capital are relevant to the investment
decision. In addition to increases in fixed assets, investments require increases in working capital items, such as
inventories and receivables.
The owners or project contingency category covers all unforeseen costs that may impact the
construction cost of a project. Contingency funds are expected to be spent. In the model,
owners contingency costs are calculated as a percentage of total EPC costs. Although
contingency factors vary by project, a nine percent contingency factor is set as an initial default
value based on the results of private power developer interviews.
Owners Cost
Owners cost includes separate costs that are directly incurred by the owner of a project.
Potential owners cost items include labor, land, project permitting, environmental reporting,
legal, and facilities. In the financial model, owners cost items should be entered as a lump sum
amount (in dollars thousand).
This input is required for projects having electricity generation as the primary output. Plant heat
rate is a measure of the amount of thermal energy needed to generate a given amount of electric
energy. Plant heat rate is stated in Btu/kWh and is based on the higher heating value (HHV) of
the relevant fuel. The user has the option of specifying a primary and secondary fuel type.
For multiple fuels, the heat rate of each fuel type is pro-rated by the percentage of time operating
on each fuel. The units of heat rate are then Btu of primary fuel/total kWh produced and Btu of
secondary fuel/total kWh produced, so that the sum of the heat rates is a weighted average heat
rate of the whole plant for an operating year.
To use the plant ramp-up option, the user should enter Yes in the designated input space
located in the Scenario Inputs sheet (in the Construction Assumptions section). To exclude the
plant ramp-up option, the user should enter No.
Process Contingency
Start-up Costs
Start-up costs include labor, materials, and consumable items directly linked to the start-up of a
plant. This includes all start-up capital cost items (including chemicals and catalysts). For the
purposes of analysis conducted using this model, the start-up cost of a project is calculated as a
percentage of total EPC costs. As an initial default value, start-up costs were set equal to two
percent of total EPC costs.
Startup costs are in addition to the initial and ongoing working capital, if they are used in the
analysis.
Tax Options
The financial model contains the following options for calculating annual income taxes:
Standard tax rates can be used to calculate annual income taxes for a project under a
regular tax schedule (i.e., during periods where there are no tax credits or benefits)
Subsidized tax rates can be used to evaluate the impact of potential tax credits on a
project. Subsidized tax rates can be employed for the entire life of a project or for a
defined grace period (i.e., a set number of years that the subsidized rate is in effect).
Investment Tax Credit can be used to reduce the tax burden of the project in the startup
year. The project or corporation must have sufficient taxable income to take the full ITC
in the startup year. The ITC cannot be carried forward into future years.
Technology Fee
Technology fee costs include all licensing costs, pre-paid royalties, and know-how fees. Similar
to owners contingency, the development fee is calculated as a percentage of total EPC costs.
Based on the results of market interviews, a four percent technology fee is used as a default value
for calculating fee costs.
TPC includes EPC cost plus process and project contingencies, and technologies fees.
TRC is includes the TPC, plus startup costs, owners costs, financing costs, and the time value of
money over the construction period, calculated as the Interest During Construction (IDC).
Variable O&M
Variable costs are dependent on the output level at a given plant. Variable O&M costs include
all consumable items, spare parts, and labor that fluctuate with the actual plant output. Variable
costs are calculated as a percentage of total EPC costs, and are adjusted according to the
Guaranteed Availably factor specified in the Plant Inputs sheet. As an initial default value,
variable O&M costs were assumed to equal 0.6% of total EPC costs. Variable O&M costs can
also be directly input, or calculated using key cost components.
The Operating Cash default in the model is set at $50,000, and maintained at that level,
accounting for inflation. The user should input an Operating Cash level appropriate to the
project.
Initial Working capital, at 7% of first year revenues, is the fund that is set up in the year prior to
operations to initially fund the Working Capital account.
The increase in working capital from year to year is subtracted from the operating cash flow to
reflect how it is used in funding operations, and to maintain the fund at the desired level. At the
end of the project life, the Working Capital fund is returned to equity investors as a positive cash
flow.
To operate the financial model, the user must have a computer equipped with 32 MB or more of
RAM, and must be running Microsoft Excel 2000 or Excel 2003 with the Analysis ToolPak
add-in installed. To install the Analysis ToolPak, go to Tools Add-Ins, and select the
Analysis ToolPak. Then select OK.
Important: The Power Systems Financial Model is not backwardly compatible with previous
versions of Excel.
Version 3.01: Corrected the calculation of plant efficiency for the case of multiple fuels, cell
B37 in the Plant Performance worksheet. This error did not affect model results, but was a point
of confusion for users.
The users manual was updated to clarify data input for the case of multiple fuels.
Version 4.0 Updated Project Contingency default, added Project Contingency, added Investment
Tax Credit Option, added option to input detailed O&M costs.
Version 5.0 Model name changed to Power Systems Financial Model (from IGCC Financial
Model.) Added Cost of Electricity (COE) and Capital Charge Factor (CCF) calculations.
Cell titles in the model were changed to improve the clarity of field descriptions.
An About the PSFM drop-down dialog box was added to the Directory menu. The box
contains the version number and date.
Reminder Users should validate all default data for their specific projects
Process Contingency
Process contingency was a new parameter in Version 4.0 of the IGCC Financial Model. Process
contingency is designed to compensate for uncertainty in cost estimates caused by performance
uncertainties associated with the technology development status of one or more plant sections.
Process contingency is only applied to technologically developing units such as gasification or
hot gas cleanup.
A fraction of the plant cost that is technologically uncertain is specified in the Plant Inputs sheet
for the project. The process contingency is then applied to this EPC fraction.
For example, if 10% of the plant is technologically uncertain, and a 40% process contingency is
applied, 4% of the EPC costs are allocated to the process contingency.
In the Scenario Inputs sheet, under Tax Assumptions, an ITC rate, and a maximum available ITC
available in the startup year, are specified. The default ITC rate is 10%, and the default
maximum available ITC is set to a large number (e.g. on the order of the EPC cost.) A lower
Default values for O&M percentages of EPC costs have been included. The Fixed O&M is set to
a default of 5%. (Remember, users should independently validate all default data.) Variable
O&M is set to a default of 0.6%.
On the Plant Inputs sheet, the user has the option to choose to directly input or to calculate O&M
costs, as opposed to using a percentage of EPC costs. Cells A45 and A47 provide Yes/No
choices to this affect.
If the user opts to directly enter or calculate costs, the O&M sheet is used for input. On this
sheet, the user chooses to Enter or Calculate O&M costs. If Enter is chosen, the O&M
costs are simply entered in the appropriate cells. If Calculate, then the O&M calculator in the
lower portion of the sheet is used.
No default values for the directly entered O&M costs are provided on the O&M sheet. These
are project specific costs that cannot be generically entered as defaults.
Construction Period
The construction period can be set to 3, 4 or 5 years.
Construction for all scenarios must start and end within the first ten years of the start of
construction of the first project. The bar chart on the Results worksheet has been updated to
show construction costs over 3 to 5 years that occur within the first ten years. (Note: See the
section on EPC Escalation. The EPC costs are assumed to be relative to the construction start
In order to accommodate a 3, 4, or 5-year construction period, three tables have been created on
the Scenario Inputs sheet that contain data for the allocation of EPC costs over 3, 4 or 5 year
construction periods. Each plant profile is based upon the appropriate table. As in earlier
versions of the model, all scenarios having the same construction period length will use the same
EPC cost allocations.
If a construction period length is between 3 and 4 years, then the 4-year allocation is applied. If
it is between 4 and 5 years, the 5-year allocation is applied. Of course, if the length is exactly 3,
4 or 5 years, then the 3, 4, or 5-year allocations, respectively, are used.
Error checking is performed on the input for each line item in the allocation tables. If any of the
totaled percentages in the tables is less than 100%, for any line item (e.g. EPC costs) an error is
generated.
However, an option has been added to explicitly escalate EPC costs in Version 3 of the model.
The EPC Escalation sheet is used to enter the un-escalated total EPC cost, the construction
period in years, and the EPC escalation factor (which is read from the Scenario Inputs sheet.)
The user must also have input a set of initial yearly cost allocations on the Scenario Inputs page
corresponding to the un-escalated EPC for the appropriate construction period.
The EPC Escalation sheet calculates an escalated EPC and a set of cost allocation percentages.
The allocations must be automatically copied back to the Scenario Inputs sheets. The allocation
percentages must be calculated for each construction time period (3, 4 and 5 years) and must be
recalculated when the escalation factor is changed.
The user must manually re-input the resulting total escalated EPC cost into the Plant Inputs sheet
for the appropriate plant profile.
On the Scenario Inputs sheet, there are two EPC percentage-by-year allocation lines; one for
escalated EPC (used to copy the escalated results, which are in red) and one for un-escalated
EPC (use for the initial allocations, which are in blue.) The user chooses which case to use with
a yes/no option on the Scenario Inputs sheet.
Input the initial yearly cost allocations for EPC in Cells B124-M124.
Important do not rely on the default data make sure to input/validate your own data.
Press the Copy button to copy the escalated-yearly-allocation percentages into the
Scenario Inputs sheet.
Manually enter the escalated EPC cost from Cell B6 into the appropriate cell in Line 31
of the Plant Inputs sheet.
Important If the EPC escalation rate is changed, this procedure must be repeated.
Multiple Fuels
Version 3 of the model allows the user to specify a primary and a secondary fuel type. The user
must specific a primary fuel, and has the option of choosing a secondary fuel or specifying
None in the Plant Inputs sheet.
For power projects, the user inputs the heat rate for each fuel type, in Btu/kWh.
For non-power projects, the user inputs the fuel consumption rate by fuel type.
This allows the user to run scenarios that employ gas and coal or coke together. If the user wants
to run three fuels (e.g. coal, coke, and gas), then the Other/Waste fuel option is used as one
fuel for coal and coke with an HHV and fuel cost weighted average according to the fuel
mixture used.
For the heat rate of each fuel type, the user pro-rates the total heat rate by the percentage of time
operating on each fuel. The units of heat rate are then Btu of primary fuel/total kWh produced
and Btu of secondary fuel/total kWh produced, so that the sum of the heat rates is a weighted
average heat rate of the whole plant for an operating year.
Printouts
Model printouts now contain a descriptive comment that is supplied by the user. This text is
entered into the Additional Comments field on the Plant Input sheet (Line 48) for each plant
profile.